A track construction platform used for binding reinforcement bars on the top slab of prefabricated box beams
By designing a rail construction platform for prefabricated box beam roof plates, the precise positioning and movement of steel bars is achieved using pulleys and motor systems, the problem of positioning and deformation during steel bar binding is solved, the construction efficiency and quality are improved, and construction safety is ensured. .
Patent Information
- Application Number
- CN202211351688.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-10-31
- Publication Date
- 2024-12-20
- Estimated Expiration
- 2042-10-31
AI Technical Summary
During the binding process of prefabricated box girder roof steel bars, the prior art is difficult to ensure the straight positioning of the steel bars and avoid pedaling and bending, which poses safety risks and is inefficient in construction.
A system including steel bar tying tire frame and track construction platform was designed, using pulleys, motors, screw lifters and transfer systems. Through the cooperation of pulleys and inverted V-shaped slides, the precise positioning and movement of the steel bars are achieved to avoid Step on, and achieve automated lifting and movement through the combination of electromagnetic clutch and umbrella gear.
It effectively avoids deformation of steel bars, improves construction efficiency and quality, ensures the linear straightness of steel bar frames, simplifies the structure, enhances adaptability, and improves construction safety through automated control.
Smart Images

Figure CN115522749B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a track construction platform, in particular to a track construction platform used for binding reinforcement bars of a prefabricated box beam top plate. Background Art
[0002] Prefabricated box girders are a key technology in modern bridge construction. During the prefabrication process, how to improve construction efficiency is a hot research direction. The top plate of the prefabricated box girder needs to be reinforced and then poured with concrete.
[0003] At present, the top plate reinforcement of prefabricated box girders is mainly tied by workers standing on the reinforcement, which can easily cause the reinforcement to be stepped on and bent, and the box girder is difficult to position and straighten during tying. There are even safety risks. Summary of the invention
[0004] The purpose of the present invention is to provide a track construction platform for binding reinforcement bars of a prefabricated box beam top plate, which can overcome the defects of the prior art and ensure construction efficiency.
[0005] Specifically, the present invention adopts the following technical solutions:
[0006] A track construction platform for tying steel bars of a prefabricated box girder top plate comprises a steel bar tying frame, the steel bar tying frame comprises a bracket, the bracket comprises a left bracket, a right bracket and a middle bracket, the left bracket, the right bracket and the middle bracket are all provided with cross beams, the cross beams are arranged on the brackets at intervals and are extended along the longitudinal direction of the brackets; tracks, steel bar longitudinal positioning beams, steel bar transverse positioning beams are arranged on the left and right cross beams in sequence from outside to inside, and an angle steel beam positioning bracket is arranged on the middle cross beam for positioning and supporting the angle steel beam; the tracks, the steel bar longitudinal positioning beams, the steel bar transverse positioning beams, the angle steel beam positioning brackets, and the steel beams are all extended along the longitudinal direction of the brackets. The invention also includes a track construction platform, which includes a base plate, a pulley is arranged below the base plate, and the pulley can be supported on the track and move along the track; it also includes a motor arranged in the middle of the base plate, and the motor drives the lifting system and the moving system of the track construction platform through a transfer system; the lifting system includes a screw lifter located at the four corners of the base plate; the moving system includes a driving wheel fixed on the shaft, and the driving wheel is engaged with the track and can drive the track construction platform to move along the track; the shaft is driven by the motor through the transfer system, and the input shaft of the screw lifter is driven by the shaft of the moving system.
[0007] Furthermore, a wheel bracket is provided below the bottom plate, and a pulley is arranged on the wheel bracket;
[0008] The pulley has a V-shaped sliding groove, and the track has an inverted V-shaped sliding rail, and the sliding groove and the sliding rail are adapted to each other.
[0009] Furthermore, the longitudinal steel bar positioning beam is used to support and position the longitudinally arranged steel bars, and the transverse steel bar positioning beam is used to support and position the transversely arranged steel bars. Notches are arranged at intervals on the transverse steel bar positioning beam, and the spacing distance of the notches is set according to the arrangement design of the prefabricated box girder top plate steel bars; the longitudinal steel bar positioning beam includes several spaced-apart vertical steel plates and connecting steel bars located between the steel plates, and a receiving groove is formed between the two steel plates for receiving the steel bars; the angle steel beam positioning bracket is used to support the angle steel beam, and the angle steel beam is supported on the vertical support rod of the angle steel beam positioning bracket in an inverted right-angle manner.
