Fault confirmation method and system for underground power equipment
By constructing an environmental model of underground power equipment and predicting failure time, the problem of fault detection caused by the soil moisture changes in underground power equipment is solved, and high-precision fault monitoring and dynamic monitoring are achieved, ensuring the stability of the underground environment.
Patent Information
- Application Number
- CN202311308498.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-10-10
- Publication Date
- 2025-01-14
- Estimated Expiration
- 2043-10-10
AI Technical Summary
In underground environments, power equipment has increased difficulty in detecting faults due to changes in soil layers, and it is difficult for the prior art to effectively monitor the failures of underground power equipment.
By obtaining soil layer moisture data in the underground area, an environmental model of power equipment is constructed, fault time is predicted, monitoring time is determined based on the water inlet, working parameters are obtained in real time to confirm the fault status, and fault monitoring accuracy is improved.
Dynamic fault monitoring of underground power equipment is realized, fault detection accuracy is improved, and interference to the underground environment is avoided.
Smart Images

Figure CN117434362B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of underground power equipment, and in particular to a fault confirmation method and system for underground power equipment. Background Art
[0002] With the development of science and technology, power equipment can be located in an underground environment and extended along underground passages through cables. At this time, the power equipment is buried underground at the initial stage of assembly and is located in an underground environment. The power equipment works in the underground environment and is in contact with the soil layer of the underground environment. At this time, the soil layer of the underground environment wraps the power equipment in multiple directions. However, the soil layer will affect the weather changes in the external environment and have moisture changes. Studies have shown that the moisture level of the soil layer will affect the failure of the power equipment. In order to certify the failure of the power equipment in the underground environment, it is necessary to peel off the soil layer of the underground environment and affect the underground environment where the underground power equipment is located to achieve dynamic monitoring of the underground power equipment. Summary of the invention
[0003] The purpose of the present invention is to overcome the shortcomings of the prior art. The present invention provides a fault confirmation method and system for underground power equipment. The environmental model of the power equipment is constructed based on the height of the soil layer and the moisture coefficient of the soil layer. The failure time of the power equipment is predicted according to the environmental model of the power equipment and the moisture resistance level of the power equipment. The monitoring time of the power equipment is determined according to the failure time of the power equipment and the amount of water inflow into the underground area within a preset time. At this time, the working parameters of the power equipment are obtained along the monitoring time of the power equipment; if there are abnormal parameters in the working parameters, it is confirmed that the underground power equipment is in a fault state so as to improve the fault monitoring accuracy of the underground power equipment.
[0004] In order to solve the above technical problems, an embodiment of the present invention provides a fault confirmation method for underground power equipment, which is applied to underground power equipment;
[0005] The method for confirming the fault of underground power equipment comprises:
[0006] Obtain the underground area corresponding to the power equipment and monitor the moisture of the soil layer corresponding to the underground area;
[0007] Taking the power equipment as the center, the soil layer corresponding to the underground area is highly stratified, and the moisture coefficient of the soil layer around the power equipment is determined;
[0008] Constructing an environmental model for power equipment based on the height of the soil layer and the moisture coefficient of the soil layer;
[0009] Predict the failure time of power equipment based on the environmental model of the power equipment and the moisture resistance level of the power equipment;
[0010] Determine the monitoring time of the power equipment according to the failure time of the power equipment and the water inflow of the underground area within a preset time;
[0011] Acquiring operating parameters of the power equipment along the monitoring time of the power equipment;
[0012] If there are abnormal parameters in the working parameters, it is confirmed that the underground power equipment is in a fault state.
[0013] In addition, an embodiment of the present invention further provides a fault confirmation system for underground power equipment, the fault confirmation system for underground power equipment comprising:
[0014] An acquisition module is used to acquire the underground area corresponding to the power equipment and monitor the moisture of the soil layer corresponding to the underground area;
[0015] A stratification module is used to stratify the soil layers corresponding to the underground area with the power equipment as the center, and determine the moisture coefficient of the soil layer around the power equipment;
[0016] Environmental module, used to build environmental models of power equipment based on the height of the soil layer and the moisture coefficient of the soil layer;
[0017] A prediction module, used for predicting the failure time of the power equipment according to the environmental model of the power equipment and the moisture resistance level of the power equipment;
[0018] A time module, used to determine the monitoring time of the power equipment according to the failure time of the power equipment and the water inflow volume of the underground area within a preset time;
[0019] A parameter module, used for obtaining working parameters of the power equipment along the monitoring time of the power equipment;
[0020] The fault module is used to confirm that the underground power equipment is in a fault state if there are abnormal parameters in the working parameters.
