Pile foundation with shear-resistant structure and pile foundation engineering construction method
By introducing a shear-resistant structure into the pile foundation and constructing a shear-resistant platform using a combination of steel reinforcement and concrete, the problem of insufficient shear resistance of existing pile foundations under horizontal loads is solved, and coordinated bearing of vertical and horizontal loads is achieved.
Patent Information
- Application Number
- CN202211322082.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-10-27
- Publication Date
- 2026-01-02
- Estimated Expiration
- 2042-10-27
AI Technical Summary
Existing pile foundations, especially those for wind tunnel equipment, have insufficient horizontal bearing capacity and shear resistance when subjected to large horizontal loads, failing to meet design requirements.
Design a pile foundation with shear resistance structure, including a shear resistance platform, a reinforced support platform and a concrete layer. A reinforcing cage is formed by combining transverse steel plates, longitudinal reinforcing bars and a ring support platform and then concrete is poured to construct a shear resistance component to enhance the horizontal bearing capacity.
It improves the anti-slip performance and anti-overturning stability of pile foundations, meets the stress requirements of horizontal loads, reduces construction costs, and achieves coordination between vertical and horizontal bearing capacity.
Smart Images

Figure CN115613620B_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The present application relates to the technical field of building construction, in particular to a pile foundation with a shear-resistant structure and a pile foundation engineering construction method. BACKGROUND
[0002] Large equipment is usually installed on an equipment foundation, which should meet the requirements of bearing capacity and normal use. In the case that natural foundation and other foundation treatment schemes cannot meet the design requirements, using a pile foundation is a reliable method. The pile foundation generally uses a concrete precast square pile or a prestressed reinforced concrete pipe pile, which has higher vertical bearing capacity and lower horizontal bearing capacity. For equipment foundations that bear large horizontal loads, such as wind tunnel equipment foundations, which often bear several hundred tons of horizontal loads, a pile foundation alone cannot meet the horizontal stress requirements. Moreover, the shear resistance of the pile foundation is usually low, and the efficiency of the pile foundation in bearing the bending moment effect of the foundation is relatively low.
[0003] In view of the problems in the related art, no effective solution has been proposed so far. SUMMARY
[0004] The present application aims to provide a pile foundation with a shear-resistant structure and a pile foundation engineering construction method to solve the problems raised in the background.
[0005] To achieve the above object, the present application provides the following technical solutions.
[0006] A pile foundation with a shear-resistant structure includes a shear-resistant structure, piles arranged in a rectangular array, a foundation pad, and a foundation layer. The shear-resistant structure comprises several transverse steel plates seamlessly joined to form a shear-resistant platform. The piles are internally hollow and open at the top. An annular support platform supporting the transverse steel plates is fixedly fitted onto the outer surface of the pile. The annular support platform and the transverse steel plates are welded together. Several reinforcing bar ties are fixedly installed at the top of each transverse steel plate. Each reinforcing bar tying column has longitudinal and transverse reinforcing bar through-holes. Longitudinal reinforcing bars are inserted into the longitudinal reinforcing bar through-holes, and transverse reinforcing bars are inserted into the transverse reinforcing bar through-holes. The reinforcing bars and the transverse reinforcing bars form a reinforcing support platform. A first concrete layer is poured on the top of the shear platform, which encloses the reinforcing support platform. The reinforcing bar ties are embedded inside the first concrete layer. The foundation pad is a second concrete layer poured on top of the first concrete layer. The piles pass through the first and second concrete layers. A concrete slab is embedded on the top surface of the first concrete layer. Secondary transverse and secondary longitudinal reinforcing bars are tied to the piles inside the second concrete layer. Inclined reinforcing bar columns are inserted at the top of the second concrete layer. The foundation layer is a third concrete layer poured on top of the second concrete layer, and the reinforcing bar columns are poured inside the third concrete layer.
[0007] Furthermore, a transverse connecting plate is fixedly provided on one side of the top edge of the transverse steel plate, and a connecting groove matching the transverse connecting plate is opened on the other side of the top edge of the transverse steel plate. A rubber sealing layer is pasted on the extrusion side of the connecting groove.
