Seamless switching method and coordination controller between energy storage systems and power generation equipment for grid connection and off-grid operation
By coordinating the controller to adjust the output voltage of the energy storage system to be in phase, frequency and phase with the output voltage of the power generation equipment, the problem of inrush current during power generation equipment switching is solved, and a stable and reliable seamless switching is achieved, thus improving the stability of the system.
Patent Information
- Application Number
- CN202210910358.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-07-29
- Publication Date
- 2026-11-10
- Estimated Expiration
- 2042-07-29
AI Technical Summary
When switching to power supply directly after the generator starts up successfully, it may cause a large inrush current, affecting system stability.
The controller obtains the output voltage, frequency, and phase difference of the power generation equipment and the energy storage system, and adjusts them to make the output voltage of the energy storage system the same as the output voltage of the power generation equipment in terms of voltage, frequency, and phase. Then, the power generation equipment is controlled to be connected to the grid.
It enables seamless switching between energy storage systems and power generation equipment, avoiding large inrush currents after the power generation equipment is connected to the grid, and improving the stability and reliability of the system.
Smart Images

Figure CN115411785B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of black-start technology, and in particular to a method and coordination controller for seamless switching between an energy storage system and a power generation device on and off the grid. Background Technology
[0002] Black start refers to the process where, when the power grid stops supplying power due to certain faults, a power plant becomes disconnected from the external grid, and all generating equipment within the power plant shuts down, the plant utilizes its local power supply to power the equipment, enabling it to operate and thus achieving self-starting of the generating equipment and restoring power supply to the grid. Black start can significantly improve the grid's fault recovery capabilities.
[0003] Power plants can use energy storage systems as a local power source for black starts. Before the generating equipment successfully starts, the energy storage system can supply power to the equipment within the power plant. After the generating equipment successfully starts, the system switches to supply power to the generating equipment. However, directly switching to power from the generating equipment after successful start-up may result in a large inrush current, affecting system stability. Summary of the Invention
[0004] This invention provides a method and coordinating controller for seamless switching between energy storage systems and power generation equipment, addressing the problem that existing black-start methods may result in large inrush currents and affect system stability when switching directly to power generation equipment after successful self-start.
[0005] In a first aspect, embodiments of the present invention provide a method for seamless switching between an energy storage system and a power generation device for grid connection and off-grid operation, applied to a coordination controller. The method for seamless switching between an energy storage system and a power generation device for grid connection and off-grid operation includes:
[0006] Obtain the output voltage of the power generation equipment and the output voltage of the energy storage system;
[0007] The output voltage of the energy storage system is adjusted according to the output voltage of the power generation equipment to make the output voltage of the energy storage system and the output voltage of the power generation equipment the same in voltage, frequency and phase;
[0008] After the output voltage of the energy storage system and the output voltage of the power generation equipment are in the same voltage, frequency and phase, the power generation equipment is controlled to be connected to the power grid.
[0009] In one possible implementation, the output voltage of the energy storage system is adjusted according to the output voltage of the power generation equipment, so that the output voltage of the energy storage system and the output voltage of the power generation equipment are in the same voltage, frequency, and phase, including:
[0010] The effective value difference between the output voltage of the power generation equipment and the output voltage of the energy storage system is obtained, and the magnitude of the output voltage of the energy storage system is adjusted according to the effective value difference to make the output voltage of the energy storage system and the output voltage of the power generation equipment the same.
[0011] The frequency difference between the output voltage of the power generation equipment and the output voltage of the energy storage system is obtained, and the frequency of the output voltage of the energy storage system is adjusted according to the frequency difference to make the output voltage of the energy storage system and the output voltage of the power generation equipment synchronized.
[0012] The phase difference between the output voltage of the power generation equipment and the output voltage of the energy storage system is obtained, and the phase of the output voltage of the energy storage system is adjusted according to the phase difference to make the output voltage of the energy storage system and the output voltage of the power generation equipment in phase.
[0013] In one possible implementation, the phase of the energy storage system's output voltage is adjusted based on the phase difference to make the output voltage of the energy storage system and the output voltage of the power generation equipment in phase, including:
[0014] The phase of the energy storage system's output voltage is adjusted in fixed steps based on the phase difference, so that the output voltage of the energy storage system and the output voltage of the power generation equipment are in phase.
[0015] In one possible implementation, the energy storage system includes multiple energy storage converters connected in parallel;
[0016] Adjusting the output voltage of the energy storage system based on the effective value difference to achieve the same voltage as the output voltage of the power generation equipment includes:
[0017] The effective value difference is broadcast to each energy storage converter in the energy storage system, so that the energy storage converter adjusts its output voltage according to the effective value difference, so that the output voltage of the energy storage system and the output voltage of the power generation equipment are the same.
[0018] Adjusting the frequency of the energy storage system's output voltage based on the frequency difference to synchronize the output voltage of the energy storage system with that of the power generation equipment includes:
[0019] The frequency difference is broadcast to each energy storage converter in the energy storage system so that the energy storage converter can adjust the frequency of its output voltage according to the frequency difference, so that the output voltage of the energy storage system and the output voltage of the power generation equipment are synchronized.
[0020] Adjusting the phase of the energy storage system's output voltage based on the phase difference to ensure that the output voltage of the energy storage system and the output voltage of the power generation equipment are in phase includes:
[0021] The phase difference is broadcast to each energy storage converter in the energy storage system, so that the energy storage converter can adjust the phase of its output voltage according to the phase difference, so that the output voltage of the energy storage system and the output voltage of the power generation equipment are in phase.
[0022] In one possible implementation, before adjusting the output voltage of the energy storage system according to the output voltage of the power generation equipment, the method for seamless on-grid / off-grid switching between the energy storage system and the power generation equipment further includes:
[0023] Determine whether the output voltage of the power generation equipment is within the preset voltage range;
[0024] If the output voltage of the power generation equipment is within the preset voltage range, the step of adjusting the output voltage of the energy storage system according to the output voltage of the power generation equipment continues.
[0025] In one possible implementation, the energy storage system is connected to the power generation equipment via a switch, and the energy storage system, the switch, and the power generation equipment are all controlled by a coordinating controller.
[0026] Controlling the connection of power generation equipment to the power grid includes:
[0027] The control switch is engaged.
[0028] Secondly, embodiments of the present invention provide a seamless switching device for grid connection and off-grid operation between an energy storage system and a power generation device, applied to a coordination controller. The seamless switching device for grid connection and off-grid operation between the energy storage system and the power generation device includes:
[0029] The acquisition module is used to acquire the output voltage of the power generation equipment and the output voltage of the energy storage system;
[0030] The synchronization module is used to adjust the output voltage of the energy storage system according to the output voltage of the power generation equipment, so that the output voltage of the energy storage system and the output voltage of the power generation equipment are the same in voltage, frequency and phase;
[0031] The grid connection module is used to control the power generation equipment to connect to the grid after the output voltage of the energy storage system and the output voltage of the power generation equipment are in the same voltage, frequency and phase.