[0021] In an embodiment of the present invention, through the method in the embodiment of the present invention, the underground area corresponding to the power equipment is obtained, and the moisture monitoring of the soil layer corresponding to the underground area is performed, and the soil layer corresponding to the underground area is highly stratified with the power equipment as the center, and the moisture coefficient of the soil layer around the power equipment is determined; based on the height of the soil layer and the moisture coefficient of the soil layer, an environmental model of the power equipment is constructed, so as to further perform fault monitoring on the power equipment in the underground environment through the environmental model of the power equipment, and predict the failure time of the power equipment according to the environmental model of the power equipment and the moisture resistance level of the power equipment. In order to further expand the predicted failure time, the monitoring time of the power equipment is determined according to the failure time of the power equipment and the water inflow of the underground area within a preset time. At this time, the working parameters of the power equipment are obtained along the monitoring time of the power equipment; if there are abnormal parameters in the working parameters, it is confirmed that the underground power equipment is in a fault state, so as to improve the fault monitoring accuracy of the underground power equipment, and at the same time, the dynamic monitoring of the underground power equipment is realized without affecting the underground environment where the underground power equipment is located. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0023] Figure 1 is a flow chart of a method for confirming a fault of underground power equipment in an embodiment of the present invention;
[0024] Figure 2 is a schematic diagram of the flow of S12 in the vehicle lighting in the embodiment of the present invention;
[0025] Figure 3 is a schematic diagram of the flow of S13 in the vehicle lighting in the embodiment of the present invention;
[0026] Figure 4 is a schematic diagram of the flow of S14 in the vehicle lighting in the embodiment of the present invention;
[0027] Figure 5 is a schematic diagram of the flow of S15 in the vehicle lighting in the embodiment of the present invention;
[0028] Figure 6 is a schematic diagram of the flow of S16 in the vehicle lighting in the embodiment of the present invention;
[0029] Figure 7 is a schematic diagram of the flow of S17 in the vehicle lighting in the embodiment of the present invention;
[0030] Figure 8 It is a schematic diagram of the structure of a fault confirmation system for underground power equipment in an embodiment of the present invention;
[0031] Fig. 9 The figure is a hardware diagram of an electronic device according to an exemplary embodiment. DETAILED DESCRIPTION
[0032] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0033] Example
[0034] See also Figures 1 to 9 , a method for confirming a fault of underground power equipment, applied to underground power equipment; the method for confirming a fault of underground power equipment comprises:
[0035] S11: Acquire the underground area corresponding to the power equipment, and monitor the moisture of the soil layer corresponding to the underground area;
[0036] In an embodiment of the present application, a mobile terminal is associated with an electric power device to obtain a positioning signal of the electric power device; a marked area of a map stored in the mobile terminal is determined based on the positioning signal to determine the underground area corresponding to the electric power device; the distance between the mobile terminal and the underground area is monitored, and a navigation path between the mobile terminal and the underground area is determined; the movement of a user using the mobile terminal is guided along the navigation path, and the soil layer corresponding to the underground area is calculated based on a soil moisture meter; and the soil layer corresponding to the underground area is monitored for moisture based on the moisture measurement of the soil layer.
[0037] Among them, communication between the mobile terminal and the power equipment is achieved through the association between the mobile terminal and the power equipment, and the relative position between the mobile terminal and the power equipment is determined along the communication between the mobile terminal and the power equipment, so as to use the mobile terminal to detect the position of the power equipment and obtain the positioning signal of the power equipment.
[0038] At this time, the marked area of the map stored in the mobile terminal is determined based on the positioning signal to determine the underground area corresponding to the power equipment; the distance between the mobile terminal and the underground area is monitored, and the navigation path between the mobile terminal and the underground area is determined, so that the navigation path is used to guide the user using the mobile terminal to move toward the underground area, thereby ensuring the accuracy of the area where the power equipment is located. At the same time, the movement of the user using the mobile terminal is guided along the navigation path, and the soil layer corresponding to the underground area is calculated based on the soil moisture meter; the soil layer corresponding to the underground area is monitored based on the moisture measurement of the soil layer, thereby realizing the monitoring of the soil layer corresponding to the underground area, so that the environmental factors of the power equipment can be controlled by moisture monitoring.
