A slope greening construction technology based on high-steep dangerous rock belt

By building flower beds, erecting protective railings, planting plants and installing irrigation sprinklers on the slopes of steep and dangerous rock belts, the problem of difficult greening construction on the slopes of steep and dangerous rock belts was solved, and safe and efficient greening construction and irrigation effects were achieved.

CN116005691BActive Publication Date: 2025-09-30重庆川东南工程勘察设计院有限公司
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202211705394.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-12-29
Publication Date
2025-09-30
Estimated Expiration
2042-12-29

AI Technical Summary

Technical Problem

The greening construction of slopes in high-steep and dangerous rock belts is difficult and the basic conditions for planting greenery are not available, so existing technologies are difficult to effectively solve the problem.

Method used

Flower beds are built on the slopes and temporary protective railings are set up. Gravel is processed, shrubs, vines and trees are planted, and irrigation sprinkler devices are installed, including a supporting middle frame, supporting side frames, sprinkler mechanisms and drive mechanisms. The irrigation coverage area is increased through organ pipes and swing plates.

Benefits of technology

It reduces the difficulty of greening construction on the slopes of high and steep dangerous rock belts, provides planting and growth conditions, improves irrigation efficiency and coverage area, and ensures the safety of workers.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116005691B_ABST
    Figure CN116005691B_ABST
Patent Text Reader

Abstract

The present application relates to a slope greening construction process based on a high-steep and dangerous rock belt, and relates to the field of geotechnical engineering and slope greening engineering technology, which includes the following steps: a flower bed construction step: a flower bed is constructed on the slope horse road, the flower bed is made of mortar-laid block stones, and reinforcement is planted in the center and below the flower bed; a construction protection step: a row of temporary protective railings are set up on the horse road and the outside of the slope mouth, and the temporary protective railings are connected to the inside of the slope; a crushed stone processing step: the crushed stones are manually discarded at the foot of the slope, and a safety rope is hung when the stones are manually thrown; a green plant planting step in the flower bed: soil is cultivated on the inside of the flower bed, shrubs and vines are planted in the flower bed, and trees are planted at the foot of the slope; an irrigation system installation step: a water reservoir is set up on the top of the slope, an irrigation sprinkler is set up in the flower bed, and the water reservoir is connected to the irrigation sprinkler. The present application has the effect of improving the difficulty of greening construction on the slope of a high-steep and dangerous rock belt.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical fields of geotechnical engineering and slope greening engineering, and in particular to a slope greening construction process based on high-steep and dangerous rock belts. Background Art

[0002] Currently, high-steep and dangerous rock formations have always been a major concern for roadside slopes due to their inherent uncertainty and danger. With the acceleration of modern road construction, slope protection and management have become increasingly important. For cities promoting green roads, slope greening in high-steep and dangerous rock formations is a key focus. This is because slope greening can cover the unsightly exposed rocks in these areas, transforming them into beautiful green belts and improving driver comfort.

[0003] Regarding the above-mentioned related technologies, the applicant believes that it is very difficult to carry out greening construction on the steep and dangerous rock belt due to its large slope. Moreover, the steep and dangerous rock slopes do not have the basic conditions for planting greening, which further increases the difficulty of greening construction on the slopes of the steep and dangerous rock belt. Summary of the Invention

[0004] In order to improve the difficulty of greening construction on the slopes of high-steep and dangerous rock belts, the purpose of this application is to provide a slope greening construction process based on high-steep and dangerous rock belts.

[0005] The slope greening construction technology based on high-steep and dangerous rock belts provided in this application adopts the following technical solutions:

[0006] A slope greening construction process based on high-steep dangerous rock belts includes the following steps:

[0007] Flower bed construction steps: Build a flower bed on the slope of the horseway. The flower bed is made of mortar-made block stone. The mortar strength is M7.5 and the block stone strength is MU30. Plant reinforcement in the center and below the flower bed. Set a drainage hole 0.1m above the ground. Use a 110mm diameter PVC pipe to pre-buried the drainage hole.

[0008] Construction protection steps: Set up a row of temporary protective railings on the outside of the bridleway and the slope entrance. The temporary protective railings are connected to the inner side of the slope. The erection of temporary protective railings must meet the DBJ50 / T-123-2020 technical standards for building guardrails. They will be removed once the plant survival rate meets the requirements.

[0009] Gravel processing steps: manually discard the crushed stones at the foot of the slope, and hang a safety rope when manually throwing the stones;

[0010] Steps for planting green plants in the flower bed: cultivate the soil inside the flower bed, plant shrubs and vines in the flower bed, and plant trees at the foot of the slope. Workers hang safety ropes throughout the planting process.

[0011] Irrigation system installation steps: set up a water reservoir on the top of the slope, set up an irrigation sprinkler device in the flower bed, and connect the water reservoir and the irrigation sprinkler device.

