Inclinometer pipe protection device and its use method based on reverse excavation and considering impact load

By designing shock-absorbing and energy-dissipating structures and protective devices on the inclinometer tube, the problem of damage and bending of the inclinometer tube under impact rolling and compaction was solved, ensuring the accuracy of measurement data and the stability of the equipment during the construction process.

CN115369935BActive Publication Date: 2024-10-22CHANGSHA UNIVERSITY OF SCIENCE AND TECHNOLOGY +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202211195573.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-09-29
Publication Date
2024-10-22
Estimated Expiration
2042-09-29

AI Technical Summary

Technical Problem

In the construction of high-fill embankments, the inclinometer pipes are easily damaged during construction processes such as impact rolling and dynamic compaction, and the severe energy causes lateral deformation and bending, affecting the measurement results.

Method used

An inclinometer pipe protection device is designed based on reverse excavation and considering impact load. It adopts a shock-absorbing energy-dissipating structure and shock-absorbing blocks, combines high modulus materials and flexible materials, and is bonded with X-shaped structural steel through epoxy resin glue. Strips, support rods and protective materials are provided, and the protective device can be detachably connected to reduce the bending and damage of the inclinometer tube.

Benefits of technology

It can effectively prevent excessive deformation and bending of the inclinometer pipe due to construction and backfilling, ensure the accuracy of measurement data, avoid exposure and damage of the inclinometer pipe, and achieve stable monitoring of the horizontal displacement of the embankment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115369935B_ABST
    Figure CN115369935B_ABST
Patent Text Reader

Abstract

The present invention discloses an inclinometer tube protection device based on reverse excavation and considering impact load and a method for using the device. The device includes a shock-absorbing and energy-dissipating structure, which is composed of a high-modulus material layer with a modulus greater than that of the soil and a flexible material layer with a buffering effect. The flexible material layer with a buffering effect is arranged in the middle of the high-modulus material layer. A shock-absorbing block is fixed at the bottom of the shock-absorbing and energy-dissipating structure and sleeved on the outer periphery of the pipe mouth of the inclinometer tube. The front, back, left, and right sides of the shock-absorbing and energy-dissipating structure are all provided with diagonal braces for accommodating deformation of the flexible material layer. The top of the first aluminum alloy tube passes through the shock-absorbing block and is detachably connected to the shock-absorbing and energy-dissipating structure. The tube body of the first aluminum alloy tube is inserted in the inclinometer tube and an inclinometer tube anti-blocking device is fixed at the bottom. A circular through hole is arranged on the shock-absorbing and energy-dissipating structure, and a plurality of support rods are respectively located in the circular through hole and inserted in the soil around the inclinometer tube. The influence of strong vibrations such as impact rolling and strong tamping on the inclinometer tube is considered.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of roadbed filling measurement devices, and relates to an inclinometer tube protection device based on reverse excavation and considering impact load, and a use method thereof. Background Art

[0002] In the construction of high embankment, it is often necessary to use inclinometer tubes to monitor the horizontal displacement of the embankment shoulder and slope platform, so as to understand the working status of the embankment at all times and ensure the safety of the project. There are currently two methods for burying this type of inclinometer tube. The first is to bury it by drilling holes on the top surface of the roadbed after the roadbed is completed. This method has the following two main disadvantages: First, the drilling depth is large, the economic cost is high, and the excessive depth will make the installation of the inclinometer tube difficult; second, the drilling process will cause great damage to the roadbed. The second method is to splice the inclinometer tube as the embankment is filled. Since the inclinometer tube is directly exposed outside the roadbed, it affects the roadbed construction, and it is very easy to cause damage to the inclinometer tube due to passing vehicles and other disturbances. Therefore, the reverse excavation method is often used for splicing. However, it is found in actual engineering that high embankment roadbeds often need to be compacted by construction methods such as impact rolling and strong tamping, but this method will damage the inclinometer tube buried in the soil. At the same time, for some stone fills or soil-rock mixed fills, when the soil layer on the top of the inclinometer tube is relatively thin, the violent energy will cause huge lateral deformation of the inclinometer tube, and due to the squeezing effect between the blocks, local deformation is easy to occur, causing the tube mouth of the inclinometer tube to bend, resulting in the inclinometer being unable to enter the inclinometer tube, thereby affecting the measurement. Summary of the invention

[0003] The purpose of the embodiments of the present invention is to provide an inclinometer tube protection device based on reverse excavation and taking impact load into consideration, so as to solve the problem that the existing inclinometer tube spliced ​​based on reverse excavation is easily damaged under severe impact such as impact rolling, strong tamping, and the like, and the problem that the inclinometer tube produces excessive abnormal bending due to impact rolling, strong tamping or backfilling, thereby affecting subsequent measurements.