[0039] S12: Taking the power equipment as the center, the soil layer corresponding to the underground area is highly stratified, and the moisture coefficient of the soil layer around the power equipment is determined;
[0040] In an embodiment of the present application, the power equipment is taken as the center, and the underground area is highly stratified based on the power equipment. At this time, the soil layer corresponding to the underground area is highly stratified, and the moisture coefficient of the soil layer around the power equipment is determined, so as to control the environment of the power equipment according to the moisture coefficient of the soil layer around the power equipment, thereby determining the actual situation of the underground environment where the power equipment is located, and thus inferring the fault prediction time of the power equipment.
[0041] In the specific implementation process of the present invention, the specific steps may be:
[0042] S121: Performing signal sensing on the underground area corresponding to the power equipment, and determining the location of the power equipment in the underground area;
[0043] S122: determining the center of the power equipment based on the location of the power equipment in the underground area;
[0044] S123: Taking the power equipment as the center, the underground area is layered in the up and down direction. At this time, the soil layer corresponding to the underground area is layered in terms of moisture content;
[0045] In an embodiment of the present application, signal sensing is performed on the underground area corresponding to the power equipment, and the position of the power equipment in the underground area is determined, thereby dividing the underground area and the power equipment, and determining the center of the power equipment based on the position of the power equipment in the underground area; the underground area is stratified along the up and down directions with the power equipment as the center. At this time, the moisture content of the soil layer corresponding to the underground area is stratified, thereby realizing the presentation of the moisture content of the underground area where the power equipment is located, and further refining the surrounding environment of the power equipment to ensure the accuracy of the surrounding environment of the power equipment.
[0046] S124: Determine a moisture coefficient of a soil layer around the electric power equipment based on moisture amounts of different soil layers;
[0047] S125: estimating the influence coefficient of the soil around the power equipment according to the moisture coefficient of the soil layer around the power equipment;
[0048] S126: triggering drying control of the soil surrounding the power equipment based on the influence coefficient of the soil surrounding the power equipment;
[0049] In an embodiment of the present application, the moisture coefficient of the soil layer surrounding the power equipment is determined based on the moisture content of different soil layers, so as to mark the actual surrounding environment of the power equipment, so as to estimate the influence coefficient of the soil surrounding the power equipment according to the moisture coefficient of the soil layer surrounding the power equipment, thereby further limiting the influence of the soil surrounding the power equipment on the failure of the power equipment, and then triggering the drying control of the soil surrounding the power equipment based on the influence coefficient of the soil surrounding the power equipment, so as to realize the control of the surrounding soil based on the influence coefficient of the soil surrounding the power equipment, and affect the surrounding soil of the power equipment through drying control, so as to further reduce the failure of the power equipment and reduce the factors of the external environment.
[0050] S13: Constructing an environmental model of the power equipment based on the height of the soil layer and the moisture coefficient of the soil layer;
[0051] In an embodiment of the present application, an environmental model of the power equipment is constructed based on the height of the soil layer and the moisture coefficient of the soil layer, and the height of the soil layer and the moisture coefficient of the soil layer are used as two main factors of the environmental model of the power equipment, so that the environmental model of the power equipment is constructed based on these two main factors.
[0052] In the specific implementation process of the present invention, the specific steps may be:
[0053] S131: Obtain the height of the soil layer and the moisture coefficient of the soil layer;
[0054] S132: Construct the surrounding environment system of the power equipment along the height of the soil layer and the power equipment;
[0055] In an embodiment of the present application, the height of the soil layer and the moisture coefficient of the soil layer are obtained, and the height of the soil layer and the moisture coefficient of the soil layer are marked, so as to construct a surrounding environment system of the power equipment along the height of the soil layer and the power equipment, thereby reflecting the surrounding environment system of the power equipment. At this time, the surrounding environment system of the power equipment is mainly based on the surrounding environment of the power equipment, and further simulates the state of the power equipment in the underground environment according to the surrounding environment of the power equipment.
[0056] S133: Locate the impact position of the power equipment according to the surrounding environment system of the power equipment;
[0057] S134: determining a moisture coefficient of a corresponding soil layer according to an impact position of the electric power equipment;
[0058] S135: sequentially adding the moisture coefficient of the soil layer to the surrounding environment system of the power equipment, and calculating the change amount of the moisture coefficient of the soil layer along the height of the soil layer;
[0059] S136: Constructing an environmental model of the power equipment according to the change in the moisture coefficient of the soil layer and the moisture coefficient corresponding to the impact position of the power equipment.
