Construction process of 35-meter super-wide road
By dividing the road into multiple sections and using integrated steel reinforcement processing and segmented casting, the problem of insufficient stability of the concrete surface layer in the construction of a 35-meter-wide road was solved, achieving efficient construction quality assurance.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- CHINA RAILWAY 19TH BUREAU GROUP SIXTH ENGINEERING CO LTD
- Filing Date
- 2023-11-01
- Publication Date
- 2026-06-02
Smart Images

Figure CN117248406B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of road construction technology, specifically to a construction process for a 35-meter-wide road. Background Technology
[0002] In the current process of concrete road construction, especially the construction of ultra-wide concrete roads, the pouring work cannot be completed in one go. Therefore, the overall stability of the concrete surface layer cannot be guaranteed due to the influence of the physical properties of concrete. So, it is particularly important to design a construction process for 35-meter ultra-wide roads in order to solve the above problems. Summary of the Invention
[0003] To address the aforementioned problems, this invention presents a construction process for an ultra-wide 35-meter road. By rationally dividing the construction into blocks and constructing them sequentially, the problem of being unable to pour the concrete in one go and being affected by the physical properties of the concrete is solved, thus ensuring the overall stability of the concrete surface layer.
[0004] To solve the above-mentioned technical problems, the present invention provides a construction process for a 35-meter ultra-wide road, characterized by the following steps:
[0005] S1: Construction preparation: Divide the 35-meter-wide road into sections, carry out roadbed construction according to sections, and lay out the roadside stakes and centerline according to the construction design drawings;
[0006] S2: Formwork erection: After the roadbed construction of each section is completed, the formwork is placed, and steel reinforcement is set on the outside of the formwork;
[0007] S3: Binding and placement of concrete reinforcing mesh: The HRB400 grade C12 steel bars are processed using an integrated steel bar processing device. The processed steel bars are bound according to size specifications to form a concrete reinforcing mesh, which is then placed in each panel with the formwork installed.
[0008] S4: Concrete pouring: Concrete is poured into the slab containing the concrete reinforcement mesh using a concrete pouring device;
[0009] S5: Curing: Curing can begin within 12 hours of the completion of the concrete slab construction. Use a plastic film watering method, watering the surface 2-3 times a day and night, keeping it moist for no less than 7 days.
[0010] Further: The template in step S2 is a steel template with a height of 0.3m and a length of 6m. A steel bar support is set every 1m on the outside of the template. Adjacent templates are tightly connected by a flat-head locking method. The template is coated with a release agent before each concrete pour.
[0011] Furthermore: In step S3, the concrete steel mesh is arranged in a double layer, and the double-layer mesh is connected by a stirrup support. The steel bars in the stirrup support are 100cm long and are arranged in a 600*600mm staggered pattern. The horizontal steel bar spacing in each mesh is 60cm and the vertical steel bar spacing is 30cm. The vertical steel bars are placed above the horizontal steel bars. The lap length of the vertical steel bars is 15cm, and single-sided lap welding is used. The lap rate is not greater than 50%.
[0012] Furthermore: After all slabs are poured, joint construction is required in the concrete pouring process described in S4. This joint construction is divided into longitudinal joint construction and transverse joint construction. Due to the segmented construction method, longitudinal construction joints exist between adjacent slabs. During the concrete pouring process, partitions need to be installed at the end of each day or during temporary interruptions of 30-45 minutes. These partitions will create transverse construction joints. For multi-lane roads, transverse construction joints should be avoided on the same cross-section. The longitudinal construction joints are flat joints, with the upper groove cut using a joint cutter. The groove is 0.5cm wide and 3cm deep, and should be filled with sealant. Sealing is performed after curing, using 70# petroleum asphalt to prevent water seepage and the accumulation of hard debris. The transverse construction joints are dummy joints, formed when the concrete strength reaches 8MPa. When cutting joints, generally, when the temperature is 25-30 degrees Celsius, cutting joints should be done 8-10 hours after concrete pouring; when the temperature is 20-25 degrees Celsius, cutting joints should be done 10-20 hours after concrete pouring. In any case, the cutting time should not exceed 24 hours. To reduce early cracking, the "skip-section method" can be used for cutting joints, that is, cut a joint every other slab, and then saw each slab one by one. The width of the transverse construction joint is 0.5cm and the depth is 5cm. The groove is filled with joint filler material. The joint filling is carried out after curing, and the material used is 70# petroleum asphalt.
[0013] Furthermore: the concrete pouring in step S4 specifically includes the following steps:
[0014] A1: Concrete placement: First, C25 concrete is placed using a concrete pumping device, and then 10cm of C40 concrete is placed before the initial setting of 20cm of C25 concrete.
[0015] A2: Concrete Vibration and Leveling: (1) After the 20cm C25 concrete mix is laid out, the first vibration operation is started. An immersion vibrator is used for vibration. When the vibrator is inserted intermittently, the distance moved each time should not exceed 1.5 times the effective radius of the vibrator and should not be greater than 50cm. The vibration time should be 15~30s. The compaction is achieved when the coarse aggregate in the mix stops settling, no more air bubbles appear on the surface, and cement slurry rises. Note that over-vibration should be avoided. The immersion vibrator should move slowly and continuously at a uniform speed; (2) After the first 20cm C25 layer is vibrated, a 10cm C40 mix is laid out; (3) After the second mix is laid out, a vibrating beam is used for leveling;
[0016] A3: Fine-level finish: After the vibratory beam has basically leveled the road surface, the thickness and water-cement ratio of the surface mortar along the longitudinal direction have reached uniformity, but it may not be uniform along the transverse direction. A 3-5m scraper should be used for finishing. After the surface water has evaporated, a finishing machine should be used to finish the surface.
