On-site logistics control system based on digital twinning technology

The on-site logistics management and control system based on digital twin technology solves the problems of cumbersome management of engineering materials and difficult monitoring of material shortages during engineering construction. It realizes real-time management and automated transportation, significantly reduces the workload of construction and technical personnel, and improves logistics efficiency. efficiency.

CN116562720BActive Publication Date: 2024-10-22ZHONGLIN GUANGSHENG TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202310186274.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-03-01
Publication Date
2024-10-22
Estimated Expiration
2043-03-01

AI Technical Summary

Technical Problem

During the project construction process, on-site engineering material management is cumbersome and inefficient, and it is difficult to control material shortages in real time, resulting in heavy workloads for construction personnel and technicians and imperfect information construction.

Method used

An on-site logistics management and control system based on digital twin technology is used to obtain the coding, coordinates and image information of engineering materials through the data collection module, and the wireless data transmission module is used to transmit the data to the data processing module to segment and match the engineering model in the virtual space. Display material status and transportation status in real time, automatically arrange transportation and manage materials, and reduce repetitive work.

Benefits of technology

It realizes real-time management and shortage monitoring of engineering materials, simplifies the material management process, improves logistics efficiency, reduces the workload of construction and technical personnel, and improves the accuracy and efficiency of material management.

✦ Generated by Eureka AI based on patent content.
Patent Text Reader

Abstract

The present invention provides an on-site logistics control system based on digital twin technology, including: data collection, data processing, dividing the engineering model into several standard units according to standard size; matching the actual code of each unit with the virtual code in the digital virtual space, and moving the standard unit in the digital virtual space corresponding to the actual code to the corresponding virtual material placement location in the site model; when the engineering material unit of the material field is transported to the installation site and installed in place, the corresponding standard unit in the digital virtual space is moved from the virtual material placement location to the virtual installation position. The present invention can present the on-site engineering material management, the construction status after the engineering materials are shipped out of the warehouse, and the shortage of materials to the material management personnel and technical personnel in the form of digital information, and the construction party, the supervision party, and the owner party can all know the engineering material status and construction status at a glance, so that the material management end and the construction end are effectively and real-time connected / combined together.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of on-site logistics, and specifically relates to an on-site logistics management and control system based on digital twin technology. Background Art

[0002] Digital twin technology is the execution basis of manufacturing activities. By establishing a multi-dimensional, multi-level, and multi-domain accurate model of the physical scene and combining the analysis of a large amount of actual twin data, it can evaluate the current state of the site, diagnose past problems, and predict future trends. It also provides the results of the analysis, simulates various possibilities, and provides more comprehensive decision support, thus solving the problems of "describing what the workshop is", "depicting what the workshop is doing", and "predicting what will happen in the workshop" in the intelligent production process. Based on digital twin technology, with the goal of three-dimensional, panoramic, and visualized control in the field, by building a three-dimensional scene, simulating, optimizing, and reconstructing the entire production / transportation process in a virtual environment, and assisting in three-dimensional visualized decision-making and command, it can produce high-quality products in an orderly, coordinated, controllable, and efficient manner, thereby maximizing production efficiency.

[0003] On-site logistics refers to the whole process of storing, transporting, packaging, processing / construction, loading and unloading, handling and managing goods in a specific domain / area in order to meet the corresponding needs. For example, on-site logistics at a construction site includes the management of feed, outbound and transportation of engineering materials. In recent years, with the rapid development of the digital economy, intelligent logistics technology has also been widely used, including logistics information systems based on digital twin technology. For example, the logistics center information platform system based on digital twin (CN115619309A) developed by Shenzhen Zhaohang Logistics Co., Ltd. uses the acquisition module to obtain the spatial information and equipment layout information of the target logistics center and conduct digital modeling based on it, builds a virtual operation model based on the operation of the target logistics center under different logistics businesses, creates a digital twin logistics information management model based on the virtual structure model and the virtual operation model, and a management module uses the digital twin logistics information management model to manage and display data in layers for the target logistics center, which can realize intelligent data acquisition, management, display and analysis, and improve the reliability of logistics information management and data accuracy. For example, the digital twin-based workshop logistics system monitoring and simulation system and method (CN114384881A) provided by Harbin Institute of Technology models, simulates and optimizes the impact of the movement path of workshop motion equipment on production logistics, the scheduling of production logistics and the production logistics operation process, thereby establishing a human-centered logistics decision support system throughout the entire process.

