A method for coordinating mid-span deformation of the cumulative lifting docking side of a stepped space frame

By using temporary supports or suspension systems to control the deformation of the stepped space frame during construction, the problem of inconsistent deformation at mid-span of the space frame was solved, and synchronous and precise control of the lifting process was achieved, ensuring construction safety.

CN116816101BActive Publication Date: 2026-11-17MCC (SHANGHAI) STEEL STRUCTURE TECHNOLOGY CORP LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202310751407.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-06-25
Publication Date
2026-11-17
Estimated Expiration
2043-06-25

AI Technical Summary

Technical Problem

During the construction of stepped space frame, the deformation of the space frame at the mid-span is not coordinated during the staged lifting process, resulting in large errors in the length of the inserted members and inconsistent stress between the upper and lower layers of the space frame, which poses a safety hazard.

Method used

Temporary support or suspension systems are used to temporarily support or suspend the space frame to control mid-span deformation. Deformation coordination is achieved by lifting and inserting members layer by layer, ensuring synchronicity and precision during the lifting process.

Benefits of technology

It effectively reduced the mid-span deformation of the space frame, improved the installation accuracy and stress coordination of the interlocking members, and ensured the safety and reliability of the construction process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116816101B_ABST
    Figure CN116816101B_ABST
Patent Text Reader

Abstract

This invention discloses a method for coordinating deformation at the mid-span of the connecting side during the cumulative lifting of a stepped space frame. The steps are as follows: Assemble the first-layer space frame unit and set up and install the lifting system; lift the first-layer space frame unit to a specified height, set up temporary supports at the mid-span of the connecting side between the first and second-layer space frame units, and assemble the second-layer space frame unit; insert supplementary support members between the first and second-layer space frame units; remove the temporary supports, lift the entire assembly of the first and second-layer space frame units to a specified height, set up temporary supports at the mid-span of the connecting side between the second and third-layer space frame units, and assemble the third-layer space frame unit; insert supplementary support members between the second and third-layer space frame units; repeat the above steps until all space frame units are connected as a whole, and synchronously lift all space frame units to the designed height. This method controls deformation coordination during assembly and improves installation accuracy.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of space frame construction technology, and specifically to a method for coordinating deformation at mid-span on the cumulative lifting docking side of a stepped space frame. Background Technology

[0002] In the construction of stepped (staggered) space frames, in order to reduce high-altitude operations and lower the height of temporary supports, a cumulative lifting method is generally adopted. However, during the staged lifting process, there will be some deformation in the mid-span of the space frame between the lifting points. If this deformation is not addressed and the space frame is directly connected to the next layer after being lifted to a certain height, it will cause problems with deformation inconsistency, resulting in large length errors in the interlocking members. It will also cause problems with uncoordinated forces on the connecting side of the upper and lower layers of the space frame, which does not meet the original design requirements and thus leads to safety hazards.

[0003] Therefore, developing a method to coordinate the deformation caused by the cumulative lifting of stepped space frames is of great practical significance. Summary of the Invention

[0004] Due to the aforementioned defects in the existing technology, the present invention provides a method for coordinating the deformation generated by the cumulative lifting of a stepped space frame, thereby solving the defect of inconsistent deformation at the mid-span of the space frame during current staged lifting.

[0005] To achieve the above objectives, the present invention provides the following technical solution:

[0006] A method for coordinating deformation at mid-span of the cumulative lifting docking side of a stepped space frame, wherein the stepped space frame comprises N layers of space frame units, arranged sequentially from high to low, where N≥2, includes the following steps:

[0007] (1) Assemble the first layer of space frame unit on the assembly jig on the floor, set up and install the lifting system, and fix the first layer of space frame unit by lifting rope;

[0008] (2) After the first-layer space frame unit is lifted to a specified height and suspended, a temporary support is set in the middle of the side span where the first-layer space frame unit and the second-layer space frame unit are connected, and the first-layer space frame unit is supported by the temporary support. At the same time, the second-layer space frame unit is assembled on the assembly jig on the floor.

[0009] (3) Install the supplementary support rods between the first-layer space frame unit and the second-layer space frame unit to connect the first-layer space frame unit and the second-layer space frame unit into one unit. The lifting system fixes the second-layer space frame unit with the lifting rope and ensures that the first-layer space frame unit and the second-layer space frame unit are lifted synchronously during the lifting process.

[0010] (4) Remove the temporary support under the first layer space frame unit, lift the whole consisting of the first layer space frame unit and the second layer space frame unit to the specified height and suspend it, set a temporary support in the middle of the side span where the second layer space frame unit and the third layer space frame unit are connected, and support the second layer space frame unit with the temporary support. At the same time, assemble the third layer space frame unit on the assembly jig on the floor.

