Multi-parameter-based bed drilling trajectory control system and method
Through a multi-parameter horizontal drilling trajectory control system, using technologies such as drilling radar and gamma detectors, the drilling trajectory is adjusted in real time, which solves the problem of imprecise drilling trajectory control in traditional technology, and realizes drilling trajectory in coal mines. The precise control and real-time update of geological models improve the accuracy and efficiency of drilling.
Patent Information
- Application Number
- CN202211409527.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-11-11
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2042-11-11
AI Technical Summary
Traditional geological guide drilling technology is difficult to ensure the precise control of the drilling trajectory in the coal seam interface in the coal seam. Especially when the thickness of the coal seam roof plate is large and the physical properties are small, it is impossible to effectively control the drilling within 2m of the coal seam interface. The advancement.
Adopt a horizontal drilling trajectory control system based on multi-parameters, including a drilling-as-as-drilling tube, a hole depth recording device, an orifice monitor and a cloud computing platform, using drilling radar, gamma detector, and drilling trajectory measurement module The and azimuth gamma measurement control module performs data processing and inversion through the cloud computing platform, and adjusts the drilling trajectory in real time to ensure the precise control of the distance between the drilling hole and the interface within the range of 0.5m to 10m.
Accurate control of drilling trajectory in coal mines, can detect the interface position of geological anomalies around the drilling hole and the target layer, with a resolution of 0.15m~0.3m, supports rapid directional drilling, and improves the accuracy and efficiency of drilling. .
Smart Images

Figure CN115898369B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of geo-steering drilling, and in particular to a multi-parameter-based layer-by-layer drilling trajectory control system and method. Background Art
[0002] With the development of intelligent coal mining, the gas control and water hazard control of coal mines have developed from qualitative to quantitative, and the need for advanced detection of mining working faces has put forward the detection requirements of high detection accuracy and long detection distance for geophysical exploration. At present, in order to ensure the safe mining of coal mines, in order to prevent water accidents and gas disasters in coal mines, many through-layer water exploration and gas extraction holes need to be drilled on the working face. In order to make the boreholes drilled along the set trajectory, directional drilling technology has been developed. However, directional drilling technology can only guarantee drilling along the set trajectory. When designing the drilling trajectory in the early stage, it is designed according to the early exploration data. Some small changes in the strata and the early exploration of small structures cannot be reflected. Therefore, directional drilling technology cannot be used for real-time advanced detection, update geological models, and adjust the design trajectory and drilling trajectory.
[0003] Geo-steering drilling (well drilling) technology is a drilling (hole drilling) technology that uses the real-time geological information and directional data of the downhole (in the borehole) provided by the drilling instrument to identify the geological environment of the drilled stratum and predict the underground conditions to be drilled, guide the drill bit into the target layer and ensure that the drilling trajectory extends along the target layer. It is a comprehensive technology of geological information, drilling instrument response and guiding the drill bit into the target layer and within the target layer, and provides data for updating the geological model of the entire area based on the information of drilling detection. Traditional geo-guided drilling (wells) use natural gamma, resistivity and other logging while drilling instruments to measure the physical property differences of the strata to ensure that the drill bit drills into the target layer. However, when the target layer is thick, it cannot ensure that the drill bit advances within a certain range from the interface. For example, in coalbed methane ground horizontal wells, in order to ensure the effect of gas extraction in broken soft coal seams, horizontal wells are arranged along the development direction of the coal seam on the coal seam roof. The horizontal wells are required to be within 2m of the coal seam. Due to the large thickness of the roof and the small physical property differences of the rock strata in the roof, the traditional logging technology geo-guided drilling cannot control the drilling within 2m from the coal seam interface. Summary of the invention
[0004] In order to overcome at least one shortcoming in the prior art, an embodiment of the present application provides a device and method for controlling a layer drilling trajectory based on multiple parameters.
[0005] In a first aspect, a multi-parameter-based horizontal drilling trajectory control system is provided, comprising: a borehole measurement while drilling probe, a borehole depth recording device, a borehole mouth monitor and a cloud computing platform, wherein the borehole measurement while drilling probe and the borehole depth recording device are both connected to the borehole mouth monitor, and the borehole mouth monitor is connected to the cloud computing platform;
[0006] The in-hole measurement while drilling probe includes a borehole radar instrument, multiple gamma detectors, a while drilling trajectory measurement module and an azimuth gamma measurement control module;
[0007] The borehole radar instrument is used to obtain the borehole radar data of each measuring point and send it to the borehole monitor;
[0008] Multiple gamma detectors are used to obtain the measurement value of each measuring point and send it to the azimuth gamma measurement control module;
[0009] The azimuth gamma measurement control module is used to process the gamma measurement value of each measuring point, determine the gamma measurement data of each measuring point, and send it to the orifice monitor;
[0010] The trajectory measurement while drilling module is used to obtain the trajectory measurement data of each measuring point, process the trajectory measurement data, determine the drilling trajectory data of each measuring point, and send it to the borehole monitor;
[0011] The hole depth recording device is used to obtain the depth of the borehole radar instrument at each measuring point and send it to the hole mouth monitor;
[0012] The borehole monitor is used to send the drilling trajectory data of each measuring point, the gamma measurement data of each measuring point, the borehole radar data of each measuring point and the depth of the borehole radar instrument of each measuring point to the cloud computing platform;
[0013] The cloud computing platform is used to determine the distance between the borehole and the interface of each measuring point based on the drilling trajectory data of each measuring point, the gamma measurement data of each measuring point, the drilling radar data of each measuring point and the depth of the drilling radar instrument at each measuring point, and send the distance between the borehole and the interface of each measuring point to the orifice monitor. The orifice monitor provides a display interface for controlling the drilling trajectory according to the distance between the borehole and the interface of each measuring point.
