An intelligent team business integrated management information system for large hydropower plants

Through the intelligent team business comprehensive management information system and combined with multiple management modules, automatic collection and feedback of tasks are achieved, the problem of low task execution efficiency in traditional hydropower plant management methods is solved, and the transparency and management efficiency of team work are improved. .

CN117787878BActive Publication Date: 2024-11-01CHINA YANGTZE POWER
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202311359064.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-10-19
Publication Date
2024-11-01
Estimated Expiration
2043-10-19

AI Technical Summary

Technical Problem

The management methods of the comprehensive business information system of traditional hydropower plants are chaotic, resulting in low efficiency in team tasks, prone to errors and untimely feedback.

Method used

Design an intelligent team business comprehensive management information system for large hydropower plants. Through the combination of task management module, production management module, safety management module, project management module, group management module and comprehensive management module, automatic collection of tasks is achieved. , dispatch, execution and feedback, provide task ledger, schedule, personal log, class meeting functions and other modules to ensure transparency and efficiency of task execution.

Benefits of technology

It improves the efficiency of team work execution, simplifies business processes, reduces task errors and omissions, and ensures timely feedback on tasks and effective supervision by management departments.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117787878B_ABST
    Figure CN117787878B_ABST
Patent Text Reader

Abstract

The present invention discloses an intelligent integrated business management information system for large hydropower plants. The system establishes independent modules based on the management functions of the management departments of the hydropower plants, and integrates all tasks to be executed or to be fed back through the task management module. Through the designed specific interface and task feedback component, each management department can issue task instructions in its own module, and the system automatically collects them into the task module. After the task is assigned and executed, the task execution status is fed back by calling the result feedback component of each module. After the task execution status is confirmed by the corresponding task issuer, it is fed back to the task management module, and the task is completed. In combination with authority management, each management department only needs to pay attention to the corresponding module, and the team only needs to pay attention to the task management module. Each department focuses on the specific part of the entire event that it is responsible for, which greatly simplifies the originally complex business process and can ensure the accuracy and high efficiency of the task at the same time.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of hydropower station operation management, in particular to an intelligent team business comprehensive management information system for large hydropower plants. Background Art

[0002] Information technology plays a vital role in improving the power generation efficiency, reliability and sustainability of hydropower stations. As the main production department of hydropower stations, the team is particularly important for the management and support of all aspects of the team's daily work. At present, the traditional comprehensive business information system of hydropower plants arranges or requires the team's business execution from the perspective of management. From the perspective of the team, the team accepts tasks from various management departments or management levels, and the task execution methods, feedback channels and requirements are different. During the busy maintenance period, there are often situations where task execution and feedback are not timely. Therefore, it is necessary to design an intelligent team business comprehensive management information system for large hydropower plants to solve the above problems, so that the system can not only meet the management requirements of hydropower plants, but also be based on the daily work of hydropower plant teams, comprehensively support all aspects of the team's business, and improve the team's work execution efficiency. Summary of the invention

[0003] The purpose of the present invention is to provide an intelligent team business comprehensive management information system for large hydropower plants. This solution solves the problems of the prior art hydropower plant team operation and maintenance scheduling management method being chaotic, prone to errors and omissions, and low in efficiency; it has the characteristics of being able to connect all aspects of the hydropower plant's business from the team's perspective and solve execution problems from the execution level, which can not only improve the management level, but also improve the work efficiency of the hydropower plant.

[0004] In order to solve the above technical problems, the technical solution of the present invention is:

[0005] An intelligent integrated management information system for team business of large hydropower plants, including a task management module, which is connected with a production management module, a safety management module, a project management module, a group management module and an integrated management module through an interface; the task management module includes a task ledger function module, a schedule function module, a personal log function module, a class meeting function module and a task template function module;

[0006] The task ledger function module includes multiple function modules: task creation function module, task assignment function module, task execution function module and task completion function module;

[0007] The task creation function module is connected to the internal system. Each management module issues task instructions in its own module. The system automatically collects them into the task module through the corresponding interface. After the task is assigned and executed, the result feedback component of each module is called to feedback the task execution status. After the task execution status is confirmed by the corresponding task issuer, it is fed back to the task management module and the task is completed.

