A construction method for replacing flanges on offshore wind power single piles
By setting up a second bolt hole and a lifting screw hole on the top of the offshore wind power monopile, and using a crane and a lifting platform to hoist and install the replacement flange, the construction of replacement flange for large-diameter monopile piles in offshore wind power is solved. Problems of low efficiency and safety hazards were eliminated to achieve an efficient and safe construction process.
Patent Information
- Application Number
- CN202211432437.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-11-15
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2042-11-15
AI Technical Summary
In offshore wind power projects, it is inconvenient to install or remove replacement flanges on the pile tops of large-diameter single piles, resulting in low construction efficiency and potential safety hazards for construction workers.
A construction method is adopted to replace the driving flange with an offshore wind power single pile. By setting up a second bolt hole and a lifting screw hole on the replacement flange, a crane and a lifting platform are used to lift the replacement flange to the top of the single pile. , and carry out construction on a hoisting platform to ensure the safety of construction workers, and flexibly switch wire rope connections to improve construction efficiency.
It improves the construction efficiency of offshore wind power monopile pile replacement flange, ensures the safety of construction workers, reduces costs, and simplifies the construction process.
Smart Images

Figure CN115676625B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of offshore wind turbine installation, and in particular to a construction method for replacing a flange with a single offshore wind turbine pile. Background Art
[0002] In offshore wind power projects, large-diameter single pile foundations are one of the main structural types currently used in offshore wind turbine foundations. With the rapid development of offshore wind power, the diameter of the single piles used is getting larger and larger. When it is necessary to install or remove a replacement flange at the top of the single pile, it is inconvenient to work at sea, the construction efficiency is low, and there are certain construction risks for construction workers when working at high altitudes.
[0003] Therefore, in the pile replacement and flange construction of large-diameter single piles, how to improve the efficiency of offshore wind turbine installation, shorten the construction period, reduce the cost of offshore wind turbine installation, and ensure the personal safety of construction workers is an urgent problem to be solved. Summary of the invention
[0004] The present invention aims to solve at least one of the technical problems existing in the prior art. To this end, the purpose of the present invention is to provide a construction method for replacing flanges on offshore wind power monopile to solve the problems of inconvenience, low efficiency and low safety when installing or removing the replacement flanges at the top of large-diameter monopile in the prior art.
[0005] In order to achieve the above object, the present invention adopts the following technical scheme:
[0006] The present application provides a method for constructing a flange for a single offshore wind power pile, comprising the following steps:
[0007] According to the size of the single pile top and the position of the first bolt hole, a corresponding second bolt hole is opened at the flange interface of the replacement flange, and a plurality of lifting screw holes are opened at positions staggered from the second bolt hole;
[0008] Using a crane to hoist a hoisting platform above the replacement flange and drop it at the center of the replacement flange, so that at least a part of the vertical projections of the first force-bearing parts of the hoisting platform cover the replacement flange;
[0009] The construction personnel go up to the hoisting platform, install the lifting bolts at the lifting screw holes, use the crane to lift the replacement flange through the lifting bolts, and drive the hoisting platform and the construction personnel to move together;
[0010] The replacement flange is hoisted above the top of the single pile, the second bolt hole of the replacement flange is aligned with the first bolt hole of the top of the single pile, and the replacement flange is lowered, and the replacement flange and the flange at the top of the single pile are connected by bolts;
[0011] Remove the wire rope shackle on the lifting point bolt and transfer it to the lifting platform, and lift the lifting platform to the deck of the ship.
[0012] In some embodiments, when a corresponding second bolt hole is opened at the flange interface of the replacement flange according to the size of the single pile top and the opening position of the first bolt hole, and a plurality of lifting screw holes are opened at positions staggered from the second bolt hole, the method includes:
[0013] Select one of the first bolt holes on the top of the single pile, open a second bolt hole at the corresponding position of the replacement flange, select a position on the replacement flange that is diagonal to the second bolt hole, open another second bolt hole, and then evenly distribute a number of second bolt holes in the circumferential direction on both sides of the replacement flange with the two second bolt holes opened as the center, so as to form a cluster of second bolt holes with the same number located on both sides of the diagonal line;
[0014] According to the above method, for each of the first bolt holes on the top of the single pile, a corresponding cluster of second bolt holes is opened on the replacement flange.
