A method for determining the minimum and economical exploration workload
By establishing a full-cost evaluation method for exploration and development, the issue of the rationality of exploration workload and investment in low-exploration blocks or mineral rights registration reduction units was resolved, the minimum and economical exploration workload and investment were determined, and the accuracy of resource value evaluation was improved.
Patent Information
- Application Number
- CN202210674447.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-06-15
- Publication Date
- 2026-11-17
- Estimated Expiration
- 2042-06-15
AI Technical Summary
In low-exploration blocks or mineral rights registration decline units, existing technologies cannot accurately determine the rationality of exploration workload and investment, resulting in inaccurate resource value assessments and an inability to reflect the relationship between exploration workload or investment and expected technically recoverable reserves.
By adopting a combined exploration and development full-cost evaluation method, and through the calculation of expected technically recoverable reserves, exploration workload, investment, and exploration and development full-cost, a relationship model between the expected reserve discovery rate and the exploration and development full-cost is established to determine the minimum and economical exploration workload.
It objectively reflects the impact of exploration investment and exploration technology level, determines the minimum and economical exploration workload and investment, reflects exploration risks, and improves the accuracy of resource value assessment.
Smart Images

Figure CN117273291B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of oilfield exploration, specifically to a method for determining the minimum / economical exploration workload in low-exploration blocks or mineral rights registration reduction units. Background Technology
[0002] In the resource value assessment of low-exploration blocks or mineral rights registration decline units, such as the Tarim Basin, the expected technically recoverable reserves are usually assigned a value based on the subjective probability method, and then the resource value is assessed. This method does not examine the relationship between exploration workload or exploration investment and expected technically recoverable reserves; it does not reflect the minimum exploration workload or minimum exploration investment required for low-exploration blocks and mineral rights registration decline units; it does not reflect the exploration workload or exploration investment required for the expected proven economic and technically recoverable reserves; and it cannot determine the rationality of the estimated recoverable reserves given by the subjective probability method. Summary of the Invention
[0003] To address the shortcomings of existing technologies that rely on subjective judgment and cannot determine the rationality of investment, this invention provides a practical method for determining the minimum / economical exploration workload by combining a full-cost evaluation method for exploration and development, thus providing a basis for the optimal selection of exploration targets.
[0004] The technical solution of the present invention is as follows:
[0005] A method for determining the minimum and economical exploration workload, characterized by the following steps:
[0006] The steps for calculating expected technically recoverable reserves are as follows: Based on the undiscovered resources in low-exploration blocks and mineral rights registration decline units, the expected technically recoverable reserves are calculated according to the expected reserve discovery rate and the recovery rate of different types of reservoir oil reservoirs.
[0007] Steps for calculating exploration workload: Establish a model relating proven technically recoverable reserves to exploration and development workload, and calculate the exploration workload for different expected reserve discovery rates.
[0008] Investment calculation steps: After determining the exploration workload under different expected reserve discovery rates, calculate the exploration and development investment under different expected reserve discovery rates based on the exploration and development investment quota.
[0009] The steps for calculating the total cost of exploration and development are as follows: Based on real-time oil prices, commodity rates, comprehensive taxes, and the total cost evaluation model for exploration and development, calculate the total cost of exploration and development under different expected exploration rates.
[0010] Economic analysis steps: Establish a model relating expected reserve discovery rate to total exploration and development costs; calculate total exploration and development costs under different expected discovery rates; and plot the relationship curve between expected reserve discovery rate and total exploration and development costs.
[0011] Steps for determining minimum and economic provenance: Based on the expected minimum and economic provenance calculation model, calculate the minimum and economic provenance of low-exploration blocks and mineral rights registration decline units;
[0012] The steps for determining the minimum and economical exploration workload for low-exploration blocks and mineral rights registration / regression units are as follows: Based on the determined minimum and economical proven rate, the recovery rate of different types of reservoir oil reservoirs, and the calculated technically recoverable reserves, and then based on the relationship model between proven technically recoverable reserves and exploration investment and exploration technology level, the minimum and economical exploration workload for low-exploration exploration areas or mineral rights registration / regression units is determined.
[0013] Preferably, the step of calculating the expected technically recoverable reserves is as follows: The expected proven technically recoverable reserves are calculated based on the recovery rate and the expected reserve discovery rate for different types of oil reservoirs.
[0014] Q r =N×ρ×E R ,
[0015] Where Qr represents the expected technically recoverable reserves, in units of ×10 4 t; N represents the undiscovered resources in the exploration area, in units of ×10 4 t; ρ represents the expected proven reserves rate, in %; E R This refers to the recovery rate.
[0016] Preferably, using the aforementioned expected technically recoverable reserves calculation step, the expected technically recoverable reserves of oil and gas equivalent in low-exploration-level blocks and mineral rights registration decline units in the Tarim Basin are calculated:
[0017]
[0018] Among them, 1 ton of crude oil = 1255 m 3 Natural gas; Q rog The expected proven technically recoverable oil and gas equivalent is expressed in units of ×10. 4 t; N oil The amount of undiscovered oil resources in the exploration area is expressed in units of 10. 4 t; N gas The amount of natural gas resources yet to be discovered in the exploration area is expressed in units of ×10. 8 m 3 ;ρ oil The expected proven rate of oil resources is expressed in %; ρ gas E represents the expected proven natural gas resource rate, in percentage (%). Roil Oil recovery rate, in %; E Rgas Gas reservoir recovery rate, in percent.
[0019] Preferably, in the step of calculating the expected technically recoverable reserves, the formula for calculating the expected oil and gas equivalent proven rate is as follows:
[0020]
[0021] Where, ρ og The expected proven oil and gas equivalent exploration rate, in %; N oil The amount of undiscovered oil resources in the exploration area is expressed in units of 10. 4 t; N gas The amount of natural gas resources yet to be discovered in the exploration area is expressed in units of ×10. 8 m 3 ;ρ oil The expected proven rate of oil resources is expressed in %; ρ gas The expected natural gas resource exploration rate is expressed in percentages.
[0022] Preferably, using the aforementioned exploration workload calculation steps, the formula for calculating the 3D seismic exploration workload of low-exploration-level blocks and mineral rights registration decline units in the Tarim Basin is as follows:
[0023] S SW =S KQ -S W ,
[0024] Among them, S SW The workload of 3D seismic exploration to determine technically recoverable reserves, per km 2 S KQ The area of the exploration area or mining rights is expressed in km². 2 S W This represents the amount of 3D seismic exploration work already completed, in km². 2 .
