State evaluation and analysis method and trend warning system for tubular units
By collecting and analyzing the working parameters of the rotor chamber, gear box and generator in the flow turbine unit, determining the adapter package and reaction time interval, the failure to fully consider the changes and trend relationship of the unit parameter in the prior art is solved. The problem has achieved more accurate and comprehensive general state analysis and trend warning.
Patent Information
- Application Number
- CN202311440860.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-11-01
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2043-11-01
AI Technical Summary
The prior art failed to fully consider the changes in the entire process parameters and trend relationship of the unit in the state analysis of the through-flow turbine unit, resulting in problems with the trend warning accuracy.
By collecting the working parameters of the rotor chamber, gear box and generator in the state trend warning system of the flow unit, performing periodic storage and change trend analysis, determining the adaptation package and reaction time interval between each component, in real time Analyze the climbing trend of transmission and power generation efficiency, generate processing signals and provide early warnings.
It improves the accuracy and comprehensiveness of transmission parameter analysis between components, ensures the accuracy of unit status analysis and trend warning, and enhances the consideration of component aging factors.
Smart Images

Figure CN117491008B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of status monitoring of tubular units, and in particular to a status evaluation and analysis method and a trend warning system for tubular units. Background Art
[0002] The tubular turbine unit is a horizontal-shaft turbine, that is, the water flow in the flow channel basically moves along the horizontal axis; it is mainly suitable for heads of 1 to 25m, and is a special type of machine for low-head, large-flow hydropower stations; because its water flow in the flow channel basically moves along the axial direction without turning, the unit's water-passing capacity and hydraulic efficiency can be improved.
[0003] The patent application with the publication number CN112818525A discloses a method for evaluating the status of a hydropower unit. It uses big data technology and cloud theory combined with the analytic hierarchy process to evaluate the current operating status of the unit under the condition of known historical healthy operating data of the unit; it evaluates the current operating status of the unit by calculation, and combines the corresponding maintenance criteria to facilitate the implementation of the unit status maintenance. The present invention also provides a hydropower unit status evaluation system, which realizes the status evaluation of the hydropower unit through nine modules: data reading and storage module, working condition differentiation module, big data statistics module, cloud theory module, expert scoring module, analytic hierarchy process module, entropy weight method module, weight fusion module, evaluation result and maintenance strategy module.
[0004] During the operation of a tubular turbine unit, there is a corresponding linkage relationship between each component. During the linkage process, there will be a driving relationship and a driving time. The previous status analysis only conducted normal analysis on a single component to determine whether its value is normal. However, this method is not comprehensive and does not take into account the parameter changes of the unit throughout the entire process and the trend relationship between them, resulting in certain accuracy problems in trend warnings. Summary of the invention
[0005] In view of the deficiencies in the prior art, the present invention provides a method for evaluating and analyzing the state of a cross-flow unit and a trend warning system, which solves the problem that the entire process parameter changes of the unit and the trend relationship between them are not taken into account, resulting in a certain accuracy problem in the trend warning.
[0006] To achieve the above objectives, the present invention is implemented through the following technical solutions: a state trend warning system for a tubular unit, comprising:
[0007] The unit data collection end collects the operating parameters generated by the impeller chamber, gearbox and generator inside the crossflow unit, wherein the operating parameters include the speed parameter of the impeller chamber, the transmission speed parameter of the gearbox and the power generation efficiency of the generator, wherein the collected operating parameters are transmitted to the database and the first-order data analysis end respectively;
[0008] The database stores the collected working parameters periodically and updates them regularly. When the time limit of the stored working parameters exceeds 72 hours, they are automatically deleted and not saved.
