Construction method of large diameter steel-concrete combined piles in high seismic intensity areas
Through the construction method of large-diameter steel-concrete piles, the problem of insufficient structural bearing capacity in high-severity earthquake areas has been solved, the shear resistance and pull-out resistance of the pile foundation have been improved, and efficient and economical pile foundation construction has been achieved.
Patent Information
- Application Number
- CN202210944463.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-08-08
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2042-08-08
AI Technical Summary
Structures in high-intensity seismic areas require a high level of vertical and horizontal bearing capacity under earthquake action, but ordinary prestressed concrete pipe piles have poor shear and pullout resistance and cannot effectively meet this demand.
The large-diameter steel-concrete pile construction method is adopted, including first burying the steel sleeve, then drilling and pouring concrete into the pile body. The steel sleeve is equipped with a shear ring, and is buried while drilling with a rotary drilling rig, supplemented by a vibrating hammer. , the steel cage is made by mold forming method, and hole clearing and concrete pouring are carried out through three-point hoisting and grouting method.
It significantly improves the efficiency and accuracy of steel sleeve embedding, enhances the shear resistance and pull-out resistance of pile foundations, is suitable for bridge foundation construction in high-intensity earthquake areas, and improves construction efficiency and economic benefits.
Smart Images

Figure CN115288118B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of bridge construction, and in particular relates to a construction method for large-diameter steel-concrete combined piles in areas with high seismic intensity. Background Art
[0002] Seismic fortification intensity of 8 degrees and above is a high-intensity earthquake zone. The structures in high-intensity earthquake zones are subject to large horizontal earthquake effects. The maximum values of horizontal earthquake influence coefficients under frequent earthquakes in the 8-degree and 9-degree zones are 0.16 and 0.32 respectively. The horizontal shear force transmitted from the structure to the foundation is also large. Therefore, in high-intensity earthquake zones, it is necessary to verify not only the vertical bearing capacity of the pile foundation under earthquake action, but also the horizontal bearing capacity of the pile.
[0003] Soft sites generally use pile foundations because the upper soil layer is poor or there is a liquefied soil layer. The horizontal bearing capacity of the pile is related to the proportional coefficient m value of the horizontal resistance coefficient of the upper soil layer. The m value of soft site soils such as silt, silty soil, clay from fluid to soft plastic, and loose silty sand is 2~6MN / m 4 , the horizontal resistance provided by soft soil to piles is not high. For earthquake verification of piles, if there is a liquefied soil layer on the site, it is necessary to verify the vertical bearing capacity and horizontal bearing capacity of the liquefied soil after the earthquake continues; secondly, when the earthquake stops, it is necessary to verify the vertical bearing capacity with zero friction above the liquefied soil layer. In addition to axial pressure, pile foundations may also be subject to horizontal shear and vertical pull-out forces under the action of horizontal earthquakes. Since ordinary prestressed concrete pipe piles have poor horizontal shear and vertical pull-out resistance, they are generally not used in pile foundations in high-intensity earthquake areas. Summary of the invention
[0004] In order to solve the disadvantage of poor seismic performance of common prestressed concrete pipe piles, the present invention provides a construction method of large-diameter steel-concrete combined piles, which is suitable for bridge foundations in areas with high earthquake intensity.
[0005] The invention provides the following technical scheme: a large-diameter steel-concrete combined pile construction method in high-seismic intensity areas, wherein a steel sleeve is buried first and then a hole is drilled, a steel cage is lowered into the hole after the hole is cleaned once and a guide tube is placed, pile body concrete is poured after the hole is cleaned twice, and after the pile foundation concrete is poured and cured for 3-7 days, when the concrete strength reaches more than 75% of the design value, a grouting pipe is used to grout the pile bottom, the grouting pipe is evenly fixed on the steel cage, a steel grouting pipe is used, the upper end of the grouting pipe is higher than the ground, and the lower end is connected to a one-way valve grouting device, the slurry has a 7-day compressive strength of not less than 5MPa, and a 28-day compressive strength is not less than the concrete strength of the pile body, after the pile head is broken, a circle of steel bars is designed on the outer top of the steel cage in the steel sleeve, the steel bars and the steel sleeve are welded by double-sided welding, and the steel bars are bent with their backs to the steel sleeve and above the steel sleeve to form a cone; wherein, after the steel sleeve is installed, it is ensured that the top of the steel sleeve extends into the bottom of the cap by 10cm.