[0032] Thirdly, embodiments of the present invention provide a coordination controller, including a processor and a memory, wherein the memory is used to store a computer program, and the processor is used to call and run the computer program stored in the memory to execute the energy storage system and power generation equipment seamless off-grid switching method as described in the first aspect or any possible implementation of the first aspect.
[0033] Fourthly, embodiments of the present invention provide a black start system for a power plant, including an energy storage system, a power generation device, a switch, and a coordination controller as described in the third aspect above; the energy storage system includes multiple energy storage converters connected in parallel;
[0034] The first terminal of the switch is connected to the energy storage system, and the second terminal of the switch is connected to the power generation equipment; the energy storage system, the power generation equipment, and the switch are all controlled by a coordinating controller.
[0035] Fifthly, embodiments of the present invention provide a computer-readable storage medium storing a computer program that, when executed by a processor, implements the steps of the seamless on-grid switching method for energy storage systems and power generation equipment as described in the first aspect or any possible implementation of the first aspect.
[0036] This invention provides a method and coordination controller for seamless switching between an energy storage system and a power generation device. By adjusting the output voltage of the energy storage system according to the output voltage of the power generation device, the output voltage of the energy storage system and the output voltage of the power generation device are made to be the same in voltage, frequency, and phase, so that the output voltages of the energy storage system and the power generation device are completely consistent. Then, the power generation device is controlled to connect to the grid. This can avoid large inrush currents after the power generation device is connected to the grid, achieve stable and reliable seamless switching, and improve system stability. Attached Figure Description
[0037] To more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.
[0038] Figure 1 This is a schematic diagram of the structure of the power plant black start system provided in an embodiment of the present invention;
[0039] Figure 2 This is a flowchart illustrating the implementation of the seamless on-grid / off-grid switching method for energy storage systems and power generation equipment provided in this embodiment of the invention.
[0040] Figure 3 This is a schematic diagram illustrating the sequence of synchronizing the output voltage of the energy storage system and the output voltage of the power generation equipment, provided by an embodiment of the present invention.
[0041] Figure 4 This is a schematic diagram of the structure of the energy storage system and power generation equipment seamless switching device between on-grid and off-grid provided in an embodiment of the present invention;
[0042] Figure 5This is a schematic diagram of the coordination controller provided in an embodiment of the present invention. Detailed Implementation
[0043] In the following description, specific details such as particular system architectures and techniques are set forth for illustrative purposes and not for limitation, in order to provide a thorough understanding of the embodiments of the invention. However, those skilled in the art will understand that the invention can be implemented in other embodiments without these specific details. In other instances, detailed descriptions of well-known systems, apparatuses, circuits, and methods are omitted so as not to obscure the description of the invention with unnecessary detail.
[0044] To make the objectives, technical solutions, and advantages of the present invention clearer, specific embodiments will be described below in conjunction with the accompanying drawings.
[0045] See Figure 1 This diagram illustrates the structure of a power plant black start system provided in an embodiment of the present invention. This power plant black start system is a system that assists a large-capacity energy storage system in performing black start-ups on a Class 9E combined high-power generating unit. See also... Figure 1 A black start system for a power plant includes an energy storage system, power generation equipment, switches, and a coordination controller; the energy storage system includes multiple parallel-connected power conversion systems (PCS).
[0046] The first terminal of the switch is connected to the energy storage system, and the second terminal of the switch is connected to the power generation equipment; the energy storage system, the power generation equipment, and the switch are all controlled by a coordinating controller.
[0047] in, Figure 1 Middle,U PCS U can represent the output voltage of an energy storage system. G It can represent the output voltage of a power generation device. The power generation device can be a high-power generator, such as a high-power gas turbine or a high-power hydroelectric generator, etc.
[0048] In some possible implementations, the aforementioned power plant black start system may also include an EMS (Energy Management System);
[0049] EMS connects to the coordination controller.
[0050] The EMS can send black-start start and black-start end commands to the coordination controller. Upon receiving the black-start start command, the coordination controller can, upon detecting a grid anomaly (such as a power outage), control the energy storage system to initiate a black start. This allows the energy storage system to supply power to the generator's motor, enabling the generator to start. After successful startup, the coordination controller synchronizes the generator and the energy storage system, ensuring their output voltages are identical in voltage, frequency, and phase. Finally, it controls the switch to engage, putting the generator into operation. Upon receiving the black-start end command, the coordination controller stops the black start process. After a preset delay, if it receives the black-start start command from the EMS and detects that the grid anomaly persists, it can restart the black start process.
[0051] The switch can be a relay. The coordination controller can be used to perform the following... Figure 2 The embodiment shown illustrates a method for seamless on-grid and off-grid switching between an energy storage system and power generation equipment.
[0052] See Figure 2 The diagram illustrates the implementation flowchart of the seamless switching method between the energy storage system and the power generation equipment provided in this embodiment of the invention. The seamless switching method between the energy storage system and the power generation equipment is applied to the coordination controller, and the execution subject of the method is the coordination controller.
[0053] The method is described in detail below:
[0054] In S101, the output voltage of the power generation equipment and the output voltage of the energy storage system are obtained.
[0055] This embodiment does not impose specific restrictions on the specific means by which the coordinating controller obtains the output voltage of the power generation equipment and the output voltage of the energy storage system; any feasible method can be used to achieve this.
[0056] In S102, the output voltage of the energy storage system is adjusted according to the output voltage of the power generation equipment, so that the output voltage of the energy storage system and the output voltage of the power generation equipment are the same in voltage, frequency and phase.
[0057] This embodiment adjusts the output voltage of the energy storage system by adjusting the output voltage of the power generation equipment, so that the output voltage of the energy storage system and the output voltage of the power generation equipment are the same in voltage, frequency and phase, so that the output of the energy storage system and the power generation equipment are consistent, thereby avoiding the generation of large inrush current when the power generation equipment is put into operation.
[0058] In S103, after the output voltage of the energy storage system and the output voltage of the power generation equipment are in the same voltage, frequency and phase, the power generation equipment is controlled to be connected to the power grid.
[0059] Once the output voltage of the energy storage system and the output voltage of the power generation equipment are detected to be the same in terms of voltage, frequency, and phase, the power generation equipment can be controlled to connect to the grid, achieving a stable and reliable seamless switching.