[0012] By adopting the above technical solution, when carrying out slope greening construction on high-steep and dangerous rock belts, the flower bed is first built. The flower bed is the basis for planting plants. During the construction of the flower bed, temporary protective railings are built in advance. The protective railings can not only protect the flower bed, but also be used to hang workers' safety belts, so that workers are safer when working on high-steep and dangerous rocks, and it is also possible for workers to work on steep slopes; the gravel generated during the construction process is directly discarded at the foot of the slope and subsequently processed in a unified manner; through the above construction steps, the difficulty of greening construction on the slope of high-steep and dangerous rock belts can be further reduced, and the setting of flower beds, water reservoirs and irrigation sprinklers can further provide green plants on the slope with planting conditions and subsequent growth conditions.

[0013] Optionally, the irrigation sprinkler device includes a supporting middle frame, a supporting side frame, a sprinkler mechanism and a driving mechanism; the supporting middle frame is installed in the flower bed, and the supporting side frames are provided at each end of the supporting middle frame; the supporting side frames are provided with straight rails, the length direction of the straight rails is consistent with the length direction of the flower bed, and the sprinkler mechanism is slidably set on the straight rails; the driving mechanism is installed on the supporting middle frame, and the driving mechanism is used to drive the sprinkler mechanism to move along the length direction of the straight rails.

[0014] By adopting the above technical solution, when watering the plants in the flower bed, the water in the water reservoir is transported to the sprinkler mechanism, and then the sprinkler mechanism is driven by the driving mechanism to move along the length direction of the supporting side frame; since the length direction of the supporting side frame is consistent with the length direction of the flower bed, and there are two supporting side frames, that is, there are two sprinkler mechanisms; therefore, the two sprinkler mechanisms can water most of the plants in the flower bed, thereby increasing the coverage area of ​​the water and improving the watering effect.

[0015] Optionally, the driving mechanism includes a rotating motor, a driving shaft, a driven shaft and a threaded moving assembly; the rotating motor is installed on the supporting middle frame, the driving shaft is coaxially installed on the output shaft of the rotating motor and the end of the driving shaft away from the rotating motor is rotatably connected to the supporting middle frame, the driven shaft is rotatably set on the supporting middle frame, the driving shaft and the driven shaft are transmitted through gear meshing, and the length directions of the driving shaft, the driven shaft and the straight rail are consistent; the threaded moving assembly is respectively provided with one on the driving shaft and the driven shaft, and the threaded moving assembly automatically moves along the length direction of the driving shaft / driven shaft when the driving shaft / driven shaft rotates, and the threaded moving assembly is connected to the spray mechanism.

[0016] By adopting the above technical solution, the rotating motor is started, so that the rotating motor drives the driving shaft to start rotating. Since the driving shaft is transmitted through gear meshing, the driven shaft will also rotate with the driving shaft. At this time, the threaded moving component will move along the length direction of the driving shaft, thereby driving the spray mechanism to move synchronously on the supporting side frame, and finally realize the driving of the spray mechanism.

[0017] Optionally, the threaded moving assembly includes a threaded moving cylinder, a limit block and a connecting rod; the driving shaft and the driven shaft are both threaded rods, and the two threaded moving cylinders are threadedly sleeved on the driving shaft and the driven shaft respectively; the limit block is arranged on the threaded moving cylinder, and a stop groove is provided on the supporting middle frame along the length direction of the supporting middle frame, and the limit block is slidably inserted in the stop groove; one end of the connecting rod is connected to the threaded moving cylinder, and the other end is connected to the spray mechanism.

[0018] By adopting the above technical solution, when the rotating motor rotates, the driving shaft and the driven shaft rotate synchronously with the rotation of the output shaft of the rotating motor, and the two threaded moving cylinders are respectively threadedly matched with the driving shaft and the driven shaft. Therefore, when the driving shaft and the driven shaft are both rotating, the threaded moving cylinder will also rotate. Since the limit block on the threaded moving cylinder is inserted in the anti-rotation groove, the threaded moving cylinder cannot rotate at this time, but will move along the length direction of the driving shaft and the driven shaft; the movement of the threaded moving cylinder will synchronously move the spray mechanism, thereby achieving the effect of driving the spray mechanism to move more conveniently.

[0019] Optionally, the spray mechanism includes a moving block, an organ pipe and a spray head; the moving block is slidably set on a straight rail, the spray head is installed on the top of the moving block, and the spray hole of the spray head is vertically facing upward; one end of the organ pipe is connected to the spray head, and the other end is connected to the water tank at the top of the slope through a water pump.

[0020] By adopting the above technical solution, the water pump is started, and the water in the water reservoir will directly enter the sprinkler head through the organ pipe. The spray hole of the sprinkler head is vertically upward, and the sprayed water will be sprinkled around the sprinkler head, and the moving block will move synchronously with the threaded moving cylinder in the straight track; and because the water supply pipeline is an organ pipe and can be extended and retracted, the moving block will allow the water in the water reservoir to enter the sprinkler head normally through the organ pipe during the movement, thereby achieving the effect of normal water supply.

