Calculation method for lining water pressure considering the variation of cross-sectional reduction factor of submarine tunnel
By calculating the water pressure reduction factor in the cross-section of the submarine tunnel, the problem of inaccurate calculation of water pressure in tunnel lining in the existing technology is solved, and a reasonable distribution and reliable calculation of water pressure are achieved.
Patent Information
- Application Number
- CN202311079301.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-08-25
- Publication Date
- 2026-11-17
- Estimated Expiration
- 2043-08-25
AI Technical Summary
Existing technologies for calculating water pressure in submarine tunnel linings cannot reflect changes in water pressure across the tunnel cross-section, especially due to the influence of the drainage system, resulting in idealized and inaccurate calculation results.
The cross-section of the undersea tunnel is divided into multiple zones, and the relative drainage volume of each zone is calculated. The water pressure reduction coefficient of each zone is calculated using seepage theory to guide the design of the lining structure.
The method achieves a reasonable distribution of water pressure in the lining, conforms to the actual characteristics of water pressure variation in tunnel cross sections, and the calculation results are reliable and easy to implement.
Smart Images

Figure CN117195516B_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of tunnel and underground engineering design and construction technology, and specifically relates to a method for calculating lining water pressure considering the variation of the reduction coefficient of the cross-section of a submarine tunnel. Background Technology
[0002] In recent years, with the acceleration of my country's modernization, more and more water-rich mountain tunnels and undersea tunnels have been put into use. These tunnels often face the challenge of high ground stress due to their large burial depth, and the continuous water supply makes the determination of the external water pressure of the lining a major problem in tunnel support design. The earliest approach to consider the external water pressure of the lining was the introduction of a reduction factor in the "Code for Design of Hydraulic Tunnels". However, the value of the reduction factor is still mainly based on experience and lacks quantitative reference. With the deepening of research on the coupling of seepage field and stress field, tunnels with sufficient water supply in confined aquifers are simplified into a steady flow model of a vertical shaft in an infinite aquifer. Thus, the analytical solution of the external water pressure of the lining can be obtained using seepage theory, leading to the current general understanding of the lining water pressure: the reduction of lining water pressure is only related to the relative drainage of the lining.
[0003] However, calculating drainage involves the permeability coefficients of the surrounding rock, grouting ring, and lining. While the permeability coefficients of the former two are usually easily determined during the design phase, the lining typically cannot tolerate seepage. Drainage of the lining is accomplished by a drainage system consisting of its back ring and longitudinal drainage blind pipes, which directs seepage from the surrounding rock into drainage ditches. Therefore, the flow rate of the drainage system needs to be equivalent to the permeability coefficient of the lining, but currently there is no clear and reasonable method. In actual calculations, the tunnel design drainage volume is often used as a substitute. However, the lining water pressure calculated in this way is still a uniformly distributed water pressure under an idealized model and cannot reflect the changes in lining water pressure across the tunnel cross-section under the influence of the drainage system. Summary of the Invention
[0004] This invention addresses the technical problem that existing technologies for calculating seepage pressure in submarine tunnel linings cannot reflect changes in lining water pressure across the tunnel cross-section. It provides a method for calculating lining water pressure that considers variations in the reduction coefficient of the submarine tunnel cross-section. The method divides the tunnel cross-section into several zones, calculates the relative drainage volume of each zone, and obtains different water pressure reduction coefficients. Then, it calculates the lining water pressure in each zone, guiding the design of the lining structure.
[0005] Water seepage from the surrounding rock behind the lining is collected via circumferential drainage pipes to the bottom longitudinal drainage pipes, and then discharged outside the tunnel through drainage ditches. The drainage capacity of both the circumferential and longitudinal drainage pipes is constant and can be determined by the pipe specifications selected based on the design drainage volume. Assume the design drainage volumes of the circumferential and longitudinal drainage pipes are Q1 and Q2, respectively. Based on the steady-state flow model in an infinite aquifer in seepage theory, the initial tunnel support experiences uniform seepage, and the initial inflow is assumed to be Q. inTherefore, the lining inflow and drainage volume of the arch crown section are the calculated inflow volume of that section and the design drainage volume Q1 of the circumferential drainage blind pipe. However, due to the limited drainage capacity, in the section below the arch crown, the water inflow behind the lining includes not only the water inflow from the initial support but also the water inflow from the upper section that could not be discharged in time, resulting in the accumulation of water inflow from top to bottom in each section. At the arch foot, due to the presence of the longitudinal drainage blind pipe, the tunnel water inflow is discharged through this pipe, and the lining water pressure is released, resulting in an uneven distribution of lining water pressure along the tunnel cross section.