[0004] Although the aforementioned logistics based on digital twin technology optimizes logistics management, it is mainly aimed at the accuracy of logistics information and the optimization of transportation routes, and is not suitable for on-site logistics management and optimization of engineering construction sites. In the process of engineering construction, the management of on-site engineering materials is very cumbersome and inefficient. Even if there are multiple material managers, they can only manage the procurement and entry and exit of engineering materials, and cannot control the subsequent matters after the engineering materials are out of the warehouse, especially the construction status and material shortage (material shortages are usually reported by technicians to material managers, especially the location of the shortage can only be known after the technicians check). In fact, there is no on-site logistics control system that can be applied to the construction site. In addition, due to the imperfect information construction technology on the site, the construction personnel can usually only report the workload to the technicians every day, and then the technicians count the construction volume / workload of the day one by one. Obviously, this adds a lot of even repetitive workload to the construction personnel and technicians. Therefore, how to reduce the workload of construction personnel and technicians based on the on-site logistics control system is also a problem that needs to be solved in the on-site information construction. Summary of the invention

[0005] The purpose of the present invention is to provide an on-site logistics management and control system based on digital twin technology, which is at least used to solve the technical problems that on-site engineering material management is very cumbersome and inefficient, and how to reduce the workload of construction personnel and technical personnel based on the on-site logistics management and control system.

[0006] In order to achieve the above-mentioned purpose, the present invention adopts the following technical solution.

[0007] The in-field logistics control system based on digital twin technology includes:

[0008] The data acquisition module is used to collect the coding information, coordinate information, image information and input material shortage information of each engineering material unit. The coordinate information includes the coordinate information of the storage place of the engineering material unit in the material yard and the coordinate information of the engineering material unit in the construction area after installation. The image information refers to the image of the engineering material unit located in the construction area after installation;

[0009] A wireless data transmission module is used to transmit the collected data to the data processing module;

[0010] The data processing module implements the following steps / functions when executing the program based on the acquired data:

[0011] S1, reading the site model in the digital virtual space and the engineering model in the site model, the coordinates of each point in the digital virtual space correspond to the coordinates of each point in the actual site;

[0012] S2, according to the standard size of each engineering material unit, the engineering model is divided into several standard units, each standard unit corresponds to a virtual code;

[0013] S3, identifying the actual code of each engineering material unit after arriving at the material yard and obtaining the coordinates of the actual material placement location;

[0014] S4, matching the obtained actual code with the virtual code in the digital virtual space, and moving the standard unit in the digital virtual space corresponding to the actual code to the corresponding virtual material placement location in the site model;

[0015] S5, when the engineering material unit of the material yard is transported to the installation site and installed in place, the corresponding standard unit in the digital virtual space is moved from the virtual material placement location to the virtual installation location;

[0016] The display module is used to display the standard unit status and transportation tool status in the digital virtual space in real time. The standard unit status includes the position and color of the standard unit.

[0017] As a preferred solution, in S2, the segmented standard unit is displayed as a transparent body;

[0018] In S4, the standard unit of the virtual material placement location is displayed in gray;

[0019] In S5, the standard cell of the virtual mounting position is displayed in a designated color.

[0020] As a preferred solution, for the engineering material units that have not arrived at the material yard before construction, their corresponding standard units in the digital virtual space are moved to the designated virtual material placement location and displayed in a specific color.