[0025] The formula for calculating the total number of wells needed to determine the expected technically recoverable reserves in low-exploration blocks and mineral rights registration decline units in the Tarim Basin is as follows:
[0026]
[0027] Among them, Q rog The expected proven technically recoverable oil and gas equivalent is expressed in units of ×10. 4 t;v p The average oil production rate of the oilfield branch company is expressed as a percentage (E). R The recovery rate is expressed as a percentage; Q0 represents the expected initial production capacity of the development well, expressed as tons per day (t / d), assigned by reservoir engineering experts based on reservoir type; T N For production timeliness, the unit is d.
[0028] The formula for calculating the number of successful exploration wells that have proven expected technically recoverable reserves is as follows:
[0029]
[0030] Among them, H CGT The workload of a successful exploration well to determine technically recoverable reserves is measured in units of H. K The total number of wells for developing expected technically recoverable reserves, per well; The percentage of exploratory wells in the total production wells, expressed in percent.
[0031] The formula for calculating the proportion of exploratory wells in production wells is as follows:
[0032]
[0033] Among them, H LT To represent the number of exploratory wells in production wells within a highly explored exploration area, the unit is wells; H LK This is used as an analogy to the total number of production wells developed in exploration areas with high exploration levels.
[0034] The formula for calculating the production capacity construction scale of expected proven technically recoverable reserves in low-exploration blocks and mineral rights registration decline units in the Tarim Basin is as follows:
[0035]
[0036] Among them, Q CJ The projected capacity expansion scale is expressed in units of 10. 4 t;v p The average oil production rate of the oilfield branch company is expressed as a percentage (E). R Recovery rate, in percentage.
[0037] Preferably, using the aforementioned investment calculation steps, the formula for calculating the proven technically recoverable reserves of expected proven reserves in low-exploration-level blocks and mineral rights registration decline units in the Tarim Basin is as follows:
[0038] I e =I W +I Z +I Y +I G ,
[0039] Among them, I e For technically recoverable reserves discovery and proof, the unit is 10,000 yuan; I W For materialized investment, the unit is 10,000 yuan; I Z Investment in exploratory wells, unit: 10,000 yuan; I Y The research cost is calculated in ten thousand yuan; I G The exploration management fee is in ten thousand yuan.
[0040] The formula for calculating geophysical investment in low-exploration blocks and mineral rights registration reduction units in the Tarim Basin is as follows:
[0041] I W =S SW ×P W ,
[0042] Among them, I W For geophysical and geochemical investment, the unit is 10,000 yuan. In the Tarim Basin, low-exploration-level blocks and mineral rights registration reduction units, two-dimensional seismic exploration is no longer conducted; geophysical and geochemical investment is mainly for three-dimensional seismic exploration. SW This represents the workload of 3D seismic exploration, expressed in units of yuan / km. 2 ;P W This is the investment quota for 3D seismic exploration, in RMB 10,000 / km. 2 .
[0043] The formula for calculating the investment of successful exploration wells in low-exploration blocks and mineral rights registration decline units in the Tarim Basin is as follows:
[0044] I Z =H CGT ×P T ,
[0045] Among them, I Z Investment in exploration wells, unit: 10,000 yuan; H CGT The amount of work required for a successful exploration well to determine technically recoverable reserves is measured per unit well (P). T The unit for investment in exploration wells is 10,000 yuan per well.
[0046] The formula for calculating the comprehensive study cost of low-exploration blocks and mineral rights registration reduction units in the Tarim Basin is as follows:
[0047] I Y =I W ×μ,
[0048] Among them, I Y The research cost is calculated in ten thousand yuan; I W The figure represents material investment, in ten thousand yuan; μ represents the statistical ratio of comprehensive research expenses to 3D seismic investment, in percentage.
[0049] The formula for calculating exploration management fees for low-exploration-level blocks and mineral rights registration reduction units in the Tarim Basin is as follows:
[0050] I G =(I W +I Z +I Y )×15%,
[0051] Among them, I G For exploration management expenses, the unit is 10,000 yuan; I W For materialized investment, the unit is 10,000 yuan; I Z Investment in exploratory wells, unit: 10,000 yuan; I Y The total research cost is expressed in ten thousand yuan.
[0052] The formula for calculating the apparent development investment for low-exploration blocks and mineral rights registration reduction units in the Tarim Basin is as follows:
[0053] I d =I K +I C ,
[0054] Among them, I d For development investment, the unit is 10,000 yuan; I K Investment in development well drilling projects is expressed in ten thousand yuan. C Investment in capacity building is measured in ten thousand yuan.
[0055] The formula for calculating the investment in development well drilling is as follows:
[0056] I K =(H K -H CGT )×P K ,
[0057] Among them, I K Investment in development well drilling projects, unit: 10,000 yuan; H K The total number of wells used to develop the expected technically recoverable reserves, expressed as a unit of wells; H CGT The number of successful exploration wells used to determine technically recoverable reserves, expressed as a unit of wells; P K Investment quota for development wells, unit: 10,000 yuan / well.
[0058] The formula for calculating investment in capacity building is:
[0059] I C =100×Q CJ ×P CJ ,
[0060] Among them, I C Investment in capacity construction is expressed in ten thousand yuan; Q CJ The unit is 10,000 yuan, depending on the scale of capacity construction; P CJ Investment in the construction of one million tons of production capacity for the oilfield branch, in RMB 100 million per million tons.
[0061] The formula for calculating operating costs and expenses is as follows:
[0062]
[0063] Among them, I o For business purposes, the unit is 10,000 yuan; H K The total number of wells for the expected proven technically recoverable reserves, expressed in wells; Q0 represents the initial production capacity of the expected development wells, expressed in tons per day (t / d), assigned by reservoir engineering experts based on reservoir type; T N For production timeliness, the unit is days (d); CO To reflect operating costs, the unit is yuan / t, based on the average operating cost of the oilfield branch.
[0064] The formula for calculating disposal costs is:
[0065] I r =(I K +I C )×5%,
[0066] Among them, I r For disposal costs, the unit is 10,000 yuan; I K The unit for the drilling investment of development wells is 10,000 yuan; I C Investment in capacity building is measured in ten thousand yuan.
[0067] Preferably, using the aforementioned exploration and development full-cost calculation steps, the expected proven technically recoverable reserves Q in low-exploration-level blocks and mineral rights registration decline units in the Tarim Basin are... r The formula for calculating the total cost of exploration and development is:
[0068]
[0069] Where P represents the unit exploration and development cost, in yuan / ton; I e The cost of exploration is expressed in ten thousand yuan; I d For development investment, the unit is 10,000 yuan; I o The unit is 10,000 yuan, representing the cumulative operating cost during the simulated development process; I r For disposal costs, the unit is 10,000 yuan; Q r The unit is the technically recoverable reserves yet to be explored, multiplied by 10. 4 t; α is the commodity rate of oil and gas production, i.e., the ratio of sales volume to output volume, in %; β is the comprehensive tax rate levied on the sale of products, including value-added tax, resource tax, urban maintenance and construction tax, education surcharge, and special petroleum revenue, in %.