[0021] Optionally, a rotating shaft is rotatably provided on the moving block, a roller is coaxially provided at one end of the rotating shaft, and an engaging wheel is provided at the other end; a rolling groove is provided on the straight rail along the length direction of the straight rail, and the roller rolls in cooperation with the rolling groove; a rack is provided on the straight rail along the length direction of the straight rail, and the engaging wheel engages with the rack.

[0022] By adopting the above technical solution, as the meshing wheel meshes with the rack and the roller rolls in the rolling groove, the moving block can move more stably in the length direction of the straight rail.

[0023] Optionally, a bar-shaped through hole is provided on the straight rail, and a swing plate is rotatably provided on the straight rail on the bar-shaped through hole, the swing plate covers the bar-shaped through hole and the swing plate is located directly below the moving block; a swing assembly is provided on the moving block, and the swing assembly is used to drive the swing plate to swing back and forth when the moving block moves along the length direction of the straight rail; the moving block is hollow inside and has an open lower end, and a branch pipe is also connected to the organ pipe, one end of the branch pipe extends into the moving block and faces the swing plate.

[0024] By adopting the above technical solution, a branch pipe is connected to the organ pipe, which will transport part of the water to the moving block and flow to the swing plate; and when the moving block is moving, the swing assembly will drive the swing plate to swing continuously, so the water flowing onto the swing plate will continuously flow down from both sides of the swing plate and flow onto the plants in the flower bed; this part of the water will irrigate the plants that cannot be irrigated by the sprinkler head under the supporting side frame, thereby further increasing the coverage area of ​​​​plant irrigation in the flower bed.

[0025] Optionally, the rocking assembly includes a cam, which is arranged on a rotating shaft; a center rotating rod is provided in the middle of the bar-shaped through hole along the length direction of the bar-shaped through hole, and a center bar hole is opened in the middle of the rocking plate along the length direction of the rocking plate, and the center rotating rod is rotated through the center bar hole and is connected to the rocking plate for rotation, and the surface of the cam is in conflict with the upper plate surface of the rocking plate on the side of the center rotating rod; a torsion spring is provided between the center rotating rod and the rocking plate, and the torsion spring makes the half of the rocking plate close to the cam always have a tendency to rotate toward the side close to the cam.

[0026] By adopting the above technical solution, during the process of meshing the meshing wheel and the rack, the rotating shaft will rotate continuously, thereby driving the cam to rotate continuously; when the wheel surface on the cam that is shortest to the cam rotation center contacts the upper plate surface of the swing plate and then the wheel surface on the cam that is farthest from the cam rotation center contacts the upper plate surface of the swing plate, the plate surface of the swing plate close to the cam will change from a horizontal state to a tilted downward state; and when the wheel surface on the cam that is farthest from the cam rotation center contacts the upper plate surface of the swing plate and then the wheel surface on the cam that is shortest to the cam rotation center contacts the upper plate surface of the swing plate, under the torsion force of the torsion spring, the plate surface of the swing plate close to the cam will change from a tilted downward state to a tilted upward state; this repetition can realize the swinging motion of the swing plate, and achieve the effect of being more convenient to drive the swing plate to continuously swing motion during the movement of the moving block.

[0027] Optionally, a guide groove is provided on the edge of the upper plate surface of the swing plate, the length direction of the guide groove is consistent with the width direction of the swing plate, and a plurality of the guide grooves are arranged along the length direction of the swing plate.

[0028] By adopting the above technical solution, the provision of the guide groove can facilitate the water to flow down along the side of the swing plate, thereby improving the water's ability to guide the flow.

[0029] Optionally, a protective cover is provided on the supporting middle frame, and the protective cover covers the rotating motor.

[0030] By adopting the above technical solution, the provision of the protective cover can protect the rotating motor and prevent the rotating motor from being damaged by being soaked in water.

[0031] In summary, this application includes at least one of the following beneficial technical effects:

[0032] 1. When constructing slope greening on high-steep and dangerous rock belts, the first step is to build a flower bed. The flower bed is the foundation for planting plants. During the construction of the flower bed, temporary protective railings will be built in advance. The protective railings not only protect the flower bed, but also serve as a place for workers to hang their safety belts, ensuring safety for workers when working on high-steep and dangerous rocks, and also enabling workers to work on steep slopes. The debris generated during the construction process is directly discarded at the foot of the slope and subsequently processed in a unified manner. Through the above construction steps, the difficulty of greening construction on the slopes of high-steep and dangerous rock belts can be further reduced. In addition, the installation of flower beds, water reservoirs and irrigation sprinklers can further provide the green plants on the slope with planting conditions and subsequent growth conditions.

[0033] 2. Start the water pump. Water from the reservoir flows directly through the organ pipes into the sprinkler heads. The nozzles of the sprinkler heads face upward, and the water sprays all around the sprinkler heads. The moving block, driven synchronously by the threaded moving cylinder, moves within the straight track. Because the water supply pipes are retractable, the moving block allows water from the reservoir to flow through the organ pipes into the sprinkler heads, achieving a normal water supply effect.

