Integrated multi-stage thermal energy storage and heat pump combined heat and power system and its operation method

By integrating multi-stage thermal energy storage with heat pump linkage into a combined heat and power system, the problems of low energy utilization efficiency and small peak-shaving depth of combined heat and power units during deep peak shaving are solved, and the flexible switching and efficient operation of the combined heat and power system during peak-valley periods are realized.

CN117739394BActive Publication Date: 2026-11-17NINGBO INSTITUTE OF TECHNOLOGY BEIHANG UNIVERSITY
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202311760124.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-12-19
Publication Date
2026-11-17
Estimated Expiration
2043-12-19

AI Technical Summary

Technical Problem

Existing combined heat and power (CHP) units suffer from problems such as low comprehensive energy utilization, inflexible parameter adjustment, inflexible heat source selection, and limited power output during peak periods, resulting in low energy utilization efficiency and shallow peak-shaving depth.

Method used

The cogeneration system adopts an integrated multi-stage thermal energy storage and heat pump linkage system, including absorption heat pumps, electric heat pumps, peak heaters, and multi-stage thermal storage tanks. Through cascade heating and thermal energy storage, it achieves deep load reduction of the cogeneration unit and increases the system's power generation during the energy release phase of the heating season.

Benefits of technology

It enables flexible and rapid switching of the cogeneration system during peak and off-peak periods, improves energy utilization efficiency and peak-shaving capability, and enhances the flexibility of parameter adjustment and system energy efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117739394B_ABST
    Figure CN117739394B_ABST
Patent Text Reader

Abstract

A combined heat and power (CHP) system and its operation method integrating multi-stage thermal energy storage and heat pump linkage are disclosed. The system includes a CHP unit, an absorption heat pump, an electric heat pump, a peak heater, a peak thermal storage tank, high, medium, and low temperature thermal storage tanks, auxiliary heaters, and various pipelines and valves. During the energy storage phase of the heating season, the absorption heat pump, steam extracted from a turbine with appropriate parameters, and the electric heat pump sequentially heat the chilled water in the low-temperature thermal storage tank, which is then stored in the peak, high-temperature, and medium-temperature thermal storage tanks respectively, achieving deep load reduction of the unit while fully recovering waste heat from the condenser. During the energy release phase of the heating season, the medium-temperature thermal storage tank supplies heat externally, and the CHP unit operates in pure condensing mode. Simultaneously, hot water from the peak and high-temperature thermal storage tanks assists in heating the turbine condensate, thereby increasing the system's power generation. This invention achieves efficient integration of absorption heat pumps, electric heat pumps, staged thermal energy storage, and the CHP unit, significantly improving the system's energy efficiency and peak-shaving capacity.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the fields of combined heat and power (CHP), power plant peak shaving, and multi-stage thermal energy storage, specifically to a CHP system and operation method that integrates multi-stage thermal energy storage with heat pump linkage. Background Technology

[0002] Solar and wind power generation exhibits strong volatility and anti-peak-shaving characteristics, posing a significant challenge to grid peak regulation. Currently, my country has overcapacity in thermal power generation, with low annual utilization hours of generating equipment. In the coming years, continuous low-load or deep peak-shaving operation of thermal power units will become the norm. Combined heat and power (CHP) units constitute a large proportion and have high capacity in thermal power generation, and are the main type of thermal power plant in northern my country. Improving the deep peak-shaving capacity of CHP units is a key technology for efficiently absorbing renewable energy generation. Currently, conventional deep peak-shaving technologies for CHP units have the following problems:

[0003] (1) The energy utilization level of peak-shaving methods such as electric boilers and bypass main steam is low. In order to improve the heating capacity of the unit during the peak heating period, the overall energy efficiency level of the unit will be further reduced.

[0004] (2) Existing cogeneration peak-shaving systems have problems such as inflexible parameter adjustment, inflexible selection of heat source steam, limited power output during peak cogeneration periods, and low energy utilization efficiency and shallow peak-shaving depth of conventional unit peak-shaving technologies. Summary of the Invention

[0005] To address the problems existing in the prior art, the present invention aims to provide a combined heat and power (CHP) system and operation method integrating multi-stage thermal energy storage and heat pump linkage. This system includes a CHP unit, an absorption heat pump, an electric heat pump, a peak heater, a peak thermal storage tank, high, medium, and low temperature thermal storage tanks, auxiliary heaters, and various pipelines and valves. During the heating season energy storage phase, the absorption heat pump, steam extracted from a turbine with appropriate parameters, and the electric heat pump sequentially heat the chilled water in the low-temperature thermal storage tank, which is then stored in peak, high-temperature, and medium-temperature thermal storage tanks respectively, achieving deep load reduction of the unit while fully recovering waste heat from the condenser. During the heating season energy release phase, the medium-temperature thermal storage tank supplies heat externally, and the CHP unit operates in pure condensing mode. Simultaneously, hot water from the peak and high-temperature thermal storage tanks assists in heating the turbine condensate, thereby increasing the system's power generation. This invention achieves efficient integration of absorption heat pumps, electric heat pumps, staged thermal energy storage, and the CHP unit, significantly improving the system's energy efficiency and peak-shaving capacity. This invention enables flexible and rapid switching of the operating mode of the cogeneration system during peak and off-peak (energy storage-energy release) periods. The peak shaving process realizes the orderly utilization of energy in a cascade manner, with high energy utilization efficiency, large peak shaving depth, and flexible parameter adjustment.