[0070] Preferably, in the economic analysis step, a relationship model is established between the expected reserve discovery rate and the total cost of exploration and development:
[0071]
[0072] Where P represents the unit exploration and development cost, in yuan / ton; ρ og N represents the expected proven oil and gas equivalent reserves, expressed as a percentage (%). og The amount of undiscovered oil and gas in the exploration area is expressed as oil and gas equivalent, in units of ×10. 4 t;I′ e The exploration cost is expressed in ten thousand yuan under different expected reserve exploration rates. d The estimated development investment is shown under different expected reserve proven rates, in ten thousand yuan.o Operating costs under different expected reserve proven rates, in ten thousand yuan; I′ r The abandonment fee is calculated under different expected reserve proven rates, in ten thousand yuan; α is the commodity rate of oil and gas production, i.e., the ratio of sales volume to production volume, in %; β is the comprehensive tax rate of value-added tax, resource tax, urban maintenance and construction tax, education surcharge and special petroleum revenue paid on the sale of products, in %.
[0073] Preferably, in the step of determining the minimum and economical rate of proven reserves, the expected technically recoverable reserves and total exploration and development costs under different expected rates of proven reserves are calculated, the minimum expected reserve rate of proven reserves is calculated, and the economical expected reserve rate of proven reserves is determined. The calculation conditions are as follows:
[0074] when At its minimum, the expected proven oil and gas equivalent reserves have a minimum value ρ. ogmin ;
[0075] When P equals the current oil price, there is an expected economic oil and gas equivalent proven rate ρ. ogjj .
[0076] Where P represents the unit exploration and development cost, in yuan / ton; ρ og ρ represents the expected proven oil and gas equivalent reserves, expressed as a percentage (%). ogmin ρ represents the expected proven oil and gas equivalent reserves, expressed as a percentage (%). ogjj The expected proven oil and gas equivalent reserves are expressed in units of %.
[0077] Preferably, utilizing the step of determining the minimum and economical exploration workload for low-exploration-level blocks and mineral rights registration reduction units, the formula for calculating the minimum / economical three-dimensional exploration workload for low-exploration-level blocks and mineral rights registration reduction units in the Tarim Basin is as follows:
[0078]
[0079]
[0080] Among them, S SWmin The minimum 3D exploration workload for low-exploration blocks or mineral rights registration decline units in the Tarim Basin, in km². 2 S SWjj The economical 3D exploration workload for low-exploration blocks or mineral rights registration reduction units in the Tarim Basin, in km². 2 N og For low-exploration-level blocks or mineral rights registration reduction units in the Tarim Basin, the unproven oil and gas equivalent is expressed in units of ×10. 4 t; ρ ogminThe minimum proven yield of expected oil and gas equivalent, in %; ρ ogjj Ω represents the expected economic proven rate of oil and gas equivalent, in percentage; θ represents the trap discovery rate, assigned by seismic interpretation experts according to reservoir and trap type, in percentage; c The expected resource abundance of the 3D seismic coverage area is expressed in ×103 4 t / km 2 S W Three-dimensional seismic exploration work has been carried out in low-exploration blocks or mining rights registration reduction units in the Tarim Basin.
[0081] The formula for calculating the minimum / economical well deployment workload in low-exploration blocks and mineral rights registration decline units in the Tarim Basin is as follows:
[0082]
[0083]
[0084] Among them, H Tmin The minimum number of exploration wells deployed for low-exploration blocks or mineral rights registration decline units in the Tarim Basin, in units of wells; H Tjj The workload for deploying exploration wells in low-exploration blocks or mineral rights registration reduction units in the Tarim Basin is expressed in units of wells (N). og For low-exploration-level blocks or mineral rights registration reduction units in the Tarim Basin, the unproven oil and gas equivalent is expressed in units of ×10. 4 t; ρ ogmin The minimum proven yield of expected oil and gas equivalent, in %; ρ ogjj γ represents the expected economic proven rate of oil and gas equivalent, in %; γ represents the well success rate, in %; N t For well exploration results, unit × 10 4 t proven reserves / port; H T The amount of exploration work already carried out in low-exploration blocks or mining rights registration reduction units in the Tarim Basin.
[0085] The formula for calculating exploration results is as follows:
[0086]
[0087] Among them, I LT To compare the proven geological reserves of highly explored areas, the unit is ×10. 4 t; I LT The number of successful exploration wells, per well, is used to compare the proven geological reserves in highly explored areas.
[0088] The formula for calculating the minimum / economical exploration investment in low-exploration blocks or mineral rights registration reduction units in the Tarim Basin is as follows:
[0089] I emin =(S SWmin ×P W ×(1+μ)+H Tmin ×P T )×(1+15%),
[0090] I ejj =(S SWjj ×P W ×(1+μ)+H Tjj ×P T )×(1+15%),
[0091] Among them, I emin Minimum exploration investment, unit: 10,000 yuan; I ejj Investment in economic exploration, unit: 10,000 yuan; S SWmin The minimum amount of work required for 3D exploration, measured in km. 2 S SWjj The economical 3D exploration workload, in km. 2 H Tmin The minimum amount of work required for deploying exploratory wells, measured in wells; H Tjj The workload for deploying exploration wells for economical purposes is expressed in wells (P). W This is the investment quota for 3D seismic exploration, in RMB 10,000 / km. 2 ;P T The unit is the investment quota for exploration wells, in RMB 10,000 per well; μ is the statistical ratio of comprehensive research costs to 3D seismic investment, in %.
[0092] Beneficial technical effects of the present invention:
[0093] This invention is based on the relationship between expected proven recoverable resources and exploration investment and exploration technology level. Under the scenario of a fixed amount of three-dimensional exploration work, it calculates and establishes a relationship model between the discovery rate of different expected resources and exploration work, exploration investment, and unit exploration and development total cost.
[0094] By applying the technical solution of this invention, a relationship model between expected technically recoverable reserves and exploration workload is established to calculate the expected technically recoverable reserves and the total cost of exploration and development under different expected reserve discovery rates. Based on the relationship model between expected reserve discovery rate and total exploration and development cost, the minimum / economic expected reserve discovery rate is determined, thereby determining the minimum / economic exploration workload (3D seismic exploration workload and well deployment workload) for low-exploration-level blocks or mineral rights registration decline units in the Tarim Basin. This determines the minimum / economic exploration investment for low-exploration-level blocks or mineral rights registration decline units. In this way, the impact of exploration investment and exploration technology level on expected proven technically recoverable reserves is considered in resource value evaluation, while also reflecting the exploration investment risk of low-exploration-level blocks or mineral rights registration decline units, objectively reflecting the investment value and risk of low-exploration-level blocks or mineral rights registration decline units.