[0009] The change trend analysis terminal performs change trend analysis on the working parameters stored in the database. The specific method is as follows:
[0010] A step threshold X1 is defined, where X1 is a preset value, generally 100 r / min, and several working parameters generated by the runner chamber are classified into intervals, with X1 as a dividing point, so that the speed parameters are classified into parameters of several different intervals, wherein several intervals are as follows: (0, X1], (X1, 2X1], (2X1, 3X1], ..., etc.;
[0011] Determine the climbing trend between different speed parameters in the runner room and the corresponding transmission rate parameters of the gear box in the interval (0, X1], determine the maximum climbing rate and the minimum climbing rate between the speed parameters, and generate a speed climbing interval, then determine the maximum climbing rate and the minimum climbing rate between the transmission rate parameters of the gear box, and generate a corresponding transmission climbing interval, and record the time points of the first group of climbing points of the runner room, then determine the time point when the gear box starts to climb, determine the reaction time through the two groups of time points, and then determine other climbing points, determine the minimum value and the maximum value from a number of reaction times, so as to lock the first-order reaction time interval between the runner room and the gear box in this single interval;
[0012] Then, the working parameters between the gearbox and the generator are determined in the interval (0, X1], and the power generation climbing interval of the generator working parameters is determined according to the determined transmission climbing interval of the gearbox in the same manner as above. At the same time, the second-order reaction time interval between the gearbox and the generator is confirmed in the same manner as above, and the speed climbing interval, the first-order reaction time interval, the transmission climbing interval, the second-order reaction time interval and the power generation climbing interval generated in the interval (0, X1] are taken as a set of adaptation packages;
[0013] Then determine the working parameters in other single intervals to generate several groups of different adaptation packages;
[0014] The unit data acquisition end transmits the real-time collected working parameters to the first-order data analysis end, where the first-order data analysis end analyzes the transmission data between the runner room and the gearbox to determine whether the transmission between the runner room and the gearbox is normal and generates a processing signal. The specific method is as follows:
[0015] According to the speed parameter of the runner room, determine the range to which this speed parameter belongs, then lock the corresponding adaptation package to confirm whether this speed parameter belongs to the climbing parameter. If this speed parameter is larger than the previous time point, then this speed parameter is a climbing parameter and the next step is executed. Otherwise, no processing is performed.
[0016] Analyze the time difference between the start of the runner chamber speed parameter climbing and the start of the gearbox internal transmission rate parameter climbing in this stage, calibrate this time difference as SC, and analyze whether SC satisfies: SC∈first-order reaction time interval. If this condition is met:
[0017] Analyze whether the rising trend of the runner room speed parameter belongs to the speed rising range. If it belongs to the speed rising range:
[0018] Determine whether the climbing trend of the gearbox transmission rate parameter belongs to the transmission climbing interval. If so, execute the second-order data analysis end. If not, generate a gearbox transmission abnormality signal and transmit it to the early warning end.
[0019] If it does not belong to the speed climbing range, continue monitoring;
[0020] If the SC does not meet the corresponding conditions, a gearbox response abnormality signal is generated and transmitted to the early warning terminal;
[0021] The second-order data analysis end analyzes the working parameters between the gearbox and the generator, determines whether the parameters between the gearbox and the generator are normal, and generates a processing signal. The specific method is as follows:
[0022] Determine the adaptation package according to the determined interval, confirm the time difference when the internal transmission rate parameter of the gearbox starts to climb and the internal power generation efficiency of the generator starts to climb in this stage, calibrate this time difference as SS, and analyze whether SS satisfies: SS∈second-order reaction time interval. If this condition is met:
[0023] Then analyze whether the rising trend of the internal power generation efficiency of the generator belongs to the power generation rising interval. If so, no processing is performed. If not, a generator power generation abnormality signal is generated and transmitted to the early warning terminal.
[0024] like In the second-order reaction time interval, a generator reaction abnormality signal is generated and transmitted to the early warning terminal.
[0025] Preferably, the early warning end performs early warning processing according to the received processing signal and directly displays it for external personnel to view, wherein the processing signal includes a gearbox transmission abnormality signal, a gearbox reaction abnormality signal, a generator power generation abnormality signal and a generator reaction abnormality signal.
[0026] Preferably, the method for evaluating and analyzing the status of a tubular unit comprises the following steps:
[0027] Step 1: Collect the operating parameters of the runner chamber, gearbox and generator inside the tubular unit, and determine the adaptation packages generated between different intervals by analyzing the past operating parameters;
[0028] Step 2: The real-time operating parameters are collected through the unit data collection terminal, and the data is analyzed through the first-order data analysis terminal to determine whether the transmission between the runner room and the gearbox is normal, and a processing signal is generated and transmitted to the early warning terminal;
[0029] Step 3: When the runner room and the gearbox are both normal, analyze the working parameters between the gearbox and the generator to determine whether the parameters between the gearbox and the generator are normal, generate a processing signal, and transmit it to the early warning terminal;
[0030] Step 4: The early warning terminal displays a timely warning based on the abnormal signal received, so that external personnel can view it and take corresponding measures in time.