[0008] Furthermore, the top surface of the concrete slab and the top surface of the concrete layer are at the same level, a circular opening is provided on the transverse steel plate for the pile body to pass through, and several steel pipe inclined piles are provided on the outer side of the pile body.
[0009] Furthermore, the surface of the pile body is recessed with a groove, and a secondary reinforcing bar binding column is fixed in the groove. The secondary reinforcing bar binding column has binding holes, and a transverse reinforcing bar is bound to the reinforcing bar column.
[0010] Furthermore, the steel reinforcement support platform is supported by a shear-resistant component, which includes a first plate and a second plate. The first plate and the second plate are connected to each other and form a T-shaped plate between them. The shear-resistant component also includes a third plate, with the second plate connected between the first plate and the third plate. The first plate, the second plate and the third plate form an I-shaped plate.
[0011] Further, the coagulation plate is a rectangular steel plate with a hollow interior, a pouring opening is formed on the top surface of the rectangular steel plate, and a plurality of reinforcing columns arranged in a straight line are transversely arranged on the coagulation plate.
[0012] Further, the pile body is arranged with a steel reinforcement cage, the steel reinforcement cage is poured into the pile body through concrete, the top of the steel reinforcement cage penetrates the pile body and is poured into the third concrete layer, and the side of the pile body is connected with an inclined shape.
[0013] A pile foundation construction method, step S1, pile body under the ground, the pile body is arranged in a rectangular array, the steel reinforcement cage is arranged under the pile body, the steel reinforcement cage extends downward from the top of the pile body to the bottom of the pile body, and then the concrete is poured into the pile body, the poured concrete covers the steel reinforcement cage, after the first pouring of the concrete, a cast-in-place pile is formed;
[0014] Step S2, after the completion of the cast-in-place pile, the transverse steel plate is penetrated on the pile body and supported by the annular support table, the transverse steel plate after final support forms a shear platform, the longitudinal reinforcement and the transverse reinforcement are inserted into the corresponding steel reinforcement perforations, the longitudinal reinforcement and the transverse reinforcement are bound at the corresponding positions by steel wire, and finally a steel reinforcement support platform is formed, the designed shear component is fixed on the top surface of the steel reinforcement support platform by steel wire binding, then the pouring formwork is fixed on the top surface of the shear platform, the concrete is poured into the pouring formwork, after the concrete reaches the predetermined strength, the pouring formwork is removed, and a shear structure is formed;
[0015] Step S3, the auxiliary transverse reinforcement and the auxiliary longitudinal reinforcement are bound on the pile body by steel wire through the binding hole, then the pouring formwork is poured on the outside of the first concrete layer, and the concrete is poured into the pouring formwork to form the second concrete layer, when the concrete of the second concrete layer is poured, the concrete also enters the coagulation plate through the pouring opening;
[0016] Step S4, after the concrete reaches the predetermined strength, the third concrete layer is poured to form the equipment foundation layer, and finally the pouring formwork is removed.
[0017] Wherein, before the initial setting of the poured concrete, the artificial holding vibrator is used to remove the concrete bubbles before the initial setting of the concrete;
[0018] Wherein, the manufacturing method of the steel reinforcement cage is that a plurality of steels are first arranged, then a ring steel of steel material is arranged, the steels are uniformly fixed in the inner side of the ring steel by welding, and finally a ring-shaped steel reinforcement cage is formed.
[0019] In step S2, the concrete is poured into the pouring formwork, a coagulation plate is placed on the top surface of the first concrete layer before the initial setting of the concrete, the coagulation plate is pressed into the coagulation plate, and finally the concrete reaches the predetermined strength;
[0020] Wherein, in step S3, before the initial setting of the concrete of the second concrete layer, the steel reinforcement column is pressed into the irregular surface of the top surface of the second concrete layer, and then the steel reinforcement is used to bind the steel reinforcement rod on the steel reinforcement column, and finally the third concrete layer is formed by pouring.
[0021] Compared with the prior art, the present application has the following beneficial effects:
[0022] The pile foundation constructed by the method can bear vertical load through the pile, and when the foundation layer moves in a certain horizontal direction under the action of horizontal load, passive earth pressure is generated on the surface of the shear-resistant structure to resist the horizontal load on the foundation layer, thereby ensuring the anti-sliding performance of the foundation layer.
