An intelligent construction control method and device for a subway shield gas tunnel

Through intelligent construction control methods, geological conditions and trial excavation data are used to adjust shield machine parameters, reduce manual intervention, improve the accuracy and stability of subway shield gas tunnel construction, and solve the correction lag and formation disturbance in the existing technology. problem.

CN117211858BActive Publication Date: 2024-10-15GUANGZHOU METRO GRP CO LTD +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202311207231.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-09-18
Publication Date
2024-10-15
Estimated Expiration
2043-09-18

AI Technical Summary

Technical Problem

The existing subway shield gas tunnel construction method has manual operations that lead to deviation correction lag, resulting in large stratum disturbances, affecting the cracking of ground structures, and the excavation progress is not timely.

Method used

Intelligent construction control methods are used to calculate the excavation deviation of the shield machine by obtaining current geological conditions and test excavation data, correct the deviation, adjust the amount of excavation and lining grouting rate, and achieve accurate matching between the shield machine and the tunnel axis, reducing the Human intervention.

Benefits of technology

It improves the excavation accuracy and construction stability of the shield machine, reduces ground disturbance, adjusts construction parameters in a timely manner, and reduces manual correction and progress lag.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117211858B_ABST
    Figure CN117211858B_ABST
Patent Text Reader

Abstract

The present application relates to an intelligent construction control method and device for a subway shield gas tunnel, the method comprising obtaining the current geological conditions and trial excavation data of the gas tunnel, obtaining the initial excavation parameters of the shield machine; in the process of the shield machine excavating the tunnel according to the initial excavation parameters, calculating the excavation deviation of the excavation mileage of the shield machine in the direction of the tunnel axis; performing excavation correction processing on the excavation deviation to obtain the correction regression parameters of the shield machine; calculating the correction deformation amount under the current geological conditions according to the correction regression parameters, and synchronously adjusting the excavation amount and lining grouting rate of the shield machine according to the correction deformation amount. The present application has the effect of reducing the large-scale disturbance of the stratum during the excavation process of the shield machine, and reducing the lag between manual correction and actual excavation progress.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of subway shield gas tunnel construction, and in particular to an intelligent construction control method and device for a subway shield gas tunnel. Background Art

[0002] At present, in the process of urbanization, subway construction often needs to face a variety of underground environments, including complex underground environments such as soil conditions, water supply and power supply pipelines. When constructing subway gas tunnels through shield machines, it is often necessary to conduct targeted construction analysis of the underground environment where the tunnel is located.

[0003] The existing construction method of subway shield gas tunnel is usually to conduct trial excavation according to the construction plan to obtain the construction parameters of the shield machine, and control the shield machine to excavate the tunnel. During the excavation process, the excavation parameters are adjusted according to the construction monitoring results of the construction personnel, so that the shield machine can continue to work according to the preset tunnel excavation route and install the tunnel segments simultaneously. However, there is an unknown geological environment ahead of the excavation route of the shield machine. When the geological conditions change, such as when a goaf appears, the shield machine needs to be manually operated to change the excavation parameters in time. Often, due to the lag of manual operation, the shield machine needs a large amount of correction when entering different excavation environments, which in turn causes a large amplitude of stratum disturbance and affects the cracking of ground structures.

[0004] In summary, the above existing subway shield gas tunnel construction scheme has the defects that the deviation correction of the manually operated shield machine lags behind the actual excavation progress, causing a large disturbance amplitude at the bottom: Summary of the invention

[0005] In order to reduce the significant disturbance of the strata caused by the shield machine excavation process and reduce the lag between manual correction and actual excavation progress, the present application provides an intelligent construction control method and device for a subway shield gas tunnel.

[0006] The above-mentioned invention objective of the present application is achieved through the following technical solutions:

[0007] An intelligent construction control method for a subway shield gas tunnel, comprising:

[0008] Obtain the current geological conditions and trial excavation data of the gas tunnel and obtain the initial excavation parameters of the shield machine;

[0009] During the tunnel boring process of the shield machine according to the initial excavation parameters, calculating the tunnel boring deviation of the tunnel boring machine in the tunnel axis direction;

[0010] Performing excavation deviation correction processing on the excavation deviation to obtain the correction regression parameter of the shield machine;

[0011] The deviation correction deformation amount under the current geological conditions is calculated according to the deviation correction regression parameter, and the excavation volume and lining grouting rate of the shield machine are synchronously adjusted according to the deviation correction deformation amount.

[0012] By adopting the above technical scheme, the initial excavation parameters of the shield machine are adjusted according to the current geological conditions and trial excavation data of the subway gas tunnel, which is helpful to quickly adjust the tunneling construction control parameters of the shield machine, and in the process of the shield machine excavating the tunnel according to the initial excavation parameters, the excavation deviation of the shield machine's excavation mileage in the direction of the tunnel axis is calculated, and it is judged according to the excavation deviation whether the current excavation disturbance of the shield machine exceeds the allowable range of the tunnel construction error, which is helpful to improve the construction matching degree between the shield machine and the tunnel axis, and perform corresponding excavation correction processing on the excavation deviation to obtain the correction regression parameters of the shield machine, which is helpful to adjust the excavation construction control parameters of the shield machine according to the correction regression parameters. Corresponding adjustments are made to make the shield machine return from the deviated excavation direction to the tunnel axis direction, thereby improving the excavation accuracy of the shield machine, and calculating the correction deformation amount under current geological conditions based on the correction regression parameters, including the regression excavation deformation required for the shield machine to correct to the tunnel axis, the stratum deformation corresponding to the stratum disturbance during the shield machine's correction excavation process, etc., so as to synchronously adjust the shield machine's excavation volume and lining grouting rate according to the correction deformation amount, so that the shield machine can always maintain a state of soil balance during the correction process for construction and excavation, reduce the large-scale disturbance of the stratum during the shield machine's excavation process, and make timely construction parameter adjustments based on the shield machine's excavation deviation to reduce the lag between manual correction and actual excavation progress.

[0013] In a preferred example, the present application may be further configured as follows: performing excavation deviation correction processing on the excavation deviation to obtain the correction regression parameter of the shield machine specifically includes:

[0014] During the tunneling process of the shield machine, obtaining an actual tunneling angle of the shield machine under the current geological conditions;

[0015] Obtaining the tunnel axis corresponding to the current excavation position, and calculating the excavation deviation value between the actual excavation angle and the tunnel axis;

[0016] Analyzing the excavation deviation trend of the shield machine according to the excavation deviation value to obtain a slope mutation analysis result of the shield machine under the current excavation deviation trend;

[0017] According to the slope mutation analysis result, a mutation correction process is performed on the slope mutation range corresponding to the slope mutation analysis result to obtain the correction regression parameters of the shield machine under the current slope mutation condition.

[0018] By adopting the above technical scheme, during the tunneling process of the shield machine, the actual tunneling angle under the current geological conditions is obtained according to the angle between the tunneling angle of the shield machine to the current geological layer and the preset tunnel axis, which is helpful to accurately correct the next tunneling direction of the shield machine according to the actual tunneling angle, so that the tunneling angle deviation can be quickly restored to the tunnel axis range, and the corresponding tunneling deviation value is calculated according to the offset angle difference between the actual tunneling angle and the tunnel axis, so as to quickly plan the tunneling correction route for the tunneling deviation value, and evaluate whether the current tunneling construction of the shield machine meets the tunnel construction requirements according to the tunneling deviation value, analyze the tunneling deviation trend of the shield machine according to the tunneling deviation value, and according to the tunneling deviation trend of the shield machine, The slope mutation caused by the current shield machine is further analyzed to obtain the slope mutation analysis results of the shield machine under the current excavation deviation trend, which is helpful to timely control the stratum disturbance risk of the excavation deviation trend according to the slope mutation analysis results. Furthermore, the corresponding slope mutation range is subjected to mutation correction processing according to the slope mutation analysis results, so that the shield machine can quickly return the deviation angle to the tunnel axis while maintaining the balanced force of the soil layer, thereby obtaining the correction regression parameters of the shield machine under the current slope mutation situation, which is helpful to timely correct the small-range excavation deviation of the shield machine according to the correction regression parameters, reduce the disturbance to the stratum caused by the correction process, and improve the excavation construction stability and adjustment timeliness of the shield machine.