[0060] This embodiment adjusts the output voltage of the energy storage system according to the output voltage of the power generation equipment, so that the output voltage of the energy storage system and the output voltage of the power generation equipment are the same in voltage, frequency and phase. This makes the output voltage of the energy storage system and the power generation equipment completely consistent. Then, the power generation equipment is connected to the grid. This can avoid large inrush currents after the power generation equipment is connected to the grid, and can achieve stable and reliable seamless switching, thereby improving system stability.
[0061] In some embodiments, S102 may include:
[0062] The effective value difference between the output voltage of the power generation equipment and the output voltage of the energy storage system is obtained, and the magnitude of the output voltage of the energy storage system is adjusted according to the effective value difference to make the output voltage of the energy storage system and the output voltage of the power generation equipment the same.
[0063] The frequency difference between the output voltage of the power generation equipment and the output voltage of the energy storage system is obtained, and the frequency of the output voltage of the energy storage system is adjusted according to the frequency difference to make the output voltage of the energy storage system and the output voltage of the power generation equipment synchronized.
[0064] The phase difference between the output voltage of the power generation equipment and the output voltage of the energy storage system is obtained, and the phase of the output voltage of the energy storage system is adjusted according to the phase difference to make the output voltage of the energy storage system and the output voltage of the power generation equipment in phase.
[0065] See Figure 3 When synchronizing the output voltage of the energy storage system and the output voltage of the power generation equipment, the voltage can be synchronized first, then the frequency, and finally the phase, ultimately achieving complete consistency between the two outputs. Among these, U... PCS U represents the output voltage of the energy storage system. G This indicates the output voltage of the power generation equipment.
[0066] The coordinating controller collects the output voltage of the power generation equipment and the output voltage of the energy storage system, calculates the differences in magnitude, frequency, and phase between the two voltages, and transmits these differences to the energy storage system via RS-485 communication or other communication methods. This transmission serves as the basis for voltage compensation in the energy storage system. The energy storage system then adjusts the magnitude, frequency, and phase of its own output voltage based on the received differences, ultimately ensuring that the voltage of the energy storage system is essentially consistent with that of the power generation equipment.
[0067] Specifically, due to the influence of the QV droop curve in the system, the voltage magnitude will deviate depending on the reactive power. In order to ensure that the output voltage of the energy storage system is synchronized with the grid, it is necessary to adjust the output voltage of the energy storage system according to the effective value difference to achieve the same voltage in the synchronization function.
[0068] Due to the influence of the PF droop curve in the system, the voltage frequency will deviate depending on the active power. It is necessary to calculate the voltage frequency of the energy storage system and the power generation equipment separately based on the phase-locked loop in the coordinating controller. The difference between the two is used as the basis for adjusting the frequency of the energy storage system and compensating for the frequency of the output voltage to achieve the same frequency in the synchronization function.
[0069] In-phase operation is achieved by calculating the phase of the output voltage of the energy storage system and the power generation equipment using the phase-locked loop in the coordinating controller. The difference between the two is used as the basis for determining the phase direction of the energy storage system and adjusting the phase of the output voltage of the energy storage system accordingly.
[0070] In this embodiment, the phase can be adjusted by adjusting the frequency. Once the phase is finally adjusted to be consistent, the frequency will also remain consistent.
[0071] In some embodiments, adjusting the phase of the output voltage of the energy storage system based on the phase difference to make the output voltage of the energy storage system and the output voltage of the power generation equipment in phase includes:
[0072] The phase of the energy storage system's output voltage is adjusted in fixed steps based on the phase difference, so that the output voltage of the energy storage system and the output voltage of the power generation equipment are in phase.
[0073] The fixed step size adjustment can be understood as adjusting the preset step size each time the phase is adjusted, that is, adjusting step by step through the preset step size, rather than adjusting it all at once.
[0074] In some embodiments, the energy storage system described above includes a plurality of energy storage converters connected in parallel;
[0075] Adjusting the output voltage of the energy storage system based on the effective value difference to achieve the same voltage as the output voltage of the power generation equipment includes:
[0076] The effective value difference is broadcast to each energy storage converter in the energy storage system, so that the energy storage converter adjusts its output voltage according to the effective value difference, so that the output voltage of the energy storage system and the output voltage of the power generation equipment are the same.
[0077] Adjusting the frequency of the energy storage system's output voltage based on the frequency difference to synchronize the output voltage of the energy storage system with that of the power generation equipment includes:
[0078] The frequency difference is broadcast to each energy storage converter in the energy storage system so that the energy storage converter can adjust the frequency of its output voltage according to the frequency difference, so that the output voltage of the energy storage system and the output voltage of the power generation equipment are synchronized.
[0079] Adjusting the phase of the energy storage system's output voltage based on the phase difference to ensure that the output voltage of the energy storage system and the output voltage of the power generation equipment are in phase includes:
[0080] The phase difference is broadcast to each energy storage converter in the energy storage system, so that the energy storage converter can adjust the phase of its output voltage according to the phase difference, so that the output voltage of the energy storage system and the output voltage of the power generation equipment are in phase.
[0081] In this embodiment, since the energy storage system includes multiple energy storage converters connected in parallel, in order to ensure the consistency of the voltage compensation values received by all energy storage converters and the synchronization of frequency and voltage regulation, the coordinating controller uses a broadcast method to send information to the energy storage converters during the synchronization process, thereby avoiding different compensations among the various energy storage converters.
[0082] Prior to this, the coordinating controller and the PCS could communicate via point-to-point communication. For example, point-to-point communication could be used to control the PCS to start black boot, power on / off, and switch states.
[0083] In some embodiments, before adjusting the output voltage of the energy storage system according to the output voltage of the power generation equipment, the method for seamless switching between the energy storage system and the power generation equipment for grid connection or disconnection further includes:
[0084] Determine whether the output voltage of the power generation equipment is within the preset voltage range;
[0085] If the output voltage of the power generation equipment is within the preset voltage range, the step of adjusting the output voltage of the energy storage system according to the output voltage of the power generation equipment continues.
[0086] The preset voltage range refers to the voltage range of the generator's output voltage after successful startup, which can be determined based on actual experiments. When the generator's output voltage is within the preset voltage range, it can be considered that the generator has successfully started, and S101 is executed again for synchronization. When the generator's output voltage is outside the preset voltage range, it can be considered that the generator has not yet successfully started and may still be in the voltage build-up process. In this case, the generator's output voltage can be monitored until it falls within the preset voltage range, and then S101 is executed again.
[0087] In some embodiments, see Figure 1The aforementioned energy storage system is connected to the power generation equipment via a switch, and the energy storage system, switch, and power generation equipment are all controlled by a coordination controller;
[0088] Controlling the connection of power generation equipment to the power grid includes:
[0089] The control switch is engaged.
[0090] See Figure 1 In this embodiment, after the synchronization is completed, the power generation equipment can be connected to the power grid by controlling the switch to close.
