Bailey frame-based high-support formwork support system and construction method
By using a clamping mechanism in the Bailey frame support system, the problem of U-shaped clamps easily falling off during installation is solved, the distribution beam and upper chord are quickly fixed, and the installation efficiency and safety are improved.
Patent Information
- Application Number
- CN202310805544.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-07-03
- Publication Date
- 2025-09-19
- Estimated Expiration
- 2043-07-03
AI Technical Summary
In the Bailey frame support system, the U-shaped clamp is easy to fall off during installation, making installation difficult and posing a safety hazard.
A clamping mechanism is used to achieve rapid clamping and fixation of the distribution beam and the upper chord through the cooperation of the connecting rod, the fixing rod and the spring.
The distribution beam and the upper chord can be quickly fixed, which simplifies the installation process, improves work efficiency and reduces safety risks.
Smart Images

Figure CN116971595B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of building construction, and in particular to a Bailey frame-based high-support formwork support system and a construction method. Background Art
[0002] Bailey frame is a support system commonly used in high-rise formwork to support and fix concrete formwork and support rods. It usually consists of horizontal brackets, columns, adjustment screws and connectors, providing an adjustable support framework so that the formwork can adapt to different heights and layout requirements.
[0003] However, there are still some defects to a certain extent: when binding the upper chord and the distribution beam, it is necessary to put the U-shaped clamp on the distribution beam and then fix it through the bottom. However, this operation can easily cause the U-shaped clamp to fall during installation, requiring the staff below to come up again and easily causing casualties. For this reason, we provide a high-support formwork support system and construction method based on Bailey frames. Summary of the Invention
[0004] In order to make the fixing method simple and convenient, the present application provides a high-support formwork support system and construction method based on Bailey frames.
[0005] The high-support formwork support system based on Bailey frames provided in this application adopts the following technical solutions:
[0006] The high-support formwork support system based on the Bailey frame includes: a clamping mechanism, a stabilizing rod is provided on the outer side of the top of the clamping mechanism, the inner side of the stabilizing rod is fixedly connected to the outer side of the clamping mechanism, a fixing ring is provided on the outer side of the clamping mechanism, a thread is provided on the outer side of the clamping mechanism, the thread is threadedly connected to the fixing ring, a support rod is provided on the outer surface of the fixing ring, the inner side of the support rod is fixedly connected to the outer surface of the fixing ring, a connecting rod 2 is provided at the center of the top of the clamping mechanism, the connecting rod 2 passes through the clamping mechanism and extends to the inside, and a fixing ring is provided inside the clamping mechanism. A limit plate is provided, the inner surface of the limit plate is fixedly connected to the outer surface of the second connecting rod, a baffle is provided at the bottom of the second connecting rod, the top of the baffle is fixedly connected to the bottom of the second connecting rod, two fixing rods are provided on both sides of the baffle, a central axis is provided inside the second fixing rod, the central axis is rotatably connected to the second fixing rod, both ends of the second fixing rod are fixedly connected to the inner surface of the clamping mechanism, a connecting shaft is provided at the bottom of the baffle, the top of the connecting shaft is fixedly connected to the bottom of the baffle, a spring is provided inside the clamping mechanism, and the spring is sleeved on the outside of the connecting shaft.
[0007] Optionally, a distribution beam is provided on the outside of the clamping mechanism, an upper chord is provided at the bottom of the distribution beam, the clamping mechanism passes through the distribution beam and extends to the bottom of the upper chord, and a lower chord is provided at the bottom of the upper chord.
[0008] Optionally, connecting plate 1 is provided on the left and right sides of the upper chord rod, and the inner side of connecting plate 1 is fixedly connected to the outer surface of the upper chord rod; connecting plate 2 is provided on the left and right sides of the lower chord rod, and the inner side of connecting plate 2 is fixedly connected to the outer surface of the lower chord rod; a support plate is provided at the bottom of the lower chord rod, and a scissors frame is provided at the bottom of the support plate, and the outer surface of the scissors frame is fixedly connected to the bottom of the support plate.