[0008] The production management module includes multiple functional modules: annual maintenance plan functional module, production task notification functional module, defect work order functional module, tool management functional module, operation knowledge base functional module and basic data functional module;

[0009] The safety management module includes multiple functional modules: safety target management function module, safety organizational structure function module, safety qualification function module, laws and regulations function module, hidden danger investigation and treatment function module, risk control function module and natural disaster early warning management function module;

[0010] The project management module includes multiple functional modules: project information management module, project classification module, project node template module, project progress module, outsourcing unit management module and training and examination module;

[0011] The group management module includes multiple functional modules, including dual organizational life account function module, rationalization suggestion function module, suggestion box function module, comment and voting function module and team culture function module;

[0012] The comprehensive management module includes multiple functional modules, including duty work functional module, key work functional module, business application functional module, human resources management functional module, skill management functional module, and meeting management functional module.

[0013] Preferably, the scheduling function module provides different task viewing perspectives for different roles:

[0014] For task managers, check the execution status of assigned tasks in the Gantt chart;

[0015] For task executors, they can view the basic information and time requirements of the tasks they need to perform in the Gantt chart.

[0016] Preferably, the personal log function module records the task execution process; when the system creates a task, it breaks down the completion steps and completion elements of the task, and when the executor fills in the log, he records the day's work content and progress by checking the steps or elements; when all steps and matters are completed, the task summary page of the corresponding module is automatically called up to provide completion summary feedback for the corresponding module.

[0017] Preferably, the class meeting function module realizes the daily pre-shift work arrangement and safety precautions publicity, as well as the post-shift work completion summary; the system automatically generates the content of the pre-shift meeting work arrangement based on the tasks that have been assigned but not yet completed in the current task ledger, or it can be manually adjusted by the user.

[0018] Preferably, the process of the task template function module is as follows:

[0019] For tasks that need to be issued repeatedly or periodically, users can create task templates in advance and then reference the task templates when creating tasks; or automatically create tasks according to the creation cycle set in the task template.

[0020] Preferably, the specific process of the production management module is as follows:

[0021] S101, the annual maintenance plan function module realizes the function of annual maintenance plan arrangement for hydropower plant equipment; the details are as follows:

[0022] a. The system synchronizes the external production management system data source to obtain the annual maintenance plan content;

[0023] b. The system creates a production task notification according to the advance reminder operation mode of the annual planned project start time;

[0024] c. Operation mode initiates the task notification creation process, adding other equipment directors and factory leaders who need to be reviewed;

[0025] d. After the notification form is created, each branch will adjust the network diagram of the standard maintenance according to the content of the notification form. After being reviewed and approved by each production department, the system will automatically create an annual maintenance task for each team;

[0026] S102, the production task notification function module realizes the daily production task notification issuance process of the production management department; the details are as follows:

[0027] Users of the production management department can manually create production task notifications here; different from the production task notifications of the annual maintenance plan, the task notifications created here can be sent to a certain profession or department. If sent to a department, the department users will decompose the task notification content to the relevant divisions for execution; the task notifications created here are not associated with relevant network diagrams;

[0028] S103, the defect work order function module obtains defect work orders from the external production system, reminds relevant professionals to handle them, and classifies and queries unprocessed and processed defects;

[0029] S104, the tool management function module combines with relevant hardware to realize the non-contact in-and-out registration management of tools between teams; the details are as follows:

[0030] The system is equipped with a facial recognition access control system. After the identity is recognized, the sensing device at the access control system determines the materials carried by the user when entering and leaving. Combined with the materials on the shelves when entering and leaving, the system automatically deduces the return and use of tools during the user's entry and exit, and generates the corresponding entry or exit order. At the same time, the system provides tool room management functions such as cargo location guidance, misplacement reminders, use approval, and intelligent inventory.

