By calculating and controlling the lifting times and target offset angle of the crane sling, the problem of erecting the spent fuel transport container when the vehicle cannot move freely is solved, ensuring the safe erection of the container and reducing safety risks.
Patent Information
- Application Number
- CN202310423895.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-04-19
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2043-04-19
AI Technical Summary
When the spent fuel transport container vehicle cannot move freely, the erection of the container cannot be effectively controlled, causing the sling to deviate from the angle, posing safety risks and lacking a solution.
By obtaining the distance between the rotating trunnion of the container and the lifting trunnion and the length of the crane sling, determine the lifting height of the crane sling and the moving distance of the transport vehicle, and calculate and control the lifting times and target deflection of the crane sling. Move the angle to ensure the safe erection of the container.
When the transport container vehicle cannot move freely, the erecting action of the spent fuel transport container can be controlled safely and reliably to avoid the phenomenon of skewed lifting and improve transportation safety.
Smart Images

Figure CN116374824B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of spent fuel post-processing, and in particular to a method, a device and equipment for determining erection control parameters of a container. Background Art
[0002] After the vehicle loaded with spent fuel transport containers arrives at the unloading hall of the spent fuel receiving and storage facility of the reprocessing plant, the container needs to be lifted from a horizontal state to a vertical state by a bridge crane and a vertical hoist, and then lifted into the cooling pit to cool the internal cavity of the container.
[0003] At present, the erection of spent fuel transport containers is based on the condition that the vehicle transporting the containers has the function of free movement, that is, the vehicle transporting the containers can move forward or backward according to the direction of the force;
[0004] When a spent fuel reprocessing plant is debugging a container, if the vehicle transporting the container does not have the free movement function due to a malfunction of the free movement function of the vehicle transporting the container, the container cannot be erected to a vertical state. If the container is forcibly erected, the bridge crane sling will deviate from the angle as the container is lifted, eventually causing the container to be tilted and lifted at an angle, posing a great safety risk. Therefore, when an emergency occurs and the vehicle transporting the container cannot move freely, there is no corresponding method to solve the problem of the spent fuel transport container being unable to be erected. Summary of the invention
[0005] The technical problem to be solved by the present invention is how to provide a method, device and equipment for determining the control parameters of the erection of a container. By determining the lifting times of the crane sling during the erection of the container and the target offset angle of the crane sling, the spent fuel transport container can be controlled to perform the erection action in the case of an emergency that causes the vehicle transporting the container to be unable to move freely.
[0006] In order to solve the above technical problems, the technical solution of the present invention is as follows:
[0007] A method for determining erection control parameters of a container, the method comprising:
[0008] Obtain the distance from the container's rotating trunnion to the lifting trunnion, and the length of the crane's sling;
[0009] Determining the lifting height of the crane sling according to the distance between the rotating trunnion and the lifting trunnion, the length of the crane sling and the preset offset angle of the crane sling;
[0010] Determining the moving distance of the transport vehicle according to the lifting height of the crane sling;
[0011] The lifting times of the crane sling in the process of controlling the erection of the container and the target offset angle of the crane sling are determined according to the lifting height of the crane sling and the moving distance of the transport vehicle.
[0012] Optionally, determining the lifting height of the crane sling according to the distance between the rotating trunnion and the lifting trunnion, the length of the crane sling and the preset offset angle of the crane sling comprises:
[0013] according to , determine the lifting height of the crane sling;
[0014] Where L is the moving distance of the transport vehicle, is the horizontal distance between the rotating trunnion of the container and the lifting trunnion before the i-th erection operation, i=1…n; n is the number of erection operations performed by the container from the horizontal state to the vertical state under the predetermined preset offset angle α; when i=1, ; h is the lifting height of the crane sling, is the length of the crane sling, is the distance between the rotating trunnion of the container and the lifting trunnion, The preset offset angle for the crane sling.
[0015] Optionally, determining the moving distance of the transport vehicle according to the lifting height of the crane sling includes:
[0016] according to , determine the moving distance of the transport vehicle;
[0017] Where L is the moving distance of the transport vehicle, is the length of the crane sling, is the distance between the rotating trunnion of the container and the lifting trunnion, The preset offset angle for the crane sling.