[0006] To achieve the above objectives, the present invention adopts the following technical solution:

[0007] A combined heat and power (CHP) system integrating multi-stage thermal energy storage and heat pump linkage includes, in sequence, a boiler 101 main steam side, a turbine high-pressure cylinder 102, a boiler 101 reheat steam side, a turbine intermediate-pressure cylinder 103, a turbine low-pressure cylinder 104, a condenser 105 shell side, a condensate pump 115, a condensate valve A 306, a seventh-stage heater 106 tube side, a sixth-stage heater 107 tube side, a condensate valve B 304, a fifth-stage heater 108 tube side, a fourth-stage heater 109 tube side, a deaerator 110, a feedwater pump 116, a feedwater valve A 330, a second-stage heater 111 tube side, a first-stage heater 112 tube side, and a boiler 101 feedwater side; the exhaust pipe of the turbine high-pressure cylinder 102 passes through the first... The first-stage regenerative steam extraction pipeline is connected to the shell side of the first-stage heater 112; the second-stage and third-stage steam extraction pipelines, with successively decreasing pressure in the intermediate-pressure cylinder 103 of the turbine, are connected to the shell side of the second-stage heater 111 and the deaerator 110, respectively; the fourth, fifth, sixth, and seventh-stage steam extraction pipelines, with successively decreasing pressure in the low-pressure cylinder 104 of the turbine, are connected to the shell side of the fourth-stage heater 109, the shell side of the fifth-stage heater 108, the shell side of the sixth-stage heater 107, and the shell side of the seventh-stage heater 106, respectively; the shell-side outlet of the first-stage heater 112 is connected to the shell side of the second-stage heater 111 and the deaerator 110 via a drain pipe; the shell-side outlet of the fourth-stage heater 109 is connected to the fifth-stage heater 108 via a drain pipe. Shell side, sixth-stage heater 107 shell side, seventh-stage heater 106 shell side, condenser 105 shell side; condenser 105 tube side is connected to cooling tower 114; turbine high-pressure cylinder 102 is connected to turbine intermediate-pressure cylinder 103, turbine low-pressure cylinder 104 and generator 113 via mechanical shaft; boiler 101 main steam side outlet, reheat steam side outlet and reheat steam side inlet pipe are connected to extraction steam pipe through extraction valve B 302, extraction steam valve A 301 and extraction steam valve C 303 respectively, extraction steam pipe is connected to peak heater 204 hot fluid side and absorption heat pump 205 generator through regulating valve A 318 and regulating valve B 319 respectively, peak heater 204 hot fluid side outlet and absorption heat pump 205 generator are connected to the absorption heat pump 205 generator. The outlet of heat pump 205 generator is connected to deaerator 110; high-temperature heat storage tank 201 is connected in sequence to variable frequency water pump A 323, high-temperature valve 328, cold fluid side of peak heater 204, control valve C 316, control valve D 315, control valve E 314, variable frequency water pump C 313 and medium-temperature heat storage tank 202; the outlet of cold fluid side of peak heater 204 is connected in sequence to control valve G 317, hot fluid side of auxiliary heater A 206, hot fluid side of auxiliary heater B 207, variable frequency water pump B 322 and low-temperature heat storage tank 203; the pipeline between control valve D 315 and control valve E 314 is connected in sequence to control valve G 310, heat user 208, variable frequency water pump B 322 and low-temperature heat storage tank 203;The pipeline between control valve D315 and control valve E314 is also connected in sequence to control valve F309, variable frequency water pump D311, and the hot fluid side outlet of auxiliary heater A206; the low-temperature heat storage tank 203 is connected in sequence to variable frequency water pump B322, control valve H320, absorption heat pump 205 absorber, and absorption heat pump 205 condenser; the pipeline between control valve C316 and control valve D315 is connected to the outlet of absorption heat pump 205 condenser; the outlet pipeline of cooling tower 114 is connected in sequence to the inlet pipeline of cooling tower 114 through cooling valve 308 and absorption heat pump 205 evaporator; the outlet pipeline of condensate pump 115 is connected in sequence to condensate valve C307, the cold fluid side of auxiliary heater B207, the cold fluid side of auxiliary heater A206, and deaerator 110; the pipe-side outlet of sixth-stage heater 107 is connected in sequence to condensate valve The cold fluid side outlet pipes of the pump 305, variable frequency water pump 312, and auxiliary heater 207 are connected in sequence; the condenser outlet pipe of the absorption heat pump 205 is also connected in sequence to the regulating valve 321, the evaporator of the electric heat pump 209, the variable frequency water pump 322, and the low-temperature heat storage tank 203; the cold fluid side outlet pipe of the peak heater 204 is also connected in sequence to the condenser of the electric heat pump 209, the electric heat pump valve 324, the variable frequency water pump 326, and the peak heat storage tank 210; the peak heat storage tank 210 is connected in sequence to the variable frequency water pump 326, the peak valve 327, the hot fluid side of the auxiliary heater 211, and the hot fluid side of the auxiliary heater 206; the outlet pipe of the feed water pump 116 is also connected in sequence to the feed water valve 329, the cold fluid side of the auxiliary heater 211, and the pipe-side outlet pipe of the first-stage heater 112; the generator 113 is connected in sequence to the electric heat pump switch 325 and the electric heat pump 209 via a circuit.

