A system for hanging ceramic tiles

The design of the inclined groove and clamping parts enables a stable connection of the ceramic bricks, solving the problems of low efficiency and high cost of the existing ceramic brick connection system, improving construction safety and installation efficiency, and reducing construction difficulty and cost.

CN116427595BActive Publication Date: 2026-01-09HAOHENG (FUJIAN) BUILDING MATERIALS TECH CO LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202310074652.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-01-30
Publication Date
2026-01-09
Estimated Expiration
2043-01-30

AI Technical Summary

Technical Problem

Existing ceramic brick mounting systems are inefficient and costly during installation and dismantling, especially posing safety risks during high-altitude operations. Furthermore, the complex mounting structure increases construction difficulty and cost.

Method used

The design employs a slanted groove and clamping parts. Slanted grooves are made on the ceramic bricks, and clamping parts on the mounting parts are used for vertical or horizontal insertion and engagement to form a fixation with at least two support points. This simplifies the installation process and fixes the ceramic bricks through mechanical hooking, clamping, and bonding, avoiding the use of bolts and adhesives.

Benefits of technology

It improves installation and disassembly speed, reduces overall cost, enhances safety, simplifies construction process, and is suitable for various installation surfaces, especially for high-altitude operations where there is no need to stay for a long time to tighten screws.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116427595B_ABST
    Figure CN116427595B_ABST
Patent Text Reader

Abstract

The application discloses a kind of ceramic brick hanging system, fixedly connected on mounting surface, comprising: locking in mounting surface on mounting piece, mounting piece includes the several clamping pieces that extend upwards from mounting piece top surface, clamping piece is integrally formed with mounting piece;Hanging in mounting piece on ceramic brick, ceramic brick and the side surface of ceramic brick mutually adhere, ceramic brick is provided with a inclined groove, inclined groove is hung in clamping piece;Inclined groove includes the first installation part that is provided in the side away from ceramic brick finish, second installation part is arranged from first installation part to the inside of ceramic brick;Clamping piece includes the first clamping part that is arranged and extends upwards from mounting piece, first clamping part is abutted with first installation part, second clamping part is arranged and extends from first clamping part to the inside of second installation part, worker only needs to fix locking mounting piece first when installing, then stack layer upon layer ceramic brick can, the speed of installation and disassembly can be greatly accelerated.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The present application relates to a kind of building brick installation system, in particular to a kind of ceramic brick hanging system. BACKGROUND

[0002] Ceramic brick is usually made of high-quality clay and purple clay and other raw materials, compared with traditional clay brick, ceramic brick is more delicate, color is more stable, and the line is beautiful, which is a new energy-saving building curtain wall material, pollution-free, green and environmental protection, light in weight, high strength, corrosion-resistant, good anti-seismic and anti-freezing performance, sound insulation and noise reduction, meets the national building energy-saving requirements, and combines traditional ceramic culture with modern architecture skillfully and perfectly.

[0003] When forming a curtain wall, a slot is usually opened in the back of the ceramic brick, then a hanging piece is clamped in the slot of the ceramic brick, then the hanging piece is hung on a connecting piece, and finally the connecting piece is fixed on the keel, thereby completing the process of rapid installation.

[0004] However, the existing slotting method either directly opens a deep slot on the inside of the ceramic brick to improve the hanging effect, or directly sets a complex hanging structure of various styles to improve the hanging force by stacking the hanging structure. If a deep slot is directly opened for fixing and matching, although the hanging force is sufficient, the solid part of the brick body is thinned, the thickness of the brick body is thinned, and the phenomenon of damage or even breakage is easy to occur. If a large number of hanging structures are connected, a more complex process is required in the process of installation and disassembly and replacement. If the installation and replacement position is a high point, the worker is difficult to work in the air, the installation efficiency is low, and a large number of hanging structures will also lead to an increase in the installation cost of the whole curtain wall, which is not convenient for the construction party to control the cost.

[0005] Therefore, the present application aims to provide a low-cost ceramic brick hanging system with a simple hanging structure and stable hanging force. SUMMARY

[0006] The present application provides a ceramic brick hanging system, which can effectively solve the above problems.