[0015] In some embodiments, when the lifting platform is lifted above the replacement flange and falls at the center of the replacement flange, the method includes:
[0016] The first stress-bearing portion extending outward from the lifting platform is distributed between the second bolt hole cluster and the lifting screw hole so that the vertical projection of the first stress-bearing portion does not block the second bolt hole cluster and the lifting screw hole. The first stress-bearing portion is a horizontal cantilever structure, and a lifting ear is arranged at the first stress-bearing portion.
[0017] In some embodiments, when the replacement flange is lifted by a crane through the lifting point bolts and the lifting platform and the construction personnel are driven to move together, the following steps are included:
[0018] Before lifting the replacement flange until it contacts the lifting platform, open the locking structure of the first force-bearing part, rotate and adjust the angle of the replacement flange so that the locking structures of multiple first force-bearing parts all correspond to the flange interface of the replacement flange, and use the locking structure to fix the replacement flange. After fixation, drive the lifting platform and construction personnel to move together.
[0019] In some embodiments, the center point of the replacement flange is taken as the origin, the line connecting the connection point where the locking structure and the replacement flange are fixed and the origin is the first construction line, the second bolt hole at the center of the second bolt hole cluster closest to the connection point is selected, and the line connecting the second bolt hole and the origin is the second construction line, the nearest lifting screw hole located on the other side of the second bolt hole cluster opposite to the connection point is selected, and the line connecting the lifting screw hole and the origin is the third construction line, and the second construction line bisects the angle formed by the first construction line and the third construction line.
[0020] In some embodiments, the angle formed by the first construction line and the third construction line is 45°, and the angle formed by the second construction line and the third construction line is 22.5°.
[0021] In some embodiments, each of the second bolt hole clusters includes 11 second bolt holes.
[0022] In some embodiments, it also includes:
[0023] When it is necessary to remove the replacement flange from the top of the single pile, the construction personnel go to the lifting platform, lift the lifting platform onto the replacement flange by the crane, and lower the first force-bearing part of the lifting platform toward the position between the second bolt hole of the replacement flange and the lifting screw hole;
[0024] Remove the bolts between the replacement flange and the top of the single pile, remove the wire rope shackle on the lifting platform and transfer it to the lifting point bolts of the replacement flange, lift the replacement flange and move the lifting platform and construction personnel to the deck of the ship.
[0025] Compared with the prior art, the present invention has at least the following beneficial effects:
[0026] The embodiment of the present application provides a construction method for replacing a flange on a single offshore wind power pile. When installing the replacement flange, a lifting platform with a manned function is lifted above the replacement flange. When the replacement flange is lifted, the lifting platform and the construction personnel are driven to move together and fall together on the top of the single pile. The construction personnel have good personal safety protection on the lifting platform. The lifting platform provides a good and safe construction platform. The steel wire rope lifting connection between the replacement flange and the lifting platform can be flexibly converted, which makes it convenient to use a crane to lift the replacement flange or the lifting platform, thereby improving construction efficiency.
[0027] The present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] The present invention is further described using the accompanying drawings, but the embodiments in the accompanying drawings do not constitute any limitation to the present invention. A person skilled in the art can obtain other drawings based on the following drawings without creative work.
[0029] Figure 1 A schematic structural diagram of a replacement flange in a construction method for replacing a flange with a single offshore wind power pile provided in this embodiment.
[0030] Figure 2 A front view of a hoisting platform in a construction method for replacing a single offshore wind power pile with a flange provided in this embodiment.
[0031] Figure 3 A top view of a hoisting platform in a construction method for replacing a single offshore wind power pile with a flange provided in this embodiment.
[0032] Figure 4 A top view of a lifting platform placed on a replacement flange in a construction method for replacing a flange with a single offshore wind power pile provided in this embodiment.
[0033] Figure 5 An intermediate cross-sectional view of a hoisting platform placed on a replacement flange in a construction method for replacing a flange with a single offshore wind power pile provided in this embodiment. DETAILED DESCRIPTION
[0034] The technical solution of the present invention will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0035] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.
[0036] In the description of the present invention, when it is described that a specific device is located between a first device and a second device, there may or may not be an intermediate device between the specific device and the first device or the second device. When it is described that a specific device is connected to other devices, the specific device may be directly connected to the other devices without an intermediate device, or may not be directly connected to the other devices but have an intermediate device.