[0034] 3. A branch pipe is connected to the organ pipe, which transports some water to the moving block and flows to the swing plate. When the moving block moves, the swing assembly drives the swing plate to swing continuously, so the water flowing onto the swing plate continuously flows down from both sides of the swing plate and flows onto the plants in the flower bed. This part of the water will irrigate the plants that are not irrigated by the sprinkler heads under the supporting side frames, thereby further increasing the coverage area of ​​the plants in the flower bed. BRIEF DESCRIPTION OF THE DRAWINGS

[0035] Figure 1 It is a schematic diagram of the overall structure of an embodiment of the present application;

[0036] Figure 2 is a partial cross-sectional view showing an irrigation sprinkler device according to an embodiment of the present application;

[0037] Figure 3 This is a partial cross-sectional view of an embodiment of the present application for illustrating a spray mechanism;

[0038] Figure 4 yes Figure 3 A partial enlarged schematic diagram of part A;

[0039] Figure 5 is an exploded schematic diagram for illustrating the connection relationship between the wobble plate and the central rotating rod according to an embodiment of the present application;

[0040] In the figure, 1. irrigation sprinkler device; 2. supporting middle frame; 21. anti-rotation groove; 22. protective cover; 3. supporting side frame; 4. spraying mechanism; 41. moving block; 42. organ pipe; 421. branch pipe; 43. sprinkler head; 5. driving mechanism; 51. rotating motor; 52. driving shaft; 53. driven shaft; 54. threaded moving assembly; 541. threaded moving cylinder; 542. limit block; 543. connecting rod; 6. straight rail; 61. rolling groove; 62. rack; 63. bar through hole; 64. center rotating rod; 7. rotating shaft; 71. roller; 72. meshing wheel; 8. rocking plate; 81. center bar hole; 82. guide groove; 9. cam; 10. torsion spring. DETAILED DESCRIPTION

[0041] The following is combined with Figure 1 -Attached Figure 5 , further details of this application are given.

[0042] A slope greening construction technology based on high steep dangerous rock belt, referring to Figure 1 , including the following steps:

[0043] Flower bed construction steps: Build a flower bed on the sidewalk. The flower bed is constructed using mortar masonry with an M7.5 mortar strength and an MU30 masonry strength. The bed must be free of weathering and cracks. The minimum thickness in the center of the flower bed should be no less than 200mm. Construction should be carried out using the mortar squeeze method, with a masonry strength of no less than 22kN / m³. Vertical joints and excessive horizontal joints should be avoided, and the quality should meet the requirements. The flower bed is 0.7m high and 0.3m wide. Depending on the width of the bridleway at different locations, it should be built 0.2-0.5m from the outside of the bridleway while maintaining overall linearity. Before construction, rebar is pre-installed below the center of the flower bed. HRB400 threaded bars are used, spaced 3m apart, with a diameter of 12mm, a depth of 0.3m, and an exposed length of 0.4m. 0.15m hooks are provided at the ends and integrated into the flower bed. A 2.5cm wide expansion joint should be set up every 15-20m and at the point where the terrain changes. The joint should be caulked with asphalt mastic to a depth of 150mm. Drain holes should be set up 0.1m from the ground. The drainage holes should be pre-buried with 110mm diameter PVC pipes and spaced 3m apart.

[0044] Construction and protection procedures: During construction, the outer side of the bridleway faces a steep slope. To protect construction workers, materials, and equipment and prevent accidents, a row of temporary guardrails will be erected outside the bridleway and the slope entrance. This serves to protect construction workers (with safety ropes) and subsequent maintenance personnel. The temporary guardrails should be erected so as not to obstruct construction and connect to the inner side of the slope to ensure overall stability. They must comply with the DBJ50 / T-123-2020 Technical Standard for Building Guardrails. The design life of the temporary guardrails is the construction period, followed by a three-year maintenance period. They will be removed once the plant survival rate reaches the required level. The temporary guardrails are constructed using a 1.2m high steel pipe frame with a 60mm diameter. In limestone areas, they are anchored to the ground using drilled grouting. In rocky areas, they are anchored using pre-buried C20 foundations with dimensions of 0.3×0.3×0.3m. Diagonal braces are installed every 10m, with a 60° inclination. A row of safety ropes is hung on the slope 1.5m above the bridleway, and the safety ropes are fixed to the slope with expansion bolts at intervals of 3m.

