A construction method for a floating dock overpass
By simulating the closed state of the overpass and the side-state grouping method, the problem of large high-altitude operations and low precision in the construction of the floating dock overpass was solved, high-precision construction and closing of the overpass was achieved, and the difficulty of safety and precision control of the construction was reduced.
Patent Information
- Application Number
- CN202211543697.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-11-29
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2042-11-29
AI Technical Summary
The existing construction methods of floating dock overpasses have problems such as large amounts of high-altitude operations and difficulty in controlling precision, which leads to increased construction difficulty and safety risks.
By simulating the closed state of the overpass, the structural margin of the closing opening of the support structure is trimmed, and the upper support structure, lower support structure and slewing mechanism of the overpass main body are installed on the assembly site. The assembly is carried out using the side assembly method, accurately positioned and Welding, reducing the amount of high-altitude work and improving accuracy.
The high-precision construction and closing of the floating dock overpass has been achieved, reducing the workload of high-altitude construction work and significantly reducing the difficulty of construction safety and precision control.
Smart Images

Figure CN115783180B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of shipbuilding, and in particular to a construction method of a floating dock flyover. Background Art
[0002] The floating dock bridge is a truss steel structure connecting the left and right dock walls. The steel structure and the main hull of the floating dock are fixed by the upper and lower supporting structures. The bridge can rotate a certain angle driven by the slewing mechanism. The bridge usually consists of two parts, left and right, which are fixed on the left and right dock walls respectively. The two parts can be opened and closed by the slewing mechanism. When the bridge is closed, the top decks of the left and right dock walls of the floating dock can be connected, so that people can pass freely on the top decks of the left and right dock walls.
[0003] At present, the floating dock bridge usually completes the prefabrication of the steel structure in sections on site, and then hoists and closes them separately after the prefabrication. When the bridge is closed, it is assembled and welded with the supporting structure, rotating mechanism and other mechanical equipment of the bridge, and the final commissioning is completed. The above production and installation methods have the following problems: 1. The base surface of the onboard closing operation is high, which increases the difficulty of construction and the closing accuracy of the bridge is difficult to control; 2. The large number of high-altitude construction operations also increases the difficulty of safety control of construction. Summary of the invention
[0004] The purpose of the present invention is to provide a construction method for a floating dock overpass, which can effectively control the construction and closing accuracy of the overpass, and has relatively less high-altitude construction operations, greatly reducing the difficulty of controlling construction safety and accuracy.
[0005] In order to achieve the above object, the technical solution of the present invention is:
[0006] A construction method for a floating dock overpass includes a method for making the floating dock overpass and a method for installing the floating dock overpass; the method for making the floating dock overpass includes the following steps: S1: making the overpass body; S2: simulating the closed state of the overpass, trimming the closing mouth structure margin of the upper supporting structure and the lower supporting structure; S3: installing the upper supporting structure, the lower supporting structure and the slewing mechanism of the overpass body on the general assembly site; the method for installing the floating dock overpass includes the following steps: T1: surveying and marking the closing ground sample line of the overpass in the large dock, T2: accurately positioning according to the closing ground sample line of the overpass, assembling the floating dock overpass on the floating dock and welding it.
[0007] Among them, the method for making the main body of the overpass in S1 includes the following steps: Q1: assembly and division of the overpass, dividing the main structure of the overpass into a platform body, vertical support, oblique support and combined support assembly; the platform body includes a head platform assembly and a tail platform assembly; Q2: assembly and production, respectively producing the platform body, vertical support, oblique support and combined support assembly divided in Q1; Q3: surveying and marking the sample line of the overpass main assembly site on the general assembly site; Q4: completing the general assembly operation of the overpass main body according to the sample line of the overpass main assembly surveyed in Q3.
[0008] Wherein, the platform break between the front platform assembly and the rear platform assembly is arranged at the position where the thickness of the platform plate changes and the position where the platform main board is butted.
