A method for floating and installing a tower crane on water

By assembling the floating platform and the tower crane's central foundation support, and installing components such as the climbing frame assembly and slewing bearing unit, the problem of low efficiency in the floating installation of tower cranes on water was solved, achieving a simplified and safe installation process.

CN115959574BActive Publication Date: 2026-11-10POLY CHANGDA ENGINEERING CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202211621238.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-12-16
Publication Date
2026-11-10
Estimated Expiration
2042-12-16

AI Technical Summary

Technical Problem

The existing tower crane floating installation process is cumbersome and inefficient.

Method used

The method of assembling a floating platform, a central foundation support for the tower crane, and an overall adjusting support is adopted. By assembling the pontoon, installing the climbing frame assembly, slewing bearing unit, boom, and operator's cab, and combining the hydraulic system and counterweight system, the overall floating and docking of the tower crane is achieved.

Benefits of technology

It simplifies the floating installation process of tower cranes on water, improves installation efficiency, and ensures operational safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115959574B_ABST
    Figure CN115959574B_ABST
Patent Text Reader

Abstract

This invention discloses a method for floating and installing a tower crane on water, relating to the field of floating and installing cranes on water, including the following steps: Step 1, Assembly of the floating platform: The floating platform uses two sets of pontoons, each set of pontoons is assembled from four pontoons of 12*3*1.5m in size, with internal pin connections. The top surface of the pontoons is connected as a whole using H350*175*7*11mm steel. The assembled pontoon group has a size of 24*17m, and the two sets of pontoons are symmetrically arranged about the center of the tower crane; Step 2, Assembly of the tower crane center foundation support: The tower crane center foundation support uses I 25a as the upright and [16 as the horizontal connecting rod, with an operating platform and guardrail on top; The floating and installing method of the tower crane on water of this invention is simple and quick to operate during the installation process, and the whole process is relatively safe.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of crane installation technology, and specifically to a method for floating and installing a tower crane on water. Background Technology

[0002] In conventional tower crane installation, auxiliary lifting equipment such as truck cranes and crawler cranes are used to install each component individually (e.g., foundation treatment, installation rails, traveling mechanism, traveling underframe, foundation section and diagonal bracing, counterweights, standard sections, outer frame, upper and lower supports, slewing tower body, tower cap, operator's cab, counterweight boom, partial counterweight, jib, and remaining counterweight). This installation procedure allows for the lifting of light weights and small tonnages with the selected auxiliary lifting equipment, but the installation time is long. When constructing at sea, the existing tower crane floating installation process is cumbersome and inefficient. Summary of the Invention

[0003] The purpose of this invention is to provide a method for floating and installing a tower crane on water, which solves the following technical problems: the existing method for floating and installing a tower crane on water is relatively complicated and has low installation efficiency.

[0004] The objective of this invention can be achieved through the following technical solutions:

[0005] A method for floating and installing a tower crane on water includes the following steps:

[0006] Step 1: Assembly of the floating platform:

[0007] The floating platform uses two sets of floating boxes. Each set of floating boxes is assembled from four floating boxes with a size of 12*3*1.5m. The floating boxes are connected internally with pins. The top surface of the floating boxes is connected as a whole with H350*175*7*11mm steel. The size of the assembled floating box group is 24*17m. The two sets of floating boxes are symmetrically arranged about the center of the tower crane.

[0008] Step 2: Assembly of the tower crane center foundation support:

[0009] The tower crane's central foundation support uses I25a as the vertical pole and [16 as the horizontal connecting pole, with an operating platform and guardrail on top;

[0010] The central foundation support of the tower crane is dismantled after the counterweight boom and lifting boom of the tower crane are installed.

[0011] Step 3: Assembly of the tower crane's overall adjustment support:

[0012] The overall adjustment support adopts a steel pipe, Bailey bridge, and steel section support system. A hydraulic system, pedestrian walkway, and operating platform are set on the top of the support. The bottom of the support is welded to the upper bridge truss of the floating box, and the top supports the counterweight arm and lifting arm of the tower crane through a hydraulic system.

