A kind of hoisting equipment and method for installation and construction of building steel structure

By designing supporting columns, docking rod seats and limit lifting structures in the construction of building steel structures, the problems of single lifting points and cumbersome steps of tower crane equipment are solved, and the lifting operation is simplified and stable, and the lifting operation is adapted to different lengths The lifting items improve construction safety and stability.

CN117720006BActive Publication Date: 2024-12-27GUANGDONG HAILONG CONSTR TECH CO LTD +1
View PDF 18 Cites 0 Cited by

Patent Information

Application Number
CN202311807691.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-12-26
Publication Date
2024-12-27
Estimated Expiration
2043-12-26

AI Technical Summary

Technical Problem

In the existing construction methods of building steel structures, tower crane equipment has single lifting points and cumbersome lifting steps, making it difficult to ensure the stability and safety of lifting objects of different lengths.

Method used

A lifting equipment including supporting columns, butt rod seats, limit lifting structures, load-mounted adjustment components, stable restricting components and lifting control components is designed, and components such as screw rods, motor drives, electric telescopic rods and winding wheels are used. , realize the adjustment and fixation of lifting position and angle, and ensure the stability of multi-point lifting.

Benefits of technology

It realizes simplification and stability of lifting operations, adapts to lifting objects of different lengths, and improves construction safety and lifting stability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117720006B_ABST
    Figure CN117720006B_ABST
Patent Text Reader

Abstract

The present invention belongs to the technical field of building hoisting equipment, and specifically relates to a hoisting equipment and method for installing and constructing building steel structures, wherein the hoisting equipment for installing and constructing building steel structures comprises a supporting connecting column, the lower end of which is fixedly connected with a docking rod seat, and the lower end of which is fixedly connected with a limited position hoisting structure. The present invention can conveniently limit and fix the supporting connecting column, the docking rod seat and the crane, and the limited position hoisting structure is provided with a combination of a supporting adjustment component, a stable limiting component and a hoisting control component. The motor drives the screw rod in the supporting adjustment component to drive the regulating end to adjust the displacement, and at the same time, a telescopic rod 1 is provided at the lower end of the hinged support, and the telescopic rod 1 is limitedly connected with the supporting inclined frame through the docking rod and the stable bracket, so that the rotation adjustment of the supporting inclined frame can be conveniently and stably performed to realize the adjustment of the hoisting position, and the operation is simple, and the hoisting operation of hoisting objects of different lengths can be adapted, and the hoisting stability performance can be ensured.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of building hoisting equipment, and in particular relates to hoisting equipment and a method for installing and constructing a building steel structure. Background Art

[0002] In recent years, with the vigorous promotion of green buildings and prefabricated buildings in my country, steel structure buildings with the characteristics of green buildings and prefabricated buildings have developed rapidly, while most of the on-site construction technologies and safety measures of steel structures are still in traditional forms. In particular, most of the current projects have short construction periods, huge welding volumes, harsh construction environments, and many cross-operations of various types of work. Traditional construction methods seriously affect construction quality and personnel safety. In addition, in the steel structure construction industry, many large steel structure components need to be installed and constructed through operating platforms during the construction process.

[0003] For example, in a Chinese invention patent application with application publication number CN115012519A and application publication date 2022.09.06, a method for installing a super high-rise building steel structure is disclosed, including the following steps: S1: pre-preparation, installing a tower crane at the construction site, and counting the number of steel plates, and stacking them for acceptance; S2: component fixing, placing the longer steel plates in the steel structure, and fixing them with fixing equipment, while installing the shorter steel plates in the middle of the two longer steel plates, and installing different numbers of short steel plates in sequence according to the required shape of the steel structure, and adjusting the horizontality between the short steel plates and the long steel plates by positioning adjustment. The trial lifting step of the present invention can ensure the stability of the rigging, prevent the steel structure from slipping during lifting, causing safety accidents, improve the safety performance of steel structure construction, and prevent safety accidents caused by ground workers not completely detaching their hands from the hook when hanging, thereby improving the safety of lifting. However, in the installation method used for the construction of super high-rise building steel structures, the tower crane equipment carries loads through lifting ropes to achieve the lifting of steel plates. However, in actual operation, the installation method has a single lifting point and requires a trial lift to ensure stable lifting and avoid lifting accidents. The lifting procedures are cumbersome. Summary of the invention

[0004] The technical problem to be solved by the present invention is to provide a hoisting device and method for the installation and construction of building steel structures in view of the shortcomings of the prior art. The present invention can adapt to the hoisting operations of hoisted objects of different lengths, the hoisting operation is simple, and the stability of multi-point hoisting can be ensured.