[0011] (5) Install the supplementary support rods between the second-layer space frame unit and the third-layer space frame unit to connect the first-layer space frame unit, the second-layer space frame unit and the third-layer space frame unit into one unit. The lifting system fixes the third-layer space frame unit with lifting ropes and ensures that the first-layer space frame unit, the second-layer space frame unit and the third-layer space frame unit are lifted synchronously during the lifting process.

[0012] (6) Repeat steps (4) to (5) until all space frame units are connected as one unit and all space frame units are simultaneously lifted to the design height through the lifting system.

[0013] The present invention relates to a method for coordinating deformation in the mid-span of the connecting side during the cumulative lifting of a stepped space frame. Specifically, after the space frame is lifted to a certain height, temporary supports are provided in the mid-span of the connecting side, or temporary support rods are used to suspend the lower chord nodes. Then, it is connected to the already assembled lower space frame, so that the deformation of the connecting side space frame is coordinated and synchronized. The temporary support (anti-support or suspension) operation is simple, the stress and bending deformation under the self-weight of the space frame are controlled, the installation accuracy of the space frame is improved, the deformation is coordinated, and the construction process is safe and reliable.

[0014] As a preferred technical solution:

[0015] As described above, in a method for coordinating deformation at mid-span of the cumulative lifting docking side of a stepped space frame, the temporary support is a temporary top support system or a temporary suspension system.

[0016] As described above, a method for coordinating deformation at mid-span of the cumulative lifting docking side of a stepped space frame includes a temporary support system comprising temporary support uprights, temporary support bottom brackets, and jacks.

[0017] The temporary support poles are arranged vertically, with the top of the temporary support poles contacting the bottom of the space frame unit. The lower section of the temporary support poles is provided with a temporary support bottom bracket. The jacks are arranged between the temporary support bottom bracket and the floor. A pad is also provided between the bottom of the temporary support poles and the floor.

[0018] As described above, a method for coordinating deformation at mid-span of the docking side during cumulative lifting of a stepped space frame includes a temporary suspension system comprising temporary suspension uprights and chain hoists.

[0019] The temporary suspension poles are vertically arranged on the floor. The end of the temporary suspension pole away from the floor is provided with a temporary suspension pole bracket. One end of the chain hoist is attached to the temporary suspension pole bracket, and the other end is attached to the space frame unit.

[0020] As described above, a method for coordinating deformation at mid-span of the cumulative lifting docking side of a stepped space frame involves dismantling and assembling the assembly jig used for assembling the first-layer space frame unit after the first-layer space frame unit is lifted.

[0021] As described above, a method for coordinating deformation at mid-span of the docking side during cumulative lifting of a stepped space frame involves dismantling and assembling the assembly jig used for assembling the Nth layer space frame unit after the Nth layer space frame unit is lifted.

[0022] As described above, in a method for coordinating deformation at mid-span of the cumulative lifting docking side of a stepped space frame, the supplementary support members are welded and fixed to the space frame unit.

[0023] The above technical solution is only one feasible technical solution of the present invention. The scope of protection of the present invention is not limited thereto. Those skilled in the art can reasonably adjust the specific design according to actual needs.

[0024] The above invention has the following advantages or beneficial effects:

[0025] (1) The present invention provides a method for coordinating the mid-span deformation of the joint side of the cumulative lifting of stepped space frame, which is aimed at the cumulative lifting construction of stepped or staggered space frame structures. It provides a construction method to reduce the mid-span deformation of the upper space frame unit, ensure the installation accuracy of the interlocking members, and coordinate the stress of the members.

[0026] (2) The method for coordinating deformation in the middle of the cross-span of the cumulative lifting of the stepped space frame of the present invention raises the middle of the cross-span of the space frame by setting simple temporary jacking or suspension measures, controls the deformation coordination problem during the assembly of the space frame, improves the installation accuracy, and is safe and reliable in the construction process, with good application prospects. Attached Figure Description

[0027] The invention, its features, shape, and advantages will become more apparent from the following detailed description of non-limiting embodiments with reference to the accompanying drawings. Like reference numerals denote like parts throughout the drawings. The drawings are not drawn to scale; the emphasis is on illustrating the gist of the invention.