[0006] In view of this, the technical solution adopted by the present invention is: a method for calculating the lining water pressure considering the change of the reduction coefficient of the submarine tunnel cross section, including the following steps:
[0007] Step 1: Simplify the undersea tunnel into a steady-flow model of a vertical shaft in an infinite aquifer. Obtain the tunnel's geological and construction parameters, including the initial hydraulic head H and the surrounding rock permeability coefficient k, through field measurements or research. r , Grouting ring permeability coefficient k g Primary branch permeability coefficient k l and the radius r of the grouting ring g Far-field distance r0, initial support internal radius r1, initial support external radius r2;
[0008] Step 2: Calculate the initial inflow Q of the tunnel. in ,
[0009]
[0010] Step 3: Consult the relevant documents to obtain the design drainage volume Q1 of the circumferential drainage blind pipe and the design drainage volume Q2 of the longitudinal drainage blind pipe in the tunnel;
[0011] Step 4: Divide the underwater tunnel chambers symmetrically and evenly into m sections from top to bottom;
[0012] Step 5: Based on the initial branch inflow rate Q in Calculate the water pressure reduction factor β for each zone based on the design drainage capacity Q1 of the circumferential drainage blind pipe and Q2 of the longitudinal drainage blind pipe. m ;
[0013] Step 6: Calculate the lining water pressure P for each zone. m =β m γ w H, where γ w The density of water. This can guide the design of the lining structure.
[0014] Furthermore, the initial inflow rate Q of each zone inThe actual water inflow rate of the zone is measured and replaced with the calculation result in step 2. At this point, the initial branch water inflow rate calculated theoretically based on steps 1 and 2 and the simplified model is used as a reference.
[0015] Furthermore, in step 5, for the zones above the longitudinal drainage blind pipe, the drainage volume is determined by the design drainage volume Q1 of the circumferential drainage blind pipe, while the inflow volume includes not only the initial branch inflow volume but also the difference between the inflow and outflow volumes from the previous zone, and the water pressure reduction coefficient.
[0016] For a zone containing the aforementioned longitudinal drainage blind pipe, its drainage volume is determined jointly by the transverse and longitudinal drainage blind pipes, with a water pressure reduction factor.
[0017] For the section below the longitudinal drainage blind pipe, the drainage volume is still determined by the design drainage volume Q of the circumferential drainage blind pipe, and the water pressure reduction factor is...
[0018] Furthermore, in step 5, if the water pressure reduction coefficient β of a certain zone... m If the value is less than 1, meaning the tunnel drainage volume is greater than the water inflow volume, then the lining water pressure of that section is not considered.
[0019] Furthermore, in step 4, the number of partitions shall not be less than three, and typical parts of the cavern, such as the vault, shoulder, waist, foot, and bottom, shall be considered when dividing the partitions.
[0020] Furthermore, regarding the convergence of the water pressure reduction coefficient calculation formula, in step 4, the number of partitions is no more than 10.
[0021] Compared with existing technologies, the beneficial effects of this invention are as follows: The lining water pressure calculation method based on seepage theory considers the characteristics of the tunnel drainage system and performs a reduction calculation of the lining water pressure, which conforms to the actual top-to-bottom variation characteristics of water pressure in tunnel cross-sections. Therefore, this calculation method is reasonable and the calculation results are reliable. The physical meaning of each step in this invention is clear, it is simple and easy to use, the steps are distinct, and the concept is novel. Attached Figure Description
[0022] Figure 1 This is a flowchart of an embodiment of the present invention;
[0023] Figure 2 This is a simplified model diagram of an embodiment of the present invention;
[0024] Figure 3 This is a schematic diagram of the tunnel cross-section partitioning according to an embodiment of the present invention. Detailed Implementation
[0025] To enable those skilled in the art to better understand the technical solution of the present invention, the present invention will be described in detail below with reference to the accompanying drawings and specific embodiments.
[0026] Embodiments of the present invention provide a method for calculating the lining water pressure considering the variation of the reduction coefficient of the submarine tunnel cross section, such as... Figure 1 As shown, it includes the following steps:
[0027] Step 1: Simplify the submarine tunnel into a steady-flow model of a vertical shaft in an infinite aquifer, such as... Figure 2 As shown, the tunnel's geological and construction parameters, including the initial water head height H and the surrounding rock permeability coefficient k, were obtained through actual measurements or research. r , Grouting ring permeability coefficient k g Primary branch permeability coefficient k l and the radius r of the grouting ring g Far-field distance r0, initial support internal radius r1, initial support external radius r2.
[0028] In this embodiment, the underwater tunnel has a water head height of 65m and an excavation span of 14m. The initial support thickness is 30cm, with a seepage resistance grade of P8; the grouting layer thickness is 5m, and the surrounding rock permeability coefficient is 10. -4 cm / s, grouting ring permeability coefficient 10 -6 cm / s.
