A method, device, equipment and medium for installing a replaceable balance steel plate

By using finite element model simulation and real-time monitoring, the problem of tunnel displacement caused by adjacent engineering was solved, and the installation of replaceable balancing steel plates was realized, ensuring the tunnel structure's resistance to displacement and stability.

CN117172065BActive Publication Date: 2025-11-28CHINA RAILWAY ENG CONSULTING GRP CO LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202311165611.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-09-11
Publication Date
2025-11-28
Estimated Expiration
2043-09-11

AI Technical Summary

Technical Problem

In urban rail transit, existing technologies have failed to effectively reduce the displacement of tunnel structures due to the impact of adjacent construction on existing tunnels, and the tunnels themselves lack the ability to resist displacement.

Method used

The offset is obtained through finite element model simulation to determine whether a replaceable balance steel plate needs to be installed, the installation range and angle are determined, and the steel plate connection nodes are monitored in real time to realize the real-time replacement of the balance steel plate.

Benefits of technology

It effectively reduces tunnel offset, prevents the balancing steel plate from failing under severe soil deformation, and maintains the stability and waterproof performance of the tunnel structure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117172065B_ABST
    Figure CN117172065B_ABST
Patent Text Reader

Abstract

The present application relates to the field of tunnel and underground engineering, and relates to a replaceable balanced steel plate installation method, device, equipment and medium, the method comprises obtaining first information, the first information includes the offset caused by the near engineering to the existing tunnel simulated and simulated by the finite element model; whether the existing tunnel is reinforced according to the first information, wherein if the first information is greater than the preset threshold information, the existing tunnel needs to be installed with a reinforcing device, and the reinforcing device is a replaceable balanced steel plate; the installation range of the reinforcing device in the existing tunnel is determined, and the second information is obtained; the installation angle is determined according to the second information, and the third information is obtained; after the reinforcing device is installed according to the third information and is monitored in real time, whether the reinforcing device needs to be replaced is judged, the balanced steel plate can be replaced in real time through real-time monitoring of the balanced steel plate connecting node, and the problem that the balanced steel plate loses the expected effect due to the fact that the soil deformation is too severe can be avoided.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The present application relates to the field of tunnels and underground engineering, in particular to a replaceable balance steel plate installation method, device, equipment and medium. BACKGROUND

[0002] Due to the rapid development of urban rail transit, the scale of rail transit is increasingly dense, and construction of building foundation and foundation pit near existing tunnels frequently occurs. The construction of the near engineering affects the stability and balance of the surrounding soil. The prior art improves soil parameters by using physical or chemical methods to achieve the purpose of reducing soil deformation, thereby reducing the influence of the construction of the near engineering on the existing tunnel. However, this way does not have the ability to resist deviation of the tunnel structure itself, and therefore there is an urgent need for a replaceable balance steel plate installation method that enables the tunnel structure itself to have the ability to resist deviation by installing a replaceable balance steel plate. SUMMARY

[0003] The present application aims to provide a replaceable balance steel plate installation method, device, equipment and readable storage medium to improve the above problems.

[0004] To achieve the above-mentioned purpose, the embodiments of the present application provide the following technical solutions:

[0005] In one aspect, the present application provides a replaceable balance steel plate installation method, which comprises:

[0006] obtaining first information, the first information including the offset caused by the near engineering to the existing tunnel simulated and simulated by a finite element model;

[0007] determining whether to reinforce the existing tunnel according to the first information, wherein if the first information is greater than a preset threshold information, a reinforcing device, which is a replaceable balance steel plate, needs to be installed in the existing tunnel;

[0008] determining the installation range of the reinforcing device in the existing tunnel to obtain second information;

[0009] determining the installation angle according to the second information to obtain third information;

[0010] monitoring in real time after installing the reinforcing device according to the third information to determine whether the reinforcing device needs to be replaced.

[0011] In a second aspect, the present application provides a replaceable balance steel plate installation device, which comprises:

[0012] an obtaining module for obtaining first information, the first information including the offset caused by the near engineering to the existing tunnel simulated and simulated by a finite element model;

[0013] a judging module, configured to judge whether the existing tunnel needs to be reinforced according to the first information, wherein if the first information is greater than a preset threshold information, the existing tunnel needs to be installed with a reinforcing device, and the reinforcing device is a replaceable balanced steel plate;

[0014] a first processing module, configured to determine an installation range of the reinforcing device in the existing tunnel, and obtain second information;

[0015] a second processing module, configured to determine an installation angle according to the second information, and obtain third information;

[0016] a monitoring module, configured to monitor in real time after the reinforcing device is installed according to the third information, and judge whether the reinforcing device needs to be replaced.