[0060] In the embodiment of the present application, the influence position of the power equipment is located according to the surrounding environment system of the power equipment, and the influence position of the power equipment is further determined, so as to process the influence position of the power equipment. At this time, the moisture coefficient of the corresponding soil layer is determined for the influence position of the power equipment, and the moisture coefficient of the soil layer is further reflected. At this time, the moisture coefficient of the soil layer is sequentially added to the surrounding environment system of the power equipment, and the change in the moisture coefficient of the soil layer is calculated along the height of the soil layer; the environmental model of the power equipment is constructed according to the change in the moisture coefficient of the soil layer and the moisture coefficient corresponding to the influence position of the power equipment, so as to use the environmental model of the power equipment to further simulate the actual situation of the circuit equipment in the underground environment.
[0061] S14: predicting the failure time of the power equipment according to the environmental model of the power equipment and the moisture resistance level of the power equipment;
[0062] In an embodiment of the present application, the failure time of the power equipment is predicted based on the environmental model of the power equipment and the moisture resistance level of the power equipment, and a preliminary estimate of the failure time of the power equipment is made to facilitate further control of the failure time of the power equipment. At this time, the environmental model of the power equipment and the moisture resistance level of the power equipment serve as the two major factors for predicting the failure time of the power equipment.
[0063] In the specific implementation process of the present invention, the specific steps may be:
[0064] S141: Obtaining an external protective layer of the power equipment;
[0065] S142: Determine the moisture resistance level of the power equipment based on the waterproof level and material of the external protective layer;
[0066] In an embodiment of the present application, the external protective layer of the electric equipment is identified in order to obtain the external protective layer of the electric equipment, and then the moisture resistance level of the electric equipment is determined based on the external protective layer of the electric equipment, so as to determine the moisture resistance level of the electric equipment based on the waterproof level and material of the external protective layer, thereby realizing the grade evaluation of the electric equipment.
[0067] S143: Environmental model of associated power equipment and moisture resistance level of power equipment;
[0068] S144: inputting the environmental model of the power equipment and the moisture resistance level of the power equipment into the failure time learning model, and predicting the failure time of the power equipment;
[0069] S145: If the fault time of the electric equipment is less than the preset fault time, further extending the fault time of the electric equipment;
[0070] In an embodiment of the present application, the environmental model of the power equipment and the moisture resistance level of the power equipment are associated, and a comprehensive evaluation is performed on the environmental model of the power equipment and the moisture resistance level of the power equipment. At this time, the environmental model of the power equipment and the moisture resistance level of the power equipment are input into a fault time learning model, and the failure time of the power equipment is predicted, so as to realize the prediction of the failure time of the power equipment. In order to further ensure the accuracy of the failure time of the power equipment, at this time, the failure time of the power equipment is compared with the preset failure time. If the failure time of the power equipment is less than the preset failure time, the failure time of the power equipment is further widened, so as to improve the accuracy of the actual time point of the failure occurrence by widening the failure time of the power equipment, thereby further avoiding the omission of the actual time point of the failure occurrence based on the widening of the failure time of the power equipment.
[0071] The method of predicting the failure time of the power equipment based on the environmental model of the power equipment and the moisture resistance level of the power equipment also includes: if the failure time of the power equipment is inconsistent with the preset failure time, further widening the failure time of the power equipment; determining the increase in the failure time of the power equipment based on the degradation of the moisture resistance level of the power equipment; determining the superimposed failure time of the power equipment based on the failure time of the power equipment and the corresponding increase, so as to ensure that the failure time of the power equipment is greater than or equal to the preset failure time. Therefore, the superposition of the failure time of the power equipment reflects the range of the failure time of the power equipment, so as to control the time point of the failure of the power equipment within the range.
[0072] S15: Determine the monitoring time of the power equipment according to the failure time of the power equipment and the water inflow of the underground area within a preset time;
[0073] In an embodiment of the present application, the failure time of the power equipment and the amount of water inflow into the underground area within a preset time further limit the monitoring time of the power equipment. In order to further control external factors, especially weather changes in the underground area within a preset time, so as to further limit the amount of water inflow into the underground area within a preset time, at this time, the monitoring time of the power equipment is determined according to the failure time of the power equipment and the amount of water inflow into the underground area within a preset time, so as to consider multiple factors in the monitoring time of the power equipment, and fully consider the weather changes in the underground area within the preset time.