[0014] In one embodiment, the in-hole measurement while drilling probe further includes: a temperature and pressure parameter measurement module in the borehole and a measurement while drilling control center CPU;
[0015] The borehole temperature and pressure parameter measurement module is used to obtain the borehole temperature and pressure at each measuring point and send them to the measurement while drilling control center CPU;
[0016] The CPU of the measurement while drilling control center is used to determine whether the system is in an effective drilling state based on the temperature and pressure in the borehole at each measuring point and the trajectory measurement data of each measuring point.
[0017] In one embodiment, judging whether the system is in an effective drilling state based on the temperature and pressure in the borehole at each measuring point and the trajectory measurement data of each measuring point includes:
[0018] Calculate the average value of the trajectory measurement data of each measuring point within each window length. The trajectory measurement data includes the magnetic field components H in the x, y, and z directions. x , H y , H z and the gravitational acceleration components G in the x, y, and z directions x , G y , G z ;
[0019] Calculate the standard deviation of the trajectory measurement data of each measuring point within each window length based on the average value;
[0020] The indicator Fw for intelligent decision-making is calculated based on the standard deviation using the following formula:
[0021]
[0022] Among them, a1, a2, a3, b1, b2, b3, c1, c2 are all weight coefficients, among which b1>b2>b3>c1>c2>a1>a2>a3, are the standard deviations of the magnetic field components in the X, Y, and Z directions of the jth measuring point within the window length tw, are the standard deviations of the gravitational acceleration components in the X, Y, and Z directions of the jth measuring point within the window length tw;
[0023] According to the indicator Fw of intelligent decision-making, it is judged whether the system is in an effective drilling state. If Fw>F0, the system is judged to be in an effective drilling state, otherwise, the system is judged to be in an ineffective drilling state.
[0024] In one embodiment, the distance between the borehole and the interface of each measuring point is determined according to the borehole trajectory data of each measuring point, the gamma measurement data of each measuring point, the borehole radar data of each measuring point and the depth of the borehole radar instrument of each measuring point, including:
[0025] Determine the drilling position coordinates of each measuring point based on the drilling trajectory data and the depth of the drilling radar instrument;
[0026] Determine whether the distance between the borehole and the interface at each measuring point enters the gamma detection area based on the gamma measurement data;
[0027] If the distance between the borehole and the interface at each measuring point enters the gamma detection area, then the distance between the borehole and the interface at each measuring point in the gamma detection area is determined by using the while-drilling azimuth gamma inversion method based on the gamma measurement data and the coordinates of the borehole position at each measuring point;
[0028] If the distance between the borehole and the interface at each measuring point does not enter the gamma detection area, the distance between the borehole and the interface at each measuring point in the non-gamma detection area is determined by using a dual-parameter full waveform inversion method based on the borehole radar data and the coordinates of the borehole position at each measuring point;
[0029] Based on the distance between the borehole and the interface of each measuring point in the gamma detection area and the distance between the borehole and the interface of each measuring point in the non-gamma detection area, the final distance between the borehole and the interface of each measuring point is determined, and the final distance between the borehole and the interface of each measuring point is used for drilling trajectory control.
[0030] In one embodiment, the drilling position coordinates of each measuring point are determined according to the drilling trajectory data and the depth of the drilling radar instrument, including:
[0031]
[0032]
[0033]
[0034]
[0035] Among them, (X k , Y k , Z k ) is the drilling position coordinate of the kth measuring point, k represents the kth measuring point, k = 1 ~ K, K is the number of measuring points, (X0, Y0, Z0) is the hole mouth coordinate, MD k is the depth of the borehole radar at the kth measuring point, θ k , are the inclination and azimuth of the kth measuring point respectively.
[0036] In one embodiment, judging whether the distance between the borehole and the interface at each measuring point enters the gamma detection area according to the gamma measurement data includes:
[0037] Calculate the gamma data GR 上 And the gamma data GR 下 If ΔGR reaches the maximum difference threshold GR0, it is judged that the distance between the borehole and the interface enters the gamma detection area, otherwise it is judged that the distance between the borehole and the interface does not enter the gamma detection area.
[0038] In a second aspect, a multi-parameter-based horizontal drilling trajectory control method is provided, comprising:
[0039] Obtain borehole radar data, borehole trajectory data, gamma measurement data and borehole radar depth for each measuring point; the borehole trajectory data includes the inclination angle θ and azimuth angle of each measuring point ; Gamma measurement data includes the upper gamma data GR of each measuring point 上 And the gamma data GR 下 ;
[0040] Determine the drilling position coordinates of each measuring point based on the drilling trajectory data and the depth of the drilling radar instrument;
[0041] Determine whether the distance between the borehole and the interface at each measuring point enters the gamma detection area based on the gamma measurement data;
[0042] If the distance between the borehole and the interface at each measuring point enters the gamma detection area, then the distance between the borehole and the interface at each measuring point in the gamma detection area is determined by using the while-drilling azimuth gamma inversion method based on the gamma measurement data and the coordinates of the borehole position at each measuring point;
[0043] If the distance between the borehole and the interface at each measuring point does not enter the gamma detection area, the distance between the borehole and the interface at each measuring point in the non-gamma detection area is determined by using a dual-parameter full waveform inversion method based on the borehole radar data and the coordinates of the borehole position at each measuring point;
[0044] Based on the distance between the borehole and the interface of each measuring point in the gamma detection area and the distance between the borehole and the interface of each measuring point in the non-gamma detection area, the final distance between the borehole and the interface of each measuring point is determined, and the final distance between the borehole and the interface of each measuring point is used for drilling trajectory control.
[0045] In one embodiment, the drilling position coordinates of each measuring point are determined according to the drilling trajectory data and the depth of the drilling radar instrument, including:
[0046]
[0047]
[0048]
[0049]
[0050] Among them, (X k , Y k , Z k ) is the drilling position coordinate of the kth measuring point, k represents the kth measuring point, k = 1 ~ K, K is the number of measuring points, (X0, Y0, Z0) is the hole mouth coordinate, MD k is the depth of the borehole radar at the kth measuring point, θ k , are the inclination and azimuth of the kth measuring point respectively.