[0017] In a third aspect, an embodiment of the present application provides an installation device of a replaceable balanced steel plate, and the device comprises a memory and a processor. The memory is used to store a computer program, and the processor is used to execute the computer program to realize the steps of the installation method of the replaceable balanced steel plate.

[0018] In a fourth aspect, an embodiment of the present application provides a readable storage medium, and the readable storage medium stores a computer program. When the computer program is executed by a processor, the steps of the installation method of the replaceable balanced steel plate are realized.

[0019] The present application has the following beneficial effects:

[0020] The present application judges whether the existing tunnel needs to be installed with a balanced steel plate for reinforcement by simulating the offset of the existing tunnel caused by the approaching engineering through a finite element model. If the existing tunnel needs to be reinforced, the installation range of the balanced steel plate in the existing tunnel is further determined, and then the installation angle is determined in the installation range to install the replaceable balanced steel plate. In addition, the replaceable balanced steel plate can be effectively replaced in real time through real-time monitoring of the connection nodes of the balanced steel plate, so that the problem that the balanced steel plate loses the expected effect due to excessive deformation of the soil body in some special cases can be avoided.

[0021] Other features and advantages of the present application will be described in the following description, and some will become apparent from the description, or will be understood from the practice of the present application. The purpose and other advantages of the present application can be achieved and obtained by the structures specifically pointed out in the written description, claims, and drawings. BRIEF DESCRIPTION OF DRAWINGS

[0022] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the following will briefly introduce the drawings needed to be used in the embodiments. It should be understood that the following drawings only show some of the embodiments of the present application, and therefore should not be considered as a limitation to the scope. For those skilled in the art, other related drawings can also be obtained from these drawings without creative labor.

[0023] Figure 1 The installation method flowchart of the replaceable balance steel plate described in the embodiments of the present application.

[0024] Figure 2 The installation device structure diagram of the replaceable balance steel plate described in the embodiments of the present application.

[0025] Figure 3 The installation device structure diagram of the replaceable balance steel plate described in the embodiments of the present application.

[0026] Figure 4 The position diagram of the approaching engineering and the existing tunnel described in the embodiments of the present application.

[0027] The figure is marked: 901, acquisition module; 902, judgment module; 903, first processing module; 904, second processing module; 905, monitoring module; 9031, first acquisition unit; 9032, first judgment unit; 9033, first processing unit; 90331, second processing unit; 90332, third processing unit; 9041, four processing units; 9042, fifth processing unit; 9043, sixth processing unit; 9044, first calculation unit; 9051, second acquisition unit; 9052, second calculation unit; 9053, second judgment unit; 90531, third calculation unit; 90532, third judgment unit; 90533, fourth judgment unit; 90534, fifth judgment unit; 800, installation equipment of replaceable balance steel plate; 801, processor; 802, memory; 803, multimedia assembly; 804, I / O interface; 805, communication assembly; 1, approaching engineering; 2, existing tunnel; 3, balance steel plate. DETAILED DESCRIPTION

[0028] In order to make the objects, technical solutions and advantages of the embodiments of the present application clearer, the following will be combined with the accompanying drawings of the embodiments of the present application to make a clear and complete description of the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only a part of the embodiments of the present application, rather than all the embodiments. The components of the embodiments of the present application described and shown in the accompanying drawings can be arranged and designed in various different configurations. Therefore, the following detailed description of the embodiments of the present application provided in the accompanying drawings is not intended to limit the scope of the claimed present application, but only represents selected embodiments of the present application. Based on the embodiments in the present application, all other embodiments obtained by those of ordinary skill in the art without creative work fall within the scope of protection of the present application.

[0029] It should be noted that: similar reference numbers and letters represent similar items in the following drawings, therefore, once an item is defined in one drawing, it does not need to be further defined and explained in subsequent drawings. Meanwhile, in the description of the present application, the terms "first", "second" and the like are only used to distinguish the description, and cannot be understood as indicating or implying relative importance.

[0030] Embodiment 1

[0031] The present embodiment provides a mounting method of replaceable balanced steel plate, it can be understood that a scene can be laid out in the present embodiment, for example: the scene that the existing tunnel is influenced by the offset of the adjacent engineering near the existing tunnel.

[0032] Referring to Figure 1 , the present method includes steps S1, S2, S3, S4 and S5, which are specifically:

[0033] Step S1, obtaining first information, the first information includes the offset of the existing tunnel caused by the adjacent engineering simulated and simulated by the finite element model;

[0034] In the present step, the offset of the existing tunnel caused by the adjacent engineering can be obtained by establishing the coupling finite element model of the existing tunnel and the adjacent engineering and simulating it, it should be noted that the establishment of the coupling model of the existing tunnel and the adjacent engineering is a technical solution known to those skilled in the art, therefore, it will not be described here.