[0023] The pile body and the steel pipe inclined pile are combined to form a combined pile foundation, and in the construction process, the components provide favorable conditions for other construction procedures, improve the construction reliability, reduce the construction cost, achieve good coordination, and finally realize the combined pile foundation with vertical bearing capacity, horizontal bearing capacity and shear-resistant function.
[0024] The pile foundation construction method and the pile foundation with shear-resistant structure provided by the present application can effectively make up for the defect of the pile foundation with only vertical pile in the prior art, which cannot meet the horizontal load requirement. BRIEF DESCRIPTION OF DRAWINGS
[0025] In order to more clearly illustrate the technical solutions in the embodiments of the present application or the prior art, the drawings needed in the embodiments will be briefly introduced as follows. Obviously, the drawings in the following description only constitute some embodiments of the present application, and other drawings can be obtained by those skilled in the art without creative effort on the basis of these drawings.
[0026] Figure 1 is a front view of a pile foundation construction method and a pile foundation with shear-resistant structure according to an embodiment of the present application;
[0027] Figure 2 is a schematic diagram of a ring-shaped support platform of a pile foundation construction method and a pile foundation with shear-resistant structure according to an embodiment of the present application;
[0028] Figure 3 is a schematic diagram of a shear-resistant structure of a pile foundation construction method and a pile foundation with shear-resistant structure according to an embodiment of the present application;
[0029] Figure 4It is a pile foundation construction method and a shearing platform of pile foundation with shearing structure according to an embodiment of the present application.
[0030] Figure 5 It is a shearing platform of pile foundation with shearing structure according to an embodiment of the present application.
[0031] Figure 6 It is a shearing platform of pile foundation with shearing structure according to an embodiment of the present application.
[0032] Figure 7 It is a shearing platform of pile foundation with shearing structure according to an embodiment of the present application.
[0033] Reference signs:
[0034] 1, shearing structure; 2, pile body; 3, foundation cushion layer; 4, foundation layer; 5, transverse steel plate; 6, shearing platform; 7, annular support platform; 8, steel binding column; 9, longitudinal steel bar perforation; 10, transverse steel bar perforation; 11, longitudinal steel bar; 12, transverse steel bar; 13, steel support platform; 14, concrete layer one; 15, concrete layer two; 16, concrete slab; 17, auxiliary transverse steel bar; 18, auxiliary longitudinal steel bar; 19, steel column; 20, concrete layer three; 21, transverse connecting plate; 22, connecting groove; 23, sealing layer; 24, steel pipe inclined pile; 25, auxiliary steel binding column; 26, binding hole; 27, first plate; 28, second plate; 29, third plate; 30, steel bar; 31, pouring opening; 32, reinforcing column; 33, steel cage. DETAILED DESCRIPTION
[0035] The application will be further described below in conjunction with the drawings and specific embodiments:
[0036] In order to more clearly understand the above-mentioned purposes, features and advantages of the present application, the present application will be further described below in conjunction with the drawings and embodiments. It should be noted that the embodiments of the present application and the features in the embodiments can be combined with each other without conflict.
[0037] In the following description, many specific details are set forth in order to provide a thorough understanding of the present application, however, the present application can be practiced in different ways from those described herein, therefore, the present application is not limited to the specific embodiments disclosed in the following description.
[0038] Embodiment one:
[0039] Please refer to Figures 1-7According to the pile foundation with the shear-resistant structure, the shear-resistant platform 6 is formed by seamlessly splicing the transverse steel plates 5, the pile body 2 is internally hollow and the top of the pile body 2 is open, the annular support table 7 is fixedly arranged on the outer surface of the pile body 2 and supports the transverse steel plates 5, the transverse steel plates 5 are welded with the annular support table 7, the steel reinforcement binding columns 8 are fixedly arranged on the top ends of the transverse steel plates 5, the longitudinal steel reinforcement perforations 9 and the transverse steel reinforcement perforations 10 are arranged on the steel reinforcement binding columns 8, the longitudinal steel reinforcements 11 are arranged in the longitudinal steel reinforcement perforations 9, the transverse steel reinforcements 12 are arranged in the transverse steel reinforcement perforations 10, the longitudinal steel reinforcements 11 and the transverse steel reinforcements 12 form the steel reinforcement support platform 13, the concrete layer one 14 is arranged on the top end of the shear-resistant platform 6 and wraps the steel reinforcement support platform 13, the steel reinforcement binding columns 8 are arranged in the concrete layer one 14, the foundation cushion layer 3 is the concrete layer two 15 arranged on the top surface of the concrete layer one 14, the pile body 2 penetrates through the concrete layer one 14 and the concrete layer two 15, the concrete layer one 14 is inlaid with the concrete plate 16, the pile body 2 is arranged in the concrete layer two 15 and is bound with the auxiliary transverse steel reinforcements 17 and the auxiliary longitudinal steel reinforcements 18, the inclined steel reinforcement column 19 is arranged on the top of the concrete layer two 15, and the foundation layer 4 is the concrete layer three 20 arranged on the top surface of the concrete layer two 15.