[0051] In one embodiment, judging whether the distance between the borehole and the interface at each measuring point enters the gamma detection area according to the gamma measurement data includes:
[0052] Calculate the gamma data GR 上 And the gamma data GR 下If ΔGR reaches the maximum difference threshold GR0, it is judged that the distance between the borehole and the interface enters the gamma detection area, otherwise it is judged that the distance between the borehole and the interface does not enter the gamma detection area.
[0053] In one embodiment, the constraint condition of the objective function in the dual-parameter full waveform inversion method is:
[0054] Constraint item m1 and weight factor W corresponding to constraint item m1 1e , constraint item m2 and the weight factor W corresponding to constraint item m2 2e ;
[0055] Constraint m1 refers to the area range information of the detection target area. The measurement point is within the detection target area. 1e is 1, the measuring point is not within the detection target area, W 1e is 0;
[0056] The constraint term m2 refers to the distance information between the measuring point and the interface measured in the gamma detection area. The measuring point is located on the interface of the gamma detection area where the boundary between the gamma detection area and the non-gamma detection area is located. Then W 2e =1, the measuring point is not on the interface of the gamma detection area where the boundary between the gamma detection area and the non-gamma detection area is located, W 2e is 0.
[0057] Compared with the prior art, the present application has the following beneficial effects: the multi-parameter-based layer-by-layer drilling trajectory control device and method of the present application can be used in coal mines, and utilizes parameters such as drilling radar while drilling, drilling azimuth gamma, drilling trajectory measurement while drilling, and temperature and pressure measurement in the hole, and the drilling radar and azimuth gamma inversion based on the cloud computing platform to invert the distance between the borehole and the target layer interface, which is used for advance detection and control of the drilling trajectory in the target layer. It can also control the drilling trajectory in a ground horizontal well to advance along the target layer interface within a certain range. During the drilling process of ground horizontal wells and underground coal mine beds, detection can be carried out, and the detection data can be transmitted to the hole mouth in real time. The hole mouth judges the geological conditions based on the detection data of the instruments in the hole, updates the geological model, and adjusts the drill bit to make the drilling trajectory move along the target. It can detect geological anomalies, water-bearing anomalies, overlying rock layers of the target layer and the interface position of the underlying strata within 0.5m to 10m around the borehole, with a resolution of 0.15m to 0.3m, providing technical support for rapid directional drilling of ground horizontal wells and underground coal mine beds. BRIEF DESCRIPTION OF THE DRAWINGS
[0058] The present application may be better understood by referring to the following description given in conjunction with the accompanying drawings, which together with the following detailed description are included in this specification and form a part of this specification. In the drawings:
[0059] Figure 1 A schematic structural diagram of a multi-parameter horizontal drilling trajectory control system according to an embodiment of the present application is shown;
[0060] Figure 2 A schematic diagram of the structure of a measurement while drilling probe in a hole according to an embodiment of the present application is shown;
[0061] Figure 3 A structural block diagram of a circuit board in a hole measurement while drilling probe according to an embodiment of the present application is shown;
[0062] Figure 4 A structural block diagram of a borehole radar control module according to an embodiment of the present application is shown;
[0063] Figure 5 A structural block diagram of an orifice monitor according to an embodiment of the present application is shown;
[0064] Figure 6 A flowchart of a multi-parameter horizontal drilling trajectory control method according to an embodiment of the present application is shown;
[0065] Figure 7 A diagram showing a borehole radar inversion result according to an embodiment of the present application is shown;
[0066] Figure 8 A diagram showing the actual borehole radar inversion result determined in an embodiment of the present application is shown. DETAILED DESCRIPTION
[0067] The exemplary embodiments of the present application will be described below in conjunction with the accompanying drawings. For the sake of clarity and conciseness, not all features of the actual embodiments are described in the specification. However, it should be understood that many implementation-specific decisions can be made in the process of developing any such actual embodiments in order to achieve the specific goals of the developer, and these decisions may vary from embodiment to embodiment.
[0068] It is also necessary to explain here that, in order to avoid obscuring the present application due to unnecessary details, only the device structure closely related to the scheme according to the present application is shown in the drawings, while other details that are not closely related to the present application are omitted.
[0069] It should be understood that the present application is not limited to the described implementation forms due to the following description with reference to the accompanying drawings. In this article, where feasible, the embodiments can be combined with each other, features between different embodiments can be replaced or borrowed, and one or more features can be omitted in one embodiment.
[0070] Figure 1The schematic diagram of the structure of the multi-parameter horizontal drilling trajectory control system according to the embodiment of the present application is shown. The system includes a drilling measurement probe 1, an external drill rod 2, a hole depth recording device 3, a borehole monitor 4 and a cloud computing platform 5. The system needs to be used with a drilling rig 6, a propulsion drill rod 7 and a drill bit 8.
[0071] Figure 2 The structural schematic diagram of the in-hole measurement while drilling probe 1 according to the embodiment of the present application is shown. The in-hole measurement while drilling probe 1 is arranged inside the external drill pipe 2, and a borehole radar instrument 9 and multiple gamma detectors are arranged inside the in-hole measurement while drilling probe 1. The in-hole measurement while drilling probe 1 includes two parts connected together, wherein the part along the drilling direction is a metal pipe, and the other part is a non-metal pipe, multiple gamma detectors and the transmitting antenna of the borehole radar instrument 9 are installed inside the metal pipe, and the receiving antenna, circuit board and battery of the borehole radar instrument 9 are installed inside the non-metal pipe, one end of the metal pipe of the in-hole measurement while drilling probe 1 is connected to the drill bit, and one end of the non-metal pipe is connected to the in-hole communication device, and then connected to the propulsion drill pipe 7. Here, two gamma detectors may be provided and arranged in a front-to-back arrangement, and each gamma detector is used to obtain the measurement value of each measuring point; the window angle of the gamma detector is ω (π / 4≤ω≤2π / 3), and the two windows are symmetrically arranged at 180°. The upper gamma orientation angle is defined as the tool orientation angle of the gamma detector. The upper gamma orientation angle of 0° indicates the tool orientation angle of the instrument when the center of the gamma detector 1 is facing upwards, and the measurement range of the upper gamma orientation angle is 0° to 360°.
