Control devices, controllers, cranes, and storage media for cranes.

By maintaining a constant ratio of distance between the hook, boom, and ground in real time, the risk of hook collision is eliminated, improving the safety and automated operation of the crane.

CN117430028BActive Publication Date: 2026-11-17ZOOMLION HEAVY INDUSTRY SCIENCE AND TECHNOLOGY CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202311277807.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-09-28
Publication Date
2026-11-17
Estimated Expiration
2043-09-28

AI Technical Summary

Technical Problem

In existing technologies, the hook is prone to colliding with the boom head or the ground during crane lifting operations, leading to accident risks. The operation is also complex and requires frequent manual switching of control modes.

Method used

By determining the vertical distance between the hook, boom, and ground in real time, crane equipment parameters are obtained, the target ratio is calculated, and the hook movement is controlled to maintain a constant distance ratio and avoid collisions.

Benefits of technology

It reduces the risk of collisions between the boom and boom head, and between the hook and the ground, improves safety performance and automation, and reduces operational complexity.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117430028B_ABST
    Figure CN117430028B_ABST
Patent Text Reader

Abstract

This application discloses a control method, controller, crane, and storage medium for a crane. The crane includes a boom head and a hook connected to the boom head. The control method includes: determining in real time a first vertical distance between the boom head and the hook, and a second vertical distance between the boom head and the ground; acquiring crane equipment parameters; determining a target ratio between the first vertical distance and a third vertical distance from the hook to the ground based on the equipment parameters; determining a first target vertical distance between the boom head and the hook corresponding to the second vertical distance based on the target ratio; and controlling the hook based on the first target vertical distance so that the difference between the adjusted ratio of the first and third vertical distances and the target ratio is less than a preset error value. Based on a constant distance ratio, the operator does not need to select and switch between different modes according to the working conditions, reducing the risk of collisions between the hook and the boom head, and between the hook and the ground, thus improving safety performance and automation.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This application relates to the field of crane technology, specifically to a control method, controller, crane, and storage medium for cranes. Background Technology

[0002] When a crane uses its hook to lift an object, the hoisting mechanism controls the movement of the wire rope. The hook can move vertically up and down via the wire rope, and it also moves up and down during luffing and telescopic crane movements. If the hook's movement is not controlled, there is a risk of it colliding with the ground, boom, or other objects, leading to a lifting accident. Currently, there are two main methods for controlling the hook's height. Method one involves manually operating a handle to control the hoisting mechanism during luffing or telescopic movements, thereby controlling the hook's movement and ensuring its height is maintained at a suitable position. This method requires constant observation of the surrounding environment and multiple operational controls, making it complex and demanding on the operator. Method two involves control through a designed ground control mode and boom control mode. This method reduces the difficulty of operation, but the operator needs to assess different working conditions and select different modes accordingly. In complex working conditions, frequent switching between operating modes may be necessary. Furthermore, there is a risk of the hook colliding with the boom head in ground mode, while there is a risk of the hook colliding with the ground in boom head mode. Summary of the Invention

[0003] The purpose of this application is to provide a control method, controller, crane, and storage medium for a crane, in order to solve the technical problem in the prior art where the hook collides with the boom head and the ground.

[0004] To achieve the above objectives, a first aspect of this application provides a control method for a crane, the crane including a boom head and a hook connected to the boom head, the control method comprising: The first vertical distance between the boom head and the hook, and the second vertical distance between the boom head and the ground are determined in real time. Obtain the crane's equipment parameters; Determine the target ratio between the first vertical distance and the third vertical distance from the hook to the ground based on the equipment parameters; Determine the first target vertical distance between the boom and the hook corresponding to the second vertical distance based on the target ratio; The hook is controlled based on the first target vertical distance, so that the difference between the ratio of the adjusted first vertical distance and the third vertical distance and the target ratio is less than the preset error value.

[0005] In embodiments of this application, the crane further includes a hydraulic cylinder corresponding to the boom. The equipment parameters include a first interval distance between the boom head and the three-dimensional model support point of the hydraulic cylinder, and a second interval distance between the three-dimensional model support point of the hydraulic cylinder and the boom tail. Determining the target ratio of the first vertical distance and the third vertical distance from the hook to the ground according to the equipment parameters includes: determining the ratio of the first interval distance and the second interval distance as the target ratio.

[0006] In the embodiments of this application, controlling the hook based on the first target vertical distance to make the difference between the ratio of the adjusted first vertical distance and the third vertical distance and the target ratio less than a preset error value includes: when the first vertical distance is greater than the first target vertical distance, controlling the hook to perform an upward operation in real time to make the difference between the ratio of the adjusted first vertical distance and the third vertical distance and the target ratio less than a preset error value.