[0035] Step S2, judging whether to reinforce the existing tunnel according to the first information, wherein if the first information is greater than the preset threshold information, the reinforcing device needs to be installed on the existing tunnel, and the reinforcing device is a replaceable balanced steel plate;

[0036] In this step, when the result of the numerical simulation simulation is less than the requirement of the existing tunnel related specification or local standard, i.e. the preset threshold information, it is not necessary to install the reinforcing device; when the result of the numerical simulation simulation is greater than the requirement of the existing tunnel related specification or local standard, i.e. the preset threshold information, it is necessary to install the balanced steel plate to provide the anti-deviation capability for the existing tunnel.

[0037] Step S3, determining the installation range of the reinforcing device in the existing tunnel, to obtain second information;

[0038] It can be understood that in the step S3, steps S31, S32 and S33 are further included, which are specifically:

[0039] Step S31, obtaining the position information of the existing tunnel and the position information of the adjacent engineering;

[0040] In this step, the position information of the existing tunnel and the adjacent engineering can be determined through field survey.

[0041] Step S32, judging whether there is an overlapping part in the planar projection of the existing tunnel and the adjacent engineering according to the position information of the existing tunnel and the position information of the adjacent engineering, to obtain a judgment result;

[0042] Step S33, determining the installation range of the reinforcing device according to the judgment result.

[0043] It can be understood that in the step S33, steps S331 and S332 are further included, which are specifically:

[0044] Step S331, when the judgment result is that there is an overlapping part in the planar projection of the existing tunnel and the adjacent engineering, a first extension line is extended to both sides of the existing tunnel with the midpoint of the overlapping part of the planar projection of the existing tunnel and the adjacent engineering as the center, the distance between the segment on the existing tunnel and the first extension line is calculated to obtain the first deviation value information of the segment, and it is judged whether the first deviation value of each segment meets the safety requirement, wherein the last ring segment of the segment meeting the safety requirement is taken as the reinforcing boundary;

[0045] Step S332, when the judgment result is that there is no overlapping part in the planar projection of the existing tunnel and the adjacent engineering, a second extension line is extended to both sides of the existing tunnel with the point closest to the perpendicular distance between the planar projection of the adjacent engineering and the existing tunnel as the center, the center is located on the planar projection of the adjacent engineering, the distance between the segment on the existing tunnel and the second extension line is calculated to obtain the second deviation value information of the segment, and it is judged whether the second deviation value of each segment meets the safety requirement, wherein the last ring segment of the segment meeting the safety requirement is taken as the reinforcing boundary.

[0046] In the embodiment, firstly, it is judged whether there is an overlapping part between the existing tunnel and the planar projection of the approaching engineering, then the center extension line is determined in different ways according to the judgment result, the distance between the segment and the extension line on the existing tunnel is calculated according to the extension line, the offset value information is obtained, then it is judged whether the offset value information meets the safety specification, so as to determine the installation boundary of the balance steel plate, and the installation range of the reinforcing device in the entire existing tunnel can be further determined according to the installation boundary, and it is accurate to the segment on which the balance steel plate is installed in the existing tunnel.

[0047] In step S4, the installation angle is determined according to the second information, and third information is obtained.

[0048] It can be understood that in step S4, steps S41, S42, S43 and S44 are further included, which are specifically:

[0049] In step S41, the center point of the approaching engineering is determined according to the position information of the approaching engineering.

[0050] In this step, as shown in the position diagram of the approaching engineering 1 and the existing tunnel 2, the position of the center point can be determined according to the position of the approaching engineering 1. Figure 4

[0051] In step S42, the center point of the existing tunnel is determined according to the position information of the existing tunnel.

[0052] In this step, the position of the center point can be determined according to the position of the existing tunnel 2.

[0053] In step S43, the center point of the approaching engineering and the center point of the existing tunnel are connected, and the included angle between the line connecting the center point of the approaching engineering and the center point of the existing tunnel and the horizontal line is determined, and the angle information is obtained.

[0054] In this step, the position of the center point can be determined according to the position of the existing tunnel 2, the line is connected, and the included angle between the line connecting the center point of the approaching engineering 1 and the center point of the existing tunnel 2 and the horizontal line is determined, and the angle information α is obtained.

[0055] In step S44, the installation angle is calculated according to the angle information.

[0056] In this step, the installation angle θ can be calculated according to the angle information α, which is specifically:

[0057]

[0058] According to the above formula, the installation angle θ can be calculated according to the angle information α, and after the installation angle θ is determined, the balance steel plate 3 can be installed on the segment of the existing tunnel.​

[0059] Step S5, after installing the reinforcement device according to the third information, monitoring in real time to determine whether the reinforcement device needs to be replaced.