[0006] Furthermore, a shear ring is provided on the inner wall of the steel sleeve. The shear ring adopts a rectangular solid section. The shear ring is made of the same material as the steel sleeve. The shear ring is connected to the inner wall of the steel sleeve by two upper and lower fillet welds. The spacing between the shear rings within 6m below the top of the steel sleeve is 1m, and the spacing between the remaining lower shear rings is 2m.
[0007] Furthermore, during the process of burying the steel sleeve, it is evenly pressed in by burying it while drilling, and assisted by vertical vibration burying with a vibrating hammer. During the construction process, in order to ensure the integrity of the steel sleeve, the steel casing is followed from the ground to the designed steel sleeve bottom elevation during construction.
[0008] Furthermore, when burying the steel casing, the positioning control piles are used to mark the position of the drill hole at the bottom of the hole, and then the steel casing is hoisted into the hole to find the center of the steel casing. A crosshair is used to make a reference at the top or bottom of the steel casing, and then the steel casing is moved so that the center of the steel casing coincides with the center of the drill hole. At the same time, a level ruler or a plumb bob is used to check that the steel casing is vertical. Thereafter, clay is backfilled symmetrically and evenly around the steel casing and compacted in layers.
[0009] Furthermore, the drilling is carried out by a rotary drill. During the drilling process, the penetration speed is controlled according to the geological conditions. When drilling from a hard formation to a soft formation, the drilling speed is accelerated; when the soft formation becomes a hard formation, the drilling speed is reduced and the advancement is slowed down. In the formation that is easy to shrink in diameter, the number of hole sweeping is increased to prevent shrinkage; high-speed drilling is adopted for hard plastic layers, and slow-speed drilling is adopted for sand layers, and the mud density and viscosity are increased.
[0010] Furthermore, the steel cage is made of a mold forming method to make a skeleton. The steel cage is divided into sections according to the designed length, the upper section is a supplementary section, and the remaining sections are standard sections. The standard section length is determined according to the fixed length of the main reinforcement. When the steel cage is entered into the hole, a pearl cotton casing is applied to the anchor steel bar of the upper section to reduce the grip of the concrete on the steel bar and facilitate the removal of the pile head. The main reinforcement is connected by a straight threaded sleeve, and the joints are staggered during connection.
[0011] Furthermore, the steel cage is hoisted by three-point hoisting, with the first hoisting point at the lower part of the steel cage, the second hoisting point at the middle part of the steel cage at the reinforcing stirrups, and the third hoisting point at the first layer of reinforcing stirrups. When hoisting, first lift the first hoisting point to lift the steel cage slightly, and then lift it at the same time as the second and third hoisting points; after the steel cage leaves the ground, the first and second hoisting points stop lifting, and continue to lift the third point. As the third hoisting point continues to rise, slowly relax the first and second hoisting points until the steel cage is vertical to the ground, and stop lifting. After the steel cage enters the hole mouth, it is straightened and slowly lowered. When the steel cage is lowered to the reinforcing stirrups near the third hoisting point and close to the hole mouth, the steel cage is supported at the hole mouth with steel sections, and the second section of the steel cage is hoisted to connect with it, until the steel cage of the pile is lowered to the designed elevation.
[0012] Furthermore, the first hole cleaning adopts air lift reverse circulation, slurry replacement method or slag removal method to clean the hole, and the second hole cleaning adopts slurry replacement method to clean the hole.
[0013] Furthermore, during the pouring of concrete for the pile body, concrete is transported by a pump truck and continuously poured underwater through the hopper and the conduit until the pouring of the entire pile is completed. As the concrete pouring height rises, the conduit is removed section by section, one section at a time. After the conduit is removed, the buried depth of the bottom of the conduit is guaranteed to be 2-6m. After the concrete top surface elevation is in place, the pouring is stopped, the pouring conduit is removed, and the concrete surface elevation is controlled to be 0.5m-1.0m higher than the designed pile top elevation.