[0019] In a preferred example, the present application can be further configured as follows: according to the slope mutation analysis result, a mutation correction process is performed on the slope mutation range corresponding to the slope mutation analysis result to obtain the correction regression parameters of the shield machine under the current slope mutation condition, specifically including:

[0020] Acquire the tunnel face geological data under the current slope mutation condition and the current shield posture of the shield machine;

[0021] Analyzing the deviation correction and regression construction route of the shield machine to return the deviation angle to the tunnel axis range area according to the face geological data and the current shield posture;

[0022] Performing hierarchical correction processing on the correction and regression construction route, and calculating the correction regression angle of the previous level correction mileage for the slope mutation according to the hierarchical correction processing results;

[0023] The correction angle parameters of the next level are adjusted according to the correction regression angle of the previous level, so as to obtain the multi-level correction regression parameters of the shield machine under the current slope mutation condition.

[0024] By adopting the above technical scheme, the geological data of the tunnel face to be excavated in front of the shield machine and the current shield posture of the shield machine are obtained under the current slope mutation situation, which is helpful to make corresponding adjustments to the next excavation direction and excavation force of the shield machine according to the tunnel face geological data and the current shield posture, thereby improving the fit between the shield machine and the tunnel face geological conditions of the next excavation direction, and analyzing the deviation angle of the shield machine under the current slope mutation to fit the correction regression construction route of the tunnel axis range area, and quickly adjusting the current construction parameters of the shield machine according to the correction regression construction route, thereby improving the timeliness of the construction parameter adjustment of the shield machine, and performing hierarchical correction processing on the correction regression construction route, so as to ensure the correctness of the correction regression construction. The route is divided into detailed layers to reduce the disturbance effect of large deviation of the shield machine on the stratum, and the correction regression angle caused by the correction mileage of the previous layer on the slope mutation is calculated according to the hierarchical correction processing results. This helps to accurately control the regression angle under the correction construction process of each layer, improve the correction accuracy of the correction regression angle of the shield machine, and adjust the correction angle parameters of the next layer in combination with the correction regression angle of the previous layer. By continuously adjusting the regression angle of the construction parameters of each layer, the multi-level correction regression parameters under the current slope mutation situation can be obtained, which helps to reduce the disturbance effect of the shield machine's correction construction on the stratum during the correction construction process of the current slope mutation.

[0025] In a preferred example, the present application can be further configured as follows: the correction deformation amount under the current geological conditions is calculated according to the correction regression parameter, and the excavation amount and lining grouting rate of the shield machine are synchronously adjusted according to the correction deformation amount, specifically including:

[0026] According to the deviation correction regression parameter, the static geological pressure corresponding to the current tunnel face and the deviated excavation pressure corresponding to the excavation deviation are obtained;

[0027] Comprehensively calculating the deviation correction deformation of the shield machine under current geological conditions according to the static geological pressure and the deviation excavation pressure;

[0028] Adjusting the tunnel face cutting rate of the shield machine according to the deviation correction deformation amount, and controlling the soil equilibrium pressure between the deviation correction excavation volume and the corresponding discharge volume at the same time node according to the tunnel face cutting rate;

[0029] The lining grouting rate of the shield machine is adjusted according to the soil equilibrium pressure, and the grouting process is performed synchronously with the cutting rate of the tunnel face.

[0030] By adopting the above technical scheme, the static geological pressure corresponding to the current face and the deviation excavation pressure corresponding to the excavation deviation are obtained according to the correction regression parameters, which is helpful to comprehensively analyze the external pressure on the shield machine at the current face, and then adjust the excavation power of the shield machine. The correction deformation of the shield machine under the current geological conditions is comprehensively calculated according to the static geological pressure and the deviation excavation pressure, and the deviation total deformation of the current shield machine is controlled, which is helpful to adjust the excavation power and excavation direction of the shield machine according to the correction deformation, and then adjust the excavation power and excavation direction of the shield machine according to the correction deformation. The deformation variable adjusts the cutting rate of the tunnel face of the shield machine, and the correction excavation volume and the discharge volume at the same time node are jointly adjusted according to the adjusted tunnel face cutting rate, so as to achieve the effect of soil pressure balance between the discharge volume and the correction excavation volume during the correction process. According to the excavation construction mileage corresponding to the soil balance pressure, the lining grouting rate of the shield machine is synchronously adjusted, so that the lining grouting rate and the tunnel face cutting rate can be kept synchronized, so as to achieve the purpose of construction control of synchronous excavation and grouting, and improve the control linkage between each construction process of the shield machine.

[0031] In a preferred example, the present application may be further configured as follows: the lining grouting rate of the shield machine is adjusted according to the soil equilibrium pressure, and the grouting process is performed synchronously with the tunnel face cutting rate, and further includes:

[0032] Obtaining the tunnel lining deformation angle of the tunnel after cement lining and the cutter head excavation diameter of the shield machine;

[0033] Calculating the grouting pressure of the next lining grouting according to the deformation angle of the tunnel lining, and performing deformation compensation for the deformation angle of the previous tunnel lining according to the grouting pressure;

[0034] According to the cutterhead excavation diameter and the corresponding tunnel segment outer diameter, adjusting the corresponding tunnel lining grouting amount;

[0035] According to the segment shield position of the shield machine, the shield tail position parameter of each tunnel segment is obtained, and the shield tail position change value obtained after the deformation compensation of the tunnel lining deformation angle is calculated;

[0036] The grouting position parameters of the next lining grouting are adjusted according to the change value of the shield tail position, and the grouting construction process of the shield machine is optimized according to the adjusted grouting position parameters and the tunnel lining grouting amount.

[0037] By adopting the above technical solution, after cement lining the tunnel, the corresponding tunnel lining deformation angle and the cutter head excavation diameter of the shield machine are obtained, which is helpful to timely correct and adjust the grouting position of the shield segment, and adjust the tunnel lining grouting amount of the next shield segment accordingly, so as to improve the adaptability between the grouting parameters and the shield deformation of the shield segment, and obtain the shield tail position parameters of the corresponding tunnel segment by the shield position of each segment, and calculate the corresponding shield tail position change of the tunnel lining deformation angle after deformation compensation in combination with the shield tail position parameters. The value is helpful to further adjust the grouting amount and grouting rate of the segment according to the change value of the shield tail position, so that the grouting cooling time is consistent with the change of the shield tail position, and the influence of the shield tail position deformation on the grouting cooling and solidification is reduced. The grouting position of the next lining grouting is adjusted according to the change value of the shield tail position, and the grouting construction process of the shield machine is optimized in combination with the adjusted grouting position parameters and the grouting amount of the tunnel lining, so that the grouting construction parameters of the shield machine can correspond to the actual shield deformation of each tunnel segment, thereby improving the grouting effect of the shield machine.

[0038] In a preferred example, the present application may be further configured as follows: the step of adjusting the corresponding tunnel lining grouting amount according to the cutterhead excavation diameter and the corresponding tunnel segment outer diameter also includes:

[0039] According to the excavation depth of the shield machine, obtaining the current segment force value of the shield segment under the excavation depth and the corresponding stratum environment;

[0040] According to the current segment force value, the support strength of the shield segment at each assembly position is adjusted to obtain a segment support strength adjustment value corresponding to the current geological environment of the shield machine;

[0041] According to the segment support strength adjustment value, the grouting rate corresponding to each segment is synchronously adjusted, and the anti-extrusion force value of each shield segment is analyzed according to the adjusted grouting rate and the corresponding segment support strength adjustment value;

[0042] The initial compression resistance parameters of the next excavation mileage of the shield machine are adjusted according to the compression resistance force value, and the shield segment construction process of the shield machine is optimized.

[0043] By adopting the above technical scheme, the stratum environment corresponding to the excavation depth of the shield machine is obtained, and the current segment force value of the shield segment in the stratum environment corresponding to the current excavation depth is further collected. The segment force situation of the corresponding stratum environment is analyzed according to the excavation pressure corresponding to the stratum depth, and the support strength of the shield segment at each assembly position is adjusted according to the current segment force value, so that each shield segment at different assembly positions can maintain a balance with the corresponding external pressure at the current assembly position, thereby obtaining the segment support strength adjustment value corresponding to different excavation depths, so that the segment support strength corresponds to the stratum pressure corresponding to each excavation depth, and through the segment support The strength adjustment value synchronously adjusts the grouting rate corresponding to each segment, and combines the adjusted grouting rate and segment support strength to comprehensively analyze the anti-extrusion stress value of each shield segment, thereby improving the accuracy of the stress analysis of the shield segment at each assembly position, and uses the anti-extrusion stress value to adjust the initial compression parameters of the next tunneling mileage of the shield machine to make the assembly of adjacent shield segments more consistent. Combined with the compression adjustment results of the compression parameters of each shield segment, the shield segment construction process of the shield machine is optimized, so that the optimized shield segment construction process is compatible with the formation pressure of the corresponding tunneling depth, thereby improving the construction accuracy of the shield segment construction.