[0072] Figure 3 The structural block diagram of the circuit board in the borehole measurement while drilling probe 1 according to the embodiment of the present application is shown. The circuit board includes a measurement while drilling control center CPU 310, a trajectory measurement while drilling module 320, a borehole temperature and pressure parameter measurement module 330, a borehole communication control module 340, a borehole radar control module 350 and an azimuth gamma measurement control module 360;
[0073] The borehole temperature and pressure parameter measurement module 330 is used to obtain the temperature T in the borehole for each measuring point. j and pressure P j , T j is the temperature in the borehole at the i-th measuring point, P j The pressure in the borehole at the i-th measuring point.
[0074] Figure 4The structural block diagram of the borehole radar control module 350 according to an embodiment of the present application is shown. The borehole radar control module 350 includes a borehole radar instrument control center 410, a wired communication module 420, a data storage module 430, a signal transmitter 440 and a signal receiver 450, wherein the signal transmitter 440 is connected to the transmitting antenna of the borehole radar instrument 9, and the signal receiver 450 is connected to the receiving antenna of the borehole radar instrument 9.
[0075] The drilling trajectory measurement module 320 includes multiple drilling trajectory measurement integrated chips, each of which is used to obtain trajectory measurement data of each measuring point, including 6 parameters, namely, the magnetic field components H in the x, y, and z directions. x , H y , H z , and the gravitational acceleration components G in the x, y, and z directions x , G y , G z The chip is a high-speed continuous sampling chip, and the sampling is uninterrupted during the entire measurement process. The drilling trajectory measurement module 320 is embedded with a drilling trajectory measurement data processing unit, which is used to process the acquired trajectory measurement data to obtain drilling trajectory data. The drilling trajectory data includes the inclination angle θ and azimuth angle of each measuring point. and working angle
[0076] The acquired trajectory measurement data is processed to obtain drilling trajectory data, which includes the inclination angle θ and azimuth angle of each measuring point. and working angle Specifically include:
[0077] Step 1: Measure the 6 parameters H obtained from the integrated chip for each drilling trajectory x , H y , H z , G x , G y , G z , the sliding window filtering method of the sampling points in the fixed time window is used for filtering, and the 6 parameters of each drilling trajectory measurement integrated chip after filtering at each measuring point are obtained;
[0078] Specifically, the following formula can be used:
[0079]
[0080]
[0081]
[0082]
[0083]
[0084]
[0085] Where k is the serial number of the kth drilling trajectory measurement integrated chip, j is the serial number of the jth measurement point measured by the kth drilling trajectory measurement integrated chip, n is the number of sampling points in a fixed time window, n>2, H xki , H yki , H zki are the magnetic field components in the X, Y, and Z directions of the i-th measuring point of the k-th drilling trajectory measurement chip, G xki , G yki , G zki are the gravitational acceleration components in the X, Y, and Z directions of the ith measuring point of the kth track measurement chip, are the filtered magnetic field components in the X, Y, and Z directions of the j-th measuring point of the k-th track measurement chip, They are the filtered gravitational acceleration components in the X, Y, and Z directions of the j-th measuring point of the k-th track measurement chip.
[0086] Step 2: for each measuring point, average the filtered 6 parameters corresponding to multiple drilling trajectory measurement integrated chips to obtain the average value of the 6 parameters at each measuring point. Specifically, the following formula can be used for calculation:
[0087]
[0088]
[0089]
[0090]
[0091]
[0092]
[0093] Where k is the serial number of the kth drilling trajectory measurement integrated chip, j is the serial number of the jth measurement point measured by the kth drilling trajectory measurement integrated chip, m is the number of trajectory measurement chips, m>1, are the magnetic field components in the X, Y, and Z directions of the jth measuring point, respectively. are the gravitational acceleration components in the X, Y, and Z directions of the j-th measuring point respectively.
[0094] Step 3: Based on the average value of the six parameters at each measuring point, the inclination angle θ and azimuth angle of each measuring point are obtained. and working angle The following formula can be used:
[0095]
[0096]
[0097]
[0098] In the formula, θ j , are the inclination angle θ of the jth measuring point and the working angle of the gamma detector. Azimuth
[0099] The gamma data processing unit is embedded in the azimuth gamma measurement control module 360, which is used to process the gamma measurement value of each measuring point to obtain gamma measurement data, that is, to convert the gamma measurement values GR1 and GR2 of the gamma detector 1 and the gamma detector 2 into upper gamma data GR 上 And the gamma data GR 下 , as the output of the azimuth gamma measurement control module 360, the specific conversion formula is as follows:
[0100] hour:
[0101] hour:
[0102] hour:
[0103] hour:
[0104] In the formula, is the working angle of the measuring point (with the opening direction of the gamma detector 1 as 0°), GR 上 It is the upper gamma data, in API, GR 下 is the gamma data in API, GR1 is the gamma measurement value of gamma detector 1 in API, GR2 is the gamma measurement value of gamma detector 1 in API, ω is the window angle of the gamma detector, π / 4≤ω≤2π / 3.