[0007] In an embodiment of this application, controlling the hook based on a first target vertical distance to ensure that the difference between the ratio of the adjusted first vertical distance and the third vertical distance and the target ratio is less than a preset error value includes: when the first vertical distance is less than the first target vertical distance, controlling the hook to perform a descent operation in real time to ensure that the difference between the ratio of the adjusted first vertical distance and the third vertical distance and the target ratio is less than the preset error value.

[0008] In the embodiments of this application, determining the first target vertical distance between the boom head and the hook corresponding to the second vertical distance based on the target ratio includes calculating the first target vertical distance according to formula (1): (1) in, This refers to the first target vertical distance between the boom head and the hook. This refers to the second vertical distance between the arm head and the ground. It refers to the target ratio.

[0009] In embodiments of this application, the crane further includes a winch drum device and a pulley connected to the hook. Real-time determination of the first vertical distance between the boom head and the hook includes: real-time acquisition of the current height below the pulley, drum data of the winch drum device, and boom data corresponding to the boom. The drum parameters include the rotation angle, drum diameter, and wire rope diameter. The boom data includes the boom length, a third interval distance between the boom tail and the winch drum device, and a fourth interval distance between the pulley connected to the hook and the bottom of the hook. The crane also includes determining the current elongation length of the wire rope based on the device parameters; determining a fifth interval distance between the boom head and the winch drum device in real-time based on the boom length and the third interval distance; and determining the first vertical distance in real-time based on the fourth interval distance, the current elongation length, and the fifth interval distance.

[0010] In the embodiments of this application, determining the first vertical distance in real time based on the fourth interval distance, the current elongation length, and the fifth interval distance includes calculating the first vertical distance according to formula (2): ( (2) in, This refers to the first vertical distance between the boom head and the hook. This refers to the current elongation of the wire rope. This refers to the fifth interval distance between the boom head and the winch drum assembly. This refers to the length of the wire rope occupied by the pulley. This refers to the ratio of the wire rope on the hook. This refers to the fourth interval distance between the pulley connected to the hook and the bottom of the hook. This refers to the correction value.

[0011] A second aspect of this application provides a controller, comprising: The memory is configured to store instructions; and The processor is configured to retrieve the instructions from the memory and, when executing the instructions, to implement the aforementioned control method for a crane.

[0012] A third aspect of this application provides a crane, comprising: Crane boom, including the boom head; The hook connects to the boom head; and The controller described above.

[0013] A fourth aspect of this application provides a machine-readable storage medium, characterized in that the machine-readable storage medium stores instructions for causing a machine to execute the aforementioned control method for a crane. The above technical solution describes a crane comprising a boom head and a hook connected to the boom head. The control method includes: real-time determination of a first vertical distance between the boom head and the hook, and a second vertical distance between the boom head and the ground; acquisition of crane equipment parameters; determination of a target ratio between the first vertical distance and a third vertical distance from the hook to the ground based on the equipment parameters; determination of a first target vertical distance between the boom head and the hook corresponding to the second vertical distance based on the target ratio; and control of the hook based on the first target vertical distance, ensuring that the difference between the adjusted ratio of the first and third vertical distances and the target ratio is less than a preset error value. Based on a constant distance ratio, operators are not required to select or switch between different modes according to working conditions, reducing the risk of collisions between the boom and the boom head, and between the hook and the ground, thus improving safety performance and automation.

[0014] Other features and advantages of the embodiments of this application will be described in detail in the following detailed description section. Attached Figure Description

[0015] The accompanying drawings are provided to further illustrate the embodiments of this application and form part of the specification. They are used together with the following detailed description to explain the embodiments of this application, but do not constitute a limitation on the embodiments of this application. In the drawings: Figure 1 The schematic diagram illustrates a flow chart of a control method for a crane according to an embodiment of this application; Figure 2 The illustration shows a schematic flowchart of a control method for a crane according to a specific embodiment of this application; Figure 3 This schematic diagram illustrates a structural block diagram of a controller according to an embodiment of the present application; Figure 4 A schematic diagram of a crane according to an embodiment of this application is shown. Figure 5 The schematic diagram illustrates a structural schematic of a device for controlling a crane according to an embodiment of this application; Figure 6 A schematic diagram of a computer device according to an embodiment of this application is shown.

[0016] Explanation of reference numerals in the attached figures Detailed Implementation

[0017] To make the objectives, technical solutions, and advantages of the embodiments of this application clearer, the technical solutions of the embodiments of this application will be clearly and completely described below with reference to the accompanying drawings. It should be understood that the specific embodiments described herein are only for illustration and explanation of the embodiments of this application and are not intended to limit the embodiments of this application. All other embodiments obtained by those skilled in the art based on the embodiments of this application without creative effort are within the scope of protection of this application.