[0009] Optionally, a second fixing bolt is provided on the left side of the support plate, and the second fixing bolt passes through the support plate and extends to the inside of the Bailey frame. An I-beam is provided at the bottom of the lower chord, and a unloading device is provided at the bottom of the I-beam.
[0010] Optionally, moving blocks are provided on both sides of the unloading device, a threaded rod is provided inside the unloading device, the threaded rod passes through the moving block and extends to the outside, a connecting ring is provided on the outside of the moving block, the connecting ring and the threaded rod are threadedly connected, a handle is provided on the outer surface of the connecting ring, the inner surface of the handle is fixedly connected to the outer surface of the connecting ring, a steel pipe is provided at the bottom of the unloading device, and a hole is opened on the inner side of the steel pipe.
[0011] Optionally, a chemical bolt is provided at the bottom of the steel pipe, a cement seat is provided at the bottom of the steel pipe, the chemical bolt passes through the steel pipe and extends into the inside of the cement seat, a fixing device is provided at the bottom of the I-beam, a fixing plate is provided inside the fixing device, and the outer surface of the fixing plate is fixedly connected to the inner surface of the fixing device.
[0012] Optionally, a pull rod is provided on the right side of the fixed plate, and a connecting rod 1 is provided on the left side of the pull rod. The right side of the connecting rod 1 is fixedly connected to the left side of the pull rod, and the connecting rod 1 passes through the fixed plate and extends to the interior.
[0013] Optionally, a spring 1 is provided on the left side of the fixed plate, a movable block is provided on the left side of the connecting rod 1, and the right side of the movable block is fixedly connected to the left side of the connecting rod 1.
[0014] Optionally, the spring is sleeved on the outside of a connecting rod 1, a fixing rod 1 is provided on the left side of the movable block, and the right side of the fixing rod 1 is fixedly connected to the left side of the movable block.
[0015] Optionally, the fixing rod 1 is adapted to the hole on the inner side of the steel pipe, a Bailey plate is provided at the bottom of the fixing device, and the top of the Bailey plate is fixedly connected to the bottom of the fixing device.
[0016] The construction method of the high-support formwork support system based on Bailey frame includes the following steps:
[0017] Step 1: First, pour the cement base, install the steel pipe, and then fix it with chemical bolts. Then, install the Bailey plate between the two steel pipes. There are fixing devices on the upper and lower sides of the Bailey plate. Pull the pull rod outward to snap it into the groove on the back. When the pull rod is pulled, the connecting rod 1 and the movable block will move to the right and squeeze the spring 1. When the movable block moves to the right, it will pull the fixing rod 1 into the fixing device.
[0018] Step 2: Place the Bailey plate between the two steel pipes, align the fixing rod with the hole inside the steel pipe, and push the pull rod upward. When the pull rod reaches the top, the spring will rebound after a while. Push the movable block to the left and push the fixing rod into the groove inside the steel pipe to secure it.
[0019] Step 3: Then install the unloading device to the top of the steel pipe and then turn the handle to drive the connecting ring to rotate and squeeze the moving block to control the height. Install the I-beam above the unloading device and then install the Bailey frame on the ground. Connect the connecting plate 2 and the connecting plate 1 on both sides of the Bailey frame, and then fix the connecting plate 2 and the connecting plate 1 with the fixing bolt 1. Then install the support plate on the left side of the Bailey frame and fix the fixing bolt 2 to the Bailey frame with the fixing bolt 2.
[0020] Step 4: After the installation is completed, use a crane to lift the Bailey frame and place it on the I-beam. Then place the distribution beam on the top of the Bailey frame and fix the Bailey frame and the I-beam distribution beam through the clamping mechanism. First, press the connecting rod 2 downward to push the inside of the fixing rod 2 together and squeeze it together with the baffle. The spring 2 will retract the fixing rod 2 into the inside.
[0021] Step 5: Then extend the clamping mechanism through the distribution beam to the bottom of the upper chord and then loosen the spring 2 of the connecting rod 2, and start to rebound to push the baffle and the connecting rod 2 upward. When the baffle is upward, it will squeeze the bottom of the fixed rod 2 to extend it outward, and then rotate the fixing ring so that it can be threaded downward to clamp the distribution beam and the upper chord with the fixed rod 2. If it is difficult to rotate the fixing ring, you can use a control tool to sleeve it on the outside of the support rod to rotate it.