[0031] S105, the operation knowledge base function module realizes the connection with the relevant attachments of the production system; the details are as follows:

[0032] By setting relevant rules, intelligent label classification of documents and materials is performed to form a knowledge base function based on knowledge graph; through a simple question model, question-and-answer document or knowledge search capabilities are realized;

[0033] S106, the basic data function module realizes the function of defining the information of the maintenance project library, standard operating procedures, warehouse files and material files.

[0034] Preferably, the specific process of the security management module is as follows:

[0035] S201, the safety target management function module realizes the safety target management of all levels of the hydropower plant throughout the year; the details are as follows:

[0036] Users can create a safety goal template in advance, select the corresponding goal in the template every year, and automatically generate the goal management tasks for the year;

[0037] S202, the safety organization structure function module realizes the management of the safety organization and personnel of the hydropower plant; the details are as follows:

[0038] The system realizes the binding of organizational positions and power plant positions. When positions are adjusted, the system automatically updates the personnel in the corresponding positions of the safety organization;

[0039] S203, the safety qualification function module realizes the registration of special operation personnel and safety management personnel qualifications of power plants, as well as the management and reminder of the re-certification time and validity period;

[0040] S204, the legal system function module realizes the maintenance of laws, regulations, standards, management systems and other legal system information, and the system synchronizes external data sources to realize automatic content update;

[0041] S205, the hidden danger investigation and management function module realizes safety inspection and hidden danger management; the details are as follows:

[0042] The system provides the function of registering daily or special safety inspection records. Hidden dangers found during the inspection can also be registered in the safety inspection records, and the system automatically collects them into the hidden danger rectification module. In the hidden danger rectification function, users can also manually add hidden dangers, and the system will automatically create hidden danger rectification tasks in the task ledger according to the hidden danger rectification content. At the same time, the system also provides an external data synchronization interface, and users can manually select hidden danger rectification information to synchronize to the external system;

[0043] S206, the risk management function module realizes the management of the operation activity risk and equipment and facility risk library; the details are as follows:

[0044] In the pre-shift (post-shift) meeting, it can be cited to identify the risks of the team's work. At the same time, the risks identified in the pre-shift (post-shift) meeting will be marked on the work activity risk map, and a tabular work activity dashboard will be provided for users to query. In addition, in order to ensure a certain degree of flexibility in risk identification in the daily work of the team, the system provides management of the branch work activity risk library and the branch equipment and facility risk library. The team can add frequently used risk items to its own library in advance for easy daily reference. At the same time, risks that are not covered in the standard library can also be added to its own risk library in advance. After that, the Safety Supervision Department will iteratively update the standard risk library on an annual basis based on the newly added risk items of each team;

[0045] S207, the natural disaster warning function module realizes the definition of various warning levels of various natural disasters, the corresponding action measures of each team, and the action record when the warning is generated; the forecast information of natural disasters can be obtained from external data sources.

[0046] Preferably, the specific process of the project management module is as follows:

[0047] S301, the project information management function module defines and edits basic project information, progress node information and project manager information, and also supports obtaining information from external data sources;

[0048] S302, the project classification function module implements the project classification definition, and sets the corresponding project category when setting the classification, so that the system automatically classifies the project according to the category;

[0049] S303, the project node template function module realizes the personalized customization requirements of different project progress nodes. Users set different types of node templates, define the corresponding project nodes and the attachment materials required for node achievement in the template. When referenced to the project, the project automatically controls the project progress according to the node;

[0050] S304, the project progress management function module implements the following functions: managing the requirements for uploading the required documents and materials for the node and submitting them for review when the project progress node of the outsourcing unit is completed;

[0051] S305, the outsourcing unit module implements outsourcing unit information management, outsourcing unit project manager management, and outsourcing personnel management; when the outsourcing project manager is defined, the outsourcing unit subsystem login account is automatically generated;

[0052] S306, the training and examination module realizes the business needs of the power plant for safety education and training examinations for outsourced personnel; the details are as follows:

[0053] Power plant personnel can assign training and examination tasks to corresponding outsourced project managers. The outsourced project managers organize training and examinations offline and upload attachments and training and examination results to the system. After approval and confirmation by relevant personnel of the hydropower plant, the training and examination records take effect.