[0105] The MWD control center CPU310 is embedded with an intelligent MWD decision-making algorithm to determine the temperature T in the hole for each measuring point. j and pressure P j, and the six parameters measured by each drilling trajectory measurement integrated chip, control the drilling radar and gamma to enter the dormant state during drilling rest and drilling adjustment and other non-effective drilling states. During the drilling process, the drilling radar and gamma enter the working state to save electricity. The specific algorithm process is as follows:
[0106] Step 1: Calculate the average value of the trajectory measurement data of each measuring point within each window length. The trajectory measurement data includes the magnetic field components H in the x, y, and z directions. x , H y , H z and the gravitational acceleration components G in the x, y, and z directions x , G y , G z ; Specifically include:
[0107] The sliding window average calculation method is used, with a sliding step size of one unit per second and t w (t0≥10s) is the sliding window length, the sampling rate of the drilling trajectory measurement integrated chip is f1, the number of sampling points per second N0=1 / f1, and the sampling rate of the temperature and pressure parameter measurement module 330 in the drilling hole is f tp , the number of sampling points per second N tp =1 / f tp , calculate t w The inner drilling trajectory measures the magnetic field components and gravitational acceleration components in the X, Y, and Z directions of the integrated chip, as well as the average and standard deviation of the temperature and pressure in the hole, and uses the weighted method to calculate the standard deviation of the window length of the eight parameters as the indicator Fw for intelligent decision-making:
[0108] The calculation formula for the average value of each parameter within each window length is as follows:
[0109]
[0110]
[0111]
[0112]
[0113]
[0114]
[0115]
[0116]
[0117] Among them, H xjk , H yjk , Hzjk are the magnetic field components in the X, Y, and Z directions of the j-th measuring point of the k-th drilling trajectory measurement chip, G xjk , G yjk and G zjk are the gravitational acceleration components in the X, Y, and Z directions of the j-th measuring point of the k-th track measurement chip, The window lengths are t w The average value of the magnetic field components in the X, Y, and Z directions of the jth measuring point, and The window lengths are t w The average value of the gravitational acceleration components in the X, Y, and Z directions of the jth measuring point, T jk The temperature of the jth measurement point of the chip is measured for the kth drilling track, P jk Measure the pressure of the jth measuring point of the chip for the kth drilling trajectory, is the window length t w The average temperature of the jth measuring point in is the window length t w The average pressure of the jth measuring point in the
[0118] Step 2: Calculate the standard deviation of the trajectory measurement data of each measuring point in each window length based on the average value; the calculation formula for the standard deviation of each parameter in each window length is as follows:
[0119]
[0120]
[0121]
[0122]
[0123]
[0124]
[0125]
[0126]
[0127] In the formula, The window lengths are t w The standard deviation of the magnetic field components in the X, Y, and Z directions of the jth measuring point, The window lengths are t w The standard deviation of the gravitational acceleration components in the X, Y, and Z directions of the jth measuring point, Window length t wThe standard deviation of the temperature at the jth measuring point in the is the window length t w The standard deviation of the pressure at the jth measuring point.
[0128] Step 3: Calculate the indicator Fw of intelligent decision-making based on the standard deviation. The formula is as follows:
[0129]
[0130] In the formula: a1, a2, a3, b1, b2, b3, c1, c2 are weight coefficients respectively, among which b1>b2>b3>c1>c2>a1>a2>a3.
[0131] Step 4, according to the intelligent decision-making index standard F0, determine whether the drilling is in an effective drilling state or an ineffective drilling state. If Fw>F0, it is an effective drilling state. For the effective drilling state, the borehole radar antenna and the gamma detector are powered and corresponding signal processing is performed. If Fw>F0, it is an ineffective drilling state. For the ineffective drilling state, the borehole radar antenna and the gamma detector are stopped from being powered, and the corresponding signal processing is stopped. The data processing of the gamma and borehole radar in the control chip of the measurement while drilling center is stopped.
[0132] The measurement while drilling control center CPU 310 includes at least two data storage chips to ensure the reliability of data storage. The data stored on the two data storage chips are the same. They store all original measurement data and processed data. All original measurement data include trajectory measurement data measured by each drilling trajectory measurement integrated chip, original drilling radar data received by the signal receiver 450, measurement values measured by multiple gamma detectors, battery power data, borehole temperature, pressure and other data. The processed data includes drilling radar data, drilling trajectory data (inclination angle θ, azimuth angle Working angle ), gamma measurement data.
[0133] The hole depth recording device 3 is installed on the drilling rig 6 and is used to obtain the depth of the drilling radar instrument 9 at each measuring point and send it to the hole mouth monitor 4.
[0134] Figure 5 The structural block diagram of the orifice monitor according to the embodiment of the present application is shown. The orifice monitor 4 is a platform for human-machine interaction for realizing geosteering directional drilling, and is composed of a battery 510, a wired communication module 520, a signal receiving module 530, a signal decoding module 540, and a orifice monitor control center 550. The orifice monitor control center 550 is the main control unit of the orifice monitor 4, and controls the signal receiving module 530, the signal decoding module 540, and the wired communication module 520.
[0135] The borehole monitor control center 550 is equipped with a mining geological guidance control software system based on the borehole radar while drilling, the battery 510 supplies power to the borehole monitor control center 550, the signal receiving module 530 receives the signal sent by the in-hole communication device, the signal decoding module 540 decodes the signal received by the signal receiving module 530, and then processes it to the borehole monitor control center 550. The wired communication module 520 provides a wired communication method for the borehole monitor 4 to communicate with the hole depth recording device 3.