[0013] Step 4: Assemble the upper structure of the tower crane:

[0014] S1. Install the climbing frame assembly; S2. Install the special section and slewing bearing unit; S3. Install the first section of the crane boom; S4. Install the operator's cab; S5. Install the counterweight boom; S6. Install the crane boom; S7. Install the float platform counterweight system; S8. Float transport of the tower crane; S9. Connect the tower crane superstructure and foundation.

[0015] As a further aspect of the present invention: S1, Install the climbing frame assembly: The climbing frame assembly includes a climbing frame, 3 standard sections, a working platform, and a lifting hydraulic system. After being assembled on the trestle, it is hoisted as a whole onto the central support of the floating box using an 85t crawler crane.

[0016] As a further aspect of the present invention: S2, installing a special section, slewing bearing unit:

[0017] Install the special section and connect it to the climbing frame using pins. Then, manually lift one of the guide beams from the guide device under the lower support, lift the front end of the guide beam and fix it with a pin and cotter pin, press down the front end of the guide beam to lift the rear end of the guide beam into place, and then fix the rear end of the guide beam with a pin and cotter pin. Install the other guide beam in the same way. After the guide device is installed, lift this set of components above the already installed transition section, so that the guide beam is in the direction of the opening of the lifting frame, and lower the entire set of components so that the four legs of the slewing lower support are inserted into the fishplate of the transition section. On the ground, first assemble the upper and lower supports, as well as the slewing mechanism, slewing bearing, platform, etc., into one unit and install it on the special section.

[0018] As a further embodiment of the present invention: S3, Install the first lifting boom section: Assemble the first lifting boom section on the ground, lift it, connect the lower end to the upper support with a pin, and connect the upper end to the counterweight arm.

[0019] As a further aspect of the present invention: S4, Install the driver's cab:

[0020] On the ground, first install the tower crane monitor display on the mounting plate; after checking all the electrical equipment in the operator's cab, lift the operator's cab onto the operator's cab platform on the upper support, and then connect the operator's cab to the upper support with bolts; all bolts should be fitted with cotter pins and the cotter pins should be opened 90°; then install the horn on the threaded hole at the bottom of the operator's cab near the door and connect the horn cable.

[0021] To facilitate lubrication and bolt tightening of the slewing bearing, a maintenance basket is designed on the lower support. This basket is for maintenance only. During normal operation, it must be removed and placed on a special section platform; otherwise, it will cause interference between the slewing operator's cab and the basket.

[0022] As a further aspect of the present invention: S5, Install the balance arm:

[0023] Select the counterweight boom assembly according to the boom length. Assemble the remaining parts of the counterweight boom except for boom section 1 on flat ground, and install the lifting mechanism, tie rod, etc. The tie rod frame is lifted on the tie rod frame and connected to the counterweight boom section 1 through the pin shaft.

[0024] As a further aspect of the present invention: S6, Install the lifting arm.

[0025] The longest boom has 11 sections. The boom sections are assembled according to different boom lengths. The 60m boom length assembly is as follows: boom section 1 + boom section 2 + boom section 3 + boom section 4 + boom section 5 + boom section 6 + boom section 7 + boom section 8 + boom head.

[0026] Assemble the crane according to the 60m boom length sequence, using pins to assemble them together, attach the trolley and basket, and fix the trolley and basket to the second section of the boom. Place the boom on a support about 1m high, so that the trolley and basket are off the ground; all pins must be fitted with cotter pins and the cotter pins must be fully opened.

[0027] As a further aspect of the present invention: S7, Floating platform counterweight system:

[0028] Water tanks and pumps are installed around the floating platform to level the floating box by pumping and draining water; a 5-cubic-meter water tank is placed in each corner.