[0014] Furthermore, before the installation of the conduit, a watertight pressure test and a joint tensile test are carried out. The water pressure during the watertight test of the conduit shall not be less than the pressure of 1.5 times the water depth in the wellbore, and the water pressure during the pressure test shall not be greater than the maximum internal pressure Pmax that the conduit wall may withstand. Pmax is calculated as follows: Pmax=1.5(γcHcmax-γwHw)=900 kPa;
[0015] Where: Pmax – the maximum internal pressure that the catheter wall may withstand, in kPa;
[0016] γc——Concrete bulk density (24KN / m 3 ), unit KN / m 3 ;
[0017] Hcmax——the maximum height of the concrete column in the conduit, using the full length of the conduit, in meters;
[0018] γw——Bore water or mud density, mud density is greater than 12KN / m 3 It is not suitable to pour underwater concrete, unit KN / m 3 ;
[0019] Hw – Depth of water or mud in the borehole, in m.
[0020] Compared with the prior art, the advantages of the present invention are:
[0021] The steel sleeve is evenly pressed in by a rotary drilling rig while drilling and buried, and is supplemented by a vibrating hammer for vertical vibration. Compared with the existing drilling technology, the efficiency of steel sleeve burial can be greatly improved; during the steel sleeve burial process, the plane position accuracy and verticality accuracy of the steel sleeve burial are improved by tooling, which can greatly improve the accuracy of steel sleeve burial compared with the existing technology. The steel sleeve is installed by a more efficient and strict steel sleeve burial process, which improves the efficiency of steel sleeve installation. According to the traditional method, the steel sleeve installation efficiency is 2m / d. According to this method, the steel sleeve installation efficiency is 5m / d, which is 2.5 times higher and has significant economic benefits. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 It is a structural schematic diagram of steel-concrete combined piles and caps.
[0023] Figure 2 Schematic diagram of the cross section of the shear ring.
[0024] In the figure: 1-rebar; 2-cap; 3-steel sleeve; 4-shear ring; 5-reinforced concrete pile. DETAILED DESCRIPTION
[0025] In order to have a clearer understanding of the technical features, purposes and effects of the present invention, the specific embodiments of the present invention are now described with reference to the accompanying drawings. The contents shown in the drawings are only used to understand the technical contents of the invention, and do not represent the actual proportions and true shapes of the products, wherein the same reference numerals represent parts with the same structure or the same function but similar structure.
[0026] In this article, "parallel", "perpendicular", etc. are not strictly limited in mathematical and / or geometric senses, and may also include errors that can be understood by those skilled in the art and are allowed when manufacturing or using the product. In addition, "perpendicular" includes not only the perpendicularity of two objects directly connected in space, but also the perpendicularity of two objects not connected in space.
[0027] like Figure 1 , Figure 2 As shown: a construction method of large-diameter steel-concrete combined piles in high seismic intensity areas, first burying a steel sleeve and then drilling a hole, after drilling a hole, after cleaning the hole once, lowering a steel cage and placing a guide tube, pouring the pile body concrete after cleaning the hole twice, after the pile foundation concrete is poured and cured for 3-7 days, when its concrete strength reaches more than 75% of the design value, the pile bottom is grouting by a grouting pipe, the grouting pipe is evenly fixed on the steel cage, a steel grouting pipe is used, the upper end of the grouting pipe is higher than the ground, and the lower end is connected to a one-way valve grouting device, the slurry has a 7-day compressive strength of not less than 5MPa, and a 28-day compressive strength is not less than the concrete strength of the pile body, after the pile head is broken, the top steel bar of the steel cage in the steel sleeve is extended by a straight threaded sleeve, the steel bar and the steel sleeve are welded by double-sided welding, and the steel bar is bent with its back to the steel sleeve above the steel sleeve to form a cone; wherein, after the steel sleeve is installed, it is ensured that the top of the steel sleeve extends into the bottom of the cap by 10cm.
[0028] The inner wall of the steel sleeve is provided with a shear ring, which is a rectangular solid section. The shear ring is made of the same material as the steel sleeve. The shear ring is connected to the inner wall of the steel sleeve by two upper and lower fillet welds. The spacing of the shear rings within 6m below the top of the steel sleeve is 1m, and the spacing of the other lower shear rings is 2m. During the burial of the steel sleeve, the steel sleeve is pressed evenly by burying it while drilling, and is supplemented by vertical vibration burial with a vibrating hammer. During the construction process, in order to ensure the integrity of the steel sleeve, the steel casing is followed from the ground to the designed bottom elevation of the steel sleeve during construction.