[0008] The integrated multi-stage thermal energy storage and heat pump linkage cogeneration system operates as follows during the heating season's energy storage phase, i.e., the off-peak electricity period: absorption heat pump 205, electric heat pump 209, and peak heater 204 are operational, while auxiliary heaters A 206, B 207, and C 211 are inactive; control valves G 317, F 309, condensate valve D 305, C 307, variable frequency pump D 311, variable frequency pump E 312, peak valve 327, and feedwater valve B 329 are closed; based on the heat load level and During periods of low electricity demand, only one of the following valves—extraction valve A 301, extraction valve B 302, and extraction valve C 303—is opened and regulated: the opening of control valve G 310 is adjusted according to the user's heat load to ensure that the hot water flow through user 208 meets the user's heat demand; variable frequency pump C 313 and control valve E 314 are adjusted to allow excess medium-temperature hot water flowing through control valve D 315 to flow into medium-temperature thermal storage tank 202 for storage; and variable frequency pump B 322 and control valve H 320 are adjusted according to the energy storage time to allow the cold water energy stored in low-temperature thermal storage tank 203 to be stored. The energy is fully released within the storage period; the opening of control valves D315 and C316 is adjusted according to the total heat load of the entire round-trip cycle of energy storage and release to ensure that the medium-temperature water stored in the medium-temperature heat storage tank 202 meets the user's heat load requirements during the energy release phase; the opening of control valves A318 and B319 is adjusted to ensure that the outlet temperature of the hot fluid in the peak heater 204 is consistent with the outlet temperature of the driving fluid in the generator of the absorption heat pump 205; the opening of the cooling valve 308 is adjusted to ensure that the flow rate of the refrigerant water flowing into the evaporator of the absorption heat pump 205 meets the requirements; the electric heating valve is closed. Pump switch 325 is switched on and its gear is adjusted. At the same time, the opening of control valve 321 and electric heat pump valve 324 are adjusted so that the overall power generation of the system meets the load demand during the off-peak period. The flow direction and flow rate of variable frequency water pump 326 are adjusted so that all the working fluid passing through the condenser of electric heat pump 209 flows to the peak heat storage tank 210 for storage. The flow rate and flow rate of variable frequency water pump 323 and the opening of high temperature valve 328 are adjusted according to the cold fluid flow rate of peak heater 204 so that all the remaining working fluid flowing through the cold fluid side of peak heater 204 is stored in high temperature heat storage tank 201.

[0009] The integrated multi-stage thermal energy storage and heat pump combined heat and power system operates as follows during the peak electricity release phase of the heating season: absorption heat pump 205, electric heat pump 209, and peak heater 204 are not in operation, while auxiliary heaters A 206, B 207, and C 211 are in operation; extraction valves A 301, B 302, C 303, H 320, D 315, C 316, cooling valves 308 and I 321, and electric heat pump valve 324 are closed. Turn on the electric heat pump switch 325; open the control valves 317, 309, and 327; adjust the flow direction and flow rate of the variable frequency water pump 326, and adjust the 327 to make the working fluid in the peak heat storage tank 210 flow to the hot fluid side of the auxiliary heater 211; at the same time, adjust the feed water valves 329 and 330 to make the temperature of the working fluid at the outlet of the cold fluid side of the auxiliary heater 211 consistent with the fluid temperature at the outlet of the tube side of the first stage heater 112; adjust the condensate valves 305, 307, and 308. Adjust the opening of valves 304 and condensate valve A 306, regulate the opening of control valve F 309, and adjust the flow direction and flow rate of variable frequency pumps D 311 and E 312 to ensure that: the hot fluid outlet temperature of auxiliary heater B 207 matches the working fluid outlet temperature of heat user 208; the cold fluid outlet temperatures of auxiliary heaters A 206 and B 207 match the working fluid outlet temperatures of the fourth-stage heater 109 and the sixth-stage heater 107, respectively; and the system's power generation meets the external electrical load demand. Adjust the flow direction and flow rate of variable frequency pump A 323 to... Adjusting the opening of high-temperature valve 328 allows high-temperature water to flow out of high-temperature heat storage tank 201, with the flow rate matching the opening of control valve 317; adjusting the opening of control valves 314 and 310 ensures the system's heat supply meets the needs of heat user 208; adjusting the flow direction and flow rate of variable frequency pump 313 allows medium-temperature water to flow out of medium-temperature heat storage tank 202, with the flow rate matching the opening of control valve 314; adjusting the flow direction and flow rate of variable frequency pump 322 allows cold water in its pipeline to flow into low-temperature heat storage tank 203 for storage.