[0018] Optionally, determining the lifting times of the crane sling in the process of controlling the erection of the container and the target offset angle of the crane sling according to the lifting height of the crane sling and the moving distance of the transport vehicle includes:
[0019] Determine the horizontal distance between the rotating trunnion and the lifting trunnion according to the distance between the rotating trunnion and the lifting trunnion and the moving distance of the transport vehicle;
[0020] The horizontal distance between the rotating trunnion and the lifting trunnion of the container after the i-th container is erected is used as the distance between the rotating trunnion and the lifting trunnion before the i+1-th container is lifted, and the lifting height of the crane sling when the i+1-th container is lifted is determined;
[0021] Determining the lifting times of the crane sling in the process of controlling the erection of the container and the target offset angle of the crane sling according to the lifting height of the crane sling;
[0022] in, , n is the number of times the container is lifted.
[0023] Optionally, determining the horizontal distance between the rotating trunnion and the lifting trunnion according to the distance between the rotating trunnion and the lifting trunnion and the moving distance of the transport vehicle comprises:
[0024] according to , determine the horizontal distance between the rotating trunnion and the lifting trunnion;
[0025] in, It is the horizontal distance between the rotating trunnion and the lifting trunnion. is the distance between the rotating trunnion and the lifting trunnion, is the moving distance of the transport vehicle.
[0026] Optionally, determining the number of times the crane sling is lifted during the process of controlling the container erection and the target offset angle of the crane sling according to the lifting height of the crane sling includes:
[0027] When the lifting height of the crane rope is greater than or equal to the length of the crane rope, the erection action of the container is completed, and the lifting times of the crane rope in the process of controlling the erection of the container and the target offset angle of the crane rope are determined.
[0028] Optionally, before determining the horizontal distance between the rotating trunnion and the lifting trunnion according to the distance between the rotating trunnion and the lifting trunnion and the moving distance of the transport vehicle, the method further includes:
[0029] The transport vehicle is controlled to move according to the moving distance of the transport vehicle, so that the preset offset angle of the crane sling is returned to 0°.
[0030] The present invention also provides a spent fuel transport container erecting device, the device comprising:
[0031] An acquisition module, used for acquiring the distance between the rotating trunnion of the container and the lifting trunnion, and the length of the crane sling;
[0032] A processing module is used to determine the lifting height of the crane sling according to the distance between the rotating ear shaft and the lifting ear shaft, the length of the crane sling and the preset offset angle of the crane sling; determine the moving distance of the transport vehicle according to the lifting height of the crane sling; determine the number of lifting times of the crane sling in the process of controlling the erection of the container and the optimal offset angle of the crane sling according to the lifting height of the crane sling and the moving distance of the transport vehicle.
[0033] The present invention also provides a computing device, comprising: a processor, a memory, and a program or instruction stored in the memory and executable on the processor, wherein the program or instruction implements the steps of the above-mentioned method when executed by the processor.
[0034] The present invention also provides a readable storage medium, on which a program or instruction is stored, and when the program or instruction is executed by a processor, the steps of the method described above are implemented.
[0035] The above solution of the present invention includes at least the following beneficial effects:
[0036] The above scheme of the present invention obtains the distance between the rotating ear shaft and the lifting ear shaft of the spent fuel transport container; determines the lifting height of the crane rope according to the distance between the rotating ear shaft and the lifting ear shaft and the preset offset angle of the crane rope; determines the moving distance of the transport vehicle according to the lifting height of the crane rope; and controls the spent fuel transport container to be erected according to the lifting height of the crane rope and the moving distance of the transport vehicle. By determining the lifting times of the crane rope during the process of controlling the erection of the container and the target offset angle of the crane rope, the spent fuel transport container can be controlled to be erected in the case of an emergency that causes the vehicle carrying the container to be unable to move freely. BRIEF DESCRIPTION OF THE DRAWINGS
[0037] Figure 1 It is a flow chart of a method for determining erection control parameters of a container provided by an embodiment of the present invention;
[0038] Figure 2 is a schematic diagram of container erection control parameters according to an embodiment of the present invention;
[0039] Figure 3 is a schematic diagram of the working state of the angle detection device according to an embodiment of the present invention;
[0040] Figure 4 is a schematic diagram of a static state of an angle detection device according to an embodiment of the present invention;
[0041] Figure 5 It is a module block diagram of a device for determining erection control parameters of a container according to an embodiment of the present invention. DETAILED DESCRIPTION
[0042] The exemplary embodiments of the present disclosure will be described in more detail below with reference to the accompanying drawings. Although exemplary embodiments of the present invention are shown in the accompanying drawings, it should be understood that the present invention can be implemented in various forms and should not be limited by the embodiments set forth herein. On the contrary, these embodiments are provided to enable a more thorough understanding of the present invention and to fully convey the scope of the present invention to those skilled in the art.