[0029] The first 4m of the steel sleeve can be drilled and pressed in with a rotary drilling rig. When the hole is drilled to a depth of 4m-6m, a 450 series vibrating hammer is used to vibrate the steel casing first, and then the hole is drilled. During the construction process of burying the steel sleeve, the vibrating hammer must be stable and the plane position on the top surface of the sleeve must be centered to avoid the sleeve from being deflected due to eccentricity as much as possible. At the same time, a horizontal ruler is used to strictly control the verticality of the sleeve to meet the requirements of the specifications. The inclination shall not be greater than 1%, and the plane position deviation shall not be greater than 50mm, and the steel sleeve shall be vertically buried in the soil. If a tendency of deflection is found, it should be corrected immediately. Due to the requirements of the buried steel sleeve operation specifications for the verticality of the steel sleeve and the center of the sleeve and the center of the pile position, the steel sleeve burying operation should be carried out during the day to facilitate timely handling and correction of problems. After the steel sleeve is buried, it should be 50cm above the ground.
[0030] When burying the steel casing, the positioning control piles are used to mark the position of the drill hole at the bottom of the hole, and then the steel casing is hoisted into the hole to find the center of the steel casing. A crosshair is used to make a reference at the top or bottom of the steel casing, and then the steel casing is moved to make the center of the steel casing coincide with the center of the drill hole. At the same time, a level ruler or plumb ball is used to check that the steel casing is vertical. After that, clay is backfilled symmetrically and evenly around the steel casing and compacted in layers. To ensure its verticality and prevent mud loss, displacement, and falling. The bottom blade of the steel casing goes deep into the impermeable layer to prevent leakage and collapse at the bottom of the steel casing. When tamping, the steel casing should be prevented from deflecting.
[0031] Drilling construction
[0032] The rotary drilling rig is positioned by itself through the crawler. After positioning, the center point of the drill bit is aligned with the center of the pile position, and the drill mast is adjusted to be vertical, and then drilling is carried out. Its working cycle is: hole alignment → drill drop → drilling → drill lifting → reverse unlocking → lifting the drill rig to rotate and unload soil → hole alignment again. Zero the depth gauge every time you drill a hole to check the drilling situation and lift and lower the wire rope appropriately. Check whether the wire rope is in the drum groove in each cycle, and check whether the wire rope has burrs or broken strands. If so, replace it in time.
[0033] During the drilling process, the penetration speed should be controlled according to the geological conditions: when drilling from a hard formation to a soft formation, the drilling speed can be appropriately accelerated; when the soft formation becomes a hard formation, the drilling speed should be slowed down; in the formation that is easy to shrink, the number of hole sweeps should be appropriately increased to prevent shrinkage; for the hard plastic layer, high-speed drilling should be used to improve drilling efficiency; for the sand layer, slow drilling should be used with a slow speed and the mud density and viscosity should be appropriately increased. When the drilling depth is close to the design value, the drilling should be stopped, and the drilling depth should be checked with a measuring rope to avoid over-digging. When the drilling reaches the design depth, the measuring rope should be used for verification. If the readings of the measuring rope and the drilling rig instrument do not match, the readings of the measuring rope should be used as the standard. During the injection of mud, avoid the mud from directly scouring the hole wall to prevent the mud from repeatedly scouring the same position, causing the hole to collapse.
[0034] During the drilling process, the mud surface should be kept no lower than 500mm below the bottom of the casing, and the drilling speed should be strictly controlled to avoid excessive drilling speed causing hole collapse and drilling accidents. The lifting speed of the drill bucket should be controlled at 0.75-0.8m / s; when the mud is first injected, it should be grouting vertically in the middle of the pile hole.
[0035] Hole inspection
[0036] During the drilling process, the hole depth is measured in time to prevent over-drilling. When the drilling depth reaches the designed hole depth, the hole diameter, hole position and verticality are checked immediately. The ultrasonic hole detector is used for hole detection. The complete set of equipment includes ultrasonic probes for verticality and main components such as winches, cables, and wellhead pulleys. During the detection, various detection data and curves can be displayed in real time, and these data can be stored and printed out. The measurement data can be uploaded to the host computer through serial communication. It is convenient to compile detection reports and hole quality inspection reports. The storage and processing of data are convenient and fast, which can greatly improve work efficiency and quality. By analyzing the detection data, the hole diameter and verticality after the hole are determined.