[0037] Technologies, methods, and equipment known to ordinary technicians in the relevant art may not be discussed in detail, but where appropriate, the technologies, methods, and equipment should be considered as part of the specification.
[0038] Reference Figures 1 to 5 This embodiment provides a construction method for replacing a single offshore wind power pile with a flange, comprising the following steps:
[0039] According to the size of the single pile top and the position of the first bolt hole, a corresponding second bolt hole 2 is opened at the flange interface of the replacement flange 1, and a plurality of lifting screw holes 3 are opened at positions staggered from the second bolt hole 2;
[0040] The hoisting platform 4 is hoisted to the top of the replacement flange 1 by a crane, and falls on the center of the replacement flange 1, so that the vertical projections of the first force-bearing parts 5 of the hoisting platform 4 at least partially cover the replacement flange 1;
[0041] The construction personnel go up to the lifting platform 4, install the lifting bolts at the lifting screw holes 3, use the crane to lift the replacement flange 1 through the lifting bolts, and drive the lifting platform 4 and the construction personnel to move together;
[0042] Lift the replacement flange 1 above the top of the monopile, align the second bolt hole 2 of the replacement flange 1 with the first bolt hole on the top of the monopile, lower the replacement flange 1, and connect the replacement flange 1 and the flange on the top of the monopile with bolts;
[0043] The wire rope shackle on the lifting point bolt is removed and transferred to the lifting platform 4, and the lifting platform 4 is lifted to the deck of the ship.
[0044] In this embodiment, the flange at the top of the single pile is evenly distributed with four first bolt holes. According to the diameter of the circle surrounded by the four first bolt holes, that is, their distribution positions on the circle, four corresponding second bolt holes 2 are opened at the flange interface of the replacement flange 1. The positions of the second bolt holes 2 coincide with the first bolt holes, and lifting screw holes 3 are opened at positions staggered from the second bolt holes 2. There are also four lifting screw holes 3, and the four lifting screw holes 3 are evenly distributed on the flange interface of the replacement flange 1.
[0045] Place the replacement flange 1 on the deck of the ship, and use a crane to place the lifting platform 4 at the center of the replacement flange 1. The center of the replacement flange 1 is hollow, and the area enclosed by it is larger than the platform for manning on the lifting platform 4, but the lifting platform 4 is also provided with four first force-bearing parts 5 extending outward. The first force-bearing parts 5 can extend horizontally or at an oblique upward angle. Since the circle formed by the free ends of the four first force-bearing parts 5 is larger than the replacement flange 1, on the vertical projection plane, the first force-bearing parts 5 are equivalent to extending from the inside to the outside of the replacement flange 1, and the vertical projection of the first force-bearing parts 5 has at least a part covering the replacement flange 1.
[0046] It should be noted that when the replacement flange 1 is placed on the deck of the ship and the lifting platform 4 is placed at the center of the replacement flange 1, the replacement flange 1 is not in direct contact with the lifting platform 4. Instead, when the construction workers walk onto the lifting platform 4 and take safety measures, one end of the wire rope is connected to the lifting point bolts installed at the lifting screw holes 3, and the other end is connected to the crane. The crane is controlled to lift the replacement flange 1. The replacement flange 1 will rise and contact with the lifting platform 4, and use the force relationship between the replacement flange 1 and the first force-bearing part 5 to lift the lifting platform 4, and the construction workers move with it.
[0047] When the replacement flange 1 is hoisted above the top of the single pile, the second bolt hole 2 of the replacement flange 1 is aligned with the first bolt hole on the top of the single pile, and the replacement flange 1 is lowered, and bolts are passed through the second bolt hole 2 and the first bolt hole to achieve threaded connection.
[0048] Since both the lifting platform 4 and the replacement flange 1 have positions for installing the wire rope, the wire rope is removed from the lifting point bolt and transferred to the lifting platform 4, and the lifting platform 4 is lifted to the deck of the ship. During the whole process, the construction workers are inside the lifting platform 4, which provides good personal safety protection, and the installation is convenient and the construction efficiency is high.