[0043] like Figure 1 As shown, an embodiment of the present invention provides a method for determining erection control parameters of a container, the method comprising:
[0044] Step 11, obtaining the distance between the rotating trunnion of the container and the lifting trunnion, and the length of the crane sling;
[0045] Step 12, determining the lifting height of the crane sling according to the distance between the rotating trunnion and the lifting trunnion, the length of the crane sling and the preset offset angle of the crane sling;
[0046] Step 13, determining the moving distance of the transport vehicle according to the lifting height of the crane sling;
[0047] Step 14, determining the lifting times of the crane sling in the process of controlling the container erection and the target offset angle of the crane sling according to the lifting height of the crane sling and the moving distance of the transport vehicle.
[0048] In this embodiment of the present invention, the method for determining the control parameters for erecting the container can calculate the lifting height of the crane sling and the moving distance of the transport vehicle before each erection of the container, and erect the container according to the calculation result, so that the container is vertical to the ground, and the number of times the container is lifted is recorded. In this way, by determining the number of times the crane sling is lifted during the process of controlling the erection of the container and the target offset angle of the crane sling, the container can be controlled to be erected in the case of an emergency that causes the vehicle transporting the container to be unable to move freely, while ensuring the safety and reliability of the container erection process.
[0049] It should be noted that the container may include but is not limited to a spent fuel transport container;
[0050] The smaller the preset offset angle of the crane sling is set, the smoother the spent fuel transport container is erected, the higher the safety of the erection is, the more times the erection operation is required, and the lower the efficiency of the erection is. The preset offset angle of the crane sling can be specifically set to be less than or equal to 5°.
[0051] like Figure 2As shown, in an optional embodiment of the present invention, step 12 may include:
[0052] Step 121, according to , determine the lifting height of the crane sling;
[0053] Where L is the moving distance of the transport vehicle, is the horizontal distance between the rotating trunnion of the container and the lifting trunnion before the i-th erection operation, i=1…n; n is the number of erection operations performed by the container from the horizontal state to the vertical state under the predetermined preset offset angle α; when i=1, ; h is the lifting height of the crane sling, is the length of the crane sling, is the distance between the rotating trunnion of the container and the lifting trunnion, The preset offset angle for the crane sling.
[0054] In this embodiment, by , can determine the lifting height of the crane sling, the calculation is simple and easy to implement.
[0055] In another optional embodiment of the present invention, step 13 may include:
[0056] Step 131, according to , determine the moving distance of the transport vehicle;
[0057] Where L is the moving distance of the transport vehicle, is the length of the crane sling, is the distance between the rotating trunnion of the container and the lifting trunnion, The preset offset angle for the crane sling.
[0058] In this embodiment, by , can determine the moving distance of the transport vehicle, the calculation is simple and easy to implement.
[0059] In another optional embodiment of the present invention, step 14 may include:
[0060] Step 141, determining the horizontal distance between the rotating trunnion and the lifting trunnion according to the distance between the rotating trunnion and the lifting trunnion and the moving distance of the transport vehicle;
[0061] Step 142, taking the horizontal distance between the rotating trunnion and the lifting trunnion of the container after the i-th container is erected as the distance between the rotating trunnion and the lifting trunnion before the i+1-th container is lifted, and determining the lifting height of the crane sling when the i+1-th container is lifted;
[0062] Step 143, determining the number of times the crane sling is lifted during the process of controlling the container erection and the target offset angle of the crane sling according to the lifting height of the crane sling;
[0063] in, , n is the number of times the container is lifted.
[0064] In this embodiment, the horizontal distance between the rotating ear shaft and the lifting ear shaft will shorten each time the container is erected. Therefore, each time the container is controlled to be erected, the horizontal distance between the rotating ear shaft and the lifting ear shaft will change; the obtained horizontal distance between the rotating ear shaft and the lifting ear shaft is used as the distance between the rotating ear shaft and the lifting ear shaft when the container is lifted next time, and the lifting height of the crane sling when lifting the container a corresponding number of times is determined; and based on the lifting height, the container is controlled to perform a corresponding number of erection actions.