[0029] When installing the floating tower crane, first replenish the water tank on the right side of the floating box with water until it reaches 0.5 times the self-weight of the tower crane to be lifted on the left side. Then, lift the left tower. After the left tower is installed, lift the right tower. During the installation of the right tower, gradually drain the water. Finally, weld the tower with flat connecting pipes. Then, use a level to level the entire floating box platform.

[0030] Then the tower body is installed. During the tower body installation process, the center of gravity of the load is kept on the vertical line of the centroid of the floating platform.

[0031] Next, the boom is installed. Before installation, the water tank on the pontoon in the boom direction is replenished with water, with the replenishment load being 0.5 times the self-weight of the first counterweight boom section. After the counterweight boom is installed, the water is drained so that the difference in draft between the front and rear of the pontoon is no more than 30cm. Then, the M1 boom is installed. During the installation process, the pre-installation load is balanced in advance by replenishing water to prevent excessive difference in draft between the front and rear. After the boom is finally installed, it is balanced through the water tank and ready for transportation.

[0032] As a further embodiment of the present invention: S8, Tower crane floating: After the tower crane is assembled, the constraints of the tower crane standard section and the central foundation support are released, the hydraulic system of the counterweight arm and the lifting arm is lifted, the overall stability of the floating box system is checked, the floating box is leveled with counterweight blocks to complete the force conversion, the tower crane central foundation support is removed, and the floating box assembly and tower crane are transported to the tower crane installation position by tugboats.

[0033] As a further aspect of the present invention: S9, connection between the tower crane upper structure and the foundation:

[0034] The top elevation of the embedded parts in the tower crane foundation is +4.6m, which is 4.6m above the water surface;

[0035] The bottom of the standard section of the superstructure, which was floated by the tower crane, was 4.8m above the water surface and 20cm higher than the top of the foundation.

[0036] When the tower crane floats to the vicinity of Pier 0 of Bridge 5, first align the pontoon group 2 with the middle of the two rows of pile foundations, and then move forward parallel to the pile foundations.

[0037] The beneficial effects of this invention are:

[0038] The tower crane floating installation method of this invention is simple, quick, and relatively safe to operate during the installation process. Attached Figure Description

[0039] The invention will now be further described with reference to the accompanying drawings.

[0040] Figure 1 This is a schematic diagram of the planar structure of the pontoon of the present invention;

[0041] Figure 2 This is a schematic diagram of the structure of the tower crane center of the present invention;

[0042] Figure 3 This is a front view structural schematic diagram of the overall adjustable support for tower cranes of the present invention;

[0043] Figure 4 This is a schematic diagram of the back structure of the overall adjustable support for tower cranes of the present invention;

[0044] Figure 5 This is a schematic diagram of the upper structure of the present invention;

[0045] Figure 6 This is a schematic diagram of the structure assembled on the tower crane pontoon of the present invention;

[0046] Figure 7 This is another structural schematic diagram of the assembly on the tower crane pontoon of the present invention;

[0047] Figure 8 This is a structural schematic diagram of the climbing frame assembly of the present invention;

[0048] Figure 9 This is a schematic diagram of the structure for installing the special section of the present invention;

[0049] Figure 10 This is another structural schematic diagram of the special section installation of the present invention;

[0050] Figure 11 This is a schematic diagram of the structure of the cab installed in this invention;

[0051] Figure 12 This is a schematic diagram of the tower crane floating structure of the present invention;

[0052] Figure 13 This is a schematic diagram of the connection between the upper structure of the tower crane and the foundation of the present invention.