[0004] Another object of an embodiment of the present invention is to provide a method for using an inclinometer casing protection device based on back excavation and taking impact load into consideration.

[0005] The technical solution adopted in the embodiment of the present invention is: an inclinometer casing protection device based on reverse excavation and considering impact load, comprising:

[0006] The shock-absorbing and energy-dissipating structure is composed of a high-modulus material layer with a modulus greater than that of the soil and a flexible material layer with a buffering effect;

[0007] A shock-absorbing block is fixed at the bottom of the shock-absorbing and energy-dissipating structure and sleeved on the outer periphery of the pipe opening of the inclinometer pipe;

[0008] in:

[0009] The flexible material layer with buffering function is arranged in the middle of the high modulus material layer.

[0010] Furthermore, the shock absorbing block and the shock absorbing and energy dissipating structure are bonded with epoxy resin glue;

[0011] The high modulus material layer and the flexible material layer are bonded by epoxy resin adhesive.

[0012] Furthermore, the shock-absorbing and energy-dissipating structure is a shock-absorbing and energy-dissipating plate composed of two high modulus material layers and a flexible material layer disposed between two carbon fiber plates;

[0013] The plane size of the shock-absorbing and energy-dissipating plate is much larger than the plane size of the shock-absorbing block.

[0014] Furthermore, the high modulus material layer is made of at least one of a carbon fiber plate, an aluminum alloy plate, and a magnesium alloy plate;

[0015] The flexible material layer is made of at least one of a rubber pad, pearl cotton, sponge and a silicone plate.

[0016] Furthermore, four sides of the shock-absorbing and energy-dissipating structure, namely the front, back, left and right sides, are provided with diagonal braces for accommodating deformation of the flexible material layer.

[0017] Further, the diagonal brace comprises two steel bars hinged to form an X-shaped structure, wherein:

[0018] The four ends of the steel bars of the X-shaped structure are respectively hinged to the high modulus material layers of the shock-absorbing and energy-dissipating structure through horizontally arranged bolts;

[0019] The diameters of the mounting holes at the four ends of the steel bar of the X-shaped structure are larger than the diameter of the screw rod of the bolt and smaller than the diameter of the bolt head.

[0020] Further, it also includes a first aluminum alloy tube and a support rod;

[0021] The top of the first aluminum alloy tube passes through the shock absorbing block and is detachably connected to the shock absorbing and energy dissipating structure, and the tube body of the first aluminum alloy tube is inserted into the inclinometer tube;

[0022] An inclinometer tube anti-blocking device is fixed at the bottom of the first aluminum alloy tube, and the side wall of the inclinometer tube anti-blocking device is in contact with the inner wall of the inclinometer tube;

[0023] The shock-absorbing and energy-dissipating structure is provided with circular through holes, and a plurality of support rods are respectively located in the circular through holes and inserted into the soil around the inclinometer tube.

[0024] Furthermore, the first aluminum alloy tube is formed by splicing various sub-tubes, and each sub-tube can be detachably connected;

[0025] The inclinometer tube anti-blocking device adopts a rubber hollow hemisphere, and the cavity of the rubber hollow hemisphere is set upward;

[0026] The support rod includes a second aluminum alloy tube and a PVC tube, and the PVC tube is sleeved on the outer periphery of the second aluminum alloy tube;

[0027] A protective material layer is filled between the pipe opening of the inclinometer tube and the shock-absorbing block;

[0028] Steel wire hoses are wound around the sides of the shock-absorbing and energy-dissipating structure and the shock-absorbing block.