[0018] It should be noted that if the embodiments of this application involve directional indicators (such as up, down, left, right, front, back, etc.), the directional indicators are only used to explain the relative positional relationship and movement of each component in a certain specific posture (as shown in the figure). If the specific posture changes, the directional indicators will also change accordingly.

[0019] Furthermore, if the embodiments of this application involve descriptions such as "first" or "second," these descriptions are for descriptive purposes only and should not be construed as indicating or implying their relative importance or implicitly specifying the number of technical features indicated. Therefore, features defined with "first" or "second" may explicitly or implicitly include at least one of those features. Additionally, the technical solutions of various embodiments can be combined with each other, but this must be based on the ability of those skilled in the art to implement them. If the combination of technical solutions is contradictory or impossible to implement, it should be considered that such a combination of technical solutions does not exist and is not within the scope of protection claimed in this application.

[0020] Figure 1 The illustration schematically shows a flow diagram of a control method for a crane according to an embodiment of this application. Figure 1 As shown in the figure, this application provides a control method for a crane, which may include the following steps.

[0021] S102, determines in real time the first vertical distance between the boom head and the hook, and the second vertical distance between the boom head and the ground.

[0022] S104, Obtain the equipment parameters of the crane.

[0023] S106, determine the target ratio of the first vertical distance to the third vertical distance from the hook to the ground based on the equipment parameters.

[0024] S108, determine the first target vertical distance between the boom and the hook corresponding to the second vertical distance based on the target ratio.

[0025] S110, control the hook based on the first target vertical distance, so that the difference between the ratio of the adjusted first vertical distance and the third vertical distance and the target ratio is less than the preset error value.

[0026] The equipment parameters of a crane are parameters that characterize the crane's main technical performance indicators. A crane includes a boom, with the boom head connected to the hook. Specifically, there is a pulley system at the boom head and another pulley system above the hook, with a wire rope connecting the two pulley systems to adjust the distance between the hook and the boom head. When the crane performs luffing and telescopic movements, the hook moves up and down accordingly. Therefore, the distance between the boom head and the hook, and the distance between the boom head and the ground, are both variable. The processor can then determine in real time the first vertical distance between the boom head and the hook, and the second vertical distance between the boom head and the ground. These first and second vertical distances can be detected by sensors or calculated using the crane's equipment parameters. The processor can acquire the crane's equipment parameters and determine a target ratio between the first vertical distance and the third vertical distance from the hook to the ground. This target ratio refers to the target value that ensures the first and third vertical distances maintain a fixed proportion during the crane's luffing or telescopic movements. The processor can determine the first target vertical distance between the boom and the hook, assuming the distance between the boom and the ground is a second vertical distance, based on the target ratio. The first target vertical distance refers to the target value of the vertical distance between the boom and the hook. The processor can control the hook based on the first target vertical distance to ensure that the difference between the adjusted ratio of the first and third vertical distances and the target ratio is less than a preset error value. The preset error value is an error value set for the difference between the target ratio and the actual ratio, controlling the actual ratio to remain within the error range.

[0027] By setting a constant ratio between the distance between the boom and the hook and the distance between the hook and the ground, the hook is kept at a constant proportional position during the crane's luffing or telescopic movements. This ensures that the hook will not touch either the boom or the ground, eliminating the need for operators to select and switch between different modes based on working conditions, thus improving safety and automation.

[0028] In one embodiment, controlling the hook based on a first target vertical distance to ensure that the difference between the ratio of the adjusted first vertical distance and the third vertical distance and the target ratio is less than a preset error value includes: when the first vertical distance is greater than the first target vertical distance, controlling the hook to perform an upward operation in real time to ensure that the difference between the ratio of the adjusted first vertical distance and the third vertical distance and the target ratio is less than the preset error value.

[0029] In one embodiment, controlling the hook based on a first target vertical distance to ensure that the difference between the ratio of the adjusted first vertical distance and the third vertical distance and the target ratio is less than a preset error value includes: when the first vertical distance is less than the first target vertical distance, controlling the hook to perform a descent operation in real time to ensure that the difference between the ratio of the adjusted first vertical distance and the third vertical distance and the target ratio is less than the preset error value.