[0017] Furthermore: the integrated rebar processing device in step S4 includes a base plate, a worktable, a turntable, a positioning block, a support column, an extrusion roller, a guide sleeve, and a cutting wheel. The worktable is fixed above the base plate by the column. The support column and the turntable are concentrically arranged and fixedly connected to the worktable. The turntable is embedded in the top of the worktable and can rotate around the support column. The upper end of the worktable is flush with the upper end of the turntable. The positioning block and the extrusion roller are located on one side of the support column. The positioning block is connected to a U-shaped guide frame through a guide block integrated with it. The U-shaped guide frame has threaded through holes. An adjusting bolt is connected to the threaded through hole. The adjusting bolt extends into the U-shaped guide frame along the threaded through hole and is connected to the guide block. One end of the adjusting bolt extending into the U-shaped guide frame is movably connected to the guide block. The extrusion roller is rotatably connected to the mounting frame. The extrusion roller extends out of the mounting frame and contacts the reinforcing bar. The mounting frame is fixed on the turntable and connected to the adjustable lever arm. A transverse through groove is provided on the worktable plate on the right side of the turntable. A baffle is movably connected to the transverse through groove. The baffle is connected to the first lifting electric cylinder, which is connected to the first translation electric cylinder. The baffle can slide along the transverse through groove under the drive of the first translation electric cylinder. The baffle can extend from the transverse through-slot under the action of the first lifting electric cylinder. A length mark is provided on one side of the transverse through-slot. Two guide sleeves are provided on the worktable plate on the left side of the turntable. The two guide sleeves and the transverse through-slot are arranged in a straight line, with a gap between the two guide sleeves. A longitudinal through-slot is formed on the worktable plate between the two guide sleeves. The cutting wheel is movably connected within the longitudinal through-slot. A downward pressing electric cylinder is installed on the top of each guide sleeve. The output shaft end of the downward pressing electric cylinder extends into the guide sleeve and connects to the arc-shaped clamping plate. Two drive rollers are arranged opposite each other on the left end of the worktable plate. Each drive roller is connected to the worktable plate via a roller connecting bracket. It is connected to a roller drive motor mounted on a roller connecting frame; the adjustable lever arm includes a connecting arm, an adjusting arm, a locking pin, and a spring. One end of the connecting arm is fixedly connected to the mounting frame. One end of the adjusting arm has a guide groove that matches the connecting arm. The other end of the connecting arm extends into the guide groove of the adjusting arm. Connecting holes are provided on the front and rear outer walls of the connecting arm end that extends into the guide groove. A locking pin is connected to the connecting hole by a spring. Several locking holes are provided on the upper and lower side walls of the adjusting arm at positions relative to the connecting holes. Several locking holes on the same side are arranged in a straight line. The locking pin extends out of the adjusting arm along the locking hole under the action of the spring. One end of the locking pin extending out of the adjusting arm is spherical.
[0018] Furthermore: the cutting wheel is installed in the fixed frame and connected to the cutting wheel drive motor. The cutting wheel extends out of the worktable along the longitudinal through groove. The fixed frame is fixed on the support plate. The support plate is slidably connected to the guide rail by a slider set at the bottom. The guide rail is fixedly set on the base plate. A second translation electric cylinder is installed on the base plate. The output shaft end of the second translation electric cylinder is connected to the support plate through a connector.
[0019] Furthermore: the concrete discharge device includes a storage box, support columns, a lower support plate, support legs, wheel mounting seats, wheels, and a guide frame assembly. Several support columns are evenly and vertically arranged at the bottom of the storage box. Each support column has a mounting hole at its bottom, and a third lifting cylinder is installed within the mounting hole. The output shaft of the third lifting cylinder extends out of the mounting hole and connects to the support leg. A wheel mounting seat is located on one side of the lower end of each support column, and a wheel is connected to the bottom of the wheel mounting seat. The lower support plate is horizontally fixed between the support columns. The guide frame assembly is installed on the lower support column via an angle adjustment mechanism. On the plate, a guide pipe is provided at the bottom of the storage box and is connected thereto. An annular guide groove is opened at the bottom of the guide pipe. A discharge pipe is connected to the annular guide groove through a second spring. A guide frame is provided at the bottom of the storage box on both the left and right sides of the guide pipe. A sealing discharge plate is slidably connected in the guide frame on both sides. The lower end of the discharge pipe is in contact with the top of the sealing discharge plate through the second spring. A sealing groove and a discharge hole are respectively provided on the left and right sides of the sealing discharge plate. The lower end of the discharge pipe is conical. A discharge switch electric cylinder is installed at the bottom of the storage box and is connected to the sealing discharge plate.