[0045] Gravel treatment steps: Due to the presence of many rubbles on the bridleway during the dangerous rock treatment, in order to facilitate the horizontal transfer of equipment and materials on the bridleway, the rubble on the bridleway needs to be removed. The removal method is to manually discard the rubble at the foot of the slope when the railing is built. In addition, on the west side of Area 1, there are many isolated boulders at the foot of the slope, which will be removed at this time. The removal method is to manually crush and remove them with a safety rope and discard them on the platform below. When manually throwing stones, the safety rope must be hung on the temporary protective railing;

[0046] Steps for planting green plants in the flower bed: Plant planting follows the principle of "trees → shrubs → grass", which is the order of plant selection under the best circumstances. At the same time, when selecting vegetation, it should be arranged in a staggered manner. When choosing trees, a certain number of shrubs and herbaceous plants should be matched with them, and when choosing shrubs, a certain number of herbaceous plants should be matched with them. In addition, in addition to considering the environmental adaptability of plants, the selection of plants must also consider the ecological balance and ecological coordination of local species, and must not cause ecological pollution; cultivate the seed soil on the inside of the flower bed, plant shrubs and vines in the flower bed, and plant trees at the foot of the slope. Workers must hang safety ropes throughout the planting process;

[0047] Irrigation system installation steps: set up a water reservoir on the top of the slope, set up an irrigation sprinkler device 1 in the flower bed, and connect the water reservoir and the irrigation sprinkler device 1;

[0048] Reference Figure 1 、 2 The irrigation sprinkler device 1 includes a supporting middle frame 2, a supporting side frame 3, a spraying mechanism 4 and a driving mechanism 5; the supporting middle frame 2 is installed in the flower bed, and the supporting side frames 3 are respectively provided with one at each end of the supporting middle frame 2; a straight rail 6 is provided on the supporting side frame 3, and the length direction of the straight rail 6 is consistent with the length direction of the flower bed, and the spraying mechanism 4 is slidably set on the straight rail 6; the driving mechanism 5 is installed on the supporting middle frame 2, and the driving mechanism 5 is used to drive the spraying mechanism 4 to move along the length direction of the straight rail 6; the spraying mechanism 4 is connected to the water reservoir at the top of the slope, that is, the water reservoir can directly transport water to the spraying mechanism 4.

[0049] The water in the water reservoir is directly transported to the spray mechanism 4, and then the water is sprayed around the supporting side frame 3 through the spray mechanism 4; since there are two supporting side frames 3, the water sprayed by the spray mechanisms 4 on the two supporting side frames 3 can cover most of the vegetation on the flower bed; and in addition, the two spray mechanisms 4 will move along the length direction of the straight rail 6 under the drive of the driving mechanism 5, so that the spray mechanism 4 can move while spraying, further increasing the coverage area of ​​the sprayed water.

[0050] Combine Figure 1 、 2The driving mechanism 5 includes a rotating motor 51, a driving shaft 52, a driven shaft 53 and a threaded moving assembly 54; the rotating motor 51 is mounted on the supporting middle frame 2, the driving shaft 52 is coaxially mounted on the output shaft of the rotating motor 51 and the end of the driving shaft 52 away from the rotating motor 51 is rotatably connected to the supporting middle frame 2, and the driven shaft 53 is rotatably arranged on the supporting middle frame 2, and the driving shaft 52 and the driven shaft 53 are meshed through gear transmission, that is, a gear is fixedly provided at a position of the driving shaft 52 close to the output shaft of the rotating motor 51, and a gear is also coaxially fixed on the driven shaft 53, and the two gears mesh with each other; the driving shaft 52, the driven shaft 53 and the straight rail 6 are all consistent in length direction; the threaded moving assembly 54 is respectively provided with one on the driving shaft 52 and the driven shaft 53, and the threaded moving assembly 54 automatically moves along the length direction of the driving shaft 52 / driven shaft 53 when the driving shaft 52 / driven shaft 53 rotates, and the threaded moving assembly 54 is connected to the spraying mechanism 4.

[0051] Combine Figure 1 、 2 Specifically, the threaded moving assembly 54 includes a threaded moving cylinder 541, a limit block 542 and a connecting rod 543; the driving shaft 52 and the driven shaft 53 are both threaded rods, and the two threaded moving cylinders 541 are respectively threadedly sleeved on the driving shaft 52 and the driven shaft 53; the limit block 542 is set on the threaded moving cylinder 541, and a rotation-stop groove 21 is set on the support middle frame 2 along the length direction of the support middle frame 2, and the limit block 542 is slidably inserted in the rotation-stop groove 21; one end of the connecting rod 543 is connected to the threaded moving cylinder 541, and the other end is connected to the threaded moving cylinder 541. One end is connected to the spray mechanism 4; two brackets are provided at the end of the driving shaft 52 and the driven shaft 53 away from the rotating motor 51, and the two brackets are mounted on the straight plate on the top of the supporting middle frame 2, and the two brackets are rotatably connected to the end of the driving shaft 52 and the driven shaft 53 respectively; in order to prevent the sprayed water from splashing onto the rotating motor 51, a protective cover 22 is provided on the supporting middle frame 2, and the protective cover 22 covers the rotating motor 51, and the gear meshing part on the driving shaft 52 and the driven shaft 53 is also in the protective cover 22.

