Construction method for soft soil geological mixing station envelope stand column reinforcement

By laying concrete in soft soil conditions and using a total station for precise positioning and corbel welding reinforcement, the problems of insufficient stability and load-bearing capacity in the construction of the encased column were solved, achieving the effects of simplified construction and reduced costs.

CN117211464BActive Publication Date: 2026-01-20THE 5TH ENG MBEC
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202311037962.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-08-17
Publication Date
2026-01-20
Estimated Expiration
2043-08-17

AI Technical Summary

Technical Problem

Under soft soil geological conditions, the construction of concrete mixing plant encasing columns is difficult and has insufficient bearing capacity. Moreover, existing technologies cannot guarantee the stability and economy of the construction.

Method used

Concrete was laid in the area of ​​the enclosed column and the position was accurately located using a total station. The column was then fixed with expansion bolts. In addition, corbels were installed between the steel pipe piles of the powder tank support legs and the enclosed column for spot welding reinforcement, and the installation of the column was gradually completed.

Benefits of technology

It achieves precise positioning and initial load-bearing of the encapsulated columns, improves the stability and load-bearing capacity of the structure, simplifies the construction process, and reduces costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117211464B_ABST
    Figure CN117211464B_ABST
Patent Text Reader

Abstract

The application discloses a construction method for soft soil geological mixing station package column sealing reinforcement, and preliminary positioning is first performed on the package column sealing by a surveyor, a layer of concrete is laid in the range of the package column sealing, and meanwhile, the flatness of the concrete is ensured; after the concrete reaches the set strength, the surveyor performs accurate positioning and lofting on the package column sealing by using a total station instrument, a crane is used to hoist the package column sealing to a design position, the package column sealing is fixed by expansion bolts after the lower surface of the package column sealing is precisely attached to the concrete; corbels are arranged between the powder tank supporting leg steel pipe piles and the package column sealing, preliminary reinforcement is performed by spot welding, after the crane is unhooked, the reinforcement is continuously supplemented to complete the package column sealing reinforcement construction. The application can realize accurate positioning and reinforcement construction of the package column sealing, and simultaneously plays a role in preliminary bearing; the corbels are arranged between the powder tank steel pipe piles and the package column sealing for reinforcement, which can increase the overall stability and bearing capacity of the structure.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The present application relates to the field of civil engineering and bridge construction, and particularly relates to a construction method for reinforcing an envelope column of a soft soil mixing station. BACKGROUND

[0002] With the rapid development of economic construction, the demand for bridges and various buildings is increasing, and the demand for concrete is also increasing. At the same time, the appearance and quality of the construction process are also improving, which means that the site selection of the concrete mixing station should be close to the construction site. In the meantime, it is also subject to the interference of environmental factors such as climate, geology, and groundwater. The envelope of the concrete mixing station also faces this problem.

[0003] The envelope of the concrete mixing station not only improves the appearance of the mixing station, but also needs to resist the influence of typhoon climate factors. The envelope column is the main load-bearing structure of the mixing building envelope. In soft soil, it is difficult to ensure the bearing capacity required by the mixing building envelope in the form of ordinary foundation, and the construction difficulty is high, and the economic cost is high. In order to ensure the stability, economy, and bearing capacity of the mixing building envelope construction in soft soil, a construction method for reinforcing the envelope column of the soft soil mixing station is needed. SUMMARY

[0004] The purpose of the present application is to provide a construction method for reinforcing the envelope column of the soft soil mixing station, which is simple in construction, high in installation precision, and can effectively reduce the construction difficulty, ensure the construction precision and the stability of the envelope column.

[0005] The purpose of the present application is achieved as follows:

[0006] A construction method for reinforcing the envelope column of the soft soil mixing station, characterized by the following specific steps:

[0007] A. The measurement personnel first preliminarily position a plurality of envelope columns, and lay a layer of concrete in the range of the plurality of envelope columns, while ensuring the flatness of the concrete;

[0008] B. After the concrete reaches the set strength, the measurement personnel use a total station to accurately position and lay out the first envelope column, and use a crane to hoist the envelope column to the designed position. The lower surface of the envelope column is precisely fitted with the concrete, and the envelope column is fixed with expansion bolts. At this time, the crane is not unhooked.