[0021] Furthermore, when it is monitored through the digital virtual space that the construction area where the construction team is located is about to run out of materials, a control instruction is issued to the dispatch center to give priority to arranging transportation tools to transfer the corresponding engineering material units.

[0022] As a preferred solution, the construction area is about to run out of materials including: for interconnected local engineering models, when standard unit A or standard unit C is already in the corresponding virtual installation position and both standard unit A and standard unit C are not at the virtual material placement location, at this time, standard unit B that is also located at the virtual material placement location is defined as the construction area is about to run out of standard unit B.

[0023] As a preferred solution, the engineering model is a pipeline engineering model, and the interconnected local engineering models include pipe segments and pipe segments, pipe segments and pipe fittings, pipe segments and valves, and pipe segments and brackets that are directly connected together.

[0024] Furthermore, the daily demands for engineering material units issued by each construction team are regularly counted, the system calculates the transportation routes for the engineering material units according to each demand, and selects the best transportation method to transport the engineering material units to the designated locations.

[0025] Furthermore, when the construction of the engineering material unit that has arrived at the material yard is completed, if a local engineering model is still short of materials, the standard unit of the designated virtual material placement location is moved to the corresponding installation position in the local engineering model and still displays a specific color.

[0026] Furthermore, for the engineering material units that arrive at the final stage of construction, the transport vehicles are controlled to directly transport them to the corresponding installation locations and unload them. After the construction is completed, the specific color of the corresponding standard unit is replaced with the specified color.

[0027] Furthermore, when a transport vehicle is in an idle section, the transport vehicle is arranged nearby to transfer waste.

[0028] Beneficial effect: The on-site logistics control system based on the digital twin technology of the present invention can not only present the construction site (on-site) engineering material management, the construction status after the engineering materials are shipped out, and the material shortage situation to the material management personnel and technical personnel in the form of digital information, so that the construction party, the supervision party, and the owner party can know the engineering material status and the construction status at a glance, and make the material management end and the construction end effectively and real-time connected / combined together, avoiding the disconnection between construction management and material management, helping to greatly simplify the management process of on-site engineering materials and improve the logistics efficiency of on-site engineering materials, and can greatly reduce the workload of construction personnel and technical personnel, especially eliminating the work of technicians repeatedly submitting material plans and simplifying the statistical work of construction workload. Implementation

[0029] The present invention is further described below by specific embodiments, but the following embodiments are only used to help understand the principle and core idea of ​​the present invention, and are not intended to limit the scope of protection of the present invention. It should be pointed out that for those skilled in the art, without departing from the principle of the present invention, improvements made to the present invention also fall within the scope of protection of the claims of the present invention. Example

[0030] An on-site logistics management and control system based on digital twin technology, comprising:

[0031] The data acquisition module is used to collect the coding information, coordinate information, image information and input material shortage information of each engineering material unit. The coordinate information includes the coordinate information of the storage place of the engineering material unit in the material yard and the coordinate information of the engineering material unit in the construction area after installation. The image information refers to the image of the engineering material unit located in the construction area after installation;

[0032] A wireless data transmission module is used to transmit the collected data to the data processing module;

[0033] The data processing module implements the following steps / functions when executing the program:

[0034] S1, reading the site model in the digital virtual space and the engineering model in the site model, the coordinates of each point in the digital virtual space correspond to the coordinates of each point in the actual site;

[0035] S2, according to the standard size of each engineering material unit, the engineering model is divided into several standard units, each standard unit corresponds to a virtual code; the divided standard units are displayed as transparent bodies;

[0036] S3, after the engineering material units arrive at the material yard, identify the actual code of each engineering material unit and obtain the coordinates of the actual material placement location;

[0037] S4, matching the obtained actual code with the virtual code in the digital virtual space, and moving the standard unit in the digital virtual space corresponding to the actual code to the corresponding virtual material placement location in the site model, and the standard unit of the virtual material placement location is displayed in gray;