[0095] 1. A model was established to show the relationship between the expected technically recoverable reserves proven rate and the total cost of exploration and development;
[0096] 2. A model was established to show the relationship between expected technically recoverable reserves and exploration workload;
[0097] 3. Based on the full cost model of exploration and development, the relationship between the expected technically recoverable reserves discovery rate and the full cost of exploration and development was clarified. The full cost of exploration and development under the condition of minimum expected technically recoverable reserves discovery and the expected economic technically recoverable reserves discovery rate under the current oil price condition were determined. In addition, the minimum exploration workload and economical exploration workload were determined, highlighting the relationship between exploration and development workload, exploration technology level and expected technically recoverable reserves. Attached Figure Description
[0098] Figure 1 This is a flowchart of an embodiment of the present invention.
[0099] Figure 2 This is a model relating the proven reserve rate to the total cost of exploration and development. Detailed Implementation
[0100] To better understand the present invention, the invention will be further explained below with reference to the accompanying drawings and specific embodiments.
[0101] Example
[0102] This embodiment is applied to the Tarim Basin. Based on exploration and development indicators and full-cost evaluation parameters for exploration and development, and under the condition of expected resource exploration rate, the full-cost calculation of exploration and development is the basis for determining the minimum / economic exploration workload.
[0103] Based on the steps of calculating expected technically recoverable reserves, exploration workload, investment, and total exploration and development costs, the basic data required for calculating the minimum / economic exploration workload in low-exploration blocks or mineral rights registration reduction units in the Tarim Basin includes four categories: basic data on oil and gas resources in the exploration area, exploration indicators, development indicators, and economic parameters.
[0104] The required basic data on oil and gas resources in the exploration area are as follows:
[0105] 1) Surface environment of the exploration area or mining rights unit, including mountains, Gobi Desert, and desert;
[0106] 2) Area of the exploration area or mining right unit, in km² 2 ;
[0107] 3) Oil and gas resources contained in the formation, per unit of oil × 10 4 t, natural gas × 10 8 m 3 ;
[0108] 4) Resource abundance, unit ×10 4 t oil and gas equivalent / km 2 ;
[0109] 5) Reservoir type of the strata: clastic rocks, carbonate rocks;
[0110] 6) Trap types: structural traps, lithological traps, stratigraphic traps, and composite traps;
[0111] 7) Reservoir properties, porosity, permeability;
[0112] 8) Reservoir depth.
[0113] The composition of the exploration work already undertaken in the exploration area or mining right unit is as follows:
[0114] 1) Area of 3D seismic exploration invested, unit: km² 2 ;
[0115] 2) Input of exploration well work, per unit.
[0116] The required exploration parameters are as follows:
[0117] 1) Trap detection rate for different trap types, in %;
[0118] 2) Well success rate, in %;
[0119] 3) Well exploration results, proven geological resources per 10,000 tons / well;
[0120] 4) Area controlled by exploration wells, in km² 2 / mouth.
[0121] The required development metrics are as follows:
[0122] 1) Average oil production rate of the oilfield branch company, in %;
[0123] 2) Recovery rate (%) of different types of reservoirs:
[0124] ■ Recovery rate of medium- and low-permeability fault blocks and lithologic reservoirs;
[0125] ■ Recovery rate of medium- and high-permeability fault blocks and lithologic reservoirs;
[0126] ■ Recovery rate of medium-to-high permeability integrated debris reservoirs;
[0127] ■ Recovery rate of carbonate reservoirs;
[0128] Recovery rate of clastic gas reservoirs;
[0129] ■ Recovery rate of carbonate gas reservoirs.
[0130] 3) Development well productivity (t / d) of different types of reservoirs:
[0131] ■Production capacity of development wells in medium- and low-permeability fault blocks and lithological reservoirs;
[0132] ■Production capacity of development wells in medium-to-high permeability fault blocks and lithological reservoirs;
[0133] ■Production capacity of development wells in medium-to-high permeability integrated debris reservoirs;
[0134] ■Production capacity of carbonate reservoir development wells;
[0135] ■Production capacity of gas reservoir development wells.
[0136] 4) Production timeliness (d / n):
[0137] ■Production efficiency of reservoir development wells;
[0138] ■Production efficiency of development wells in clastic gas reservoirs;
[0139] ■ Production efficiency of carbonate gas reservoirs.
[0140] The required economic parameters are as follows:
[0141] 1) Exploration investment quota:
[0142] ■ Quotas for 3D seismic data acquisition and processing under different surface environments, unit: 10,000 yuan / km 2 ;
[0143] ■ The ratio of total research costs to 3D seismic data acquisition costs, in units of f;
[0144] ■ Investment quotas for exploration wells at different depths, unit: RMB 10,000 per well;
[0145] ■ Investment quotas for gas reservoir exploration wells at different depths, in RMB 10,000 per well.
[0146] 2) Development investment quota:
[0147] • Investment quotas for oil reservoir development wells at different depths, in RMB 10,000 per well;
[0148] ■ Investment quotas for gas reservoir development wells at different depths, in RMB 10,000 per well;
[0149] ■ Investment in the construction of a million-ton production capacity under different surface environments, in RMB 100 million per million tons;
[0150] ■ Investment in building a billion cubic meters of production capacity under different surface environments, in RMB 100 million / billion cubic meters.
[0151] 3) Operating costs:
[0152] ■ Oilfield production and operation costs, unit: yuan / ton;
[0153] ■ Gas field production cost, unit: yuan / thousand cubic meters.
[0154] 4) Oil weather prices and commodity rates:
[0155] ■Prices for different qualities, in yuan / ton, or US dollars / barrel;
[0156] Natural gas price, unit: yuan / cubic meter;
[0157] ■Petroleum commodity rate, in %;
[0158] • Natural gas commodity rate, in %.
[0159] 5) Comprehensive tax revenue, unit: %
[0160] 6) Disposal cost, in %
[0161] Specific;
[0162] 1. The calculation steps for expected technically recoverable reserves: For low-exploration blocks or mineral rights registration decline units in the Tarim Basin, the minimum / economic exploration workload calculation must be based on the expected proven technically recoverable resources. The relationship between the expected proven technically recoverable resources and the expected resource proof rate is as follows:
[0163] Q r =N×ρ×E R ,
[0164] Among them, Q r The expected technically recoverable resources are expressed in ×102 4 t; N represents the undiscovered resources in the exploration area, in units of ×10 4 t; ρ represents the expected resource exploration rate, in %; ER This refers to the recovery rate.