[0020] Furthermore: the material guide frame assembly consists of an inner frame, a middle frame, and an outer frame. The left and right ends of the inner frame are connected to the lower support plate via an angle adjustment mechanism. Each of the left and right ends of the inner frame is connected to a middle frame. A first guide protrusion is provided on the front and rear outer walls of each of the left and right ends of the inner frame. The middle frame is slidably connected to the first guide protrusions on the front and rear outer walls of the inner frame via first limiting guide grooves formed on the front and rear inner walls. A second guide protrusion is provided on each of the front and rear outer walls of the middle frame. The outer frame is slidably connected to the second guide protrusions on the front and rear outer walls of the middle frame via second limiting guide grooves formed on the front and rear inner walls. A first threaded hole is provided on one end of the outer wall of the middle frame, directly opposite the first guide protrusion. The first threaded hole communicates with the first limiting guide groove and is connected to a first tightening bolt. The first tightening bolt passes through the first threaded hole and extends into the first limiting guide groove, contacting the first guide protrusion. A second threaded hole is provided on one end of the outer wall of the outer frame, directly opposite the second guide protrusion. The second threaded hole is connected to the second limiting guide groove and a second tightening bolt is connected inside it. The second tightening bolt passes through the second threaded hole and extends into the second limiting guide groove to contact the second guide protrusion. The angle adjustment mechanism includes a first suspension bracket, a second suspension bracket, a first electric telescopic rod, a second electric telescopic rod, and slide rails set on the top of the front and rear outer walls at both ends of the inner frame. The slide rails are inverted trapezoidal. The first suspension bracket and the second suspension bracket are slidably connected to the slide rails at the top of both ends of the inner frame through sliders set at the bottom. The front and rear ends of the first suspension bracket are each connected to the lower support plate through a first electric telescopic rod. The output shaft end of the first electric telescopic rod is movably connected to the first suspension bracket. The front and rear ends of the second suspension bracket are each connected to the lower support plate through a second electric telescopic rod. The output shaft end of the second electric telescopic rod is movably connected to the second suspension bracket. A side plate is set on the top of the inner frame on both sides of each slide rail. The side plates on both sides are connected to the left and right ends of the slider through a third spring.
[0021] Furthermore: A guide frame is provided at the top of each of the left and right ends of the storage box. A guide seat is slidably connected to the guide frame, with both ends of the guide seat extending out of the guide frame. An installation rod is slidably connected to the guide seat, with both ends of the installation rod extending out of the guide seat. A vibrator is detachably installed at the end of the installation rod extending above the storage box. A third threaded hole is provided at the top of one end of the guide seat, and a third tightening bolt is connected to the third threaded hole. The third tightening bolt passes through the third threaded hole and extends into the guide seat, contacting the installation rod. A screw is vertically installed at the top of the guide seat. A guide groove for the screw to slide back and forth is provided on the guide frame. The upper end of the screw passes through the guide frame along the guide groove. A locking nut is connected to the screw passing through the guide frame, and the locking nut contacts the top of the guide frame.
[0022] By adopting the above structure, this invention solves the problem of being affected by the physical properties of concrete due to the inability to pour in one go by dividing the construction blocks into sequential construction blocks, thus ensuring the overall stability of the concrete surface layer. The integrated steel bar processing device used in this invention can not only bend the steel bars, but also cut them to a precise length, greatly increasing its practicality. Attached Figure Description
[0023] The present invention will now be described in further detail with reference to the accompanying drawings and specific embodiments.
[0024] Figure 1 This is a structural diagram of an integrated steel bar processing device.
[0025] Figure 2 for Figure 1 A magnified view of A in the middle.
[0026] Figure 3 This is a diagram showing the installation structure of the cutting wheel.
[0027] Figure 4 This is a structural diagram of an adjustable lever arm.
[0028] Figure 5 This is a structural diagram of a concrete discharge device.
[0029] Figure 6 This is a partial structural diagram of a concrete discharge device.
[0030] Figure 7 This is a structural diagram of the material guide frame assembly.
[0031] Figure 8 for Figure 7 A magnified view of B in the middle. Detailed Implementation
[0032] This invention provides a construction process for a 35-meter ultra-wide road, comprising the following steps:
[0033] S1: Construction preparation: Divide the 35-meter-wide road into sections, carry out roadbed construction according to sections, and lay out the roadside stakes and centerline according to the construction design drawings;
[0034] S2: Formwork erection: After the roadbed construction of each section is completed, the formwork is placed, and steel reinforcement is set on the outside of the formwork;
[0035] S3: Binding and placement of concrete reinforcing mesh: The HRB400 grade C12 steel bars are processed using an integrated steel bar processing device. The processed steel bars are bound according to size specifications to form a concrete reinforcing mesh, which is then placed in each panel with the formwork installed.
[0036] S4: Concrete pouring: Concrete is poured into the slab containing the concrete reinforcement mesh using a concrete pouring device;
[0037] S5: Curing: Curing can begin within 12 hours of the completion of the concrete slab construction. Use a plastic film watering method, watering the surface 2-3 times a day and night, keeping it moist for no less than 7 days.
[0038] The above-mentioned step S1 divides the roadbed into eight sections from left to right. The first, second, third, sixth, seventh, and eighth sections on both sides are 4.5m long, while the fourth and fifth sections in the middle are 4m long. The roadbed construction by section in step S1 specifically means that the third section is constructed on the first day, the first section on the second day, the second section on the third day, the sixth section on the fourth day, the eighth section on the fifth day, the seventh section on the sixth day, the fifth section on the seventh day, and the fourth section on the eighth day. The fourth and fifth sections are used as the concrete pump station positions. After the third section reaches a certain strength, the concrete pump station is placed on it.