[0038] S5, when the engineering material unit of the material yard is transported to the installation site and installed in place, the corresponding standard unit in the digital virtual space is moved from the virtual material placement location to the virtual installation location, and the standard unit at the virtual installation location is displayed in a specified color;

[0039] S6, for the engineering material units that have not arrived at the material yard before construction, the corresponding standard units in the digital virtual space are moved to the designated virtual material placement location and displayed in a specific color; when the digital virtual space monitors that the construction area where the construction team is located is about to run out of materials, a control instruction is issued to the dispatch center to give priority to arranging transportation tools to transfer the corresponding engineering material units; the engineering material unit requirements issued by each construction team on the same day are regularly counted, and the system calculates the transportation route of the engineering material units according to each requirement, and selects the best transportation method to transport the engineering material units to the destination;

[0040] S7, when the construction of the engineering material unit that has arrived at the material yard is completed, if a local engineering model is still short of materials, the standard unit of the designated virtual material placement location is moved to the corresponding installation position in the local engineering model, and the specific color is still displayed;

[0041] S8, for the engineering material units that arrive at the construction site at the end of the construction, control the transport vehicle to directly transport them to the corresponding installation location and unload them. After the construction is completed, change the specific color of the corresponding standard unit to the specified color;

[0042] S9, when a transport vehicle is in an idle section, the transport vehicle is arranged nearby to transfer waste;

[0043] The display module is used to display the standard unit status and transportation tool status in the digital virtual space in real time. The standard unit status includes the position and color of the standard unit.

[0044] In the present invention, the construction area is about to be short of materials, including: for the interconnected local engineering models, the interconnected local engineering models include but are not limited to pipe segments and pipe segments, pipe segments and pipe fittings, pipe segments and valves, and pipe segments and brackets that are directly connected. For example, when pipe segment 1 (defined as standard unit A, corresponding to the actual engineering material unit A), elbow (defined as standard unit B, corresponding to the actual engineering material unit B), pipe segment 2 (defined as standard unit C, corresponding to the actual engineering material unit C), pipe segment 2 (defined as standard unit D, corresponding to the actual engineering material unit D) are interconnected, when standard unit A or standard unit C is already in the corresponding virtual installation position and standard unit A and standard unit C are not at the virtual material placement location, at this time, standard unit B still located at the virtual material placement location is defined as the construction area is about to be short of standard unit B.

[0045] The following takes the pipeline construction at the construction site as an example to further illustrate the use of the on-site logistics management and control system based on the digital twin technology in the embodiment.

[0046] The designer builds a site model in the digital virtual space, and builds an engineering model in the site model. The coordinates of each point in the digital virtual space correspond to the coordinates of each point in the actual site, and each engineering material unit in the engineering model is coded. The entire engineering model (pipeline engineering model) is divided into several standard units, which are displayed in transparent bodies. Each standard unit corresponds to a virtual code (the virtual code corresponds to the code of the actual engineering material. For example, if the code of an actual engineering material unit is defined as GD003, then the virtual code in the virtual space corresponding to the engineering material unit is also GD003). Among them, the standard unit includes at least a single pipe section of standard length, a single pipe fitting, a single valve, a single bracket, a single equipment body, a single accessory of the equipment body, a single skid, and a single instrument on the pipeline (such as a flow meter). Among them, the site model also includes a virtual material placement location relative to the actual material yard.

[0047] The general contractor or owner purchases engineering materials based on the engineering model provided by the designer, and the engineering material manufacturer supplies goods based on procurement requirements. The goods supplied must contain the code of the engineering material unit, that is, each engineering material unit is marked with the code provided by the designer before leaving the factory.