[0037] One-time hole cleaning
[0038] The primary hole cleaning is carried out by air lift reverse circulation, slurry replacement or slag removal.
[0039] Air lift reverse circulation: Use an underwater pipe to perform air reverse circulation to clean the hole. The injection pressure is moderate (0.8-1MPa) so that the drilling debris at the bottom and corners of the hole can also be sucked out. Note that the grouting pipe must be inserted to the bottom of the hole. If the insertion depth of the grouting pipe is not in place, it will cause the hole to collapse due to injection. After the steel cage is placed to the design elevation, if the mud index and sedimentation thickness exceed the standard, the hole should be cleaned for the second time until it reaches the standard. When cleaning the hole, the method of deepening the drilling depth cannot be used instead of cleaning the hole.
[0040] Hole cleaning by slurry replacement method: When drilling, stop drilling after the hole is completed, slightly lift the drill bit 10 to 20 cm away from the bottom of the hole and let it run idle, and keep the mud circulating normally. Press in relatively pure mud with a relative density of 1.03 to 1.10 at a medium speed, and replace the mud with more suspended drill residues in the borehole until the drill residues at the bottom of the hole are completely removed. When drilling with an impact drill, you can also use a slag extraction barrel to clean the hole until the mud index in the hole meets the requirements.
[0041] The rotary drilling rig uses the slag removal drill bit to repeatedly clean the bottom without drilling, so as to reduce the empty slag at the bottom of the hole.
[0042] The hole should be cleaned to ensure that the mud meets the following standards: the mud discharged from the hole has no 2-3mm particles when touched by hand, the mud specific gravity is not greater than 1.1, the sand content is less than 2%, and the viscosity is 17-20s. At the same time, the thickness of the sediment at the bottom of the hole before underwater concrete pouring should be ensured: column pile ≯5cm, friction pile ≯20cm.
[0043] The steel cage is made of a mold forming method. The steel cage is divided into sections according to the designed length. The upper section is a supplementary section, and the remaining sections are standard sections. The standard section length is determined according to the fixed length of the main reinforcement. When the steel cage is inserted into the hole, a pearl cotton sleeve is applied to the anchor steel bar of the upper section to reduce the grip of the concrete on the reinforcement and facilitate the removal of the pile head. The main reinforcement is connected with a straight threaded sleeve, and the joints are staggered during connection.
[0044] The steel cage is hoisted into place by a car crane or crawler crane. Three-point hoisting is adopted. The first hoisting point is at the bottom of the steel cage, the second hoisting point is set at the reinforcing stirrup in the middle of the steel cage, and the third hoisting point is set at the first layer of reinforcing stirrup. When hoisting, first lift the first hoisting point to lift the steel cage slightly, and then lift it at the same time as the second and third hoisting points. After the steel cage leaves the ground, stop hoisting the first and second hoisting points, and continue to hoist the third point. As the third hoisting point continues to rise, slowly relax the first and second hoisting points until the steel cage is vertical to the ground, and stop hoisting. When the steel cage enters the hole, it should be straightened and slowly lowered, and it is strictly forbidden to swing and hit the wall. Then, the temporary radial skeleton reinforcements are removed one by one from bottom to top. When the steel cage is lowered to the reinforcing stirrup near the third hoisting point and close to the hole, the steel cage is supported at the hole with steel sections, and the second section of the steel cage is hoisted to dock until the steel cage of the pile is lowered to the designed elevation.
[0045] After the entire steel cage is hoisted, its lifting rod and lifting ring are passed through the rod (steel pipe), and square wood is placed on the outer side of the casing wall perpendicular to the rod direction to 10cm above the top of the casing to prevent the steel cage from sinking or floating. When fixing the steel cage, ensure that the cage mouth is in the center of the steel casing and must not be offset.