[0074] In the specific implementation process of the present invention, the specific steps may be:
[0075] S151: Obtaining the failure time of the power equipment;
[0076] S152: Calculating the water inflow of the underground area within a preset time based on the rain conditions corresponding to the underground area;
[0077] S153: adjusting the environmental model of the power equipment according to the water inflow into the underground area within a preset time, and determining the extended fault time according to the adjusted environmental model of the power equipment;
[0078] S154: Determine the monitoring time of the power equipment according to the failure time and the extended failure time of the power equipment.
[0079] In an embodiment of the present application, the fault time of the power equipment is obtained. At this time, the fault time of the power equipment is used as a preliminary fault time, not the actual fault time. In order to further limit the fault time, at this time, the water inflow of the underground area within a preset time is estimated based on the rain conditions corresponding to the underground area; the environmental model of the power equipment is adjusted according to the water inflow of the underground area within the preset time, and the extended fault time is determined according to the adjusted environmental model of the power equipment, so that the environmental model is adjusted according to the water inflow of the underground area within the preset time, so as to consider the weather impact in the environmental model, and the extended fault time is determined according to the adjusted environmental model of the power equipment, so as to determine the extended fault time and further superimpose the fault time. At the same time, the monitoring time of the power equipment is determined according to the fault time and the extended fault time of the power equipment.
[0080] S16: Acquiring operating parameters of the power equipment along the monitoring time of the power equipment;
[0081] In an embodiment of the present application, operating parameters of the power equipment are acquired along the monitoring time of the power equipment, and the operating status of the power equipment is monitored so that the operating status of the power equipment can be reflected through the operating parameters.
[0082] In the specific implementation process of the present invention, the specific steps may be:
[0083] S161: Obtain monitoring time of power equipment;
[0084] S162: triggering monitoring of the power equipment based on the monitoring time of the power equipment, and obtaining working parameters of the power equipment in real time;
[0085] S163: performing abnormality detection on the working parameters acquired by the electric power equipment, and forming a parameter set for the working parameters acquired by the electric power equipment;
[0086] S164: traversing data based on the parameter set and screening multiple parameters;
[0087] S165: Determine abnormal parameters based on multiple parameters.
[0088] In an embodiment of the present application, the monitoring time of the power equipment is obtained, the monitoring time of the power equipment is controlled, and the monitoring of the power equipment is triggered based on the monitoring time of the power equipment, and the working parameters of the power equipment are obtained in real time, so that the working parameters can be obtained in real time within the monitoring time of the power equipment, thereby forming a working parameter set, so that the working status of the power equipment can be reflected through the working parameter set.
[0089] In addition, anomaly detection is performed on the working parameters obtained by the power equipment, and a parameter set is formed for the working parameters obtained by the power equipment; data traversal is performed based on the parameter set, and multiple parameters are screened; abnormal parameters are determined based on multiple parameters, and then the abnormality of the power equipment is controlled, so that the abnormal parameters can be determined based on multiple parameters and further limited.
[0090] S17: If there are abnormal parameters in the working parameters, it is confirmed that the underground power equipment is in a fault state;
[0091] In an embodiment of the present application, the failure time of the power equipment is predicted based on the environmental model of the power equipment and the moisture resistance level of the power equipment. In order to further expand the predicted failure time, the monitoring time of the power equipment is determined based on the failure time of the power equipment and the amount of water inflow into the underground area within a preset time. At this time, the working parameters of the power equipment are obtained along the monitoring time of the power equipment; if there are abnormal parameters in the working parameters, it is confirmed that the underground power equipment is in a fault state, so as to improve the fault monitoring accuracy of the underground power equipment and realize dynamic monitoring of the underground power equipment without affecting the underground environment in which the underground power equipment is located.
[0092] In the specific implementation process of the present invention, the specific steps may be:
[0093] S171: If there are abnormal parameters in the working parameters, it is predicted that the underground power equipment is in a fault state;
[0094] S172: troubleshooting fault factors based on the fault status, and screening out fault areas of underground power equipment;
[0095] S173: Review and work individually based on the fault area of underground power equipment;
[0096] S174: Confirming that the underground power equipment is in a fault state based on the current working parameters of the fault area under review.