[0007] The present application is implemented as follows:

[0008] A ceramic brick hanging system is fixed to an installation surface, comprising:

[0009] A mounting piece is locked to the installation surface, the mounting piece comprises a plurality of clamping pieces extending upward from the top surface of the mounting piece, and the clamping pieces are integrally formed with the mounting piece;

[0010] A ceramic brick is hung on the mounting piece, the ceramic bricks are mutually attached to the side surfaces of the ceramic bricks, a slant slot is formed on the ceramic brick, and the slant slot is hung on the clamping piece.

[0011] The chute comprises a first mounting part opened on a side away from the ceramic tile facing, and a second mounting part extending from the first mounting part to the interior of the ceramic tile;

[0012] The clamping member comprises a first clamping part extending upward from the mounting member, the first clamping part abutting against the first mounting part, and a second clamping part extending from the first clamping part to the interior of the second mounting part.

[0013] As a further improvement, the first mounting part is obliquely arranged, the second mounting part is communicated with the first mounting part and is flush with the horizontal plane, the first clamping part is clamped on the interior side of the first mounting part, and the second clamping part is clamped on the interior side of the second mounting part.

[0014] As a further improvement, the clamping member further comprises a third clamping part extending from the second clamping part to the interior of the second mounting part.

[0015] As a further improvement, one end of the interior side of the first mounting part is a straight line, the other end of the interior side of the first mounting part is an oblique line, the second mounting part is communicated with the first mounting part and is flush with the horizontal plane, the first clamping part is perpendicular to the mounting member and abuts on the straight line of the interior side of the first mounting part, the second clamping part is perpendicular to the first clamping part, the third clamping part is obliquely upward from the second clamping part, or the third clamping part is obliquely downward from the second clamping part.

[0016] As a further improvement, one end of the interior side of the first mounting part is a straight line, the other end of the interior side of the first mounting part is an oblique line, the second mounting part is communicated with the first mounting part and is flush with the horizontal plane, the first clamping part is perpendicular to the mounting member and abuts on the straight line of the interior side of the first mounting part, the second clamping part is obliquely downward from the first clamping part, and the third clamping part is obliquely upward from the first clamping part.

[0017] As a further improvement, one end of the interior side of the first mounting part is a straight line, the other end of the interior side of the first mounting part is an oblique line, the second mounting part is communicated with the first mounting part and is flush with the horizontal plane, the first clamping part is perpendicular to the mounting member and abuts on the straight line of the interior side of the first mounting part, the second clamping part is obliquely downward from the first clamping part, and the third clamping part is obliquely downward from the first clamping part.

[0018] As a further improvement, the first mounting part is obliquely arranged, the second mounting part is obliquely arranged downward / upward from the first mounting part, the first clamping part is clamped on the inner side of the first mounting part, the second clamping part is connected with the first clamping part and is flush with the horizontal plane, and the third clamping part is connected below / above the second clamping part.

[0019] As a further improvement, the first mounting part is obliquely arranged, the second mounting part is obliquely arranged downward / upward from the first mounting part, the first clamping part is clamped on the inner side of the first mounting part, the second clamping part is obliquely arranged downward from the first clamping part, and the third clamping part is connected below / above the second clamping part.

[0020] As a further improvement, the mounting member is a C-shaped steel, a plurality of clamping members are uniformly and equidistantly arranged on the C-shaped steel, the C-shaped steel is locked on a keel frame, and the keel frame is locked on the mounting surface.

[0021] As a further improvement, the mounting member is a mounting bottom plate, a plurality of clamping members are arranged on the mounting bottom plate, the mounting bottom plate is locked on the mounting surface, or the mounting bottom plate is locked on a keel frame, and the keel frame is locked on the mounting surface.

[0022] The present application has the following beneficial effects:

[0023] The present application has the following beneficial effects: BRIEF DESCRIPTION OF DRAWINGS

[0024] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the following will briefly introduce the drawings needed to be used in the embodiments. It should be understood that the following drawings only show some embodiments of the present application, and therefore should not be regarded as a limitation to the scope. For those skilled in the art, other related drawings can also be obtained without creative labor on the basis of these drawings.

[0025] Figure 1is a structural schematic diagram of a ceramic brick hanging system provided by the present application (first perspective view).

[0026] Figure 2 is a structural schematic diagram of a ceramic brick hanging system provided by the present application (second perspective view).