[0029] Another technical solution adopted by the embodiment of the present invention is: a method for using an inclinometer casing protection device based on reverse excavation and considering impact load, which is performed according to the following steps:

[0030] Step S1, fix the point and drill a hole on the original foundation, install the inclinometer tube, record the pipe mouth elevation and the actual buried depth of the inclinometer tube, use the inclinometer to perform initial measurement, the measured initial depth of the inclinometer tube is recorded as L0, the bottom of the inclinometer tube is defined as 0 during the initial depth measurement, and the measured initial horizontal displacement of the inclinometer tube is recorded as C0;

[0031] Step S2, excavating a landfill pit for burying an inclinometer tube protection device (hereinafter referred to as a protection device) based on reverse excavation and considering impact load, wherein the top surface elevation of the landfill pit is not higher than the original ground elevation;

[0032] Step S3, selecting a first aluminum alloy tube of appropriate length according to the length of the inclinometer tube, where the length of the first aluminum alloy tube is denoted as X0;

[0033] Step S4, inserting the first aluminum alloy tube into the inclinometer tube, placing the protection device into the landfill pit, and using a level to measure the top surface elevation h0 of the protection device;

[0034] Step S5: Filling. After filling 1-1.5 m, use metal detector / total station to locate and determine the current filling elevation H. n , n is the number of filling times;

[0035] Step S6: reverse excavation, the excavation depth is H n -h n-1 ,h n-1 The top elevation of the protective device measured before the n-1th filling, when the protective device is lifted after the excavation is completed;

[0036] Step S7: Use an inclinometer to measure, and the current horizontal displacement read by the inclinometer is recorded as C n The current depth of the inclinometer tube read by the inclinometer is recorded as L n , the effective data depth range is L n -X n-1 , X n-1 is the length of the first aluminum alloy tube during the n-1th filling. The total horizontal displacement of the foundation during construction is the horizontal displacement C of the section of the inclinometer tube that does not include the first aluminum alloy tube.n Subtract the initial horizontal displacement C0;

[0037] Step S8: After splicing the inclinometer tube, select a first aluminum alloy tube of appropriate length. The current length of the first aluminum alloy tube is recorded as X. n , placing the first aluminum alloy tube into the inclinometer tube, and placing the protective device on the top of the spliced ​​inclinometer tube;

[0038] Step S9: Backfill the soil around the protective device and tamp it so that the top surface of the protective device is flush with the ground. Record the top surface elevation of the protective device as h. n ;

[0039] Step S10: repeat steps S5 to S9 until the filling is completed.

[0040] Furthermore, in step S3, the length of the first aluminum alloy tube needs to ensure that the first aluminum alloy tube extends into the inclinometer tube by 2-4 m;

[0041] In step S7, the relative horizontal displacement inside the embankment before and after one splicing is C n -C n-1 , C n-1 is the horizontal displacement of the pipe section on the inclinometer pipe that does not include the first aluminum alloy pipe during the n-1th filling;

[0042] In step S8, the inclinometer tube is spliced ​​as the roadbed is filled, and the length of each splicing is determined by the thickness of the roadbed.

[0043] The beneficial effects of the embodiments of the present invention are:

[0044] 1. The influence of strong vibrations such as impact rolling and strong tamping on the inclinometer tube is taken into consideration, which effectively prevents the inclinometer tube from being over-deformed and abnormally bent due to the intense energy during construction and backfilling of the soil around the inclinometer tube. It solves the problem that the existing inclinometer tube based on reverse excavation splicing is easily damaged by severe impacts such as impact rolling and strong tamping, and the problem that the inclinometer tube is over-bent due to impact rolling, strong tamping or backfilling, which affects subsequent measurements;

[0045] 2. Avoid the risk of damage caused by the inclinometer tube being exposed to the outside, and observe the horizontal displacement during construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0046] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0047] Figure 1 It is a schematic diagram of the overall structure of the inclinometer casing protection device of this embodiment based on reverse excavation and considering the impact load.

[0048] Figure 2 It is a schematic diagram of the structure of the inclinometer pipe protection device after installation based on reverse excavation and considering the impact load of this embodiment.

[0049] Figure 3 Schematic diagram of the structure of the diagonal brace of this embodiment.

[0050] Figure 4 Schematic diagram of the structure of the support rod of this embodiment.