[0009] Among them, the fractures of the vertical support and the oblique support are divided based on the length of the round tube with the maximum processing capacity, avoiding the complex structural area, and the assembly and welding areas between the vertical support, the oblique support and the platform body are divided into the same group.
[0010] Among them, the vertical support and the oblique support in Q2 are formed by welding cylinders, and angle steel fixtures are respectively installed at the upper and lower ends of each section of the cylinder, and the center position of the cylinder is marked on the angle steel fixture.
[0011] Among them, the ground sample lines of the main assembly of the overpass mentioned in Q3 include: the ground line of the center line of the vertical support tube, the ground line of the center line of the inclined support tube, the theoretical ground line of the overpass top plate, the ground line of the center axis of the slewing mechanism and the calibration line.
[0012] Among them, the general assembly operation of the Q4 overpass adopts side-by-side general assembly on the general assembly site.
[0013] Among them, in T2, a skybridge closing guide plate is installed on the wall of the floating dock that is about to be welded.
[0014] Among them, the sample line for the closure of the overpass in T1 is surveyed based on the actual position of the center line of the floating dock hull and the first sealing plate of the dock wall.
[0015] Among them, the floating dock bridge and the floating dock in T2 are welded by means of a horse plate. After installation, the horse plate remains on the floating dock bridge and the floating dock.
[0016] After adopting the above technical solution, the beneficial effects of the present invention are:
[0017] The invention discloses a construction method of a floating dock overpass, including a method for making a floating dock overpass and a method for installing the floating dock overpass; the method for making the floating dock overpass includes the following steps: S1: making the overpass body; S2: simulating the closed state of the overpass, trimming and cutting the closing structure margin of the upper supporting structure and the lower supporting structure; S3: installing the upper supporting structure, the lower supporting structure and the slewing mechanism of the overpass body on the general assembly site; the installation method of the floating dock overpass includes the following steps: T1: surveying and marking the closing ground sample line of the overpass in the dock, T2: accurately positioning according to the closing ground sample line of the overpass, assembling the floating dock overpass on the floating dock and welding. The invention simulates the closed state of the overpass, thereby realizing underground cutting, reducing the amount of high-altitude operations, preventing accidents in long-term high-altitude operations, and improving work efficiency at the same time; by reasonably setting the assembly sequence and welding method of the overpass body, the welding deformation of the overpass body is reduced, and the manufacturing accuracy of the overpass body is ensured.
[0018] The method for making the main body of the overpass in S1 includes the following steps: Q1: the overpass assembly is divided, and the main structure of the overpass is divided into a platform body, a vertical support, an inclined support and a combined support assembly; the platform body includes a head platform assembly and a tail platform assembly; Q2: assembly and production, and the platform body, vertical support, inclined support and combined support assembly divided in Q1 are produced separately; Q3: surveying and marking the ground sample line of the overpass main assembly on the general assembly site; Q4: completing the general assembly of the overpass main body according to the ground sample line of the overpass main assembly surveyed in Q3. By dividing the main structure of the overpass into multiple assemblies and independently constructing and transporting the multiple assemblies, the problems of long overall construction period of the overpass structure, large segment size, difficult transportation construction, and difficult to control installation accuracy at high places are solved; by surveying and marking the ground sample line of the overpass main assembly, a basis is provided for the later closing to ensure the closing accuracy.
[0019] By setting the platform break between the front platform assembly and the rear platform assembly at the position where the platform plate thickness changes and the position where the platform main plate is docked, the process can be moved forward to the maximum extent and the construction difficulty and workload of the overpass assembly can be reduced.
[0020] The length of the round tube with the maximum processing capacity is used as the basis for division through the gaps of the vertical supports and the oblique supports to avoid the complex structural areas. The assembly and welding areas between the vertical supports, the oblique supports and the platform body are divided into the same group. By optimizing the division of the overpass assembly, the more complex assembly and welding operations in the overpass body can be completed in advance in the assembly stage.
[0021] By setting up the angle steel fixture and marking the center position of the cylinder on the angle steel fixture, a basis is provided for subsequent positioning.