[0049] As an implementation mode, according to the size of the single pile top and the position of the first bolt hole, a corresponding second bolt hole 2 is opened at the flange interface of the replacement flange 1, and a plurality of lifting screw holes 3 are opened at positions staggered from the second bolt hole 2, including:
[0050] One of the four first bolt holes on the top of the single pile is selected, and a second bolt hole 2 is opened at the corresponding position of the replacement flange 1. Then, another second bolt hole 2 is opened at the diagonal position of the second bolt hole 2 that has been opened. The two second bolt holes 2 are located on the same diameter of the replacement flange 1 that passes through the center of the circle. Then, with the two second bolt holes 2 opened as the center, a number of second bolt holes 2 are evenly distributed circumferentially on both sides of the replacement flange 1 to form a second bolt hole cluster 31 with the same number located on both sides of the diagonal line, which is equivalent to that the two second bolt hole clusters 31 are arranged on both sides of the diagonal line, symmetrically at the center, and each second bolt hole cluster 31 is an odd number of second bolt holes 2;
[0051] According to the above method, for each first bolt hole on the top of the single pile, a corresponding second bolt hole cluster 31 is opened on the replacement flange 1.
[0052] Of course, if the first bolt holes on the top of the single pile are arranged symmetrically, that is, there is at least one pair of first bolt holes located at diagonal positions, and the two second bolt hole clusters 31 corresponding to the two first bolt holes are overlapped, the above method is very suitable for the offshore environment with strong winds and severe corrosion. First, during installation, under the action of wind, the replacement flange 1 is easy to shake in the hoisting state. When there is a second bolt hole cluster 31 arranged in an arc, the second bolt hole 2 is better aligned with the first bolt hole, and no matter which second bolt hole 2 in the second bolt hole cluster 31 is aligned with one of the first bolt holes, the remaining three first bolt holes are naturally aligned. All that is left is to put down the replacement flange 1 and connect the bolts one by one. In addition, since the bolt holes and the corresponding second bolt holes 2 in the connected state are prone to corrosion and failure, when the replacement flange 1 is disassembled and reinstalled, the original second bolt holes 2 may no longer be used. At this time, only the second bolt holes 2 need to be replaced. As long as one second bolt hole 2 is replaced by translation, the other second bolt holes 2 will also be replaced to meet the use requirements.
[0053] In addition, after the first bolt hole and the second bolt hole 2 are connected, the remaining second bolt holes 2 that are not screwed will be screwed with protective rubber sleeves or glued to prevent them from direct contact with the outside air to avoid corrosion and rust. When used later, you only need to remove the protective rubber sleeves or glue.
[0054] As an implementation mode, when the hoisting platform 4 is hoisted above the replacement flange 1 and falls on the center of the replacement flange 1, it includes:
[0055] Since the second bolt hole cluster 31 and the lifting screw hole 3 are arranged in sequence on the flange interface of the replacement flange 1, a lifting screw hole 3 is arranged on both sides of the second bolt hole cluster 31, and there is a certain distance between them, the first force-bearing part 5 extending outward from the lifting platform 4 is distributed between the second bolt hole cluster 31 and the lifting screw hole 3, so that the vertical projection of the first force-bearing part 5 does not block the second bolt hole cluster 31 and the lifting screw hole 3, which is convenient for the subsequent installation of bolts and fixing of wire ropes.
[0056] Preferably, the first force-bearing portion 5 is a horizontal cantilever structure, which is erected on the replacement flange 1, and a lifting lug 6 is provided at the first force-bearing portion 5, and the lifting lug 6 is used to fix the wire rope.
[0057] As an implementation method, when the replacement flange 1 is lifted by a crane through the lifting point bolts, and the lifting platform 4 and the construction personnel are driven to move together, it includes:
[0058] Before lifting the replacement flange 1 until it contacts the lifting platform 4, open the locking structure of the first force-bearing part 5, rotate and adjust the angle of the replacement flange 1, so that the locking structures of multiple first force-bearing parts 5 all correspond to the flange interface of the replacement flange 1; after the replacement flange 1 rises and contacts the first force-bearing part 5, use the locking structure to fix the replacement flange 1 so that the lifting platform 4 will not rotate relative to the replacement flange 1; after fixation, drive the lifting platform 4 and the construction personnel to move together to ensure lifting safety.