[0097] In an embodiment of the present application, if there are abnormal parameters in the working parameters, it is predicted that the underground power equipment is in a fault state. At this time, the fault state of the underground power equipment is reflected by the abnormal parameters, and the fault factors are checked based on the fault state, and the fault area of the underground power equipment is screened out to facilitate the determination of the fault area of the underground power equipment, so as to review the fault area of the underground power equipment and perform separate work; based on the current working parameters of the fault area during the review, it is confirmed that the underground power equipment is in a fault state.
[0098] In an embodiment of the present invention, through the method in the embodiment of the present invention, the underground area corresponding to the power equipment is obtained, and the moisture monitoring of the soil layer corresponding to the underground area is performed, and the soil layer corresponding to the underground area is highly stratified with the power equipment as the center, and the moisture coefficient of the soil layer around the power equipment is determined; based on the height of the soil layer and the moisture coefficient of the soil layer, an environmental model of the power equipment is constructed, so as to further perform fault monitoring on the power equipment in the underground environment through the environmental model of the power equipment, and predict the failure time of the power equipment according to the environmental model of the power equipment and the moisture resistance level of the power equipment. In order to further expand the predicted failure time, the monitoring time of the power equipment is determined according to the failure time of the power equipment and the water inflow of the underground area within a preset time. At this time, the working parameters of the power equipment are obtained along the monitoring time of the power equipment; if there are abnormal parameters in the working parameters, it is confirmed that the underground power equipment is in a fault state, so as to improve the fault monitoring accuracy of the underground power equipment, and at the same time, the dynamic monitoring of the underground power equipment is realized without affecting the underground environment where the underground power equipment is located.
[0099] Example
[0100] See also Figure 8 , Figure 8 It is a schematic diagram of the structure of a fault confirmation system for underground power equipment in an embodiment of the present invention.
[0101] like Figure 8 As shown, a fault confirmation system for underground power equipment, the fault confirmation system for underground power equipment comprises:
[0102] The acquisition module 21 is used to acquire the underground area corresponding to the power equipment and monitor the moisture of the soil layer corresponding to the underground area;
[0103] The stratification module 22 is used to stratify the soil layers corresponding to the underground area with the power equipment as the center, and determine the moisture coefficient of the soil layer around the power equipment;
[0104] An environmental module 23, for constructing an environmental model of the power equipment based on the height of the soil layer and the moisture coefficient of the soil layer;
[0105] A prediction module 24, used to predict the failure time of the power equipment according to the environmental model of the power equipment and the moisture resistance level of the power equipment;
[0106] The time module 25 is used to determine the monitoring time of the power equipment according to the failure time of the power equipment and the water inflow of the underground area within a preset time;
[0107] A parameter module 26, used for obtaining operating parameters of the power equipment along the monitoring time of the power equipment;
[0108] The fault module 27 is used to confirm that the underground power equipment is in a fault state if there are abnormal parameters in the working parameters.
[0109] Example
[0110] See also Fig. 9 , refer to the following Fig. 9 The electronic device 40 according to this embodiment of the present invention will be described. Fig. 9 The electronic device 40 shown is only an example and should not bring any limitation to the functions and scope of use of the embodiments of the present invention.
[0111] like Fig. 9 As shown, the electronic device 40 is in the form of a general computing device. The components of the electronic device 40 may include but are not limited to: at least one processing unit 41, at least one storage unit 42, and a bus 43 connecting different system components (including the storage unit 42 and the processing unit 41).
[0112] The storage unit stores program codes, which can be executed by the processing unit 41, so that the processing unit 41 executes the steps according to various exemplary embodiments of the present invention described in the above “Embodiment Method” section of this specification.
[0113] The storage unit 42 may include a readable medium in the form of a volatile storage unit, such as a random access memory unit (RAM) 421 and / or a cache memory unit 422 , and may further include a read-only memory unit (ROM) 423 .
[0114] The storage unit 42 may also include a program / utility 424 having a set (at least one) of program modules 425, such program modules 425 including but not limited to: an operating system, one or more application programs, other program modules, and program data, each of which or some combination may include an implementation of a network environment.
[0115] Bus 43 may represent one or more of several types of bus structures, including a memory unit bus or memory unit controller, a peripheral bus, an accelerated graphics port, a processing unit, or a local bus using any of a variety of bus architectures.