[0029] Step 2: Substitute the above tunnel geological and construction parameters into the following formula to calculate the initial support water inflow Q of the tunnel. in ,
[0030]
[0031] Step 3: Consult relevant materials to obtain the design drainage capacity Q1 = 0.12m for the tunnel's circumferential drainage blind pipe. 3 / m·d, the design drainage capacity of the longitudinal drainage blind pipe is Q2=0.26m 3 / m·d.
[0032] Step 4: Considering the arch, shoulders, waist, foot, and bottom of the cavern, the subsea tunnel is symmetrically and evenly divided into 5 sections (m=5) from top to bottom, such as... Figure 3 As shown.
[0033] Step 5: Calculate the water pressure reduction factor β for each zone. m Specifically:
[0034] There are three zones above the longitudinal drainage blind pipe. The drainage volume of each zone is determined by the design drainage volume Q1 of the circumferential drainage blind pipe. The inflow volume includes the initial branch inflow volume and the difference between the inflow and outflow volumes from the previous zone. Therefore, the water pressure reduction coefficients for these three zones are calculated respectively:
[0035]
[0036]
[0037]
[0038] The fourth zone contains longitudinal drainage blind pipes. Its drainage volume is determined by both transverse and longitudinal drainage blind pipes. Calculate the water pressure reduction factor for this zone:
[0039] The fifth zone is the zone below the longitudinal drainage blind pipe. Its drainage volume is still determined by the design drainage volume Q1 of the circumferential drainage blind pipe. Therefore, calculate its water pressure reduction factor:
[0040] Step 6: Calculate the lining water pressure P for each zone. m =β m γ w H is shown in Table 1.
[0041] Table 1. Water Pressure Table for Lining Sections of Tunnel Cross-Section
[0042] partition 1 2 3 4 5 Water pressure / kPa 471.4 541.4 566.9 477.7 547.8
[0043] The present invention has been described in detail above through embodiments, but the content described is only an exemplary embodiment of the present invention and should not be considered as limiting the scope of the present invention. The scope of protection of the present invention is defined by the claims. Any technical solutions designed by those skilled in the art using the technical solutions described in the present invention, or designed by those skilled in the art under the inspiration of the technical solutions of the present invention, within the substance and protection scope of the present invention, to achieve the above-mentioned technical effects, or any equivalent changes and improvements made to the scope of the application, should still fall within the patent protection scope of the present invention.
Claims
1. A method for calculating the lining water pressure considering the variation of the reduction coefficient of the submarine tunnel cross section, characterized in that, Includes the following steps: Step 1: Simplify the undersea tunnel into a steady-flow model of a vertical shaft in an infinite aquifer, and obtain the tunnel's geological and construction parameters, including the initial hydraulic head. Permeability coefficient of surrounding rock grouting ring permeability coefficient Primary branch permeability coefficient and the radius of the grouting ring Far field distance , internal radius of primary branch , the outer radius of the initial branch ; Step 2: Calculate the initial water inflow of the tunnel. , ; Step 3: Obtain the design drainage capacity of the tunnel's circumferential drainage blind pipe. Design drainage capacity of longitudinal drainage blind pipe ; Step 4: Divide the subsea tunnel chambers symmetrically and evenly from top to bottom into... One partition; Step 5: Based on the initial branch water inflow Design drainage capacity of circumferential drainage blind pipe Design drainage capacity of longitudinal drainage blind pipe Calculate the water pressure reduction factor for each zone. ; Step 6: Calculate the lining water pressure for each zone. ,in, The specific gravity of water; In step 5, for the zones above the longitudinal drainage blind pipes, the water pressure reduction factor is... ; For the zone containing the aforementioned longitudinal drainage blind pipe, the water pressure reduction factor ; For the zone below the aforementioned longitudinal drainage blind pipe, the water pressure reduction factor is: .
2. The method for calculating lining water pressure considering the variation of the cross-sectional reduction coefficient of a submarine tunnel as described in claim 1, characterized in that, Initial inflow of water in each zone The actual water inflow in each zone is measured and obtained, replacing the calculation result in step 2.
3. The method for calculating lining water pressure considering the variation of the reduction coefficient of the submarine tunnel cross-section as described in claim 1, characterized in that, If the water pressure reduction factor for a certain zone If the lining water pressure of that zone is not considered, then the lining water pressure of that zone will not be considered.
4. The method for calculating lining water pressure considering the variation of the reduction coefficient of the submarine tunnel cross-section as described in claim 1 or 2, characterized in that, In step 4, the number of partitions shall not be less than 3, and typical parts of the cavern shall be considered when dividing the partitions.
5. The method for calculating lining water pressure considering the variation of the reduction coefficient of the submarine tunnel cross-section as described in claim 1 or 2, characterized in that, In step 4, the number of partitions is no more than 10.
Citation Information
Patent Citations
Conversion permeability coefficient-based method for controlling tunnel discharge by regions
CN105528492A
Method for controlling mining method tunnel secondary lining water pressure
CN107178392A