[0165] Based on the abundant oil and natural gas resources in the Tarim Basin exploration area, the relationship between the expected proven technically recoverable oil and gas equivalent and the expected proven rate of oil resources and natural gas resources is as follows:
[0166]
[0167] Among them, 1 ton of crude oil = 1255 m 3 Natural gas; Q rog The expected proven technically recoverable oil and gas equivalent is expressed in units of ×10. 4 t; N oil The amount of undiscovered oil resources in the exploration area is expressed in units of 10. 4 t; N gas The amount of natural gas resources yet to be discovered in the exploration area is expressed in units of ×10. 8 m 3 ;ρ oil The expected proven rate of oil resources is expressed in %; ρ gas E represents the expected proven natural gas resource rate, in percentage (%). Roil Oil recovery rate, in %; E Rgas Gas reservoir recovery rate, in percent.
[0168] 2. Steps for calculating exploration workload: The workload required for the exploration and development of technically recoverable resources expected to be discovered in low-exploration blocks or mineral rights registration decline units in the Tarim Basin consists of the following:
[0169] 1) The exploration workload for the expected technically recoverable resources:
[0170] ■Workload for 3D seismic exploration;
[0171] ■ Workload for well deployment;
[0172] 2) The workload for developing the expected technically recoverable resources:
[0173] ■Workload for development well deployment;
[0174] ■ Workload for capacity building.
[0175] The 3D seismic exploration workload for the expected proven technically recoverable resources in low-exploration blocks or mineral rights registration decline units in the Tarim Basin is:
[0176] S SW =S KQ -S W ,
[0177] Among them, S SW The workload of 3D seismic exploration to determine technically recoverable resources, per km2 S KQ The area of the exploration area or mining rights is expressed in km². 2 S W This represents the amount of 3D seismic exploration work already completed, in km². 2 .
[0178] The workload for successfully deploying exploration wells to assess the expected technically recoverable resources in low-exploration blocks or mineral rights-registered decline units in the Tarim Basin is as follows:
[0179]
[0180] Among them, H CGT The amount of work required for a successful exploration well to determine technically recoverable resources is measured per unit well (H). K The total number of wells for developing the expected technically recoverable resources, expressed per well; The percentage of exploratory wells in the total production wells, expressed in percent.
[0181] The formula for calculating the proportion of exploratory wells in production wells is as follows:
[0182]
[0183] Among them, H LT To represent the number of exploratory wells in production wells within a highly explored exploration area, the unit is wells; H LK The total number of production wells in a high-exploration-level exploration area is represented by the number of wells.
[0184] The formula for calculating the total number of wells needed to develop technically recoverable resources is as follows:
[0185]
[0186] Among them, Q rog The expected proven technically recoverable oil and gas equivalent is expressed in units of ×10. 4 t;v p The average oil production rate of the oilfield branch company is expressed as a percentage (E). R The recovery rate is expressed as a percentage; Q0 represents the expected initial production capacity of the development well, expressed as tons per day (t / d), assigned by reservoir engineering experts based on reservoir type; T N For production timeliness, the unit is d.
[0187] The workload for deploying development wells to assess the expected technically recoverable resources in low-exploration blocks or mineral rights registration decline units in the Tarim Basin is as follows:
[0188]
[0189] Among them, H KC The workload for deploying development wells to develop the expected technically recoverable resources, per unit of wells; HK The total number of wells for developing the expected technically recoverable resources, expressed per well; The percentage of exploratory wells in the total production wells, expressed in percent.
[0190] The workload for capacity construction to develop technically recoverable resources is calculated based on the expected capacity scale, using the following formula:
[0191]
[0192] Among them, Q CJ The projected capacity expansion scale is expressed in units of 10. 4 t;v p The average oil production rate of the oilfield branch company is expressed as a percentage (E). R Recovery rate, in percentage.
[0193] 3. Investment calculation steps: The investment composition for exploration and development in low-exploration-level blocks or mineral rights registration reduction units in the Tarim Basin is as follows:
[0194] 1) Proofing costs of expected technically recoverable resources:
[0195] ■ Investment in 3D seismic exploration;
[0196] ■ Investment in exploration well deployment;
[0197] ■Comprehensive research expenses;
[0198] ■ Exploration management costs.
[0199] 2) Expected development costs for technically recoverable resources:
[0200] ■ Investment in development well deployment;
[0201] ■ Investment in capacity building.
[0202] 3) Operating costs
[0203] 4) Disposal costs
[0204] The formula for calculating the proven technically recoverable resources of low-exploration blocks or mineral rights registration decline units in the Tarim Basin is as follows:
[0205] I e =I W +I Z +I Y +I G ,
[0206] Among them, I e The cost of proving the expected technically recoverable resources, in ten thousand yuan; I W Investment in 3D seismic exploration, unit: 10,000 yuan; IZ Investment in exploratory wells, unit: 10,000 yuan; I Y The research cost is calculated in ten thousand yuan; I G The exploration management fee is in ten thousand yuan.
[0207] The formula for calculating geophysical investment in low-exploration blocks or mineral rights registration reduction units in the Tarim Basin is as follows:
[0208] I W =S SW ×P W ,
[0209] Among them, I W Investment in 3D seismic exploration is expressed in ten thousand yuan. In the Tarim Basin, 2D seismic exploration is no longer conducted in low-exploration-level blocks and mineral rights registration reduction units; therefore, geophysical and geochemical exploration investment is primarily for 3D seismic exploration. SW This represents the workload of 3D seismic exploration, expressed in units of yuan / km. 2 ;P W This is the investment quota for 3D seismic exploration, in RMB 10,000 / km. 2 .
[0210] The formula for calculating the investment of successful exploration wells in low-exploration blocks or mineral rights registration decline units in the Tarim Basin is as follows:
[0211] I Z =H CGT ×P T ,
[0212] Among them, I Z Investment in exploration wells, unit: 10,000 yuan; H CGT The amount of work required for a successful exploration well to determine technically recoverable resources is measured per unit well (P). T The unit for investment in exploration wells is 10,000 yuan per well.
[0213] The comprehensive research cost for low-exploration-level blocks and mineral rights registration reduction units in the Tarim Basin is calculated based on the proportion of 3D seismic exploration in these blocks and units.
[0214] I Y =I W ×μ,
[0215] Among them, I Y The research cost is calculated in ten thousand yuan; I W 1. Investment in 3D seismic exploration, in ten thousand yuan; μ is the statistical ratio of comprehensive research expenses to 3D seismic investment, in %.
[0216] The statistical calculation formula for the proportion of 3D seismic exploration in low-exploration blocks or mineral rights registration decline units in the Tarim Basin is as follows:
[0217]
[0218] Where μ represents the statistical ratio of comprehensive research costs to 3D seismic investment, in %; I LY To compare the comprehensive research costs of exploration areas with high exploration levels, the unit is 10,000 yuan; I LW The unit is 10,000 yuan, representing the investment in 3D seismic exploration in areas with high exploration levels.