[0031] The present invention provides a method for evaluating and analyzing the status of a tubular unit and a trend warning system. Compared with the prior art, it has the following beneficial effects:
[0032] The present invention confirms and analyzes the transmission parameters between the components through the linkage relationship existing inside the tubular unit, and generates an adaptation package of the components interrelated with each other, whose values are updated in real time, taking into account the factors of component aging, so that the standard adaptation package is more accurate, and the accuracy of trend warning in the later stage is higher;
[0033] By analyzing and determining layer by layer, it is determined whether the components with transmission relationships are working normally. If the component in front is abnormal, the component in the rear does not need to be analyzed, and the values it produces must be abnormal. If the parameters of the component in front are normal, then the analysis is carried out backward to lock the corresponding parameter changes, so as to determine whether the parameters of the component in the rear are normal. By changing the original state analysis method and taking into account the transmission change trend between components, the analysis values are more comprehensive and accurate, thereby ensuring the comprehensiveness of the unit state analysis. BRIEF DESCRIPTION OF THE DRAWINGS
[0034] Figure 1 It is a schematic diagram of the principle framework of the present invention;
[0035] Figure 2 The figure is a schematic diagram of the process flow of the method of the present invention. DETAILED DESCRIPTION
[0036] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0037] Embodiment 1
[0038] See also Figure 1 , the present application provides a status trend warning system for a tubular unit, including a unit data acquisition terminal, a database, a change trend analysis terminal, a first-order data analysis terminal, a second-order data analysis terminal and a warning terminal;
[0039] The unit data acquisition terminal is electrically connected to the database and the first-order data analysis terminal input node respectively, wherein the database, the change trend analysis terminal and the first-order data analysis terminal are electrically connected from the output node to the input node in sequence, wherein the change trend analysis terminal is electrically connected to the second-order data analysis terminal input node, and the first-order data analysis terminal and the second-order data analysis terminal are both electrically connected to the early warning terminal input node;
[0040] The unit data collection end collects the operating parameters generated by the impeller chamber, gearbox and generator inside the crossflow unit, wherein the operating parameters include the speed parameter of the impeller chamber, the transmission speed parameter of the gearbox and the power generation efficiency of the generator, wherein the collected operating parameters are respectively transmitted to the database and the first-order data analysis end. Specifically, the collected unit data are all determined by sensors arranged in different areas of the unit, and the specific values determined are all parameters generated in real time;
[0041] The database periodically stores and regularly updates the collected working parameters. When the time limit of the stored working parameters exceeds 72 hours, they are automatically deleted and not saved.
[0042] The change trend analysis end performs change trend analysis on the working parameters stored in the database, wherein the working parameters are the working parameters 5 minutes before the current moment, locks the adaptation change trends generated between the runner room, the gear box and the generator, and bundles the locked adaptation change trends into a group of adaptation packages, and uses the bundled several adaptation packages as standard packages for extraction by the first-order data analysis end and the second-order data analysis end, wherein the specific method of performing the change trend analysis is:
[0043] A step threshold X1 is defined, where X1 is a preset value, generally 100 r / min, and several working parameters generated by the runner chamber are classified into intervals, with X1 as a dividing point, so that the speed parameters are classified into parameters of several different intervals, wherein several intervals are as follows: (0, X1], (X1, 2X1], (2X1, 3X1], ..., etc.;
[0044] Determine the climbing trend between different speed parameters in the runner room and the corresponding transmission rate parameters of the gear box in the interval (0, X1], determine the maximum climbing rate and the minimum climbing rate between the speed parameters, and generate a speed climbing interval, then determine the maximum climbing rate and the minimum climbing rate between the transmission rate parameters of the gear box, and generate a corresponding transmission climbing interval, and record the time points of the first group of climbing points of the runner room, then determine the time point when the gear box starts to climb, determine the reaction time through the two groups of time points, and then determine other climbing points, determine the minimum value and the maximum value from a number of reaction times, so as to lock the first-order reaction time interval between the runner room and the gear box in this single interval;
[0045] Then, the working parameters between the gearbox and the generator are determined in the interval (0, X1], and the power generation climbing interval of the generator working parameters is determined according to the determined transmission climbing interval of the gearbox in the same manner as above. At the same time, the second-order reaction time interval between the gearbox and the generator is confirmed in the same manner as above, and the speed climbing interval, the first-order reaction time interval, the transmission climbing interval, the second-order reaction time interval and the power generation climbing interval generated in the interval (0, X1] are taken as a set of adaptation packages;
[0046] Then determine the working parameters in other single intervals to generate several groups of different adaptation packages;
[0047] Specifically, the specific transmission method of the cross-flow unit is: the external water source drives the impeller inside the impeller chamber to rotate, and then the rotation drives the gear inside the gear box to transmit, and the driven rod drives the generator to generate electricity. Therefore, there is a linkage relationship between the three, and there is a corresponding reaction time in the linkage process. Due to the aging of the working components in the cross-flow unit, it is necessary to fully consider the update of the data. Past data cannot be a good pending standard. Existing data can be used as a standard reference. When transmission is carried out, when the previous transmission component starts to transmit, there will be a transmission rate, thereby driving the subsequent transmission components to transmit, and their changing trends are corresponding.