[0027] Figure 3 is a structural schematic diagram of a mounting base plate provided by the present application.

[0028] Figure 4 is a front view structural schematic diagram of a ceramic brick hanging system provided by the fourth embodiment of the present application.

[0029] Figure 5 is a front view structural schematic diagram of a ceramic brick provided by the first to fourth embodiments of the present application.

[0030] Figure 6 is a front view structural schematic diagram of a ceramic brick provided by the fifth to sixth embodiments of the present application (second mounting portion is downwardly inclined).

[0031] Figure 7 is a front view structural schematic diagram of a ceramic brick provided by the fifth to sixth embodiments of the present application (second mounting portion is upwardly inclined).

[0032] Figure 8 is a structural schematic diagram of a clamping member provided by the first embodiment of the present application.

[0033] Figure 9 is a structural schematic diagram of a clamping member provided by the second embodiment of the present application (third clamping portion is downwardly inclined).

[0034] Figure 10 is a structural schematic diagram of a clamping member provided by the second embodiment of the present application (third clamping portion is upwardly inclined).

[0035] Figure 11 is a structural schematic diagram of a clamping member provided by the third embodiment of the present application.

[0036] Figure 12 is a structural schematic diagram of a clamping member provided by the fourth embodiment of the present application.

[0037] Figure 13 is a structural schematic diagram of a clamping member provided by the fifth embodiment of the present application (third clamping portion is connected below the second clamping portion).

[0038] Figure 14 is a structural schematic diagram of a clamping member provided by the fifth embodiment of the present application (third clamping portion is connected above the second clamping portion).

[0039] Figure 15It is a structure schematic view of the clamping piece provided by the sixth embodiment of the present application (the third clamping part is connected above the second clamping part).

[0040] Figure 16 It is a structure schematic view of the clamping piece provided by the sixth embodiment of the present application (the third clamping part is connected below the second clamping part). DETAILED DESCRIPTION

[0041] For the embodiments of the present application, all belong to the protection scope of the present application. Therefore, the following detailed description of the embodiments of the present application provided in the drawings is not intended to limit the scope of the claimed application, but only represents selected embodiments of the present application. Based on the embodiments in the present application, all other embodiments obtained by those of ordinary skill in the art without creative labor, belong to the protection scope of the present application.

[0042] In the description of the present application, the terms "first", "second" are only used for the purpose of description, and cannot be understood as the purpose of indicating the manner, the technical solution and the advantages are more clear, the technical solutions in the embodiments of the present application will be described clearly and completely, obviously, the described embodiments are part of the embodiments of the present application, rather than all the embodiments. Based on the embodiments in the present application, all other embodiments obtained by those of ordinary skill in the art without creative labor, belong to the protection scope of the present application.

[0043] Under the requirements of building construction, dry hanging method gradually replaces wet hanging method, various dry hanging structures are also endless, but in order to ensure safety performance, the existing dry hanging structure is completely connected to various installation locking structures upwards, for example, through various bolts, glue, adhesive, to form a stable structure between the ceramic tile and the hanging part, in this way, although the ceramic tile can be indeed stably installed, but it needs to go through a long installation process during the installation stage, the worker's construction period is long, the cost is high, and once a part of it appears damage or functional degradation needs to be replaced, the replacement procedure is complex, the labor intensity of the worker is too high, the high-altitude operation increases the risk by one part for every one part of time, in order to solve the above technical problems, the present application proposes the following technical scheme:

[0044] REFERENCE Figures 1-16As shown, a kind of ceramic brick hanging system, fixed on mounting surface, comprising: mounting piece 1 locked on the mounting surface, the mounting piece 1 includes several clamping pieces 11 extending upwards from the top surface of the mounting piece 1, and the clamping pieces 11 are integrally formed with the mounting piece 1;Mounting lug plate 2 welded on the outside of the mounting piece 1;Ceramic brick 3 hung on the mounting piece 1, the ceramic brick 3 is mutually adhered with the side surface of the ceramic brick 3, and a bevel groove 31 is formed in the ceramic brick 3, and the bevel groove 31 is hung on the clamping piece 11;The bevel groove 31 includes a first mounting portion 311 formed on the side away from the finish surface of the ceramic brick 3, and a second mounting portion 312 extending from the first mounting portion 311 to the inside of the ceramic brick 3;The clamping piece 11 includes a first clamping portion 111 extending upwards from the mounting piece 1, the first clamping portion 111 abuts against the first mounting portion 311, and a second clamping portion 112 extending from the first clamping portion 111 to the inside of the second mounting portion 312.