[0051] In the figure, 1. inclinometer tube, 2. high modulus material layer, 3. flexible material layer, 4. shock-absorbing block, 5. diagonal support, 6. first aluminum alloy tube, 7. protective material layer, 8. thread, 9. steel wire hose, 10. handle, 11. sleeve, 12. inclinometer tube anti-blocking device, 13. support rod, 14. second aluminum alloy tube, 15. PVC tube. DETAILED DESCRIPTION

[0052] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0053] Example 1

[0054] The embodiment of the present invention provides an inclinometer casing protection device based on reverse excavation and considering impact load, such as Figure 1~2 As shown, it includes a shock-absorbing and energy-dissipating structure and a shock-absorbing block 4. The shock-absorbing block 4 is fixed at the bottom of the shock-absorbing and energy-dissipating structure and sleeved on the outer periphery of the pipe opening of the inclinometer casing 1.

[0055] In some embodiments, the shock-absorbing and energy-dissipating structure is composed of a high-modulus material layer 2 whose modulus is greater than that of the soil and a flexible material layer 3 having a buffering effect. Specifically, the flexible material layer 3 is arranged in the middle of the high-modulus material layer 2. When impact rolling or strong tamping is performed, energy is transferred from the soil to the high-modulus material layer 2. Since the modulus of the high-modulus material layer 2 is much greater than the modulus of the soil, and the contact area between the high-modulus material layer 2 and the soil is large, an obvious stress diffusion phenomenon will occur, thereby transferring energy to the surrounding soil. Furthermore, through the energy dissipation effect of the flexible material layer 3 and the shock-absorbing block 4, the vibration transmitted from the soil is weakened.

[0056] In some embodiments, the shock-absorbing and energy-dissipating structure is a shock-absorbing and energy-dissipating plate composed of two layers of high modulus material layers 2 and a flexible material layer 3 arranged between two layers of carbon fiber plates; the plane size of the shock-absorbing and energy-dissipating plate is much larger than the plane size of the shock-absorbing block 4 to ensure the shock-absorbing and energy-dissipating effect.

[0057] In some embodiments, the high modulus material layer 2 is a lightweight high modulus material layer, and the flexible material layer 3 is a lightweight flexible material layer with a buffering effect.

[0058] In some embodiments, the high modulus material layer 2 and the flexible material layer 3 are bonded with epoxy resin glue, and the shock absorbing block 4 and the shock absorbing and energy dissipating structure are bonded with epoxy resin glue to ensure the shock absorbing and energy dissipating effect.

[0059] In some embodiments, the high modulus material layer 2 is made of carbon fiber board, the flexible material layer 3 is made of rubber pad, the shock-absorbing and energy-dissipating structure is a shock-absorbing and energy-dissipating board composed of two layers of carbon fiber boards and a rubber pad arranged between the two layers of carbon fiber boards, and the shock-absorbing block 4 is fixed to the bottom of the carbon fiber board under the rubber pad to ensure the shock-absorbing and energy-dissipating effect.

[0060] In some embodiments, the high modulus material layer 2 is made of at least one of an aluminum alloy plate and a magnesium alloy plate, and the flexible material layer 3 is made of at least one of pearl cotton, sponge, and a silicone plate.

[0061] In some embodiments, the front, back, left, and right sides of the shock-absorbing and energy-dissipating plate are all provided with diagonal braces 5 for accommodating the deformation of the flexible material layer 3 under the action of impact force, etc. Figure 1 shown.

[0062] In some embodiments, Figure 3 As shown, the diagonal brace 5 comprises two steel bars hinged to form an X-shaped structure, wherein:

[0063] The four ends of the X-shaped steel bar are respectively hinged to the high modulus material layer 2 of the shock-absorbing and energy-dissipating structure through horizontally arranged bolts; the diameter of the mounting holes at the four ends of the X-shaped steel bar is larger than the screw diameter of the bolt and smaller than the diameter of the bolt head; so as to adapt to the deformation of the flexible material layer 3 and ensure its stability when lifting the shock-absorbing and energy-dissipating plate.

[0064] In some embodiments, the shock absorbing block 4 is hollow inside, and a protective material layer 7 is filled between the pipe opening of the inclinometer tube 1 and the shock absorbing block 4. The protective material layer 7 is made of low-cost flexible materials such as cotton wool and sponge to avoid damage to the pipe opening of the inclinometer tube 1.