[0030] Specifically, during the boom's luffing or telescopic movements, the ratio between the first and third vertical distances changes. Therefore, the processor can, in real-time, control the hook to lower when the first vertical distance between the boom and hook is less than the first target vertical distance, increasing the first vertical distance to ensure the difference between the adjusted ratio of the first and third vertical distances and the target ratio is less than a preset error value, thus preventing collision between the boom and hook. Conversely, if the first vertical distance between the boom and hook is greater than the first target vertical distance, the processor can, in real-time, control the hook to rise, decreasing the first vertical distance to ensure the difference between the adjusted ratio of the first and third vertical distances and the target ratio is less than a preset error value, thus preventing collision between the hook and the ground. This reduces the risks during crane operation, protects the lifting equipment, and extends its service life.

[0031] In one embodiment, the crane further includes a hydraulic cylinder corresponding to the boom, and the equipment parameters include a first interval distance between the boom head and the three-dimensional model support point of the hydraulic cylinder, and a second interval distance between the three-dimensional model support point of the hydraulic cylinder and the boom tail; determining the target ratio of the first vertical distance and the third vertical distance according to the equipment parameters includes: determining the ratio between the first interval distance and the second interval distance as the target ratio.

[0032] The 3D model support point is the center coordinate point of the contact area between the support structure and the model entity. Specifically, the processor can determine the target ratio of the first vertical distance and the third vertical distance based on the ratio of the first interval distance between the 3D model support point of the boom head and the cylinder and the second interval distance between the 3D model support point of the cylinder and the boom tail. In another embodiment, the target ratio can also be set by a preset ratio, that is, the technician directly gives a ratio as the target ratio. Another method is to use the ratio between the distance between the boom head and the hook and the distance between the hook and the ground when the crane is first controlled as the target ratio. All of the above methods can set a target ratio to quantitatively control the lifting and lowering operations of the hook so that the crane can accurately perform the corresponding operations.

[0033] In another implementation, a target ratio of the third vertical distance from the hook to the ground to the second vertical distance from the boom to the ground can be determined based on equipment parameters. This target ratio can then be used to determine the first target vertical distance between the boom and the hook corresponding to the second vertical distance, allowing for adjustment of the hook's lifting and lowering. Alternatively, a target ratio of the third vertical distance from the hook to the ground to the first vertical distance between the boom and the hook can be determined based on equipment parameters, allowing for adjustment of the hook's lifting and lowering.

[0034] In one embodiment, determining the first target vertical distance between the boom and the hook corresponding to the second vertical distance based on the target ratio includes calculating the first target vertical distance according to formula (1): (1) in, This refers to the first target vertical distance between the boom head and the hook. This refers to the second vertical distance between the arm head and the ground. This refers to the target ratio. The second vertical distance between the boom tip and the ground minus the first vertical distance between the boom tip and the hook equals the vertical distance between the hook and the ground. Therefore, regardless of whether the boom is performing luffing or telescopic movements, by controlling the first vertical distance between the boom tip and the hook based on the target ratio, collisions between the boom tip and the hook, and between the hook and the ground, can be avoided.

[0035] In embodiments of this application, the crane further includes a winch drum device and a pulley connected to the hook. Real-time determination of the first vertical distance between the boom head and the hook includes: real-time acquisition of the current height below the pulley, drum data of the winch drum device, and boom data corresponding to the boom. The drum parameters include the rotation angle, drum diameter, and wire rope diameter. The boom data includes the boom length, a third interval distance between the boom tail and the winch drum device, and a fourth interval distance between the pulley connected to the hook and the bottom of the hook. The crane also includes determining the current elongation length of the wire rope based on the device parameters; determining a fifth interval distance between the boom head and the winch drum device in real-time based on the boom length and the third interval distance; and determining the first vertical distance in real-time based on the fourth interval distance, the current elongation length, and the fifth interval distance.

[0036] The winch drum assembly contains a wire rope connected to a hook, which descends as the wire rope extends. Therefore, the processor can calculate the current extension length of the wire rope released from the winch drum assembly based on the winch drum assembly's rotation angle, drum diameter, and wire rope diameter. Simultaneously, the processor can calculate the fifth interval distance between the boom head and the winch drum assembly based on the geometric relationship between the boom length, the third interval distance from the boom tail to the winch drum assembly, and the diameter of the pulley connected to the boom head. The processor can then determine the first vertical distance in real time based on the fourth interval distance, the current extension length, and the fifth interval distance.

[0037] Specifically, in one embodiment, determining the first vertical distance in real time based on the fourth interval distance, the current elongation length, and the fifth interval distance includes calculating the first vertical distance according to formula (2): ( (2) in, This refers to the first vertical distance between the boom head and the hook. This refers to the current elongation of the wire rope. This refers to the fifth interval distance between the boom head and the winch drum assembly. This refers to the length of the wire rope occupied by the pulley. This refers to the ratio of the wire rope on the hook. This refers to the fourth interval distance between the pulley connected to the hook and the bottom of the hook. This refers to the correction value. Specifically, based on the diameters of the pulleys connected to the boom and the hook, the length of the wire rope occupied by the two pulleys can be calculated. .