[0022] The general assembly operation of the overpass adopts side-state general assembly on the general assembly site. By adopting side-state general assembly, it facilitates the general assembly construction of the main body of the overpass while providing a good construction base surface for the pre-installation of the upper and lower supporting structures in advance, ensuring the pre-installation accuracy.
[0023] The floating dock overpass and the floating dock are welded by means of horse plates. After installation, the horse plates are retained on the floating dock overpass and the floating dock. The horse plates are sealed to ensure the closing accuracy of the overpass mechanism. At the same time, the horse plates are retained, thereby reducing the workload of removing the horse plates.
[0024] In summary, the construction method of a floating dock overpass of the present invention solves the technical problems in the prior art that the production and installation of floating dock overpasses have a large amount of high-altitude operations and low precision. The floating dock overpass produced by the construction method of the present invention has high production and installation precision, and relatively less high-altitude construction operations, which greatly reduces the difficulty of safety control and precision control of construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 It is a schematic diagram of the main part of the overpass and the division of the overpass assembly;
[0026] Figure 2 It is a schematic diagram of a cylindrical structure with vertical support and oblique support;
[0027] Figure 3 yes Figure 2 Schematic diagram of the B-direction structure;
[0028] Figure 4 yes Figure 3 A partial enlarged view of middle A;
[0029] Figure 5 It is a structural schematic diagram of a combined support assembly;
[0030] Figure 6 It is a survey and planning diagram of the skybridge assembly site sample line;
[0031] Figure 7 This is the general group operation diagram of the main body of the overpass;
[0032] Figure 8 It is a schematic diagram of the installation structure of the upper supporting structure, the lower supporting structure and the slewing mechanism;
[0033] Fig. 9 It is a schematic diagram of the installation structure of the lower support structure;
[0034] Fig.10 It is a schematic diagram of the installation structure of the upper support structure and the slewing mechanism;
[0035] Fig.11 It is a schematic diagram of the surplus trimming of the upper supporting structure and the lower supporting structure;
[0036] Fig.12 1. It is a schematic diagram of the guide plate installation structure;
[0037] Fig.13 This is a schematic diagram of the survey and demarcation of the ground line of the overpass closure;
[0038] Fig.14 It is a schematic diagram of the installation structure of the floating dock bridge;
[0039] Fig.15 This is a schematic diagram of the installation accuracy of the floating dock bridge detected by the total station;
[0040] In the figure: 1. Platform body, 11. Forward platform assembly, 12. Rear platform assembly, 2. Vertical support, 21. Steel plate, 22. Angle steel, 221. First right angle piece, 222. Second right angle piece, 223. Center of circle, 23. Upper support structure, 24. Lower support structure, 3. Oblique support, 4. Combined support assembly, 41. First support tube, 42. Second support tube, 51. Support tube center ground wire, 52. Standard pallet, 61. Vertical Toward support tube centerline ground line, 62, oblique support tube centerline ground line, 63, skybridge top plate theoretical ground line, 64, slewing mechanism center axis ground line, 65, calibration line, 7, support tooling, 8, slewing mechanism, 9, guide plate, 92, skybridge closure ground line, 921, bow platform assembly rotation axis, 922, tail platform assembly rotation axis, 923, skybridge length positioning reference line, 924, dock wall theoretical line, 925, floating dock centerline. DETAILED DESCRIPTION
[0041] The present invention is further described below in conjunction with the accompanying drawings and embodiments.
[0042] The directions mentioned in this specification are based on the directions shown in the drawings and only represent relative positions, not absolute positions.
[0043] A construction method for a floating dock overpass includes a manufacturing method for the floating dock overpass and an installation method for the floating dock overpass.
[0044] 1. The method for making a floating dock overpass comprises the following steps:
[0045] S1: Production of the main body of the overpass.
[0046] The method for making the main body of the overpass comprises the following steps:
[0047] Q1: Division of overpass assembly.