[0053] In the diagram: 1; Floating platform; 2; Longitudinal reinforcing I-beam; 3; Tower crane center foundation support; 4; Deck I-beam; 5; Reinforced I-beam; 6; Column support; 7; Steel pipe column; 8; Diagonal brace; 9; Longitudinal horizontal bracing; 10; Top beam; 11; Bailey bridge; 12; Upper horizontal bracing of Bailey bridge; 13; Horizontal horizontal bracing; 14; Tower crane hoisting truss; 15; Tower crane support truss; 16; Bailey bridge horizontal bracing; 17; Upper load-bearing beam of jack; 18; Climbing frame; 19; Upper platform of the frame; 20; Frame; 21; Lower platform of the frame; 22; Lifting cylinder; 23; Frame climbing ladder. Detailed Implementation

[0054] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0055] Please see Figure 1-13 As shown, this invention is a method for floating and installing a tower crane on water. The tower crane floating platform support includes a floating platform, a tower crane bottom foundation support, and an overall adjustment support, and includes the following steps:

[0056] Step 1, Assembly of Floating Platform 1: See Figure 1 As shown;

[0057] The floating platform 1 uses two sets of floating boxes. Each set of floating boxes is assembled from four floating boxes with a size of 12*3*1.5m. The floating boxes are connected by pins inside. The top surface of the floating boxes is connected into a whole by H350*175*7*11mm steel. The size of the assembled floating box group is 24*17m. The two sets of floating boxes are symmetrically arranged about the center of the tower crane.

[0058] Step 2, Assembly of Tower Crane Center Foundation Support 3: See Figure 2 As shown;

[0059] The tower crane's central foundation support uses I25a as the vertical pole and [16 as the horizontal connecting pole, with an operating platform and guardrail on top;

[0060] The central foundation support of the tower crane is dismantled after the counterweight boom and lifting boom of the tower crane are installed.

[0061] Step 3: Assembly of the tower crane's overall adjustment support: See Figure 3-4 As shown;

[0062] The overall adjustment support is composed of longitudinally reinforcing H-beams 3; deck H-beams 4; reinforced H-beams 5; column supports 6; steel pipe columns 7; diagonal braces 8; longitudinal horizontal bracing 9; top crossbeams 10; Bailey bridges 11; upper horizontal bracing of Bailey bridges 12; horizontal horizontal bracing 13; tower crane hoisting truss 14; tower crane support truss 15; Bailey bridge horizontal bracing 16; and upper load-bearing beams of jacks 17. A hydraulic system, pedestrian walkway, and operating platform are set above the support. The bottom of the support is welded to the upper bridge truss of the floating box, and the top supports the counterweight arm and lifting arm of the tower crane through the hydraulic system.

[0063] Step 4: Assemble the upper structure of the tower crane:

[0064] The tower crane's superstructure consists of an 18-section climbing frame (including 3 standard sections), special sections, a slewing mechanism, and a counterweight boom (without a counterweight). The boom is assembled as a whole on the floating box. The assembled superstructure is 55m long, 3.3m wide at most, 16m high, and weighs 50t. Figure 5 As shown;

[0065] The upper components of the tower crane are assembled on the side of ramp A of the trestle bridge, using an 85t crawler crane;

[0066] After the pontoon support is erected and positioned, the assembly of the tower crane's upper structure begins. The assembly process is as follows: install the climbing frame assembly → install the special section and slewing bearing assembly → install the operator's cab → install the counterweight boom → install the lifting boom; Figure 6-7 As shown;

[0067] S1. Installation of the climbing frame assembly: The climbing frame assembly includes the upper platform 19, the frame 20, the lower platform 21, the lifting cylinder 22, and the climbing ladder 23. After assembly on the trestle, it is hoisted as a whole onto the central support of the pontoon using an 85t crawler crane. See [link / details]. Figure 8 As shown;

[0068] S2. Installation of special sections and slewing bearing units: See Figure 9-10 As shown;

[0069] Install the special section and connect it to the climbing frame using pins. Then, manually lift one of the guide beams from the guide device under the lower support, lift the front end of the guide beam and fix it with a pin and cotter pin, press down the front end of the guide beam to lift the rear end of the guide beam into place, and then fix the rear end of the guide beam with a pin and cotter pin. Install the other guide beam in the same way. After the guide device is installed, lift this set of components above the already installed transition section, so that the guide beam is in the direction of the opening of the lifting frame, and lower the entire set of components so that the four legs of the slewing lower support are inserted into the fishplate of the transition section. On the ground, first assemble the upper and lower supports, as well as the slewing mechanism, slewing bearing, platform, etc., into one unit and install it on the special section.