[0038] By setting a constant ratio between the distance from the boom to the hook and the distance from the hook to the ground, the crane ensures that the hook remains at a constant proportional distance between the boom and the ground during luffing or telescopic movements. This prevents the hook from touching either the boom or the ground, eliminating the need for operators to select and switch between different modes based on working conditions, reducing the risks associated with manual operation, and improving safety and automation. Furthermore, by setting a target ratio based on the crane's own parameters, customized ratios can be set for different crane models, facilitating both single-machine automated operation and multi-machine collaborative operation.

[0039] Figure 1 This is a flowchart illustrating a control method for a crane in one embodiment. It should be understood that, although... Figure 1The steps in the flowchart are shown sequentially as indicated by the arrows, but these steps are not necessarily executed in the order indicated by the arrows. Unless otherwise specified herein, there is no strict order in which these steps are executed, and they can be performed in other orders. Figure 1 At least some of the steps in the process may include multiple sub-steps or multiple stages. These sub-steps or stages are not necessarily completed at the same time, but can be executed at different times. The execution order of these sub-steps or stages is not necessarily sequential, but can be executed in turn or alternately with other steps or at least some of the sub-steps or stages of other steps.

[0040] In one embodiment, such as Figure 2 As shown, a specific embodiment of a control system for a crane is provided, including a main module 10, a ratio processing module 20, a distance processing module 30, and a control processing module 40. During operation, the main module 10 sequentially calls the ratio processing module 20, the distance processing module 30, and the control processing module 40. This calling process is repeatedly executed to implement the aforementioned control method for the crane, thereby controlling the hook.

[0041] The task of the ratio processing module 20 is to generate target ratios and provide them to the distance processing module 30. The ratio processing module 20 provides several methods for generating target ratios. The first method involves a technician directly specifying a ratio as the target ratio. The second method, for situations where crane control has just begun, uses the ratio between the distance from the boom head to the hook and the distance from the hook to the ground as the target ratio. The third method uses the ratio of the first interval distance between the boom head and the 3D model support point of the hydraulic cylinder, and the second interval distance between the 3D model support point of the hydraulic cylinder and the boom tail, to determine the target ratios for the first and third vertical distances. All of the above methods can set target ratios to quantitatively control the lifting and lowering of the hook, allowing the crane to precisely execute the corresponding operations.

[0042] The distance processing module 30 has three main tasks. The first task is parameter acquisition, including receiving the target ratio generated by the ratio processing module 20 and acquiring the second vertical distance between the boom head and the ground in real time. The second task is to generate the first target vertical distance between the boom head and the hook. The first target vertical distance is generated according to formula (1) mentioned above. The third task of the distance processing module 30 is to provide the first target vertical distance generated by the second task to the control processing module 40.

[0043] The control processing module 40 acquires the first vertical distance between the boom head and the hook in real time, and then compares this real-time value with a target value, i.e., the first vertical distance and the first target vertical distance. When the difference between the real-time value and the target value is greater than the upper tolerance limit (the upper limit corresponding to the preset error value), the control processing module 40 outputs a command to control the winch drum device to drive the wire rope, causing the hook to rise to the first target vertical distance. When the difference between the real-time value and the target value is less than the lower tolerance limit (the lower limit corresponding to the preset error value), the control processing module 40 outputs a command to control the winch drum device to drive the wire rope, causing the hook to descend to the first target vertical distance. The output command of the control processing module 40 ensures that the ratio of the vertical distance between the boom head and the hook to the vertical distance between the hook and the ground is a constant value.

[0044] In one embodiment, such as Figure 3 As shown, a specific embodiment of a control method for a crane is provided. Combined with... Figure 2 The system is used for the crane's control system. If the crane performs luffing or telescopic operations, the main module calls the ratio processing module to generate a preset ratio value K=1 as the target ratio value. If the crane does not perform luffing or telescopic operations, no operation is taken. That is, during luffing or telescopic operations, although the vertical distance between the boom and the ground... The distance changes in real time, but the hook is always kept in the middle position between the boom tip and the ground. At this time, the main module calls the distance processing module to generate the target distance value between the boom tip and the hook (the first target vertical distance). Only the vertical distance between the boom head and the hook needs to be controlled according to... The action can be executed based on the changing patterns. The main module can call the control processing module. In the event of this condition, the control processing module controls the hook to rise. If it does not meet the requirements... In such cases, further determination is needed. .exist In such cases, the control processing module lowers the hook. This reduces the risk of the hook colliding with the boom head and the ground.