[0010] Compared with the prior art, the present invention has the following advantages:

[0011] (1) The return water of the heating network adopts absorption heat pump, steam extraction with appropriate parameters of steam turbine, and electric heat pump for cascade heating to realize the orderly utilization of energy in a cascade manner.

[0012] (2) Multi-stage heat storage tanks are used to recover and store heat energy according to grade, and absorption heat pumps are used to preheat the return water of the heat network to fully realize the recovery and utilization of waste heat, thereby improving the energy efficiency of the system.

[0013] (3) By complementing and exchanging heat and electricity between the thermal storage system and the cogeneration unit, and by using absorption heat pumps and electric heat pumps to achieve high-grade heat value-added, the energy efficiency level and operational flexibility of the cogeneration unit during the heating season have been improved.

[0014] (4) By rationally matching the operating method and system configuration, this invention improves the flexible switching speed of the cogeneration system during peak and off-peak hours in the heating season, with a large peak shaving depth and flexible parameter adjustment. Attached Figure Description

[0015] Figure 1 This is a schematic diagram of a combined heat and power system and its operation method that integrates multi-stage thermal energy storage and heat pump linkage according to the present invention. Detailed Implementation

[0016] The present invention will now be described in further detail with reference to the accompanying drawings and specific embodiments.

[0017] To achieve efficient and flexible coupling of staged thermal energy storage technology, absorption heat pump technology, electric heat pump technology, and cogeneration units, this invention provides a cogeneration system integrating multi-stage thermal energy storage and heat pump linkage, such as... Figure 1As shown, the system includes, in sequence, the main steam side of boiler 101, the high-pressure cylinder 102 of turbine, the reheat steam side of boiler 101, the intermediate-pressure cylinder 103 of turbine, the low-pressure cylinder 104 of turbine, the shell side of condenser 105, condensate pump 115, condensate valve A 306, the tube side of seventh-stage heater 106, the tube side of sixth-stage heater 107, condensate valve B 304, the tube side of fifth-stage heater 108, the tube side of fourth-stage heater 109, deaerator 110, feedwater pump 116, feedwater valve A 330, the tube side of second-stage heater 111, the tube side of first-stage heater 112, and the feedwater side of boiler 101; the exhaust pipe of the high-pressure cylinder 102 of turbine is connected to the first-stage heater via the first-stage regenerative extraction pipe. The shell side of heater 112 is connected; the second and third stage extraction steam pipes of the intermediate pressure cylinder 103 of the turbine, with successively decreasing pressure, are connected to the shell side of the second stage heater 111 and the deaerator 110, respectively; the fourth, fifth, sixth, and seventh stage extraction steam pipes of the low pressure cylinder 104 of the turbine, with successively decreasing pressure, are connected to the shell side of the fourth stage heater 109, the shell side of the fifth stage heater 108, the shell side of the sixth stage heater 107, and the shell side of the seventh stage heater 106, respectively; the shell side outlet of the first stage heater 112 is connected to the shell side of the second stage heater 111 and the deaerator 110 in sequence through a drain pipe; the shell side outlet of the fourth stage heater 109 is connected to the shell side of the fifth stage heater 108 and the shell side of the sixth stage heater 106 in sequence through a drain pipe. The condenser 107 shell side, the seventh-stage heater 106 shell side, and the condenser 105 shell side; the condenser 105 tube side is connected to the cooling tower 114; the turbine high-pressure cylinder 102 is connected to the turbine intermediate-pressure cylinder 103, turbine low-pressure cylinder 104, and generator 113 via a mechanical shaft; the main steam side outlet, reheat steam side outlet, and reheat steam side inlet pipe of boiler 101 are respectively connected to the extraction steam pipe through extraction valve B 302, extraction steam valve A 301, and extraction steam valve C 303; the extraction steam pipe is respectively connected to the hot fluid side of peak heater 204 and the absorption heat pump 205 generator through regulating valve A 318 and regulating valve B 319; the hot fluid side outlet of peak heater 204 and the absorption heat pump 205 generator are respectively connected to the generator. 5. All generator outlets are connected to deaerator 110; high-temperature heat storage tank 201 is connected in sequence to variable frequency water pump A 323, high-temperature valve 328, peak heater 204 (cold fluid side), control valve C 316, control valve D 315, control valve E 314, variable frequency water pump C 313, and medium-temperature heat storage tank 202; the outlet of the cold fluid side of peak heater 204 is connected in sequence to control valve G 317, auxiliary heater A 206 (hot fluid side), auxiliary heater B 207 (hot fluid side), variable frequency water pump B 322, and low-temperature heat storage tank 203; the pipeline between control valve D 315 and control valve E 314 is connected in sequence to control valve G 310, heat user 208, variable frequency water pump B 322, and low-temperature heat storage tank 203;The pipeline between control valve D315 and control valve E314 is also connected in sequence to control valve F309, variable frequency water pump D311, and the hot fluid side outlet of auxiliary heater A206; the low-temperature heat storage tank 203 is connected in sequence to variable frequency water pump B322, control valve H320, absorption heat pump 205 absorber, and absorption heat pump 205 condenser; the pipeline between control valve C316 and control valve D315 is connected to the outlet of absorption heat pump 205 condenser; the outlet pipeline of cooling tower 114 is connected in sequence to the inlet pipeline of cooling tower 114 through cooling valve 308 and absorption heat pump 205 evaporator; the outlet pipeline of condensate pump 115 is connected in sequence to condensate valve C307, the cold fluid side of auxiliary heater B207, the cold fluid side of auxiliary heater A206, and deaerator 110; the pipe-side outlet of sixth-stage heater 107 is connected in sequence to condensate valve The cold fluid side outlet pipes of the valve 305, variable frequency water pump 312, and auxiliary heater 207 are connected in sequence; the condenser outlet pipe of the absorption heat pump 205 is also connected in sequence to the regulating valve 321, the evaporator of the electric heat pump 209, the variable frequency water pump 322, and the low-temperature heat storage tank 203; the cold fluid side outlet pipe of the peak heater 204 is also connected in sequence to the condenser of the electric heat pump 209, the electric heat pump valve 324, the variable frequency water pump 326, and the peak heat storage tank 210; the peak heat storage tank 210 is connected in sequence to the variable frequency water pump 326, the peak valve 327, the hot fluid side of the auxiliary heater 211, and the hot fluid side of the auxiliary heater 206; the outlet pipe of the water pump 116 is also connected in sequence to the water supply valve 329, the cold fluid side of the auxiliary heater 211, and the pipe side outlet pipe of the first-stage heater 112; the generator 113 is connected in sequence to the electric heat pump switch 325 and the electric heat pump 209 via a circuit. Based on the system configuration of the above invention, the return water of the heating network can be heated in a cascade manner by absorption heat pumps, peak heaters, and electric heat pumps, thereby achieving the orderly cascade utilization of system energy.