[0065] In some embodiments, the inclinometer casing protection device based on reverse excavation and considering impact load of this embodiment further includes a first aluminum alloy tube 6, the top of the first aluminum alloy tube 6 passes through the shock absorbing block 4 and is detachably connected to the shock absorbing and energy dissipating structure, such as Figure 2As shown, the tube body of the first aluminum alloy tube 6 is inserted in the inclinometer tube 1. Excessive buried deformation based on the back-excavation method mainly occurs when the soil around the inclinometer tube 1 is backfilled and compacted. Since there is no support inside and around the inclinometer tube 1 after the inclinometer tube 1 is extended, when the inclinometer tube 1 deforms with the lateral deformation of the roadbed, strong compaction will cause the inclinometer tube 1 to tilt toward the outside of the roadbed. After splicing on this basis, when the soil is backfilled around the inclinometer tube 1, the inclination angle of the inclinometer tube 1 may become larger and larger, resulting in excessive bending, so that the inclinometer cannot be placed. The embodiment of the present invention can avoid unnecessary deformation and bending of the inclinometer tube 1 through the first aluminum alloy tube 6 in the inclinometer tube 1.

[0066] In some embodiments, an inclinometer tube anti-blocking device 12 is fixed at the bottom of the first aluminum alloy tube 6, and the side wall of the inclinometer tube anti-blocking device 12 is in contact with the inner wall of the inclinometer tube 1, and is used to collect stones, broken soil and other materials that fall into the inclinometer tube 1 when the inclinometer tube protection device (hereinafter referred to as the protection device) based on reverse excavation and considering the impact load is lifted, so as to avoid blockage of the inclinometer tube 1.

[0067] In some embodiments, the inclinometer tube anti-blocking device 12 is a rubber hollow hemisphere, the cavity of the rubber hollow hemisphere is set upward, and the side of the rubber hollow hemisphere is in contact with the inner wall of the inclinometer tube 1, effectively collecting stones, broken soil and other materials that fall into the inclinometer tube 1 when the inclinometer tube protection device based on reverse excavation considering impact load is pulled, and at the same time, the rubber hollow hemisphere can prevent the first aluminum alloy tube 6 from causing damage to the inclinometer tube 1. If necessary, lubricating oil can be applied to the side of the rubber hollow hemisphere to reduce the friction between the rubber hollow hemisphere and the inclinometer tube 1, so as to facilitate pulling and insertion.

[0068] In some embodiments, the first aluminum alloy tube 6 is threadedly connected to the shock absorbing and energy dissipating structure.

[0069] In some embodiments, the first aluminum alloy tube 6 is formed by splicing various sub-tube segments, and the sub-tube segments are detachably connected, such as by threaded connection.

[0070] In some embodiments, for the convenience of operation, each segment of the first aluminum alloy tube 6 is provided with a thread 8 , and each segment of the first aluminum alloy tube 6 is threadedly connected via a sleeve 11 .

[0071] In some embodiments, a handle 10 is provided on the top of the shock-absorbing and energy-dissipating structure to facilitate lifting the shock-absorbing and energy-dissipating structure.

[0072] In some embodiments, the side of the shock-absorbing and energy-dissipating structure and the shock-absorbing block 4 is wrapped with a steel hose 9 to prevent the shock-absorbing and energy-dissipating structure and the shock-absorbing block 4 from being too tightly connected to the soil, so as to remove the shock-absorbing and energy-dissipating structure. Specifically, the steel hose 9 is firstly spirally wrapped around the entire side of the shock-absorbing block 4 from bottom to top, and then the steel hose 9 is extended to the side along the bottom of the shock-absorbing and energy-dissipating structure, and then the entire side of the shock-absorbing and energy-dissipating structure is spirally wrapped from bottom to top. Finally, the end of the steel hose 9 can be placed on the top of the shock-absorbing and energy-dissipating structure, and specifically can be wrapped around the handle 10. Two sections of steel hose 9 can also be used to wrap around the shock-absorbing and energy-dissipating structure and the side of the shock-absorbing block 4 respectively.