[0010] Furthermore, the screw lifter includes an input shaft and a lifting rod, one end of the input shaft is connected to the screw lifter, and the other end is connected to the shaft, the shaft is supported on the base plate by bearings, and the two parallel shafts are arranged perpendicular to the direction of the track, and the four screw lifters are connected into two groups, each group of two linkage combinations; the motor drives the two parallel shafts to rotate in the same direction through the transfer system, and each shaft drives two screw lifters. The four screw lifters drive their lifting rods to rise and fall under the drive of the driving shaft, and a universal wheel is arranged under each lifting rod; the four screw lifters complete the lifting action synchronously.
[0011] Furthermore, pulleys or sprockets are provided on both sides of the V-shaped groove of the pulley; the driving wheel is arranged directly above the pulley, and pulleys or sprockets are correspondingly provided on both sides of the driving wheel, the shaft drives the driving wheel to rotate, and the driving wheel further drives the pulley to rotate through a chain or belt.
[0012] Furthermore, the output shaft of the motor is connected to a bevel gear, and two bevel gears are vertically meshed on both sides of the bevel gear. The output shaft of each of the two bevel gears is provided with an input bevel gear that rotates synchronously, and the output bevel gear is meshed with the input bevel gear configured on the shaft; the power from the motor is transmitted to the two shafts through the transfer system composed of bevel gears, driving the two shafts to rotate synchronously and in the same direction.
[0013] Furthermore, an electromagnetic clutch is arranged on the shaft near each screw lifter, and the electromagnetic clutch is arranged between the screw lifter and the driving wheel; the fixed part of the electromagnetic clutch is installed on the base plate, its input end is the shaft, and its output end is the driving shaft of the screw lifter, and the input power of the shaft is input or disconnected to the driving shaft through the electromagnetic clutch.
[0014] Furthermore, the construction platform also includes a cover body, which covers the top of the base plate and covers the lifting, moving and driving systems from above. The top of the cover body is the platform for construction workers to stand.
[0015] Furthermore, it also includes a control device and a power line connected to the motor, the control device serves as the power supply system and control system of the motor; the power line is used for an external power supply.
[0016] The present invention also provides an operation method of a track construction platform for binding reinforcement bars of a prefabricated box beam top plate, comprising the following steps:
[0017] Step 1: construct a steel bar binding frame, which is constructed according to the parameters of the prefabricated box girder top plate to be constructed, and a track is set on the frame;
[0018] Step 2: Move the construction platform to the front of the tire frame, control the electromagnetic clutch to engage through the control device, start the lifting control of the construction platform; make the construction platform rise and align the pulley of the construction platform with the track of the tire frame; and move the construction platform forward for a distance;
[0019] Step 3: Control the construction platform to descend so that the pulley of the construction platform is accurately embedded in the track; continue to reverse the motor so that the lifting rod of the construction platform continues to retract;
[0020] Step 4: Control the electromagnetic clutch to disconnect through the control device, and the rotation of the motor will not be transmitted to the lifting system; at the same time, rotate the motor forward and reverse, and debug the equipment;
[0021] Step 5: After the equipment is debugged, move the construction platform to the specified starting position and start the operation;
[0022] Step 6: The control device drives the motor to rotate at a fixed time, so that the construction platform moves a predetermined distance after a predetermined time.
[0023] The present invention uses a track-type construction platform, which can effectively avoid stepping on the steel bars that have been tied during the steel bar tying process, causing the steel bars to deform;
[0024] The tire frame is welded strictly according to the drawings using channel steel and steel plates to ensure that the tied steel bars meet the construction and design requirements;
[0025] Use pulley blocks to complete the steel bar binding and moving construction on the top plate;
[0026] Greatly improve the construction efficiency, and the construction quality can be guaranteed;
[0027] Tying the steel bars on the tire frame can ensure that the steel bar skeleton is linear, straight and beautiful;
[0028] The lifting system is adopted to avoid the defects of the upper and lower rails of the hoisting platform in the prior art; the self-driving system is adopted to avoid the additional traction system, and the same set of driving devices is used to drive the lifting and moving systems at the same time, so that the structure of the present invention is compact and has strong adaptability.