[0044] In a preferred example, the present application may be further configured as follows: in the process of the shield machine excavating the tunnel according to the initial excavation parameters, calculating the excavation deviation of the shield machine in the tunnel axis direction, further comprising:

[0045] Obtaining the cutter head excavation temperature of the shield machine under the current geological conditions;

[0046] Determine the cutter head wear value of the tool when cutting the soil layer according to the cutter head excavation temperature, and analyze the stratum disturbance risk of the current geological conditions during the soil cutting process according to the cutter head wear value;

[0047] According to the stratum disturbance risk, the deviation between the soil cutting vibration amplitude of the current face and the tunnel axis is analyzed, and the cutter head excavation rate of the shield machine is adjusted accordingly according to the analysis result.

[0048] By adopting the above technical scheme, in the process of continuous excavation of the shield machine, the excavation temperature of the cutter head of the shield machine under the current geological conditions is obtained, which is helpful to judge the difficulty of cutting the stratum soil according to the excavation temperature of the cutter head, and further judge the cutter head wear value of the tool when cutting the soil layer, which is helpful to analyze the adaptability of the current cutter head material and the current cutting soil layer according to the cutter head wear value, analyze the stratum disturbance risk in the soil cutting process under the current geological conditions according to the cutter head wear value, analyze the stratum disturbance risk caused by cutter wear in the soil cutting process, improve the correlation between tool wear and stratum disturbance risk, and analyze the deviation between the soil cutting jitter amplitude of the current heading and the tunnel axis in combination with the stratum disturbance risk, judge the cutting error rate of the shield machine head according to the analysis result, and then adjust the cutter head excavation rate of the shield machine to make the cutter head excavation rate compatible with the current jitter amplitude, reduce the cutting jitter error of the shield machine for different stratum soil materials, and further improve the excavation stability of the shield machine in different stratum environments.

[0049] The second object of the invention is achieved by the following technical solutions:

[0050] An intelligent construction control device for a subway shield gas tunnel, characterized by comprising:

[0051] The data acquisition module is used to obtain the current geological conditions and trial excavation data of the gas tunnel and obtain the initial excavation parameters of the shield machine;

[0052] A deviation calculation module is used to calculate the excavation deviation of the excavation mileage of the shield machine in the direction of the tunnel axis during the process of the shield machine excavating the tunnel according to the initial excavation parameters;

[0053] A deviation correction module, used for performing a deviation correction process on the excavation deviation to obtain a deviation correction regression parameter of the shield machine;

[0054] The construction adjustment module is used to calculate the deviation correction deformation under the current geological conditions according to the deviation correction regression parameter, and synchronously adjust the excavation volume and lining grouting rate of the shield machine according to the deviation correction deformation.

[0055] By adopting the above technical scheme, the initial excavation parameters of the shield machine are adjusted according to the current geological conditions and trial excavation data of the subway gas tunnel, which is helpful to quickly adjust the tunneling construction control parameters of the shield machine, and in the process of the shield machine excavating the tunnel according to the initial excavation parameters, the excavation deviation of the shield machine's excavation mileage in the direction of the tunnel axis is calculated, and it is judged according to the excavation deviation whether the current excavation disturbance of the shield machine exceeds the allowable range of the tunnel construction error, which is helpful to improve the construction matching degree between the shield machine and the tunnel axis, and perform corresponding excavation correction processing on the excavation deviation to obtain the correction regression parameters of the shield machine, which is helpful to adjust the excavation construction control parameters of the shield machine according to the correction regression parameters. Corresponding adjustments are made to make the shield machine return from the deviated excavation direction to the tunnel axis direction, thereby improving the excavation accuracy of the shield machine, and calculating the correction deformation amount under current geological conditions based on the correction regression parameters, including the regression excavation deformation required for the shield machine to correct to the tunnel axis, the stratum deformation corresponding to the stratum disturbance during the shield machine's correction excavation process, etc., so as to synchronously adjust the shield machine's excavation volume and lining grouting rate according to the correction deformation amount, so that the shield machine can always maintain a state of soil balance during the correction process for construction and excavation, reduce the large-scale disturbance of the stratum during the shield machine's excavation process, and make timely construction parameter adjustments based on the shield machine's excavation deviation to reduce the lag between manual correction and actual excavation progress.

[0056] The third objective of the present application is achieved through the following technical solutions:

[0057] A computer device comprises a memory, a processor and a computer program stored in the memory and executable on the processor. When the processor executes the computer program, the steps of the intelligent construction control method of the subway shield gas tunnel are implemented.

[0058] The fourth objective of the present application is achieved through the following technical solutions:

[0059] A computer-readable storage medium stores a computer program, which, when executed by a processor, implements the steps of the intelligent construction control method for a subway shield gas tunnel.

[0060] In summary, the present application includes at least one of the following beneficial technical effects:

[0061] 1. Adjusting the initial excavation parameters of the shield machine according to the current geological conditions and trial excavation data of the subway gas tunnel is helpful to quickly adjust the excavation construction control parameters of the shield machine, and in the process of the shield machine excavating the tunnel according to the initial excavation parameters, calculate the excavation deviation of the shield machine's excavation mileage in the direction of the tunnel axis, and judge whether the current excavation disturbance of the shield machine exceeds the allowable range of the tunnel construction error according to the excavation deviation, which is helpful to improve the construction matching degree between the shield machine and the tunnel axis, and perform corresponding excavation correction processing on the excavation deviation to obtain the correction regression parameters of the shield machine, which is helpful to make corresponding adjustments to the excavation construction control parameters of the shield machine according to the correction regression parameters. , so that the shield machine returns to the tunnel axis direction from the deviated excavation direction, improves the excavation accuracy of the shield machine, and calculates the correction deformation under the current geological conditions according to the correction regression parameters, including the regression excavation deformation required for the shield machine to correct to the tunnel axis, the stratum deformation corresponding to the stratum disturbance during the shield machine correction excavation process, etc., so as to synchronously adjust the shield machine's excavation volume and lining grouting rate according to the correction deformation, so that the shield machine always maintains the state of soil balance during the correction process to carry out construction excavation, reduce the large-scale disturbance of the stratum during the shield machine excavation process, and make timely construction parameter adjustments according to the shield machine's excavation deviation, so as to reduce the lag between manual correction and actual excavation progress;

[0062] 2. During the tunneling process of the shield machine, the actual tunneling angle under the current geological conditions is obtained based on the tunneling angle of the shield machine to the current geological layer and the angle between the shield machine and the preset tunnel axis, which helps to accurately correct the next tunneling direction of the shield machine according to the actual tunneling angle, so that the tunneling angle deviation can be quickly restored to the tunnel axis range. According to the offset angle difference between the actual tunneling angle and the tunnel axis, the corresponding tunneling deviation value is calculated, so as to quickly plan the tunneling correction route for the tunneling deviation value, and evaluate whether the current tunneling construction of the shield machine meets the tunnel construction requirements according to the tunneling deviation value. According to the tunneling deviation value, the tunneling deviation trend of the shield machine is analyzed, and according to the tunneling deviation trend of the shield machine, the current shield is corrected. The slope mutation caused by the shield machine is further analyzed, so as to obtain the slope mutation analysis result of the shield machine under the current excavation deviation trend, which is helpful to timely control the stratum disturbance risk of the excavation deviation trend according to the slope mutation analysis result. Further, according to the slope mutation analysis result, the corresponding slope mutation range is subjected to mutation correction processing, so that the shield machine can quickly return the deviation angle to the tunnel axis while maintaining the balanced force of the soil layer, so as to obtain the correction regression parameter of the shield machine under the current slope mutation condition, which is helpful to timely correct the small-range excavation deviation of the shield machine according to the correction regression parameter, reduce the disturbance to the stratum caused by the correction process, and improve the excavation construction stability and adjustment timeliness of the shield machine;