[0045] Figure 4 A schematic block diagram of a controller according to an embodiment of this application is shown. Figure 4 As shown, this application embodiment provides a controller 400, which may include: Memory 410 is configured to store instructions; and The processor 420 is configured to retrieve instructions from the memory 410 and, when executing the instructions, to implement the aforementioned method for controlling the boom.

[0046] Specifically, in this embodiment of the application, the processor 420 can be configured to: The first vertical distance between the boom head and the hook, and the second vertical distance between the boom head and the ground are determined in real time. Obtain the crane's equipment parameters; Determine the target ratio between the first vertical distance and the third vertical distance based on the equipment parameters; Determine the first target vertical distance between the boom and the hook corresponding to the second vertical distance based on the target ratio; The hook is controlled based on the first target vertical distance, so that the difference between the ratio of the adjusted first vertical distance and the third vertical distance and the target ratio is less than the preset error value.

[0047] Furthermore, the processor 420 is also configured to: The crane also includes hydraulic cylinders corresponding to the boom. The equipment parameters include a first interval distance between the boom head and the support point of the three-dimensional model of the hydraulic cylinder, and a second interval distance between the support point of the three-dimensional model of the hydraulic cylinder and the tail of the boom. Determining the target ratio of the first vertical distance and the third vertical distance according to the equipment parameters includes: determining the ratio between the first interval distance and the second interval distance as the target ratio.

[0048] Furthermore, the processor 420 is also configured to: Controlling the hook based on the first target vertical distance to ensure that the difference between the ratio of the adjusted first vertical distance and the third vertical distance and the target ratio is less than a preset error value includes: when the first vertical distance is greater than the first target vertical distance, controlling the hook to perform an upward operation in real time to ensure that the difference between the ratio of the adjusted first vertical distance and the third vertical distance and the target ratio is less than a preset error value.

[0049] Furthermore, the processor 420 is also configured to: Controlling the hook based on the first target vertical distance to ensure that the difference between the ratio of the adjusted first vertical distance and the third vertical distance and the target ratio is less than a preset error value includes: when the first vertical distance is less than the first target vertical distance, controlling the hook to perform a descent operation in real time to ensure that the difference between the ratio of the adjusted first vertical distance and the third vertical distance and the target ratio is less than a preset error value.

[0050] Furthermore, the processor 420 is also configured to: The first target vertical distance between the boom and the hook, corresponding to the second vertical distance, is determined based on the target ratio. This includes calculating the first target vertical distance according to formula (1): (1) in, This refers to the first target vertical distance between the boom head and the hook. This refers to the second vertical distance between the arm head and the ground. It refers to the target ratio.

[0051] Furthermore, the processor 420 is also configured to: The crane also includes a winch drum assembly and a pulley connected to the hook. Real-time determination of the first vertical distance between the boom head and the hook includes: acquiring the current height below the pulley, the drum data of the winch drum assembly, and the boom data corresponding to the boom. The drum parameters include the rotation angle, drum diameter, and wire rope diameter. The boom data includes the boom length, the third interval distance between the boom tail and the winch drum assembly, and the fourth interval distance between the pulley connected to the hook and the bottom of the hook. The crane also determines the current elongation length of the wire rope based on the device parameters; determines the fifth interval distance between the boom head and the winch drum assembly in real time based on the boom length and the third interval distance; and determines the first vertical distance in real time based on the fourth interval distance, the current elongation length, and the fifth interval distance.

[0052] Furthermore, the processor 420 is also configured to: The first vertical distance is determined in real time based on the fourth interval distance, the current elongation length, and the fifth interval distance, including the calculation of the first vertical distance according to formula (2): ( (2) in, This refers to the first vertical distance between the boom head and the hook. This refers to the current elongation of the wire rope. This refers to the fifth interval distance between the boom head and the winch drum assembly. This refers to the length of the wire rope occupied by the pulley. This refers to the ratio of the wire rope on the hook. This refers to the fourth interval distance between the pulley connected to the hook and the bottom of the hook. This refers to the correction value.

[0053] like Figure 5 As shown in the embodiments of this application, a crane is also provided, which may include: The boom 510 includes the boom head 511; Hook 520, connected to boom head 511; and Controller 400 as described above.

[0054] In one embodiment, the crane may further include a hydraulic cylinder, a winch drum assembly, a first pulley connected to the boom head, and a second pulley connected to the hook. The first and second pulleys are connected by a wire rope. Based on a first interval distance between the boom head and the three-dimensional model support point of the hydraulic cylinder, and a second interval distance between the three-dimensional model support point of the hydraulic cylinder and the boom tail, the ratio between the first and second interval distances can be determined as a target ratio.