[0070] S3. Install crane boom section one: Assemble crane boom section one (including luffing mechanism, rope pulley, etc. installed on counterweight boom, and connect the required wires for each part) on the ground, lift it, connect the lower end to the upper support with a pin, and connect the upper end to the counterweight boom.

[0071] S4. Install the driver's cab: See Figure 11 As shown;

[0072] On the ground, first install the tower crane monitor display on the mounting plate (for air conditioning, the air conditioning manufacturer must complete installation and commissioning at the factory before the tower crane is shipped). After checking all electrical equipment in the operator's cab, hoist the operator's cab onto the operator's cab platform on the upper support, and then connect the operator's cab to the upper support with bolts. All bolts must be fitted with cotter pins, and the cotter pins should be opened 90 degrees. Then install the horn on the threaded hole at the bottom of the operator's cab near the door, and connect the horn cable;

[0073] To facilitate lubrication and bolt tightening of the slewing bearing, a maintenance basket is designed on the lower support. This basket is for maintenance only. During normal operation, it must be removed and placed on a special section platform; otherwise, it will cause interference between the slewing operator's cab and the basket.

[0074] S5. Install the counterweight arm:

[0075] Select a counterweight boom assembly based on the boom length (60m boom, counterweight boom assembly consists of boom section 1 + boom section 2 + boom section 3). Assemble the counterweight boom except for boom section 1 on flat ground, and install the lifting mechanism, tie rods, etc., with the tie rods mounted on the tie rod frame. Lift the crane and connect it to counterweight boom section 1 via a pin.

[0076] S6. Install the lifting boom

[0077] The longest boom has 11 sections. The boom sections are assembled according to different boom lengths. The 60m boom length assembly is as follows: boom section 1 + boom section 2 + boom section 3 + boom section 4 + boom section 5 + boom section 6 + boom section 7 + boom section 8 + boom head.

[0078] Assemble the crane according to the 60m boom length sequence, using pins to assemble them together, attach the trolley and basket, and fix the trolley and basket to the second section of the boom. Place the boom on a support about 1m high, so that the trolley and basket are off the ground; all pins must be fitted with cotter pins and the cotter pins must be fully opened.

[0079] S7, Floating Platform Counterweight System:

[0080] Water tanks and pumps are installed around the floating platform to level the floating box by pumping and draining water; a 5-cubic-meter water tank is placed in each corner.

[0081] When installing the floating tower crane, first replenish the water tank on the right side of the floating box with water until it reaches 0.5 times the self-weight of the tower crane to be lifted on the left side. Then, lift the left tower. After the left tower is installed, lift the right tower. During the installation of the right tower, gradually drain the water. Finally, weld the tower with flat connecting pipes. Then, use a level to level the entire floating box platform.

[0082] Then the tower body is installed. During the tower body installation process, the center of gravity of the load is kept on the vertical line of the centroid of the floating platform.

[0083] Next, the boom is installed. Before installation, the water tank on the pontoon in the boom direction is replenished with water, with the replenishment load being 0.5 times the self-weight of the first counterweight boom section. After the counterweight boom is installed, the water is drained so that the difference in draft between the front and rear of the pontoon is no more than 30cm. Then, the M1 boom is installed. During the installation process, the pre-installation load is balanced in advance by replenishing water to prevent excessive difference in draft between the front and rear. After the boom is finally installed, it is balanced through the water tank and ready for transportation.

[0084] S8. Tower Crane Floating Transportation: After the tower crane is assembled, the constraints of the standard tower crane sections and the central foundation support are released. The hydraulic systems of the counterweight boom and lifting boom are raised. After checking the overall stability of the pontoon system, counterweights are used to level the pontoons, completing the force transfer. The central foundation support of the tower crane is then dismantled. Tugboats are used to transport the pontoon assembly and the tower crane to the tower crane installation location. See also Figure 12 As shown;

[0085] S9. Connection between tower crane superstructure and foundation: See Figure 13 As shown.