[0029] At the same time, the driving system of the present invention can automatically control the moving speed and distance, facilitate the steel bar binding, and ensure the construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] Figure 1 Schematic diagram of a steel bar binding frame of a track construction platform for binding steel bars of a prefabricated box girder top plate according to an embodiment of the present invention;
[0031] Figure 2 It is an overall schematic diagram of a track construction platform for binding reinforcement bars of a prefabricated box girder top plate according to an embodiment of the present invention;
[0032] Figure 3 Schematic diagram of a driving system of a track construction platform for binding reinforcement bars of a prefabricated box girder top plate according to an embodiment of the present invention;
[0033] Figure 4 It is a structural schematic diagram of the bottom plate of the track construction platform to which the reinforcement of the top plate of the prefabricated box beam is tied according to an embodiment of the present invention;
[0034] Figure 5 It is a schematic diagram of the cooperation between the bottom plate and the cover of the track construction platform for binding the reinforcement of the top plate of the prefabricated box beam according to an embodiment of the present invention;
[0035] Figure 6 Schematic diagram of a moving system of a track construction platform for binding reinforcement bars of a prefabricated box girder top plate according to an embodiment of the present invention;
[0036] Figure 7 It is a schematic diagram of the sub-system of the track construction platform for binding the reinforcement of the top plate of the prefabricated box beam according to an embodiment of the present invention. DETAILED DESCRIPTION
[0037] The present invention is described in detail below with reference to the accompanying drawings.
[0038] like Figure 1 As shown, the present invention provides a track construction platform for steel bar binding of a prefabricated box girder top plate, including a steel bar binding frame, the steel bar binding frame including a bracket 1, the bracket 1 is constructed of three parts by a steel rail, a crossbeam 11 is arranged on the left bracket and the right bracket, and a crossbeam 111 is arranged on the middle bracket, the crossbeams 11, 111 are arranged on the bracket 1 at intervals, and are extended along the longitudinal direction of the bracket 1. The left and right crossbeams 11 are sequentially arranged from outside to inside with a track 11, a steel bar longitudinal positioning beam 13, and a steel bar transverse positioning beam 14, and an angle steel beam positioning bracket 16 is arranged on the middle crossbeam 111 for positioning and supporting an angle steel beam 15. The track 11, the steel bar longitudinal positioning beam 13, the steel bar transverse positioning beam 14, the angle steel beam positioning bracket 16, and the steel beam 15 all extend along the longitudinal direction of the bracket 1, that is, along the construction direction of the prefabricated box girder top plate.
[0039] The longitudinal steel bar positioning beam 13 is used to support and position the longitudinally arranged steel bars, and the transverse steel bar positioning beam 14 is used to support and position the transversely arranged steel bars. Notches are arranged at intervals on the transverse steel bar positioning beam 14. The spacing distance of the notches is set according to the arrangement design of the steel bars of the prefabricated box girder top plate. When in use, the steel bars can be directly placed in the notches to complete the transverse spacing positioning of the steel bars.
[0040] The steel bar longitudinal positioning beam 13 includes several spaced-apart vertical steel plates and connecting steel bars between the steel plates, so that a receiving groove is formed between the two steel plates. When in use, the steel bar is longitudinally arranged in the receiving groove, thereby completing the longitudinal positioning of the steel bar.
[0041] The angle steel beam positioning bracket 16 is used to support the angle steel beam 15 , and the angle steel beam 15 is supported on the vertical support rod of the angle steel beam positioning bracket 16 in a right-angled inverted manner.
[0042] The transverse steel bars, longitudinal steel bars and angle steel beams are arranged on the frame strictly according to the design, so that they can be tied to ensure that the tied steel bars are straight and neat.
[0043] refer to Figure 2-7 The track construction platform for tying reinforcement bars of the top plate of a prefabricated box beam of the present invention further comprises a track construction platform, the track construction platform comprises a bottom plate 53, a wheel bracket 531 is arranged below the bottom plate 53, a pulley 251 is arranged on the wheel bracket 531, the pulley 251 can be supported on the track 11 and move along the track 11. In particular, the pulley 251 has a V-shaped slide groove, the track 11 has an inverted V-shaped slide rail, the slide groove and the slide rail are adapted to each other, so that the pulley 251 is stably supported in the slide rail 11 without falling off the rail.
[0044] A transmission system is fixed above the bottom plate 53 , and the transmission system includes a lifting system and a moving system.