[0048] Combination Figure 2The unit data acquisition end transmits the real-time collected working parameters to the first-order data analysis end, where the first-order data analysis end analyzes the transmission data between the runner room and the gearbox to determine whether the transmission between the runner room and the gearbox is normal, and generates a processing signal to transmit to the early warning end. The specific method for determining whether the transmission between the runner room and the gearbox is normal is as follows:
[0049] According to the speed parameter of the runner room, determine the range to which this speed parameter belongs, then lock the corresponding adaptation package to confirm whether this speed parameter belongs to the climbing parameter. If this speed parameter is larger than the previous time point, then this speed parameter is a climbing parameter and the next step is executed. Otherwise, no processing is performed.
[0050] Analyze the time difference between the start of the runner chamber speed parameter climbing and the start of the gearbox internal transmission rate parameter climbing in this stage, calibrate this time difference as SC, and analyze whether SC satisfies: SC∈first-order reaction time interval. If this condition is met:
[0051] Analyze whether the rising trend of the runner room speed parameter belongs to the speed rising range. If it belongs to the speed rising range:
[0052] Determine whether the climbing trend of the gearbox transmission rate parameter belongs to the transmission climbing interval. If so, execute the second-order data analysis end. If not, generate a gearbox transmission abnormality signal and transmit it to the early warning end.
[0053] If it does not belong to the speed climbing range, continue monitoring;
[0054] If the SC does not meet the corresponding conditions, a gearbox response abnormality signal is generated and transmitted to the early warning terminal.
[0055] Embodiment 2
[0056] In the specific implementation process, compared with the first embodiment, the specific difference of this embodiment is that this embodiment is mainly aimed at the secondary implementation process, and its specific implementation method is as follows:
[0057] The second-order data analysis end analyzes the working parameters between the gearbox and the generator, determines whether the parameters between the gearbox and the generator are normal, and generates a processing signal, which is transmitted to the early warning end. The specific method for determining whether the transmission between the runner chamber and the gearbox is normal is as follows:
[0058] Determine the adaptation package according to the determined interval, confirm the time difference when the internal transmission rate parameter of the gearbox starts to climb and the internal power generation efficiency of the generator starts to climb in this stage, calibrate this time difference as SS, and analyze whether SS satisfies: SS∈second-order reaction time interval. If this condition is met:
[0059] Then analyze whether the rising trend of the internal power generation efficiency of the generator belongs to the power generation rising interval. If so, no processing is performed. If not, a generator power generation abnormality signal is generated and transmitted to the early warning terminal.
[0060] like In the second-order reaction time interval, a generator reaction abnormality signal is generated and transmitted to the early warning terminal.
[0061] The early warning end performs early warning processing according to the received processing signal and directly displays it for external personnel to view, wherein the processing signal includes a gearbox transmission abnormality signal, a gearbox reaction abnormality signal, a generator power generation abnormality signal and a generator reaction abnormality signal.