[0048] Data collection is performed using a data collection terminal (such as a mobile phone or barcode scanner with a data collection system / App). The data collection terminal can at least collect the coding information, coordinate information, image information and input material shortage information of each engineering material unit, and can transmit the collected data to the data processing module. Among them:

[0049] (a) When the engineering material unit A arrives at the material yard (i.e., the supplier transports the engineering material unit A to the material yard at the construction site), the material management personnel or their team members use the data acquisition terminal to identify the actual code of each engineering material unit A and simultaneously obtain the coordinates of the actual material placement location of each engineering material unit A, and feed the obtained information back to the data processing module. After the data processing module obtains the information, it controls the standard unit A corresponding to the engineering material unit A in the digital virtual space to move to the corresponding virtual material placement location in the site model; this process mainly involves the storage management of the engineering materials arriving at the material yard, and the system simultaneously performs the first transfer of the corresponding standard unit A (transferring the corresponding standard unit A to the virtual material placement location);

[0050] (b) When the construction personnel receive the engineering material unit A from the material yard and transport it to the installation site and install it in place, the construction personnel use the data acquisition terminal to identify the actual code of the engineering material unit A again, that is, mark the engineering material unit A that has been shipped out and installed, and feed its code information back to the data processing module again; after the data processing module obtains the shipping and installation information, it matches the actual code of the engineering material unit A with the virtual code in the digital virtual space again, and moves the corresponding standard unit A in the digital virtual space from the virtual material placement location to the virtual installation location, and the standard unit A at the virtual installation location is displayed in a specified color; this process mainly manages the shipping and construction of the engineering materials that have been put into storage, and the system simultaneously performs the second transfer of the corresponding standard unit A (transferring the corresponding standard unit A from the virtual material placement location to the virtual installation location);

[0051] (c) With reference to the above sections (a) and (b), manage the storage, delivery and construction of all construction materials arriving on site;

[0052] (d) If the engineering material units A, B, C, and D are connected in sequence to form a local pipeline engineering model, when the engineering material units A, B, and D have all arrived at the material yard, but the engineering material unit C (defined as code GJ006) has not arrived at the material yard, the corresponding standard unit C (code GJ006) in the digital virtual space is moved to the designated virtual material placement location and displayed in a specific color; if the engineering material units A, B, and D are all in the construction area and have been constructed (including prefabrication), the construction personnel send material shortage information (lack of engineering material unit C) to the data processing module through the data acquisition terminal. After receiving the material shortage information, the data processing module moves the standard unit C at the designated virtual material placement location to the corresponding installation position in the local engineering model and still displays the specific color;

[0053] (e) The system regularly / periodically counts the engineering material unit requirements issued by each construction team on the day, calculates the transportation route of the engineering material units based on each requirement, and selects the best transportation method (such as the fastest transportation route) to transport the engineering material units to the destination;

[0054] For example, for engineering material F that has arrived at the material yard, when the construction team's construction area is about to run out of engineering material unit F through digital virtual space monitoring, a control instruction is issued to the dispatch center to give priority to arranging transportation tools to transport engineering material unit F to the construction area;

[0055] (f) For the engineering material units that arrive at the construction site at the end of the construction phase, the transport vehicles are controlled to directly transport them to the corresponding installation locations and unload them. After the construction is completed, the specific color of the corresponding standard unit is replaced with the specified color;

[0056] (g) When a transport vehicle is in an idle section, arrange for the transport vehicle nearby to transfer waste.

[0057] The on-site logistics control system based on digital twin technology in this embodiment can not only present the construction site (on-site) engineering material management of the engineering construction, the construction status after the engineering materials are shipped out, and the shortage of materials to the material management personnel and technical personnel in digital information, so that the construction party, the supervision party, and the owner party can quickly know the engineering material status and construction status synchronously and clearly, so that the material management end and the construction end are effectively and real-timely connected / combined together, avoiding the disconnection between construction management and material management, helping to greatly simplify the management process of on-site engineering materials, and improve the logistics efficiency of on-site engineering materials, and can greatly reduce the workload of construction personnel and technical personnel, especially eliminating the work of technicians repeatedly submitting material plans, and simplifying the statistical work of construction workload. Compared with the existing operation mode, after adopting the present invention, the workload of technical personnel in terms of materials and engineering quantity statistics can be reduced by at least 40%, material management, especially material dynamic management, is simpler, more efficient, accurate, and convenient, and the workload of material management personnel has also been greatly reduced.