[0040] Embodiment two
[0041] Please refer to Figure 2 and Figure 4 , one side of the top edge of the transverse steel plate 5 is fixedly provided with the transverse connecting plate 21, the other side of the top edge of the transverse steel plate 5 is provided with the connecting groove 22 matched with the transverse connecting plate 21, the extrusion side of the connecting groove 22 is pasted with the sealing layer 23 made of rubber, the top surface of the concrete plate 16 is in the same horizontal plane with the top surface of the concrete layer one 14, the transverse steel plate 5 is provided with the circular through hole through which the pile body 2 penetrates, and the outer side surface of the pile body 2 is provided with the plurality of steel pipe inclined piles 24.
[0042] Through the above scheme of the present application, the beneficial effects are: the transverse steel plate 5 is sleeved on the pile body 2, the transverse connecting plate 21 on the adjacent transverse steel plate 5 matches the connecting groove 22, and then the sealing layer 23 of rubber material is in contact with the transverse connecting plate 21, after the transverse steel plate 5 is welded with the annular support table 7, a plurality of transverse steel plates are spliced into an integral shear platform 6, and the main effect is that the concrete layer one 14 is poured on the shear platform 6, the steel reinforced support platform 13 is poured and wrapped in the concrete layer one 14, the transverse steel bars 12 and the transverse steel bars 12 are further improved, the sealing layer 23 of rubber material ensures that the transverse steel plates 5 are spliced in a seamless state; the transverse steel plate 5 is provided with a circular through hole for the pile body 2 to pass through, and the transverse steel plate 5 is supported on the annular support table 7 and then welded, so that the part of the transverse steel plate 5 passing through the pile body 2 is sealed, and the pouring of concrete will not cause leakage.
[0043] Example three:
[0044] Please refer to Figure 5 , the recessed groove is arranged on the surface of the pile body 2, the auxiliary steel bar binding column 25 is fixedly arranged in the recessed groove, the binding hole 26 is arranged on the auxiliary steel bar binding column 25, and the transverse steel bar 30 is bound on the steel bar column 19.
[0045] Through the above scheme of the present application, the beneficial effects are: the auxiliary transverse steel bar 17 is overlapped on the pile body 2, the auxiliary steel bar binding column 25 in the recess corresponds to the auxiliary transverse steel bar 17, the steel wire passes through the binding hole 26 and is bound on the auxiliary transverse steel bar 17, and the binding mode of the auxiliary longitudinal steel bar 18 is consistent, so that after the pouring of the concrete layer two, the poured concrete rigidly wraps the auxiliary transverse steel bar 17 and the auxiliary longitudinal steel bar 18, and further has the shear function, so that the final equipment foundation layer has good support mechanical stability.
[0046] Example four:
[0047] Please refer to Figure 1 , the shear assembly is supported on the steel reinforced support platform 13, the shear assembly comprises a first plate 27, a second plate 28, the first plate 27 and the second plate 28 are connected with each other and form a T-shaped plate therebetween, the shear assembly further comprises a third plate 29, the second plate 28 is connected between the first plate 27 and the third plate 29, and the first plate 27, the second plate 28 and the third plate 29 form an I-shaped plate therebetween.
[0048] Through the above scheme of the present application, the beneficial effects are: the shear assembly is bound on the steel reinforced support platform 13, that is, the second plate 28, the first plate 27 and the third plate 29 are bound, the shear assembly is poured and wrapped in the concrete layer one 14 and waits to be hardened, and has the shear effect.