[0219] Exploration management fees are calculated according to the relevant standards for economic evaluation of exploration and development projects, using the following formula:
[0220] I G =(I W +I Z +I Y )×i g ,
[0221] Among them, I G For exploration management expenses, the unit is 10,000 yuan; I W Investment in 3D seismic exploration, unit: 10,000 yuan; I Z Investment in exploratory wells, unit: 10,000 yuan; I Y The total research cost is expressed in ten thousand yuan. g The percentage for calculating exploration management fees, expressed as a percentage.
[0222] The formula for calculating the expected technically recoverable resources in low-exploration blocks or mineral rights registration decline units in the Tarim Basin, based on development costs, is as follows:
[0223] I d =I K +I C ,
[0224] Among them, I d For development investment, the unit is 10,000 yuan; I K The unit for the drilling investment of development wells is 10,000 yuan; I C Investment in capacity building is measured in ten thousand yuan.
[0225] The formula for calculating the investment in deploying development wells is as follows:
[0226] I K =(H K -H CGT )×P K ,
[0227] Among them, I K Investment in development well drilling projects, unit: 10,000 yuan; H K The total number of wells used to exploit technically recoverable resources, expressed per well; H CGT The number of successful exploration wells used to determine technically recoverable resources, expressed as a unit (P). KInvestment quota for development wells, unit: 10,000 yuan / well.
[0228] The formula for calculating investment in capacity building is:
[0229] I C =100×Q CJ ×P CJ ,
[0230] Among them, I C Investment in capacity construction is expressed in ten thousand yuan; Q CJ To determine the scale of capacity construction, the unit is multiplied by 10. 4 t; P CJ Investment in the construction of one million tons of production capacity for the oilfield branch, in RMB 100 million per million tons.
[0231] The operating cost for developing the expected technically recoverable resources in low-exploration blocks or mineral rights registration decline units in the Tarim Basin is calculated using the following formula:
[0232]
[0233] Among them, I o For business purposes, the unit is 10,000 yuan; Q rog The expected proven technically recoverable oil and gas equivalent is expressed in units of ×10. 4 t;C O To determine the unit operating cost, the unit is assigned as yuan / t based on the average unit operating cost of the oilfield branch.
[0234] Specifically, the abandonment cost for the expected proven technically recoverable resources in low-exploration blocks or mineral rights registration reduction units in the Tarim Basin is calculated using the following formula:
[0235] I r =(I K +I C )×τ,
[0236] Among them, I r For disposal costs, the unit is 10,000 yuan; I K Investment in development well drilling projects is expressed in ten thousand yuan. C The unit is RMB 10,000 for capacity construction investment, and τ is the percentage of abandonment costs accrued.
[0237] 4. Steps for calculating the full cost of exploration and development: The formula for calculating the full cost of exploration and development in low-exploration blocks or mineral rights registration decline units in the Tarim Basin is as follows:
[0238]
[0239] Where P represents the unit exploration and development cost, in yuan / ton; I e Investment in exploration is expressed in ten thousand yuan; I dFor development investment, the unit is 10,000 yuan; I o The unit is 10,000 yuan, representing the cumulative operating cost during the simulated development process; I r For disposal costs, the unit is 10,000 yuan; Q r The amount of technically recoverable resources to be explored, in units of 10. 4 t; α is the commodity rate of oil and gas production, i.e., the ratio of sales volume to output volume, in %; β is the comprehensive tax rate levied on the sale of products, including value-added tax, resource tax, urban maintenance and construction tax, education surcharge, and special petroleum revenue, in %.
[0240] 5. Economic analysis steps: The formula for calculating the total cost of exploration and development under different expected resource proven rates is as follows:
[0241]
[0242] Where P represents the unit exploration and development cost, in yuan / ton; ρ og N represents the expected proven oil and gas equivalent reserves, expressed as a percentage (%). og The amount of undiscovered oil and gas in the exploration area is expressed as oil and gas equivalent, in units of ×10. 4 t;I′ e The exploration investment is expressed in ten thousand yuan under different expected resource exploration rates. d The apparent development investment is given under different expected resource exploration rates, in ten thousand yuan; I′ o Operating costs under different expected resource proven rates, in ten thousand yuan; I′ r The abandonment fee is calculated under different expected resource exploration rates, in ten thousand yuan; α is the commodity rate of oil and gas production, i.e., the ratio of sales volume to production volume, in %; β is the comprehensive tax rate of value-added tax, resource tax, urban maintenance and construction tax, education surcharge and special petroleum revenue paid on the sale of products, in %.
[0243] As shown in Table 1, in this embodiment, by calculating the expected technically recoverable reserves and the total cost of exploration and development under different expected reserve exploration conditions, the minimum / economic expected reserve exploration rate is analyzed and determined, thereby determining the minimum / economic exploration workload for low-exploration blocks or mineral rights registration decline units in the Tarim Basin.
[0244] Table 1. Forecast results of expected technically recoverable reserves and total exploration and development costs under different expected reserve verification conditions.
[0245]
[0246]
[0247]
[0248] like Figure 2 As shown in the figure, the expected reserve discovery rate and the total cost of exploration and development are related by the expected technically recoverable reserves and the prediction results of the total cost of exploration and development under different expected reserve discovery conditions.
[0249] 6. Steps for determining minimum and economic proven rates: The method for determining the minimum / economic resource proven rate in low-exploration blocks or mineral rights registration decline units in the Tarim Basin is as follows:
[0250] when At its minimum, the expected proven oil and gas equivalent reserves have a minimum value ρ. ogmin ;
[0251] When P equals the current oil price, there is an expected economic oil and gas equivalent proven rate ρ. ogjj .
[0252] Where P represents the unit exploration and development cost, in yuan / ton; ρ og ρ represents the expected proven oil and gas equivalent reserves, expressed as a percentage (%). ogmin ρ represents the expected proven oil and gas equivalent reserves, expressed as a percentage (%). ogjj The expected proven oil and gas equivalent reserves are expressed in units of %.
[0253] 7. Steps for determining the minimum and economical exploration workload for low-exploration-level blocks and mineral rights registration reduction units: The formula for calculating the minimum / economical 3D exploration workload for low-exploration-level blocks or mineral rights registration reduction units in the Tarim Basin is as follows:
[0254]
[0255]
[0256] Among them, S SWmin The minimum 3D exploration workload for low-exploration blocks or mineral rights registration decline units in the Tarim Basin, in km². 2 S SWjj The economical 3D exploration workload for low-exploration blocks or mineral rights registration reduction units in the Tarim Basin, in km². 2 N og For low-exploration-level blocks or mineral rights registration reduction units in the Tarim Basin, the unproven oil and gas equivalent is expressed in units of ×10. 4 t; ρ ogmin The minimum proven yield of expected oil and gas equivalent, in %; ρ ogjj Ω represents the expected economic proven rate of oil and gas equivalent, in percentage; θ represents the trap discovery rate, assigned by seismic interpretation experts according to reservoir and trap type, in percentage; c The expected resource abundance of the 3D seismic coverage area is expressed in ×103 4t / km 2 S W Three-dimensional seismic exploration work has been carried out in low-exploration blocks or mining rights registration reduction units in the Tarim Basin.