[0062] Specifically, by analyzing and determining layer by layer, it is determined whether the components with transmission relationship are working normally. If the front component is abnormal, the rear component does not need to be analyzed, and the value generated must be abnormal. If the parameters of the front component are normal parameters, then the analysis is carried out backward to lock the corresponding parameter changes, so as to determine whether the parameters of the rear component are normal. If the parameters are normal, it means that the cross-flow unit is working normally. If it is abnormal, the corresponding signal can be directly generated.
[0063] By changing the original state analysis method and considering the transmission change trend between components, the analysis values are more comprehensive and accurate, thus ensuring the comprehensiveness of the unit state analysis.
[0064] Embodiment 3
[0065] The state evaluation and analysis method of a tubular unit comprises the following steps:
[0066] Step 1: Collect the operating parameters of the runner chamber, gearbox and generator inside the tubular unit, and determine the adaptation packages generated between different intervals by analyzing the past operating parameters;
[0067] Step 2: The real-time operating parameters are collected through the unit data collection terminal, and the data is analyzed through the first-order data analysis terminal to determine whether the transmission between the runner room and the gearbox is normal, and a processing signal is generated and transmitted to the early warning terminal;
[0068] Step 3: When the runner room and the gearbox are both normal, analyze the working parameters between the gearbox and the generator to determine whether the parameters between the gearbox and the generator are normal, generate a processing signal, and transmit it to the early warning terminal;
[0069] Step 4: The early warning terminal displays a timely warning based on the abnormal signal received, so that external personnel can view it and take corresponding measures in time.
[0070] Embodiment 4
[0071] The specific implementation process of this embodiment includes all the implementation processes of the above three groups of embodiments.
[0072] Some of the data in the above formulas are numerically calculated by removing their dimensions. Meanwhile, the contents not described in detail in this specification belong to the prior art known to those skilled in the art.
[0073] The above embodiments are only used to illustrate the technical method of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical method of the present invention may be modified or replaced by equivalents without departing from the spirit and scope of the technical method of the present invention.
Claims
1. The status trend warning system of the tubular unit is characterized by: include: The unit data collection end collects the operating parameters generated by the impeller chamber, gearbox and generator inside the crossflow unit, wherein the operating parameters include the speed parameter of the impeller chamber, the transmission speed parameter of the gearbox and the power generation efficiency of the generator, wherein the collected operating parameters are transmitted to the database and the first-order data analysis end respectively; The database stores the collected working parameters periodically and updates them regularly. When the time limit of the stored working parameters exceeds 72 hours, they are automatically deleted and not saved. The change trend analysis end performs change trend analysis on the working parameters stored in the database. The working parameters are the working parameters 5 minutes before this moment. The adaptation change trends generated between the runner room, gearbox and generator are locked, and the locked adaptation change trends are bundled into a set of adaptation packages. The bundled adaptation packages are used as standard packages for extraction by the first-order data analysis end and the second-order data analysis end. The specific method is as follows: A step threshold X1 is defined, where X1 is a preset value, which is 100 r / min. Several working parameters generated by the runner chamber are classified into intervals, and X1 is used as a dividing point to classify the speed parameters into parameters of several different intervals, wherein the several intervals include: (0, X1], (X1, 2X1], (2X1, 3X1], ...; Determine the climbing trend between different speed parameters in the runner room and the corresponding transmission rate parameters of the gear box in the interval (0, X1], determine the maximum climbing rate and the minimum climbing rate between the speed parameters, and generate a speed climbing interval, then determine the maximum climbing rate and the minimum climbing rate between the transmission rate parameters of the gear box, and generate a corresponding transmission climbing interval, and record the time points of the first group of climbing points of the runner room, then determine the time point when the gear box starts to climb, determine the reaction time through the two groups of time points, and then determine other climbing points, determine the minimum value and the maximum value from a number of reaction times, so as to lock the first-order reaction time interval between the runner room and the gear box in this single interval; Then, the working parameters between the gearbox and the generator are determined in the interval (0, X1], and the power generation climbing interval of the generator working parameters is determined according to the determined transmission climbing interval of the gearbox in the same manner as above. At the same time, the second-order reaction time interval between the gearbox and the generator is confirmed in the same manner as above, and the speed climbing interval, the first-order reaction time interval, the transmission climbing interval, the second-order reaction time interval and the power generation climbing interval generated in the interval (0, X1] are taken as a set of adaptation packages; Then determine the working parameters in other single intervals to generate several groups of different adaptation packages; The unit data acquisition end transmits the real-time collected working parameters to the first-order data analysis end, where the first-order data analysis end analyzes the transmission data between the runner room and the gearbox to determine whether the transmission between the runner room and the gearbox is normal, and generates a processing signal and transmits it to the early warning end; The second-order data analysis end analyzes the working parameters between the gearbox and the generator, determines whether the parameters between the gearbox and the generator are normal, generates a processing signal, and transmits it to the early warning end.