[0045] Firstly, during installation, the mounting piece 1 can be directly installed on the conventional keel frame, and when installed on some uneven mounting surface, for example, in some uneven brick wall structure, since the surface is uneven without being coated with concrete, it is difficult to fix the keel frame, so the mounting piece 1 can be directly locked on the uneven mounting surface without the transition of the keel frame, and the installation mode is more flexible.

[0046] During actual installation, the ceramic brick 3 can be hung vertically or horizontally, as long as the position of the corresponding clamping piece 11 is adjusted.

[0047] In the embodiment, the clamping piece 11 does not need to be welded on the mounting piece 1, nor locked on the mounting piece 1, but it is a part of the mounting piece 1 itself, and in the embodiment, the mounting piece 1 can adopt the structure of conventional mounting piece 1, but before leaving the factory, the manufacturer can determine the specific layout position of the clamping piece 11 according to the requirements of the building facade assembled by the customer, such as knowing the distance between the bricks in advance, so as to cut the shape of the clamping piece 11 by cutting machine before leaving the factory, and then roll the clamping piece 11 into a shape suitable for the brick hanging groove by plate rolling machine, so that the hanging piece can be immediately put into use after being transported to the site without processing on site by the master.

[0048] In the embodiment, the ceramic brick 3 is divided into an outer decorative brick layer 32 and an outer connecting brick layer 33, and both the outer decorative brick layer 32 and the outer connecting brick layer 33 are made of clay and fired, so that the heat preservation capacity is well reflected after being installed into curtain wall or other decorative surface.

[0049] The outer decorative brick layer 32 can be colored in different colors or carved with different patterns according to the use and the installation environment, which is not limited in particular.

[0050] The thickness of the outer connecting brick layer 33 is at least 2-3 cm longer than the inclined groove 31, which can ensure the overall strength of the outer connecting brick layer 33.

[0051] In the embodiment, the outer connecting brick layer 33 of the single ceramic brick 3 is provided with two inclined grooves 31 to ensure the installation strength, so that the hanging part can provide sufficient hanging force to pull the outer decorative brick layer 32 and the outer connecting brick layer 33.

[0052] Since the longitudinal hanging force needs to be provided, the inclined groove 31 can only be inclined, and if the inclined groove 31 is simply provided as a straight groove or a T-shaped groove, the structure of the clamping part 11 needs to be changed, which makes the structure of the clamping part 11 complex and increases the cost.

[0053] If only single-point fixing is used, the ceramic brick 3 is easy to directly fall off once deformed under the interference of external force, so in the embodiment, the inclined groove 31 is provided with at least a first mounting portion 311 and a second mounting portion 312, and correspondingly, the clamping part 11 is provided with at least a first clamping portion 111 and a second clamping portion 112, so that the first clamping portion 111 and the second clamping portion 112 are respectively clamped into the first mounting portion 311 and the second mounting portion 312 to form at least two node fixings, and when one of the nodes is deformed and loses the binding fixing effect, the other node can still have a fixing effect.

[0054] However, in some cases where the ceramic brick has a heavy weight or the installation environment is relatively harsh, it is still difficult to fix well by relying on only two fixing nodes, and the ceramic brick 3 still has the risk of falling off, so the clamping part 11 further includes a third clamping portion 113 extending from the second clamping portion 112 to the second mounting portion 312, and the third clamping portion 113 forms a third fixing node in the second mounting portion 312, so that three fixing nodes form a three-layer fixing effect in the inclined groove 31, and the overall fixing effect is equivalent to a complex hanging structure, but in terms of disassembly and cost control, it is completely superior to the complex hanging structure.