[0049] Embodiment Five:
[0050] Please refer to Figure 1 , Figure 6 and Figure 7 , the coagulation plate 16 is a rectangular steel plate with a hollow interior, the top surface of the rectangular steel plate is provided with a pouring opening 31, a plurality of reinforcing columns 32 arranged in a straight line are transversely arranged on the coagulation plate 16, a steel cage 33 is arranged inside the pile body 2, and the steel cage 33 is poured into the pile body 2 by concrete, the top of the steel cage 33 penetrates out of the pile body 2 and is poured into the third concrete layer 20, and the side edge of the pile body 2 is connected with an inclined.
[0051] Through the above scheme of the present application, the beneficial effects are: while pouring the second concrete layer, the concrete will enter the coagulation plate 16 along the pouring opening 31, and the concrete will solidify, the second concrete layer, the first concrete layer, the coagulation plate 16 and the reinforcing column 32 are hardened as one, which ensures that the internal steel reinforcement after hardening has good shear resistance; each pile is a bored pile, so that the top of each pile protrudes above the upper surface of the shear-resistant structure for embedding in the interior of the foundation layer 4, and the steel reinforcement of each pile protrudes into the interior of the foundation layer 4 to ensure the firmness of the connection between each pile and the foundation layer 4.
[0052] A pile foundation construction method, comprising: step S1, embedding pile bodies 2 in the ground, arranging the pile bodies 2 in a rectangular array, embedding a steel cage 33 in the pile body 2, the steel cage 33 extending downward from the top of the pile body 2 to the bottom of the pile body 2, and then pouring concrete into the pile body 2, the poured concrete covering the steel cage 33, and after the first pouring of concrete, a bored pile is formed;
[0053] Step S2, after the completion of the bored pile, the transverse steel plate 5 is inserted on the pile body 2 and supported by the annular support table 7, the finally supported transverse steel plate 5 forms a shear-resistant platform 6, the longitudinal steel bars 11 and the transverse steel bars 12 are inserted into the corresponding steel bar perforations, the longitudinal steel bars 11 and the transverse steel bars 12 are bound at the corresponding positions by steel wires, and finally a steel reinforcement support platform 13 is formed, the designed shear-resistant assembly is fixed on the top surface of the steel reinforcement support platform 13 by steel wire binding, and then a pouring formwork is fixed on the top surface of the shear-resistant platform 6, concrete is poured into the pouring formwork, after the concrete reaches the predetermined strength, the pouring formwork is removed, and a shear-resistant structure is formed;
[0054] Step S3, the auxiliary transverse steel bars 17 and the auxiliary longitudinal steel bars 18 are bound on the pile body 2 by steel wires passing through the binding holes 26, and then a pouring formwork is arranged outside the first concrete layer 14, and concrete is poured into the pouring formwork to form the second concrete layer 15, when the concrete of the second concrete layer 15 is poured, the concrete will also enter the coagulation plate 16 along the pouring opening 31.
[0055] Step S4, after the concrete reaches the predetermined strength, the concrete layer three 20 is poured to form the equipment foundation layer, and the pouring formwork is finally removed.
[0056] Before the above pouring concrete initial setting, the artificial supporting vibrator is used to remove the concrete bubbles before the initial setting of the concrete;
[0057] The manufacturing method of the reinforcement cage 33 is that a plurality of steel bars are arranged, then a ring steel of steel material is arranged, the steel bars are uniformly fixed in the inner side of the ring steel in a ring shape by welding, and finally the ring-shaped reinforcement cage is formed.