[0046] Before installing the conduit, a watertight pressure test and joint tensile test are carried out, including the following steps:
[0047] (1) Check whether there are obvious holes in each section of the conduit, and check the sealing ring of each section of the conduit. If it is missing or worn out and cannot be used, it should be removed and replaced or added in time, and appropriate grease should be applied to the steel cable groove.
[0048] (2) Select a site so that the conduits can be docked evenly on the ground. When docking, number the pipes in sequence.
[0049] (3) Install a sealing device at both ends of the conduit. The sealing device uses an existing pressure test sleeve. Install water inlet holes at both ends of the pressure test seal. When installing, make sure that the two holes are located directly above the pipe so that air can overflow from the holes when water is injected.
[0050] (4) Install a water pipe to inject water into the conduit. Stop injecting water when water flows out from the other end of the pipe. Make sure that the water in the conduit reaches more than 70% before stopping.
[0051] (5) Seal the water injection hole at one end and install a pressure gauge, connect the other end to the water pump, check the installation of the closed end of the conduit connection, and after the inspection is qualified, pressurize the air blower to 0.6MPa and maintain the pressure for 15 minutes. Check the water overflow at the conduit joint and make a record of the overflow. For the pressure test, roll the conduit 180º, pressurize it again, maintain the pressure for 15 minutes, and make a record of the inspection.
[0052] (6) The water pressure during the watertight test of the conduit should not be less than 1.5 times the water depth in the wellbore. The water pressure during the pressure test should not be greater than the maximum internal pressure Pmax that the conduit wall can withstand. Pmax can be calculated as follows: Pmax = 1.5 (γcHcmax - γwHw) = 900 kPa;
[0053] Where: Pmax – the maximum internal pressure that the catheter wall may withstand, in kPa;
[0054] γc——Concrete bulk density (24KN / m 3 ), unit KN / m 3 ;
[0055] Hcmax——the maximum height of the concrete column in the conduit, using the full length of the conduit, in meters;
[0056] γw——Bore water or mud density, mud density is greater than 12KN / m 3 It is not suitable to pour underwater concrete, unit KN / m 3 ;
[0057] Hw – Depth of water or mud in the borehole, in m.
[0058] Secondary hole cleaning
[0059] The interval between placing the steel cage and the conduit and pouring underwater concrete is long, and sediment is easy to form at the bottom of the hole. After the steel cage and the conduit are placed, the hole is cleaned for the second time by the slurry replacement method to replace the sediment. When all technical indicators of the slurry at the bottom of the hole meet the design requirements and the thickness of the sediment at the bottom of the hole is re-measured and is within the design range, the hole is cleaned and underwater concrete pouring is carried out immediately.
[0060] Concrete pouring
[0061] After the concrete is transported to the site, the amount of concrete to be poured for the first time is calculated in advance, and then a sufficient amount of concrete is placed in the funnel (a 2m³ funnel is used for the first batch of concrete pouring, and a water-blocking ball with a diameter slightly smaller than that of the steel sleeve is placed in the steel sleeve in advance to ensure that the first pour of concrete can be successfully sealed at the bottom. At the same time, a mesh screen is placed in the funnel). When pouring begins, the funnel valve is quickly opened to allow the concrete to fall with great force to ensure that the pressure is sufficient to completely squeeze out the water in the steel sleeve and neutralize the water pressure so that the concrete can be successfully sealed at the bottom, meeting the requirement of burying the pipe for more than one meter). After the first pour of concrete is successfully poured, the subsequent pouring process can be appropriately adjusted according to the equipment and conditions.
[0062] According to the specification, the volume of the first batch of concrete meets the following requirements: 1m ≤ buried depth of conduit ≤ 3m, and during the pouring process, it meets the following requirements: 2m ≤ buried depth of conduit ≤ 6m. During the pouring process, technicians will measure the height of concrete pouring at any time (measured by a hammer). The technicians will strictly control the pouring process of the first batch of concrete on site.