[0028] Figure 1 and 2 These are the front view and top view of the first step state of the method for coordinating the deformation of the mid-span of the docking side for cumulative lifting of stepped space frame according to the present invention;

[0029] Figure 3 and 4These are the front view and top view of the (2) state of the cumulative lifting docking mid-span deformation coordination method for stepped space frame of the present invention;

[0030] Figure 5 and 6 These are the front view and top view of the (3rd) state of the method for coordinating the deformation of the mid-span of the docking side for cumulative lifting of stepped space frame according to the present invention;

[0031] Figure 7 and 8 These are the front view and top view of the (4th) state of the method for coordinating the deformation of the mid-span of the docking side for cumulative lifting of stepped space frame according to the present invention;

[0032] Figure 9 and 10 These are the front view and top view of the fifth step state of the method for coordinating the deformation of the mid-span of the docking side for cumulative lifting of stepped space frame according to the present invention;

[0033] Figure 11 and 12 These are the front view and top view of the (6th) state of the method for coordinating the deformation of the mid-span of the docking side for cumulative lifting of stepped space frame according to the present invention;

[0034] Figure 13 This is a schematic diagram of the temporary support system involved in the present invention;

[0035] Figure 14 This is a schematic diagram of the temporary suspension system involved in the present invention;

[0036] Among them, 1 is the uppermost space frame unit, 2 is the middle layer space frame unit, 3 is the lowermost space frame unit, 4 is the lifting system, 5 is the assembly jig, 6 is the temporary support, 6a is the temporary top support pole, 6a1 is the temporary top support bottom bracket, 6b is the temporary suspension pole, 6b1 is the temporary suspension pole bracket, 7 is the supplementary support member, 8 is the floor, 91 is the jack, 92 is the chain hoist, and 10 is the pad. Detailed Implementation

[0037] The structure of the present invention will be further described below with reference to the accompanying drawings and specific embodiments, but this is not intended to limit the present invention.

[0038] Example 1

[0039] A method for coordinating mid-span deformation on the docking side of a stepped space frame during cumulative lifting includes the following steps:

[0040] (1) As Figures 1-2 As shown, the uppermost space frame unit 1 is assembled on the assembly frame 5 on the floor, and the lifting system 4 is set up and installed. The lifting system 4 fixes the uppermost space frame unit 1 with lifting ropes.

[0041] (2) Figures 3-4 As shown, after the top-level space frame unit 1 is lifted to a specified height and suspended, a temporary support 6 is set in the middle of the side span where the top-level space frame unit 1 and the middle-level space frame unit 2 are connected. The temporary support 6 supports the top-level space frame unit 1. At the same time, the assembly jig 5 used to assemble the top-level space frame unit is removed, and the middle-level space frame unit 2 is assembled on the assembly jig on the floor.

[0042] Temporary support can be a temporary jacking system or a temporary suspension system;

[0043] Temporary support system such as Figure 13 As shown, it includes a temporary support pole 6a, a temporary support bottom bracket 6a1, and a jack 91. The temporary support pole 6a is arranged vertically, and the top of the temporary support pole 6a contacts the bottom of the space frame unit. The lower section of the temporary support pole 6a is provided with a temporary support bottom bracket 6a1. The jack 91 is arranged between the temporary support bottom bracket 6a1 and the floor 5. A pad 10 is also provided between the bottom of the temporary support pole 6a and the floor 5.

[0044] Temporary suspension systems such as Figure 14 As shown, it includes a temporary suspension pole 6b and a chain hoist 92. The temporary suspension pole 6b is vertically arranged on the floor 5. The end of the temporary suspension pole 6b away from the floor is provided with a temporary suspension pole bracket 6b1. One end of the chain hoist 92 is attached to the temporary suspension pole bracket 6b1, and the other end is attached to the space frame unit.

[0045] (3) Figures 5-6 As shown, the interlocking rod 7 (the interlocking rod is welded and fixed to the space frame unit) is installed between the uppermost space frame unit 1 and the middle space frame unit 2 to connect the uppermost space frame unit 1 and the middle space frame unit 2 into one unit. The lifting system 4 fixes the middle space frame unit 2 with the lifting rope and ensures that the uppermost space frame unit 1 and the middle space frame unit 2 are lifted synchronously during the lifting process.

[0046] (4) Figures 7-8 As shown, the temporary support 6 under the uppermost space frame unit 1 is removed, and the whole consisting of the uppermost space frame unit 1 and the middle space frame unit 2 is lifted to the designated height and suspended. Temporary support 6 is set in the middle of the side span where the middle space frame unit 2 and the lowermost space frame unit 3 are connected, and the temporary support 6 supports the middle space frame unit 2. At the same time, the assembly frame 5 used to assemble the middle space frame unit is removed, and the lowermost space frame unit 3 is assembled on the assembly frame 5 on the floor.

[0047] (5) Figures 9-10As shown, the interlocking rod 7 between the intermediate layer space frame unit 2 and the lowest layer space frame unit 3 connects the uppermost layer space frame unit 1, the intermediate layer space frame unit 2 and the lowest layer space frame unit 3 into one unit. The lifting system 4 fixes the lowest layer space frame unit 3 with lifting ropes and ensures that the uppermost layer space frame unit 1, the intermediate layer space frame unit 2 and the lowest layer space frame unit 3 are lifted synchronously during lifting.

[0048] (6) Figures 11-12 As shown, the uppermost space frame unit 1, the middle space frame unit 2 and the lowermost space frame unit 3 are simultaneously lifted to the design height by the lifting system 4, while the assembly jig 5 used to assemble the lowermost space frame unit 3 is removed.