[0022] In summary, this application includes at least one of the following beneficial technical effects:
[0023] The present invention presses the connecting rod 2 downward to push the fixing rod 2 closer to the inside and squeezes the spring 2 together with the baffle. When the fixing rod 2 is retracted into the inside, the clamping mechanism is extended through the distribution beam to the bottom of the upper chord rod, and then the connecting rod 2 is released. The spring 2 starts to rebound and pushes the baffle and the connecting rod 2 upward. When the baffle is upward, it squeezes the bottom of the fixing rod 2 to extend it outward, and then the fixing ring is rotated to clamp the distribution beam and the upper chord rod downward through the thread of the fixing rod 2. The distribution beam and the upper chord rod can be quickly fixed with simple operation and high work efficiency.
[0024] The present invention is provided with a fixing device, and the pull rod is pulled outward to clamp it into the groove on the back. When the pull rod is pulled, the connecting rod 1 and the movable block will be driven to move to the right and squeeze the spring 1. When the movable block moves to the right, the fixing rod 1 will be pulled into the fixing device, and then the fixing rod 1 will be aligned with the hole on the inner side of the steel pipe. Then the pull rod is pushed upward. After the pull rod is pushed to the top, the spring 1 will start to rebound after a while, pushing the movable block to the left and then pushing the fixing rod 1 into the groove inside the steel pipe for fixing. The Bailey plate can be quickly fixed between the two steel pipes. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 It is a schematic diagram of the overall structure of the present invention;
[0026] Figure 2 It is a schematic diagram of the internal structure of the fixing device of the present invention;
[0027] Figure 3 It is a structural schematic diagram of the unloading device of the present invention;
[0028] Figure 4 It is a schematic diagram of the left side structure of the Bailey frame of the present invention;
[0029] Figure 5 It is a schematic diagram of the internal structure of the clamping mechanism of the present invention;
[0030] Figure 6 This is a front structural schematic diagram of the Bailey frame of the present invention;
[0031] Figure 7 yes Figure 1 A partial enlarged view of middle A.
[0032] Explanation of reference numerals: 1. Cement seat; 101. Steel pipe; 102. Chemical bolt; 103. I-beam; 104. Distribution beam; 2. Fixing device; 201. Fixing rod 1; 202. Movable block; 203. Spring 1; 204. Connecting rod 1; 205. Fixing plate; 206. Pull rod; 3. Clamping mechanism; 301. Stabilizing rod; 302. Fixing ring; 303. Support rod; 304. Limiting plate; 305. Connecting rod 2; 306. Thread; 30 7. Fixing rod 2; 308. Center axis; 309. Baffle; 310. Spring 2; 311. Connecting shaft; 4. Bailey frame; 401. Lower chord; 402. Upper chord; 403. Connecting plate 1; 404. Connecting plate 2; 405. Fixing bolt 1; 406. Support plate; 407. Scissors frame; 408. Fixing bolt 2; 5. Unloading device; 501. Moving block; 502. Threaded rod; 503. Handle; 504. Connecting ring; 6. Bailey piece. DETAILED DESCRIPTION
[0033] The following is combined with Figure 1—7 provides further details of this application.