[0060] In this step, in some special cases, the deformation of the soil may be too severe, causing excessive force on the balance steel plate, leading to plastic deformation of the rigid joint node, and cracking or even crushing of the outer concrete on the balance steel plate, which not only causes the balance steel plate to lose its intended effect, but also damages the waterproof performance of the tunnel. Therefore, by monitoring the balance steel plate connection node in real time, the balance steel plate can be effectively replaced in real time to avoid such problems.

[0061] It can be understood that the step S5 also includes steps S51, S52 and S53, which are specifically:

[0062] Step S51, obtaining the tensile stress value information and stress control information of the anchor bolt screw of the real-time monitoring reinforcement device, the tensile stress value information being the tensile stress value of the outermost row of anchor bolt screws on the tensile side, and the stress control information including the average tensile stress value of the outermost row of anchor bolt screws on the tensile side of the anchor bolt when visible cracks appear in the balance steel plate outer concrete;

[0063] In this step, the stress control information is specifically:

[0064]

[0065] In the above formula, σ i is the measured stress value of the i-th anchor bolt screw on the outermost row on the tensile side of the anchor when visible cracks appear in the balance steel plate outer concrete, n is the number of anchor bolts on the outermost row on the tensile side of the anchor along the longitudinal direction of the tunnel, σ max and σ min respectively represent the maximum and minimum values of the measured stress value of the anchor bolt screw on the outermost row on the tensile side of the anchor when visible cracks appear in the balance steel plate outer concrete.

[0066] Step S52, calculating according to the tensile stress value information to obtain a calculation result;

[0067] In this step, the tensile stress value of the outermost row of anchor bolt screws on the tensile side is calculated according to the real-time monitoring and collection of the stress sensor, and the average tensile stress value of the outermost row of anchor bolt screws on the tensile side is obtained. Calculation result.

[0068] Step S53, comparing the calculation result with the stress control information to determine whether the reinforcement device needs to be replaced.

[0069] It can be understood that the step S53 further comprises a step S531, a step S532, a step S533 and a step S534, which are specifically:

[0070] The step S531 calculates the first stress threshold information and the second stress threshold information according to the stress control information, wherein the first stress threshold information is 0.7 times of the stress control information, and the second stress threshold information is 0.9 times of the stress control information.

[0071] In this step, it is assumed that the stress control information is The first stress threshold information is The second stress threshold information is

[0072] The step S532 judges whether the calculation result is greater than the first stress threshold information and less than the second stress threshold information, and if yes, enters the secondary early warning state.

[0073] In this step, it is judged whether the calculation result is greater than the first stress threshold information and less than the second stress threshold information, which is specifically:

[0074]

[0075] In the above formula, σ i测 is the measured stress value of the i th anchor rod on the outermost row of the anchor rod on the tension side collected by the sensor in real time, σ max and σ min respectively represent the maximum value and the minimum value of the measured stress value of the anchor rod on the outermost row of the anchor rod on the tension side collected in real time, and n is the number of the anchor rod on the outermost row of the anchor rod on the tension side along the longitudinal direction of the tunnel. It should be noted that the monitoring frequency should be not less than 2 times / day during the approach engineering construction process, and should be not less than 1 time / day after the approach engineering construction is completed. When entering the secondary early warning state, the monitoring frequency should be not less than 1 time / 2 hours.

[0076] The step S533 judges whether the calculation result is greater than the second stress threshold information and less than the stress control information, and if yes, enters the primary early warning state.

[0077] In this step, it is judged whether the calculation result is greater than the second stress threshold information and less than the stress control information, which is specifically:

[0078]

[0079] It should be noted that when entering the primary early warning state, the monitoring frequency should be not less than 1 time / hour.

[0080] Step S534: Determine whether the calculated result is greater than the stress control information. If it is greater, the nearby project will stop construction and the existing tunnel will be replaced with a reinforcement device.

[0081] In this step, when the calculated result exceeds the stress control information, the nearby project needs to stop construction and the existing tunnel reinforcement device needs to be replaced. The specific process for replacing the balance steel plate is as follows: during unloading, first unscrew the chemical anchor nuts, then remove the connecting weld and ribs between the inner steel plate and the balance steel plate, remove the inner steel plate, use equipment to pull the balance steel plate into the tunnel, and then use equipment to push the new prefabricated balance steel plate out horizontally.

[0082] Example 2:

[0083] like Figure 2 As shown, this embodiment provides an installation device for a replaceable balance steel plate. The device includes an acquisition module 901, a judgment module 902, a first processing module 903, a second processing module 904, and a monitoring module 905, specifically:

[0084] The acquisition module 901 is used to acquire first information, which includes the offset of the adjacent project to the existing tunnel obtained by finite element model simulation.