[0065] In this way, the container can be controlled to stand upright multiple times according to the determined lifting height of the crane sling and the moving distance of the transport vehicle, so that the container is gradually stood upright and finally the container is vertical to the ground.
[0066] In another optional embodiment of the present invention, step 141 may include:
[0067] Step 1411, according to , determine the horizontal distance between the rotating trunnion and the lifting trunnion;
[0068] in, It is the horizontal distance between the rotating trunnion and the lifting trunnion. is the distance between the rotating trunnion and the lifting trunnion, is the moving distance of the transport vehicle.
[0069] In this embodiment, the horizontal distance between the rotating ear shaft and the lifting ear shaft is equal to the distance between the rotating ear shaft and the lifting ear shaft minus the distance moved by the transport vehicle; based on the horizontal distance between the rotating ear shaft and the lifting ear shaft, the lifting height of the crane sling and the moving distance of the transport vehicle for the next time can be calculated.
[0070] In another optional embodiment of the present invention, step 143 may include:
[0071] Step 1431, when the lifting height of the crane sling is greater than or equal to the length of the crane sling, the erection action of the container is completed, and the lifting times of the crane sling in the process of controlling the erection of the container and the target offset angle of the crane sling are determined.
[0072] In this embodiment, when the lifting height of the crane sling is greater than or equal to the length of the crane sling, that is, When the crane sling cannot continue to lift, the container has reached the completion of erection. The number of times the transport vehicle moves is recorded. The number of times the transport vehicle moves can indicate the efficiency of the container erection. The preset offset angle of the crane sling can indicate the safety of the container erection. The operator can select the appropriate preset offset angle of the crane sling as the target offset angle of the crane sling according to the actual working conditions to perform the container erection operation.
[0073] In an optional specific embodiment of the present invention, the specific process of determining the target offset angle of the crane sling may include:
[0074] Step 1, presetting the preset offset angles of the crane sling to 5°, 4°, and 3° respectively;
[0075] Step 2, according to the distance between the rotating ear shaft and the lifting ear shaft of the container in the horizontal state, the length of the crane sling, and the preset offset angle of the crane sling, determine the corresponding lifting height of the crane sling and the moving distance of the transport vehicle when the preset offset angle of the crane sling is 5° according to the above steps, and record the number of lifting times of the crane sling;
[0076] When the preset offset angle of the crane sling is 4°, the corresponding lifting height of the crane sling and the moving distance of the transport vehicle are recorded, and the number of lifting times of the crane sling is recorded;
[0077] When the preset offset angle of the crane sling is 3°, the corresponding lifting height of the crane sling and the moving distance of the transport vehicle are recorded, and the number of lifting times of the crane sling is recorded;
[0078] Step 3, the operator can select an appropriate preset offset angle of the crane sling as the target offset angle of the crane sling according to the actual working conditions and comprehensively consider the preset offset angle of the crane sling and the number of hoisting times of the crane sling, and perform the erection operation on the container.
[0079] In another optional embodiment of the present invention, before step 141, the following steps may also be included:
[0080] Step 140, controlling the transport vehicle to move according to the moving distance of the transport vehicle so that the preset offset angle of the crane sling is returned to 0°.
[0081] In this embodiment, during the process of erecting the container, the crane rope will deviate. After the container is erected once, by controlling the transport vehicle to move according to the moving distance of the transport vehicle, the crane rope can be returned to the initial position without changing the position of the container, that is, the preset offset angle of the crane rope is returned to 0.
[0082] It should be noted that a Figure 3 and Figure 4 The angle detection device shown in the figure is composed of a weight and an angle scale. During the process of erecting the container, the offset angle of the current crane sling can be determined by the direction of the weight of the angle detection device.
[0083] Before erecting the container, fix the transport vehicle and control the crane sling to slowly lift the container. Figure 3 As shown, when the weight of the angle detection device points to a value close to the offset angle limit, that is, the preset offset angle α of the crane sling, the container erection action is stopped and the transport vehicle is controlled to move along the track according to the moving distance of the transport vehicle, as shown in FIG. Figure 4 As shown, when the weight of the angle detection device coincides with the reference line, it means that the offset angle of the crane sling is 0°, and the crane sling returns to the initial position, the transport vehicle is stopped from moving and the vehicle is fixed again. The crane sling is controlled to rise, and when the angle detection device on the crane boom points to an angle with the reference line again and approaches the angle limit, the crane sling is controlled to stop rising. Follow the previous steps in sequence until the container completes the vertical action, that is, the container is flipped to a completely vertical state with the ground.