[0049] The above embodiments are for cumulatively lifting a stepped space frame with three layers of space frame units. Of course, those skilled in the art can also adjust the sequence of steps according to actual needs to meet the needs of stepped space frames with more layers of space frame units.

[0050] Verification has shown that the method for coordinating mid-span deformation during cumulative lifting of stepped space frames is specifically designed for the cumulative lifting construction of stepped or staggered space frame structures. It provides a construction method that reduces mid-span deformation of upper space frame units, ensures the installation accuracy of interlocking members, and coordinates the stress on the members. By setting simple temporary jacking or suspension measures, the mid-span of the space frame is lifted, controlling the deformation coordination problem during space frame assembly, improving installation accuracy, ensuring safe and reliable construction, and showing good application prospects.

[0051] Those skilled in the art should understand that variations can be implemented by combining existing technology with the above embodiments, which will not be elaborated here. Such variations do not affect the essence of the present invention, and will not be elaborated here either.

[0052] The preferred embodiments of the present invention have been described above. It should be understood that the present invention is not limited to the specific embodiments described above, and the devices and structures not described in detail should be understood as being implemented in a conventional manner in the art. Any person skilled in the art can make many possible variations and modifications to the technical solutions of the present invention using the methods and techniques disclosed above, or modify them into equivalent embodiments with equivalent changes, without departing from the scope of the present invention. This does not affect the essential content of the present invention. Therefore, any simple modifications, equivalent changes, and modifications made to the above embodiments based on the technical essence of the present invention without departing from the content of the present invention's technical solutions still fall within the protection scope of the present invention.

Claims

1. A method for coordinating deformation at mid-span of the cumulative lifting docking side of a stepped space frame, wherein the stepped space frame comprises N layers of space frame units, the first to the Nth layers of space frame units are arranged sequentially from high to low, and N≥2, characterized in that: Includes the following steps: (1) Assemble the first layer of space frame unit on the assembly jig on the floor, set up and install the lifting system, and fix the first layer of space frame unit by lifting rope; (2) After the first-layer space frame unit is lifted to a specified height and suspended, a temporary support is set in the middle of the side span where the first-layer space frame unit and the second-layer space frame unit are connected, and the first-layer space frame unit is supported by the temporary support. At the same time, the second-layer space frame unit is assembled on the assembly jig on the floor. (3) Installing the supplementary support rods between the first-layer space frame unit and the second-layer space frame unit, that is, connecting the first-layer space frame unit and the second-layer space frame unit into one unit, the lifting system fixes the second-layer space frame unit with the lifting rope and ensures that the first-layer space frame unit and the second-layer space frame unit are lifted synchronously during the lifting; the supplementary support rods are welded and fixed to the space frame unit; (4) Remove the temporary support under the first-layer space frame unit, lift the first-layer space frame unit and the second-layer space frame unit together to the specified height and suspend them. After the first-layer space frame unit is lifted, remove the assembly jig used to assemble the first-layer space frame unit. Set temporary support in the middle of the side span where the second-layer space frame unit and the third-layer space frame unit meet, and support the second-layer space frame unit with the temporary support. At the same time, assemble the third-layer space frame unit on the assembly jig on the floor. (5) Install the supplementary support rods between the second-layer space frame unit and the third-layer space frame unit to connect the first-layer space frame unit, the second-layer space frame unit and the third-layer space frame unit into one unit. The lifting system fixes the third-layer space frame unit with lifting ropes and ensures that the first-layer space frame unit, the second-layer space frame unit and the third-layer space frame unit are lifted synchronously during the lifting process. (6) Repeat steps (4) to (5) until all space frame units are connected as one unit and all space frame units are simultaneously lifted to the design height through the lifting system; The temporary support is a temporary jacking system or a temporary suspension system; The temporary support system includes temporary support poles, temporary support bottom brackets, and jacks; the temporary support poles are arranged vertically, with the top of the temporary support poles contacting the bottom of the space frame unit, the lower section of the temporary support poles being provided with temporary support bottom brackets, the jacks being arranged between the temporary support bottom brackets and the floor, and a pad being provided between the bottom of the temporary support poles and the floor; The temporary suspension system includes temporary suspension poles and chain hoists; the temporary suspension poles are vertically arranged on the floor, and the end of the temporary suspension pole away from the floor is provided with a temporary suspension pole bracket; one end of the chain hoist is attached to the temporary suspension pole bracket, and the other end is attached to the space frame unit.

2. The method for coordinating mid-span deformation of the cumulative lifting docking side of a stepped space frame according to claim 1, characterized in that, After the Nth layer space frame unit is lifted, the assembly jig used to assemble the Nth layer space frame unit is dismantled.