[0045] The lifting system includes screw lifters 23 located at the four corners of the base plate 53, and a motor 283 located in the middle of the base plate 53. The screw lifter 23 includes an input shaft 291 and a lifting rod 22. One end of the input shaft 291 is connected to the screw lifter 23, and the other end is connected to the shaft 29. The shaft 29 is supported on the base plate 53 by a bearing. In this way, two parallel shafts 29 are arranged perpendicular to the direction of the track 11, and the four screw lifters 23 are connected into two groups, each group of two linkage combinations. It also includes a motor 283, which is fixed in the middle of the base plate 53, and drives the two parallel shafts 29 to rotate in the same direction through the transfer system 281. Each shaft 29 drives two screw lifters 23, thus forming a lifting device with four screw lifters 23 linkage. The four screw lifters 23 drive their lifting rods 22 to rise and fall under the drive of the drive shaft 291, and a universal wheel 21 is arranged below the lifting rod 22. When the motor 283 rotates forward, the lifting rod 22 extends toward the ground until the universal wheel 21 touches the ground. The lifting height of the bottom plate 53 is adjusted so that the pulley 251 is aligned with the slide rail 11. Then the motor 283 is reversed and the height of the bottom plate is adjusted again so that the lifting rod 22 extends toward the sky. As the bottom plate descends, the pulley 251 is engaged with the track 11. The four screw lifters 23 complete the lifting action synchronously. In this way, the track construction platform can be exempted from hoisting and can achieve the upper and lower rail actions by relying on its own power.
[0046] On the shaft 29, an electromagnetic clutch 24 is provided near each screw lifter 23, and a driving wheel 25 is provided on the side of the electromagnetic clutch 24 away from the screw lifter 23. The fixed part of the electromagnetic clutch 24 is installed on the bottom plate 53, and its input end is the shaft 29, and its output end is the driving shaft 291, so that the input power of the shaft 29 can be input or disconnected to the driving shaft 291 through the electromagnetic clutch. When the platform completes the rail-mounting action, the electromagnetic clutch needs to be disconnected, thereby ensuring that the lifting action of the platform is completed and terminated.
[0047] refer to Figure 6 , shows a mobile system of a track construction platform of the present invention, which includes a driving wheel 25 driven by a shaft 29 fixed above a bottom plate 53, and a pulley 251 fixed below the bottom plate 53 through a support 531, and pulleys or sprockets are arranged on both sides of the V-shaped groove of the pulley 251. The two ends of the driving wheel 25 can be supported by a bearing seat and a bearing 26, and only part of the bearing 26 is schematically shown in the figure. The driving wheel 25 is arranged directly above the pulley 251, and the shaft 29 drives the driving wheel 25 to rotate, and the driving wheel 25 further drives the pulley 251 to rotate through a chain or a belt.
[0048] In this way, the construction platform of the present invention can be lifted and moved by a power system, and has a simple structure and high reliability.
[0049] Reference again Figure 7 , which shows the transfer system of the present application, including a motor 283, the output shaft of the motor 283 is connected to a bevel gear 2811, and the two sides of the bevel gear 2811 are respectively vertically meshed with bevel gears 2812 and 2813. Taking one end as an example, the output shaft of the bevel gear 2813 is equipped with a bevel gear 271 that rotates synchronously, and the bevel gear 271 is meshed with the bevel gear 272 configured on the shaft 29. Thus, the power from the motor 283 is transmitted to the upper and lower shafts 29 through the bevel gears, and the drive shafts 29 rotate synchronously and in the same direction, and the shafts 29 then drive the drive wheels 25 and the pulleys 251 to rotate, so that the construction platform can move along the track 11.
[0050] refer to, Figure 4 On the bottom plate 53 of the present invention, a hollow elongated groove 41 is respectively provided at the four corners, and the elongated groove 41 allows the chain or belt between the driving wheel 25 and the pulley 251 to pass through, and at the same time allows the lifting rod 22 of the screw lifter 23 to pass through.
[0051] In a particular embodiment, the screw lifter 23, the electromagnetic clutch 24, the seat of the bearing 26, and the bracket 531 are all fixedly arranged on both sides of the elongated slot 41. Due to the provision of the elongated slot, the lateral position of the driving wheel 25 can be adjusted, that is, the driving wheel 25 can be adjusted along the length direction of the elongated slot to adapt to the width of the track 11; at the same time, the position of the pulley 251 will also be adjusted accordingly to match the driving wheel. The presence of the elongated slot makes it possible for the mobile construction platform of the present invention to adapt to different types of box beam top plates. It is only necessary to adjust the installation position of the screw lifter 23, the driving wheel 25, and the bracket 531 to achieve adaptation to tracks 11 of different widths. In this way, the adaptability of the product is enhanced.
[0052] refer to Figure 5 The construction platform of the present invention further comprises a cover 52, which covers the top of the bottom plate 53 and covers the lifting, moving and driving system of the present invention from above. The top of the cover 52 is the platform for construction workers to stand.