[0039] The template used in step S2 above is a steel template with a height of 0.3m and a length of 6m. A steel bar support is set every 1m on the outside of the template. Adjacent templates are tightly connected by a flat-head locking method. A release agent is applied to the template before each concrete pour.
[0040] The concrete reinforcement mesh in step S3 above is arranged in a double layer. The double-layer mesh is connected by a stirrup support. The length of the steel bars in the stirrup support is 100cm. They are arranged in a 600*600mm quincunx pattern. The spacing between the transverse steel bars in each mesh is 60cm and the spacing between the longitudinal steel bars is 30cm. The longitudinal steel bars are placed above the transverse steel bars. The lap length of the longitudinal steel bars is 15cm. Single-sided lap welding is used, and the lap rate is not greater than 50%.
[0041] After all slabs are poured, joint construction is required in the concrete pouring process described in S4 above. This joint construction includes longitudinal and transverse joint construction. Because the road surface is constructed in sections, longitudinal construction joints exist between adjacent slabs. During the concrete pouring process, partitions need to be installed at the end of each day or during temporary interruptions of 30-45 minutes. These partitions will create transverse construction joints. For multi-lane roads, transverse construction joints should be avoided on the same cross-section. The longitudinal construction joints are flat joints, with the upper groove cut using a joint cutter. The groove is 0.5cm wide and 3cm deep, and should be filled with sealant. Sealing should be done after curing, using 70# petroleum asphalt to prevent water seepage and the accumulation of hard debris. The transverse construction joints are dummy joints. When the concrete strength reaches 8MPa... When cutting joints, generally, when the temperature is 25-30 degrees Celsius, cutting joints should be done 8-10 hours after concrete pouring; when the temperature is 20-25 degrees Celsius, cutting joints should be done 10-20 hours after concrete pouring. In any case, the cutting time should not exceed 24 hours. To reduce early cracking, the "skip-section method" can be used for cutting joints, that is, cut a joint every other slab, and then saw each slab one by one. The width of the transverse construction joint is 0.5cm and the depth is 5cm. The groove is filled with joint filler material. The joint filling is carried out after curing, and the material used is 70# petroleum asphalt.
[0042] The concrete pouring in step S4 above is specifically divided into the following steps:
[0043] A1: Concrete placement: First, C25 concrete is placed using a concrete pumping device, and then 10cm of C40 concrete is placed before the initial setting of 20cm of C25 concrete.
[0044] A2: Concrete Vibration and Leveling: (1) After the 20cm C25 concrete mix is laid out, the first vibration operation is started. An immersion vibrator is used for vibration. When the vibrator is inserted intermittently, the distance moved each time should not exceed 1.5 times the effective radius of the vibrator and should not be greater than 50cm. The vibration time should be 15~30s. The compaction is achieved when the coarse aggregate in the mix stops settling, no more air bubbles appear on the surface, and cement slurry rises. Note that over-vibration should be avoided. The immersion vibrator should move slowly and continuously at a uniform speed; (2) After the first 20cm C25 layer is vibrated, a 10cm C40 mix is laid out; (3) After the second mix is laid out, a vibrating beam is used for leveling;
[0045] A3: Fine-level finish: After the vibratory beam has basically leveled the road surface, the thickness and water-cement ratio of the surface mortar along the longitudinal direction have reached uniformity, but it may not be uniform along the transverse direction. A 3-5m scraper should be used for finishing. After the surface water has evaporated, a finishing machine should be used to finish the surface.
[0046] During the curing period of the concrete slab, a designated person shall supervise the process and prohibit passage. When the concrete reaches 40% strength (approximately 4-7 days), pedestrian access is permitted. Twelve days after pouring, when the concrete strength reaches 70%, small cars and light vehicles are allowed to pass. Normal use is permitted after 28 days of pouring, when the concrete strength reaches 100%. After the curing period, the covering material shall be removed, leaving no trace on the slab surface. Formwork removal should be carried out by a carpenter, taking care not to damage the edges and corners of the concrete, and maintaining the integrity of the formwork as much as possible, especially at the joints, which should be removed by a designated person.