[0009] C. A corbel is arranged between the powder tank support leg steel pipe pile and the envelope column, and is preliminarily reinforced by spot welding. After the crane is unhooked, the reinforcement is continued by supplementary welding.

[0010] D. Repeat steps B and C to complete the installation and construction of the remaining envelope columns and corbels.

[0011] The present application is to set up corbel between powder tank supporting leg steel pipe pile and enveloping column to reinforce, to lay concrete in the area of enveloping column, which mainly plays the role of accurate positioning and preliminary bearing of enveloping column, to set up expansion bolt on the lower surface of enveloping column to play the role of preliminary fixing.

[0012] Compared with the prior art, the present application has the following advantages:

[0013] 1. Laying concrete in the area of enveloping column can accurately position the enveloping column and simultaneously play the role of preliminary bearing;

[0014] 2. Setting up corbel between powder tank supporting leg steel pipe pile and enveloping column to reinforce can increase the overall stability and bearing capacity of the structure;

[0015] 3. The present application can realize the reinforcement construction of enveloping column in soft soil, and has the advantages of simple and smart structure, simple construction, high installation precision, flexible operation, saved materials and simplified construction process. BRIEF DESCRIPTION OF DRAWINGS

[0016] Figure 1 It is a corbel position layout;

[0017] Figure 2 It is a step A construction drawing of corbel welding reinforcement;

[0018] Figure 3 It is a step B construction drawing of corbel welding reinforcement;

[0019] Figure 4 It is a step C construction drawing of corbel welding reinforcement. DETAILED DESCRIPTION

[0020] The present application will be further described in detail below with reference to the drawings and in combination with the embodiments.

[0021] In combination with the drawings, Figures 1-4 An implementation mode of a construction method for reinforcing enveloping columns of a soft soil mixing station:

[0022] A. The measurement personnel first preliminarily position a plurality of enveloping columns 3, and lay a layer of concrete 2 in the range of the plurality of enveloping columns 3, while ensuring the flatness of the concrete 2;

[0023] B. After the concrete 2 reaches the set strength, the measurement personnel accurately position and lay out the first enveloping column 3 using a total station, and use a crane to hoist the enveloping column 3 to the designed position, and after the lower surface of the enveloping column 3 precisely fits the concrete 2, fix the enveloping column 3 with expansion bolts 4, at this time the crane does not unhook under force;

[0024] C. Between the powder tank supporting leg steel pipe pile 1 and the enclosed column 3, a bracket 5 is arranged, and the preliminary reinforcement is carried out by spot welding, after the crane is unhooked, the reinforcement is continued by supplement welding;

[0025] D. Repeat steps B, C, complete the remaining enclosed column 3, bracket 5 installation construction.

[0026] The above is only a preferred embodiment of the present application, and does not limit the scope of the present application, any equivalent structural changes made by applying the content of the present application and the drawings are included in the scope of the present application.

Claims

1. A construction method for reinforcing the columns of a mixing plant in soft soil conditions, characterized in that: The specific steps are as follows: A. The surveyors first make preliminary positioning of several enclosed columns, and then lay a layer of concrete within the area where the enclosed columns are located, while ensuring the flatness of the concrete. B. After the concrete reaches the set strength, the surveyors use a total station to accurately position and lay out the first encapsulated column. The encapsulated column is then lifted to the design position using a crane. After the lower surface of the encapsulated column is precisely fitted with the concrete, the encapsulated column is fixed with expansion bolts. At this time, the crane is under load and does not detach. C. Install corbels between the steel pipe piles supporting the powder tank legs and the encapsulation column, and perform initial reinforcement by spot welding. After the crane is unhooked, continue to weld for reinforcement. D. Repeat steps B and C to complete the installation of the remaining encapsulated columns and corbels.