[0005] The present invention is realized by the following technical measures: a hoisting device for installation and construction of building steel structure, comprising a supporting connecting column, the lower end of which is fixedly connected to a docking rod seat, and the lower end of which is fixedly connected to a limited position hoisting structure;

[0006] The position-limiting hoisting structure comprises a load-bearing adjustment component, the lower end of which is connected to a stable limiting component, the side end of which is hinged to a hoisting control component, and the upper end of which is hinged to the load-bearing adjustment component;

[0007] The support adjustment component includes two limit frames parallel to each other, the inner cavities of the two limit frames are rotatably connected with screw rods respectively, both ends of each limit frame are fixedly connected with hinged supports, the lower end of each hinged support is hinged with a telescopic rod, the lower end of each telescopic rod is hinged with a docking rod, and a stable bracket is fixedly connected between the two docking rods located at the same end of the limit frame.

[0008] Preferably, the stable limiting component includes two limit blocks fixed at the lower end of the limit frame and parallel to each other, two combined support rods are fixedly connected between the two limit blocks, two telescopic rods are hinged on the two combined support rods respectively, and the telescopic rods on the two combined support rods are symmetrically arranged, and the lower end of the telescopic rod is fixedly connected to a docking shaft block.

[0009] Preferably, the lifting control component includes a fixed combined guide block, the fixed combined guide block is fixedly connected to the load-bearing column frame, the lower end of the load-bearing column frame is fixedly connected to a positioning block, the lower end of the positioning block is fixedly connected to a stabilizing pillar, and the lower end of the stabilizing pillar is fixedly connected to a hook. Through the structural setting of the stabilizing limiting component, the limit block in the stabilizing limiting component is fixedly connected to the lower end of the limit frame, and a combined support rod is arranged on the limit block, and the combined support rod is connected to the supporting inclined frame through the telescopic rod 2 and the docking shaft block, which can cooperate to adjust the angle of the supporting inclined frame to improve the stability of the operation of the supporting inclined frame. The fixed combined guide block, the load-bearing column frame, the positioning block and the stabilizing pillar in the lifting control component are fixed, which is convenient for the installation of the hook. The hook can hook up the lifting object, and at the same time, the wire rope can be wound around the winding wheel to realize auxiliary positioning of the side, and the position of the winding wheel can be limited, thereby ensuring the stability of multi-point lifting.

[0010] Preferably, the hoisting control component also includes a regulating end head, the central rotation of the regulating end head is connected to a rotating adjustment shaft, the lower end of the rotating adjustment shaft is fixedly connected to a supporting inclined frame, the rear end of the supporting inclined frame is fixedly connected to a supporting assembly frame, the lower end of the supporting assembly frame is fixedly connected to a mounting frame, and the upper end of the mounting frame is fixedly installed with an electric telescopic rod, and the upper support of the limited lifting structure can be carried out through the structural setting of the supporting connecting column and the docking rod seat, which is convenient for limited fixing with the crane through the supporting connecting column and the docking rod seat, and the limited lifting structure is fixed by the supporting adjustment component and the stable limit A control component and a lifting control component are arranged in combination, wherein the support adjustment component can control the position of the lifting control component, the screw rod in the support adjustment component is driven by a motor, and can drive the regulating end to adjust the displacement, and at the same time a telescopic rod is arranged at the lower end of the hinged support, and the telescopic rod is limitedly connected to the supporting inclined frame through a docking rod and a stable bracket. Through the setting of the telescopic rod, the angular position of the supporting inclined frame relative to the regulating end can be changed, which is convenient for adjusting the inclination. By adjusting the inclination and distance, it can be adjusted according to the hoisting object during hoisting, thereby improving the hoisting stability performance.