[0055] This application also provides a machine-readable storage medium storing instructions for causing a machine to perform the above-described control method for a crane.

[0056] The processor contains a kernel, which retrieves the corresponding program units from memory. One or more kernels can be configured, and the control method for the crane can be implemented by adjusting the kernel parameters.

[0057] The memory may include non-permanent memory in computer-readable media, such as random access memory (RAM) and / or non-volatile memory, such as read-only memory (ROM) or flash RAM, and the memory includes at least one memory chip.

[0058] This application provides a storage medium storing a program that, when executed by a processor, implements the above-described control method for a crane.

[0059] This application provides a processor for running a program, wherein the program executes the above-described control method for a crane.

[0060] In one embodiment, a computer device is provided, which may be a server, and its internal structure diagram may be as follows: Figure 6 As shown, the computer device includes a processor A01, a network interface A02, memory (not shown), and a database (not shown) connected via a system bus. The processor A01 provides computing and control capabilities. The memory includes internal memory A03 and a non-volatile storage medium A04. The non-volatile storage medium A04 stores an operating system B01, a computer program B02, and a database (not shown). The internal memory A03 provides an environment for the operation of the operating system B01 and the computer program B02 stored in the non-volatile storage medium A04. The database stores data for crane control methods. The network interface A02 communicates with external terminals via a network connection. When the computer program B02 is executed by the processor A01, it implements a crane control method.

[0061] Those skilled in the art will understand that Figure 6 The structure shown is merely a block diagram of a portion of the structure related to the present application and does not constitute a limitation on the computer device to which the present application is applied. Specific computer devices may include more or fewer components than those shown in the figure, or combine certain components, or have different component arrangements.

[0062] Those skilled in the art will understand that embodiments of this application can be provided as methods, systems, or computer program products. Therefore, this application can take the form of a completely hardware embodiment, a completely software embodiment, or an embodiment combining software and hardware aspects. Furthermore, this application can take the form of a computer program product embodied on one or more computer-usable storage media (including, but not limited to, disk storage, CD-ROM, optical storage, etc.) containing computer-usable program code.

[0063] This application is described with reference to flowchart illustrations and / or block diagrams of methods, apparatus (systems), and computer program products according to embodiments of this application. It will be understood that each block of the flowchart illustrations and / or block diagrams, and combinations of blocks in the flowchart illustrations and / or block diagrams, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, special-purpose computer, embedded processor, or other programmable data processing apparatus to produce a machine, such that the instructions, which execute via the processor of the computer or other programmable data processing apparatus, generate instructions for implementing the flowchart... Figure 1 One or more processes and / or boxes Figure 1 A device that provides the functions specified in one or more boxes.

[0064] These computer program instructions may also be stored in a computer-readable storage medium that can direct a computer or other programmable data processing device to function in a particular manner, such that the instructions stored in the computer-readable storage medium produce an article of manufacture including instruction means, which are implemented in a process Figure 1 One or more processes and / or boxes Figure 1 The function specified in one or more boxes.

[0065] These computer program instructions may also be loaded onto a computer or other programmable data processing equipment to cause a series of operational steps to be performed on the computer or other programmable equipment to produce a computer-implemented process, thereby providing instructions that execute on the computer or other programmable equipment for implementing the process. Figure 1 One or more processes and / or boxes Figure 1 The steps of the function specified in one or more boxes.

[0066] In a typical configuration, a computing device includes one or more processors (CPU), input / output interfaces, network interfaces, and memory.

[0067] Memory may include non-persistent memory in computer-readable media, such as random access memory (RAM) and / or non-volatile memory, such as read-only memory (ROM) or flash RAM. Memory is an example of computer-readable media.

[0068] Computer-readable media includes both permanent and non-permanent, removable and non-removable media that can store information using any method or technology. Information can be computer-readable instructions, data structures, modules of programs, or other data. Examples of computer storage media include, but are not limited to, phase-change memory (PRAM), static random access memory (SRAM), dynamic random access memory (DRAM), other types of random access memory (RAM), read-only memory (ROM), electrically erasable programmable read-only memory (EEPROM), flash memory or other memory technologies, CD-ROM, digital versatile optical disc (DVD) or other optical storage, magnetic tape, magnetic disk storage or other magnetic storage devices, or any other non-transferable medium that can be used to store information accessible by a computing device. As defined herein, computer-readable media does not include transient computer-readable media, such as modulated data signals and carrier waves.

[0069] It should also be noted that the terms "comprising," "including," or any other variations thereof are intended to cover non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements includes not only those elements but also other elements not expressly listed, or elements inherent to such process, method, article, or apparatus. Unless otherwise specified, an element defined by the phrase "comprising one..." does not exclude the presence of other identical elements in the process, method, article, or apparatus that includes that element.