Claims

1. The in-field logistics control system based on digital twin technology is characterized by: include: The data acquisition module is used to collect the coding information, coordinate information, image information and input material shortage information of each engineering material unit. The coordinate information includes the coordinate information of the storage place of the engineering material unit in the material yard and the coordinate information of the engineering material unit in the construction area after installation. The image information refers to the image of the engineering material unit located in the construction area after installation; A wireless data transmission module is used to transmit the collected data to the data processing module; The data processing module implements the following steps / functions when executing the program: S1, reading the site model in the digital virtual space and the engineering model in the site model, the coordinates of each point in the digital virtual space correspond to the coordinates of each point in the actual site; S2, according to the standard size of each engineering material unit, the engineering model is divided into several standard units, each standard unit corresponds to a virtual code; S3, identifying the actual code of each engineering material unit after arriving at the material yard and obtaining the coordinates of the actual material placement location; S4, matching the obtained actual code with the virtual code in the digital virtual space, and moving the standard unit in the digital virtual space corresponding to the actual code to the corresponding virtual material placement location in the site model; S5, when the engineering material unit of the material yard is transported to the installation site and installed in place, the corresponding standard unit in the digital virtual space is moved from the virtual material placement location to the virtual installation location; A display module, used to display the status of standard units and transportation tools in the digital virtual space in real time, wherein the status of standard units includes the position and color of the standard units; For the engineering material units that have not arrived at the material yard before construction, the corresponding standard units in the digital virtual space are moved to the designated virtual material placement location and displayed in a specific color; When the construction team is monitoring through the digital virtual space that the construction area is about to run out of materials, a control command is sent to the dispatch center to give priority to arranging transportation tools to transfer the corresponding engineering material units; The construction area is about to be short of materials including: for interconnected local engineering models, when standard unit A or standard unit C is already in the corresponding virtual installation position and both standard unit A and standard unit C are not at the virtual material placement location, at this time, standard unit B that is also located at the virtual material placement location is defined as the construction area is about to be short of standard unit B.

2. The on-site logistics control system according to claim 1, characterized in that: In S2, the segmented standard unit is displayed as a transparent body; In S4, the standard unit of the virtual material placement location is displayed in gray; In S5, the standard cell of the virtual mounting position is displayed in a designated color.

3. The on-site logistics control system according to claim 2 is characterized in that: The engineering model is a pipeline engineering model, and the interconnected local engineering models include pipe sections and pipe sections, pipe sections and pipe fittings, pipe sections and valves, and pipe sections and brackets that are directly connected together.

4. The on-site logistics control system according to claim 3 is characterized by: The system regularly counts the engineering material unit demands issued by each construction team on the day, calculates the transportation routes of the engineering material units according to each demand, and selects the best transportation method to transport the engineering material units to the designated locations.

5. The on-site logistics control system according to claim 4 is characterized in that: When the construction of the engineering material unit that has arrived at the material yard is completed, if a local engineering model is still short of materials, the standard unit of the designated virtual material placement location will be moved to the corresponding installation position in the local engineering model and will still be displayed in a specific color.

6. The on-site logistics control system according to claim 5 is characterized by: For the engineering material units that arrive at the construction site at the end of the construction phase, the transport vehicles are controlled to directly transport them to the corresponding installation locations and unload them. After the construction is completed, the specific color of the corresponding standard unit is replaced with the specified color.

7. The on-site logistics control system according to any one of claims 1 to 6, characterized in that: When a transport vehicle is in an idle section, the nearest transport vehicle will be arranged to transfer waste.