[0054] Preferably, the specific process of the comprehensive management module is as follows:

[0055] S401, the key work module realizes the task arrangement and work reporting of key work and supervision work; among them, key work and supervision work automatically create tasks for relevant reporters according to the definition in the work report configuration, and the reporter records and feedbacks the information execution process in the task management;

[0056] S402, the business application function module realizes the functions of power plant official vehicle application, mailing application, overtime meal application and application information statistics;

[0057] S403, the human resources management function module realizes the synchronization of external data source information, and realizes the functions of employee basic information query, employee birthday reminder and reserve cadre application;

[0058] S404, the skill management module realizes the relevant business management of power plant staff learning, training and examination; including the functions of learning material management, training plan, question bank management, examination management and expert database;

[0059] S405, the conference management module implements the internal conference management business of the hydropower plant, including conference room management, conference application, and conference arrangement functions.

[0060] The beneficial effects of the above-mentioned intelligent team business comprehensive management information system for large hydropower plants are as follows:

[0061] The present invention mainly establishes independent modules based on the management functions of the management departments of the hydropower plant. The production management department corresponds to production management, the safety supervision department corresponds to safety management, the project port of the production management department corresponds to project management, the general department corresponds to group management, and the general port of the general department corresponds to general management; task management is a collection of all tasks to be executed or to be fed back; through the designed specific interface and task feedback component, each management department can issue task instructions in its own module, and the system automatically collects them into the task module. After the task is assigned and executed, the task execution status is fed back by calling the result feedback component of each module; after the task execution status is confirmed by the corresponding task issuer, it is fed back to the task management module, and the task is completed; in this way, in conjunction with authority management, each management department only needs to pay attention to the corresponding module, and the team only needs to pay attention to the task management module. Each department focuses on the specific part of the entire event that it is responsible for, which can greatly simplify the originally complex business process, and at the same time ensure that the task is not missed or omitted, thereby greatly improving the execution efficiency of the task. BRIEF DESCRIPTION OF THE DRAWINGS

[0062] Figure 1 Schematic diagram of the system architecture of the present invention. DETAILED DESCRIPTION

[0063] like Figure 1 As shown, an intelligent team business integrated management information system for large hydropower plants includes a task management module, which is connected to a production management module, a safety management module, a project management module, a group management module and an integrated management module through an interface; the task management module includes a task ledger function module, a schedule function module, a personal log function module, a class meeting function module and a task template function module;

[0064] The task ledger function module includes multiple function modules: task creation function module, task assignment function module, task execution function module and task completion function module;

[0065] The task creation function module is connected to the internal system. Each management module issues task instructions in its own module. The system automatically collects them into the task module through the corresponding interface. After the task is assigned and executed, the result feedback component of each module is called to feedback the task execution status. After the task execution status is confirmed by the corresponding task issuer, it is fed back to the task management module and the task is completed.

[0066] The production management module includes multiple functional modules: annual maintenance plan functional module, production task notification functional module, defect work order functional module, tool management functional module, operation knowledge base functional module and basic data functional module;

[0067] The safety management module includes multiple functional modules: safety target management function module, safety organizational structure function module, safety qualification function module, laws and regulations function module, hidden danger investigation and treatment function module, risk control function module and natural disaster early warning management function module;

[0068] The project management module includes multiple functional modules: project information management module, project classification module, project node template module, project progress module, outsourcing unit management module and training and examination module;

[0069] The group management module includes multiple functional modules, including dual organizational life account function module, rationalization suggestion function module, suggestion box function module, comment and voting function module and team culture function module;

[0070] The comprehensive management module includes multiple functional modules, including duty work functional module, key work functional module, business application functional module, human resources management functional module, skill management functional module, and meeting management functional module.

[0071] Preferably, the scheduling function module provides different task viewing perspectives for different roles:

[0072] For task managers, check the execution status of assigned tasks in the Gantt chart;

[0073] For task executors, they can view the basic information and time requirements of the tasks they need to perform in the Gantt chart.