[0034] Reference Figure 1-7 The high-support formwork support system based on the Bailey frame includes: a clamping mechanism 3, a stabilizing rod 301 is provided on the outside of the top of the clamping mechanism 3, the inner side of the stabilizing rod 301 is fixedly connected to the outer side of the clamping mechanism 3, a fixing ring 302 is provided on the outer side of the clamping mechanism 3, a thread 306 is provided on the outer side of the clamping mechanism 3, the thread 306 is threadedly connected to the fixing ring 302, a support rod 303 is provided on the outer surface of the fixing ring 302, the inner side of the support rod 303 is fixedly connected to the outer surface of the fixing ring 302, and a connecting rod 303 is provided at the center of the top of the clamping mechanism 3. 05, the second connecting rod 305 passes through the clamping mechanism 3 and extends to the inside, a limit plate 304 is provided inside the clamping mechanism 3, the inner surface of the limit plate 304 is fixedly connected to the outer surface of the second connecting rod 305, a baffle 309 is provided at the bottom of the second connecting rod 305, the top of the baffle 309 is fixedly connected to the bottom of the second connecting rod 305, a second fixing rod 307 is provided on both sides of the baffle 309, a central axis 308 is provided inside the second fixing rod 307, the central axis 308 is rotatably connected to the second fixing rod 307, and both ends of the second fixing rod 307 are connected to the clamping mechanism 3 The inner surface is fixedly connected, a connecting shaft 311 is provided at the bottom of the baffle 309, and the top of the connecting shaft 311 is fixedly connected to the bottom of the baffle 309. A spring 2 310 is provided inside the clamping mechanism 3, and the spring 2 310 is sleeved on the outside of the connecting shaft 311. By pressing the connecting rod 2 305 to push the fixing rod 2 307 downward to get closer and squeeze the spring 2 310 together with the baffle 309. When the fixing rod 2 307 is retracted to the inside, the clamping mechanism 3 is then extended through the distribution beam 104 to the bottom of the upper chord rod 402 and then the connecting rod 2 305 is released. The second spring 310 begins to rebound, pushing the baffle 309 and the second connecting rod 305 upward. When the baffle 309 moves upward, it squeezes the bottom of the second fixing rod 307, causing it to extend outward. Then, the fixing ring 302 is rotated to clamp the distribution beam 104 and the upper chord rod 402 downward with the second fixing rod 307 through the thread 306. This allows the distribution beam 104 and the upper chord rod 402 to be fixed quickly and easily. The operation is efficient. The baffle 309 pushes the bottom of the second fixing rod 307 upward, causing the other side to expand outward.
[0035] A distribution beam 104 is provided on the outside of the clamping mechanism 3, an upper chord 402 is provided at the bottom of the distribution beam 104, the clamping mechanism 3 passes through the distribution beam 104 and extends to the bottom of the upper chord 402, and a lower chord 401 is provided at the bottom of the upper chord 402; the upper chord 402 and the distribution beam 104 are fixed by the clamping mechanism 3.
[0036] Connecting plates 1 403 are provided on the left and right sides of the upper chord 402, and the inner side of connecting plate 1 403 is fixedly connected to the outer surface of the upper chord 402. Connecting plates 2 404 are provided on the left and right sides of the lower chord 401, and the inner side of connecting plate 2 404 is fixedly connected to the outer surface of the lower chord 401. A support plate 406 is provided at the bottom of the lower chord 401, and a scissors frame 407 is provided at the bottom of the support plate 406, and the outer surface of the scissors frame 407 is fixedly connected to the bottom of the support plate 406. Multiple Bailey frames 4 can be connected through connecting plate 1 403 and connecting plate 2 404.
[0037] A second fixing bolt 408 is provided on the left side of the support plate 406. The second fixing bolt 408 passes through the support plate 406 and extends to the inside of the Bailey frame 4. An I-beam 103 is provided at the bottom of the lower chord 401. A unloading device 5 is provided at the bottom of the I-beam 103. The scissors frame 407 is fixed to the Bailey frame 4 by the second fixing bolt 408.
[0038] Moving blocks 501 are provided on both sides of the unloading device 5, and a threaded rod 502 is provided inside the unloading device 5. The threaded rod 502 penetrates the moving block 501 and extends to the outside. A connecting ring 504 is provided on the outside of the moving block 501. The connecting ring 504 is threadedly connected to the threaded rod 502. A handle 503 is provided on the outer surface of the connecting ring 504. The inner surface of the handle 503 is fixedly connected to the outer surface of the connecting ring 504. A steel pipe 101 is provided at the bottom of the unloading device 5, and a hole is opened on the inner side of the steel pipe 101. The height of different areas can be adjusted through the unloading device 5.