[0085] The judgment module 902 is used to determine whether to reinforce the existing tunnel based on the first information. If the first information is greater than a preset threshold information, then a reinforcement device needs to be installed on the existing tunnel. The reinforcement device is a replaceable balance steel plate.

[0086] The first processing module 903 is used to determine the installation range of the reinforcement device in the existing tunnel and obtain the second information;

[0087] The second processing module 904 is used to determine the installation angle based on the second information and obtain the third information;

[0088] The monitoring module 905 is used to install the reinforcement device based on the third information and monitor it in real time to determine whether the reinforcement device needs to be replaced.

[0089] In one specific embodiment of this disclosure, the first processing module 903 further includes a first acquisition unit 9031, a first judgment unit 9032, and a first processing unit 9033, specifically as follows:

[0090] The first acquisition unit 9031 is used to acquire the location information of the existing tunnel and the location information of the adjacent project;

[0091] The first judging unit 9032 is configured to judge whether the existing tunnel and the approaching engineering have an overlapping part in the planar projection according to the position information of the existing tunnel and the position information of the approaching engineering, and obtain a judging result.

[0092] The first processing unit 9033 is configured to determine the installation range of the reinforcing device according to the judging result.

[0093] In an embodiment of the present disclosure, the first processing unit 9033 further comprises a second processing unit 90331 and a third processing unit 90332, which are specifically configured as follows:

[0094] The second processing unit 90331 is configured to, when the judging result is that the existing tunnel and the approaching engineering have an overlapping part in the planar projection, extend a first extension line to both sides of the existing tunnel with the midpoint of the overlapping part of the existing tunnel and the approaching engineering in the planar projection as the center, calculate the distance between the segment on the existing tunnel and the first extension line, and obtain the first offset value information of the segment; judge whether the first offset value of each segment meets the safety requirement, wherein the last segment of the segment that meets the safety requirement is taken as the reinforcing boundary.

[0095] The third processing unit 90332 is configured to, when the judging result is that the existing tunnel and the approaching engineering do not have an overlapping part in the planar projection, extend a second extension line to both sides of the existing tunnel with the point closest to the perpendicular distance between the approaching engineering and the planar projection of the existing tunnel as the center, the center being located on the planar projection of the approaching engineering, calculate the distance between the segment on the existing tunnel and the second extension line, and obtain the second offset value information of the segment; judge whether the second offset value of each segment meets the safety requirement, wherein the last segment of the segment that meets the safety requirement is taken as the reinforcing boundary.

[0096] In an embodiment of the present disclosure, the second processing module 904 further comprises a fourth processing unit 9041, a fifth processing unit 9042, a sixth processing unit 9043 and a first calculation unit 9044, which are specifically configured as follows:

[0097] The fourth processing unit 9041 is configured to determine the center point of the approaching engineering according to the position information of the approaching engineering.

[0098] The fifth processing unit 9042 is configured to determine the center point of the existing tunnel according to the position information of the existing tunnel.

[0099] The sixth processing unit 9043 is configured to connect the center point of the approaching engineering and the center point of the existing tunnel, and determine the included angle between the line connecting the center point of the approaching engineering and the center point of the existing tunnel and the horizontal line, and obtain the angle information.

[0100] The first calculation unit 9044 is configured to calculate according to the angle information to obtain the installation angle.

[0101] In an embodiment of the present disclosure, the monitoring module 905 further includes a second acquisition unit 9051, a second calculation unit 9052, and a second judgment unit 9053, which are specifically as follows:

[0102] The second acquisition unit 9051 is configured to acquire real-time monitoring of the tensile stress value information of the anchor bolt screw rod of the reinforcing device and stress control information, wherein the tensile stress value information is the tensile stress value of the outermost row of anchor bolt screw rods on the tensile side, and the stress control information includes the average tensile stress value of the outermost row of anchor bolt screw rods on the tensile side of the anchor bolt screw rod when visible cracks appear on the balanced steel plate outer wrapped concrete.

[0103] The second calculation unit 9052 is configured to calculate according to the tensile stress value information to obtain a calculation result.

[0104] The second judgment unit 9053 is configured to compare the calculation result with the stress control information to determine whether the reinforcing device needs to be replaced.

[0105] In an embodiment of the present disclosure, the second judgment unit 9053 further includes a third calculation unit 90531, a third judgment unit 90532, a fourth judgment unit 90533, and a fifth judgment unit 90534, which are specifically as follows:

[0106] The third calculation unit 90531 is configured to calculate according to the stress control information to obtain first stress threshold information and second stress threshold information, wherein the first stress threshold information is 0.7 times the stress control information, and the second stress threshold information is 0.9 times the stress control information.