[0055] And, the cooperation of the ceramic tile 3 in the embodiment and the mounting piece 1 is completely fixed by the mechanical hanging, clamping, abutting and attaching, and no bolt is used in the whole hanging process. Even if the ceramic tile 3 is installed at a high position, the worker can still easily install it without locking the screw for a long time. In the whole process, no adhesive or glue is used to avoid the difficulty in disassembly due to the fixing effect of the glue. In the embodiment, if the ceramic tile 3 needs to be replaced, the ceramic tile 3 in the corresponding column is taken out layer by layer from the top or the side, and then the complete ceramic tile 3 is sequentially sleeved.

[0056] After the hanging is completed, in the longitudinal direction, the ceramic tile 3 is stacked layer by layer and clamped and fixed by the clamping pieces 11, and in the longitudinal direction, the ceramic tile 3 is clamped and fixed by the clamping pieces 11, and in the transverse direction, the ceramic tile 3 is attached to the ceramic tile 3 to form a compact structure and is pressed against each other, thereby forming a complete curtain wall structure. The above hanging process can also be changed in direction, for example, the ceramic tile 3 is fixed by the clamping pieces 11 in the transverse direction, and the ceramic tile 3 is attached to the ceramic tile 3 in the longitudinal direction.

[0057] In the above, the ceramic tile 3 is fixed by clamping each other in the transverse direction, so as to improve the cooperation effect between the external tile layers 33 and the external tile layers 33. One side of the external tile layer 33 is provided with a cooperation block 3321, the other side of the external tile layer 33 is recessed inwardly to form a cooperation groove 3322, and the cooperation block 3321 and the cooperation groove 3322 are clamped and connected. In this way, in the transverse direction, the external tile layers 33 are sequentially fixed by the cooperation block 3321 and the cooperation groove 3322, and in the longitudinal direction, the hanging piece stably pulls the external tile layers 33 to form a stable surface decoration structure.

[0058] In the conventional curtain wall or other surface wall, after the ceramic tile or other ceramic tile is fixed, some caulking is needed to improve the heat preservation and waterproof ability of the surface wall and improve the overall appearance. However, in the embodiment, the caulking is directly realized by the ceramic tile body. Specifically, the external decoration tile layer 32 and the external tile layer 33 are integrally formed, and the external tile layer 33 is at least partially longer than the external decoration tile layer 32. The part protruding from the external decoration tile layer 32 serves as one side of the caulking, and the cooperation block 3321 of the external tile layer 33 is clamped in the cooperation groove 3322, but part of it is exposed outside after being clamped in the cooperation groove 3322, which serves as the other side of the caulking. The ceramic tiles adjacent to each other form four caulking surfaces, and no separate caulking construction structure and steps are needed to form the caulking by themselves.

[0059] Because different buildings and different installation positions have different requirements for the ceramic tile 3 and the clamping piece 11, the installation part in the chute 31 and the clamping part in the clamping piece 11 are also adaptively adjusted correspondingly. Specifically, there are several embodiments. First, there is no third clamping part 113 in the clamping piece 11.

[0060] Embodiment one

[0061] In this embodiment, the first installation part 311 is obliquely arranged, the second installation part 312 is communicated with the first installation part 311 and is flush with the horizontal plane, the first clamping part 111 is clamped on the inner side of the first installation part 311, and the second clamping part 112 is clamped on the inner side of the second installation part 312. The first installation part 311 and the second installation part 312 are relatively simple obtuse angle type designs. Through the first clamping part 111 and the second clamping part 112 which are also obtuse angle type designs, the fixation of two nodes is completed. This is suitable for some relatively mild environments and the ceramic tile itself is relatively light.

[0062] In the next several embodiments, the clamping piece 11 is provided with a third clamping part 113, that is, the clamping piece 11 has three fixed nodes inside the chute 31.

[0063] Embodiment two

[0064] The inner side of the first installation part 311 is a straight line, the other end of the inner side of the first installation part 311 is an oblique line, the second installation part 312 is communicated with the first installation part 311 and is flush with the horizontal plane, the first clamping part 111 is perpendicular to the installation piece 1 and abuts on the straight line on the inner side of the first installation part 311, the second clamping part 112 is perpendicular to the first clamping part 111, and the third clamping part 113 is inclined upward from the second clamping part 112 or inclined downward from the second clamping part 112. In this embodiment, the second clamping part 112 and the third clamping part 113 are both located on the inner side of the second installation part 312, forming two-point fixation. In addition, the first clamping part 111 and the first installation part 311 are fixed, and the cooperation effect among the three is good. The ceramic tile 3 can be tightly pulled together.