[0047] The integrated steel bar processing device in step S4 above is as follows: Figure 1 , Figure 2 and Figure 4As shown, it specifically includes a base plate, a worktable 1, a turntable 2, a positioning block 3, a support column 4, an extrusion roller 9, a guide sleeve 13, and a cutting wheel 18. The worktable is fixed above the base plate by the column. The support column and the turntable are concentrically arranged. The support column is fixedly connected to the worktable. The turntable is embedded in the top of the worktable and can rotate around the support column. The upper end of the worktable is flush with the upper end of the turntable. The positioning block and the extrusion roller are located on one side of the support column. The positioning block is connected to the U-shaped guide frame 5 by a guide block 6 integrated with it. The U-shaped guide frame has a threaded through hole, and the threaded through hole connects to... An adjusting bolt 7 extends into the U-shaped guide frame along a threaded through hole and connects to the guide block. One end of the adjusting bolt extending into the U-shaped guide frame is movably connected to the guide block. The extrusion roller is rotatably connected to the mounting frame 8. The extrusion roller extends out of the mounting frame and contacts the reinforcing bar. The mounting frame is fixed on the turntable and connected to the adjustable lever arm 10. A transverse through groove is provided on the worktable plate on the right side of the turntable. A baffle 15 is movably connected in the transverse through groove. The baffle is connected to the first lifting electric cylinder, which is connected to the first translation electric cylinder. The baffle can slide along the transverse through groove under the drive of the first translation electric cylinder. The cutting wheel can extend from the transverse through-slot. A length marker 16 is provided on one side of the transverse through-slot. Two guide sleeves 13 are provided on the worktable plate on the left side of the turntable. The two guide sleeves and the transverse through-slot are arranged in a straight line, with a gap between the two guide sleeves. A longitudinal through-slot is formed on the worktable plate between the two guide sleeves. The cutting wheel is movably connected within the longitudinal through-slot. A downward-pressing electric cylinder 14 is installed on the top of each guide sleeve. The output shaft of the downward-pressing electric cylinder extends into the guide sleeve and connects to the arc-shaped clamping plate. Two drive rollers 11 are arranged opposite each other on the left end of the worktable plate. Each drive roller is connected to the worktable plate via a roller connecting bracket 12. The drive rollers are connected to the rollers mounted on the roller... The rollers on the connecting frame are connected to the drive motor; the adjustable lever arm includes a connecting arm 10-1, an adjusting arm 10-2, a locking pin 10-3, and a spring. One end of the connecting arm is fixedly connected to the mounting frame. One end of the adjusting arm has a guide groove that matches the connecting arm. The other end of the connecting arm extends into the guide groove of the adjusting arm. Connecting holes are provided on the front and rear outer walls of the connecting arm end that extends into the guide groove. A locking pin is connected to the connecting hole by a spring. Several locking holes are provided on the upper and lower side walls of the adjusting arm at positions relative to the connecting holes. Several locking holes on the same side are arranged in a straight line. The locking pin extends out of the adjusting arm along the locking hole under the action of the spring. One end of the locking pin extending out of the adjusting arm is spherical.
[0048] When the reinforcing bar needs processing, it is transported to the right by two drive rollers, passing between the support column and the extrusion roller. The drive rollers stop transporting the reinforcing bar, and the adjustable lever arm is moved to bend it. After bending, the baffle is adjusted and extended, and the drive rollers are restarted to continue transporting the reinforcing bar to the right. The reinforcing bar stops under the obstruction of the baffle. At this point, the drive rollers stop transporting the reinforcing bar, and the downward-pressing electric cylinder is activated to clamp the reinforcing bar using an arc-shaped clamping plate. The cutting wheel then cuts the reinforcing bar. After cutting, the baffle retracts back into the transverse slot, and the cut and bent reinforcing bar is removed. This invention, using the above structure, can not only bend reinforcing bars but also perform precise length cutting, greatly increasing its practicality.
[0049] like Figure 3 The cutting wheel shown is installed in the fixed frame 21 and connected to the cutting wheel drive motor 22. The cutting wheel extends out of the worktable along the longitudinal through groove. The fixed frame is fixed on the support plate 19. The support plate is slidably connected to the guide rail 17 by a slider set at the bottom. The guide rail is fixedly set on the base plate. A second translation electric cylinder 20 is installed on the base plate. The output shaft end of the second translation electric cylinder is connected to the support plate through a connector.
[0050] like Figure 5 and Figure 6 The concrete discharge device shown includes a storage box 23, support columns 26, a lower support plate 24, support legs 27, wheel mounting seats 29, wheels 28, and a guide frame assembly 30. Several support columns are evenly and vertically arranged at the bottom of the storage box. Each support column has a mounting hole at its bottom, and a third lifting cylinder is installed within the mounting hole. The output shaft of the third lifting cylinder extends out of the mounting hole and connects to the support leg. A wheel mounting seat is located on one side of the lower end of each support column, and a wheel is connected to the bottom of the wheel mounting seat. The lower support plate is horizontally fixed between the support columns. The guide frame assembly is mounted on the lower support column via an angle adjustment mechanism. On the support plate, a guide pipe 37 is provided at the bottom of the storage box and is connected thereto. An annular guide groove is opened at the bottom of the guide pipe. A discharge pipe is connected to the annular guide groove through a second spring. A guide frame 39 is provided at the bottom of the storage box on both the left and right sides of the guide pipe. A sealing discharge plate 40 is slidably connected in the guide frame on both sides. The lower end of the discharge pipe is in contact with the top of the sealing discharge plate through the second spring. A sealing groove and a discharge hole are respectively provided on the left and right sides of the sealing discharge plate. The lower end of the discharge pipe is conical. A discharge switch electric cylinder 38 is installed at the bottom of the storage box and is connected to the sealing discharge plate.
[0051] This invention controls the movement of the material storage box by cooperating with the third lifting electric cylinder and the traveling wheels, transporting it to the designated template, and then pouring concrete into the designated slab by cooperating with the material guide frame assembly and the angle adjustment mechanism.