[0059] In this embodiment, four second bolt hole clusters 31 are provided on the replacement flange 1, and a lifting screw hole 3 is provided at intervals in the counterclockwise direction of each second bolt hole cluster 31, and the connection point of the first force-bearing part 5 on the replacement flange 1 is located in the clockwise direction of the second bolt hole cluster 31. The lifting screw holes 3, the second bolt hole cluster 31 and the connection point of the first force-bearing part 5 on the replacement flange 1 arranged in sequence along the clockwise direction are selected as the description objects, and the center point of the replacement flange 1 is taken as the origin, and the connection point and the origin fixed with the locking structure and the replacement flange 1 are connected. The line connecting the connection point and the origin is the first structural line, the second bolt hole 2 at the center of the second bolt hole cluster 31 is selected, and the line connecting the second bolt hole 2 and the origin is the second structural line, and the lifting screw hole 3 and the origin are connected. The line connecting the lifting screw hole 3 and the origin is the third structural line. The third structural line, the second structural line and the first structural line are arranged in sequence along the clockwise direction, and the second structural line bisects the angle formed by the first structural line and the third structural line. The above arrangement is provided at four locations on the replacement flange 1.
[0060] Preferably, the angle formed by the first construction line and the third construction line is 45°, the angle formed by the second construction line and the third construction line is 22.5°, and each second bolt hole cluster 31 includes 11 second bolt holes 2 .
[0061] Through the above method, it can be ensured that when the lifting screw hole 3 is subjected to force, the force on the replacement flange 1 and the lifting platform 4 is relatively uniform, and when connecting the first bolt hole and the second bolt hole 2, the construction balance and scientific force can be maintained.
[0062] In addition, in addition to using the lifting platform 4 to connect the replacement flange 1 to the top of the single pile, the replacement flange 1 can also be removed from the top of the single pile:
[0063] When it is necessary to remove the replacement flange 1 from the top of the single pile, the construction personnel go to the lifting platform 4, lift the lifting platform 4 onto the replacement flange 1 by a crane, and lower the first force-bearing part 5 of the lifting platform 4 toward the position between the second bolt hole 2 and the lifting screw hole 3 of the replacement flange 1. Preferably, after lowering, the locking structure is used to fix the lifting platform 4 and the replacement flange 1.
[0064] Remove the bolts between the replacement flange 1 and the top of the single pile, remove the wire rope shackle on the lifting ear 6 of the lifting platform 4 and transfer it to the lifting point bolts of the replacement flange 1, lift the replacement flange 1 and drive the lifting platform 4 and the construction personnel to move to the deck of the ship to complete the removal of the replacement flange 1.
[0065] Compared with the prior art, the above-mentioned embodiment provides a construction method for replacing a flange on a single offshore wind power pile top. When installing the replacement flange 1, a lifting platform 4 with a manned function is lifted above the replacement flange 1. When the replacement flange 1 is lifted, the lifting platform 4 and the construction personnel are driven to move together and fall on the top of the single pile together. The construction personnel are well protected in terms of personal safety on the lifting platform 4. The lifting platform 4 provides a good and safe construction platform, and the wire rope lifting connection between the replacement flange 1 and the lifting platform 4 can be flexibly converted, so that the replacement flange 1 or the lifting platform 4 can be lifted by a crane, thereby improving construction efficiency.
[0066] The technical features of the above embodiments may be combined arbitrarily. To make the description concise, not all possible combinations of the technical features in the above embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.
[0067] The above embodiments only express several implementation methods of the present invention, and the descriptions thereof are relatively specific and detailed, but they cannot be understood as limiting the scope of the invention patent. It should be pointed out that, for those of ordinary skill in the art, several variations and improvements can be made without departing from the concept of the present invention, and these all belong to the protection scope of the present invention. Therefore, the protection scope of the patent of the present invention shall be subject to the attached claims.
Claims
1. A construction method for replacing flanges on offshore wind power single piles. It is characterized in that The following steps are involved: According to the size of the single pile top and the position of the first bolt hole, a corresponding second bolt hole is opened at the flange interface of the replacement flange, and a plurality of lifting screw holes are opened at positions staggered from the second bolt hole; Using a crane to hoist a hoisting platform above the replacement flange and drop it at the center of the replacement flange, so that at least a part of the vertical projections of the first force-bearing parts of the hoisting platform cover the replacement flange; The construction personnel go up to the hoisting platform, install the lifting bolts at the lifting screw holes, use the crane to lift the replacement flange through the lifting bolts, and drive the hoisting platform and the construction personnel to move together; The replacement flange is hoisted above the top of the single pile, the second bolt hole of the replacement flange is aligned with the first bolt hole of the top of the single pile, and the replacement flange is lowered, and the replacement flange and the flange at the top of the single pile are connected by bolts; Remove the wire rope shackle on the lifting point bolt and transfer it to the lifting platform, and lift the lifting platform to the deck of the ship.