[0039] A chemical bolt 102 is provided at the bottom of the steel pipe 101, and a cement seat 1 is provided at the bottom of the steel pipe 101. The chemical bolt 102 penetrates the steel pipe 101 and extends into the inside of the cement seat 1. A fixing device 2 is provided at the bottom of the I-beam 103, and a fixing plate 205 is provided inside the fixing device 2. The outer surface of the fixing plate 205 is fixedly connected to the inner surface of the fixing device 2. The chemical bolt 102 can fix the steel pipe 101 on the cement seat 1.
[0040] A pull rod 206 is provided on the right side of the fixed plate 205, and a connecting rod 1 204 is provided on the left side of the pull rod 206. The right side of the connecting rod 1 204 is fixedly connected to the left side of the pull rod 206. The connecting rod 1 204 passes through the fixed plate 205 and extends to the inside. When the pull rod 206 is pulled outward, it is stuck in the groove on the back. When the pull rod 206 is pulled, the connecting rod 1 204 and the movable block 202 are moved to the right and squeeze the spring 1 203. When the movable block 202 moves to the right, the fixed rod 1 204 is pressed against the spring 1 203. 01 is pulled into the fixing device 2, and then the fixing rod 201 is aligned with the hole on the inside of the steel pipe 101, and then the pull rod 206 is pushed upward. After the pull rod 206 is pushed to the top, the spring 203 will start to rebound, and the movable block 202 is pushed to the left. Then the fixing rod 201 is pushed into the groove inside the steel pipe 101 for fixing. The Bailey piece 6 can be quickly fixed between the two steel pipes 101. The Bailey piece 6 is fixed between the two steel pipes 101 through the fixing device 2.
[0041] A spring 203 is provided on the left side of the fixed plate 205, and a movable block 202 is provided on the left side of the connecting rod 204. The right side of the movable block 202 is fixedly connected to the left side of the connecting rod 204. After the spring 203 loses its force, the internal structure of the fixing device 2 can be restored.
[0042] Spring 1 203 is sleeved on the outside of connecting rod 1 204 , a fixed rod 1 201 is provided on the left side of the movable block 202 , the right side of the fixed rod 1 201 is fixedly connected to the left side of the movable block 202 , and the movable block 202 can push the fixed rod 1 201 to move.
[0043] The fixing rod 201 is adapted to the hole inside the steel pipe 101 . A Bailey piece 6 is provided at the bottom of the fixing device 2 . The top of the Bailey piece 6 is fixedly connected to the bottom of the fixing device 2 . The Bailey piece 6 can increase the stability of the steel pipe 101 .
[0044] The construction method of the high-support formwork support system based on Bailey frame includes the following steps:
[0045] Step 1: First, pour the cement base 1, install the steel pipe 101, and then use the chemical bolt 102 to fix it. Then, install the Bailey piece 6 between the two steel pipes 101. The Bailey piece 6 is provided with a fixing device 2 on the upper and lower sides. Pull the pull rod 206 outward to snap it into the groove on the back. When pulling the pull rod 206, it will drive the connecting rod 1 204 and the movable block 202 to move to the right and squeeze the spring 1 203. When the movable block 202 moves to the right, it will pull the fixing rod 1 201 into the fixing device 2.
[0046] Step 2: Place the Bailey plate 6 between the two steel pipes 101, align the fixing rod 201 with the hole inside the steel pipe 101, and push the pull rod 206 upward. When the pull rod 206 reaches the top, the spring 203 will start to rebound, push the movable block 202 to the left, and then push the fixing rod 201 into the groove inside the steel pipe 101 to fix it;
[0047] Step 3: Then install the unloading device 5 to the top of the steel pipe 101 and then twist the handle 503 to drive the connecting ring 504 to rotate and squeeze the moving block 501 to control the height. Install the I-beam 103 above the unloading device 5 and then install the Bailey frame 4 on the ground. Connect the connecting plate 2 404 and the connecting plate 1 403 on both sides of the Bailey frame 4, and then fix the connecting plate 2 404 and the connecting plate 1 403 with the fixing bolt 1 405. Then install the support plate 406 on the left side of the Bailey frame 4 and then fix the fixing bolt 2 408 to the Bailey frame 4 with the fixing bolt 2 408;
[0048] Step 4: After the installation is completed, use a crane to lift the Bailey frame 4 and place it on the I-beam 103. Then place the distribution beam 104 on the top of the Bailey frame 4. Use the clamping mechanism 3 to fix the Bailey frame 4 and the I-beam distribution beam 104. First, press the second connecting rod 305 to push the second fixing rod 307 downward to push it together with the baffle 309. The second spring 310 retracts the second fixing rod 307 into the interior.