[0116] The electronic device 40 may also communicate with one or more external devices (e.g., keyboards, pointing devices, Bluetooth devices, etc.), one or more devices that enable a user to interact with the electronic device 40, and / or any device that enables the electronic device 40 to communicate with one or more other computing devices (e.g., routers, modems, etc.). Such communication may be performed via an input / output (I / O) interface 44. Furthermore, the electronic device 40 may also communicate with one or more networks (e.g., a local area network (LAN), a wide area network (WAN), and / or a public network, such as the Internet) via a network adapter 45. Fig. 9 As shown, the network adapter 45 communicates with other modules of the electronic device 40 via the bus 43. It should be understood that although Fig. 9 Not shown, other hardware and / or software modules may be used in conjunction with the electronic device 40, including but not limited to: microcode, device drivers, redundant processing units, external disk drive arrays, RAID systems, tape drives, and data backup planning systems.
[0117] Through the description of the above implementation, it is easy for those skilled in the art to understand that the example implementation described here can be implemented by software, or by software combined with necessary hardware. Therefore, the technical solution according to the implementation of the present disclosure can be embodied in the form of a software product, which can be stored in a non-volatile storage medium (which can be a CD-ROM, a USB flash drive, a mobile hard disk, etc.) or on a network, including several instructions to enable a computing device (which can be a personal computer, a server, a terminal device, or a network device, etc.) to execute the method according to the implementation of the present disclosure.
[0118] Those skilled in the art can understand that all or part of the steps in the various methods of the above embodiments can be completed by instructing related hardware through a program, and the program can be stored in a computer-readable storage medium, and the storage medium can include: a read-only memory (ROM), a random access memory (RAM), a disk or an optical disk, etc. In addition, it stores computer program instructions, and when the computer program instructions are executed by a computer, the computer executes the above method.
[0119] In addition, the above describes in detail the fault confirmation method and system for underground power equipment provided in the embodiments of the present invention. Specific examples are used herein to illustrate the principles and implementation methods of the present invention. The description of the above embodiments is only used to help understand the method of the present invention and its core idea. At the same time, for those skilled in the art, according to the ideas of the present invention, there will be changes in the specific implementation methods and application scopes. In summary, the content of this specification should not be understood as a limitation on the present invention.
Claims
1. A method for confirming a fault of underground power equipment, characterized in that: Applied to underground power equipment; The method for confirming the fault of underground power equipment comprises: Obtain the underground area corresponding to the power equipment and monitor the moisture of the soil layer corresponding to the underground area; Taking the power equipment as the center, the soil layer corresponding to the underground area is highly stratified, and the moisture coefficient of the soil layer around the power equipment is determined; Constructing an environmental model for power equipment based on the height of the soil layer and the moisture coefficient of the soil layer; Predict the failure time of power equipment based on the environmental model of the power equipment and the moisture resistance level of the power equipment; Determine the monitoring time of the power equipment according to the failure time of the power equipment and the water inflow of the underground area within a preset time; Acquiring operating parameters of the power equipment along the monitoring time of the power equipment; If there are abnormal parameters in the working parameters, it is confirmed that the underground power equipment is in a fault state; The method of stratifying the soil layer corresponding to the underground area with the power equipment as the center and determining the moisture coefficient of the soil layer around the power equipment includes: Perform signal sensing on the underground area corresponding to the power equipment and determine the location of the power equipment in the underground area; determining a center of the electrical equipment based on the location of the electrical equipment in the underground area; Taking the power equipment as the center, the underground area is layered in the up and down directions. At this time, the moisture content of the soil layer corresponding to the underground area is layered; Determining a moisture coefficient of a soil layer around the power equipment based on moisture amounts of different soil layers; Estimate the influence coefficient of the soil around the power equipment according to the moisture coefficient of the soil layer around the power equipment; triggering drying control of the soil around the power equipment based on the influence coefficient of the soil around the power equipment; The environmental model of the power equipment is constructed based on the height of the soil layer and the moisture coefficient of the soil layer, including: Get the height of the soil layer and the moisture coefficient of the soil layer; Construct the surrounding environment system of the power equipment along the height of the soil layer and the power equipment; Locate the impact position of the power equipment according to the surrounding environment system of the power equipment; Determine the moisture coefficient of the corresponding soil layer according to the impact position of the power equipment; The moisture coefficient of the soil layer is sequentially added to the surrounding environment system of the power equipment, and the change of the moisture coefficient of the soil layer is measured along the height of the soil layer; The environmental model of the power equipment is constructed according to the change of the moisture coefficient of the soil layer and the moisture coefficient corresponding to the impact position of the power equipment; The method of predicting the failure time