[0086] The top elevation of the embedded parts in the tower crane foundation is +4.6m, which is 4.6m above the water surface;

[0087] The bottom of the standard section of the superstructure, which was floated by the tower crane, was 4.8m above the water surface and 20cm higher than the top of the foundation.

[0088] When the tower crane floats to the vicinity of Pier 0 of Bridge 5, first align the pontoon group 2 with the middle of the two rows of pile foundations, and then move forward parallel to the pile foundations.

[0089] The foregoing has provided a detailed description of one embodiment of the present invention, but this description is merely a preferred embodiment and should not be construed as limiting the scope of the invention. All equivalent variations and modifications made within the scope of the claims of this invention should still fall within the patent coverage of this invention.

Claims

1. A method for floating and installing a tower crane on water, characterized in that, Includes the following steps: Step 1: Assembly of the floating platform: The floating platform uses two sets of floating boxes. Each set of floating boxes is assembled from four floating boxes with a size of 12*3*1.5m. The floating boxes are connected internally with pins. The top surface of the floating boxes is connected as a whole with H350*175*7*11mm steel. The size of the assembled floating box group is 24*17m. The two sets of floating boxes are symmetrically arranged about the center of the tower crane. Step 2: Assembly of the tower crane center foundation support: The tower crane's central foundation support uses I25a as the vertical pole and [16 as the horizontal connecting pole, with an operating platform and guardrail on top; The central foundation support of the tower crane is dismantled after the counterweight boom and lifting boom of the tower crane are installed. Step 3: Assembly of the tower crane's overall adjustment support: The overall adjustment support adopts a steel pipe, Bailey bridge, and steel section support system. A hydraulic system, pedestrian walkway, and operating platform are set on the top of the support. The bottom of the support is welded to the upper bridge truss of the floating box, and the top supports the counterweight arm and lifting arm of the tower crane through a hydraulic system. Step 4: Assemble the upper structure of the tower crane: S1. Install the climbing frame assembly; S2. Install the special section and slewing bearing unit; S3. Install the first section of the lifting boom; S4. Install the operator's cab; S5. Install the counterweight boom; S6. Install the lifting boom; S7. Install the float platform counterweight system; S8. Float transport of the tower crane; S9. Connect the tower crane superstructure and foundation; S7, Floating Platform Counterweight System: Water tanks and pumps are installed around the floating platform to level the floating box by pumping and draining water; a 5-cubic-meter water tank is placed in each corner. When installing the floating tower crane, first replenish the water tank on the right side of the floating box with water until it reaches 0.5 times the self-weight of the tower crane to be lifted on the left side. Then, lift the left tower. After the left tower is installed, lift the right tower. During the installation of the right tower, gradually drain the water. Finally, weld the tower with flat connecting pipes. Then, use a level to level the entire floating box platform. Then the tower body is installed. During the tower body installation process, the center of gravity of the load is kept on the vertical line of the centroid of the floating platform. Next, the boom is installed. Before installation, the water tank on the pontoon in the boom direction is replenished with water, with the replenishment load being 0.5 times the self-weight of the first counterweight boom section. After the counterweight boom is installed, the water is drained so that the difference in draft between the front and rear of the pontoon is no more than 30cm. Then, the M1 boom is installed. During the installation process, the pre-installation load is balanced in advance by replenishing water to prevent excessive difference in draft between the front and rear. After the boom is finally installed, it is balanced through the water tank and ready for transportation.

2. The method for floating and installing a tower crane on water according to claim 1, characterized in that, S1. Install the climbing frame assembly: The climbing frame assembly includes a climbing frame, 3 standard sections, a working platform, and a lifting hydraulic system. After assembly on the trestle, it is hoisted as a whole onto the center support of the pontoon using an 85t crawler crane.