[0058] In step S2, the concrete is poured into the pouring formwork, a concrete slab 16 is placed on the top surface of the concrete layer one 14 before the initial setting of the concrete, and the concrete slab 16 is pressed into the pouring formwork, and finally the concrete reaches the predetermined strength;
[0059] In step S3, before the initial setting of the concrete of the concrete layer two 15, the steel reinforcement column 19 is pressed into the top surface of the concrete layer two 15 in an irregular state, then the steel reinforcement column 19 is bound with the steel reinforcement bar 30 by using the steel reinforcement, and finally the concrete layer three 20 is poured;
[0060] In actual application, the pile foundation built bears the vertical load through the pile; the foundation layer 4 moves in a certain horizontal direction under the action of the horizontal load, and the passive earth pressure on the surface of the shear-resistant structure 1 resists the horizontal load acting on the foundation layer 4, so that the anti-sliding performance of the foundation layer 4 is ensured; and the anti-overturning stability of the foundation layer 4 is ensured through the combined action of the pile body 2 and the shear-resistant structure, so that the shortcomings that the pile foundation with only vertical piles in the prior art cannot meet the horizontal stress requirement are effectively made up;
[0061] The foundation layer 4 is supported by the pile body 2 and bears the punching shear force and bending moment of the pile body 2; the pile body 2 and the steel pipe inclined pile are combined to form a combined pile foundation, in the construction process, the components provide favorable conditions for other construction procedures, improve the construction reliability, reduce the construction cost, achieve a good coordination effect, and finally realize the combined pile foundation with vertical bearing capacity, horizontal bearing capacity and shear-resistant function;
[0062] Finally, the pile foundation construction method and the pile foundation with the shear-resistant structure provided by the application can effectively make up the shortcomings that the pile foundation with only vertical piles in the prior art cannot meet the horizontal stress requirement.
[0063] While embodiments of the application have been shown and described, it is to be understood that the embodiments described are merely exemplary of the principles and application of the present application. Numerous modifications and adaptions can be effected without departing from the spirit and scope of the present application, which is not limited to the exact construction and arrangement described. It is intended, therefore, to cover all modifications and adaptions that fall within the scope of the claims and their equivalents.
Claims
1. A pile foundation with a shear-resistant structure, characterized in that, The system includes a shear-resistant structure (1), piles forming a rectangular array (2), a foundation pad (3), and a foundation layer (4). The shear-resistant structure (1) includes several transverse steel plates (5), which are seamlessly spliced together to form a shear-resistant platform (6). The piles (2) are hollow inside, and the top of the piles (2) is open. An annular support platform (7) supporting the transverse steel plates (5) is fixedly fitted on the outer surface of the piles (2). The annular support platform (7) and the transverse steel plates (5) are welded together. Several reinforcing bar binding columns (8) are fixedly installed on the top of each transverse steel plate (5). The reinforcing bar binding columns (8) have longitudinal reinforcing bar through holes (9) and transverse reinforcing bar through holes (10). Longitudinal reinforcing bars (11) are inserted into the longitudinal reinforcing bar through holes (9), and transverse reinforcing bars (12) are inserted into the transverse reinforcing bar through holes (10). The longitudinal reinforcing bars (11) and the transverse reinforcing bars (12) form a reinforcing bar support. The support platform (13) has a concrete layer (14) poured on top of the shear-resistant platform (6). The concrete layer (14) encloses the steel reinforcement support platform (13), and the steel reinforcement binding column (8) is embedded inside the concrete layer (14). The foundation pad (3) is a concrete layer (15) poured on the top surface of the concrete layer (14). The pile (2) passes through the concrete layer (14) and the concrete layer (15). The top surface of the first concrete layer (14) is inlaid with a concrete slab (16), the pile body (2) inside the second concrete layer (15) is tied with secondary transverse steel bars (17) and secondary longitudinal steel bars (18), the top of the second concrete layer (15) is inserted with an inclined steel column (19), the foundation layer (4) is a third concrete layer (20) poured on the top surface of the second concrete layer (15), and the steel column (19) is poured inside the third concrete layer (20).
2. A pile foundation with shear-resistant structure according to claim 1, characterized in that, A transverse connecting plate (21) is fixedly provided on one side of the top edge of the transverse steel plate (5), and a connecting groove (22) matching the transverse connecting plate (21) is provided on the other side of the top edge of the transverse steel plate (5). A rubber sealing layer (23) is pasted on the extrusion side of the connecting groove (22).
3. A pile foundation with shear-resistant structure according to claim 2, characterized in that, The top surface of the concrete slab (16) and the top surface of the first concrete layer (14) are on the same horizontal plane. A circular opening is provided on the transverse steel plate (5) for the pile body (2) to pass through. Several steel pipe inclined piles (24) are provided on the outer side of the pile body (2).