[0257] The formula for calculating the minimum / economical well deployment workload in low-exploration blocks or mineral rights registration decline units in the Tarim Basin is as follows:
[0258]
[0259]
[0260] Among them, H Tmin The minimum number of exploration wells deployed for low-exploration blocks or mineral rights registration decline units in the Tarim Basin, in units of wells; H Tjj The workload for deploying exploration wells in low-exploration blocks or mineral rights registration reduction units in the Tarim Basin is expressed in units of wells (N). og For low-exploration-level blocks or mineral rights registration reduction units in the Tarim Basin, the unproven oil and gas equivalent is expressed in units of ×10. 4 t; ρ ogmin The minimum proven yield of expected oil and gas equivalent, in %; ρ ogjj γ represents the expected economic proven rate of oil and gas equivalent, in %; γ represents the well success rate, in %; N t For well exploration results, unit × 10 4 t Proven resource quantity / port; H T The amount of exploration work already carried out in low-exploration blocks or mining rights registration reduction units in the Tarim Basin.
[0261] The formula for calculating exploration results is as follows:
[0262]
[0263] Among them, I LT To compare the proven geological resources of highly explored areas, the unit is ×10. 4 t;H LT The number of successful exploration wells, per well, is used to compare the proven geological resources in highly explored areas.
[0264] The formula for calculating the minimum / economical exploration investment in low-exploration blocks or mineral rights registration decline units in the Tarim Basin is as follows:
[0265] I Tmin =(S SWmin ×P W ×(1+μ)+H Tmin ×P T )×(1+i g ),
[0266] I Tjj =(S SWjj ×P W ×(1+μ)+H Tjj ×P T )×(1+i g ),
[0267] Among them, I Tmin Minimum exploration investment, unit: 10,000 yuan; I Tjj Investment in economic exploration, unit: 10,000 yuan; S SWmin The minimum amount of work required for 3D exploration, measured in km. 2 S SWjj The economical 3D exploration workload, in km. 2 H Tmin The minimum amount of work required for deploying exploratory wells, measured in wells; H Tjj The workload for deploying exploration wells for economical purposes is expressed in wells (P). W This is the investment quota for 3D seismic exploration, in RMB 10,000 / km. 2 ;P T The unit for investment in exploration wells is 10,000 yuan per well; μ represents the statistical ratio of comprehensive research costs to 3D seismic investment, in %. g The percentage for calculating exploration management fees, expressed as a percentage.
[0268] As can be seen from the above description, the above embodiments achieve the following technical effects:
[0269] 1. Based on the calculation of expected technically recoverable reserves under different expected reserve discovery rates, the exploration and development workload and investment are calculated. Then, the total exploration and development cost is calculated according to the full-cost evaluation model. A relationship model between expected reserve discovery rate and total exploration and development cost is established. Under the constraints of expected reserve discovery rate and total exploration and development cost, the minimum expected reserve discovery rate is determined. Under the constraint of current oil price, the economical expected reserve discovery rate is determined.
[0270] 2. Based on the relationship model between technically recoverable reserves and exploration investment and exploration technology level, the minimum / economic exploration workload is calculated on the basis of determining the expected minimum / economic reserve discovery rate.
[0271] 3. Based on the determination of the minimum / economic exploration workload and in accordance with the exploration investment quota, this invention calculates the minimum / economic exploration investment. From the perspective of economic analysis, this invention provides a decision-making basis for exploration planning and mineral rights registration / reduction in low-exploration blocks and mineral rights registration reduction units in the Tarim Basin. It highlights the relationship between expected proven reserves and exploration investment and exploration technology level, and also highlights the risks associated with exploration investment.
Claims
1. A method for determining the minimum and economical amount of exploration work, characterized in that... Includes the following steps: The steps for calculating expected technically recoverable reserves are as follows: Based on the undiscovered resources in low-exploration blocks and mineral rights registration decline units, the expected technically recoverable reserves are calculated according to the expected reserve discovery rate and the recovery rate of different types of reservoir oil reservoirs. Steps for calculating exploration workload: Establish a model relating proven technically recoverable reserves to exploration and development workload, and calculate the exploration workload for different expected reserve discovery rates. Investment calculation steps: After determining the exploration workload under different expected reserve discovery rates, calculate the exploration and development investment under different expected reserve discovery rates based on the exploration and development investment quota. The steps for calculating the total cost of exploration and development are as follows: Based on real-time oil prices, commodity rates, comprehensive taxes, and the total cost evaluation model for exploration and development, calculate the total cost of exploration and development under different expected exploration rates. Economic analysis steps: Establish a model relating expected reserve discovery rate to total exploration and development costs; calculate total exploration and development costs under different expected discovery rates; and plot the relationship curve between expected reserve discovery rate and total exploration and development costs. Steps for determining minimum and economic provenance: Based on the expected minimum and economic provenance calculation model, calculate the minimum and economic provenance of low-exploration blocks and mineral rights registration decline units; The steps for determining the minimum and economical exploration workload for low-exploration blocks and mineral rights registration / reduction units are as follows: Based on the determined minimum and economical proven rate, the recovery rate of different types of reservoir oil reservoirs, and the calculated technically recoverable reserves, and then based on the relationship model between proven technically recoverable reserves and exploration investment and exploration technology level, the minimum and economical exploration workload for low-exploration exploration areas and mineral rights registration / reduction units are determined.
2. The method according to claim 1, characterized in that... The steps for calculating the expected technically recoverable reserves are as follows: Based on the recovery rate and the expected reserve discovery rate of different types of oil reservoirs, the expected proven technically recoverable reserves are calculated. , in, The expected technically recoverable reserves are expressed in units of... ; The amount of undiscovered resources in the exploration area, per unit ; The percentage of proven reserves is %; This refers to the recovery rate.
3. The method according to claim 1, characterized in that... Using the aforementioned expected technically recoverable reserves calculation steps, the expected technically recoverable reserves of oil and gas equivalent in low-exploration blocks and mineral rights registration decline units in the Tarim Basin are calculated: , Among them, 1 ton of crude oil = 1255 natural gas; To determine the expected technically recoverable oil and gas equivalent, per unit ; The amount of undiscovered oil resources in the exploration area, per unit ; The amount of undiscovered natural gas resources in the exploration area, per unit ; The expected proven oil resource rate is expressed in % (%). The expected natural gas resource exploration rate is expressed in percentages (%). Oil recovery rate, expressed in % (%) Gas reservoir recovery rate, in units.