[0073] In some embodiments, a circular through hole is provided on the shock-absorbing and energy-dissipating structure, and a plurality of support rods 13 are respectively located in the circular through holes and inserted into the soil around the inclinometer tube. The support rods 13 can not only ensure the stability of the protection device of this embodiment, but also further diffuse the effect of the impact load after the soil backfill is completed.

[0074] In some embodiments, Figure 4 As shown, the support rod 13 includes a second aluminum alloy tube 14 and a PVC tube 15, and the PVC tube 15 is sleeved on the outer periphery of the second aluminum alloy tube 14. The bottom of the support rod 13 can be gradually raised with backfilling, or directly left in the soil. If the support rod 13 is directly left in the soil, after the backfilling is completed, the impact load will be further diffused through the support rod 13, increasing the ability of this structure to resist the impact load. At the same time, since the support rod 13 adopts the form of a PVC tube 15 plus a second aluminum alloy tube 14, the second aluminum alloy tube 14 can be taken out when the inclinometer tube 1 is spliced ​​back and forth next time, leaving only the PVC tube 15 inside the soil, so that the rigidity of the support rod 13 will not affect the subsequent data of the inclinometer tube 1.

[0075] Example 2

[0076] This embodiment provides a method for using an inclinometer casing protection device based on reverse excavation and considering impact loads, which is performed according to the following steps:

[0077] Step S1, fix the point and drill a hole on the original foundation, install the inclinometer tube 1, record the pipe mouth elevation and the actual buried depth of the inclinometer tube 1, use the inclinometer to perform initial measurement, the measured initial depth of the inclinometer tube 1 is recorded as L0, the bottom of the inclinometer tube 1 is defined as 0 during the initial depth measurement, and the measured initial horizontal displacement of the inclinometer tube 1 is recorded as C0;

[0078] Step S2, excavating a landfill pit for burying an inclinometer tube protection device (hereinafter referred to as protection device) based on reverse excavation and considering impact load, wherein the elevation of the top surface of the landfill pit is not higher than the original ground elevation;

[0079] Step S3, according to the length of the inclinometer tube 1, select a first aluminum alloy tube 6 of appropriate length, the length of the first aluminum alloy tube 6 is recorded as X0, and the size of X0 is preferably such that the first aluminum alloy tube 6 extends into the inclinometer tube 1 by 2-4 m;

[0080] Step S4, inserting the first aluminum alloy tube 6 into the inclinometer tube 1, placing the protection device into the landfill pit, and using a level to measure the top surface elevation h0 of the protection device;

[0081] Step S5: Filling. After filling about 1-1.5 m, use metal detector / total station to locate and determine the current filling elevation H. n , n is the number of filling cycles;

[0082] Step S6: Use excavators and other construction equipment to perform reverse excavation, and the excavation depth is H. n -h n-1 ,h n-1 is the top elevation of the protective device measured before the n-1th backfilling. After a certain depth is excavated, manual excavation is performed. After the manual excavation is completed, the protective device is lifted. When the first aluminum alloy tube 6 is short, the protective device can be lifted manually. When the first aluminum alloy tube 6 is long, the protective device can be lifted by mechanical lifting equipment.

[0083] Step S7: Use an inclinometer to measure, and the current horizontal displacement read by the inclinometer is recorded as C n , the current depth of the inclinometer tube 1 read by the inclinometer is recorded as L n , the effective data depth range is L n -X n-1 , X n-1 is the length of the first aluminum alloy tube 6 during the n-1th filling, and the effective data depth range is limited to L n -X n-1 The reading of the inclinometer tube 1 where the first aluminum alloy tube 6 is located is eliminated. Therefore, the total horizontal displacement of the foundation during construction is the section of the inclinometer tube 1 that does not contain the first aluminum alloy tube 6 (0~L n The horizontal displacement C n Subtracting the initial horizontal displacement C0, the relative horizontal displacement inside the embankment before and after the first splicing is C n -C n-1 , C n-1 is the horizontal displacement of the pipe section on the inclinometer pipe 1 that does not include the first aluminum alloy pipe 6 during the n-1th filling, and the horizontal displacement refers to the displacement perpendicular to the direction of the driving lane;