2. The tubular unit status trend warning system according to claim 1, characterized in that: The first-order data analysis end determines whether the transmission between the runner chamber and the gear box is normal in the following specific manner: According to the speed parameter of the runner room, determine the range to which this speed parameter belongs, then lock the corresponding adaptation package to confirm whether this speed parameter belongs to the climbing parameter. If this speed parameter is larger than the previous time point, then this speed parameter is a climbing parameter and the next step is executed. Otherwise, no processing is performed. Analyze the time difference between the start of the runner chamber speed parameter climbing and the start of the gearbox internal transmission rate parameter climbing in this stage, calibrate this time difference as SC, and analyze whether SC satisfies: SC∈first-order reaction time interval. If this condition is met: Analyze whether the rising trend of the runner room speed parameter belongs to the speed rising range. If it belongs to the speed rising range: Determine whether the climbing trend of the gearbox transmission rate parameter belongs to the transmission climbing interval. If so, execute the second-order data analysis end. If not, generate a gearbox transmission abnormality signal and transmit it to the early warning end. If it does not belong to the speed climbing range, continue monitoring; If the SC does not meet the corresponding conditions, a gearbox response abnormality signal is generated and transmitted to the early warning terminal.
3. The tubular unit status trend warning system according to claim 1, characterized in that: The specific method of determining whether the transmission between the runner chamber and the gear box is normal at the second-order data analysis end is: Determine the adaptation package according to the determined interval, confirm the time difference when the internal transmission rate parameter of the gearbox starts to climb and the internal power generation efficiency of the generator starts to climb in this stage, calibrate this time difference as SS, and analyze whether SS satisfies: SS∈second-order reaction time interval. If this condition is met: Then analyze whether the rising trend of the internal power generation efficiency of the generator belongs to the power generation rising interval. If so, no processing is performed. If not, a generator power generation abnormality signal is generated and transmitted to the early warning terminal. like In the second-order reaction time interval, a generator reaction abnormality signal is generated and transmitted to the early warning terminal.
4. The tubular unit status trend warning system according to claim 1, characterized in that: The early warning end performs early warning processing according to the received processing signal and directly displays it for external personnel to view, wherein the processing signal includes a gearbox transmission abnormality signal, a gearbox reaction abnormality signal, a generator power generation abnormality signal and a generator reaction abnormality signal.
5. A method for evaluating and analyzing the status of a tubular unit, the method being operated based on the trend warning system according to any one of claims 1 to 4, characterized in that: The following steps are involved: Step 1: Collect the operating parameters of the runner chamber, gearbox and generator inside the tubular unit, and determine the adaptation packages generated between different intervals by analyzing the past operating parameters; Step 2: The real-time operating parameters are collected through the unit data collection terminal, and the data is analyzed through the first-order data analysis terminal to determine whether the transmission between the runner room and the gearbox is normal, and a processing signal is generated and transmitted to the early warning terminal; Step 3: When the runner room and the gearbox are both normal, analyze the working parameters between the gearbox and the generator to determine whether the parameters between the gearbox and the generator are normal, generate a processing signal, and transmit it to the early warning terminal; Step 4: The early warning terminal displays a timely warning based on the abnormal signal received, so that external personnel can view it and take corresponding measures in time.
Citation Information
Patent Citations
Hydroelectric generating set state evaluation method and system
CN112818525A
Method and system for early warning and diagnosing water turbine runner blade crack breakdown
CN103439091A
State development trend prediction method, apparatus and device, and storage medium
CN112668772A
Prediction analysis method and system for data trend of water-turbine generator set
CN115423158A
Hydroelectric generating set state monitoring system based on data analysis
CN116222659A