3. The method for floating and installing a tower crane on water according to claim 1, characterized in that, S2. Install special sections and slewing bearing units: Install the special section and connect it to the climbing frame using pins. Then, manually lift one of the guide beams from the guide device under the lower support, lift the front end of the guide beam and fix it with a pin and cotter pin, press down the front end of the guide beam to lift the rear end of the guide beam into place, and then fix the rear end of the guide beam with a pin and cotter pin. Install the other guide beam in the same way. After the guide device is installed, lift this set of components above the already installed transition section, so that the guide beam is in the direction of the opening of the lifting frame, and lower the entire set of components so that the four legs of the slewing lower support are inserted into the fishplate of the transition section. On the ground, first assemble the upper and lower supports, as well as the slewing mechanism, slewing bearing, and platform into one unit and install them on the special section.

4. The method for floating and installing a tower crane on water according to claim 1, characterized in that, S3. Install crane boom section one: Assemble crane boom section one on the ground, lift it, connect the lower end to the upper support with a pin, and connect the upper end to the counterweight boom.

5. A method for floating and installing a tower crane on water according to claim 1, characterized in that, S4. Install the driver's cab: On the ground, first install the tower crane monitor display on the mounting plate; after checking all the electrical equipment in the operator's cab, lift the operator's cab onto the operator's cab platform on the upper support, and then connect the operator's cab to the upper support with bolts; all bolts should be fitted with cotter pins and the cotter pins should be opened 90°; then install the horn on the threaded hole at the bottom of the operator's cab near the door and connect the horn cable. To facilitate lubrication and bolt tightening of the slewing bearing, a maintenance basket is designed on the lower support. This basket is for maintenance only. During normal operation, it must be removed and placed on a special section platform; otherwise, it will cause interference between the slewing operator's cab and the basket.

6. A method for floating and installing a tower crane on water according to claim 1, characterized in that, S5. Install the counterweight arm: Select the counterweight boom assembly according to the boom length. Assemble the remaining parts of the counterweight boom except for boom section 1 on flat ground, and install the lifting mechanism and tie rod. The tie rod frame is lifted on the tie rod frame and connected to the counterweight boom section 1 through a pin.

7. A method for floating and installing a tower crane on water according to claim 1, characterized in that, S6. Install the lifting boom The longest boom has 11 sections. The boom sections are assembled according to different boom lengths. The 60m boom length assembly is as follows: boom section 1 + boom section 2 + boom section 3 + boom section 4 + boom section 5 + boom section 6 + boom section 7 + boom section 8 + boom head. Assemble the crane according to the 60m boom length sequence, using pins to assemble them together, attach the trolley and basket, and fix the trolley and basket to the second section of the boom. Place the boom on a support about 1m high, so that the trolley and basket are off the ground; all pins must be fitted with cotter pins and the cotter pins must be fully opened.

8. A method for floating and installing a tower crane on water according to claim 1, characterized in that, S8. Tower Crane Floating Transportation: After the tower crane is assembled, the constraints of the standard tower crane sections and the central foundation support are released. The hydraulic systems of the counterweight boom and the lifting boom are raised. After checking the overall stability of the pontoon system, the pontoon is leveled with counterweights to complete the force conversion. The central foundation support of the tower crane is removed. The pontoon assembly and the tower crane are transported to the tower crane installation position by tugboats.

9. A method for floating and installing a tower crane on water according to claim 1, characterized in that, S9. Connection between tower crane superstructure and foundation: The top elevation of the embedded parts in the tower crane foundation is +4.6m, which is 4.6m above the water surface; The bottom of the standard section of the superstructure, which was floated by the tower crane, was 4.8m above the water surface and 20cm higher than the top of the foundation. When the tower crane floats to the vicinity of Pier 0 of Bridge 5, it first aligns the floating box assembly with the middle of the two rows of pile foundations, and then moves forward parallel to the pile foundations.