[0052] like Figure 7 and Figure 8 The shown guide frame assembly consists of an inner frame 30-1, a middle frame 30-2, and an outer frame 30-3. The left and right ends of the inner frame are connected to the lower support plate via angle adjustment mechanisms. Each of the left and right ends of the inner frame is connected to a middle frame. A first guide ridge is provided on the front and rear outer walls of each of the left and right ends of the inner frame. The middle frame is slidably connected to the first guide ridges on the front and rear outer walls of the inner frame via first limiting guide grooves formed on the front and rear inner walls. A second guide ridge is provided on the front and rear outer walls of the middle frame. The frame body is slidably connected to the second guide protrusions on the front and rear outer walls of the intermediate frame body via second limiting guide grooves formed on the front and rear inner walls. A first threaded hole is formed on one end of the outer wall of the intermediate frame body, directly opposite the first guide protrusion. This first threaded hole communicates with the first limiting guide groove and is connected to a first tightening bolt. The first tightening bolt passes through the first threaded hole, extends into the first limiting guide groove, and contacts the first guide protrusion. A second threaded hole is formed on one end of the outer wall of the outer frame body, directly opposite the second guide protrusion. This second threaded hole communicates with the second limiting guide groove. The guide grooves are interconnected and a second tightening bolt is connected inside them. The second tightening bolt passes through the second threaded hole and extends into the second limiting guide groove to contact the second guide protrusion. The angle adjustment mechanism includes a first suspension bracket 30-5, a second suspension bracket 30-10, a first electric telescopic rod 30-11, a second electric telescopic rod 30-4, and slide rails 30-8 set on the top of the front and rear outer walls at both ends of the inner frame. The slide rails are inverted trapezoidal. The first suspension bracket and the second suspension bracket are slidably connected by a slider 30-6 set at the bottom. On the slide rails at the top of the left and right ends of the inner frame, the front and rear ends of the first suspension bracket are each connected to the lower support plate via a first electric telescopic rod. The output shaft end of the first electric telescopic rod is movably connected to the first suspension bracket. The front and rear ends of the second suspension bracket are each connected to the lower support plate via a second electric telescopic rod. The output shaft end of the second electric telescopic rod is movably connected to the second suspension bracket. A side plate 30-9 is provided on the top of the inner frame on both sides of each slide rail. The side plates on both sides are connected to the left and right ends of the slider via a third spring 30-7.
[0053] like Figure 5The material storage box shown has a guide frame 32 at the top of each of its left and right ends. A guide seat 33 is slidably connected to each guide frame, with both ends of the guide seat extending out of the guide frame. An installation rod 31 is slidably connected to each guide seat, with both ends extending out of the guide seat. A vibrator 36 is detachably installed at the end of the installation rod extending above the material storage box. A third threaded hole is formed at the top of one end of the guide seat, and a third tightening bolt 35 is connected to this third threaded hole. The third tightening bolt passes through the third threaded hole and extends into the guide seat, contacting the installation rod. A screw 34 is vertically mounted on the top of the guide seat. A guide groove for the screw to slide back and forth is formed on the guide frame. The upper end of the screw passes through the guide groove and through the guide frame. A locking nut is connected to the screw passing through the guide frame, and the locking nut contacts the top of the guide frame. This invention, through the vibrator, can vibrate the concrete at any location within the material storage box, thereby removing air bubbles and improving the pouring quality.
[0054] The above are merely preferred embodiments of the present invention. The scope of protection of the present invention is not limited to the above embodiments. All technical solutions falling within the scope of the present invention's concept are within the scope of protection of the present invention. It should be noted that for those skilled in the art, any improvements and modifications made without departing from the principles of the present invention should be considered within the scope of protection of the present invention.
Claims
1. A construction technique for a 35-meter ultra-wide road, characterized by: Includes the following steps: S1: Construction preparation: Divide the 35-meter-wide road into sections, carry out roadbed construction according to sections, and lay out the roadside stakes and centerline according to the construction design drawings; S2: Formwork erection: After the roadbed construction of each section is completed, the formwork is placed, and steel reinforcement is set on the outside of the formwork; S3: Binding and placement of concrete reinforcing mesh: The HRB400 grade C12 steel bars are processed using an integrated steel bar processing device. The processed steel bars are bound according to size specifications to form a concrete reinforcing mesh, which is then placed in each panel with the formwork installed. S4: Concrete pouring: Concrete is poured into the slab containing the concrete reinforcement mesh using a concrete pouring device; S5: Curing: Curing can begin within 12 hours of the completion of the concrete slab construction. Use a plastic film watering curing method, watering the surface 2-3 times a day and night, keeping it moist for no less than 7 days. The concrete discharge device includes a storage box (23), support columns (26), a lower support plate (24), support feet (27), a traveling wheel mounting seat (29), a traveling wheel (28), and a guide frame assembly (30). Several support columns are evenly and vertically arranged at the bottom of the storage box. Each support column has a mounting hole at its bottom, and a third lifting cylinder is installed within the mounting hole. The output shaft of the third lifting cylinder extends out of the mounting hole and connects to the support foot. A traveling wheel mounting seat is provided on one side of the lower end of each support column, and a traveling wheel is connected to the bottom of the mounting seat. The lower support plate is horizontally fixed between the support columns. The guide