[0052] After starting the rotating motor 51, the output shaft of the rotating motor 51 will drive the driving shaft 52 to rotate, and since the driving shaft 52 and the driven shaft 53 are transmitted through gear meshing, the driven shaft 53 will also rotate; and the two threaded moving cylinders 541 are respectively threadedly engaged with the driving shaft 52 and the driven shaft 53, so when the driving shaft 52 and the driven shaft 53 are both rotating, the threaded moving cylinder 541 will also rotate, and since the limit block 542 on the threaded moving cylinder 541 is inserted in the anti-rotation groove 21, the threaded moving cylinder 541 cannot rotate at this time, but will move along the length direction of the driving shaft 52 and the driven shaft 53; the movement of the threaded moving cylinder 541 will synchronously move the spray mechanism 4, thereby achieving the effect of driving the spray mechanism 4 to move more conveniently.

[0053] Combine Figure 3 、 4 The spray mechanism 4 includes a moving block 41, an organ pipe 42 and a spray head 43; the moving block 41 is slidably set on the straight rail 6, and the spray head 43 is installed on the top of the moving block 41, and the spray hole of the spray head 43 is vertically facing upward; one end of the organ pipe 42 is connected to the spray head 43, and the other end is connected to the water tank at the top of the slope through a water pump, and one end of the connecting rod 543 is connected to the threaded moving cylinder 541, and the other end is connected to the moving block 41, that is, the movement of the threaded moving cylinder 541 will drive the moving block 41 to move on the straight rail 6.

[0054] When the water pump is started, the water in the water reservoir will directly enter the sprinkler head 43 through the organ pipe 42. The spray hole of the sprinkler head 43 is vertically upward, and the sprayed water will be sprinkled around the sprinkler head 43, while the moving block 41 will be moved synchronously with the threaded moving cylinder 541 within the straight rail 6; and since the water supply pipeline is the organ pipe 42, which can be extended and retracted, the moving block 41 will allow the water in the water reservoir to enter the sprinkler head 43 normally through the organ pipe 42 during the movement, thereby achieving the effect of normal water supply.

[0055] Reference Figure 3 、 4 A rotating shaft 7 is rotatably provided on the moving block 41, and a roller 71 is coaxially provided at one end of the rotating shaft 7 and an engaging wheel 72 is provided at the other end; a rolling groove 61 is opened on the straight rail 6 along the length direction of the straight rail 6, and the roller 71 rolls with the rolling groove 61; a rack 62 is provided on the straight rail 6 along the length direction of the straight rail 6, and the engaging wheel 72 meshes with the rack 62; and in order to ensure the moving stability of the moving block 41 on the straight rail 6, a guide rod is also provided on the straight rail 6 along the length direction of the straight rail 6, an extension rod is coaxially extended on the rotating shaft 7, and a sliding sleeve is provided at the end of the extension rod, and the lower end of the sliding sleeve is provided with a notch, and the sliding sleeve is slidably sleeved on the upper half rod surface of the extension rod. With the cooperation of the guide rod and the sliding sleeve, the moving block 41 can move more stably on the straight rail 6.

[0056] When the moving block 41 moves along the length direction of the straight rail 6, the meshing wheel 72 at the end of the rotating shaft 7 will move along the length direction of the rack 62 while meshing with the rack 62, thereby driving the roller 71 to roll in the rolling groove 61, and then allowing the sliding sleeve to slide along the length direction of the guide rod. In this way, the moving block 41 can move stably on the straight rail 6 without being easily disengaged, thereby improving the movement stability of the moving block 41 on the straight rail 6.

[0057] Reference Figure 4, a strip-shaped through-hole 63 is opened on the straight rail 6, and a swing plate 8 is rotatably arranged on the strip-shaped through-hole 63 on the straight rail 6, and the swing plate 8 covers the strip-shaped through-hole 63 and the swing plate 8 is located directly below the moving block 41; a swing assembly is provided on the moving block 41, and the swing assembly is used to drive the swing plate 8 to swing back and forth when the moving block 41 moves along the length direction of the straight rail 6; the moving block 41 is hollow inside and has an open lower end, and a branch pipe 421 is also connected to the organ pipe 42, and one end of the branch pipe 421 extends into the moving block 41 and faces the swing plate 8; specifically, the swing assembly includes a cam 9, which is arranged on the rotating shaft 7; the middle of the strip-shaped through-hole 63 is along the strip A center rotating rod 64 is provided in the length direction of the shaped through hole 63, and a center bar hole 81 is opened in the middle of the swing plate 8 along the length direction of the swing plate 8. The center rotating rod 64 is rotated through the center bar hole 81 and is rotatably connected to the swing plate 8. The surface of the cam 9 is in contact with the upper plate surface of the swing plate 8 on the side of the center rotating rod 64; a torsion spring 10 is provided between the center rotating rod 64 and the swing plate 8, and the torsion spring 10 makes the half of the plate body of the swing plate 8 close to the cam 9 always have a tendency to rotate toward the side close to the cam 9; that is, the torsion spring 10 is sleeved on the center rotating rod 64, one end of the torsion spring 10 is connected to the rod wall of the center rotating rod 64, and the other end is connected to the inner hole wall of the center bar hole 81.