4. The method according to claim 1, characterized in that... In the step of calculating the expected technically recoverable reserves, the formula for calculating the expected oil and gas equivalent proven rate is as follows: , Among them, 1 ton of crude oil = 1255 natural gas; The expected proven oil and gas equivalent exploration rate is expressed in % (%). The amount of undiscovered oil resources in the exploration area, per unit ; The amount of undiscovered natural gas resources in the exploration area, per unit ; The expected proven oil resource rate is expressed in % (%). The expected proven rate of natural gas resources is expressed in percent.
5. The method according to claim 1, characterized in that... Using the aforementioned exploration workload calculation steps, the formula for calculating the 3D seismic exploration workload of low-exploration-level blocks and mineral rights registration decline units in the Tarim Basin is as follows: , in, The workload of 3D seismic exploration to determine technically recoverable reserves, per km 2 ; The area of the exploration area or mining rights is expressed in km². 2 ; This represents the amount of 3D seismic exploration work already completed, in km². 2 ; The formula for calculating the total number of wells needed to determine the expected technically recoverable reserves in low-exploration blocks and mineral rights registration decline units in the Tarim Basin is as follows: , in, To determine the expected technically recoverable oil and gas equivalent, per unit ; The average oil production rate of the oilfield branch company is expressed as a percentage. Recovery rate, in %; The expected initial production capacity of the development well is expressed in t / d, and is assigned by reservoir engineering experts based on reservoir type. Production time, unit: days (d). The formula for calculating the number of successful exploration wells that have proven expected technically recoverable reserves is as follows: , in, The workload per unit well for successfully exploring technically recoverable reserves; The total number of wells for developing expected technically recoverable reserves, per well; The percentage of exploratory wells in the total production wells, expressed in % (%). The formula for calculating the proportion of exploratory wells in production wells is as follows: , in, To represent the number of exploratory wells in production wells within a highly explored exploration area, the unit is well; To draw an analogy to the total number of production wells in exploration areas with high exploration levels; The formula for calculating the production capacity construction scale of expected proven technically recoverable reserves in low-exploration blocks and mineral rights registration decline units in the Tarim Basin is as follows: , in, For the expected capacity construction scale, unit ; The average oil production rate of the oilfield branch company is expressed as a percentage. Recovery rate, in percent.
6. The method according to claim 1, characterized in that... Using the aforementioned investment calculation steps, the formula for calculating the proven technically recoverable reserves of expected proven reserves in low-exploration blocks and mineral rights registration decline units in the Tarim Basin is as follows: , in, For technically recoverable reserves discovered and proven, the unit is 10,000 yuan; This refers to materialized investment, expressed in ten thousand yuan. Investment in exploratory wells, in ten thousand yuan; The research cost is calculated in ten thousand yuan. For exploration management expenses, the unit is 10,000 yuan; The formula for calculating geophysical investment in low-exploration blocks and mineral rights registration reduction units in the Tarim Basin is as follows: , in, For geophysical and geochemical investment, the unit is 10,000 yuan. In the Tarim Basin, low exploration level blocks and mineral rights registration reduction units, two-dimensional seismic exploration is no longer carried out. Geophysical and geochemical exploration investment is mainly three-dimensional seismic exploration investment. This represents the workload of 3D seismic exploration, expressed in km². 2 ; This is the investment quota for 3D seismic exploration, in RMB 10,000 / km. 2 ; The formula for calculating the investment of successful exploration wells in low-exploration blocks and mineral rights registration decline units in the Tarim Basin is as follows: , in, Investment in exploratory wells, in ten thousand yuan; The workload per unit well for successfully exploring technically recoverable reserves; This is the investment quota for exploration wells, in ten thousand yuan per well; The formula for calculating the comprehensive study cost of low-exploration blocks and mineral rights registration reduction units in the Tarim Basin is as follows: , in, The research cost is calculated in ten thousand yuan. This refers to materialized investment, expressed in ten thousand yuan. The statistical ratio of comprehensive research costs to 3D seismic investment is shown in percentage. The formula for calculating exploration management fees for low-exploration-level blocks and mineral rights registration reduction units in the Tarim Basin is as follows: , in, For exploration management expenses, the unit is 10,000 yuan; This refers to materialized investment, expressed in ten thousand yuan. Investment in exploratory wells, in ten thousand yuan; The research cost is calculated in ten thousand yuan. The formula for calculating the apparent development investment for low-exploration blocks and mineral rights registration reduction units in the Tarim Basin is as follows: , in, For development investment, the unit is 10,000 yuan; The unit for investment in development well drilling projects is 10,000 yuan. Investment in capacity building is expressed in ten thousand yuan. The formula for calculating the investment in development well drilling is as follows: , in, The unit for investment in development well drilling projects is 10,000 yuan. The total number of wells for developing expected technically recoverable reserves, per well; The number of successful exploration wells used to determine technically recoverable reserves, per well; Investment quota for development wells, unit: 10,000 yuan / well; The formula for calculating investment in capacity building is: , in, Investment in capacity building is measured in 100 million yuan. The unit is 10,000 tons, depending on the scale of capacity construction. Investment in the construction of one million tons of production capacity for the oilfield branch company, in 100 million yuan per million tons; The formula for calculating operating costs and expenses is as follows: , in, For business purposes, the unit is 10,000 yuan; The total number of wells for developing expected technically recoverable reserves, per well; The expected initial production capacity of the development well is expressed in t / d, and is assigned by reservoir engineering experts based on reservoir type. Production time, unit: days (d). To reflect operating costs, the unit is yuan / ton, based on the average operating cost of the oilfield branch. The formula for calculating disposal costs is: , in, The disposal cost is in ten thousand yuan. The unit for the drilling investment of development wells is 10,000 yuan; Investment in capacity building is measured in ten thousand yuan.
7. The method according to claim 1, characterized in that... Using the aforementioned exploration and development full-cost calculation steps, the expected proven technically recoverable reserves in low-exploration blocks and mineral rights registration decline units in the Tarim Basin are... The formula for calculating the total cost of exploration and development is: , in, The total cost of exploration and development is expressed in yuan / ton. The cost of exploration is expressed in ten thousand yuan. Depending on the development investment, the unit is 10,000 yuan; The unit is 10,000 yuan, representing the cumulative operating costs during the simulated development process. This is the disposal fee, in ten thousand yuan. The unit is the technically recoverable reserves yet to be explored, expressed as ×10. 4 t; α represents the commodity rate of oil and gas production, i.e., the ratio of sales volume to production volume, in percentage (%). The comprehensive tax rate, per unit, for the sale of products, including value-added tax, resource tax, urban maintenance and construction tax, education surcharge, and special petroleum revenue.
Citation Information
Patent Citations
Quantitative classification method of oil and gas unit exploration degree
CN106033126A
Method for determining exploration block investment potential based on voluntary workload
CN107516162A