[0084] In an optional specific embodiment of the present invention, the specific implementation process of the method for determining the erection control parameters of the container may include:
[0085] Step 1: Obtain the distance between the rotating trunnion and the lifting trunnion when the container is in a horizontal state , and the length of the crane sling ;
[0086] Step 2, determining the lifting height of the crane sling according to the distance between the rotating trunnion and the lifting trunnion, the length of the crane sling and the preset offset angle of the crane sling;
[0087] Step 21, according to , determine the lifting height of the crane sling;
[0088] Where L is the moving distance of the transport vehicle, is the horizontal distance between the rotating trunnion of the container and the lifting trunnion before the i-th erection operation, i=1…n; n is the number of erection operations performed by the container from the horizontal state to the vertical state under the predetermined preset offset angle α; when i=1, ; h is the lifting height of the crane sling, is the length of the crane sling, is the distance between the rotating trunnion of the container and the lifting trunnion, The preset offset angle for the crane sling;
[0089] Step 3, determining the moving distance of the transport vehicle according to the lifting height of the crane sling;
[0090] Step 31, according to , determine the moving distance of the transport vehicle;
[0091] Where L is the moving distance of the transport vehicle, is the length of the crane sling, is the distance between the rotating trunnion of the container and the lifting trunnion, The preset offset angle for the crane sling;
[0092] Step 4: record the lifting height h of the crane sling obtained in step 21 as ; The moving distance L of the transport vehicle in step 31 is recorded as ;
[0093] Step 5, according to the lifting height of the crane sling Control the lifting of the container according to the moving distance of the transport vehicle Control the movement of the transport vehicle; make the crane sling offset angle return to 0°; here the crane sling offset angle can be verified by the angle detection device;
[0094] Step 6: Determine the horizontal distance between the rotating ear shaft and the lifting ear shaft according to the distance between the rotating ear shaft and the lifting ear shaft and the moving distance of the transport vehicle. ;
[0095] Step 61, according to , determine the horizontal distance between the rotating trunnion and the lifting trunnion;
[0096] in, It is the horizontal distance between the rotating trunnion and the lifting trunnion. is the distance between the rotating trunnion and the lifting trunnion, is the moving distance of the transport vehicle;
[0097] Step 7: Horizontal distance between the rotating trunnion and the lifting trunnion , as the distance between the rotating trunnion and the lifting trunnion when lifting the container for the second time, to determine the lifting height of the crane sling when lifting the container for the second time;
[0098] Step 8, repeating steps 3 to 7 until it is determined that the lifting height of the crane sling is greater than or equal to the length of the crane sling, then the container is erected and the number of times the transport vehicle moves is recorded.
[0099] Step 10, according to the needs of actual working conditions, comprehensively considering the preset offset angle of the crane sling and the moving distance of the transport vehicle, selecting an appropriate preset offset angle of the crane sling as the target offset angle of the crane sling, and performing an erection operation on the container.
[0100] In the above-mentioned embodiment of the present invention, through the method for determining the control parameters for erecting the container, after determining the offset angle α, the lifting height h of the crane sling each time, the moving distance L of the transport vehicle, and the number of times n the container is controlled to be lifted can be calculated; the method for determining the control parameters for erecting the container is simple and easy to implement. By determining the number of times the crane sling is lifted during the process of controlling the erection of the container and the target offset angle of the crane sling, the container can be controlled to be erected in the event of an emergency that causes the vehicle transporting the container to be unable to move freely.
[0101] like Figure 5 As shown, an embodiment of the present invention further provides a device 50 for determining erection control parameters of a container, the device 50 comprising:
[0102] An acquisition module 51 is used to acquire the distance between the rotating trunnion of the container and the lifting trunnion, and the length of the crane sling;
[0103] The processing module 52 is used to determine the lifting height of the crane rope according to the distance between the rotating ear shaft and the lifting ear shaft, the length of the crane rope and the preset offset angle of the crane rope; determine the moving distance of the transport vehicle according to the lifting height of the crane rope; determine the number of lifting times of the crane rope in the process of controlling the erection of the container and the target offset angle of the crane rope according to the lifting height of the crane rope and the moving distance of the transport vehicle.