frame assembly is installed via an angle adjustment mechanism. On the lower support plate, a guide pipe (37) is provided at the bottom of the storage box and is connected to it. An annular guide groove is opened at the bottom of the guide pipe. A discharge pipe is connected to the annular guide groove through a second spring. A guide frame (39) is provided at the bottom of the storage box on both the left and right sides of the guide pipe. A sealing discharge plate (40) is slidably connected in the guide frame on both the left and right sides. The lower end of the discharge pipe is in contact with the top of the sealing discharge plate through the second spring. A sealing groove and a discharge hole are provided on the left and right sides of the sealing discharge plate respectively. The lower end of the discharge pipe is conical. A discharge switch electric cylinder (38) is installed at the bottom of the storage box and is connected to the sealing discharge plate. The material guide frame assembly consists of an inner frame (30-1), a middle frame (30-2), and an outer frame (30-3). The left and right ends of the inner frame are connected to the lower support plate via angle adjustment mechanisms. Each of the left and right ends of the inner frame is connected to a middle frame. A first guide protrusion is provided on the front and rear outer walls of each of the left and right ends of the inner frame. The middle frame is slidably connected to the first guide protrusions on the front and rear outer walls of the inner frame via first limiting guide grooves formed on the front and rear inner walls. A second guide protrusion is provided on the front and rear outer walls of the middle frame. The frame body is slidably connected to the second guide protrusions on the front and rear outer walls of the intermediate frame body via second limiting guide grooves formed on the front and rear inner walls. A first threaded hole is formed on one end of the outer wall of the intermediate frame body, directly opposite the first guide protrusion. This first threaded hole communicates with the first limiting guide groove and contains a first tightening bolt. The first tightening bolt passes through the first threaded hole, extends into the first limiting guide groove, and contacts the first guide protrusion. A second threaded hole is formed on one end of the outer wall of the outer frame body, directly opposite the second guide protrusion. This second threaded hole is connected to the second limiting guide groove. The inner frame is connected to a second tightening bolt, which passes through a second threaded hole and extends into a second limiting guide groove to contact a second guide protrusion. The angle adjustment mechanism includes a first suspension bracket (30-5), a second suspension bracket (30-10), a first electric telescopic rod (30-11), a second electric telescopic rod (30-4), and slide rails (30-8) located on the top of the front and rear outer walls at both ends of the inner frame. The slide rails are in the shape of an inverted trapezoid. The first and second suspension brackets are slidably connected by a slider (30-6) located at the bottom. The first suspension bracket is connected to the slide rails at the top of the left and right ends of the inner frame. The front and rear ends of the first suspension bracket are connected to the lower support plate through a first electric telescopic rod. The output shaft end of the first electric telescopic rod is movably connected to the first suspension bracket. The front and rear ends of the second suspension bracket are connected to the lower support plate through a second electric telescopic rod. The output shaft end of the second electric telescopic rod is movably connected to the second suspension bracket. Each slide rail has a side plate (30-9) at the top of the inner frame on both sides. The side plates on both sides are connected to the left and right ends of the slider through a third spring (30-7).
2. The construction process for a 35-meter ultra-wide road according to claim 1, characterized in that: The template used in step S2 is a steel template with a height of 0.3m and a length of 6m. A steel bar support is set every 1m on the outside of the template. Adjacent templates are tightly connected by a flat-head locking method. A release agent is applied to the template before each concrete pour.
3. The construction process for a 35-meter ultra-wide road according to claim 1, characterized in that: In step S3, the concrete reinforcement mesh is arranged in a double layer. The double-layer mesh is connected by a stirrup support. The length of the steel bars in the stirrup support is 100cm. They are arranged in a 600*600mm staggered pattern. The spacing between the transverse steel bars in each mesh is 60cm and the spacing between the longitudinal steel bars is 30cm. The longitudinal steel bars are placed above the transverse steel bars. The lap length of the longitudinal steel bars is 15cm. Single-sided lap welding is used, and the lap rate is not greater than 50%.
4. The construction process for a 35-meter ultra-wide road according to claim 1, characterized in that: After all slabs are poured, joint construction is required in the S4 section of the concrete pouring process. This joint construction includes longitudinal and transverse joint construction. Because the road surface is constructed in sections, longitudinal construction joints exist between adjacent slabs. During the concrete pouring process, partitions need to be installed at the end of each day or during temporary interruptions of 30-45 minutes. These partitions will create transverse construction joints. For multi-lane roads, transverse construction joints should be avoided on the same cross-section. The longitudinal construction joints are flat joints, with the upper groove cut using a joint cutter. The groove is 0.5cm wide and 3cm deep, and should be filled with sealant. Sealing is done after curing, using 70# petroleum asphalt to prevent water seepage and the accumulation of hard debris. The transverse construction joints are dummy joints, formed when the concrete strength reaches 8MPa. When cutting joints, generally, when the temperature is 25-30 degrees Celsius, cutting joints should be done 8-10 hours after concrete pouring; when the temperature is 20-25 degrees Celsius, cutting joints should be done 10-20 hours after concrete pouring. In any case, the cutting time should not exceed 24 hours. To reduce early cracking, the "skip-section method" can be used for cutting joints, that is, cut a joint every other slab, and then saw each slab one by one. The width of the transverse construction joint is 0.5cm and the depth is 5cm. The groove is filled with joint filler. The joint filling is carried out after curing, and the material used is 70# petroleum asphalt.