[0058] The organ pipe 42 is connected to a branch pipe 421, which transports part of the water into the moving block 41 and flows to the swing plate 8. In the process of meshing the meshing wheel 72 and the rack 62, the rotating shaft 7 will rotate continuously, thereby driving the cam 9 to rotate continuously; when the wheel surface of the cam 9 that is shortest from the rotation center of the cam 9 conflicts with the upper plate surface of the swing plate 8 and then to the wheel surface of the cam 9 that is farthest from the rotation center of the cam 9 conflicts with the upper plate surface of the swing plate 8, the plate surface of the swing plate 8 close to the cam 9 will change from a horizontal state to a tilted downward state; and when the wheel surface of the cam 9 that is farthest from the rotation center of the cam 9 During the period from the farthest wheel surface to the upper plate surface of the swing plate 8 and then to the wheel surface on the cam 9 with the shortest distance from the rotation center of the cam 9 to the upper plate surface of the swing plate 8, under the torsion of the torsion spring 10, the plate surface of the swing plate 8 close to the cam 9 will change from a tilted downward state to a tilted upward state; this repetition can realize the swinging motion of the swing plate 8, so the water flowing onto the swing plate 8 continuously flows down from both sides of the swing plate 8 and flows onto the plants in the flower bed; this part of the water will irrigate the plants that cannot be irrigated by the sprinkler head 43 under the supporting side frame 3, thereby further increasing the coverage area of ​​plant irrigation in the flower bed.

[0059] Combine Figure 5In order to allow water to flow smoothly down the edge of the swing plate 8 along the width direction of the swing plate 8, a guide groove 82 is opened on the edge of the upper plate surface of the swing plate 8. The length direction of the guide groove 82 is consistent with the width direction of the swing plate 8, and multiple guide grooves 82 are arranged along the length direction of the swing plate 8.

[0060] The implementation principle of the embodiment of the present application is: first start the water pump to transport the water in the water reservoir to the sprinkler head 43 through the organ pipe 42, so that the sprinkler head 43 sprays water vertically upward and sprinkles it from all sides of the sprinkler head 43; then start the rotating motor 51, so that the two sprinkler heads 43 move back and forth on both sides of the supporting middle frame 2, and part of the water in the organ pipe 42 will flow from the branch pipe 421 to the swing plate 8. Under the swinging motion of the swing plate 8, water will flow out successively under the straight rail 6 and on both sides of the swing plate 8, thereby increasing the coverage area of ​​​​vegetation irrigation in the flower bed.

[0061] The examples of this specific embodiment are all preferred embodiments of this application and are not intended to limit the scope of protection of this application. Identical components are represented by the same reference numerals. Therefore, any equivalent changes made based on the structure, shape, and principle of this application should be included in the scope of protection of this application.