[0107] The third judgment unit 90532 is configured to determine whether the calculation result is greater than the first stress threshold information and less than the second stress threshold information, wherein if yes, a second-level early warning state is entered.

[0108] The fourth judgment unit 90533 is configured to determine whether the calculation result is greater than the second stress threshold information and less than the stress control information, wherein if yes, a first-level early warning state is entered.

[0109] The fifth judgment unit 90534 is configured to determine whether the calculation result is greater than the stress control information, wherein if yes, the construction of the adjacent project is stopped, and the reinforcing device of the existing tunnel is replaced.

[0110] It should be noted that the specific manner in which each module performs its operation in the apparatus described in the above embodiments has been described in detail in the embodiments of the method, and will not be elaborated here.

[0111] Example 3:

[0112] Corresponding to the above method embodiments, this embodiment also provides an installation device for a replaceable balance steel plate. The installation device for a replaceable balance steel plate described below and the installation method for a replaceable balance steel plate described above can be referred to in correspondence.

[0113] Figure 3 This is a block diagram illustrating an installation device 800 with a replaceable balance plate according to an exemplary embodiment. Figure 3 As shown, the mounting device 800 for the replaceable balance plate may include a processor 801 and a memory 802. The mounting device 800 may also include one or more of a multimedia component 803, an I / O interface 804, and a communication component 805.

[0114] The processor 801 is configured to control overall operations of the replaceable balance steel plate installation device 800 to complete all or part of the steps in the above-described replaceable balance steel plate installation method. The memory 802 is configured to store various types of data to support operations of the replaceable balance steel plate installation device 800, which can include, for example, instructions for any application or method operating on the replaceable balance steel plate installation device 800, and application-related data, such as contact data, sent and received messages, pictures, audio, video, and the like. The memory 802 can be implemented by any type of volatile or non-volatile storage device or a combination thereof, such as static random access memory (SRAM), electrically erasable programmable read-only memory (EEPROM), erasable programmable read-only memory (EPROM), programmable read-only memory (PROM), read-only memory (ROM), magnetic storage, flash memory, magnetic disk or optical disk. The multimedia component 803 can include a screen and an audio component. The screen can be, for example, a touch screen, and the audio component is configured to output and / or input audio signals. For example, the audio component can include a microphone configured to receive external audio signals. The received audio signals can be further stored in the memory 802 or transmitted through the communication component 805. The audio component also includes at least one speaker configured to output audio signals. The I / O interface 804 provides an interface between the processor 801 and other interface modules, which can be a keyboard, a mouse, a button, and the like. The buttons can be virtual buttons or physical buttons. The communication component 805 is configured to enable wired or wireless communication between the replaceable balance steel plate installation device 800 and other devices. Wireless communication, such as Wi-Fi, Bluetooth, near field communication (NFC), 2G, 3G or 4G, or a combination of one or more of them, so the corresponding communication component 805 can include a Wi-Fi module, a Bluetooth module, an NFC module.

[0115] In an exemplary embodiment, the installation device 800 of the replaceable balance steel plate can be implemented by one or more of an Application Specific Integrated Circuit (ASIC), a Digital Signal Processor (DSP), a Digital Signal Processing Device (DSPD), a Programmable Logic Device (PLD), a Field Programmable Gate Array (FPGA), a controller, a microcontroller, a microprocessor, or other electronic elements, for executing the above-described installation method of the replaceable balance steel plate.

[0116] In another exemplary embodiment, a computer-readable storage medium including program instructions is also provided, which, when executed by a processor, implement the steps of the above-described installation method of the replaceable balance steel plate. For example, the computer-readable storage medium can be the above-described memory 802 including program instructions, which can be executed by the processor 801 of the installation device 800 of the replaceable balance steel plate to complete the above-described installation method of the replaceable balance steel plate.

[0117] Embodiment 4:

[0118] Corresponding to the above method embodiments, the present embodiment also provides a readable storage medium, which can be mutually corresponding with the above-described installation method of the replaceable balance steel plate as described below.

[0119] A readable storage medium, on which a computer program is stored, the computer program being executed by a processor to implement the steps of the above-described installation method of the replaceable balance steel plate according to the method embodiments.

[0120] The readable storage medium can specifically be a U disk, a mobile hard disk, a Read-Only Memory (ROM), a Random Access Memory (RAM), a magnetic disk or an optical disk, and various readable storage media that can store program codes.

[0121] The above only describes the preferred embodiments of the present application and is not used to limit the present application. For those skilled in the art, the present application can have various modifications and changes. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.