4. A pile foundation with a shear-resistant structure according to claim 3, characterized in that, The surface of the pile body (2) is recessed with a groove, and a secondary steel bar binding column (25) is fixed in the groove. The secondary steel bar binding column (25) has binding holes (26), and a transverse steel bar rod (30) is bound on the steel bar column (19).
5. A pile foundation with shear-resistant structure according to claim 4, characterized in that, The steel reinforcement support platform (13) is supported by a shear-resistant component, which includes a first plate (27) and a second plate (28). The first plate (27) and the second plate (28) are connected to each other and form a T-shaped plate. The shear-resistant component also includes a third plate (29). The second plate (28) is connected between the first plate (27) and the third plate (29). The first plate (27), the second plate (28) and the third plate (29) form an I-shaped plate.
6. A pile foundation with shear-resistant structure according to claim 5, characterized in that, The concrete slab (16) is a rectangular steel plate with a hollow interior. A pouring port (31) is provided on the top surface of the rectangular steel plate. Multiple reinforcing columns (32) are horizontally arranged in a straight line on the concrete slab (16).
7. A pile foundation with shear resistance structure according to claim 6, wherein a steel cage (33) is arranged inside the pile body (2), and the steel cage (33) is poured into the pile body (2) by concrete, the top of the steel cage (33) protrudes from the pile body (2) and is poured into the concrete layer three (20), and the side of the pile body (2) is connected with an inclined shape.
8. A construction method for pile foundation engineering, characterized in that, A pile foundation with shear-resistant structure as described in any one of claims 1-7, comprising the following steps; Step S1: Piles (2) are laid on the ground and arranged in a rectangular array. A steel cage (33) is laid under the piles (2). The steel cage (33) extends from the top of the piles (2) downward to the bottom of the piles (2). Concrete is then poured into the piles (2). The poured concrete covers the steel cage (33). After the first pouring of concrete, a cast-in-place pile is formed. Step S2: After the cast-in-place pile is completed, the transverse steel plate (5) is inserted into the pile body (2) and supported by the ring support platform (7). The transverse steel plate (5) after support forms a shear platform (6). The longitudinal steel bars (11) and transverse steel bars (12) are inserted into the corresponding steel bar holes. The longitudinal steel bars (11) and transverse steel bars (12) are tied together with steel wire to form a steel bar support platform (13). The designed shear components are fixed to the top surface of the steel bar support platform (13) by steel wire tying. Then the formwork for pouring is fixed to the top surface of the shear platform (6). Concrete is poured into the pouring formwork. After the concrete reaches the predetermined strength, the pouring formwork is removed to form a shear structure. Step S3: Tie the secondary transverse reinforcement (17) and secondary longitudinal reinforcement (18) on the pile body (2). Tie them by passing the steel wire through the binding hole (26). Then, pour the formwork on the outside of the first concrete layer (14) and pour concrete into the formwork to form the second concrete layer (15). When pouring concrete in the second concrete layer (15), the concrete will also enter the concrete slab (16) through the pouring port (31). Step S4: After the concrete reaches the predetermined strength, pour the third concrete layer (20) to form the equipment foundation layer, and finally remove the pouring formwork.
9. A construction method for pile foundation engineering according to claim 8, characterized in that, Before the concrete initially sets, the air bubbles in the concrete are removed by manually supporting the vibrating device. The method for making the steel cage (33) is as follows: first, multiple steel bars are used, and then a steel ring is made. The steel bars are welded together to form a ring and are evenly fixed inside the ring, thus forming a ring-shaped steel cage.
10. A construction method for pile foundation engineering according to claim 9, characterized in that, In step S2, concrete is poured into the casting template. Before the concrete sets, a concrete slab (16) is placed on the top surface of the first concrete layer (14) and the concrete slab (16) is pressed in. Finally, wait for the concrete to reach the predetermined strength. In step S3, before the concrete of the second concrete layer (15) is initially set, steel bars (19) are pressed into the top surface of the second concrete layer (15) in an irregular state. Then, steel bars (30) are tied on the steel bars (19) and finally the third concrete layer (20) is formed.
Citation Information
Patent Citations
Light roadbed structure crossing karez, and design and construction methods thereof
CN111395059A
Pile foundation construction method and pile foundation with anti-shear structure
CN111395388A