[0048] like Figure 1As shown, according to the structural characteristics of the overpass body, the overpass body structure is divided into a platform body 1, a vertical support 2, an oblique support 3 and a combined support assembly 4. The platform body 1 includes a head platform assembly 11 and a tail platform assembly 12. The oblique support 3 is processed in two sections; the combined support assembly 4 includes a first support tube 41 and a second support tube 42 set at a certain angle.
[0049] The division of the overpass assembly facilitates assembly, transportation and painting operations; reduces the difficulty of segmented assembly of the overpass, reduces the workload of segmented assembly, and takes the principle of moving the process forward. The platform body 1 of the overpass is divided into two parts: the head platform assembly 11 and the tail platform assembly 12, which reduces the length dimension of the assembly and facilitates the transportation and painting operations of the entire assembly. The platform break between the head platform assembly 11 and the tail platform assembly 12 is set at the position where the thickness of the platform plate changes and the position where the platform main board is connected. The platform break is selected at the position where the thickness of the platform plate changes to reduce the number of panels during assembly; the platform break is also set in the area where only the platform main board is connected, avoiding the area where the complex structure needs to be welded.
[0050] The fractures of the vertical support 2 and the oblique support 3 are divided based on the length of the cylinder with the maximum processing capacity, avoiding the complex structural area. At the same time, the assembly and welding areas between the vertical support 2, the oblique support 3 and the platform body 1 are divided into the same group.
[0051] The above-mentioned assembly division realizes the maximum advancement of process steps and reduces the construction difficulty and workload of subsequent overpass assembly.
[0052] Q2: Assembly production.
[0053] The platform body 1, vertical support 2, oblique support 3 and combined support assembly 4 divided by Q1 are manufactured.
[0054] The production of the platform body 1 is divided into the production of the head platform assembly 11 and the tail platform assembly 12. The head platform assembly 11 and the tail platform assembly 12 are produced separately, and the production methods are the same, so no distinction is made below.
[0055] The platform body 1 is manufactured by the positive manufacturing method. The surrounding plates of the platform body 1 are cut and welded with flat iron ribs, etc. When the platform body 1 is manufactured, the platform bottom plate is first assembled into the upper part and sealed firmly with the tire frame; then the ribs and side plates are installed in sequence. When the ribs and side plates are installed, anti-falling supports are set to ensure construction safety. Small flat irons are installed above the ribs in advance to facilitate welding with the top plate later; after the above assembly is completed, the internal welding of the platform body 1 is completed first, and then the top plate is buckled. The top plate is provided with plug welding holes at the position aligned with the internal ribs, and the welding of the plug welding holes is completed. The corners of the top plate and the side plates are welded to form a complete platform body 1. After the platform body 1 is manufactured, it is separated from the tire frame into a free state, and then pyrotechnic correction is performed to make its accuracy meet the requirements.
[0056] like Figure 2 , Figure 3 and Figure 4 As shown together, the vertical support 2 and the oblique support 3 are welded by a cylinder, and the cylinder is formed into a circle by cold bending of a steel plate 21, and the longitudinal seam of the welded cylinder is formed into a cylinder. When the steel plate 21 is cut, a pressure margin of about 50 mm is reserved for the longitudinal seam of the cylinder, and an assembly adjustment margin of 10 mm is reserved at both ends of the cylinder. An angle steel fixture is respectively installed at the upper and lower ends of each section of the cylinder, and the position of the center of the cylinder 223 is marked on the angle steel fixture with a sample gun point to provide a positioning reference for the subsequent overpass assembly. The angle steel fixture includes an angle steel 22, and the two ends of the angle steel 22 are fixed to the side wall of the cylinder by positioning welding. The angle steel 22 includes a first right-angle piece 221 and a second right-angle piece 222 arranged perpendicularly to each other, and the intersection of the first right-angle piece 221 and the second right-angle piece 222 is perpendicular to the axis of the cylinder, and the top plane of the first right-angle piece 221 passes through the central axis of the cylinder. The angle steels 22 at the upper and lower ends of each section of the cylinder are arranged relatively. Mark the center of circle 223 with a sample gun as required on the first right angle piece 221. For the convenience of processing and transportation, the oblique support 3 is processed in two sections.