[0136] According to the drilling situation on site, the operator issues a control command to the drilling measurement probe 1 in the hole through the borehole monitor 4, and obtains the data returned by the drilling measurement probe 1 and the hole depth recording device 3, wherein the data returned by the drilling measurement probe 1 in the hole includes the drilling trajectory data of each measuring point, the gamma measurement data of each measuring point, the drilling radar data of each measuring point, and the data returned by the hole depth recording device 3 includes the depth of the drilling radar 9 of each measuring point. The mine geological guidance control software system is installed on the borehole monitor 4, and the mine geological guidance control software system on the borehole monitor 4 is connected to the cloud computing platform 5 through wifi, and the real-time measured data on site is transmitted to the cloud computing platform 5, and the cloud computing platform 5 performs the inversion calculation of the stratum interface, and the cloud computing platform 5 transmits the calculation results to the mine geological guidance control software system in real time. The operator displays the real-time calculation results according to the drilling situation on site and the mine geological guidance control software system, and the operator determines whether to adjust the drill bit and the drilling trajectory, and guides the drilling in real time.
[0137] The following is a detailed introduction to the specific implementation process of the multi-parameter horizontal drilling trajectory control method. Figure 6 The flowchart of the multi-parameter horizontal drilling trajectory control method according to the embodiment of the present application is shown. The method includes:
[0138] Step S610, obtaining borehole radar data, drilling trajectory data, gamma measurement data and depth of the borehole radar instrument at each measuring point, wherein the drilling trajectory data includes the inclination angle θ, azimuth angle ; Gamma measurement data includes upper gamma data GR 上 And the gamma data GR 下 .
[0139] Step S620, determining the drilling position coordinates of each measuring point according to the drilling trajectory data; the drilling position coordinates of the kth measuring point can be calculated using the following formula (X k ,Y k ,Z k )calculate:
[0140]
[0141]
[0142]
[0143]
[0144] Where: k represents the kth measuring point, k = 1~K, K is the number of measuring points, (X0, Y0, Z0) is the coordinate of the orifice, MD k is the depth of the borehole radar at the kth measuring point, θ k , are the inclination and azimuth of the kth measuring point respectively.
[0145] Step S630: judging whether the distance between the borehole and the interface at each measuring point enters the gamma detection area according to the gamma measurement data; the judgment may be made by the following method:
[0146] Calculate the gamma data GR 上 And the gamma data GR 下 If ΔGR reaches the maximum difference threshold GR0, it is judged that the distance between the borehole and the interface enters the gamma detection area, otherwise it is judged that the distance between the borehole and the interface does not enter the gamma detection area;
[0147] Step S640: If the distance between the borehole and the interface of each measuring point enters the gamma detection area, the distance between the borehole and the interface of each measuring point in the gamma detection area is determined by using the while drilling azimuth gamma inversion method based on the gamma measurement data and the coordinates of the borehole position of each measuring point; here, the while drilling azimuth gamma inversion method is the method in the public patent document: CN202111253553.4. Here, after determining the distance between the borehole and the interface of each measuring point, the interface in the gamma detection area can be determined.
[0148] Step S650: If the distance between the borehole and the interface of each measuring point does not enter the gamma detection area, then based on the borehole radar data and the coordinates of the borehole position of each measuring point, a dual-parameter (dielectric constant and conductivity) full waveform inversion method is used to determine the distance between the borehole and the interface of each measuring point in the non-gamma detection area;
[0149] In this step, since the borehole radar antenna is omnidirectional and non-directional, when the full-space inversion is performed in the borehole, two results that are symmetrical above and below appear, such as Figure 7 As shown in the figure, (a) is the relative permittivity distribution of the borehole radar inversion results, and (b) is the conductivity distribution of the borehole radar inversion results. Figure 7It can be seen that there are two formation interfaces above the borehole and two formation interfaces below the borehole. The distance between the inverted borehole and the interface has multiple solutions, which requires further analysis and judgment to select a result suitable for the actual situation. Therefore, in the process of solving the problem using the dual-parameter (dielectric constant and conductivity) full waveform inversion method, the constraint conditions of the objective function are set. The constraint conditions include: constraint term m1 and the weight factor W corresponding to the constraint term m1 1e , constraint item m2 and the weight factor W corresponding to constraint item m2 2e Here, the constraint item m1 refers to the area range information of the detection target area. The measurement point is within the detection target area. 1e is 1, the measuring point is not within the detection target area, W 1e is 0; the constraint term m2 refers to the distance information between the measuring point and the interface measured in the gamma detection area. Here, the distance information can be obtained according to the calculation result of step 640. The measuring point is located on the interface of the gamma detection area (i.e., the initial interface of the borehole radar inversion) at the junction of the gamma detection area and the non-gamma detection area. Then W 2e =1, the measuring point is not on the interface of the gamma detection area where the boundary between the gamma detection area and the non-gamma detection area is located, W 2e is 0, and the initial interface of the borehole radar inversion determined by the intersection position serves as a constraint item for the subsequent point inversion to prevent multiple solutions. Figure 8 The figure shows the actual borehole radar inversion result obtained in the embodiment of the present application.
[0150] Step S660, based on the distance between the borehole and the interface of each measuring point in the gamma detection area and the distance between the borehole and the interface of each measuring point in the non-gamma detection area, the final distance between the borehole and the interface of each measuring point is determined; the final distance between the borehole and the interface of each measuring point is used for drilling trajectory control. The final distance between the borehole and the interface of each measuring point is transmitted to the borehole monitor by the cloud computing platform, and the drilling personnel adjust the drill bit according to the distance information displayed on the borehole monitor to ensure that the drill bit drills along the coal seam.
[0151] In summary, the multi-parameter-based horizontal drilling trajectory control device and method of the present application can detect the geological conditions around and in front of the borehole during the drilling process in the coal mine, adjust the geological model of the area, guide the adjustment of the drilling trajectory, so that the drilling trajectory moves along the target layer, and detect during the drilling process, providing favorable geological data for the construction of smart coal mines in real time, which can save detection time. Compared with existing detection equipment, the advantages of this application are mainly reflected in the following points:
[0152] (1) Save detection time and obtain detection information in real time during the drilling process. Detection does not affect the drilling construction in the coal mine. In addition, real-time detection can be used to guide drilling and improve drilling efficiency, so that the drilling process in the coal mine can better serve the drilling target.