of the electric equipment according to the environmental model of the electric equipment and the moisture resistance level of the electric equipment comprises: Obtaining the outer protective layer of electrical equipment; Determine the moisture resistance level of the power equipment based on the waterproof level and material of the external protective layer; Correlate the environmental model of the power equipment and the moisture resistance level of the power equipment; Input the environmental model of the power equipment and the moisture resistance level of the power equipment into the failure time learning model, and predict the failure time of the power equipment; If the fault time of the power equipment is less than the preset fault time, the fault time of the power equipment is further extended; The predicting of the failure time of the electric equipment according to the environmental model of the electric equipment and the moisture resistance level of the electric equipment also includes: If the fault time of the power equipment is inconsistent with the preset fault time, the fault time of the power equipment is further extended; Determining an increase in failure time of the electric equipment based on a degradation in moisture resistance level of the electric equipment; Determine the superimposed failure time of the electric equipment based on the failure time of the electric equipment and the corresponding increase, so as to ensure that the failure time of the electric equipment is greater than or equal to the preset failure time; Determining the monitoring time of the power equipment according to the fault time of the power equipment and the water inflow volume of the underground area within a preset time includes: Obtain the failure time of power equipment; Calculate the water inflow of the underground area within a preset time based on the corresponding rainfall conditions of the underground area; adjusting an environmental model of the power equipment according to the amount of water inflow into the underground area within a preset time, and determining an extended fault time based on the adjusted environmental model of the power equipment; The monitoring time of the power equipment is determined according to the failure time and the extended failure time of the power equipment.
2. The method for confirming the fault of underground power equipment according to claim 1, characterized in that: The obtaining of the underground area corresponding to the electric power equipment and monitoring the moisture of the soil layer corresponding to the underground area includes: Associating the mobile terminal with the power equipment and obtaining the positioning signal of the power equipment; Determine a marked area on a map stored in the mobile terminal based on the positioning signal to determine the underground area corresponding to the power equipment; monitoring the distance between the mobile terminal and the underground area, and determining a navigation path between the mobile terminal and the underground area; Guide the movement of the user using the mobile terminal along the navigation path, and calculate the soil layer corresponding to the underground area based on the soil moisture meter; The moisture content of the soil layer corresponding to the underground area is monitored based on the moisture measurement of the soil layer.
3. The method for confirming the fault of underground power equipment according to claim 2, characterized in that: The obtaining of operating parameters of the electric power equipment along the monitoring time of the electric power equipment includes: Get the monitoring time of power equipment; Trigger the monitoring of the power equipment based on the monitoring time of the power equipment, and obtain the working parameters of the power equipment in real time; Performing abnormal detection on the working parameters acquired by the power equipment and forming a parameter set for the working parameters acquired by the power equipment; Traverse data based on parameter sets and filter multiple parameters; An abnormal parameter is determined based on a plurality of parameters.
4. The method for confirming the fault of underground power equipment according to claim 3, characterized in that: If there are abnormal parameters in the working parameters, confirming that the underground power equipment is in a fault state includes: If there are abnormal parameters in the working parameters, it is predicted that the underground power equipment is in a fault state; Conduct fault factor investigation based on the fault status and screen out the fault area of underground power equipment; Review and work individually according to the fault area of underground power equipment; It is confirmed that the underground power equipment is in a fault state based on the current operating parameters of the fault area under review.
5. A fault confirmation system for underground power equipment, characterized in that: The underground power equipment fault confirmation system is applied to the underground power equipment fault confirmation method according to any one of claims 1 to 4, and the underground power equipment fault confirmation system comprises: An acquisition module is used to acquire the underground area corresponding to the power equipment and monitor the moisture of the soil layer corresponding to the underground area; A stratification module is used to stratify the soil layers corresponding to the underground area with the power equipment as the center, and determine the moisture coefficient of the soil layer around the power equipment; Environmental module, used to build environmental model of power equipment based on the height of soil layer and moisture coefficient of soil layer; A prediction module, used for predicting the failure time of the power equipment according to the environmental model of the power equipment and the moisture resistance level of the power equipment; A time module, used to determine the monitoring time of the power equipment according to the failure time of the power equipment and the water inflow volume of the underground area within a preset time; A parameter module, used for obtaining working parameters of the power equipment along the monitoring time of the power equipment; The fault module is used to confirm that the underground power equipment is in a fault state if there are abnormal parameters in the working parameters.
Citation Information
Patent Citations
Power supply emergency repair environment monitoring method and system for guaranteeing life safety
CN116777088A
KR20220085213A