[0091] In some possible implementations, in order to achieve black start, prior to S101 above, the method for seamless on-grid and off-grid switching of the energy storage system and the power generation equipment also includes:
[0092] The system controls the shutdown of all energy storage converters in the energy storage system and switches all energy storage converters in the energy storage system to off-grid VSG (Virtual Synchronous Generator) state.
[0093] The first energy storage converter is controlled to start up in a voltage soft-start manner; the first energy storage converter can be any one of the energy storage converters in the energy storage system.
[0094] After the first energy storage converter is started, all other energy storage converters in the control energy storage system are started in sequence. During and after the start-up process, the energy storage converters in the energy storage system supply power to the generators of the power plant so that the generators can drive the power generation equipment to start and restore power supply to the grid.
[0095] In this embodiment, all energy storage converters in the energy storage system are first shut down and switched to off-grid VSG state so that the parallel operation process can be completed after each energy storage converter is started.
[0096] Among them, after each energy storage converter is successfully started, power sharing control can be performed on each energy storage converter to achieve parallel operation without communication.
[0097] Voltage slow-start refers to a gradual increase in output voltage from 0, rather than an instantaneous increase. In other words, the output voltage of the first energy storage converter is gradually increased from 0, thus preventing a large instantaneous voltage surge to the transformer in the power plant system and avoiding large inrush currents.
[0098] The first energy storage converter can be any energy storage converter in the energy storage system. For example, it can be the energy storage converter with the smallest or largest number, or it can be an energy storage converter determined by other rules. No specific restrictions are made here.
[0099] This embodiment does not impose specific restrictions on the means of controlling the first energy storage converter to start up in a voltage soft-start manner; any existing feasible method can be used for implementation.
[0100] In this embodiment, after the first energy storage converter is started, the other energy storage converters in the energy storage system are started in turn. This ensures that the power and current supplied by the energy storage system to the power plant system do not increase instantaneously, but gradually, thereby improving system stability and reliability.
[0101] The order in which the energy storage converters are started can be in ascending or descending order of their numbers, or any other order; no specific restrictions are imposed here.
[0102] The energy storage converter in the energy storage system supplies power to the generators of the power plant both during and after startup. This means that the energy storage converter is connected to the power plant system as soon as it starts up, rather than after startup. This allows the voltage of the connected energy storage converter to gradually increase from low to high, rather than suddenly increasing, thus avoiding inrush current.
[0103] Once the energy storage converter starts up, it can supply power to the motor of the power generation equipment. This motor can then drive the power generation equipment to start, thereby restoring power supply to the grid.
[0104] In some possible implementations, the energy storage converter in the energy storage system can also supply power to other loads of the power plant during and after startup, without specific limitations.
[0105] This embodiment controls the first energy storage converter to start in a voltage-gradient manner, and then controls the other energy storage converters to start sequentially. This allows the output voltage of the energy storage system to gradually increase from zero, and the voltage applied to the load to also gradually increase from zero, without instantaneously applying a large voltage. Therefore, it does not bring a large inrush current to the system, which can improve the stability and reliability of the power plant system. Furthermore, by controlling the energy storage converter to switch to off-grid VSG mode, the various energy storage converters can be controlled to complete parallel operation in this state.
[0106] In some possible implementations, the energy storage converters in the above-mentioned controlled energy storage system, excluding the first energy storage converter, are started sequentially, which may include:
[0107] In the control energy storage system, all energy storage converters except the first energy storage converter are started sequentially using a voltage soft-start method.
[0108] In this embodiment, the starting method of each energy storage converter in the energy storage system, except for the first energy storage converter, can be the same as the starting method of the first energy storage converter, which is a voltage slow-start method. This allows the power and current input to the power plant system to increase more gradually and slowly, thereby further improving the system stability and reliability.
[0109] In some possible implementations, the energy storage converter in the energy storage system completes the parallel operation process in off-grid VSG mode.
[0110] In this embodiment, after the energy storage converter in the energy storage system is successfully started, it can share power with other energy storage converters in the off-grid VSG state, thus completing the parallel operation process.
[0111] In some possible implementations, the method for seamless on-grid and off-grid switching of the energy storage system and the power generation equipment before all energy storage converters in the aforementioned energy storage system are shut down may also include:
[0112] All energy storage converters in the control energy storage system are in standby mode;
[0113] When a grid anomaly is detected and a black start command is received from the EMS, the process of shutting down all energy storage converters in the energy storage system continues.
[0114] In this embodiment, the coordination controller can first control all energy storage converters in the energy storage system to be in standby mode. When it receives the black start command sent by the EMS and detects a grid anomaly, it can control all energy storage converters in the energy storage system to shut down, and then control each energy storage converter to start up in sequence.
[0115] Among them, the grid voltage can be used to determine whether the grid is abnormal. For example, if the grid voltage is lower than the preset voltage value, the grid is determined to be abnormal; otherwise, the grid is determined to be normal.
[0116] EMS can issue a black start command under human control, or it can issue a black start command after detecting that the power plant system has disconnected from the grid, and so on.
[0117] In some possible implementations, the coordinating controller can control all energy storage converters in the energy storage system to be in standby mode after detecting that the power plant system has disconnected from the grid.
[0118] In some possible implementations, the above-mentioned method for seamless on-grid and off-grid switching between energy storage systems and power generation equipment may also include:
[0119] During the black start process, if a black start end command is received from the EMS, the black start is stopped, and after a preset delay, the process jumps to the step where all energy storage converters of the energy storage system are in standby mode to continue execution.
[0120] EMS can issue a black boot termination command under human control, or it can issue a black boot termination command after detecting that there is a problem in the black boot process and it can no longer continue, and so on.
[0121] During the black start process, if the coordinating controller receives a black start end command sent by the EMS, it means that the black start should be stopped at this time. At this time, the start of the energy storage converter can be stopped, and after a preset delay, the process will jump to the step of controlling all energy storage converters of the energy storage system to be in standby state and continue to execute, and the black start can be restarted.
[0122] The preset duration can be set according to actual needs, such as 30 seconds, etc.
[0123] This embodiment uses a black boot termination command to prevent the black boot process from freezing.
[0124] In some possible implementations, the above-mentioned method for seamless on-grid and off-grid switching between energy storage systems and power generation equipment may also include:
[0125] During the startup process of each energy storage converter in the energy storage system, if a certain energy storage converter fails to start, the process skips that energy storage converter and controls the startup of the next energy storage converter.
[0126] If the number of successfully started energy storage converters in the energy storage system is less than the preset number after all energy storage converters in the energy storage system have been started, then the black start is determined to have failed.