[0049] Step 5: Then extend the clamping mechanism 3 through the distribution beam 104 to the bottom of the upper chord rod 402 and then loosen the spring 2 310 of the connecting rod 2 305, and start to rebound to push the baffle 309 and the connecting rod 2 305 upward. When the baffle 309 is upward, it will squeeze the bottom of the fixing rod 2 307 to extend it outward, and then rotate the fixing ring 302 so that it can clamp the distribution beam 104 and the upper chord rod 402 downward through the thread 306 and the fixing rod 2 307. If it is difficult to rotate the fixing ring 302, you can use a control tool to sleeve it on the outside of the support rod 303 to rotate it.
[0050] The implementation principles of the high-support formwork support system and construction method based on Bailey frames in the embodiment of the present application are as follows:
[0051] First, pour the cement seat 1, install the steel pipe 101, and then use the chemical bolt 102 to fix it. Then, install the Bailey piece 6 between the two steel pipes 101. Fixing devices 2 are set on the upper and lower sides of the Bailey piece 6. Pull the pull rod 206 outward to snap it into the groove on the back. When pulling the pull rod 206, it will drive the connecting rod 1 204 and the movable block 202 to move to the right and squeeze the spring 1 203. When the movable block 202 moves to the right, it will pull the fixing rod 1 201 into the fixing device 2. Then place the Bailey piece 6 between the two steel pipes 101, and then make the fixing rod 1 20 1 Align the hole on the inner side of the steel pipe 101 and then push the pull rod 206 upwards. After pushing the pull rod 206 to the top, the spring 1 203 will start to rebound. Push the movable block 202 to the left and then push the fixing rod 1 201 into the groove inside the steel pipe 101 to fix it. Then install the unloading device 5 to the top of the steel pipe 101 and then twist the handle 503 to drive the connecting ring 504 to rotate and squeeze the moving block 501 to control the height. Install the I-beam 103 above the unloading device 5 and then install the Bailey frame 4 on the ground. Connect the connecting plate 2 404 and the connecting plate 1 403 on both sides of the Bailey frame 4, and then pass Fix the connecting plate 2 404 and the connecting plate 1 403 by fixing bolt 1 405, then install the support plate 406 on the left side of the Bailey frame 4, and then fix the fixing bolt 2 408 to the Bailey frame 4 by fixing bolt 2 408. After the installation is completed, use a crane to lift the Bailey frame 4 and place it on the I-beam 103. Then place the distribution beam 104 on the top of the Bailey frame 4 and fix the Bailey frame 4 and the I-beam distribution beam 104 by the clamping mechanism 3. First press the connecting rod 2 305 to push the fixing rod 2 307 downward to push it together with the baffle 309. The spring 2 310 is used as a fixing The fixed rod 2 307 is retracted into the inside, and then the clamping mechanism 3 is extended through the distribution beam 104 to the bottom of the upper chord rod 402 and then the spring 2 310 of the connecting rod 2 305 is released, and it starts to rebound to push the baffle 309 and the connecting rod 2 305 upward. When the baffle 309 is upward, it will squeeze the bottom of the fixed rod 2 307 to extend it outward, and then the fixing ring 302 is rotated so that it can clamp the distribution beam 104 and the upper chord rod 402 downward with the fixing rod 2 307 through the thread 306. If it is difficult to rotate the fixing ring 302, you can use a control tool to sleeve it on the outside of the support rod 303 to rotate it.
[0052] The above are all preferred embodiments of the present application, and are not intended to limit the scope of protection of the present application. Therefore, any equivalent changes made based on the structure, shape, and principle of the present application should be included in the scope of protection of the present application.