[0018] To more scientifically and effectively develop the economic and flexibility potential of the integrated multi-stage thermal energy storage and heat pump cogeneration system, the system operates as follows during the heating season's energy storage phase, i.e., the off-peak electricity period: absorption heat pump 205, electric heat pump 209, and peak heater 204 are in operation, while auxiliary heaters A 206, B 207, and C 211 are not. Control valves G 317, F 309, D 305, C 307, D 311, E 312, peak valve 327, and B 329 are closed, thus preventing flow in the pipelines containing auxiliary heaters A 206, B 207, and C 211, meaning they are not operating. Based on the heat load level and power generation demand during off-peak periods, only one of the following valves—extraction valve A 301, extraction valve B 302, and extraction valve C 303—is opened and adjusted to ensure stable extraction steam heat source pressure and match the required extraction steam temperature. The opening of control valve G 310 is adjusted according to the user's heat load to ensure the hot water flow through user 208 meets the user's heat demand. Adjusting variable frequency pump C 313 and control valve E 314 allows excess medium-temperature hot water flowing through control valve D 315 to flow into medium-temperature heat storage tank 202 for storage, thus ensuring sufficient medium-temperature heat source to adjust the ratio of heat supply to auxiliary heating condensate during the energy release phase. This allows for more flexible and efficient operation and switching of the system under varying external heat and electrical load conditions. Adjusting variable frequency pump B 322 and control valve H 320 according to the energy storage time allows the cold water stored in low-temperature heat storage tank 203 to... The system can fully release energy within the storage period, ensuring that all water stored in the low-temperature thermal storage tank 203 can be heated throughout the entire storage period. The opening of control valves D 315 and C 316 is adjusted according to the total heat load of the entire round-trip energy release cycle to ensure that the medium-temperature water stored in the medium-temperature thermal storage tank 202 meets the user's heat load requirements during the energy release phase, thus achieving deep decoupling of the system's thermal and electrical energy flow control. The opening of control valves A 318 and B 319 is adjusted to ensure that the outlet temperature of the hot fluid in the peak heater 204 is consistent with the outlet temperature of the generator-driven fluid in the absorption heat pump 205, thereby reducing the risk of heat loss during the mixing process of the two fluids. Losses; adjust the opening of cooling valve 308 to ensure that the flow rate of refrigerant water into the evaporator of absorption heat pump 205 meets the demand, thereby recovering part of the low-grade waste heat of condenser 105; close electric heat pump switch 325 and adjust its gear, while adjusting the opening of control valve 321 and electric heat pump valve 324 to ensure that the overall power generation of the system meets the load demand during the off-peak period; adjust the flow direction and flow rate of variable frequency water pump 326 so that all the working fluid passing through the condenser of electric heat pump 209 flows to the peak heat storage tank 210 for storage, thereby maximizing the proportion of auxiliary heating water supply during the energy release stage, i.e., the peak power period, and further increasing the power generation of the system during the peak power period; adjust the flow rate and flow rate of variable frequency water pump 323 and the opening of high temperature valve 328 according to the cold fluid flow rate of peak heater 204 so that all the remaining working fluid flowing through the cold fluid side of peak heater 204 is stored in high temperature heat storage tank 201. By adopting the above operating mode, the system can ensure that while completing the task of external heating during the energy storage phase, it can also rationally and efficiently store thermal energy of different energy levels, thus preparing for increased power output during the energy release phase.