[0011] Preferably, the interior of the mounting frame is rotatably connected to a mounting shaft, both ends of the mounting shaft pass through the outside of the mounting frame and are respectively fixedly connected to a winding wheel, and a middle portion of the mounting shaft is evenly provided with a plurality of limit slots along its circumference for plugging and cooperating with the telescopic end of the electric telescopic rod.

[0012] Preferably, the side end of the supporting assembly frame is fixedly connected to the fixed assembly guide block, and the fixed assembly guide block is connected to the hook in a limited position through the bearing column frame, the positioning fixed block and the stabilizing pillar.

[0013] Preferably, the docking shaft block is rotatably connected to the bottom of the supporting oblique frame.

[0014] Preferably, the regulating end is threadedly connected to the screw rod, and the lower end of the stabilizing bracket is fixedly connected to the middle part of the supporting oblique bracket.

[0015] Preferably, a camera is installed at the side end of the supporting oblique frame, and a position sensor is installed at the middle part of one end of the docking rod seat.

[0016] A method for hoisting a building steel structure for installation and construction based on the hoisting equipment for installation and construction of the building steel structure comprises the following steps:

[0017] S1. The supporting work of the supporting connecting column, the docking rod seat and the limited lifting structure is realized by locking the supporting connecting column and the crane, and the lifting position is adjusted according to the size of the lifting object: the motor set on the limited frame is driven to drive the screw rod to rotate, and the rotation of the screw rod causes the regulating end head to move along it, which can change the position of the regulating end head in the limited frame. The upper end of the supporting inclined frame swings along the movement of the screw rod through the regulating end head, so that the supporting inclined frame rotates, and the inclination of the supporting inclined frame is adjusted. When the supporting inclined frame rotates, the telescopic rod 2 and the telescopic rod 1 are adaptively extended and retracted, so that the supporting inclined frame remains stable;

[0018] S2. The operator fixes the hoisted object on the hook through the hoisting rope. The upper end of the hook is supported by a stable pillar, a positioning fixed block, a load-bearing column frame, and a fixed combined guide block. At the same time, a steel wire rope is set in the reel to fix the hoisted object and limit the side of the hoisted object;

[0019] S3. When the required position is reached, the electric telescopic rod starts working, and the telescopic end of the electric telescopic rod is inserted into the interior of the mounting shaft to limit and lock the winding wheel, thereby achieving side limit of the hoisted object, improving transportation stability, and completing the work.

[0020] Beneficial effects of the present invention:

[0021] First, the present invention can provide upper support for the limited lifting structure through the structural setting of the supporting connecting column and the docking rod seat, and can facilitate the limited fixing with the crane through the supporting connecting column and the docking rod seat. The limited lifting structure is combined with a supporting adjustment component, a stable limiting component, and a lifting control component, wherein the supporting adjustment component can control the position of the lifting control component, and the screw rod in the supporting adjustment component is driven by a motor to drive the regulating end to adjust the displacement. At the same time, a telescopic rod 1 is arranged at the lower end of the hinged support, and the telescopic rod 1 is limitedly connected with the supporting inclined frame through the docking rod and the stable bracket, so that the rotation adjustment of the supporting inclined frame can be conveniently and stably performed to realize the adjustment of the lifting position. The operation is simple, and it can adapt to the lifting operation of lifting objects of different lengths, and can ensure the stable performance of the lifting.