[0063] 3. Under the current slope mutation situation, obtaining the geological data of the tunnel face in front of the shield machine and the current shield posture of the shield machine will help to make corresponding adjustments to the next tunneling direction and tunneling force of the shield machine according to the tunnel face geological data and the current shield posture, thereby improving the fit between the shield machine and the tunnel face geological conditions of the next tunneling direction, and analyzing the deviation angle of the shield machine under the current slope mutation to fit to the tunnel axis range area. According to the deviation correction regression construction route, the current construction parameters of the shield machine are quickly adjusted to improve the timeliness of the shield machine's construction parameter adjustment, and the deviation correction regression construction route is hierarchically corrected. Refined stratification can reduce the disturbance effect of large deviation of shield machine on the stratum, and calculate the correction regression angle caused by the correction mileage of the previous level on the slope mutation according to the hierarchical correction processing results. This helps to accurately control the regression angle under the correction construction process of each level, improve the correction accuracy of the correction regression angle of the shield machine, and adjust the correction angle parameters of the next level in combination with the correction regression angle of the previous level. By continuously adjusting the regression angle of the construction parameters of each level, the multi-level correction regression parameters under the current slope mutation situation can be obtained, which helps to reduce the disturbance effect of the shield machine's correction construction on the stratum during the correction construction process of the current slope mutation. BRIEF DESCRIPTION OF THE DRAWINGS

[0064] Figure 1 The invention is a flow chart for realizing an intelligent construction control method of a subway shield gas tunnel.

[0065] Figure 2 The invention is a flow chart for realizing the risk assessment of ground disturbance in an intelligent construction control method of a subway shield gas tunnel.

[0066] Figure 3 The invention is a flow chart for realizing step S30 of an intelligent construction control method for a subway shield gas tunnel.

[0067] Figure 4 The invention is a flow chart for realizing step S304 of an intelligent construction control method for a subway shield gas tunnel.

[0068] Figure 5 The invention is a flow chart for realizing step S40 of an intelligent construction control method for a subway shield gas tunnel.

[0069] Figure 6 The invention is a flow chart for realizing step S404 of an intelligent construction control method for a subway shield gas tunnel.

[0070] Figure 7 The invention is a flow chart for realizing step S4043 of an intelligent construction control method for a shield gas tunnel in a subway.

[0071] Figure 8 The present invention is a structural block diagram of an intelligent construction control device for a subway shield gas tunnel.

[0072] Fig. 9 The present invention is a schematic diagram of the internal structure of a computer device used to realize an intelligent construction control method for a subway shield gas tunnel. DETAILED DESCRIPTION

[0073] The present application is further described in detail below in conjunction with the accompanying drawings.

[0074] In one embodiment, if Figure 1 As shown, the present application discloses an intelligent construction control method for a subway shield gas tunnel, which specifically includes the following steps:

[0075] S10: obtaining the current geological conditions and trial excavation data of the gas tunnel, and obtaining the initial excavation parameters of the shield machine;

[0076] Specifically, according to the construction plan of the gas tunnel, the information on the engineering geology, hydrogeological conditions, tunnel burial depth, line type, ground surrounding environment, underground pipelines and obstacles of the corresponding construction location is obtained, and the geological distribution on the construction route is sampled and analyzed to obtain the current geological conditions of the gas tunnel, such as setting the tunneling parameters of the shield machine in the 100-meter trial excavation stage, and combining the construction monitoring during the excavation process to correct the initial excavation parameters of the shield machine, so that the construction process parameters of the shield machine correspond to the geological conditions at the tunnel entrance, such as rock layer distribution and sediment content, to obtain the initial excavation parameters of the shield machine.

[0077] S20: when the shield machine excavates the tunnel according to the initial excavation parameters, calculating the excavation deviation of the shield machine in the tunnel axis direction;

[0078] Specifically, in the process of the shield machine excavating the tunnel according to the initial excavation parameters, the actual excavation parameters of the shield machine are monitored by construction parameters. Each construction mileage is used as the calculation unit, and the construction measurement parameters of each excavation mileage are checked with the three-dimensional coordinates of the corresponding mileage. For example, the horizontal deviation of the head position of the shield machine in the horizontal direction along the mileage direction and the tunnel axis, and the vertical deviation of the head position of the shield machine in the vertical direction and perpendicular to the tunnel axis are used as the excavation deviation along the tunnel axis.

[0079] In one embodiment, the risk of disturbing the ground layer due to the shaking of the machine head when cutting different geological layers is reduced, such as Figure 2 As shown, after step S20, it also includes:

[0080] S201: Obtaining the cutter head excavation temperature of the shield machine under current geological conditions;

[0081] Specifically, when the shield machine is cutting the soil layer on the current tunnel face, the cutter head excavation temperature generated by the shield machine when cutting the soil layer under the current geological conditions is obtained through a temperature sensor preset at the head position of the shield machine.

[0082] S202: judging the cutter head wear value of the tool when cutting the soil layer according to the cutter head excavation temperature, and analyzing the stratum disturbance risk of the current geological conditions during the soil cutting process according to the cutter head wear value;

[0083] Specifically, the cutter head wear value when the tool is cutting the current soil layer is judged according to the cutter head excavation temperature. For example, when the tool is cutting dense buildings and complex strata, the cutter head temperature generated when cutting rock strata of different hardness is different. The higher the cutter head excavation temperature, the higher the hardness of the cutting rock strata, and the more serious the wear on the tool. The tool wear value is comprehensively judged in combination with the cutter head vibration amplitude during cutting. The higher the tool wear value, the higher the risk of stratum disturbance when cutting the soil under the current geological conditions, that is, the greater the vibration amplitude of the cutter head during the cutting process. Similarly, the lower the tool wear value, the lower the risk of stratum disturbance when cutting the soil under the current geological conditions, that is, the smaller the vibration amplitude of the cutter head during the cutting process.

[0084] S203: According to the risk of ground disturbance, the deviation between the soil cutting vibration amplitude of the current face and the tunnel axis is analyzed, and the cutter head excavation rate of the shield machine is adjusted accordingly according to the analysis results.

[0085] Specifically, according to the risk of stratum disturbance caused by the current tool wear, a directional analysis is performed on the deviation between the soil cutting jitter amplitude of the current face and the tunnel axis. The larger the jitter amplitude, the greater the deviation error between the corresponding excavation direction and the tunnel axis. The excavation rate of the shield machine's cutter head is adjusted. If the jitter amplitude is larger, the cutter head excavation rate is reduced, and if the jitter amplitude is smaller, the cutter head excavation rate is increased, thereby obtaining the cutter head excavation rate corresponding to the soil cutting jitter amplitude.

[0086] S30: performing excavation deviation correction processing on the excavation deviation to obtain the correction regression parameter of the shield machine;

[0087] Specifically, Figure 3 As shown, step S30 specifically includes the following steps:

[0088] S301: During the tunneling process of the shield machine, an actual tunneling angle of the shield machine under current geological conditions is obtained;

[0089] Specifically, during the shield machine excavation process, based on the actual excavation mileage of the shield machine, the starting point of the actual excavation mileage or the end point of the previous excavation mileage is taken as the origin, the end point of the actual excavation inner layer is taken as the end point, and the angle deviation between the origin and the end point of the actual excavation mileage is taken as the actual excavation angle under the current geological conditions.

[0090] S302: Obtain the tunnel axis corresponding to the current excavation position, and calculate the excavation deviation value between the actual excavation angle and the tunnel axis;

[0091] Specifically, the excavation route corresponding to the actual excavation angle is extended to the tunnel axis until there is an intersection between the actual excavation route and the tunnel axis. Taking the intersection as the origin, the angle difference between the deviation angle between the actual excavation route and the tunnel axis and the actual excavation angle is taken as the corresponding excavation deviation value.

[0092] S303: Analyzing the tunneling deviation trend of the shield machine according to the tunneling deviation value, and obtaining a slope mutation analysis result of the shield machine under the current tunneling deviation trend;

[0093] Specifically, the tunneling deviation trend of the shield machine is analyzed according to the tunneling deviation value. For example, 0.4% of the angle deviation between the actual tunneling construction and the tunnel axis is set as the deviation angle threshold according to the tunnel construction requirements. When the angle deviation angle exceeds 0.4%, it means that the slope mutation of the shield machine under the current tunneling deviation trend has reached the level of stratum disturbance. When the angle deviation angle does not exceed 0.4%, it means that the slope mutation of the shield machine under the current tunneling deviation trend is still within the allowable range of deviation error of tunnel construction.