[0127] During the process of starting up the various energy storage converters in the energy storage system, if a certain energy storage converter fails to start due to a dead battery or other faults, that energy storage converter is skipped, and the next energy storage converter is controlled to continue starting. This prevents the system from being unable to continue due to a faulty energy storage converter.
[0128] Regardless of whether the energy storage converter starts successfully or fails to start due to a fault, the startup is considered complete. If, after all energy storage converters in the energy storage system have started, the number of successfully started energy storage converters is less than a preset number, the black start is considered a failure, and subsequent black start steps cannot be performed. Personnel should be notified to repair the faulty energy storage converter. If the grid remains abnormal after repair, the black start process should continue. If the number of successfully started energy storage converters in the energy storage system is not less than the preset number, the black start of the energy storage system is considered successful.
[0129] The preset number is less than the total number of energy storage converters in the energy storage system. For example, the total number of energy storage converters in the energy storage system can be 18, and the preset number can be 16.
[0130] In some possible implementations, prior to S101 above, the method for seamless on-grid and off-grid switching of the energy storage system and the power generation equipment also includes:
[0131] After each energy storage converter in the energy storage system is successfully started, power sharing control is performed on that energy storage converter to achieve parallel operation without communication.
[0132] In some possible implementations, the aforementioned power-sharing control of the energy storage converter to achieve communication-free parallel operation may include:
[0133] Based on the droop characteristics of active power and frequency, the active power reference value of the energy storage converter is obtained;
[0134] Based on virtual inertia, the reference value of the angular frequency of the energy storage converter is determined according to the given value of active power;
[0135] Based on the droop characteristics of reactive power and voltage, the reference value of voltage amplitude of the energy storage converter is obtained;
[0136] The voltage reference value for the energy storage converter is generated based on the voltage amplitude reference value and the angular frequency reference value.
[0137] Based on the voltage reference value, voltage loop and current loop control are performed on the energy storage converter to achieve communication-free parallel operation.
[0138] This application is based on VSG to realize the off-grid parallel connection of multiple energy storage converters without communication lines and drive the motor of the power generation equipment to start. Under the high load of the motor of the power generation equipment, the system can still operate stably.
[0139] VSG is a control strategy proposed based on the correspondence between the main circuit of the grid-connected inverter and the equivalent circuit of the synchronous generator, simulating the motion equation of the synchronous generator rotor, the active power-frequency (PF) droop characteristic, and the reactive power-voltage (QV) droop characteristic.
[0140] This embodiment determines the active power reference value of the energy storage converter based on the droop characteristics of active power and frequency. By using virtual inertia, specifically virtual rotational inertia, the drop in active power and the rise in active power are slowed down, resulting in more stable active power. Based on the QV droop characteristics, the voltage amplitude reference value of the energy storage converter can be determined. According to the voltage reference value, dual closed-loop control of the energy storage converter (voltage loop and current loop) can be implemented, ultimately achieving power sharing among the energy storage converters and communication-free parallel operation.
[0141] In some possible implementations, obtaining the active power reference value of the energy storage converter based on the droop characteristics of active power and frequency can include:
[0142] Obtain the angular frequency sampling value ω of the energy storage converter fdb And based on the rated angular frequency ω0 and the angular frequency sample value ω of the energy storage converter fdb The angular frequency difference is obtained.
[0143] The active power adjustment is obtained based on the angular frequency difference.
[0144] The active power reference value is obtained based on the active power adjustment and the rated active power P0 of the energy storage converter.
[0145] The angular frequency difference is obtained by subtracting the sampled angular frequency value ω from the rated angular frequency ω0. Based on the angular frequency difference and the active power droop coefficient M, the active power adjustment is obtained. The active power adjustment is then added to the rated active power P0 to obtain the active power reference value.
[0146] In some possible implementations, the above-mentioned determination of the angular frequency reference value of the energy storage converter based on virtual inertia and the given active power value may include:
[0147] Obtain the active power sample value P of the energy storage converter fdb Based on the active power reference value and the active power sample value P fdb The difference in active power is obtained.
[0148] The angular frequency adjustment is obtained based on the difference in active power.
[0149] Based on the angular frequency adjustment and the rated angular frequency ω0 of the energy storage converter, the angular frequency reference value ω is obtained. REF .
[0150] Active power reference value minus active power sample value P fdb The active power difference is obtained. Based on the active power difference and related parameters of virtual inertia... The angular frequency adjustment amount is obtained. Adding the angular frequency adjustment amount to the rated angular frequency ω0 yields the angular frequency reference value ω. REF .in, Let be the transfer function of the inertial element. In the prior art, the transfer function of the inertial element is usually . In this embodiment, to provide a smaller moment of inertia, it is modified to... K D A coefficient greater than 1.
[0151] In some possible implementations, obtaining the voltage amplitude reference value of the energy storage converter based on the reactive power and voltage droop characteristics can include:
[0152] Obtain the reactive power reference value Q of the energy storage converter REF and reactive power sampling value Q fdb And based on the reactive power reference value Q REF and reactive power sampling value Q fdb The reactive power difference is obtained.
[0153] The voltage amplitude adjustment amount is obtained based on the reactive power difference;
[0154] Based on the voltage amplitude adjustment and the rated voltage amplitude U0 of the energy storage converter, the voltage amplitude reference value U is obtained. REF .
[0155] Reactive power reference value Q REF Subtract the reactive power sample value Q f d b The reactive power difference is obtained. Based on the reactive power difference and the reactive power droop coefficient N, the voltage amplitude adjustment is obtained. The voltage amplitude adjustment is added to the rated voltage amplitude U0 to obtain the voltage amplitude reference value U. REF .
[0156] In some possible implementations, generating the voltage reference value for the energy storage converter based on the voltage amplitude reference value and the angular frequency reference value may include:
[0157] According to the angular frequency reference value ω REF Determine the phase reference value
[0158] According to the voltage amplitude reference value U REF and phase reference value Generate the voltage reference value for the energy storage converter.
[0159] Reference value of angular frequency ω REF Perform an integration operation to obtain the phase reference value. According to the voltage amplitude reference value U REF and phase reference value It can generate voltage reference values for energy storage converters.
[0160] In some possible implementations, the above-mentioned voltage loop and current loop control of the energy storage converter based on the voltage reference value may include:
[0161] The d-axis reference voltage U is obtained by performing a dq coordinate transformation on the voltage reference value. d and q-axis reference voltage U q ;
[0162] For the d-axis reference voltage U d Perform voltage loop and current loop control to obtain the first control quantity;
[0163] For the q-axis reference voltage U q Voltage loop and current loop control are performed to obtain the second control quantity;
[0164] The first and second control quantities are modulated by SVPWM (Space Vector Pulse Width Modulation) to obtain a PWM wave, and the energy storage converter is controlled according to the PWM wave.