Claims
1. The high-support formwork support system based on Bailey frames is characterized by: include: A clamping mechanism (3), wherein a stabilizing rod (301) is provided on the outside of the top of the clamping mechanism (3), and the inner side of the stabilizing rod (301) is fixedly connected to the outer side of the clamping mechanism (3); a fixing ring (302) is provided on the outer side of the clamping mechanism (3), and a thread (306) is provided on the outer side of the clamping mechanism (3), and the thread (306) is threadedly connected to the fixing ring (302); a support rod (303) is provided on the outer surface of the fixing ring (302), and the inner side of the support rod (303) is fixedly connected to the outer surface of the fixing ring (302); a connecting rod 2 (305) is provided at the center of the top of the clamping mechanism (3), and the connecting rod 2 (305) passes through the clamping mechanism (3) and extends to the inside; a limiting plate (304) is provided inside the clamping mechanism (3), and the inner side of the limiting plate (304) The surface is fixedly connected to the outer surface of the second connecting rod (305), the bottom of the second connecting rod (305) is provided with a baffle (309), the top of the baffle (309) is fixedly connected to the bottom of the second connecting rod (305), the two sides of the baffle (309) are provided with a second fixing rod (307), the inside of the second fixing rod (307) is provided with a central shaft (308), the central shaft (308) is rotatably connected to the second fixing rod (307), the two ends of the second fixing rod (307) are fixedly connected to the inner surface of the clamping mechanism (3), the bottom of the baffle (309) is provided with a connecting shaft (311), the top of the connecting shaft (311) is fixedly connected to the bottom of the baffle (309), the inside of the clamping mechanism (3) is provided with a second spring (310), the second spring (310) is sleeved on the outside of the connecting shaft (311); A distribution beam (104) is provided on the outside of the clamping mechanism (3), an upper chord (402) is provided at the bottom of the distribution beam (104), the clamping mechanism (3) passes through the distribution beam (104) and extends to the bottom of the upper chord (402), and a lower chord (401) is provided at the bottom of the upper chord (402); The upper chord (402) is provided with a connecting plate 1 (403) on both sides, the inner side of the connecting plate 1 (403) is fixedly connected to the outer surface of the upper chord (402), the lower chord (401) is provided with a connecting plate 2 (404) on both sides, the inner side of the connecting plate 2 (404) is fixedly connected to the outer surface of the lower chord (401), the bottom of the lower chord (401) is provided with a support plate (406), the bottom of the support plate (406) is provided with a scissors frame (407), the outer surface of the scissors frame (407) is fixedly connected to the bottom of the support plate (406); A second fixing bolt (408) is provided on the left side of the support plate (406), and the second fixing bolt (408) passes through the support plate (406) and extends into the interior of the Bailey frame (4); an I-beam (103) is provided at the bottom of the lower chord (401), and a discharging device (5) is provided at the bottom of the I-beam (103); Moving blocks (501) are provided on both sides of the unloading device (5), a threaded rod (502) is provided inside the unloading device (5), the threaded rod (502) passes through the moving block (501) and extends to the outside, a connecting ring (504) is provided on the outside of the moving block (501), the connecting ring (504) and the threaded rod (502) are threadedly connected, a handle (503) is provided on the outer surface of the connecting ring (504), the inner surface of the handle (503) is fixedly connected to the outer surface of the connecting ring (504), and a steel pipe (101) is provided at the bottom of the unloading device (5), and a hole is opened on the inner side of the steel pipe (101).
2. The high-support formwork support system based on Bailey frames according to claim 1, characterized in that: A chemical bolt (102) is provided at the bottom of the steel pipe (101), a cement seat (1) is provided at the bottom of the steel pipe (101), the chemical bolt (102) penetrates the steel pipe (101) and extends into the interior of the cement seat (1), a fixing device (2) is provided at the bottom of the I-beam (103), a fixing plate (205) is provided inside the fixing device (2), and the outer surface of the fixing plate (205) is fixedly connected to the inner surface of the fixing device (2).