[0057] like Figure 5 As shown, the combined support assembly 4 includes a first support tube 41 and a second support tube 42 set at a certain angle. Before assembling the combined support assembly 4, a support tube center ground line 51 is marked in advance on the assembly production site to assist in determining the assembly angle of the first support tube 41 and the second support tube 42 of the combined support assembly 4. The production of the first support tube 41 and the second support tube 42 is consistent with the production of the vertical support 2 and the oblique support 3. When manufacturing the combined support assembly 4, the first support tube 41 and the second support tube 42 are first assembled and then welded. During assembly, the first support tube 41 and the second support tube 42 are aligned with the marked support tube center ground line 51 based on the center 223 of the angle steel fixture at the end of the cylinder to ensure the installation angle of the vertical and oblique support tubes. A standard card plate 52 is set on the inner part where the first support tube 41 and the second support tube 42 intersect to assist in positioning the installation angle of the first support tube 41 and the second support tube 42.
[0058] Q3: Survey and mark the sample line of the main assembly site of the overpass.
[0059] like Figure 6 As shown in the figure, the main assembly ground sample lines used by the general assembly of the overpass are surveyed and drawn with a total station on the general assembly site. The main assembly ground sample lines of the overpass include: the ground line 61 of the center line of the vertical support pipe, the ground line 62 of the center line of the oblique support pipe, the theoretical ground line 63 of the overpass top plate, the ground line 64 of the center axis of the slewing mechanism and the calibration line 65.
[0060] Q4: Complete the general assembly work of the main body of the overpass according to the sample line of the main body assembly of the overpass surveyed in Q3.
[0061] like Figure 7 As shown, the general assembly of the overpass adopts the side assembly on the general assembly site. Before the general assembly, various types of support tooling 7 suitable for the platform body 1, vertical support 2, oblique support 3 and combined support assembly 4 are placed in advance according to the division of the overpass assembly. During the general assembly process, the largest platform body 1 is first positioned on the tire, and the positioning accuracy of the platform body 1 is determined by aligning the theoretical ground line 63 of the overpass top plate with the vertical support tube centerline ground line 61 and the oblique support tube centerline ground line 62. After the platform body 1 is accurately positioned, a rigid tire seal is set to ensure that the safety and accuracy of the vertical support 2 and the oblique support 3 meet the relevant requirements. When the oblique support 3 and the vertical support 2 participate in the general assembly, anti-roll tooling is set to ensure the safety of the support tube general assembly.
[0062] After all components of the general assembly of the overpass are assembled, they are welded as a whole. The front platform assembly 11 and the rear platform assembly 12 are welded to form the platform body 1. One end of the vertical support 2 is welded to the rear platform assembly 12, and the other end is welded to the first support tube 41. The two sections of the oblique support 3 are welded to each other and the top is welded to the front platform assembly 11, and the bottom is welded to the second support tube 42. After welding is completed, the accuracy of the overpass body is measured, and the measurement is carried out through the calibration line 65. The part that exceeds the standard is corrected by pyrotechnics. After all accuracy indicators meet the requirements, subsequent operations are carried out.
[0063] S2: Simulate the closed state of the overpass and trim the structural margins of the upper supporting structure 23 and the lower supporting structure 24.
[0064] like Fig.11 As shown, the accuracy of the two port and starboard bridges when they are docked and closed is measured in advance using a total station, and combined with the actual closing data of the dock wall, the accuracy of the bridge is simulated and analyzed, and the closing margins of the upper supporting structure 23, the lower supporting structure 24 and the bridge body are trimmed in advance.
[0065] S3: Install the upper support structure 23, the lower support structure 24 and the slewing mechanism 8 on the assembly site.