[0165] The dq coordinate transformation can also be called the Park transformation.
[0166] By performing a dq coordinate transformation on the voltage reference value, the d-axis reference voltage U can be obtained. d and q-axis reference voltage U q .
[0167] d-axis reference voltage U d Subtract the d-axis sampling voltage U dfdb The d-axis voltage difference is obtained, and voltage loop PI control is applied to the d-axis voltage difference to obtain the d-axis reference current I. d d-axis reference current I d Subtract the d-axis sampling current I dfdb The d-axis current difference is obtained, and a current loop PI control is applied to the d-axis current difference to obtain the third control quantity. The third control quantity is then added to U. d / 1.732, the fourth control variable is obtained. The fourth control variable is normalized to between 0 and 1 to obtain the first control variable.
[0168] q-axis reference voltage U q Subtract the q-axis sampling voltage U qfdb The q-axis voltage difference is obtained, and a voltage loop PI control is applied to the q-axis voltage difference to obtain the q-axis reference current I. q q-axis reference current I q Subtract the q-axis sampling current I qfdb The q-axis current difference is obtained, and a current loop PI control is applied to the q-axis current difference to obtain the fifth control value. This fifth control value is then added to U. q / 1.732, the sixth control variable is obtained. The sixth control variable is normalized to between 0 and 1 to obtain the second control variable.
[0169] By performing SVPWM modulation on the first and second control variables, a PWM wave can be obtained, which is used to control the energy storage converter.
[0170] Wherein, the d-axis sampling voltage U dfdb and q-axis sampling voltage U qfdb It can be obtained by performing a dq coordinate transformation based on the voltage sampling value of the energy storage converter. The d-axis reference current I...d and q-axis reference current I q This can be obtained by performing a dq coordinate transformation based on the current reference value of the energy storage converter. The d-axis sampling current I... dfdb and q-axis sampling current I qfdb It can be obtained by performing a dq coordinate transformation based on the current sampling value of the energy storage converter.
[0171] This application achieves power sharing and stable operation by applying the same control to each energy storage converter in the energy storage system, and by adding droop control and rotational inertia to the dual closed-loop control. Specifically, multiple converters are connected in parallel with the same droop coefficient, and the angular frequency and voltage are adjusted through droop control. After a period of adjustment, the output voltage and frequency of each energy storage converter tend to be consistent, ultimately achieving the goal of equal distribution of active and reactive power. At the same time, virtual inertia is added to ensure the stable operation of the system during dynamic processes, enabling the stable operation of multiple energy storage converters under the high load of the generator motor (10MW impact), with small voltage fluctuations and even power distribution, which improves the reliability of the system, and enables communication-free parallel operation with fast response speed and no communication interference.
[0172] It should be understood that the sequence number of each step in the above embodiments does not imply the order of execution. The execution order of each process should be determined by its function and internal logic, and should not constitute any limitation on the implementation process of the embodiments of the present invention.
[0173] Figure 4 A schematic diagram of the structure of the energy storage system and power generation equipment seamless switching device provided in an embodiment of the present invention is shown. For ease of explanation, only the parts related to the embodiment of the present invention are shown, and are described in detail below:
[0174] This device is used in coordination controllers. For example... Figure 4 As shown, the seamless switching device 30 between the energy storage system and the power generation equipment includes: an acquisition module 31, a synchronization module 32, and a grid connection module 33.
[0175] The acquisition module 31 is used to acquire the output voltage of the power generation equipment and the output voltage of the energy storage system;
[0176] Synchronization module 32 is used to adjust the output voltage of the energy storage system according to the output voltage of the power generation equipment, so that the output voltage of the energy storage system and the output voltage of the power generation equipment are the same in voltage, frequency and phase;
[0177] The grid connection module 33 is used to control the power generation equipment to connect to the grid after the output voltage of the energy storage system and the output voltage of the power generation equipment are in the same voltage, frequency and phase.
[0178] In one possible implementation, the synchronization module 32 is specifically used for:
[0179] The effective value difference between the output voltage of the power generation equipment and the output voltage of the energy storage system is obtained, and the magnitude of the output voltage of the energy storage system is adjusted according to the effective value difference to make the output voltage of the energy storage system and the output voltage of the power generation equipment the same.
[0180] The frequency difference between the output voltage of the power generation equipment and the output voltage of the energy storage system is obtained, and the frequency of the output voltage of the energy storage system is adjusted according to the frequency difference to make the output voltage of the energy storage system and the output voltage of the power generation equipment synchronized.
[0181] The phase difference between the output voltage of the power generation equipment and the output voltage of the energy storage system is obtained, and the phase of the output voltage of the energy storage system is adjusted according to the phase difference to make the output voltage of the energy storage system and the output voltage of the power generation equipment in phase.
[0182] In one possible implementation, the contemporaneous module 32 is also used for:
[0183] The phase of the energy storage system's output voltage is adjusted in fixed steps based on the phase difference, so that the output voltage of the energy storage system and the output voltage of the power generation equipment are in phase.
[0184] In one possible implementation, the energy storage system includes multiple energy storage converters connected in parallel;
[0185] Module 32 is also used for:
[0186] The effective value difference is broadcast to each energy storage converter in the energy storage system, so that the energy storage converter adjusts its output voltage according to the effective value difference, so that the output voltage of the energy storage system and the output voltage of the power generation equipment are the same.
[0187] The frequency difference is broadcast to each energy storage converter in the energy storage system so that the energy storage converter can adjust the frequency of its output voltage according to the frequency difference, so that the output voltage of the energy storage system and the output voltage of the power generation equipment are synchronized.
[0188] The phase difference is broadcast to each energy storage converter in the energy storage system, so that the energy storage converter can adjust the phase of its output voltage according to the phase difference, so that the output voltage of the energy storage system and the output voltage of the power generation equipment are in phase.
[0189] In one possible implementation, the energy storage system and the power generation equipment seamless switching device 30 may further include a voltage judgment module.
[0190] The voltage judgment module is used for:
[0191] Determine whether the output voltage of the power generation equipment is within the preset voltage range;
[0192] If the output voltage of the power generation equipment is within the preset voltage range, the step of adjusting the output voltage of the energy storage system according to the output voltage of the power generation equipment continues.
[0193] In one possible implementation, the energy storage system is connected to the power generation equipment via a switch, and the energy storage system, the switch, and the power generation equipment are all controlled by a coordinating controller.
[0194] Grid-connected module 33 is specifically used for:
[0195] After the output voltage of the energy storage system and the output voltage of the power generation equipment are in the same voltage, frequency and phase, the control switch is activated.