[0094] S304: According to the slope mutation analysis result, a mutation correction process is performed on the slope mutation range corresponding to the slope mutation analysis result to obtain a correction regression parameter of the shield machine under the current slope mutation condition.

[0095] Specifically, Figure 4 As shown, step S304 specifically includes:

[0096] S3041: Obtaining the geological data of the tunnel face under the current slope mutation condition and the current shield posture of the shield machine;

[0097] Specifically, the address data of the tunnel face under the current slope mutation condition is obtained, including the rock layer distribution, mud-sand ratio, etc. of the current tunnel face, so as to obtain the tunnel face geological data of the current tunnel face, wherein the tunnel face is the soil surface that is in contact or about to be in contact with the head of the shield machine, and according to the shield posture of the shield machine in the waiting state for the next tunnel construction after completing the previous tunneling mileage, the current shield posture of the shield machine is obtained.

[0098] S3042: Based on the geological data of the tunnel face and the current shield posture, the shield machine is analyzed to return the deviation angle to the corrective regression construction route within the tunnel axis range;

[0099] Specifically, according to the face address data and the corresponding current shield posture, the fitting displacement of the shield machine to fit the deviation angle within the tunnel axis range is analyzed, and the shield machine's correction and regression construction route is planned according to the fitting displacement and the current cutter head offset angle. According to the planning results, the construction parameters of the next excavation mileage of the shield machine are modified to the correction parameters corresponding to the correction and regression construction route.

[0100] S3043: Perform hierarchical correction processing on the correction regression construction route, and calculate the correction regression angle of the previous level correction mileage for the slope mutation according to the hierarchical correction processing results;

[0101] Specifically, the correction and regression construction route of each level is set according to the optimal excavation deviation floating range of the shield machine under the current geological conditions, so that the excavation direction of the shield machine is always kept within the allowable deviation range, and after the correction construction of the previous level is completed, combined with the correction mileage of the previous level corresponding to the correction construction of the previous level, the correction regression angle caused by the sudden slope change after the current correction construction is calculated, such as calculating the ratio between the correction mileage of the completed construction and the total correction mileage corresponding to the total correction regression route, and taking the product of the mileage ratio and the total deviation angle caused by the total slope mutation as the corresponding correction regression angle.

[0102] S3044: The correction angle parameters of the next level are adjusted according to the correction regression angle of the previous level, so as to obtain the multi-level correction regression parameters of the shield machine under the current slope mutation condition.

[0103] Specifically, according to the correction regression angle of the previous level correction, the initial correction angle parameters of the next level corresponding to the correction processing result of the current level of the correction regression construction route are adjusted. For example, the sum of the correction regression angle and the initial correction angle parameter is used as the comprehensive correction angle of the current level correction route, and according to the comprehensive correction angle, the shield machine excavation direction and excavation power corresponding to the current level correction route are adjusted. For example, according to the comprehensive correction angle, when excavating in an uphill section, the thrust of the lower cylinder of the shield machine is increased according to the comprehensive uphill angle of the uphill section; when excavating in a downbreak, the thrust of the upper cylinder is increased; or when the comprehensive correction angle is for excavating a turning curve section, the thrust of the left or right cylinder is increased according to the comprehensive turning angle; when on a straight and flat slope route, the thrust of all cylinders is adjusted to be the same, thereby obtaining the multi-level correction regression parameters of the shield machine under the current slope mutation condition.

[0104] S40: Calculate the deviation correction deformation under the current geological conditions according to the deviation correction regression parameter, and synchronously adjust the excavation volume of the shield machine and the lining grouting rate according to the deviation correction deformation.

[0105] Specifically, Figure 5 As shown, step S40 specifically includes the following steps:

[0106] S401: Obtaining the static geological pressure corresponding to the current tunnel face and the deviated excavation pressure corresponding to the excavation deviation according to the deviation correction regression parameter;

[0107] Specifically, according to the correction regression parameters of the shield machine, the static geological pressure caused by the current heading on the head of the shield machine under static conditions is collected through the pressure sensor preset on the head of the shield machine. The deviation excavation pressure corresponding to the excavation deviation mainly comes from the jack thrust pressure during deviated excavation. The deviation excavation pressure is calculated by the product of the current jack thrust pressure and the cosine value of the deviation angle.

[0108] S402: comprehensively calculating the deviation correction deformation of the shield machine under the current geological conditions according to the static geological pressure and the deviation excavation pressure;

[0109] Specifically, the pressure difference between the static geological pressure and the deviated tunneling pressure is used as the comprehensive tunneling force exerted on the shield machine at the current face, the total correction mileage of the shield machine under the comprehensive tunneling force is collected, and the mapping value of the total correction mileage in the direction of the tunnel axis is calculated, such as the cosine value of the total correction mileage, etc. The difference between the mapping value of the total correction mileage and the ideal tunneling mileage in the preset tunnel axis direction is used as the correction deformation under the current geological conditions.

[0110] S403: adjusting the tunnel face cutting rate of the shield machine according to the deviation correction deformation amount, and controlling the soil equilibrium pressure between the deviation correction excavation volume and the corresponding discharge volume at the same time node according to the tunnel face cutting rate;

[0111] Specifically, the face cutting rate of the shield machine is adjusted according to the deviation correction deformation, such as adjusting the rotation speed of the cutting disc. For example, the larger the deviation correction deformation, the greater the face cutting rate. In the same excavation time, the excavation direction is closer to the tunnel axis, and the deviation correction rate of the shield machine is improved. According to the face cutting rate, the deviation correction excavation volume and the corresponding soil discharge volume at the same time node are adjusted. For example, the excavation volume corresponding to the deviation correction mileage of each level is calculated by formula (1). Formula (1) is as follows:

[0112] Q=π / 4×D×L (1)

[0113] Among them, Q represents the excavation volume corresponding to the correction mileage of each level, D represents the excavation diameter of the shield machine, and L represents the ring width of the segment. The excavation diameter of the shield machine in this embodiment is selected as 6.68 square meters, and the ring width of the segment is selected as 1.5 meters, so the excavation volume is calculated to be 52.56 cubic meters per ring.

[0114] The soil discharge volume in this embodiment is set to be between 130% and 150% of the excavated soil volume, that is, between 68.34 cubic meters per ring and 78.85 cubic meters per ring. The soil balance pressure between the excavated soil volume and the soil discharge volume is achieved by adjusting the propulsion speed of the shield machine and the rotation speed of the screw conveyor.

[0115] S404: The lining grouting rate of the shield machine is adjusted according to the soil equilibrium pressure, and the grouting process is synchronized with the cutting rate of the tunnel face.

[0116] Specifically, the lining grouting rate of the shield machine is adjusted according to the soil equilibrium pressure. For example, when the soil equilibrium pressure deviates, it means that the shield machine has over-excavation, and it is necessary to increase the lining grouting rate and lining grouting position of the shield machine to perform advance grouting treatment on the shield machine. When the soil equilibrium pressure is in a relatively stable state, the lining grouting rate is adjusted to be consistent with the face cutting rate, so that when the shield machine is cutting at the face cutting rate, the shield segments can be synchronously grouted according to the lining grouting rate.

[0117] In one embodiment, if Figure 6 As shown, step S404 also includes:

[0118] S4041: Obtain the tunnel lining deformation angle and the cutter head excavation diameter of the shield machine after the tunnel is cement lined;

[0119] Specifically, after cement lining the shield segments, the tunnel lining deformation angle caused by the cement layer lined between adjacent shield segments is obtained according to the connection angle of adjacent shield segments, that is, the solidification displacement of the solidifying cement layer caused by the gravity of the shield segments or the compression of the stratum during the cooling and solidification of the cement after cement lining. The solidification displacement of the cement layer is manifested in the connection deviation angle between adjacent shield segments. Therefore, the corresponding tunnel lining deformation angle is obtained by measuring the connection angle of adjacent shield segments, and different cutter heads are selected in the excavation environment of different rock formations. The excavation diameter of the cutter head of the shield machine is obtained by measuring the diameter of the replacement cutter head in advance when replacing the cutter head.

