A masonry wall construction method on both sides of the deformation joint position

By planting ribs at the bottom of the beam and installing cantilever plates, combined with concrete pouring and formwork support systems, the problem of the walls on both sides of the deformed joints cannot be constructed, the strength of the deformed joints and the smooth construction are achieved, ensuring the normal performance of the building functions of the walls.

CN116044049BActive Publication Date: 2025-07-11SHANGHAI BAOYE GRP CORP
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202310178164.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-02-28
Publication Date
2025-07-11
Estimated Expiration
2043-02-28

AI Technical Summary

Technical Problem

During the construction of the house, the walls and structural columns on both sides of the deformed joints cannot be constructed in the structural beam area, resulting in construction difficulties.

Method used

Plant the ribs at the bottom of the beam and set up cantilever plates to increase the length of the cantilever plates, increase the concrete strength level, and pour concrete through fine stone concrete pumping and manual vibration, combining the special pouring sequence of the formwork support system and structural columns to ensure the smooth progress of the construction.

Benefits of technology

The problem of the walls on both sides of the deformed joints cannot be constructed, ensuring the strength of the deformed joints and the smooth progress of the construction, and achieving the normal performance of the building functions of the walls.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116044049B_ABST
    Figure CN116044049B_ABST
Patent Text Reader

Abstract

The present invention relates to a method for masonry wall construction on both sides of the deformation joint position, which includes implanting steel bars at the bottom of the beam to make a cantilever slab; roughening the interface between the new and old concrete and applying neat cement slurry; making a formwork support system at the cantilever slab; pouring concrete for the cantilever slab; when the strength of the cantilever slab reaches the requirement for form removal, removing the formwork support system; first, masonry one side of the masonry wall up to the bottom of the ring beam, and pouring the structural columns and ring beam below the ring beam; then, masonry the other wall up to the bottom of the ring beam, and pouring the structural columns and ring beam below the ring beam; masonry the first wall up to the position of the cantilever slab, pour the structural column, and use small bricks for capping in the later stage; then, masonry the other wall up to the position of the cantilever slab, support the formwork of the structural column, and pour the structural column. The present invention adds a cantilever slab at the lower part of the beam and simultaneously conducts concrete pouring to ensure the strength of the deformation joint, overcoming the problem in the traditional construction method that it is impossible to construct due to the narrow space inside the deformation joint gap.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of building construction, and specifically to a method for masonry wall construction on both sides of the deformation joint position. Background Art

[0002] During the construction of building projects, there are various types of deformation joints, and masonry walls are used for filling and partitioning on both sides of the deformation joints. However, due to the small space of the deformation joint and the presence of structural beams on both sides of the deformation joint, it will cause problems that the walls and construction columns at the positions on both sides of the deformation joint cannot be constructed in the structural beam area. Summary of the Invention

[0003] The purpose of the present invention is to overcome the above defects and propose a method for masonry wall construction on both sides of the deformation joint position, so as to solve the problem that the masonry walls on both sides of the deformation joint cannot be constructed, and achieve the purpose that the masonry walls play their due building functions.

[0004] To achieve the above purpose, the present invention is implemented as follows:

[0005] A method for masonry wall construction on both sides of the deformation joint position, characterized by including

[0006] Step 1: Drill holes and insert reinforcement bars at the bottom of the beam to make a cantilever slab, and the length of the cantilever slab is the same as the top;

[0007] Step 2: Chisel the interface between the new and old concretes, chisel and clean, and apply neat cement slurry;

[0008] Step 3: Make a formwork support system at the cantilever slab;

[0009] Step 4: Pour the concrete of the cantilever slab, and the strength grade is one strength grade higher than that of the beam concrete;

[0010] Step 5: Use a small concrete pump hose to pour the concrete from the deformation joint, use fine aggregate concrete for pumping, and vibrate manually;

[0011] Step 6: When the strength of the cantilever slab reaches the formwork removal requirement, remove the formwork support system;

[0012] Step 7: First, masonry one side of the masonry wall to the bottom of the ring beam, and pour the construction column and the ring beam below the ring beam;

[0013] Step 8: Then, masonry the other wall to the bottom of the ring beam, and pour the construction column and the ring beam below the ring beam;

[0014] Step 9: Masonry the first wall to the position of the cantilever slab, pour the construction column, and use small bricks for capping later;

[0015] Step 10: Then build another wall up to the cantilever slab position, support the formwork of the construction column, and pour the construction column. The formwork of the construction column is reinforced in a way that it will not be removed later;

[0016] Among them,

[0017] The length of the planted bars is not less than 300 mm, and Class A bonding adhesive for planted bars is used;

[0018] The interface between the new and old concretes is chiseled and cleaned, and an interface agent is applied.