[0066] like Figure 8 , Fig. 9 and Fig.10 As shown together, the upper support structure 23, the lower support structure 24 and the slewing mechanism 8 are pre-assembled with the main body of the skybridge on the site. During pre-assembly, the angular position relationship between the upper support structure 23, the lower support structure 24 and the skybridge is consistent, that is, the simulated skybridge has been docked and closed with the main hull of the floating dock, and the skybridge is in the horizontal direction toward the bow along the centerline of the hull.
[0067] The upper support structure 23, the lower support structure 24 and the slewing mechanism 8 are made of standard parts, and the manufacturing process is not described in detail. When the upper support structure 23, the lower support structure 24 and the slewing mechanism 8 are pre-installed on the site with the main body of the overpass, it should be ensured that the axis of the upper support structure 23 and the lower support structure 24 are on the same straight line, that is, all points of the axis should fall on the ground line 64 of the central axis of the slewing mechanism surveyed by S1, and the pre-installation accuracy is determined by the auxiliary measurement of the total station, and the error shall not exceed 1mm. After the pre-installation is completed, the rotation axis of the upper support structure 23 and the lower support structure 24 should be marked with a light target at a conspicuous and convenient position for measurement in the dock, so as to facilitate the positioning and measurement when the overpass is closed. At the same time, a disposable light target is attached to the bottom plate of the main body of the overpass, and one is set every 10m or so from the rotation axis of the overpass as the reference, so as to facilitate the measurement and positioning of the overpass when it is closed.
[0068] After the upper supporting structure 23, the lower supporting structure 24 and the slewing mechanism 8 are pre-assembled with the overpass body on site and the accuracy meets the requirements, the upper supporting structure 23, the lower supporting structure 24 and the slewing mechanism 8 are temporarily sealed and fixed to the overpass body with channel steel or angle steel.
[0069] 2. The installation method of the floating dock bridge includes the following steps:
[0070] T1: Survey and mark the ground sample line for overpass closure in the dock.
[0071] T2: According to the precise positioning of the bridge closure ground sample line, the floating dock bridge is assembled to the floating dock and welded.
[0072] like Fig.11 , Fig.12 , Fig.13 , Fig.14 and Fig.15 As shown in the figure, before the overpass is put into the dock and closed as a whole, the main body of the floating dock wall welded to the overpass should be welded. Measure the structural closing deviation of the floating dock relative to the upper supporting structure 23 and the lower supporting structure 24 of the overpass, and install the overpass closing guide plate 9 on the floating dock wall where the upper supporting structure 23 and the lower supporting structure 24 of the overpass are about to be welded in advance. This guide plate 9 is used to assist the overpass in closing and quickly positioning, and also serves as a sealing tool after the overpass is accurately positioned.
[0073] The bridge closure ground line 92 is surveyed and marked in advance in the bridge closure dock, and high-type supporting tools are placed. The bridge closure ground line 92 mainly includes the head platform assembly rotation axis 921, the tail platform assembly rotation axis 922, the bridge length positioning reference line 923, the dock wall theoretical line 924, and the floating dock center line 925. The ground line survey should be conducted based on the actual position of the floating dock center line 925 and the dock wall first sealing plate to ensure the bridge closure accuracy.
[0074] The main structure of the overpass is hoisted with the upper support structure 23, the lower support structure 24 and the slewing mechanism 8 as a whole, and then put into the dock for closure. The axis mark light targets of the upper support structure 23 and the lower support structure 24 of the overpass are measured and aligned with the axis ground line of the large dock to determine the precise positioning size of the overpass. At the same time, the alignment between the half-width theoretical line of the overpass platform and the center line 925 of the floating dock is measured to determine the closing positioning accuracy of the main body of the overpass platform, and the positioning size of the overpass is checked by measuring the length direction of the overpass.
[0075] After the bridge is positioned, the bridge and the floating dock body are sealed and welded using precisely cut slats at the top deck of the bridge body and the upper support structure 23 and lower support structure 24. The sealed slats can be permanently retained, reducing the workload of slat removal. After the bridge is sealed, other bridge-related equipment and outfitting parts are installed, and the opening and closing commissioning of the bridge is finally completed.