[0122] The above merely illustrates the specific embodiments of the present application, but the protection scope of the present application is not limited thereto, any person skilled in the art can easily think of the changes or replacements within the technical range disclosed by the present application, which should be covered in the protection scope of the present application. Therefore, the protection scope of the present application should be subject to the protection scope of the claims.

Claims

1. A method of installing a replaceable balance steel plate, characterized by, The application relates to a method for installing a reinforcing device in an existing tunnel, comprising the following steps: acquiring first information, wherein the first information comprises offset values of the existing tunnel caused by a near-proximity project simulated by a finite element model simulation; determining whether the existing tunnel needs to be reinforced according to the first information, wherein if the first information is greater than a preset threshold value, the existing tunnel needs to be installed with a reinforcing device, and the reinforcing device is a replaceable balance steel plate; determining an installation range of the reinforcing device in the existing tunnel to obtain second information; determining an installation angle according to the second information to obtain third information; monitoring a balance steel plate connecting joint in real time after the reinforcing device is installed according to the third information, and determining whether the reinforcing device needs to be replaced; wherein the step of determining the installation range of the reinforcing device in the existing tunnel comprises the following steps: acquiring position information of the existing tunnel and position information of the near-proximity project; determining whether there is an overlapping part between the existing tunnel and the near-proximity project according to the position information of the existing tunnel and the position information of the near-proximity project to obtain a determination result; determining the installation range of the reinforcing device according to the determination result, comprising the following steps: when the determination result is that there is an overlapping part between the existing tunnel and the near-proximity project, a first extension line is drawn from a midpoint of the overlapping part between the existing tunnel and the near-proximity project as a center to both sides of the existing tunnel, a distance between a segment of the existing tunnel and the first extension line is calculated to obtain a first offset value of the segment, and it is determined whether the first offset value of each segment meets a safety requirement, wherein a last segment of the segment meeting the safety requirement is taken as a reinforcing boundary; when the determination result is that there is no overlapping part between the existing tunnel and the near-proximity project, a second extension line is drawn from a point closest to the existing tunnel in a vertical distance of the near-proximity project as a center to both sides of the existing tunnel, a distance between a segment of the existing tunnel and the second extension line is calculated to obtain a second offset value of the segment, and it is determined whether the second offset value of each segment meets a safety requirement, wherein a last segment of the segment meeting the safety requirement is taken as a reinforcing boundary.

2. The method of installing replaceable counterbalance steel plates of claim 1, wherein, determining the installation angle according to the second information to obtain third information, comprising the following steps: determining a center point of the near-proximity project according to the position information of the near-proximity project; determining a center point of the existing tunnel according to the position information of the existing tunnel; connecting the center point of the near-proximity project and the center point of the existing tunnel, and determining an included angle between the connecting line of the center point of the near-proximity project and the center point of the existing tunnel and a horizontal line to obtain angle information; calculating the installation angle according to the angle information.

3. The method of installing replaceable counterbalance steel plates of claim 1, wherein, monitoring the balance steel plate connecting joint in real time after the reinforcing device is installed according to the third information, and determining whether the reinforcing device needs to be replaced, comprising the following steps: The tension stress value information of the anchor bolt screw of the real-time monitoring reinforcing device is obtained, the tension stress value information is the tension stress value of the outermost row of anchor bolt screws on the tension side, and the stress control information includes the average tension stress value of the outermost row of anchor bolt screws on the tension side when visible cracks appear on the balanced steel plate outer concrete; The calculation result is obtained by calculation according to the tension stress value information; The calculation result is compared with the stress control information to determine whether the reinforcing device needs to be replaced.

4. The method of installing replaceable counterbalance steel plates of claim 3, wherein, The calculation result is compared with the stress control information to determine whether the reinforcing device needs to be replaced, including: The first stress threshold information and the second stress threshold information are obtained by calculation according to the stress control information, the first stress threshold information is 0.7 times the stress control information, and the second stress threshold information is 0.9 times the stress control information; It is judged whether the calculation result is greater than the first stress threshold information and less than the second stress threshold information, and if so, a secondary early warning state is entered; It is judged whether the calculation result is greater than the second stress threshold information and less than the stress control information, and if so, a primary early warning state is entered; It is judged whether the calculation result is greater than the stress control information, and if so, the approaching engineering stops construction, and the reinforcing device of the existing tunnel is replaced.