[0019] In order to more scientifically and effectively develop the economic and flexibility potential of the integrated multi-stage thermal energy storage and heat pump linkage cogeneration system, the system operates in the following manner during the heating season energy release phase, i.e., the peak electricity period: the absorption heat pump 205, the electric heat pump 209, and the peak heater 204 do not work, while the auxiliary heater A 206, the auxiliary heater B 207, and the auxiliary heater C 211 work. Close extraction valves A301, B302, C303, H320, D315, C316, 308, I321, and 324; disconnect the electric heat pump switch 325. This prevents flow in the pipelines containing the absorption heat pump 205, peak heater 204, and electric heat pump 209, cutting off their operation. Open control valves G317, F309, and peak valve 327. Adjust the flow direction and flow rate of variable frequency water pump F326 and peak valve 327 to direct the working fluid in peak heat storage tank 210 to the hot fluid side of auxiliary heater C211. Simultaneously adjust feedwater valves B329 and A330 to ensure the working fluid temperature at the cold fluid outlet of auxiliary heater C211 matches the fluid temperature at the tube outlet of the first-stage heater 112, thus guaranteeing the mixing process. To minimize losses, adjust the opening degrees of condensate valves D305, C307, B304, and A306; adjust the opening degree of control valve F309; and adjust the flow direction and flow rate of variable frequency pumps D311 and E312 to ensure that the outlet temperature of the hot fluid in auxiliary heater B207 matches the outlet temperature of the working fluid in heat user 208, thereby guaranteeing the mixing process. To minimize losses, the cold fluid outlet temperatures of auxiliary heaters A 206 and B 207 are consistent with the outlet working fluid temperatures of the fourth-stage heater 109 and the sixth-stage heater 107, respectively. This ensures that the external heating process of condensate maximizes the thermal economy of the cogeneration unit, maximizes safety, and meets the external electrical load demand. Adjusting the flow direction and flow rate of variable frequency pump A 323 and the opening of high-temperature valve 328 allows high-temperature water to flow out of the high-temperature storage tank 201 at a flow rate consistent with that of control valve G 317. The opening degrees are matched to ensure the safety of the pipeline and the economy of the system; the opening degrees of regulating valves E314 and G310 are adjusted to ensure that the system's heat supply meets the needs of heat user 208; the flow direction and flow rate of variable frequency water pump C313 are adjusted to ensure that the medium-temperature water in the medium-temperature heat storage tank 202 flows out and the flow rate matches the opening degree of regulating valve E314, thus ensuring the safety of the pipeline and the economy of the system; the flow direction and flow rate of variable frequency water pump B322 are adjusted to ensure that the cold water in its pipeline flows into the low-temperature heat storage tank 203 for storage. Through the reasonable matching of the operating method and system configuration, this invention can realize flexible and efficient switching of the operating mode of the cogeneration unit during peak and off-peak periods in the heating season, with a large peak shaving depth and flexible parameter adjustment.