[0063] After the first batch of concrete pouring is completed, the large funnel is replaced with a small funnel, and the normal pouring stage is entered. The concrete is transported by a pump truck and continuously poured underwater through the small hopper and the conduit until the entire pile is poured. As the concrete pouring height rises, the conduit is removed section by section, one section of the conduit is removed each time. After the conduit is removed, the buried depth of the bottom of the conduit is guaranteed to be 2-6m. During the concrete pouring process, the concrete surface elevation is measured at any time to determine the buried depth of the conduit and the timing of removing the conduit. In addition, before removing the conduit, ask the mixing station about the volume of concrete that has been delivered to the site so that it can be compared with the volume of concrete calculated on site based on the measured elevation to prevent errors. When the concrete pouring is about to end, check the volume of concrete poured again to determine whether the height of the measured concrete is accurate. After the concrete top surface elevation is in place, stop pouring and remove the pouring conduit. The concrete surface elevation is controlled to be 0.5m-1.0m higher than the designed pile top elevation (according to the design requirements, the top of each pile extends into the cap 10cm) to ensure the quality of the pile head concrete.
[0064] All bored piles are tested non-destructively. The testing method complies with the provisions of the "Railway Engineering Piles Non-destructive Testing Regulations", and the testing frequency meets the design requirements. The length of the 8-10# pier foundation of the Lancang River Bridge is greater than 40m (the pile diameter is 2m), and the hole detection is carried out using ultrasonic detection.
[0065] Pile bottom grouting
[0066] After the concrete pouring of the pile foundation is completed and maintained for 3-7 days, the acoustic wave detection of the pile body is completed. When the concrete strength reaches more than 75% of the design value, the pile bottom is grouting using a grouting pipe. The slurry requires a compressive strength of not less than 5MPa in 7 days and a compressive strength of not less than the concrete strength of the pile body in 28 days. The grouting amount and grouting control pressure should be strictly controlled during grouting. Grouting should be done at low pressure and slow speed so that the sediment at the bottom of the pile is fully compacted after grouting. Before grouting the bottom of the pile, the grouting pressure, grouting amount, and the pull-out resistance of the pile should be calculated and determined, and the grouting pressure, grouting amount, pile top reaction force and other values should be continuously monitored during each grouting test and grouting process. The grouting pipe is evenly fixed on the steel cage, and two steel grouting pipes with an inner diameter of 25mm and a wall thickness of ≥3mm are used. The upper end of the grouting pipe should be higher than the ground, and the lower end should be connected to a one-way valve grouting device.
[0067] It should be understood that although this specification is described according to various embodiments, not every embodiment contains only one independent technical solution. This narrative method of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation methods that can be understood by those skilled in the art.
[0068] The series of detailed descriptions listed above are only specific descriptions of feasible embodiments of the present invention. They are not intended to limit the scope of protection of the present invention. All equivalent embodiments or changes that do not deviate from the technical spirit of the present invention should be included in the scope of protection of the present invention.
Claims
1. A method for constructing large-diameter steel-concrete combined piles in areas with high seismic intensity, characterized by: First bury the steel sleeve and then drill the hole. After drilling, clean the hole once, put the steel cage in and place the guide tube. After cleaning the hole twice, pour the pile body concrete. After the pile foundation concrete is poured and cured for 3-7 days, when its concrete strength reaches more than 75% of the design value, use the grouting pipe to grout the pile bottom. The grouting pipe is evenly fixed on the steel cage. The steel grouting pipe is used. The upper end of the grouting pipe is higher than the ground, and the lower end is connected to the one-way valve grouting device. The slurry has a 7-day compressive strength of not less than 5MPa, and a 28-day compressive strength of not less than the concrete strength of the pile body. After the pile head is broken, the top steel bar of the steel cage in the steel sleeve is extended by a straight threaded sleeve. The steel bar and the steel sleeve are welded by double-sided welding. The steel bar is bent with its back to the steel sleeve and surrounded by a cone above the steel sleeve; after the steel sleeve is installed, ensure that the top of the steel sleeve extends into the bottom of the cap by 10cm; The inner wall of the steel sleeve is provided with a shear ring, which adopts a rectangular solid section. The shear ring is made of the same material as the steel sleeve. The shear ring is connected to the inner wall of the steel sleeve by two upper and lower fillet welds. The spacing of the shear rings within 6m below