[0022] Secondly, the present invention stabilizes the structural setting of the limiting component, and the limit block in the limiting component is fixedly connected to the lower end of the limit frame. A combined support rod is arranged on the limit block, and the combined support rod is connected to the supporting inclined frame through telescopic rod 2 and a docking shaft block, which can cooperate in the angle adjustment of the supporting inclined frame to improve the stability of the operation of the supporting inclined frame. The fixed combined guide block, the load-bearing column frame, the positioning and fixing block, and the stable pillar in the lifting control component are fixed to facilitate the installation of the hook. The hook can hook up the lifting object, and at the same time, a wire rope can be wound on the winding wheel to realize auxiliary positioning of the side, and the position of the winding wheel can be limited, thereby ensuring the stability of multi-point lifting. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1 The three-dimensional structure diagram of the hoisting equipment for the installation and construction of the building steel structure in Example 1 of the present invention Figure 1 ;

[0024] Figure 2 The three-dimensional structure diagram of the hoisting equipment for the installation and construction of the building steel structure in Example 1 of the present invention Figure 2 ;

[0025] Figure 3 It is a schematic diagram of the three-dimensional structure of the position-limiting hoisting structure in Embodiment 1 of the present invention;

[0026] Figure 4 It is a schematic diagram of the three-dimensional structure of the supporting and adjusting component in Example 1 of the present invention;

[0027] Figure 5 It is a schematic diagram of the three-dimensional structure of the stabilizing and limiting component in Example 1 of the present invention;

[0028] Figure 6 It is a schematic diagram of the three-dimensional structure of the hoisting control component in Example 1 of the present invention;

[0029] Figure 7 This is a schematic diagram of the exploded structure of the hoisting control component in Example 1 of the present invention;

[0030] Figure 8 for Figure 7 The enlarged view of point A in the middle;

[0031] Fig. 9 It is a schematic diagram of the three-dimensional structure of the lifting equipment used for the installation and construction of the building steel structure in Example 2 of the present invention.

[0032] In the figure: 1-support connecting column, 2-jointing rod seat, 3-limiting lifting structure, 4-support adjustment component, 5-stable limiting component, 6-lifting control component, 7-limiting frame, 8-screw, 9-hinge support, 10-telescopic rod one, 11-jointing rod, 12-stable bracket, 13-limiting block, 14-combined support rod, 15-telescopic rod two, 16-jointing shaft block, 17-hook, 18-stable pillar, 19-positioning fixed block, 20-bearing column frame, 21-fixed combined guide block, 22-regulating end, 23-rotating adjustment shaft, 24-support oblique frame, 25-winding wheel, 26-support combination frame, 27-electric telescopic rod, 28-mounting frame, 29-mounting shaft, 30-limiting slot, 31-camera, 32-position sensor. DETAILED DESCRIPTION

[0033] In order to clearly illustrate the technical features of this solution, this solution is described below through specific implementation methods and in conjunction with the accompanying drawings.

[0034] Example 1

[0035] A hoisting device for installation and construction of building steel structure comprises a supporting connecting column 1, the lower end of the supporting connecting column 1 is fixedly connected with a docking rod seat 2, and the lower end of the docking rod seat 2 is fixedly connected with a limited position hoisting structure 3.

[0036] like Figure 3 As shown, the position-limiting hoisting structure 3 includes a supporting and adjusting component 4, the lower end of the supporting and adjusting component 4 is connected to a stable limiting component 5, the side end of the stable limiting component 5 is hinged to a hoisting control component 6, and the upper end of the hoisting control component 6 is hinged to the supporting and adjusting component 4;

[0037] like Figure 4 As shown, the supporting adjustment component 4 includes two limit frames 7 which are parallel to each other. The inner cavities of the two limit frames 7 are rotatably connected with screw rods 8 respectively. Both ends of each limit frame 7 are fixedly connected with hinged supports 9. The lower end of each hinged support 9 is hinged with a telescopic rod 10. The lower end of each telescopic rod 10 is hinged with a docking rod 11. A stabilizing bracket 12 is fixedly connected between the two docking rods 11 at the same end of the limit frame 7.

[0038] like Figure 5 As shown, the stable limiting component 5 includes two limit blocks 13 fixed at the lower end of the limit frame 7 and parallel to each other, two combined support rods 14 are fixedly connected between the two limit blocks 13, two telescopic rods 15 are hinged on the two combined support rods 14, and the telescopic rods 15 on the two combined support rods 14 are symmetrically arranged, and the lower end of the telescopic rod 15 is fixedly connected with a docking shaft block 16, which is rotatably connected to the bottom of the supporting inclined frame 24, which can ensure that the supporting inclined frame 24 can rotate and keep the supporting inclined frame 24 stable.