[0120] S4042: Calculate the grouting pressure of the next lining grouting according to the deformation angle of the tunnel lining, and perform deformation compensation for the deformation angle of the previous tunnel lining according to the grouting pressure;

[0121] Specifically, the total extrusion pressure of the static groundwater pressure and the static soil pressure on the lining segment is calculated under static conditions, and the product of the total extrusion pressure and the cosine value of the tunnel lining deformation angle is used as the grouting pressure for the next lining grouting, and the deformation angle of the previous tunnel lining is compensated for according to the grouting pressure. For example, the current shield segment is quickly grouted according to the grouting pressure, and the deformation error of the previous tunnel lining is simulated back to the preset tunnel line. If the deformation of the previous tunnel lining is an upward deformation, the next tunnel lining is tightened downward according to the grouting pressure, so that the comprehensive laying direction between the previous tunnel segment and the next tunnel segment remains the same as the preset tunnel line direction.

[0122] S4043: According to the cutter head excavation diameter and the corresponding tunnel segment outer diameter, the corresponding tunnel lining grouting amount is adjusted; specifically, the tunnel lining grouting amount is calculated by formula (2), which is as follows:

[0123] V=π / 4×K×L×(D2-D1) (2)

[0124] Wherein, V represents the grouting volume of the tunnel lining, K represents the expansion coefficient, in this embodiment, K takes a value of 1.5-2.0, L represents the ring width formed by the shield segment, D1 represents the outer diameter of the shield segment, and D2 represents the excavation diameter of the shield machine. In this embodiment, the calculated synchronous grouting volume per ring is 6.47 cubic meters to 8.63 cubic meters.

[0125] In one embodiment, if Figure 7 As shown, S4043 also includes:

[0126] S501: According to the excavation depth of the shield machine, obtain the current segment force value of the shield segment under the excavation depth and the corresponding stratum environment;

[0127] Specifically, the excavation depth of the shield machine is the straight-line distance from the excavation position to the ground. According to the excavation depth of the shield machine and the corresponding stratum environment, including the distribution of rock strata corresponding to the excavation depth, the stress conditions of the shield segments at the current excavation depth are analyzed. For example, the stress conditions at the head position of the shield machine are detected by a pressure sensor to obtain the squeezing force of the stratum soil on the segments, thereby obtaining the current segment stress value of the shield segments.

[0128] S502: adjusting the support strength of the shield segment at each assembly position according to the current segment force value, and obtaining a segment support strength adjustment value corresponding to the current geological environment of the shield machine;

[0129] Specifically, the supporting strength of the shield segment at each assembly position is adjusted according to the current segment stress value. For example, the segment located above the tunnel needs to support the dual pressure of the extrusion stress of the stratum soil and the segment's own gravity, so the supporting strength of the segment is adjusted to the superimposed pressure of the current segment stress value and the segment's own gravity. For another example, the supporting strength of the shield segment at the side assembly position is the comprehensive stress value of the current segment stress value and the cosine value of its own gravity at the current side inclination angle, thereby obtaining the segment support strength adjustment value of each segment corresponding to the current geological environment of the shield machine.

[0130] S503: According to the segment support strength adjustment value, the grouting rate corresponding to each segment is synchronously adjusted, and according to the adjusted grouting rate and the corresponding segment support strength adjustment value, the anti-extrusion force value of each shield segment is analyzed;

[0131] Specifically, according to the segment support strength adjustment value, the grouting rate corresponding to each segment is synchronously adjusted, and the slurry cooling and solidification speed of each segment is controlled by adjusting the grouting rate. For example, when grouting the segment above the tunnel, combined with the support strength adjustment value of the current segment, the grouting rate is increased to keep consistent with the support strength adjustment value or slightly greater than the support strength adjustment value, so that the mud can be injected into the gaps between the segments. For another example, when grouting the side segments, according to the corresponding segment support strength adjustment value and the corresponding mud flow rate, the grouting rate of the corresponding segment is increased, so that the grouting cooling and solidification rate is greater than the mud flow rate, and the anti-extrusion stress condition of each shield segment is analyzed after grouting and solidification. For example, after grouting, the adjacent segments are connected together, and the stress value of each segment is the resultant force between the external stratum extrusion force and the static water pressure, thereby obtaining the anti-extrusion stress value of each shield segment.

[0132] S504: adjusting the initial compression resistance parameters of the shield machine for the next excavation mileage according to the compression resistance stress value, and optimizing the parameters of the shield segment construction process of the shield machine.

[0133] Specifically, the construction parameters of the next excavation mileage of the shield machine are adjusted according to the anti-extrusion stress value of the segment, such as adjusting the initial compression parameters of the next excavation mileage, and taking the maximum excavation thrust of the previous excavation mileage as the initial compression thrust of the next excavation mileage; and during the continuous excavation of the next excavation mileage, the shield segment construction process of the shield machine is optimized according to the actual construction progress, including the construction thrust, excavation speed, grouting speed, and the coordinated coordination parameters between excavation and discharge volume.

[0134] S4044: according to the shield position of the shield machine segment, the shield tail position parameter of each tunnel segment is obtained, and the shield tail position change value obtained after the deformation compensation of the tunnel lining deformation angle is calculated;

[0135] Specifically, according to the shield position of the shield machine's segment, the shield tail position of each tunnel segment is marked to obtain the corresponding shield tail position parameters. After deformation compensation is performed on the tunnel lining deformation angle, the shield tail position difference of adjacent shield segments is calculated, and the shield tail position change value caused by the corresponding deformation compensation is obtained based on the shield tail position difference.

[0136] S4045: Adjust the grouting position parameters of the next lining grouting according to the change value of the shield tail position, and optimize the grouting construction process of the shield machine according to the adjusted grouting position parameters and the tunnel lining grouting amount.

[0137] Specifically, the grouting position parameters of the next lining grouting are adjusted according to the change value of the shield tail position. If the shield tail position of the previous lining segment is too high, the grouting position of the next lining segment is lowered in the opposite direction on the original basis, so that the tunnel pipeline formed by multiple shield segments and the preset pipeline direction of the construction drawings remain the same within the allowable error range, and the adjusted grouting position parameters and tunnel lining grouting amount are modified to the original lining construction process, and the grouting construction process of the shield machine is optimized by optimizing grouting parameters such as grouting position and grouting amount, so as to obtain a grouting construction process that is more in line with the actual excavation conditions.

[0138] It should be understood that the size of the serial numbers of the steps in the above embodiments does not mean the order of execution. The execution order of each process should be determined by its function and internal logic, and should not constitute any limitation on the implementation process of the embodiments of the present application.

[0139] In one embodiment, an intelligent construction control device for a subway shield gas tunnel is provided, and the intelligent construction control device for a subway shield gas tunnel corresponds one-to-one to the intelligent construction control method for a subway shield gas tunnel in the above embodiment. Figure 8 As shown, the intelligent construction control device of the subway shield gas tunnel includes a data acquisition module, a deviation calculation module, a deviation correction module and a construction adjustment module. The detailed description of each functional module is as follows:

[0140] The data acquisition module is used to obtain the current geological conditions and trial excavation data of the gas tunnel and obtain the initial excavation parameters of the shield machine;

[0141] The deviation calculation module is used to calculate the excavation deviation of the shield machine's excavation mileage in the direction of the tunnel axis when the shield machine excavates the tunnel according to the initial excavation parameters;

[0142] The deviation correction module is used to correct the excavation deviation and obtain the correction regression parameters of the shield machine;

[0143] The construction adjustment module is used to calculate the correction deformation amount under the current geological conditions according to the correction regression parameters, and synchronously adjust the shield machine's excavation volume and lining grouting rate according to the correction deformation amount.

[0144] Preferably, The correction module specifically includes:

[0145] The tunneling data acquisition submodule is used to obtain the actual tunneling angle of the shield machine under the current geological conditions during the tunneling process of the shield machine;

[0146] The excavation deviation calculation submodule is used to obtain the tunnel axis corresponding to the current excavation position and calculate the excavation deviation value between the actual excavation angle and the tunnel axis;

[0147] The deviation trend analysis submodule is used to analyze the tunneling deviation trend of the shield machine according to the tunneling deviation value, and obtain the slope mutation analysis result of the shield machine under the current tunneling deviation trend;

[0148] The mutation correction submodule is used to perform mutation correction processing on the slope mutation range corresponding to the slope mutation analysis results according to the slope mutation analysis results, and obtain the correction regression parameters of the shield machine under the current slope mutation situation.