3. The high-rise formwork support system based on Bailey frames according to claim 2, characterized in that: A pull rod (206) is provided on the right side of the fixed plate (205), a connecting rod 1 (204) is provided on the left side of the pull rod (206), the right side of the connecting rod 1 (204) is fixedly connected to the left side of the pull rod (206), the connecting rod 1 (204) passes through the fixed plate (205) and extends to the inside, a spring 1 (203) is provided on the left side of the fixed plate (205), a movable block (202) is provided on the left side of the connecting rod 1 (204), and the right side of the movable block (202) is fixedly connected to the left side of the connecting rod 1 (204).
4. The high-rise formwork support system based on Bailey frames according to claim 3 is characterized in that: The spring 1 (203) is sleeved on the outside of the connecting rod 1 (204), and a fixed rod 1 (201) is provided on the left side of the movable block (202), and the right side of the fixed rod 1 (201) is fixedly connected to the left side of the movable block (202).
5. The high-rise formwork support system based on Bailey frames according to claim 4 is characterized in that: The fixing rod 1 (201) is adapted to the hole on the inner side of the steel pipe (101), and a Bailey plate (6) is provided at the bottom of the fixing device (2), and the top of the Bailey plate (6) is fixedly connected to the bottom of the fixing device (2).
6. A construction method for a Bailey frame-based high-rise formwork support system according to claim 4, characterized in that: The following steps are involved: Step 1: First, pour the cement base (1), install the steel pipe (101), and then use chemical bolts (102) to fix it. Then, install the Bailey plate (6) between the two steel pipes (101). Fixing devices (2) are set on the upper and lower sides of the Bailey plate (6). Pull the pull rod (206) outward to snap it into the groove on the back. When pulling the pull rod (206), it will drive the connecting rod 1 (204) and the movable block (202) to move to the right and squeeze the spring 1 (203). When the movable block (202) moves to the right, it will pull the fixing rod 1 (201) into the fixing device (2); Step 2: Then place the Bailey plate (6) between the two steel pipes (101), then align the fixing rod (201) with the hole inside the steel pipe (101), and then push the pull rod (206) upward. After pushing the pull rod (206) to the top, the spring (203) will start to rebound, push the movable block (202) to the left, and then push the fixing rod (201) into the groove inside the steel pipe (101) to fix it; Step 3: Then install the unloading device (5) to the top of the steel pipe (101) and then twist the handle (503) to drive the connecting ring (504) to rotate the extrusion moving block (501) to control the height, install the I-beam (103) above the unloading device (5) and then install the Bailey frame (4) on the ground, connect the connecting plate 2 (404) and the connecting plate 1 (403) on both sides of the Bailey frame (4), and then fix the connecting plate 2 (404) and the connecting plate 1 (403) by fixing bolt 1 (405), and then install the support plate (406) on the left side of the Bailey frame (4) and then fix the fixing bolt 2 (408) to the Bailey frame (4) by fixing bolt 2 (408); Step 4: After the installation is completed, use a crane to lift the Bailey frame (4) and place it on the I-beam (103). Then place the distribution beam (104) on the top of the Bailey frame (4). Fix the Bailey frame (4) and the I-beam distribution beam (104) through the clamping mechanism (3). First, press the connecting rod 2 (305) downward to push the fixing rod 2 (307) closer to the inside and squeeze it together with the baffle (309). The spring 2 (310) retracts the fixing rod 2 (307) to the inside. Step 5: Then extend the clamping mechanism (3) through the distribution beam (104) to the bottom of the upper chord (402) and then loosen the spring (310) of the connecting rod (305). The spring (310) starts to rebound and push the baffle (309) and the connecting rod (305) upward. When the baffle (309) moves upward, it squeezes the bottom of the fixing rod (307) to extend it outward. Then rotate the fixing ring (302) so that it can clamp the distribution beam (104) and the upper chord (402) downward with the fixing rod (307) through the thread (306). If it is difficult to rotate the fixing ring (302), you can use a control tool to connect it to the outside of the support rod (303) to rotate it.
Citation Information
Patent Citations
Pedicle screw with barbs, and pusher and method for forming pedicle screw
CN103654936A
Fishbone-shaped anchor rod
CN106567384A