[0065] Embodiment three

[0066] The difference between the embodiment and the embodiment two is that the second clamping part 112 is arranged downwardly inclined from the first clamping part 111, specifically, one end of the first mounting part 311 is a straight line, the other end of the first mounting part 311 is an inclined line, the second mounting part 312 is communicated with the first mounting part 311 and is flush with the horizontal plane, the first clamping part 111 is perpendicular to the mounting piece 1 and abuts on the straight line of the inner side of the first mounting part 311, the second clamping part 112 is arranged downwardly inclined from the first clamping part 111, and the third clamping part 113 is arranged upwardly inclined from the first clamping part 111, so that the same technical effects can be achieved as the above embodiment.

[0067] Embodiment four

[0068] The difference between the embodiment and the embodiment three is that the third clamping part 113 is arranged downwardly inclined from the first clamping part 111, specifically, one end of the first mounting part 311 is a straight line, the other end of the first mounting part 311 is an inclined line, the second mounting part 312 is communicated with the first mounting part 311 and is flush with the horizontal plane, the first clamping part 111 is perpendicular to the mounting piece 1 and abuts on the straight line of the inner side of the first mounting part 311, the second clamping part 112 is arranged downwardly inclined from the first clamping part 111, and the third clamping part 113 is arranged downwardly inclined from the first clamping part 111, so that the same technical effects can be achieved as the above embodiment.

[0069] In the above embodiments two to four, one end of the inner side of the first mounting part 311 is a straight line, and the other end of the inner side of the first mounting part 311 is an inclined line. The purpose of such arrangement is that, first, the inclined line design of the first mounting part 311 can ensure that the worker can insert at a certain angle during installation, and the installation is more smooth. After installation, the first clamping part 111 can abut on the straight line part of the first mounting part 311. During daily use, the ceramic tiles 3 are tightly attached together. Even if part of the ceramic tiles shakes, the shaking force can be reduced or even eliminated due to the cooperation between the first clamping part 111 and the first mounting part 311.

[0070] In the above several embodiments, the first mounting part 311 is inclined at one end and straight at the other end. Actually, the first mounting part 311 can also have other styles, for example:

[0071] Embodiment five

[0072] The first installation part 311 is obliquely arranged, the second installation part 312 is obliquely arranged downward / upward from the first installation part 311, the first clamping part 111 is clamped on the inner side of the first installation part 311, the second clamping part 112 is connected with the first clamping part 111 and is flush with the horizontal plane, the third clamping part 113 is connected below / above the second clamping part 112, the first clamping part 111 and the first installation part 311 are correspondingly obliquely arranged, and the second clamping part 112 and the third clamping part 113 are fixed in the second installation part 312, so that the fixing mode of three nodes in a single groove is completed, and compared with the complex groove type fixing mode in the traditional brick, the fixing effect is the same or even better than that of similar products.

[0073] Embodiment six

[0074] The difference between the embodiment and embodiment five is that the second clamping part 112 is obliquely arranged downward from the first clamping part 111, specifically, the first installation part 311 is obliquely arranged, the second installation part 312 is obliquely arranged downward / upward from the first installation part 311, the first clamping part 111 is clamped on the inner side of the first installation part 311, the second clamping part 112 is obliquely arranged downward from the first clamping part 111, and the third clamping part 113 is connected below / above the second clamping part 112. In the embodiment, because the second clamping part 112 is obliquely arranged downward from the first clamping part 111, there is a bending force between the connection between the first clamping part 111 and the second clamping part 112, and the bending degree and the tension of the whole clamping part 11 are greatly improved under the condition that there is a bending force between the third clamping part 113 and the second clamping part 112. In combination with the oblique arrangement of the first clamping part 111, the clamping part 11 can better tension and fix the ceramic brick 3.

[0075] In actual use, if the number of ceramic bricks 3 hung on the simple fence or decorative surface is small, workers can fix the installation part 1 one by one, but if the front is large in width and height, workers still fix the installation part 1 one by one, which is troublesome for workers and the construction period. Therefore, the following two embodiments are provided in the application.