[0019] By adopting the above construction method, compared with the traditional construction plan, the cantilever slab at the lower part of the beam is added, and concrete pouring is carried out at the same time. In this way, the strength of the deformation joint is ensured, enabling it to achieve the designed function and overcoming the problem that construction cannot be carried out due to the narrow space inside the deformation joint gap in the traditional construction method. Description of the Drawings

[0020] Figure 1 It is a comparison diagram between this construction method and the traditional construction method.

[0021] Figure 2 It is a specific schematic diagram of the cantilever slab in this construction method.

[0022] Figure 3 It is a schematic diagram of the formwork system of the cantilever slab in this construction method. Detailed Embodiment

[0023] The present invention is further illustrated by the following specific embodiments.

[0024] As Figure 1 shown, a masonry wall construction method on both sides of the deformation joint position includes

[0025] Step 1: Conduct bar planting at the bottom of the beam to make a cantilever slab, and the length of the cantilever slab is the same as that at the top; (As Figure 2 )

[0026] Step 2: Conduct chiseling treatment on the interface between the new and old concretes, chisel and clean, and apply pure cement slurry;

[0027] Step 3: Make a formwork support system at the cantilever slab position (As Figure 3 )

[0028] Step 4: Pour the concrete of the cantilever slab, and the strength grade is increased by one grade compared with the beam concrete;

[0029] Step 5: When pouring the concrete, use a small ground pump hose to pour from the deformation joint, adopt fine aggregate concrete for pumping, and vibrate manually;

[0030] Step 6: When the strength of the cantilever slab reaches the form removal requirement, remove the formwork support system;

[0031] Step 7: First, build one side of the masonry wall up to the bottom of the ring beam, and pour the construction columns and the ring beam below the ring beam.

[0032] Step 8: Then, build the other wall up to the bottom of the ring beam, and pour the construction columns and the ring beam below the ring beam.

[0033] Step 9: Build the first wall up to the position of the cantilever slab, pour the construction column, and use small bricks for capping in the later stage.

[0034] Step 10: Build the other wall up to the position of the cantilever slab, support the formwork of the construction column, and pour the construction column. The formwork of the construction column is reinforced in a way that it will not be removed later.

[0035] Among them,

[0036] The length of the implanted steel bars is not less than 300 mm, and Class A implanting adhesive is used.

[0037] The interface between the new and old concretes is chiseled and cleaned, and an interface agent is applied.

[0038] The present invention adopts the above construction method. Compared with the traditional construction plan, a cantilever slab is added below the beam, and concrete pouring is carried out at the same time. In this way, the strength of the deformation joint is ensured, enabling it to achieve the designed function and overcoming the problem that it is impossible to construct due to the narrow space inside the deformation joint gap in the traditional construction method.

Claims

1. A masonry wall construction method on both sides of the deformation joint position, characterized in that: including Step 1: Drill holes for steel bars at the bottom of the beam and construct a cantilever slab with the same length as the top of the original structural slab; Step 2: Chip the interface between the new and old concrete, clean it after chipping, and apply a layer of neat cement slurry; Step 3: Build a formwork support system for the cantilever slab; Step 4: Pour the concrete for the cantilever slab with a strength grade one level higher than that of the beam concrete; Step 5: Use a small ground pump hose to pour the concrete from the expansion joint, adopt fine aggregate concrete for pumping, and manually vibrate; Step 6: When the strength of the cantilever slab reaches the requirement for formwork removal, remove the formwork support system; Step 7: First, build one side of the masonry wall up to the bottom of the ring beam, and pour the construction columns and ring beam below the ring beam; Step 8: Then, build the other wall up to the bottom of the ring beam, and pour the construction columns and ring beam below the ring beam; Step 9: Build the first wall up to the position of the cantilever slab, pour the construction column, and later use small bricks for capping; Step 10: Build the other wall up to the position of the cantilever slab, support the formwork of the construction column, and pour the construction column; the formwork of the construction column is reinforced in a way that it will not be removed later; Among them, the length of the drilled steel bars is not less than 300 mm, and A-grade anchoring adhesive is used; Chip and clean the interface between the new and old concrete, and apply an interface agent.

Citation Information

Patent Citations

  • External ring beam constructional column expansion joint structure and construction method thereof

    CN113737972A

  • Expension joint material for the concrete slab

    KR1019980037025A