[0084] Step S8: After splicing the inclinometer tube 1, select a first aluminum alloy tube 6 of appropriate length. The current length of the first aluminum alloy tube 6 is recorded as X. nThe inclinometer tube 1 is spliced ​​along with the filling of the roadbed. The length of each splicing is determined by the thickness of the roadbed filling. The first aluminum alloy tube 6 is placed in the inclinometer tube 1. The protective device is placed on the top of the spliced ​​inclinometer tube 1. With the help of the rigidity of the first aluminum alloy tube 6, the inclinometer tube 1 that has just been spliced ​​is prevented from being excessively tilted and bent when the backfill soil is rammed, and the pipe opening of the inclinometer tube 1 that has just been spliced ​​is prevented from being damaged when the backfill soil is rammed;

[0085] Step S9: backfill the soil around the protective device, and after the backfilling is completed, use a frog-type rammer or other equipment to tamp it so that the top surface of the protective device is flush with the ground, and record the elevation of the top surface of the protective device as h. n ;

[0086] Step S10: repeat steps S5 to S9 until the filling is completed.

[0087] The above description is only a preferred embodiment of the present invention and is not intended to limit the protection scope of the present invention. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention are included in the protection scope of the present invention.

Claims

1. An inclinometer casing protection device based on reverse excavation and considering impact loads, characterized in that: include: A shock-absorbing and energy-dissipating structure, the shock-absorbing and energy-dissipating structure is composed of a high-modulus material layer (2) having a modulus greater than that of the soil and a flexible material layer (3) having a buffering effect; A shock absorbing block (4), the shock absorbing block (4) is fixed to the bottom of the shock absorbing and energy dissipating structure and is sleeved on the outer periphery of the pipe opening of the inclinometer pipe (1); in: A flexible material layer (3) having a buffering effect is arranged in the middle of the high modulus material layer (2); The shock-absorbing and energy-dissipating structure is a shock-absorbing and energy-dissipating plate composed of two high-modulus material layers (2) and a flexible material layer (3) arranged between the high-modulus material layers (2); The plane size of the shock-absorbing and energy-dissipating plate is much larger than the plane size of the shock-absorbing block (4).

2. The inclinometer casing protection device based on reverse excavation and considering impact load according to claim 1 is characterized in that: The shock absorbing block (4) and the shock absorbing and energy dissipating structure are bonded with epoxy resin glue; The high modulus material layer (2) and the flexible material layer (3) are bonded together using epoxy resin adhesive.

3. The inclinometer casing protection device based on reverse excavation and considering impact load according to claim 1 is characterized in that: The high modulus material layer (2) is made of at least one of a carbon fiber plate, an aluminum alloy plate, and a magnesium alloy plate; The flexible material layer (3) is made of at least one of a rubber pad, pearl cotton, sponge, and a silicone plate.

4. The inclinometer casing protection device based on reverse excavation and considering impact load according to any one of claims 1 to 3, characterized in that: The four side surfaces of the shock-absorbing and energy-dissipating structure, namely the front, rear, left, and right sides, are all provided with diagonal braces (5) for accommodating deformation of the flexible material layer (3).

5. The inclinometer casing protection device based on reverse excavation and considering impact load according to claim 4 is characterized in that: The diagonal brace (5) comprises two steel bars hingedly connected to form an X-shaped structure, wherein: The four ends of the steel bars of the X-shaped structure are respectively hinged to the high modulus material layer (2) of the shock-absorbing and energy-dissipating structure through horizontally arranged bolts; The diameters of the mounting holes at the four ends of the steel bar of the X-shaped structure are larger than the diameter of the screw rod of the bolt and smaller than the diameter of the bolt head.

6. The inclinometer casing protection device based on reverse excavation and considering impact load according to any one of claims 1 to 3 or 5, characterized in that: It also includes a first aluminum alloy tube (6) and a support rod (13); The top of the first aluminum alloy tube (6) passes through the shock absorbing block (4) and is detachably connected to the shock absorbing and energy dissipating structure, and the tube body of the first aluminum alloy tube (6) is inserted into the inclinometer tube (1); An inclinometer tube anti-blocking device (12) is fixed at the bottom of the first aluminum alloy tube (6), and a side wall of the inclinometer tube anti-blocking device (12) is in contact with an inner wall of the inclinometer tube (1); A circular through hole is provided on the shock-absorbing and energy-dissipating structure, and a plurality of support rods (13) are respectively located in the circular through holes and inserted into the soil around the inclinometer tube.