[0104] Optionally, determining the lifting height of the crane sling according to the distance between the rotating trunnion and the lifting trunnion, the length of the crane sling and the preset offset angle of the crane sling comprises:
[0105] according to , determine the lifting height of the crane sling;
[0106] Where L is the moving distance of the transport vehicle, is the horizontal distance between the rotating trunnion of the container and the lifting trunnion before the i-th erection operation, i=1…n; n is the number of erection operations performed by the container from the horizontal state to the vertical state under the predetermined preset offset angle α; when i=1, ; h is the lifting height of the crane sling, is the length of the crane sling, is the distance between the rotating trunnion of the container and the lifting trunnion, The preset offset angle for the crane sling.
[0107] Optionally, determining the moving distance of the transport vehicle according to the lifting height of the crane sling includes:
[0108] according to , determine the moving distance of the transport vehicle;
[0109] Where L is the moving distance of the transport vehicle, is the length of the crane sling, is the distance between the rotating trunnion of the container and the lifting trunnion, The preset offset angle for the crane sling.
[0110] Optionally, determining the lifting times of the crane sling in the process of controlling the erection of the container and the target offset angle of the crane sling according to the lifting height of the crane sling and the moving distance of the transport vehicle includes:
[0111] Determine the horizontal distance between the rotating trunnion and the lifting trunnion according to the distance between the rotating trunnion and the lifting trunnion and the moving distance of the transport vehicle;
[0112] The horizontal distance between the rotating trunnion and the lifting trunnion of the container after the i-th container is erected is used as the distance between the rotating trunnion and the lifting trunnion before the i+1-th container is lifted, and the lifting height of the crane sling when the i+1-th container is lifted is determined;
[0113] Determining the lifting times of the crane sling in the process of controlling the erection of the container and the target offset angle of the crane sling according to the lifting height of the crane sling;
[0114] in, , n is the number of times the container is lifted.
[0115] Optionally, determining the horizontal distance between the rotating trunnion and the lifting trunnion according to the distance between the rotating trunnion and the lifting trunnion and the moving distance of the transport vehicle comprises:
[0116] according to , determine the horizontal distance between the rotating trunnion and the lifting trunnion;
[0117] in, It is the horizontal distance between the rotating trunnion and the lifting trunnion. is the distance between the rotating trunnion and the lifting trunnion, is the moving distance of the transport vehicle.
[0118] Optionally, determining the number of times the crane sling is lifted during the process of controlling the container erection and the target offset angle of the crane sling according to the lifting height of the crane sling includes:
[0119] When the lifting height of the crane rope is greater than or equal to the length of the crane rope, the erection action of the container is completed, and the lifting times of the crane rope in the process of controlling the erection of the container and the target offset angle of the crane rope are determined.
[0120] Optionally, before determining the horizontal distance between the rotating trunnion and the lifting trunnion according to the distance between the rotating trunnion and the lifting trunnion and the moving distance of the transport vehicle, the processing module 52 may also be used to:
[0121] The transport vehicle is controlled to move according to the moving distance of the transport vehicle, so that the preset offset angle of the crane sling is returned to 0°.
[0122] It should be noted that the device is a device corresponding to the above method, and all implementation methods in the above method embodiments are applicable to the embodiments of the device and can achieve the same technical effects.
[0123] The embodiment of the present invention further provides a computing device, comprising: a processor, a memory storing a computer program, wherein when the computer program is executed by the processor, the method described above is executed. All implementations in the above method embodiment are applicable to this embodiment and can achieve the same technical effect.
[0124] The embodiment of the present invention further provides a computer-readable storage medium, including instructions, which, when executed on a computer, enable the computer to execute the method described above. All implementations in the above method embodiment are applicable to this embodiment and can achieve the same technical effect.
[0125] Those skilled in the art will appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, or a combination of computer software and electronic hardware. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professional and technical personnel can use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of the present invention.
[0126] Those skilled in the art can clearly understand that, for the convenience and brevity of description, the specific working processes of the systems, devices and units described above can refer to the corresponding processes in the aforementioned method embodiments and will not be repeated here.
[0127] In the embodiments provided by the present invention, it should be understood that the disclosed devices and methods can be implemented in other ways. For example, the device embodiments described above are only schematic. For example, the division of the units is only a logical function division. There may be other division methods in actual implementation, such as multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some interfaces, indirect coupling or communication connection of devices or units, which can be electrical, mechanical or other forms.