the top of the steel sleeve is 1m, and the spacing of the other lower shear rings is 2m. During the embedding process of the steel sleeve, the steel sleeve is evenly pressed in by drilling and embedding, and is assisted by vertical vibration embedding with a vibrating hammer. During the construction process, in order to ensure the integrity of the steel sleeve, the steel casing is followed from the ground to the designed steel sleeve bottom elevation during construction; When burying the steel casing, the positioning control pile is used to mark the position of the drill hole at the bottom of the hole, and then the steel casing is hoisted into the hole to find the center of the steel casing. A crosshair is used to make a reference at the top or bottom of the steel casing, and then the steel casing is moved to make the center of the steel casing coincide with the center of the drill hole. At the same time, a level ruler or a plumb ball is used to check that the steel casing is vertical. Thereafter, clay is backfilled symmetrically and evenly around the steel casing and compacted in layers. The drilling hole is drilled by a rotary drill. During the drilling process, the penetration speed is controlled according to the geological conditions. When drilling from a hard stratum to a soft stratum, the drilling speed is accelerated; when the soft stratum becomes a hard stratum, the drilling speed is slowed down. In the stratum that is easy to shrink, the number of hole sweeps is increased to prevent the shrinkage. A high-speed drilling is used for the hard plastic layer, and a slow-speed drilling is used for the sand layer, and the mud density and viscosity are increased; The steel cage adopts the mold forming method to make the skeleton. The steel cage is divided into sections according to the designed length. The upper section is a supplementary section, and the other sections are standard sections. The standard section length is determined according to the fixed length of the main reinforcement. When the steel cage is inserted into the hole, the pearl cotton sleeve is covered at the upper section anchoring reinforcement to reduce the holding force of the concrete on the reinforcement and facilitate the removal of the pile head. The main reinforcement is connected by a straight threaded sleeve, and the joints are staggered when connected. The primary hole cleaning adopts gas lift reverse circulation, slurry replacement method or slag removal method to clean the hole, and the secondary hole cleaning adopts slurry replacement method to clean the hole; The conduit is subjected to watertight pressure bearing and joint tensile tests before installation. The water pressure during the watertight test of the conduit is not less than the pressure of 1.5 times the water depth in the wellbore, and the water pressure during the pressure bearing test is not greater than the maximum internal pressure Pmax that the conduit wall may withstand. Pmax is calculated according to the following formula: Pmax=1.5(γcHcmax-γwHw)=900 kPa; Where: Pmax – the maximum internal pressure that the catheter wall may withstand, in kPa; γc——Concrete bulk density, 24KN / m 3 , unit KN / m 3 ; Hcmax——the maximum height of the concrete column in the conduit, using the full length of the conduit, in meters; γw——Bore water or mud density, mud density is greater than 12KN / m 3 It is not suitable to pour underwater concrete, unit KN / m 3 ; Hw – Depth of water or mud in the borehole, in m.
2. The method for constructing large-diameter steel-concrete combined piles in high seismic intensity areas according to claim 1 is characterized in that: The steel cage is hoisted by three-point hoisting, the first hoisting point is at the lower part of the steel cage, the second hoisting point is set at the reinforcing stirrup in the middle of the steel cage, and the third hoisting point is set at the first layer of reinforcing stirrups. When hoisting, first lift the first hoisting point to lift the steel cage slightly, and then lift it at the same time with the second and third hoisting points; after the steel cage leaves the ground, the first and second hoisting points stop hoisting, and continue to hoist the third point. As the third hoisting point continues to rise, slowly relax the first and second hoisting points until the steel cage is vertical to the ground, stop hoisting, and when the steel cage enters the hole, straighten it and slowly lower it. When the steel cage is lowered to the reinforcing stirrup near the third hoisting point and is close to the hole, use steel sections to support the steel cage at the hole, and hoist the second section of the steel cage to dock, until the steel cage is lowered to the designed elevation.
3. The method for constructing large-diameter steel-concrete combined piles in high seismic intensity areas according to claim 1, characterized in that: During the concrete pouring process of the pile body, concrete is transported by a pump truck and continuously poured underwater through a hopper and a conduit until the pouring of the entire pile is completed. As the concrete pouring height rises, the conduit is removed section by section, one section of the conduit is removed each time. After the conduit is removed, the buried depth of the bottom of the conduit is guaranteed to be 2-6m. After the concrete top surface elevation is in place, the pouring is stopped, the pouring conduit is removed, and the concrete surface elevation is controlled to be 0.5m-1.0m higher than the designed pile top elevation.