7. The inclinometer casing protection device based on reverse excavation and considering impact load according to claim 6 is characterized in that: The first aluminum alloy tube (6) is formed by splicing various sub-tube sections, and the sub-tube sections are detachably connected; The inclinometer tube anti-blocking device (12) adopts a rubber hollow hemisphere, and the cavity of the rubber hollow hemisphere is arranged upward; The support rod (13) comprises a second aluminum alloy tube (14) and a PVC tube (15), wherein the PVC tube (15) is sleeved on the outer periphery of the second aluminum alloy tube (14); A protective material layer (7) is filled between the pipe opening of the inclinometer pipe (1) and the shock-absorbing block (4); A steel wire hose (9) is wound around the side surfaces of the shock-absorbing and energy-dissipating structure and the shock-absorbing block (4).

8. The method for using the inclinometer casing protection device based on reverse excavation and considering impact load as described in any one of claims 1 to 3, 5 or 7, characterized in that: Follow these steps: Step S1, locate a point and drill a hole on the original foundation, install an inclinometer tube (1), record the elevation of the tube mouth and the actual buried depth of the inclinometer tube (1), use an inclinometer to perform initial measurement, the measured initial depth of the inclinometer tube (1) is recorded as L0, the bottom of the inclinometer tube (1) is defined as 0 during the initial depth measurement, and the measured initial horizontal displacement of the inclinometer tube (1) is recorded as C0; Step S2, excavating a landfill pit for burying an inclinometer tube protection device (hereinafter referred to as a protection device) based on reverse excavation and considering impact load, wherein the top surface elevation of the landfill pit is not higher than the original ground elevation; Step S3, selecting a first aluminum alloy tube (6) of appropriate length according to the length of the inclinometer tube (1), the length of the first aluminum alloy tube (6) being denoted as X0; Step S4, inserting the first aluminum alloy tube (6) into the inclinometer tube (1), placing the protection device into the landfill pit, and using a level to measure the top surface elevation h0 of the protection device; Step S5: Filling. After filling 1-1.5 m, use metal detector / total station to locate and determine the current filling elevation H. n , n is the number of filling times; Step S6: reverse excavation, the excavation depth is H n -h n-1 ,h n-1 The top elevation of the protective device measured before the n-1th filling, when the protective device is lifted after the excavation is completed; Step S7: Use an inclinometer to measure, and the current horizontal displacement read by the inclinometer is recorded as C n , the current depth of the inclinometer tube (1) read by the inclinometer is recorded as L n , the effective data depth range is L n -X n-1 , X n-1 is the length of the first aluminum alloy tube (6) during the n-1th filling, and the total horizontal displacement of the foundation during construction is the horizontal displacement C of the section of the inclinometer tube (1) that does not include the first aluminum alloy tube (6). n Subtract the initial horizontal displacement C0; Step S8: After splicing the inclinometer tube (1), select a first aluminum alloy tube (6) of appropriate length. The current length of the first aluminum alloy tube (6) is recorded as X. n , placing the first aluminum alloy tube (6) into the inclinometer tube (1), and placing the protective device on the top of the spliced ​​inclinometer tube (1); Step S9: Backfill the soil around the protective device and tamp it so that the top surface of the protective device is flush with the ground. Record the top surface elevation of the protective device as h. n ; Step S10: repeat steps S5 to S9 until the filling is completed.

9. The inclinometer casing protection device based on reverse excavation and considering impact load according to claim 8 is characterized in that: In step S3, the length of the first aluminum alloy tube (6) needs to ensure that the first aluminum alloy tube (6) extends into the inclinometer tube (1) by 2 to 4 meters; In step S7, the relative horizontal displacement inside the embankment before and after one splicing is C n -C n-1 , C n-1 is the horizontal displacement of the pipe section on the inclinometer pipe (1) that does not include the first aluminum alloy pipe (6) during the n-1th filling; In step S8, the inclinometer tube (1) is spliced ​​as the roadbed is filled, and the length of each splicing is determined by the thickness of the roadbed filling.