[0153] (2) The outer shell of the transmitting antenna of the borehole radar while drilling is the connection section between the metal probe tube and the drill bit. The metal drill rod is used to avoid the damage of the non-metallic outer shell of the borehole radar caused by the huge torque when the drill bit is drilling. At the same time, the transmitting antenna of the borehole radar while drilling is connected to the metal rod. The metal rod can be used as an extended amplification section of the transmitting antenna to form a waveguide on the metal rod. During the operation of the borehole radar while drilling, the detection end is closer to the drill bit, the detection effect is better, and it is more conducive to guiding drilling, avoiding the lag of detection caused by the gap between the borehole radar and the drill bit.
[0154] (3) Use multiple drilling trajectory measurement chips for continuous dynamic measurement to ensure that the trajectory data of all depth sampling points are obtained in real time, and use the information of trajectory measurement chips, temperature, and pressure measurements for intelligent control to ensure that the drilling radar and azimuth gamma data are collected during the drilling process, and automatically stop collecting data during the drilling stop and retraction process to extend the power supply time.
[0155] (4) Comprehensive analysis of borehole radar, azimuth gamma and borehole trajectory is used to guide drilling along the layer. Complementary detection is performed by using the short detection distance of azimuth gamma while drilling and the long detection distance of borehole radar. In addition, azimuth gamma is used to constrain the borehole radar inversion result, so that the output result of the distance between the borehole and the interface is unique.
[0156] (5) The cloud computing platform is equipped with a multi-parameter layer-based geosteering calculation system to perform borehole radar and azimuth gamma inversion processing, and the real-time calculation results are transmitted to the borehole monitor using the underground ring network equipment of the coal mine, which can avoid excessive load on the borehole monitor and affect efficiency. At the same time, the cloud computing platform can match large-capacity storage in the cloud server according to the calculation needs, store a large number of databases, and provide technical support for rapid inversion. After the cloud computing platform performs rapid inversion calculations, the results are transmitted to the borehole monitor, and the driller adjusts the drill bit according to the results displayed on the borehole monitor.
[0157] The above are only various implementations of the present application, but the protection scope of the present application is not limited thereto. Any person skilled in the art who is familiar with the present technical field can easily think of changes or substitutions within the technical scope disclosed in the present application, which should be included in the protection scope of the present application. Therefore, the protection scope of the present application should be based on the protection scope of the claims.
Claims
1. A multi-parameter based horizontal drilling trajectory control system, characterized in that: include: An in-hole measurement while drilling probe (1), a hole depth recording device (3), a hole mouth monitor (4) and a cloud computing platform (5), wherein the in-hole measurement while drilling probe (1) and the hole depth recording device (3) are both connected to the hole mouth monitor (4), and the hole mouth monitor (4) is connected to the cloud computing platform (5); The in-hole measurement while drilling probe (1) comprises a borehole radar instrument (9), a plurality of gamma detectors, a while drilling trajectory measurement module (320) and an azimuth gamma measurement control module (360); The borehole radar instrument (9) is used to obtain borehole radar data of each measuring point and send it to the borehole monitor (4); The multiple gamma detectors are used to obtain the measurement value of each measurement point and send it to the azimuth gamma measurement control module (360); The azimuth gamma measurement control module (360) is used to process the gamma measurement value of each measuring point, determine the gamma measurement data of each measuring point, and send it to the orifice monitor (4); The while-drilling trajectory measurement module (320) is used to obtain trajectory measurement data of each measuring point, process the trajectory measurement data, determine the drilling trajectory data of each measuring point, and send it to the borehole monitor (4); The hole depth recording device (3) is used to obtain the depth of the borehole radar instrument (9) at each measuring point and send it to the hole mouth monitor (4); The borehole monitor (4) is used to send the drilling trajectory data of each measuring point, the gamma measurement data of each measuring point, the borehole radar data of each measuring point and the depth of the borehole radar instrument (9) of each measuring point to the cloud computing platform; The cloud computing platform is used to determine the distance between the borehole and the interface of each measuring point based on the drilling trajectory data of each measuring point, the gamma measurement data of each measuring point, the drilling radar data of each measuring point and the depth of the drilling radar instrument (9) of each measuring point, and send the distance between the borehole and the interface of each measuring point to the orifice monitor (4). The orifice monitor (4) provides a display interface for controlling the drilling trajectory based on the distance between the borehole and the interface of each measuring point.
2. The system according to claim 1, characterized in that The in-hole measurement while drilling probe (1) further comprises: a borehole temperature and pressure parameter measurement module (330) and a measurement while drilling control center CPU (310); The borehole temperature and pressure parameter measurement module (330) is used to obtain the borehole temperature and pressure of each measuring point and send them to the measurement while drilling control center CPU (310); The measurement while drilling control center CPU (310) is used to determine whether the system is in an effective drilling state according to the temperature and pressure in the borehole of each measuring point and the trajectory measurement data of each measuring point.
3. The system according to claim 2, characterized in that Judging whether the system is in an effective drilling state according to the temperature and pressure in the borehole of each measuring point and the trajectory measurement data of each measuring point includes: Calculate the average value of the trajectory measurement data of each measuring point within each window length, wherein the trajectory measurement data includes the magnetic field components H in the x, y, and z directions. x , H y , H z and the gravitational acceleration components G in the x, y, and z directions x , G y , G z ; Calculate the standard deviation of the trajectory measurement data of each measuring point within each window length based on the average value; The indicator Fw of intelligent decision-making is calculated based on the standard deviation using the following formula: Among them, a1, a2, a3, b1, b2, b3, c1, c2 are all weight coefficients, among which b1>b2>b3>c1>c2>a1>a2>a3, are the standard deviations of the magnetic field components in the X, Y, and Z directions of the jth measuring point within the window length tw, are the standard deviations of the gravitational acceleration components in the X, Y, and Z directions of the jth measuring point within the window length tw; According to the indicator Fw of intelligent decision-making, it is judged whether the system is in an effective drilling state. If Fw>F0, the system is judged to be in an effective drilling state, otherwise, the system is judged to be in an ineffective drilling state.