[0149] Preferably, the mutation correction submodule specifically includes:

[0150] The shield data acquisition unit is used to obtain the geological data of the tunnel face under the current slope mutation condition and the current shield posture of the shield machine;

[0151] The construction route planning unit is used to analyze the deviation angle of the shield machine and return it to the tunnel axis range area according to the geological data of the face and the current shield posture, and then return to the corrective regression construction route;

[0152] A deviation correction parameter calculation unit is used to perform hierarchical deviation correction processing on the deviation correction regression construction route, and calculate the deviation correction regression angle of the previous level deviation correction mileage for the slope mutation situation according to the hierarchical deviation correction processing results;

[0153] The correction parameter adjustment unit is used to adjust the correction angle parameters of the next level according to the correction regression angle of the previous level correction, so as to obtain the multi-level correction regression parameters of the shield machine under the current slope mutation condition.

[0154] Preferably, the construction adjustment module specifically includes:

[0155] The shield pressure acquisition submodule is used to obtain the static geological pressure corresponding to the current tunnel face and the deviated excavation pressure corresponding to the excavation deviation according to the deviation correction regression parameters;

[0156] The correction deformation calculation submodule is used to comprehensively calculate the correction deformation of the shield machine under the current geological conditions based on the static geological pressure and the deviation tunneling pressure;

[0157] The pressure regulating submodule is used to adjust the tunnel face cutting rate of the shield machine according to the deviation correction deformation variable, and control the soil equilibrium pressure between the deviation correction excavation volume and the corresponding discharge volume at the same time node according to the tunnel face cutting rate;

[0158] The synchronous grouting adjustment submodule is used to adjust the lining grouting rate of the shield machine according to the soil equilibrium pressure, and to perform synchronous grouting processing with the cutting rate of the tunnel face.

[0159] Preferably, the synchronous grouting adjustment submodule further includes:

[0160] The lining data acquisition unit is used to obtain the tunnel lining deformation angle and the cutter head excavation diameter of the shield machine after the tunnel is cement lined;

[0161] The deformation compensation unit is used to calculate the grouting pressure of the next lining grouting according to the deformation angle of the tunnel lining, and to compensate the deformation angle of the previous tunnel lining according to the grouting pressure;

[0162] The grouting amount adjustment unit is used to adjust the corresponding tunnel lining grouting amount according to the cutter head excavation diameter and the corresponding tunnel segment outer diameter;

[0163] The shield tail position acquisition unit is used to obtain the shield tail position parameters of each tunnel segment according to the segment shield position of the shield machine, and calculate the shield tail position change value obtained after the deformation compensation of the tunnel lining deformation angle;

[0164] The grouting process optimization unit is used to adjust the grouting position parameters of the next lining grouting according to the change value of the shield tail position, and optimize the grouting construction process of the shield machine according to the adjusted grouting position parameters and the tunnel lining grouting amount.

[0165] Preferably, the grouting amount adjustment unit further includes:

[0166] The segment force analysis subunit is used to obtain the current segment force value of the shield segment under the excavation depth and the corresponding formation environment according to the excavation depth of the shield machine;

[0167] The support force adjustment subunit is used to adjust the support force of the shield segment at each assembly position according to the current segment force value, so as to obtain the segment support force adjustment value corresponding to the current geological environment of the shield machine;

[0168] The compressive stress analysis subunit is used to synchronously adjust the grouting rate corresponding to each segment according to the segment support strength adjustment value, and analyze the compressive stress value of each shield segment according to the adjusted grouting rate and the corresponding segment support strength adjustment value;

[0169] The parameter optimization subunit is used to adjust the initial compression resistance parameters of the shield machine for the next excavation mileage according to the anti-extrusion force value, and to optimize the parameters of the shield segment construction process of the shield machine.

[0170] Preferably, the deviation calculation module further includes:

[0171] The cutter head parameter acquisition submodule is used to obtain the cutter head excavation temperature of the shield machine under the current geological conditions;

[0172] The disturbance risk analysis submodule is used to determine the cutter head wear value of the tool when cutting the soil layer according to the cutter head excavation temperature, and analyze the stratum disturbance risk in the soil cutting process under the current geological conditions according to the cutter head wear value;

[0173] The tunneling rate adjustment submodule is used to analyze the deviation between the soil cutting vibration amplitude of the current face and the tunnel axis according to the risk of stratum disturbance, and adjust the tunneling rate of the shield machine cutter head accordingly according to the analysis results.

[0174] The specific definition of the intelligent construction control device for subway shield gas tunnel can be found in the definition of the intelligent construction control method for subway shield gas tunnel mentioned above, which will not be repeated here. Each module in the above-mentioned intelligent construction control device for subway shield gas tunnel can be implemented in whole or in part by software, hardware and their combination. The above-mentioned modules can be embedded in or independent of the processor in the computer device in the form of hardware, or can be stored in the memory of the computer device in the form of software, so that the processor can call and execute the operations corresponding to the above modules.

[0175] In one embodiment, a computer device is provided. The computer device may be a server, and its internal structure diagram may be as follows: Fig. 9As shown. The computer device includes a processor, a memory, a network interface and a database connected through a system bus. Among them, the processor of the computer device is used to provide computing and control capabilities. The memory of the computer device includes a non-volatile storage medium and an internal memory. The non-volatile storage medium stores an operating system, a computer program and a database. The internal memory provides an environment for the operation of the operating system and the computer program in the non-volatile storage medium. The database of the computer device is used to store the construction data of the shield machine during the tunnel construction process and the control parameters of the shield machine. The network interface of the computer device is used to communicate with an external terminal through a network connection. When the computer program is executed by the processor, an intelligent construction control method for a subway shield gas tunnel is realized.

[0176] In one embodiment, a computer-readable storage medium is provided, on which a computer program is stored. When the computer program is executed by a processor, the steps of the above-mentioned intelligent construction control method for a subway shield gas tunnel are implemented.

[0177] Those skilled in the art can understand that all or part of the processes in the above-mentioned embodiment methods can be completed by instructing the relevant hardware through a computer program, and the computer program can be stored in a non-volatile computer-readable storage medium. When the computer program is executed, it can include the processes of the embodiments of the above-mentioned methods. Among them, any reference to memory, storage, database or other media used in the embodiments provided in this application can include non-volatile and / or volatile memory. Non-volatile memory can include read-only memory (ROM), programmable ROM (PROM), electrically programmable ROM (EPROM), electrically erasable programmable ROM (EEPROM) or flash memory. Volatile memory can include random access memory (RAM) or external cache memory. As an illustration and not limitation, RAM is available in many forms, such as static RAM (SRAM), dynamic RAM (DRAM), synchronous DRAM (SDRAM), double data rate SDRAM (DDRSDRAM), enhanced SDRAM (ESDRAM), synchronous link (Synchlink) DRAM (SLDRAM), memory bus (Rambus) direct RAM (RDRAM), direct memory bus dynamic RAM (DRDRAM), and memory bus dynamic RAM (RDRAM).

[0178] Those skilled in the art can clearly understand that for the convenience and simplicity of description, only the division of the above-mentioned functional units and modules is used as an example. In actual applications, the above-mentioned functions can be distributed and completed by different functional units and modules as needed, that is, the internal structure of the device can be divided into different functional units or modules to complete all or part of the functions described above.

[0179] The embodiments described above are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application has been described in detail with reference to the aforementioned embodiments, a person skilled in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some of the technical features may be replaced by equivalents. Such modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present application, and should all be included in the protection scope of the present application.