Claims

1. A slope greening construction process based on high-steep dangerous rock belt, characterized in that: The following steps are involved: Flower bed construction steps: Build a flower bed on the slope of the horseway. The flower bed is made of mortar-made block stone. The mortar strength is M7.5 and the block stone strength is MU30. Plant reinforcement in the center and below the flower bed. Set a drainage hole 0.1m above the ground. Use a 110mm diameter PVC pipe to pre-buried the drainage hole. Construction protection steps: Set up a row of temporary protective railings on the outside of the bridleway and the slope entrance. The temporary protective railings are connected to the inside of the slope. The erection of temporary protective railings must meet the DBJ50 / T-123-2020 technical standards for building guardrails. They will be removed once the plant survival rate meets the requirements. Gravel processing steps: manually discard the crushed stones at the foot of the slope, and hang a safety rope when manually throwing the stones; Steps for planting green plants in the flower bed: cultivate the soil inside the flower bed, plant shrubs and vines in the flower bed, and plant trees at the foot of the slope. Workers hang safety ropes throughout the planting process. The steps of installing the irrigation system are as follows: a water reservoir is set on the top of the slope, an irrigation sprinkler device (1) is set in the flower bed, and the water reservoir and the irrigation sprinkler device (1) are connected; The irrigation spray device (1) comprises a supporting middle frame (2), a supporting side frame (3), a spray mechanism (4) and a driving mechanism (5); the supporting middle frame (2) is installed in the flower bed, and the supporting side frame (3) is provided at each end of the supporting middle frame (2); a straight rail (6) is provided on the supporting side frame (3), the length direction of the straight rail (6) is consistent with the length direction of the flower bed, and the spray mechanism (4) is slidably provided on the straight rail (6); the driving mechanism (5) is installed on the supporting middle frame (2), and the driving mechanism (5) is used to drive the spray mechanism (4) to move along the length direction of the straight rail (6); The spray mechanism (4) comprises a moving block (41), an organ pipe (42) and a spray head (43); the moving block (41) is slidably arranged on a straight rail (6); the spray head (43) is installed on the top of the moving block (41), and the spray hole of the spray head (43) is vertically upward; one end of the organ pipe (42) is connected to the spray head (43), and the other end is connected to a water reservoir at the top of the slope through a water pump; A rotating shaft (7) is rotatably provided on the moving block (41), a roller (71) is coaxially provided at one end of the rotating shaft (7), and a meshing wheel (72) is provided at the other end; a rolling groove (61) is provided on the straight rail (6) along the length direction of the straight rail (6), and the roller (71) and the rolling groove (61) are in rolling engagement; a rack (62) is provided on the straight rail (6) along the length direction of the straight rail (6), and the meshing wheel (72) meshes with the rack (62); A strip-shaped through hole (63) is provided on the straight rail (6); a swing plate (8) is rotatably provided on the strip-shaped through hole (63) on the straight rail (6); the swing plate (8) covers the strip-shaped through hole (63) and the swing plate (8) is located directly below the moving block (41); a swing assembly is provided on the moving block (41), and the swing assembly is used to drive the swing plate (8) to swing back and forth when the moving block (41) moves along the length direction of the straight rail (6); the interior of the moving block (41) is hollow and the lower end is open, and the organ pipe (42) is also connected to the branch pipe (421), and one end of the branch pipe (421) extends into the moving block (41) and faces the swing plate (8); The swing assembly comprises a cam (9), and the cam (9) is arranged on the rotating shaft (7); a central rotating rod (64) is arranged in the middle of the strip-shaped through hole (63) along the length direction of the strip-shaped through hole (63); a central strip hole (81) is opened in the middle of the swing plate (8) along the length direction of the swing plate (8); the central rotating rod (64) is rotated through the central strip hole (81) and is connected to the swing plate (8) in rotation; the surface of the cam (9) contacts the upper plate surface of the swing plate (8) on the side of the central rotating rod (64); a torsion spring (10) is arranged between the central rotating rod (64) and the swing plate (8), and the torsion spring (10) makes the half plate body of the swing plate (8) close to the cam (9) always have a tendency to rotate toward the side close to the cam (9).

2. The slope greening construction process based on high-steep and dangerous rock belt according to claim 1 is characterized in that: The driving mechanism (5) comprises a rotating motor (51), a driving shaft (52), a driven shaft (53) and a threaded moving assembly (54); the rotating motor (51) is mounted on the supporting middle frame (2); the driving shaft (52) is coaxially mounted on the output shaft of the rotating motor (51); and one end of the driving shaft (52) away from the rotating motor (51) is rotatably connected to the supporting middle frame (2); the driven shaft (53) is rotatably arranged on the supporting middle frame (2); the driving shaft (52) and the driven shaft (53) are driven by gear meshing, and the length directions of the driving shaft (52), the driven shaft (53) and the straight rail (6) are consistent; the threaded moving assembly (54) is respectively provided on the driving shaft (52) and the driven shaft (53), and the threaded moving assembly (54) automatically moves along the length direction of the driving shaft (52) / the driven shaft (53) when the driving shaft (52) / the driven shaft (53) rotates, and the threaded moving assembly (54) is connected to the spray mechanism (4).

3. The slope greening construction process based on high-steep and dangerous rock belt according to claim 2 is characterized in that: The threaded moving assembly (54) includes a threaded moving cylinder (541), a limiting block (542) and a connecting rod (543); the driving shaft (52) and the driven shaft (53) are both threaded rods, and the two threaded moving cylinders (541) are respectively threadedly sleeved on the driving shaft (52) and the driven shaft (53); the limiting block (542) is arranged on the threaded moving cylinder (541), and a rotation-stop groove (21) is provided on the supporting middle frame (2) along the length direction of the supporting middle frame (2), and the limiting block (542) is slidably inserted in the rotation-stop groove (21); one end of the connecting rod (543) is connected to the threaded moving cylinder (541), and the other end is connected to the spray mechanism (4).

4. The slope greening construction process based on high-steep and dangerous rock belt according to claim 1 is characterized in that: A guide groove (82) is provided on the edge of the upper plate surface of the swing plate (8), the length direction of the guide groove (82) is consistent with the width direction of the swing plate (8), and a plurality of the guide grooves (82) are arranged along the length direction of the swing plate (8).

5. The slope greening construction process based on high-steep and dangerous rock belt according to claim 2 is characterized in that: A protective cover (22) is provided on the supporting middle frame (2), and the protective cover (22) covers the rotating motor (51).

Citation Information

Patent Citations

  • Method for greening high precipitous rock slope

    CN101112157A

  • Highway subgrade protection slope

    CN214940241U

  • Sewage treatment agent spraying device for sewage treatment

    CN216779201U