[0039] like Figure 6 As shown, the hoisting control component 6 includes a fixed combined guide block 21, the lower end of the fixed combined guide block 21 is fixedly connected to a load-bearing column frame 20, the lower end of the load-bearing column frame 20 is fixedly connected to a positioning fixed block 19, the lower end of the positioning fixed block 19 is fixedly connected to a stabilizing pillar 18, the lower end of the stabilizing pillar 18 is fixedly connected to a hook 17, the hoisted object is fixed to the hook 17 by a hoisting rope to achieve the stability of the hoisted object, and the upper end of the hook 17 is supported by the stabilizing pillar 18, the positioning fixed block 19, the load-bearing column frame 20, and the fixed combined guide block 21.

[0040] like Figure 7 , Figure 8As shown, the hoisting control component 6 also includes a regulating end 22, the center of the regulating end 22 is rotatably connected to a rotating adjustment shaft 23, the lower end of the rotating adjustment shaft 23 is fixedly connected to a supporting inclined frame 24, the rear end of the supporting inclined frame 24 is fixedly connected to a supporting assembly frame 26, the lower end of the supporting assembly frame 26 is fixedly connected to a mounting frame 28, and the upper end of the mounting frame 28 is fixedly installed with an electric telescopic rod 27, a motor is provided on the driving limit frame 7, the motor drives a screw rod 8 to rotate, the screw rod 8 is threadedly connected to the regulating end 22, and the rotation of the screw rod 8 causes the regulating end 22 to move along it, thereby changing the position of the regulating end 22 in the limit frame 7, and realizing the adjustment of the lifting length, the telescopic rod 10 is telescoped, the upper end of the telescopic rod 10 is hinged to the limit frame 7 through a hinged support 9, and the lower end is hinged to a stable bracket 12 through a docking rod 11, and the stable bracket 12 is fixed on the supporting inclined frame 24, while ensuring that the supporting inclined frame 24 can rotate, it can also ensure the stability of the supporting inclined frame 24.

[0041] The interior of the mounting frame 28 is rotatably connected to a mounting shaft 29, and both ends of the mounting shaft 29 extend through the exterior of the mounting frame 28 and are respectively fixedly connected to a winding wheel 25. A plurality of limit slots 30 that are plugged into and matched with the telescopic ends of the electric telescopic rod 27 are evenly arranged in the middle portion of the mounting shaft 29 along its circumference. A steel wire rope is arranged inside the winding wheel 25, which can be fixed to the hoisted object to limit the side of the hoisted object. When the desired position is reached, the electric telescopic rod 27 works, and the telescopic end of the electric telescopic rod 27 is inserted into the limit slot 30 on the mounting shaft 29 to limit and lock the winding wheel 25, thereby realizing the side limitation of the hoisted object and improving the transportation stability.

[0042] The side end of the support assembly frame 26 is fixedly connected to the fixed assembly guide block 21 , and the fixed assembly guide block 21 is connected to the hook 17 through the bearing column frame 20 , the positioning and fixing block 19 , and the stabilizing support column 18 for limiting connection.

[0043] The regulating end 22 is threadedly connected to the screw rod 8, the lower end of the stabilizing bracket 12 is fixedly connected to the middle of the supporting oblique frame 24, and the telescopic rod 10 is hingedly arranged with the supporting oblique frame 24 through the docking rod 11 and the stabilizing bracket 12.

[0044] Example 2

[0045] like Fig. 9 As shown, in this embodiment, on the basis of embodiment 1, a camera 31 is installed at the side end of the supporting inclined frame 24, and a position sensor 32 is installed at the middle of one end of the docking rod seat 2. The camera 31 is arranged at the lower end of the supporting inclined frame 24, and can monitor the lower hoisting state in real time and feed it back to the controller of the crane, which is convenient for monitoring the hoisting situation. At the same time, the position sensor 32 feeds back the real-time hoisting position to the controller of the crane, which is convenient for real-time positioning monitoring.