[0076] Embodiment seven

[0077] The mounting piece 1 is a C-shaped steel 1A, a plurality of clamping pieces 11 are uniformly and equidistantly arranged on the C-shaped steel 1A, the C-shaped steel 1A is locked on a keel frame through a mounting lug plate 2, the keel frame is locked on the mounting surface, in a small building or a local mounting surface, the fixing mode of the C-shaped steel 1A can be used, according to the above-mentioned, the factory opens the positions and intervals of the corresponding clamping pieces 11 according to the size of the ceramic tile 3 of the customer, and then directly locks the C-shaped steel 1A on the keel frame or the mounting surface, and then hangs the ceramic tile 3 step by step.

[0078] On the C-shaped steel 1A, the style of the clamping piece 11 arranged thereon can be any of the styles in the above-mentioned embodiments, and correspondingly, the style of the inclined groove 31 of the ceramic tile 3 matched therewith can also be any of the styles in the above-mentioned embodiments, and the two can be combined for use.

[0079] Embodiment eight

[0080] The difference between the embodiment and the embodiment seven is that the mounting piece 1 is a mounting bottom plate 1B, specifically, the mounting piece 1 is a mounting bottom plate 1B, a plurality of clamping pieces 11 are arranged on the mounting bottom plate 1B, and the mounting bottom plate 1B is locked on the mounting surface, or the mounting bottom plate 1B is locked on the keel frame, and the keel frame is locked on the mounting surface, when the position where the ceramic tile 3 needs to be hung is a large-area wall body, for example, a whole-face curtain wall needs to be hung, if the C-shaped steel 1A is installed column by column, it is relatively troublesome for the workers, although the hanging effect is the same, but the construction period and the labor cost are both increased by more than one time, and if the horizontal rods and the vertical rods are directly punched into the keel frame, the whole-face mounting bottom plate 1B can be directly installed on the horizontal rods and the vertical rods of the keel frame, the span of the horizontal rods and the vertical rods is large, and since the horizontal rods and the vertical rods are arranged at intervals to support, the stress borne by the mounting bottom plate 1B is completely sufficient.

[0081] On the mounting bottom plate 1B, the style of the clamping piece 11 arranged thereon can be any of the styles in the above-mentioned embodiments, and correspondingly, the style of the inclined groove 31 of the ceramic tile 3 matched therewith can also be any of the styles in the above-mentioned embodiments, and the two can be combined for use.

[0082] No matter the C-shaped steel 1A or the mounting bottom plate 1B, a reinforcing rib is arranged thereon to improve the overall strength when the C-shaped steel 1A or the mounting bottom plate 1B is subjected to a shaking force or a vibration force.

[0083] The above only describes the preferred embodiments of the present application and is not used to limit the present application, and the present application can have various changes and variations for those skilled in the art. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.

Claims

1. A ceramic tile hanging system for attachment to a mounting surface, characterised in that, The utility model relates to a kind of ceramic tile and mounting piece, comprising: Mounting piece (1) is locked on mounting surface, the mounting piece (1) includes several clamping pieces (11) extending upward from the top surface of the mounting piece (1), the clamping piece (11) is integrally formed with the mounting piece (1); Ceramic tile (3) is hung on the mounting piece (1), the ceramic tile (3) is attached to the side of the ceramic tile (3), a bevel slot (31) is provided on the ceramic tile (3), and the bevel slot (31) is hung on the clamping piece (11); The bevel slot (31) includes a first mounting portion (311) provided on the side away from the finish surface of the ceramic tile (3), and a second mounting portion (312) extending from the first mounting portion (311) to the inside of the ceramic tile (3); The clamping piece (11) includes a first clamping portion (111) extending upward from the mounting piece (1), the first clamping portion (111) abuts against the first mounting portion (311), and a second clamping portion (112) extending from the first clamping portion (111) to the inside of the second mounting portion (312); The clamping piece (11) further includes a third clamping portion (113) extending from the second clamping portion (112) to the inside of the second mounting portion (312); The first mounting portion (311) is linear on one end inside, and is oblique on the other end inside, the second mounting portion (312) is communicated with the first mounting portion (311) and is flush with the horizontal plane, the first clamping portion (111) is perpendicular to the mounting piece (1) and abuts against the linear inside of the first mounting portion (311), the second clamping portion (112) is perpendicular to the first clamping portion (111), the third clamping portion (113) is inclined upward from the second clamping portion (112), or the third clamping portion (113) is inclined downward from the second clamping portion (112); The ceramic tile (3) is divided into an outer decorative tile layer (32) and an outer connecting tile layer (33), one side of the outer connecting tile layer (33) extends to provide a matching block (3321), and the other side of the outer connecting tile layer (33) is recessed inward to provide a matching groove (3322), the matching block (3321) and the matching groove (3322) are clamped and connected with each other between adjacent ceramic tiles (3); The outer decorative tile layer (32) and the outer connecting tile layer (33) are integrally formed, and the outer connecting tile layer (33) is longer than the outer decorative tile layer (32) at least in part, the part protruding from the outer decorative tile layer (32) serves as one side of the joint, the matching block (3321) of the outer connecting tile layer (33) is clamped in the matching groove (3322), and part of the matching block (3321) is exposed outside after being clamped in the matching groove (3322), serving as the other side of the joint, and four sides of the joint are formed between adjacent ceramic tiles (3).