Claims

1. A combined heat and power system integrating multi-stage thermal energy storage and heat pump linkage, characterized in that: Including the following components connected in sequence: boiler (101) main steam side, turbine high-pressure cylinder (102), boiler (101) reheat steam side, turbine intermediate-pressure cylinder (103), turbine low-pressure cylinder (104), condenser (105) shell side, condensate pump (115), condensate valve A (306), seventh-stage heater (106) tube side, sixth-stage heater (107) tube side, condensate valve B (304), fifth-stage heater (108) tube side, fourth-stage heater (109) tube side, deaerator (110), feedwater pump (116), feedwater valve A (330), second-stage heater (111) tube side, first-stage heater (112) tube side, boiler (101) On the feedwater side; the exhaust pipe of the high-pressure cylinder (102) of the steam turbine is connected to the shell side of the first-stage heater (112) through the first-stage regenerative extraction pipe; the second-stage extraction pipe and the third-stage extraction pipe of the intermediate-pressure cylinder (103) of the steam turbine, with the pressure decreasing sequentially, are connected to the shell side of the second-stage heater (111) and the deaerator (110) respectively; the fourth-stage, fifth-stage, sixth-stage, and seventh-stage extraction pipes of the low-pressure cylinder (104) of the steam turbine, with the pressure decreasing sequentially, are connected to the shell side of the fourth-stage heater (109), the shell side of the fifth-stage heater (108), the shell side of the sixth-stage heater (107), and the shell side of the seventh-stage heater (106) respectively; the shell side outlet of the first-stage heater (112) is connected to the first-stage heater (112) through the drain pipe. The shell side of the secondary heater (111) and the deaerator (110) are connected in sequence through a drain pipe to the shell side of the fifth-stage heater (108), the shell side of the sixth-stage heater (107), the shell side of the seventh-stage heater (106), and the shell side of the condenser (105); the tube side of the condenser (105) is connected to the cooling tower (114); the high-pressure cylinder (102) of the steam turbine is connected to the intermediate-pressure cylinder (103), the low-pressure cylinder (104), and the generator (113) of the steam turbine through a mechanical shaft; the main steam side outlet, the reheat steam side outlet, and the reheat steam side inlet pipe of the boiler (101) are respectively connected to the extraction valve B (302) and the extraction valve A (301). The extraction steam valve (303) is connected to the extraction steam pipeline. The extraction steam pipeline is connected to the hot fluid side of the peak heater (204) and the absorption heat pump (205) generator through the control valve (318) and control valve (319) respectively. The outlet of the hot fluid side of the peak heater (204) and the outlet of the absorption heat pump (205) generator are both connected to the deaerator (110). The high temperature heat storage tank (201) is connected in sequence to the variable frequency water pump (323), the high temperature valve (328), the cold fluid side of the peak heater (204), the control valve (316), the control valve (315), the control valve (314), the variable frequency water pump (313), and the medium temperature heat storage tank (202).The cold fluid side outlet of the peak heater (204) is sequentially connected to the control valve Gui (317), the hot fluid side of the auxiliary heater A (206), the hot fluid side of the auxiliary heater B (207), the variable frequency water pump B (322), and the low-temperature heat storage tank (203); the pipeline between the control valve Ding (315) and the control valve Wu (314) is sequentially connected to the control valve Geng (310), the heat user (208), the variable frequency water pump B (322), and the low-temperature heat storage tank (203); the pipeline between the control valve Ding (315) and the control valve Wu (314) is also sequentially connected to the control valve Ji (309), the variable frequency water pump Ding (310), and the variable frequency water pump D (314). 11) The hot fluid side outlet of auxiliary heater A (206); the low temperature heat storage tank (203) is connected in sequence to variable frequency water pump B (322), control valve Xin (320), absorption heat pump (205) absorber, and absorption heat pump (205) condenser; the pipe between control valve C (316) and control valve D (315) is connected to the outlet of absorption heat pump (205) condenser; the outlet pipe of cooling tower (114) is connected in sequence to the inlet pipe of cooling tower (114) through cooling valve (308) and absorption heat pump (205) evaporator; the outlet pipe of condensate pump (115) is connected in sequence to the condensate pump (205) condenser. Condensation valve C (307), auxiliary heater B (207) cold fluid side, auxiliary heater A (206) cold fluid side, and deaerator (110) are connected in sequence; the outlet of the sixth stage heater (107) pipe side is connected in sequence to condensate valve D (305), variable frequency water pump E (312), and the outlet pipe of auxiliary heater B (207) cold fluid side; the outlet pipe of the absorption heat pump (205) condenser is also connected in sequence to regulating valve I (321), electric heat pump (209) evaporator, variable frequency water pump B (322), and low temperature heat storage tank (203); the outlet pipe of the peak heater (204) cold fluid side is also connected in sequence to electric The heat pump (209) includes a condenser, an electric heat pump valve (324), a variable frequency water pump (326), and a peak heat storage tank (210). The peak heat storage tank (210) is sequentially connected to the variable frequency water pump (326), the peak valve (327), the hot fluid side of the auxiliary heater (211), and the hot fluid side of the auxiliary heater (206). The outlet pipe of the feed water pump (116) is also sequentially connected to the feed water valve (329), the cold fluid side of the auxiliary heater (211), and the outlet pipe of the first-stage heater (112). The generator (113) is sequentially connected to the electric heat pump switch (325) and the electric heat pump (209) via a circuit.