[0046] A method for hoisting a building steel structure for installation and construction based on the hoisting equipment for installation and construction of the building steel structure comprises the following steps:

[0047] S1. Assemble and install the supporting connecting column 1, the docking rod seat 2 and the limiting hoisting structure 3, and lock the supporting connecting column 1 with the crane to realize the supporting work of the supporting connecting column 1, the docking rod seat 2 and the limiting hoisting structure 3, and adjust the hoisting position according to the size of the hoisting object: drive the motor set on the limiting frame 7 to drive the screw rod 8 to rotate, the screw rod 8 is threadedly connected with the regulating end head 22, and the rotation of the screw rod 8 makes the regulating end head 22 move along it, which can change the position of the regulating end head 22 in the limiting frame 7, and the upper end of the supporting inclined frame 24 swings along the movement of the regulating end head 22 along the screw rod 8, so that the supporting inclined frame 24 rotates, and the inclination of the supporting inclined frame 24 is adjusted. When the supporting inclined frame 24 rotates, the telescopic rod 2 15 and the telescopic rod 1 10 are adaptively extended and retracted, so that the supporting inclined frame 24 remains stable;

[0048] S2. The operator fixes the hoisted object on the hook 17 through the hoisting rope to ensure the stability of the hoisted object. The upper end of the hook 17 is supported by a stabilizing pillar 18, a positioning and fixing block 19, a bearing column frame 20, and a fixed combination guide block 21. At the same time, a steel wire rope is arranged in the winding wheel 25 to fix the hoisted object and limit the side of the hoisted object.

[0049] S3. When the desired position is reached, the electric telescopic rod 27 starts working, and the telescopic end of the electric telescopic rod 27 is inserted into the limit slot 30 on the mounting shaft 29 (with manual assistance if necessary), and the winding wheel 25 is locked in a limit position, thereby achieving side limit of the hoisted object, improving transportation stability, and completing the work.

[0050] Technical features not described in the present invention can be implemented by existing technologies and will not be described in detail here. The present invention is not limited to the above specific embodiments, and changes, modifications, additions or substitutions made by ordinary technicians in the field within the essential scope of the present invention should also fall within the protection scope of the present invention.

Claims

1. A hoisting device for installation and construction of building steel structures, characterized in that: It comprises a supporting connecting column (1), the lower end of which is fixedly connected to a docking rod seat (2), and the lower end of which is fixedly connected to a limited position lifting structure (3); The position-limiting hoisting structure (3) comprises a load-bearing adjustment component (4), the lower end of the load-bearing adjustment component (4) is connected to a stabilizing limiting component (5), the side end of the stabilizing limiting component (5) is hingedly connected to a hoisting control component (6), and the upper end of the hoisting control component (6) is hingedly connected to the load-bearing adjustment component (4); The support adjustment component (4) comprises two mutually parallel limit frames (7), the inner cavities of the two limit frames (7) are rotatably connected to screw rods (8), both ends of each limit frame (7) are fixedly connected to hinged supports (9), the lower end of each hinged support (9) is hinged to a telescopic rod (10), the lower end of each telescopic rod (10) is hinged to a docking rod (11), and a stable bracket (12) is fixedly connected between the two docking rods (11) at the same end of the limit frame (7); The stable limiting component (5) comprises two limiting blocks (13) fixed at the lower end of the limiting frame 7 and parallel to each other, two combined support rods (14) are fixedly connected between the two limiting blocks (13), two telescopic rods (15) are hingedly connected to the two combined support rods (14), and the telescopic rods (15) on the two combined support rods (14) are symmetrically arranged, and the lower end of the telescopic rod (15) is fixedly connected to a docking shaft block (16); The lifting control component (6) comprises a fixed combined guide block (21), the lower end of the fixed combined guide block (21) is fixedly connected to a bearing column frame (20), the lower end of the bearing column frame (20) is fixedly connected to a positioning fixed block (19), the lower end of the positioning fixed block (19) is fixedly connected to a stabilizing pillar (18), and the lower end of the stabilizing pillar (18) is fixedly connected to a lifting hook (17); The hoisting control component (6) further comprises a regulating end head (22), the center of the regulating end head (22) being rotatably connected to a rotating regulating shaft (23), the lower end of the rotating regulating shaft (23) being fixedly connected to a supporting inclined frame (24), the rear end of the supporting inclined frame (24) being fixedly connected to a supporting assembly frame (26), the lower end of the supporting assembly frame (26) being fixedly connected to a mounting frame (28), and the upper end of the mounting frame (28) being fixedly mounted with an electric telescopic rod (27); The interior of the mounting frame (28) is rotatably connected to a mounting shaft (29), both ends of the mounting shaft (29) pass through the exterior of the mounting frame (28) and are respectively fixedly connected to a reel (25), and a plurality of limit slots (30) are evenly arranged along the circumference of the middle portion of the mounting shaft (29) for plugging and cooperating with the telescopic ends of the electric telescopic rod (27).