[0128] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.
[0129] In addition, each functional unit in each embodiment of the present invention may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit.
[0130] If the functions are implemented in the form of software functional units and sold or used as independent products, they can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present invention, or the part that contributes to the prior art, or the part of the technical solution, can be embodied in the form of a software product. The computer software product is stored in a storage medium, including several instructions for a computer device (which can be a personal computer, server, or network device, etc.) to perform all or part of the steps of the method described in each embodiment of the present invention. The aforementioned storage medium includes: various media that can store program codes, such as USB flash drives, mobile hard disks, ROM, RAM, magnetic disks, or optical disks.
[0131] In addition, it should be pointed out that in the apparatus and method of the present invention, it is obvious that each component or each step can be decomposed and / or recombined. These decompositions and / or recombinations should be regarded as equivalent schemes of the present invention. Moreover, the steps of performing the above series of processing can naturally be performed in chronological order according to the order of description, but it is not necessary to perform them in chronological order, and some steps can be performed in parallel or independently of each other. For those of ordinary skill in the art, it is understandable that all or any steps or components of the method and apparatus of the present invention can be implemented in hardware, firmware, software or a combination thereof in any computing device (including processors, storage media, etc.) or a network of computing devices, which can be achieved by those of ordinary skill in the art using their basic programming skills after reading the description of the present invention.
[0132] Therefore, the purpose of the present invention can also be achieved by running a program or a group of programs on any computing device. The computing device can be a well-known general device. Therefore, the purpose of the present invention can also be achieved by simply providing a program product containing a program code that implements the method or device. That is to say, such a program product also constitutes the present invention, and the storage medium storing such a program product also constitutes the present invention. Obviously, the storage medium can be any well-known storage medium or any storage medium developed in the future. It should also be pointed out that in the device and method of the present invention, it is obvious that each component or each step can be decomposed and / or recombined. These decompositions and / or recombinations should be regarded as equivalent schemes of the present invention. In addition, the steps of performing the above-mentioned series of processing can naturally be performed in chronological order according to the order of description, but it is not necessary to perform them in chronological order. Some steps can be performed in parallel or independently of each other.
[0133] The above is a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principles of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.
Claims
1. A method for determining the erection control parameters of a container, characterized in that: The method comprises: Obtain the distance from the container's rotating trunnion to the lifting trunnion, and the length of the crane's sling; Determining the lifting height of the crane sling according to the distance between the rotating trunnion and the lifting trunnion, the length of the crane sling and the preset offset angle of the crane sling; Determining the moving distance of the transport vehicle according to the lifting height of the crane sling; Determining the lifting times of the crane sling during the process of controlling the erection of the container and the target offset angle of the crane sling according to the lifting height of the crane sling and the moving distance of the transport vehicle; Wherein, determining the lifting height of the crane sling according to the distance between the rotating trunnion and the lifting trunnion, the length of the crane sling and the preset offset angle of the crane sling comprises: according to , determine the lifting height of the crane sling; Where L is the moving distance of the transport vehicle, is the horizontal distance between the rotating trunnion of the container and the lifting trunnion before the i-th erection operation, i=1…n; n is the number of erection operations performed by the container from the horizontal state to the vertical state under the predetermined preset offset angle α; when i=1, ; h is the lifting height of the crane sling, is the length of the crane sling, is the distance between the rotating trunnion of the container and the lifting trunnion, The preset offset angle for the crane sling; Wherein, determining the moving distance of the transport vehicle according to the lifting height of the crane sling comprises: according to , determine the moving distance of the transport vehicle; Where L is the moving distance of the transport vehicle, is the length of the crane sling, is the distance between the rotating trunnion of the container and the lifting trunnion, The preset offset angle for the crane sling; According to the lifting height of the crane sling and the moving distance of the transport vehicle, the lifting times of the crane sling in the process of controlling the erection of the container and the target offset angle of the crane sling are determined, including: Determine the horizontal distance between the rotating trunnion and the lifting trunnion according to the distance between the rotating trunnion and the lifting trunnion and the moving distance of the transport vehicle; The horizontal distance between the rotating trunnion and the lifting trunnion of the container after the i-th container is erected is used as the distance between the rotating trunnion and the lifting trunnion before the i+1-th container is lifted, and the lifting height of the crane sling when the i+1-th container is lifted is determined; According to the lifting height of the crane sling, determining the lifting times of the crane sling in the process of controlling the erection of the container and the target offset angle of the crane sling, wherein the target offset angle is one of a plurality of preset offset angles, and the plurality of preset offset angles are 5°, 4°, and 3° respectively; Wherein, according to the lifting height of the crane rope, determining the lifting times of the crane rope in the process of controlling the erection of the container and the target offset angle of the crane rope, including: when the lifting height of the crane rope is greater than or equal to the length of the crane rope, completing the erection action of the container, determining the lifting times of the crane rope in the process of controlling the erection of the container and the target offset angle of the crane rope; Wherein, before determining the horizontal distance between the rotating trunnion and the lifting trunnion according to the distance between the rotating trunnion and the lifting trunnion and the moving distance of the transport vehicle, the method further includes: The transport vehicle is controlled to move according to the moving distance of the transport vehicle, so that the preset offset angle of the crane sling is returned to 0°.