2. A system for hanging ceramic tiles according to claim 1, characterized in that The first mounting portion (311) is obliquely arranged, the second mounting portion (312) is communicated with the first mounting portion (311) and is flush with the horizontal plane, the first clamping portion (111) is clamped inside the first mounting portion (311), and the second clamping portion (112) is clamped inside the second mounting portion (312).

3. A system for hanging ceramic tiles according to claim 1, characterized in that The inner side of the first installation part (311) is a straight line, the other end of the inner side of the first installation part (311) is an inclined line, the second installation part (312) is communicated with the first installation part (311) and is flush with the horizontal plane, the first clamping part (111) is perpendicular to the installation part (1) and abuts on the straight line of the inner side of the first installation part (311), the second clamping part (112) is inclined downward from the first clamping part (111), and the third clamping part (113) is inclined upward from the first clamping part (111).

4. A system for hanging ceramic tiles according to claim 1, characterized in that The inner side of the first installation part (311) is a straight line, the other end of the inner side of the first installation part (311) is an inclined line, the second installation part (312) is communicated with the first installation part (311) and is flush with the horizontal plane, the first clamping part (111) is perpendicular to the installation part (1) and abuts on the straight line of the inner side of the first installation part (311), the second clamping part (112) is inclined downward from the first clamping part (111), and the third clamping part (113) is inclined downward from the first clamping part (111).

5. A system for hanging ceramic tiles according to claim 1, characterized in that The first installation part (311) is inclined, the second installation part (312) is inclined downward / upward from the first installation part (311), the first clamping part (111) is clamped on the inner side of the first installation part (311), the second clamping part (112) is connected with the first clamping part (111) and is flush with the horizontal plane, and the third clamping part (113) is connected below / above the second clamping part (112).

6. A system for hanging ceramic tiles according to claim 1, characterized in that The first installation part (311) is inclined, the second installation part (312) is inclined downward / upward from the first installation part (311), the first clamping part (111) is clamped on the inner side of the first installation part (311), the second clamping part (112) is inclined downward from the first clamping part (111), and the third clamping part (113) is connected below / above the second clamping part (112).

7. A system for hanging ceramic tiles according to claim 1, characterized in that The installation part (1) is a C-shaped steel (1A), a plurality of clamping parts (11) are uniformly and equidistantly arranged on the C-shaped steel (1A), the C-shaped steel (1A) is locked on a keel frame, and the keel frame is locked on the installation surface.

8. A system for hanging ceramic tiles according to claim 1, characterized in that The installation part (1) is a mounting bottom plate (1B), a plurality of clamping parts (11) are arranged on the mounting bottom plate (1B), the mounting bottom plate (1B) is locked on the installation surface, or the mounting bottom plate (1B) is locked on a keel frame, and the keel frame is locked on the installation surface.

Citation Information

Patent Citations

  • Dry hanging ceramic tile and hanging member thereof

    CN203924576U

  • Earthenware brick hanging system

    CN219491412U

  • Bracket rail for attaching tiles and construction method of dry tiles using the same, and dry tile wall surface structure

    JP2020186637A