[0070] The above are merely embodiments of this application and are not intended to limit the scope of this application. Various modifications and variations can be made to this application by those skilled in the art. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of this application should be included within the scope of the claims of this application.

Claims

1. A control method for a crane, characterized in that, The crane includes a boom head and a hook connected to the boom head, as well as a hydraulic cylinder corresponding to the boom. The control method includes: The first vertical distance between the boom head and the hook, and the second vertical distance between the boom head and the ground are determined in real time. Obtain the equipment parameters of the crane, which include a first interval distance between the boom head and the three-dimensional model support point of the hydraulic cylinder, and a second interval distance between the three-dimensional model support point of the hydraulic cylinder and the boom tail. The three-dimensional model support point is the center coordinate point of the contact area between the support structure and the model entity. The target ratio of the first vertical distance to the third vertical distance from the hook to the ground is determined based on the equipment parameters. The first target vertical distance between the boom head and the hook, corresponding to the second vertical distance, is determined based on the target ratio. The hook is controlled based on the first target vertical distance so that the difference between the ratio of the adjusted first vertical distance and the third vertical distance and the target ratio is less than a preset error value; The step of determining the target ratio between the first vertical distance and the third vertical distance from the hook to the ground based on the equipment parameters includes: The ratio of the first interval distance to the second interval distance is determined as the target ratio. The determination of the first target vertical distance between the boom head and the hook corresponding to the second vertical distance based on the target ratio includes calculating the first target vertical distance according to formula (1): (1) in, This refers to the first target vertical distance between the boom head and the hook. This refers to the second vertical distance between the arm head and the ground. This refers to the target ratio.

2. The control method for a crane according to claim 1, characterized in that, The step of controlling the hook based on the first target vertical distance, so that the difference between the ratio of the adjusted first vertical distance and the third vertical distance and the target ratio is less than a preset error value, includes: When the first vertical distance is greater than the first target vertical distance, the hook is controlled to perform an upward operation in real time so that the difference between the ratio of the adjusted first vertical distance and the third vertical distance and the target ratio is less than the preset error value.

3. The control method for a crane according to claim 1, characterized in that, The step of controlling the hook based on the first target vertical distance, so that the difference between the ratio of the adjusted first vertical distance and the third vertical distance and the target ratio is less than a preset error value, includes: When the first vertical distance is less than the first target vertical distance, the hook is controlled to perform a descent operation in real time so that the difference between the ratio of the adjusted first vertical distance and the third vertical distance and the target ratio is less than the preset error value.

4. The control method for a crane according to claim 1, characterized in that, The crane further includes a winch drum assembly and a pulley connected to the hook, and the real-time determination of the first vertical distance between the boom head and the hook includes: The system acquires in real time the current height below the pulley, the drum data of the winch drum device, and the boom data corresponding to the boom. The drum data includes the rotation angle value, drum diameter, and wire rope diameter. The boom data includes the boom length, the third interval distance between the boom tail and the winch drum device, and the fourth interval distance between the pulley connected to the hook and the bottom of the hook. The current elongation of the wire rope is determined based on the device parameters; The fifth interval distance between the boom head and the winch drum device is determined in real time based on the length of the boom and the third interval distance. The first vertical distance is determined in real time based on the fourth interval distance, the current elongation length, and the fifth interval distance.

5. The control method for a crane according to claim 4, characterized in that, The real-time determination of the first vertical distance based on the fourth interval distance, the current elongation length, and the fifth interval distance includes calculating the first vertical distance according to formula (2): ( (2) in, This refers to the first vertical distance between the boom head and the hook. This refers to the current elongation of the wire rope. This refers to the fifth interval distance between the boom head and the hoisting drum device. This refers to the length of the wire rope occupied by the pulley. This refers to the ratio of the wire rope on the hook. This refers to the fourth interval distance between the pulley connected to the hook and the bottom of the hook. This refers to the correction value.

6. A controller, characterized in that, include: The memory is configured to store instructions; as well as The processor is configured to retrieve the instructions from the memory and, when executing the instructions, to implement the control method for a crane according to any one of claims 1 to 5.

7. A crane, characterized in that, include: Crane boom, including the boom head; The hook is connected to the boom head; as well as The controller according to claim 6.

8. A machine-readable storage medium, characterized in that, The machine-readable storage medium stores instructions for causing the machine to perform the control method for a crane according to any one of claims 1 to 5.

Citation Information

Patent Citations

  • Method and device for controlling height of crane hook and crane

    CN109437019A

  • Crane and crane control method

    CN113247775A