[0196] Figure 5 This is a schematic diagram of the coordination controller provided in an embodiment of the present invention. Figure 5 As shown, the coordination controller 4 in this embodiment includes a processor 40 and a memory 41. The memory 41 stores a computer program 42, and the processor 40 calls and runs the computer program 42 stored in the memory 41 to execute the steps in the above embodiments of the seamless off-grid switching method between the energy storage system and the power generation equipment, for example... Figure 2 S101 to S103 are shown. Alternatively, the processor 40 is used to call and run the computer program 42 stored in the memory 41 to implement the functions of each module / unit in the above-described device embodiments, for example... Figure 4 The functions of modules / units 31 to 33 shown.
[0197] For example, the computer program 42 can be divided into one or more modules / units, which are stored in the memory 41 and executed by the processor 40 to complete the present invention. The one or more modules / units can be a series of computer program instruction segments capable of performing a specific function, which describe the execution process of the computer program 42 in the coordination controller 4. For example, the computer program 42 can be divided into... Figure 4 Modules / units 31 to 33 are shown.
[0198] The coordination controller 4 may include, but is not limited to, a processor 40 and a memory 41. Those skilled in the art will understand that... Figure 5 This is merely an example of the coordination controller 4 and does not constitute a limitation on it. It may include more or fewer components than illustrated, or combine certain components, or use different components. For example, the coordination controller may also include input / output devices, network access devices, buses, etc. For instance, the coordination controller may also include the aforementioned DMS and OMS, etc.
[0199] The processor 40 can be a Central Processing Unit (CPU), or other general-purpose processors, digital signal processors (DSPs), application-specific integrated circuits (ASICs), field-programmable gate arrays (FPGAs), or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, etc. The general-purpose processor can be a microprocessor or any conventional processor.
[0200] The memory 41 can be an internal storage unit of the coordination controller 4, such as a hard disk or RAM of the coordination controller 4. The memory 41 can also be an external storage device of the coordination controller 4, such as a plug-in hard disk, Smart Media Card (SMC), Secure Digital (SD) card, or Flash Card equipped on the coordination controller 4. Furthermore, the memory 41 can include both internal storage units and external storage devices of the coordination controller 4. The memory 41 is used to store the computer program and other programs and data required by the coordination controller. The memory 41 can also be used to temporarily store data that has been output or will be output.
[0201] For the coordination controller mentioned above, see [link to relevant documentation]. Figure 1 The present invention also provides a black start system for a power plant, including a coordination controller as described above, and further including an energy storage system, a power generation device and a switch; the energy storage system includes multiple energy storage converters connected in parallel;
[0202] The first terminal of the switch is connected to the energy storage system, and the second terminal of the switch is connected to the power generation equipment; the energy storage system, the power generation equipment, and the switch are all controlled by a coordinating controller.
[0203] For a description of the power plant black start system, please refer to the description in the foregoing embodiments, and will not be repeated here.
[0204] Those skilled in the art will clearly understand that, for the sake of convenience and brevity, the above-described division of functional units and modules is merely an example. In practical applications, the above functions can be assigned to different functional units and modules as needed, that is, the internal structure of the device can be divided into different functional units or modules to complete all or part of the functions described above. The functional units and modules in the embodiments can be integrated into one processing unit, or each unit can exist physically separately, or two or more units can be integrated into one unit. The integrated unit can be implemented in hardware or as a software functional unit. Furthermore, the specific names of the functional units and modules are only for easy differentiation and are not intended to limit the scope of protection of this application. The specific working process of the units and modules in the above system can be referred to the corresponding process in the foregoing method embodiments, and will not be repeated here.
[0205] In the above embodiments, the descriptions of each embodiment have different focuses. For parts that are not described in detail or recorded in a certain embodiment, please refer to the relevant descriptions of other embodiments.
[0206] Those skilled in the art will recognize that the units and algorithm steps of the various examples described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, or a combination of computer software and electronic hardware. Whether these functions are implemented in hardware or software depends on the specific application and design constraints of the technical solution. Those skilled in the art can use different methods to implement the described functions for each specific application, but such implementations should not be considered beyond the scope of this invention.
[0207] In the embodiments provided by this invention, it should be understood that the disclosed device / coordination controller and method can be implemented in other ways. For example, the device / coordination controller embodiments described above are merely illustrative. For instance, the division of modules or units is only a logical functional division, and in actual implementation, there may be other division methods. For example, multiple units or components may be combined or integrated into another system, or some features may be ignored or not executed. Furthermore, the coupling or direct coupling or communication connection shown or discussed may be through some interfaces; the indirect coupling or communication connection between devices or units may be electrical, mechanical, or other forms.
[0208] The units described as separate components may or may not be physically separate. The components shown as units may or may not be physical units; that is, they may be located in one place or distributed across multiple network units. Some or all of the units can be selected to achieve the purpose of this embodiment according to actual needs.
[0209] Furthermore, the functional units in the various embodiments of the present invention can be integrated into one processing unit, or each unit can exist physically separately, or two or more units can be integrated into one unit. The integrated unit can be implemented in hardware or as a software functional unit.
[0210] If the integrated module / unit is implemented as a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, all or part of the processes in the above embodiments of the present invention can also be implemented by a computer program instructing related hardware. The computer program can be stored in a computer-readable storage medium. When executed by a processor, the computer program can implement the steps of the above embodiments of seamless off-grid switching methods for energy storage systems and power generation equipment. The computer program includes computer program code, which can be in the form of source code, object code, executable files, or certain intermediate forms. The computer-readable medium can include: any entity or device capable of carrying the computer program code, recording media, USB flash drives, portable hard drives, magnetic disks, optical disks, computer memory, read-only memory (ROM), random access memory (RAM), electrical carrier signals, telecommunication signals, and software distribution media, etc. It should be noted that the content contained in the computer-readable medium may be appropriately added to or subtracted from the content as required by the legislation and patent practice in the jurisdiction. For example, in some jurisdictions, according to legislation and patent practice, the computer-readable medium may not include electrical carrier signals and telecommunication signals.
[0211] The above-described embodiments are only used to illustrate the technical solutions of the present invention, and are not intended to limit it. Although the present invention has been described in detail with reference to the foregoing embodiments, those skilled in the art should understand that modifications can still be made to the technical solutions described in the foregoing embodiments, or equivalent substitutions can be made to some of the technical features. Such modifications or substitutions do not cause the essence of the corresponding technical solutions to deviate from the spirit and scope of the technical solutions of the embodiments of the present invention, and should all be included within the protection scope of the present invention.