4. The system according to claim 1, characterized in that in, Determining the distance between the borehole and the interface at each measuring point according to the drilling trajectory data of each measuring point, the gamma measurement data of each measuring point, the borehole radar data of each measuring point and the depth of the borehole radar instrument at each measuring point includes: Determine the drilling position coordinates of each measuring point according to the drilling trajectory data and the depth of the drilling radar instrument; Determine whether the distance between the borehole and the interface at each measuring point enters the gamma detection area according to the gamma measurement data; If the distance between the borehole and the interface of each measuring point enters the gamma detection area, then based on the gamma measurement data and the coordinates of the borehole position of each measuring point, the distance between the borehole and the interface of each measuring point in the gamma detection area is determined by using a while drilling azimuth gamma inversion method; If the distance between the borehole and the interface at each measuring point does not enter the gamma detection area, then based on the borehole radar data and the coordinates of the borehole position of each measuring point, a dual-parameter full waveform inversion method is used to determine the distance between the borehole and the interface at each measuring point in the non-gamma detection area; Based on the distance between the borehole and the interface of each measuring point in the gamma detection area and the distance between the borehole and the interface of each measuring point in the non-gamma detection area, the final distance between the borehole and the interface of each measuring point is determined, and the final distance between the borehole and the interface of each measuring point is used for drilling trajectory control.
5. The system according to claim 4, characterized in that in, Determining the drilling position coordinates of each measuring point according to the drilling trajectory data and the depth of the drilling radar instrument includes: Among them, (X k , Y k , Z k ) is the drilling position coordinate of the kth measuring point, k represents the kth measuring point, k = 1 ~ K, K is the number of measuring points, (X0, Y0, Z0) is the hole mouth coordinate, MD k is the depth of the borehole radar at the kth measuring point, θ k , are the inclination and azimuth of the kth measuring point respectively.
6. The system according to claim 4, characterized in that in, Judging whether the distance between the borehole and the interface at each measuring point enters the gamma detection area according to the gamma measurement data includes: Calculate the upper gamma data GR 上 and the lower gamma data GR 下 If ΔGR reaches the maximum difference threshold GR0, it is judged that the distance between the borehole and the interface enters the gamma detection area, otherwise it is judged that the distance between the borehole and the interface does not enter the gamma detection area.
7. A multi-parameter-based horizontal drilling trajectory control method, characterized in that: include: Obtain borehole radar data, borehole trajectory data, gamma measurement data and borehole radar depth at each measuring point; the borehole trajectory data includes the inclination angle θ and azimuth angle of each measuring point The gamma measurement data includes the upper gamma data GR of each measurement point 上 And the gamma data GR 下 ; Determine the drilling position coordinates of each measuring point according to the drilling trajectory data and the depth of the drilling radar instrument; Determine whether the distance between the borehole and the interface at each measuring point enters the gamma detection area according to the gamma measurement data; If the distance between the borehole and the interface of each measuring point enters the gamma detection area, then based on the gamma measurement data and the coordinates of the borehole position of each measuring point, the distance between the borehole and the interface of each measuring point in the gamma detection area is determined by using a while drilling azimuth gamma inversion method; If the distance between the borehole and the interface at each measuring point does not enter the gamma detection area, then based on the borehole radar data and the coordinates of the borehole position of each measuring point, a dual-parameter full waveform inversion method is used to determine the distance between the borehole and the interface at each measuring point in the non-gamma detection area; Based on the distance between the borehole and the interface of each measuring point in the gamma detection area and the distance between the borehole and the interface of each measuring point in the non-gamma detection area, the final distance between the borehole and the interface of each measuring point is determined, and the final distance between the borehole and the interface of each measuring point is used for drilling trajectory control.
8. The method according to claim 7, characterized in that in, Determining the drilling position coordinates of each measuring point according to the drilling trajectory data and the depth of the drilling radar instrument includes: Among them, (X k , Y k , Z k ) is the drilling position coordinate of the kth measuring point, k represents the kth measuring point, k = 1 ~ K, K is the number of measuring points, (X0, Y0, Z0) is the hole mouth coordinate, MD k is the depth of the borehole radar at the kth measuring point, θ k , are the inclination and azimuth of the kth measuring point respectively.
9. The method according to claim 7, characterized in that in, Judging whether the distance between the borehole and the interface at each measuring point enters the gamma detection area according to the gamma measurement data includes: Calculate the upper gamma data GR 上 and the lower gamma data GR 下 If ΔGR reaches the maximum difference threshold GR0, it is judged that the distance between the borehole and the interface enters the gamma detection area, otherwise it is judged that the distance between the borehole and the interface does not enter the gamma detection area.
10. The method according to claim 7, characterized in that The constraint condition of the objective function in the dual-parameter full waveform inversion method is: Constraint item m1 and weight factor W corresponding to constraint item m1 1e , constraint item m2 and the weight factor W corresponding to constraint item m2 2e ; Constraint m1 refers to the area range information of the detection target area. The measurement point is within the detection target area. 1e is 1, the measuring point is not within the detection target area, W 1e is 0; The constraint term m2 refers to the distance information between the measuring point and the interface measured in the gamma detection area. The measuring point is located on the interface of the gamma detection area where the boundary between the gamma detection area and the non-gamma detection area is located. Then W 2e =1, the measuring point is not on the interface of the gamma detection area where the boundary between the gamma detection area and the non-gamma detection area is located, W 2e is 0.