[0053] The control device 60 and the power line 61 connected to the motor 281 are also included. The control device 60 serves as the power supply system and control system of the motor. The power line is used for external power supply.
[0054] The control device 60 can control the rotation of the motor, for example, timed rotation, so that when the worker completes a certain distance of steel bar binding work, the construction platform automatically moves forward, so that the worker can bind the next section of steel bars. In particular, the control device 60 can be equipped with a remote control device, such as a Bluetooth control device, so that the worker can repeatedly control the mobile construction platform to move forward, backward, or up and down during construction.
[0055] The control device 60 is also electrically connected to the electromagnetic clutch 24 and can disconnect or engage the electromagnetic clutch 24 .
[0056] The present invention also provides an operation method of a track construction platform used for binding reinforcement bars of a prefabricated box girder top plate, comprising the following steps:
[0057] Step 1: constructing a tire frame, which is constructed according to the parameters of the prefabricated box girder top plate to be constructed, ensuring that it can support and position the pre-tied steel bars in a standard and regular manner, and at the same time setting tracks on the tire frame;
[0058] Step 2: Move the construction platform to the front of the tire frame by locomotive traction or manual traction, start the construction platform lifting control, control the electromagnetic clutch 24 to engage through the control device 60, so that the construction platform is raised and the pulley 251 of the construction platform is aligned with the track 11 of the tire frame; and move the construction platform forward for a distance, which is used as the debugging distance; this movement can be achieved by traction or manual push.
[0059] Step 3: Control the construction platform to descend so that the pulley 251 of the construction platform is accurately fitted into the track 11; continue to reverse the motor so that the lifting rod 23 of the construction platform continues to retract until it leaves the ground at a certain height, which does not affect the movement of the construction platform; when the motor is reversed and the lifting rod 23 is retracted, the pulley 251 will drive the construction platform to move backward within the debugging distance;
[0060] Step 4: Control the electromagnetic clutch 24 to be disconnected through the control device 60, so that the rotation of the motor will not be transmitted to the lifting system; at the same time, the motor is rotated forward and reversed, and the equipment is debugged;
[0061] Step 5: After the equipment is debugged, move the construction platform to the specified starting position and start the operation.
[0062] Step 6: The control device 60 drives the motor to rotate at a fixed time, so that the construction platform moves a predetermined distance after a predetermined time. Within the predetermined time, the workers will complete the steel bar binding of the predetermined distance. In this way, the work efficiency of the workers is guaranteed. The predetermined time can be adjusted. At the same time, during the period of timing the motor driving, the motor can also be controlled to stop, forward and reverse at any time to deal with various unexpected or temporary situations.
[0063] The construction platform of the present invention has a high degree of automation, can ensure that the top plate reinforcement is tied straight and regular, ensure construction safety, and improve the construction efficiency of workers.
[0064] Finally, it should be noted that the embodiments described above are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present invention.
Claims
1. A track construction platform for tying reinforcement bars on the top plate of a prefabricated box beam. Features: It includes a steel bar binding frame, the steel bar binding frame includes a bracket, the bracket includes a left bracket, a right bracket and a middle bracket, the left bracket, the right bracket and the middle bracket are all provided with cross beams, the cross beams are arranged on the brackets at intervals, and are extended along the longitudinal direction of the brackets; tracks, steel bar longitudinal positioning beams, steel bar transverse positioning beams are arranged on the left and right cross beams in sequence from the outside to the inside, and an angle steel beam positioning bracket is arranged on the middle cross beam for positioning and supporting the angle steel beam; the tracks, steel bar longitudinal positioning beams, steel bar transverse positioning beams, angle steel beam positioning brackets, and steel beams all extend along the longitudinal direction of the brackets; it also includes a track construction platform The track construction platform comprises a bottom plate, a pulley is arranged below the bottom plate, the pulley can be supported on the track and move along the track; it also comprises a motor arranged in the middle of the bottom plate, the motor drives the lifting system and the moving system of the track construction platform through the transfer system; the lifting system comprises screw lifters located at the four corners of the bottom plate; the moving system comprises a driving wheel fixed on the shaft, the driving wheel is engaged with the track, and can drive the track construction platform to move along the track; the shaft is driven by the motor through the transfer system, and the input shaft of the screw lifter is driven by the shaft of the moving system; The screw lifter comprises an input shaft and a lifting rod, one end of the input shaft is connected to the screw lifter, and the other end is connected to the shaft, the shaft is supported on the bottom plate by a bearing, two parallel shafts are arranged perpendicular to the direction of the track, and four screw lifters are connected into two groups, each group of two linkage combinations; the motor drives the two parallel shafts to rotate in the same direction through the transfer system, each shaft drives two screw lifters, and the four screw lifters drive their lifting rods to rise and fall under the drive of the driving shaft, and a universal wheel is arranged under each lifting rod; the four screw lifters complete the lifting action synchronously; On the shaft, an electromagnetic clutch is arranged near each screw lifter, and the electromagnetic clutch is arranged between the screw lifter and the driving wheel; the fixed part of the electromagnetic clutch is installed on the base plate, its input end is the shaft, and its output end is the driving shaft of the screw lifter, and the input power of the shaft is input or disconnected to the driving shaft through the electromagnetic clutch.