2. The hoisting equipment for installation and construction of building steel structure according to claim 1 is characterized by: The side end of the support assembly frame (26) is fixedly connected to the fixed assembly guide block (21), and the fixed assembly guide block (21) is connected to the hook (17) through the bearing column frame (20), the positioning and fixing block (19), and the stabilizing pillar (18).

3. The hoisting equipment for installation and construction of building steel structure according to claim 2 is characterized by: The docking shaft block (16) is rotatably connected to the bottom of the supporting oblique frame (24).

4. The hoisting equipment for installation and construction of building steel structure according to claim 3 is characterized by: The regulating end head (22) is threadedly connected to the screw rod (8), and the lower end of the stabilizing bracket (12) is fixedly connected to the middle part of the supporting inclined bracket (24).

5. The hoisting equipment for installation and construction of building steel structure according to claim 4 is characterized by: A camera (31) is installed at the side end of the supporting oblique frame (24), and a position sensor (32) is installed at the middle of one end of the docking rod seat (2).

6. A method for hoisting a building steel structure for installation and construction based on the hoisting equipment for installation and construction of a building steel structure according to claim 5, characterized in that: The steps include: S1. The supporting column (1), the docking rod seat (2) and the limit hoisting structure (3) are locked by the supporting column (1) and the crane to realize the supporting work. The hoisting position is adjusted according to the size of the hoisting object: the motor arranged on the limit frame (7) is driven to drive the screw rod (8) to rotate. The rotation of the screw rod (8) causes the regulating end head (22) to move along it, so that the position of the regulating end head (22) in the limit frame (7) can be changed. The upper end of the supporting inclined frame (24) is swung by the movement of the regulating end head (22) along the screw rod 8, so that the supporting inclined frame (24) is rotated, and the inclination of the supporting inclined frame (24) is adjusted. When the supporting inclined frame (24) rotates, the telescopic rod 2 (15) and the telescopic rod 1 (10) are adaptively extended and retracted, so that the supporting inclined frame (24) remains stable. S2. The operator fixes the hoisted object on the hook (17) by means of a hoisting rope. The upper end of the hook (17) is supported by a stabilizing support (18), a positioning and fixing block (19), a bearing column frame (20), and a fixed combination guide block (21). At the same time, a steel wire rope is arranged in the reel (25) to fix the hoisted object and limit the side of the hoisted object. S3. When the desired position is reached, the electric telescopic rod (27) starts to work, and the telescopic end of the electric telescopic rod (27) is inserted into the interior of the mounting shaft (29) to limit and lock the winding wheel (25), thereby achieving side limit of the hoisted object, improving transportation stability, and completing the work.

Citation Information

Patent Citations

  • Mounting method for super high-rise building steel structure construction

    CN115012519A

  • Raise-and-fall device of piping up construction steels

    CN106348138A

  • Scaffold hoisting bearing equipment for building construction

    CN108915239A

  • Reinforced concrete prefabricated part mounting and hoisting machine

    CN111573497A

  • Hoisting equipment for fabricated building construction

    CN113233309A