5. The construction process for a 35-meter ultra-wide road according to claim 1, characterized in that: The concrete pouring in step S4 is specifically divided into the following steps: A1: Concrete placement: First, C25 concrete is placed using a concrete pumping device, and then 10cm of C40 concrete is placed before the initial setting of 20cm of C25 concrete. A2: Concrete vibration and leveling: (1) After the 20cm C25 concrete mix is laid out, the first vibration operation is started. An immersion vibrator is used for vibration. When the vibrator is inserted intermittently, the distance moved each time should not exceed 1.5 times the effective radius of the vibrator and should not be greater than 50cm. The vibration time should be 15~30s. The compaction is judged by the coarse aggregate in the mix stopping settling, no more air bubbles appearing on the surface, and cement slurry rising. Note that over-vibration should be avoided. The immersion vibrator should move slowly and continuously at a uniform speed. (2) After the first 20cm C25 is vibrated, a 10cm C40 mix is laid out. (3) After the second mix is laid out, a vibrating beam is used for leveling. A3: Fine-level finish: After the vibratory beam has basically leveled the road surface, the thickness and water-cement ratio of the surface mortar along the longitudinal direction have reached uniformity, but it may not be uniform along the transverse direction. A 3-5m scraper should be used for finishing. After the surface water has evaporated, a finishing machine should be used to finish the surface.
6. The construction process for a 35-meter ultra-wide road according to claim 1, characterized in that: The integrated steel bar processing device in step S4 includes a base plate, a worktable (1), a turntable (2), a positioning block (3), a support column (4), an extrusion roller (9), a guide sleeve (13), and a cutting wheel (18). The worktable is fixed above the base plate by a column. The support column and the turntable are concentrically arranged. The support column is fixedly connected to the worktable. The turntable is embedded in the top of the worktable and can rotate around the support column. The upper end of the worktable is flush with the upper end of the turntable. The positioning block and the extrusion roller are arranged on one side of the support column. The positioning block is connected to the U-shaped guide frame (5) by a guide block (6) integrated with it. The U-shaped guide frame has openings. The device has a threaded through hole, and an adjusting bolt (7) is connected inside the threaded through hole. The adjusting bolt extends into the U-shaped guide frame along the threaded through hole and is connected to the guide block. One end of the adjusting bolt extending into the U-shaped guide frame is movably connected to the guide block. The extrusion roller is rotatably connected inside the mounting frame (8). The extrusion roller extends out of the mounting frame and contacts the reinforcing bar. The mounting frame is fixed on the turntable and connected to the adjustable lever arm (10). A transverse through groove is provided on the worktable plate on the right side of the turntable. A baffle (15) is movably connected inside the transverse through groove. The baffle is connected to the first lifting electric cylinder. The first lifting electric cylinder is connected to the first translation electric cylinder. The baffle can slide along the transverse through groove under the drive of the first translation electric cylinder. The baffle can extend from the transverse through groove under the action of the first lifting electric cylinder. A length mark (16) is provided on one side of the transverse through groove. The worktable on the left side of the turntable is provided with two guide sleeves (13). The two guide sleeves and the transverse through groove are arranged in a straight line. There is a gap between the two guide sleeves. A longitudinal through groove is opened on the worktable between the two guide sleeves. The cutting wheel is movably connected in the longitudinal through groove. A pressing electric cylinder (14) is installed on the top of the guide sleeve. The output shaft end of the pressing electric cylinder extends into the guide sleeve and is connected to the arc-shaped clamp. Two drive rollers (11) are arranged opposite each other on the left end of the worktable. Each of the two drive rollers is connected to the worktable through a roller connecting frame (12). The wheel is connected to a roller drive motor mounted on a roller connecting frame; the adjustable lever arm includes a connecting arm (10-1), an adjusting arm (10-2), a locking pin (10-3), and a spring. One end of the connecting arm is fixedly connected to the mounting frame. One end of the adjusting arm has a guide groove that matches the connecting arm. The other end of the connecting arm extends into the guide groove of the adjusting arm. Connecting holes are provided on the front and rear outer walls of the connecting arm end that extends into the guide groove. A locking pin is connected to the connecting hole by a spring. Several locking holes are provided on the upper and lower side walls of the adjusting arm at positions relative to the connecting holes. Several locking holes on the same side are arranged in a straight line. The locking pin extends out of the adjusting arm along the locking hole under the action of the spring. One end of the locking pin extending out of the adjusting arm is spherical.
7. The construction process for a 35-meter ultra-wide road according to claim 6, characterized in that: The cutting wheel is installed in the fixed frame (21) and connected to the cutting wheel drive motor (22). The cutting wheel extends out of the worktable along the longitudinal through groove. The fixed frame is fixed on the support plate (19). The support plate is slidably connected to the guide rail (17) by a slider set at the bottom. The guide rail is fixedly set on the base plate. A second translation electric cylinder (20) is installed on the base plate. The output shaft end of the second translation electric cylinder is connected to the support plate through a connector.
8. The construction process for a 35-meter ultra-wide road according to claim 1, characterized in that: Each of the left and right ends of the storage box is provided with a guide frame (32). A guide seat (33) is slidably connected to the guide frame. Both ends of the guide seat extend out of the guide frame. An installation rod (31) is slidably connected to the guide seat. Both ends of the installation rod extend out of the guide seat. A vibrator (36) is detachably installed at the end of the installation rod that extends to the top of the storage box. A third threaded hole is opened at the top of one end of the guide seat. A third tightening bolt (35) is connected in the third threaded hole. The third tightening bolt passes through the third threaded hole and extends into the guide seat to contact the installation rod. A screw (34) is vertically provided at the top of the guide seat. A guide groove for the screw to slide back and forth is opened on the guide frame. The upper end of the screw passes through the guide frame along the guide groove. A locking nut is connected to the screw that passes through the guide frame. The locking nut contacts the top of the guide frame.