2. A construction method for replacing flanges with a single offshore wind power pile as claimed in claim 1, It is characterized in that When a corresponding second bolt hole is opened at the flange interface of the replacement flange according to the size of the single pile top and the opening position of the first bolt hole, and a plurality of lifting screw holes are opened at positions staggered from the second bolt hole, the method includes: Select one of the first bolt holes on the top of the single pile, open a second bolt hole at the corresponding position of the replacement flange, select a position on the replacement flange diagonally opposite to the second bolt hole, open another second bolt hole, and then evenly distribute a plurality of second bolt holes circumferentially on both sides of the replacement flange with the two opened second bolt holes as the center, so as to form a cluster of second bolt holes with the same number located on both sides of the diagonal line; According to the above method, for each of the first bolt holes on the top of the single pile, a corresponding cluster of second bolt holes is opened on the replacement flange.
3. A construction method for replacing flanges with a single offshore wind power pile as claimed in claim 2, It is characterized in that When the lifting platform is lifted above the replacement flange and falls on the center of the replacement flange, it includes: The first stress-bearing portion extending outward from the lifting platform is distributed between the second bolt hole cluster and the lifting screw hole so that the vertical projection of the first stress-bearing portion does not block the second bolt hole cluster and the lifting screw hole. The first stress-bearing portion is a horizontal cantilever structure, and a lifting ear is arranged at the first stress-bearing portion.
4. A construction method for replacing flanges with a single offshore wind power pile as claimed in claim 3, It is characterized in that When the replacement flange is lifted by the crane through the lifting point bolts and the lifting platform and the construction personnel are driven to move together, the method includes: Before lifting the replacement flange until it contacts the lifting platform, open the locking structure of the first force-bearing part, rotate and adjust the angle of the replacement flange so that the locking structures of multiple first force-bearing parts all correspond to the flange interface of the replacement flange, and use the locking structure to fix the replacement flange. After fixation, drive the lifting platform and construction personnel to move together.
5. A construction method for replacing flanges with a single offshore wind power pile as claimed in claim 4, It is characterized in that Taking the center point of the replacement flange as the origin, the line connecting the connection point where the locking structure and the replacement flange are fixed and the origin is the first construction line, the second bolt hole at the center of the second bolt hole cluster closest to the connection point is selected, and the line connecting the second bolt hole and the origin is the second construction line, the nearest lifting screw hole located on the other side of the second bolt hole cluster opposite to the connection point is selected, and the line connecting the lifting screw hole and the origin is the third construction line, and the second construction line bisects the angle formed by the first construction line and the third construction line.
6. A construction method for replacing flanges with a single offshore wind power pile as claimed in claim 5, It is characterized in that The angle formed by the first construction line and the third construction line is 45°, and the angle formed by the second construction line and the third construction line is 22.5°.
7. A construction method for replacing flanges with a single offshore wind power pile as claimed in claim 6, It is characterized in that Each of the second bolt hole clusters includes 11 second bolt holes.
8. A construction method for replacing flanges with a single offshore wind power pile as claimed in any one of claims 1 to 7, It is characterized in that Also includes: When it is necessary to remove the replacement flange from the top of the single pile, the construction personnel go to the lifting platform, lift the lifting platform onto the replacement flange by the crane, and lower the first force-bearing part of the lifting platform toward the position between the second bolt hole of the replacement flange and the lifting screw hole; Remove the bolts between the replacement flange and the top of the single pile, remove the wire rope shackle on the lifting platform and transfer it to the lifting point bolts of the replacement flange, lift the replacement flange and move the lifting platform and construction personnel to the deck of the ship.
Citation Information
Patent Citations
Construction technology of non-rock-socked single pile for offshore wind power foundation
CN108842806A
Pile clamping platform for single pile rock-socketing and implementation mode of pile clamping platform
CN110130392A
Offshore wind power single pile foundation construction method and special ship
CN114319356A
Connecting fitting for replacing and hitting device
CN215105328U
Negative-pressure barrel type single pile gripper construction mechanism and construction method thereof
WO2021052174A1