2. The operation method of a combined heat and power system integrating multi-stage thermal energy storage and heat pump linkage according to claim 1, characterized in that: During the energy storage phase of the heating season, which is also the off-peak electricity period, the absorption heat pump (205), electric heat pump (209), and peak heater (204) are in operation, while auxiliary heaters A (206), B (207), and C (211) are not in operation; control valves G (317), F (309), D (305), C (307), D (311), E (312), peak valve (327), and B (329) are closed; and the extraction steam valve is opened and adjusted according to the heat load level and the power generation demand during the off-peak electricity period. One of valves, valve A (301), valve B (302), and valve C (303), adjusts the opening of valve G (310) according to the user's heat load, so that the hot water flow through the user (208) meets the user's heat demand; adjusts variable frequency pump C (313) and valve E (314) so ​​that excess medium-temperature hot water flowing through valve D (315) flows into medium-temperature heat storage tank (202) for storage; adjusts variable frequency pump B (322) and valve H (320) according to the energy storage time so that the cold water stored in the low-temperature heat storage tank (203) can be fully released within the energy storage time. Release; adjust the opening of control valves D (315) and C (316) according to the total heat load of the entire round-trip cycle of energy storage and release so that the medium-temperature water stored in the medium-temperature heat storage tank (202) meets the user's heat load requirements during the energy release stage; adjust the opening of control valves A (318) and B (319) so that the hot fluid outlet temperature of the peak heater (204) and the generator drive fluid outlet temperature of the absorption heat pump (205) are consistent; adjust the opening of the cooling valve (308) so that the flow rate of the refrigerant water flowing into the evaporator of the absorption heat pump (205) meets the requirements; close the electric heat pump switch (325). Adjust its gear and simultaneously adjust the opening of the control valve (321) and the electric heat pump valve (324) so ​​that the overall power generation of the system meets the load demand during the power off-peak period. Adjust the flow direction and flow rate of the variable frequency water pump (326) so that all the working fluid passing through the condenser of the electric heat pump (209) flows to the peak heat storage tank (210) for storage. Adjust the flow rate and flow rate of the variable frequency water pump (323) and the opening of the high temperature valve (328) according to the cold fluid flow rate of the peak heater (204) so ​​that all the remaining working fluid flowing through the cold fluid side of the peak heater (204) is stored in the high temperature heat storage tank (201).

3. The operation method of a combined heat and power system integrating multi-stage thermal energy storage and heat pump linkage according to claim 1, characterized in that: During the energy release phase of the heating season, i.e., the peak electricity consumption period, the absorption heat pump (205), electric heat pump (209), and peak heater (204) are not in operation, while auxiliary heaters A (206), B (207), and C (211) are in operation; the extraction valves A (301), B (302), C (303), H (320), D (315), C (316), cooling valve (308), I (321), and electric heat pump valve (324) are closed, and the electric heat pump switch (325) is disconnected; the control valves G (206), D (315), C (316), cooling valve (308), I (321), and electric heat pump valve (324) are opened. 317) Adjust valve F (309) and peak valve (327); adjust the flow direction and flow rate of variable frequency water pump F (326), adjust peak valve (327) so that the working fluid in peak heat storage tank (210) flows to the hot fluid side of auxiliary heater C (211), and at the same time adjust feed water valve B (329) and feed water valve A (330) so that the temperature of the working fluid at the outlet of the cold fluid side of auxiliary heater C (211) is consistent with the fluid temperature at the outlet of the tube side of the first stage heater (112); adjust condensate valve D (305), condensate valve C (307), condensate valve B (304) and condensate valve Adjust the opening of valve A (306), adjust the opening of control valve F (309), and adjust the flow direction and flow rate of variable frequency water pump D (311) and variable frequency water pump E (312) so that: the hot fluid outlet temperature of auxiliary heater B (207) is consistent with the outlet working fluid temperature of heat user (208), and the cold fluid outlet temperatures of auxiliary heater A (206) and auxiliary heater B (207) are consistent with the outlet working fluid temperatures of the fourth stage heater (109) and the sixth stage heater (107) respectively, so that the system power generation meets the external power load demand; adjust the flow direction and flow rate of variable frequency water pump A (323), and adjust the high temperature valve The opening degree of valve (328) allows high-temperature water to flow out of the high-temperature heat storage tank (201) and the flow rate to match the opening degree of control valve Gui (317); the opening degree of control valve Wu (314) and control valve Geng (310) is adjusted so that the system heat supply meets the needs of heat users (208); the flow direction and flow rate of variable frequency water pump Bing (313) are adjusted so that medium-temperature water to flow out of the medium-temperature heat storage tank (202) and the flow rate to match the opening degree of control valve Wu (314); the flow direction and flow rate of variable frequency water pump Yi (322) are adjusted so that the cold water in its pipeline flows into the low-temperature heat storage tank (203) for storage.

Citation Information

Patent Citations

  • Heat supply unit thermoelectricity decoupling system and running method thereof

    CN109579112A

  • Thermoelectric cooperation system of coupling compressor unit and operation method

    CN114233420A