Claims
1. A method for seamless switching between grid-connected and off-grid operation of an energy storage system and a power generation device, characterized in that, Applied to a coordination controller, the method for seamless on-grid and off-grid switching of the energy storage system and power generation equipment includes: The system controls all energy storage converters in the energy storage system to shut down and switches all energy storage converters in the energy storage system to off-grid VSG state. The first energy storage converter is controlled to start up in a voltage soft-start manner; the first energy storage converter is any one of the energy storage converters in the energy storage system. After the first energy storage converter is started, the other energy storage converters in the energy storage system are started sequentially. During and after the start-up process, the energy storage converters in the energy storage system supply power to the generators of the power plant so that the generators can drive the power generation equipment to start and restore the power grid. Obtain the output voltage of the power generation equipment and the output voltage of the energy storage system; The output voltage of the energy storage system is adjusted according to the output voltage of the power generation equipment, so that the output voltage of the energy storage system and the output voltage of the power generation equipment are in the same voltage, frequency and phase. After the output voltage of the energy storage system and the output voltage of the power generation equipment are in the same voltage, frequency and phase, the power generation equipment is controlled to be connected to the power grid.
2. The method for seamless switching between the energy storage system and the power generation equipment for grid connection and off-grid operation according to claim 1, characterized in that, The step of adjusting the output voltage of the energy storage system according to the output voltage of the power generation equipment, so that the output voltage of the energy storage system and the output voltage of the power generation equipment are in the same voltage, frequency, and phase, includes: The effective value difference between the output voltage of the power generation equipment and the output voltage of the energy storage system is obtained, and the magnitude of the output voltage of the energy storage system is adjusted according to the effective value difference to make the output voltage of the energy storage system and the output voltage of the power generation equipment the same. The frequency difference between the output voltage of the power generation equipment and the output voltage of the energy storage system is obtained, and the frequency of the output voltage of the energy storage system is adjusted according to the frequency difference to make the output voltage of the energy storage system and the output voltage of the power generation equipment synchronized. The phase difference between the output voltage of the power generation device and the output voltage of the energy storage system is obtained, and the phase of the output voltage of the energy storage system is adjusted according to the phase difference to make the output voltage of the energy storage system and the output voltage of the power generation device in phase.
3. The method for seamless switching between grid-connected and off-grid operation of energy storage system and power generation equipment according to claim 2, characterized in that, The step of adjusting the phase of the output voltage of the energy storage system according to the phase difference value, so that the output voltage of the energy storage system and the output voltage of the power generation equipment are in phase, includes: The phase of the output voltage of the energy storage system is adjusted by a fixed step size based on the phase difference, so that the output voltage of the energy storage system and the output voltage of the power generation equipment are in phase.
4. The method for seamless switching between grid-connected and off-grid operation of energy storage system and power generation equipment according to claim 2, characterized in that, The energy storage system includes multiple energy storage converters connected in parallel; The step of adjusting the output voltage of the energy storage system based on the effective value difference to make the output voltage of the energy storage system and the output voltage of the power generation equipment the same includes: The effective value difference is broadcast to each energy storage converter in the energy storage system, so that the energy storage converter adjusts its output voltage according to the effective value difference, so that the output voltage of the energy storage system and the output voltage of the power generation equipment are the same. The step of adjusting the frequency of the output voltage of the energy storage system according to the frequency difference, so that the output voltage of the energy storage system and the output voltage of the power generation equipment are synchronized, includes: The frequency difference is broadcast to each energy storage converter in the energy storage system, so that the energy storage converter adjusts the frequency of its output voltage according to the frequency difference, so that the output voltage of the energy storage system and the output voltage of the power generation equipment are synchronized. The step of adjusting the phase of the output voltage of the energy storage system according to the phase difference value, so that the output voltage of the energy storage system and the output voltage of the power generation equipment are in phase, includes: The phase difference value is broadcast to each energy storage converter in the energy storage system, so that the energy storage converter adjusts the phase of its output voltage according to the phase difference value, so that the output voltage of the energy storage system and the output voltage of the power generation equipment are in phase.
5. The method for seamless switching between grid-connected and off-grid operation of energy storage system and power generation equipment according to claim 1, characterized in that, Before adjusting the output voltage of the energy storage system according to the output voltage of the power generation equipment, the method for seamless on-grid / off-grid switching between the energy storage system and the power generation equipment further includes: Determine whether the output voltage of the power generation equipment is within the preset voltage range; If the output voltage of the power generation equipment is within the preset voltage range, then the step of adjusting the output voltage of the energy storage system according to the output voltage of the power generation equipment continues.
6. The method for seamless switching between energy storage system and power generation equipment on and off the grid according to any one of claims 1 to 5, characterized in that, The energy storage system is connected to the power generation equipment via a switch, and the energy storage system, the switch, and the power generation equipment are all controlled by the coordination controller; The control of the power generation equipment to connect to the power grid includes: Control the switch to engage.
7. A device for seamless switching between energy storage system and power generation equipment, characterized in that, The energy storage system and the power generation equipment seamless on-grid / off-grid switching device, applied to the coordination controller, includes: The acquisition module is used to acquire the output voltage of the power generation equipment and the output voltage of the energy storage system; The synchronization module is used to adjust the output voltage of the energy storage system according to the output voltage of the power generation equipment, so that the output voltage of the energy storage system and the output voltage of the power generation equipment are in the same voltage, frequency and phase. The grid connection module is used to control the power generation equipment to connect to the power grid after the output voltage of the energy storage system and the output voltage of the power generation equipment are in the same voltage, frequency and phase. Before obtaining the output voltage of the power generation equipment and the output voltage of the energy storage system, the method further includes: The system controls all energy storage converters in the energy storage system to shut down and switches all energy storage converters in the energy storage system to off-grid VSG state. The first energy storage converter is controlled to start up in a voltage soft-start manner; the first energy storage converter is any one of the energy storage converters in the energy storage system. After the first energy storage converter is started, the other energy storage converters in the energy storage system are started sequentially. During and after the start-up process, the energy storage converters in the energy storage system supply power to the generators of the power plant so that the generators can drive the power generation equipment to start and restore the power grid.
8. A coordination controller, characterized in that, It includes a memory and a processor, the memory being used to store a computer program, and the processor being used to call and run the computer program stored in the memory to execute the method for seamless off-grid switching of the energy storage system and power generation equipment as described in any one of claims 1 to 6.
9. A black start system for a power plant, characterized in that, It includes an energy storage system, a power generation device, a switch, and a coordination controller as described in claim 8; the energy storage system includes multiple energy storage converters connected in parallel; The first end of the switch is connected to the energy storage system, and the second end of the switch is connected to the power generation equipment; the energy storage system, the power generation equipment, and the switch are all controlled by the coordination controller.
10. A computer-readable storage medium storing a computer program, characterized in that, When the computer program is executed by the processor, it implements the steps of the method for seamless off-grid switching of the energy storage system and power generation equipment as described in any one of claims 1 to 6.