2. A device for determining the erection control parameters of a container, characterized in that: The device comprises: An acquisition module, used for acquiring the distance between the rotating trunnion of the container and the lifting trunnion, and the length of the crane sling; A processing module, configured to determine the lifting height of the crane rope according to the distance between the rotating ear shaft and the lifting ear shaft, the length of the crane rope and the preset offset angle of the crane rope; determine the moving distance of the transport vehicle according to the lifting height of the crane rope; determine the number of lifting times of the crane rope in the process of controlling the erection of the container and the target offset angle of the crane rope according to the lifting height of the crane rope and the moving distance of the transport vehicle; Wherein, determining the lifting height of the crane sling according to the distance between the rotating trunnion and the lifting trunnion, the length of the crane sling and the preset offset angle of the crane sling comprises: according to , determine the lifting height of the crane sling; Where L is the moving distance of the transport vehicle, is the horizontal distance between the rotating trunnion of the container and the lifting trunnion before the i-th erection operation, i=1…n; n is the number of erection operations performed by the container from the horizontal state to the vertical state under the predetermined preset offset angle α; when i=1, ; h is the lifting height of the crane sling, is the length of the crane sling, is the distance between the rotating trunnion of the container and the lifting trunnion, The preset offset angle for the crane sling; Wherein, determining the moving distance of the transport vehicle according to the lifting height of the crane sling comprises: according to , determine the moving distance of the transport vehicle; Where L is the moving distance of the transport vehicle, is the length of the crane sling, is the distance between the rotating trunnion of the container and the lifting trunnion, The preset offset angle for the crane sling; According to the lifting height of the crane sling and the moving distance of the transport vehicle, the lifting times of the crane sling in the process of controlling the erection of the container and the target offset angle of the crane sling are determined, including: Determine the horizontal distance between the rotating trunnion and the lifting trunnion according to the distance between the rotating trunnion and the lifting trunnion and the moving distance of the transport vehicle; The horizontal distance between the rotating trunnion and the lifting trunnion of the container after the i-th container is erected is used as the distance between the rotating trunnion and the lifting trunnion before the i+1-th container is lifted, and the lifting height of the crane sling when the i+1-th container is lifted is determined; According to the lifting height of the crane sling, determining the lifting times of the crane sling in the process of controlling the erection of the container and the target offset angle of the crane sling, wherein the target offset angle is one of a plurality of preset offset angles, and the plurality of preset offset angles are 5°, 4°, and 3° respectively; Wherein, according to the lifting height of the crane rope, determining the lifting times of the crane rope in the process of controlling the erection of the container and the target offset angle of the crane rope, including: when the lifting height of the crane rope is greater than or equal to the length of the crane rope, completing the erection action of the container, determining the lifting times of the crane rope in the process of controlling the erection of the container and the target offset angle of the crane rope; Wherein, before determining the horizontal distance between the rotating trunnion and the lifting trunnion according to the distance between the rotating trunnion and the lifting trunnion and the moving distance of the transport vehicle, the method further includes: The transport vehicle is controlled to move according to the moving distance of the transport vehicle, so that the preset offset angle of the crane sling is returned to 0°.
3. A computing device, characterized in that: include: A processor, a memory, and a program or instruction stored in the memory and executable on the processor, wherein the program or instruction implements the steps of the method according to claim 1 when executed by the processor.
4. A readable storage medium, characterized in that: The readable storage medium stores a program or instruction, and when the program or instruction is executed by a processor, the steps of the method according to claim 1 are implemented.