2. A track construction platform for tying reinforcement bars on the top plate of a prefabricated box beam according to claim 1, Features: A wheel bracket is provided below the bottom plate, and a pulley is arranged on the wheel bracket; The pulley has a V-shaped sliding groove, and the track has an inverted V-shaped sliding rail, and the sliding groove and the sliding rail are adapted to each other.
3. A track construction platform for tying reinforcement bars on the top plate of a prefabricated box beam according to claim 1, Features: The longitudinal steel bar positioning beam is used to support and position the longitudinally arranged steel bars, and the transverse steel bar positioning beam is used to support and position the transversely arranged steel bars. Notches are arranged at intervals on the transverse steel bar positioning beam, and the spacing distance of the notches is set according to the arrangement design of the prefabricated box girder top plate steel bars; the longitudinal steel bar positioning beam includes several spaced-apart vertical steel plates and connecting steel bars located between the steel plates, and a receiving groove is formed between the two steel plates for receiving the steel bars; the angle steel beam positioning bracket is used to support the angle steel beam, and the angle steel beam is supported in a right-angled inverted manner on the vertical support rod of the angle steel beam positioning bracket.
4. A track construction platform for tying reinforcement bars on the top plate of a prefabricated box beam according to claim 1, Features: Pulleys or sprockets are arranged on both sides of the V-shaped groove of the pulley; the driving wheel is arranged directly above the pulley, and pulleys or sprockets are arranged on both sides of the driving wheel accordingly, the shaft drives the driving wheel to rotate, and the driving wheel further drives the pulley to rotate through a chain or belt.
5. A track construction platform for tying reinforcement bars on the top plate of a prefabricated box beam according to claim 4, Features: The output shaft of the motor is connected to a bevel gear, and two bevel gears are vertically meshed on both sides of the bevel gear. The output shaft of each of the two bevel gears is equipped with an output bevel gear that rotates synchronously, and the output bevel gear is meshed with the input bevel gear configured on the shaft; The power from the motor is transmitted to the two shafts through a transfer system composed of bevel gears, driving the two shafts to rotate synchronously and in the same direction.
6. A track construction platform for tying reinforcement bars on the top plate of a prefabricated box beam according to claim 1, Features: The construction platform also includes a cover body, which covers the top of the bottom plate and covers the lifting, moving and driving systems from above. The top of the cover body is the platform for construction workers to stand.
7. A track construction platform for tying reinforcement bars on the top plate of a prefabricated box beam according to claim 6, Features: It also includes a control device and a power line connected to the motor. The control device serves as a power supply system and a control system for the motor; the power line is used for an external power supply.
8. An operating method for a track construction platform for tying reinforcement bars of a prefabricated box girder top plate according to any one of claims 1 to 7, Features: The following steps are involved: Step 1: construct a steel bar binding frame, which is constructed according to the parameters of the prefabricated box girder top plate to be constructed, and a track is set on the frame; Step 2: Move the construction platform to the front of the tire frame, control the electromagnetic clutch to engage through the control device, start the lifting control of the construction platform; make the construction platform rise and align the pulley of the construction platform with the track of the tire frame; and move the construction platform forward for a distance; Step 3: Control the construction platform to descend so that the pulley of the construction platform is accurately embedded in the track; continue to reverse the motor so that the lifting rod of the construction platform continues to retract; Step 4: Control the electromagnetic clutch to disconnect through the control device, and the rotation of the motor will not be transmitted to the lifting system; at the same time, rotate the motor forward and reverse, and debug the equipment; Step 5: After the equipment is debugged, move the construction platform to the specified starting position and start the operation; Step 6: The control device drives the motor to rotate at a fixed time, so that the construction platform moves a predetermined distance after a predetermined time.