[0076] The construction method of a floating dock overpass of the present invention solves the technical problems in the prior art that the production of the overpass body and the installation of the floating dock overpass require a large amount of high-altitude work and low precision. The floating dock overpass produced by the construction method of the present invention has high production and closing precision, and relatively less high-altitude construction work, which greatly reduces the difficulty of safety control in construction.
[0077] The present invention is not limited to the above-mentioned specific implementation modes. Various changes made by ordinary technicians in this field based on the above-mentioned concepts without creative work are all within the protection scope of the present invention.
Claims
1. A construction method for a floating dock bridge, characterized in that: It includes a method for making a floating dock overpass and a method for installing a floating dock overpass; The manufacturing method of the floating dock overpass comprises the following steps: S1: Production of the main body of the overpass; The method for making the main body of the overpass comprises the following steps: Q1: The overpass assembly is divided into the main structure of the overpass into the platform body, vertical support, oblique support and combined support assembly; The combined support assembly includes a first support tube and a second support tube arranged at a certain angle, and the platform body includes a head platform assembly and a tail platform assembly; Q2: Assembly and production, the platform body, vertical support, oblique support and combined support divided in Q1 are assembled and produced separately; Q3: Survey and mark the sample line of the main assembly site of the overpass; Q4: Complete the assembly work of the main body of the overpass according to the sample line of the main body of the overpass surveyed in Q3; The bow platform assembly and the tail platform assembly are welded to form the platform body, one end of the vertical support is welded to the tail platform assembly, and the other end is welded to the first support tube, the two sections of the oblique support are welded to each other, the top is welded to the bow platform assembly, and the bottom is welded to the second support tube; S2: simulate the closed state of the overpass and trim the closing structure margin of the upper and lower supporting structures; S3: Install the upper supporting structure, lower supporting structure and slewing mechanism of the main body of the overpass on the assembly site; The installation method of the floating dock bridge comprises the following steps: T1: Survey and draw the ground sample line for the bridge closure in the dock. T2: According to the precise positioning of the bridge closure ground sample line, the floating dock bridge is assembled to the floating dock and welded.
2. The construction method of a floating dock bridge according to claim 1, characterized in that: The platform break between the front platform assembly and the rear platform assembly is arranged at the position where the thickness of the platform plate changes and at the position where the platform main plate butts against each other.
3. The construction method of a floating dock bridge according to claim 1, characterized in that: The fractures of the vertical supports and the oblique supports are divided based on the length of the round tube with the maximum processing capacity, avoiding the complex structural areas, and the assembly and welding areas between the vertical supports, the oblique supports and the platform body are divided into the same group.
4. The construction method of a floating dock bridge according to claim 1, characterized in that: The vertical support and the oblique support in Q2 are welded by cylinders, and angle steel fixtures are respectively installed at the upper and lower ends of each section of the cylinder, and the center position of the cylinder is marked on the angle steel fixture.
5. The construction method of a floating dock bridge according to claim 1, characterized in that: The ground sample lines for the main assembly of the overpass described in Q3 include: the ground line of the center line of the vertical support tube, the ground line of the center line of the inclined support tube, the theoretical ground line of the overpass top plate, the ground line of the center axis of the slewing mechanism and the calibration line.
6. The construction method of a floating dock bridge according to claim 1, characterized in that: The general assembly operation of the Q4 overpass adopts side-by-side general assembly on the general assembly site.
7. The construction method of a floating dock bridge according to claim 1, characterized in that: In T2, the overpass closing guide plate is installed on the floating dock wall to be welded.
8. The construction method of a floating dock bridge according to claim 1, characterized in that: The sample line for the closure of the overpass in T1 is surveyed based on the actual position of the center line of the floating dock hull and the first sealing plate of the dock wall.
9. The construction method of a floating dock bridge according to claim 1, characterized in that: In T2, the floating dock overpass and the floating dock are welded by means of a horse plate. After installation, the horse plate remains on the floating dock overpass and the floating dock.