Claims

1. An intelligent construction control method for a subway shield gas tunnel, characterized in that: include: Obtain the current geological conditions and trial excavation data of the gas tunnel and obtain the initial excavation parameters of the shield machine; During the tunnel boring process of the shield machine according to the initial excavation parameters, calculating the tunnel boring deviation of the tunnel boring machine in the tunnel axis direction; Performing excavation deviation correction processing on the excavation deviation to obtain the correction regression parameter of the shield machine; According to the deviation correction regression parameter, the deviation correction deformation amount under the current geological conditions is calculated, and the excavation amount and lining grouting rate of the shield machine are synchronously adjusted according to the deviation correction deformation amount; The step of calculating the correction deformation amount under the current geological conditions according to the correction regression parameter, and synchronously adjusting the excavation amount and lining grouting rate of the shield machine according to the correction deformation amount specifically includes: According to the deviation correction regression parameter, the static geological pressure corresponding to the current tunnel face and the deviated excavation pressure corresponding to the excavation deviation are obtained; Comprehensively calculating the deviation correction deformation of the shield machine under current geological conditions according to the static geological pressure and the deviation excavation pressure; Adjusting the tunnel face cutting rate of the shield machine according to the deviation correction deformation amount, and controlling the soil equilibrium pressure between the deviation correction excavation volume and the corresponding discharge volume at the same time node according to the tunnel face cutting rate; The lining grouting rate of the shield machine is adjusted according to the soil equilibrium pressure, and the grouting process is performed synchronously with the cutting rate of the tunnel face; The method further comprises: adjusting the lining grouting rate of the shield machine according to the soil equilibrium pressure and performing synchronous grouting processing with the tunnel face cutting rate; Obtaining the tunnel lining deformation angle of the tunnel after cement lining and the cutter head excavation diameter of the shield machine; Calculating the grouting pressure of the next lining grouting according to the deformation angle of the tunnel lining, and performing deformation compensation for the deformation angle of the previous tunnel lining according to the grouting pressure; According to the cutterhead excavation diameter and the corresponding tunnel segment outer diameter, adjusting the corresponding tunnel lining grouting amount; The tunnel lining grouting volume is calculated by formula (2), which is as follows: V=π / 4×K×L×(D2-D1) (2) Wherein, V represents the amount of grouting for tunnel lining, K represents the expansion coefficient, K is 1.5-2.0, L represents the ring width formed by the shield segment, D1 represents the outer diameter of the shield segment, and D2 represents the excavation diameter of the shield machine; According to the segment shield position of the shield machine, the shield tail position parameter of each tunnel segment is obtained, and the shield tail position change value obtained after the deformation compensation of the tunnel lining deformation angle is calculated; The grouting position parameters of the next lining grouting are adjusted according to the change value of the shield tail position, and the grouting construction process of the shield machine is optimized according to the adjusted grouting position parameters and the tunnel lining grouting amount.

2. The intelligent construction control method for a subway shield gas tunnel according to claim 1 is characterized in that: The performing excavation deviation correction processing on the excavation deviation to obtain the correction regression parameter of the shield machine specifically includes: During the tunneling process of the shield machine, obtaining an actual tunneling angle of the shield machine under the current geological conditions; Obtaining the tunnel axis corresponding to the current excavation position, and calculating the excavation deviation value between the actual excavation angle and the tunnel axis; Analyzing the excavation deviation trend of the shield machine according to the excavation deviation value to obtain a slope mutation analysis result of the shield machine under the current excavation deviation trend; According to the slope mutation analysis result, a mutation correction process is performed on the slope mutation range corresponding to the slope mutation analysis result to obtain the correction regression parameters of the shield machine under the current slope mutation condition.

3. The intelligent construction control method for a subway shield gas tunnel according to claim 2 is characterized in that: According to the slope mutation analysis result, performing mutation correction processing on the slope mutation range corresponding to the slope mutation analysis result to obtain the correction regression parameter of the shield machine under the current slope mutation condition specifically includes: Acquire the tunnel face geological data under the current slope mutation condition and the current shield posture of the shield machine; Analyzing the deviation correction and regression construction route of the shield machine to return the deviation angle to the tunnel axis range area according to the face geological data and the current shield posture; Performing hierarchical correction processing on the correction and regression construction route, and calculating the correction regression angle of the previous level correction mileage for the slope mutation according to the hierarchical correction processing results; The correction angle parameters of the next level are adjusted according to the correction regression angle of the previous level, so as to obtain the multi-level correction regression parameters of the shield machine under the current slope mutation condition.

4. The intelligent construction control method for a subway shield gas tunnel according to claim 1 is characterized in that: The step of adjusting the corresponding tunnel lining grouting amount according to the cutter head excavation diameter and the corresponding tunnel segment outer diameter also includes: According to the excavation depth of the shield machine, obtaining the current segment force value of the shield segment under the excavation depth and the corresponding stratum environment; According to the current segment force value, the support strength of the shield segment at each assembly position is adjusted to obtain a segment support strength adjustment value corresponding to the current geological environment of the shield machine; According to the segment support strength adjustment value, the grouting rate corresponding to each segment is synchronously adjusted, and the anti-extrusion force value of each shield segment is analyzed according to the adjusted grouting rate and the corresponding segment support strength adjustment value; The initial compression resistance parameters of the next excavation mileage of the shield machine are adjusted according to the compression resistance force value, and the shield segment construction process of the shield machine is optimized.

5. The intelligent construction control method for a subway shield gas tunnel according to claim 1 is characterized in that: The method of calculating the tunneling deviation of the shield machine in the tunneling mileage direction of the tunnel axis during tunneling by the shield machine according to the initial excavation parameters further includes: Obtaining the cutter head excavation temperature of the shield machine under the current geological conditions; Determine the cutter head wear value of the tool when cutting the soil layer according to the cutter head excavation temperature, and analyze the stratum disturbance risk of the current geological conditions during the soil cutting process according to the cutter head wear value; According to the stratum disturbance risk, the deviation between the soil cutting vibration amplitude of the current face and the tunnel axis is analyzed, and the cutter head excavation rate of the shield machine is adjusted accordingly according to the analysis result.

6. An intelligent construction control device for a subway shield gas tunnel, characterized in that: include: The data acquisition module is used to obtain the current geological conditions and trial excavation data of the gas tunnel and obtain the initial excavation parameters of the shield machine; A deviation calculation module is used to calculate the excavation deviation of the excavation mileage of the shield machine in the direction of the tunnel axis during the process of the shield machine excavating the tunnel according to the initial excavation parameters; A deviation correction module, used for performing a deviation correction process on the excavation deviation to obtain a deviation correction regression parameter of the shield machine; A construction adjustment module, used to calculate the deviation correction deformation under the current geological conditions according to the deviation correction regression parameter, and synchronously adjust the excavation volume and lining grouting rate of the shield machine according to the deviation correction deformation; The construction adjustment module is specifically used to obtain the static geological pressure corresponding to the current tunnel face and the deviated excavation pressure corresponding to the excavation deviation according to the deviation correction regression parameter; Comprehensively calculating the deviation correction deformation of the shield machine under current geological conditions according to the static geological pressure and the deviation excavation pressure; Adjusting the tunnel face cutting rate of the shield machine according to the deviation correction deformation amount, and controlling the soil equilibrium pressure between the deviation correction excavation volume and the corresponding discharge volume at the same time node according to the tunnel face cutting rate; The lining grouting rate of the shield machine is adjusted according to the soil equilibrium pressure, and the grouting process is performed synchronously with the cutting rate of the tunnel face; The method further comprises: adjusting the lining grouting rate of the shield machine according to the soil equilibrium pressure and performing synchronous grouting processing with the tunnel face cutting rate; Obtaining the tunnel lining deformation angle of the tunnel after cement lining and the cutter head excavation diameter of the shield machine; Calculating the grouting pressure of the next lining grouting according to the deformation angle of the tunnel lining, and performing deformation compensation for the deformation angle of the previous tunnel lining according to the grouting pressure; According to the cutterhead excavation diameter and the corresponding tunnel segment outer diameter, adjusting the corresponding tunnel lining grouting amount; The tunnel lining grouting volume is calculated by formula (2), which is as follows: V=π / 4×K×L×(D2-D1) (2) Wherein, V represents the amount of grouting for tunnel lining, K represents the expansion coefficient, K is 1.5-2.0, L represents the ring width formed by the shield segment, D1 represents the outer diameter of the shield segment, and D2 represents the excavation diameter of the shield machine; According to the segment shield position of the shield machine, the shield tail position parameter of each tunnel segment is obtained, and the shield tail position change value obtained after the deformation compensation of the tunnel lining deformation angle is calculated; The grouting position parameters of the next lining grouting are adjusted according to the change value of the shield tail position, and the grouting construction process of the shield machine is optimized according to the adjusted grouting position parameters and the tunnel lining grouting amount.

7. A computer device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that: When the processor executes the computer program, the steps of the intelligent construction control method for a subway shield gas tunnel as described in any one of claims 1 to 5 are implemented.

8. A computer-readable storage medium storing a computer program, characterized in that: When the computer program is executed by the processor, the steps of the intelligent construction control method for a subway shield gas tunnel as claimed in any one of claims 1 to 5 are implemented.