5. An installation device for a replaceable balance steel plate, characterized in that Including: The acquisition module is used to acquire first information, and the first information includes the offset caused by the approaching engineering to the existing tunnel simulated and simulated by the finite element model; The judgment module is used to determine whether the existing tunnel needs to be reinforced according to the first information, and if the first information is greater than the preset threshold information, the reinforcing device needs to be installed on the existing tunnel, and the reinforcing device is a replaceable balanced steel plate; The first processing module is used to determine the installation range of the reinforcing device in the existing tunnel to obtain second information; The second processing module is used to determine the installation angle according to the second information to obtain third information; The monitoring module is used to monitor the balanced steel plate connection node in real time after the reinforcing device is installed according to the third information, and determine whether the reinforcing device needs to be replaced; The first processing module includes: The first acquisition unit is used to acquire the position information of the existing tunnel and the position information of the approaching engineering; The first judgment unit is used to determine whether the existing tunnel and the planar projection of the approaching engineering have an overlapping part according to the position information of the existing tunnel and the position information of the approaching engineering to obtain a judgment result; The first processing unit is used to determine the installation range of the reinforcing device according to the judgment result; The first processing unit includes: The second processing unit is configured to, when the judgment result is that the existing tunnel overlaps with the planar projection of the approaching engineering, extend a first extension line to both sides of the existing tunnel with the midpoint of the overlapping part of the existing tunnel and the planar projection of the approaching engineering as the center, calculate the distance between the segment on the existing tunnel and the first extension line to obtain the first offset value information of the segment, and judge whether the first offset value of each segment meets the safety requirement, wherein the last segment of the segment meeting the safety requirement is taken as the reinforcement boundary. The third processing unit is configured to, when the judgment result is that the existing tunnel does not overlap with the planar projection of the approaching engineering, extend a second extension line to both sides of the existing tunnel with the point closest to the vertical distance between the approaching engineering and the planar projection of the existing tunnel as the center, the center being located on the planar projection of the approaching engineering, calculate the distance between the segment on the existing tunnel and the second extension line to obtain the second offset value information of the segment, and judge whether the second offset value of each segment meets the safety requirement, wherein the last segment of the segment meeting the safety requirement is taken as the reinforcement boundary.

6. The replaceable counterbalance steel plate mounting device of claim 5, wherein, The second processing module comprises: The fourth processing unit is configured to determine the center point of the approaching engineering according to the position information of the approaching engineering. The fifth processing unit is configured to determine the center point of the existing tunnel according to the position information of the existing tunnel. The sixth processing unit is configured to connect the center point of the approaching engineering and the center point of the existing tunnel, and determine the included angle between the line connecting the center point of the approaching engineering and the center point of the existing tunnel and the horizontal line to obtain the angle information. The first calculation unit is configured to calculate according to the angle information to obtain the installation angle.

7. The replaceable counterbalance steel plate mounting device of claim 5, wherein, The monitoring module comprises: The second acquisition unit is configured to acquire the tensile stress value information of the anchor bolt screw rod of the reinforcement device and the stress control information, the tensile stress value information being the tensile stress value of the outermost row of anchor bolt screw rods on the tensile side, and the stress control information including the average tensile stress value of the outermost row of anchor bolt screw rods on the tensile side when visible cracks appear on the balanced steel plate outer concrete. The second calculation unit is configured to calculate according to the tensile stress value information to obtain a calculation result. The second judgment unit is configured to compare the calculation result with the stress control information to judge whether the reinforcement device needs to be replaced.

8. The replaceable counterbalance steel plate mounting device of claim 7, wherein, The second judgment unit comprises: The third calculation unit is configured to calculate according to the stress control information to obtain first stress threshold information and second stress threshold information, the first stress threshold information being 0.7 times the stress control information, and the second stress threshold information being 0.9 times the stress control information. The third judgment unit is configured to judge whether the calculation result is greater than the first stress threshold information and less than the second stress threshold information, and if yes, enter a secondary early warning state. The fourth judgment unit is configured to judge whether the calculation result is greater than the second stress threshold information and less than the stress control information, and if yes, enter a primary early warning state. A fifth judging unit is configured to judge whether the calculation result is greater than stress control information, and if so, the construction of the approaching project is stopped and the reinforcement device of the existing tunnel is replaced.

9. An installation apparatus for a replaceable balance steel plate, characterized by The application further provides a computer readable storage medium having stored thereon a computer program. The computer readable storage medium has stored thereon a computer program, and the computer program is executed by the processor to implement the steps of the installation method of the replaceable balance steel plate according to any one of claims 1 to 4. The computer readable storage medium has stored thereon a computer program, and the computer program is executed by the processor to implement the steps of the installation method of the replaceable balance steel plate according to any one of claims 1 to 4.

10. A readable storage medium, characterized by: ​

Citation Information

Patent Citations

  • Active protection structurefor water-rich soft soil area shield closely passing throughoperation tunnel and construction method

    CN110230499A

  • Space monitoring method for deformation and displacement of existing underground structure in subway station construction

    CN112629478A

  • Novel rapid reinforcing method for existing tunnel structure through steel corrugated plates

    CN115949435A