[0074] Preferably, the personal log function module records the task execution process; when the system creates a task, it breaks down the completion steps and completion elements of the task, and when the executor fills in the log, he records the day's work content and progress by checking the steps or elements; when all steps and matters are completed, the task summary page of the corresponding module is automatically called up to provide completion summary feedback for the corresponding module.

[0075] Preferably, the class meeting function module realizes the daily pre-shift work arrangement and safety precautions publicity, as well as the post-shift work completion summary; the system automatically generates the content of the pre-shift meeting work arrangement based on the tasks that have been assigned but not yet completed in the current task ledger, or it can be manually adjusted by the user.

[0076] Preferably, the process of the task template function module is as follows:

[0077] For tasks that need to be issued repeatedly or periodically, users can create task templates in advance and then reference the task templates when creating tasks; or automatically create tasks according to the creation cycle set in the task template.

[0078] Preferably, the specific process of the production management module is as follows:

[0079] S101, the annual maintenance plan function module realizes the function of annual maintenance plan arrangement for hydropower plant equipment; the details are as follows:

[0080] a. The system synchronizes the external production management system data source to obtain the annual maintenance plan content;

[0081] b. The system creates a production task notification according to the advance reminder operation mode of the annual planned project start time;

[0082] c. Operation mode initiates the task notification creation process, adding other equipment directors and factory leaders who need to be reviewed;

[0083] d. After the notification form is created, each branch will adjust the network diagram of the standard maintenance according to the content of the notification form. After being reviewed and approved by each production department, the system will automatically create an annual maintenance task for each team;

[0084] S102, the production task notification function module realizes the daily production task notification issuance process of the production management department; the details are as follows:

[0085] Users of the production management department can manually create production task notifications here; different from the production task notifications of the annual maintenance plan, the task notifications created here can be sent to a certain profession or department. If sent to a department, the department users will decompose the task notification content to the relevant divisions for execution; the task notifications created here are not associated with relevant network diagrams;

[0086] S103, the defect work order function module obtains defect work orders from the external production system, reminds relevant professionals to handle them, and classifies and queries unprocessed and processed defects;

[0087] S104, the tool management function module combines with relevant hardware to realize the non-contact in-and-out registration management of tools between teams; the details are as follows:

[0088] The system is equipped with a facial recognition access control system. After the identity is recognized, the sensing device at the access control system determines the materials carried by the user when entering and leaving. Combined with the materials on the shelves when entering and leaving, the system automatically deduces the return and use of tools during the user's entry and exit, and generates the corresponding entry or exit order. At the same time, the system provides tool room management functions such as cargo location guidance, misplacement reminders, use approval, and intelligent inventory.

[0089] S105, the operation knowledge base function module realizes the connection with the relevant attachments of the production system; the details are as follows:

[0090] By setting relevant rules, intelligent label classification of documents and materials is performed to form a knowledge base function based on knowledge graph; through a simple question model, question-and-answer document or knowledge search capabilities are realized;

[0091] S106, the basic data function module realizes the function of defining the information of the maintenance project library, standard operating procedures, warehouse files and material files.

[0092] Preferably, the specific process of the security management module is as follows:

[0093] S201, the safety target management function module realizes the safety target management of all levels of the hydropower plant throughout the year; the details are as follows:

[0094] Users can create a safety goal template in advance, select the corresponding goal in the template every year, and automatically generate the goal management tasks for the year;

[0095] S202, the safety organization structure function module realizes the management of the safety organization and personnel of the hydropower plant; the details are as follows:

[0096] The system realizes the binding of organizational positions and power plant positions. When positions are adjusted, the system automatically updates the personnel in the corresponding positions of the safety organization;

[0097] S203, the safety qualification function module realizes the registration of special operation personnel and safety management personnel qualifications of power plants, as well as the management and reminder of the re-certification time and validity period;

[0098] S204, the legal system function module realizes the maintenance of laws, regulations, standards, management systems and other legal system information, and the system synchronizes external data sources to realize automatic content update;

[0099] S205, the hidden danger investigation and management function module realizes safety inspection and hidden danger management; the details are as follows:

[0100] The system provides the function of registering daily or special safety inspection records. Hidden dangers found during the inspection can also be registered in the safety inspection records, and the system automatically collects them into the hidden danger rectification module. In the hidden danger rectification function, users can also manually add hidden dangers, and the system will automatically create hidden danger rectification tasks in the task ledger according to the hidden danger rectification content. At the same time, the system also provides an external data synchronization interface, and users can manually select hidden danger rectification information to synchronize to the external system;

[0101] S206, the risk management function module realizes the management of the operation activity risk and equipment and facility risk library; the details are as follows:

[0102] In the pre-shift (post-shift) meeting, it can be cited to identify the risks of the team's work. At the same time, the risks identified in the pre-shift (post-shift) meeting will be marked on the work activity risk map, and a tabular work activity dashboard will be provided for users to query. In addition, in order to ensure a certain degree of flexibility in risk identification in the daily work of the team, the system provides management of the branch work activity risk library and the branch equipment and facility risk library. The team can add frequently used risk items to its own library in advance for easy daily reference. At the same time, risks that are not covered in the standard library can also be added to its own risk library in advance. After that, the Safety Supervision Department will iteratively update the standard risk library on an annual basis based on the newly added risk items of each team;

[0103] S207, the natural disaster warning function module realizes the definition of various warning levels of various natural disasters, the corresponding action measures of each team, and the action record when the warning is generated; the forecast information of natural disasters can be obtained from external data sources.

[0104] Preferably, the specific process of the project management module is as follows:

[0105] S301, the project information management function module defines and edits basic project information, progress node information and project manager information, and also supports obtaining information from external data sources;

[0106] S302, the project classification function module implements the project classification definition, and sets the corresponding project category when setting the classification, so that the system automatically classifies the project according to the category;

[0107] S303, the project node template function module realizes the personalized customization requirements of different project progress nodes. Users set different types of node templates, define the corresponding project nodes and the attachment materials required for node achievement in the template. When referenced to the project, the project automatically controls the project progress according to the node;

[0108] S304, the project progress management function module implements the following functions: managing the requirements for uploading the required documents and materials for the node and submitting them for review when the project progress node of the outsourcing unit is completed;

[0109] S305, the outsourcing unit module implements outsourcing unit information management, outsourcing unit project manager management, and outsourcing personnel management; when the outsourcing project manager is defined, the outsourcing unit subsystem login account is automatically generated;

[0110] S306, the training and examination module realizes the business needs of the power plant for safety education and training examinations for outsourced personnel; the details are as follows:

[0111] Power plant personnel can assign training and examination tasks to corresponding outsourced project managers. The outsourced project managers organize training and examinations offline and upload attachments and training and examination results to the system. After approval and confirmation by relevant personnel of the hydropower plant, the training and examination records take effect.

[0112] Preferably, the specific process of the comprehensive management module is as follows:

[0113] S401, the key work module realizes the task arrangement and work reporting of key work and supervision work; among them, key work and supervision work automatically create tasks for relevant reporters according to the definition in the work report configuration, and the reporter records and feedbacks the information execution process in the task management;

[0114] S402, the business application function module realizes the functions of power plant official vehicle application, mailing application, overtime meal application and application information statistics;

[0115] S403, the human resources management function module realizes the synchronization of external data source information, and realizes the functions of employee basic information query, employee birthday reminder and reserve cadre application;

[0116] S404, the skill management module realizes the relevant business management of power plant staff learning, training and examination; including the functions of learning material management, training plan, question bank management, examination management and expert database;

[0117] S405, the conference management module implements the internal conference management business of the hydropower plant, including conference room management, conference application, and conference arrangement functions.

[0118] The above-mentioned embodiments are only preferred technical solutions of the present invention and should not be regarded as limitations of the present invention. The embodiments and features in the embodiments of the present application can be arbitrarily combined with each other without conflict. The protection scope of the present invention shall be the technical solutions recorded in the claims, including the equivalent replacement solutions of the technical features in the technical solutions recorded in the claims. That is, equivalent replacement improvements within this scope are also within the protection scope of the present invention.

Claims

1. An intelligent team business integrated management information system for large hydropower plants. It is characterized in that It includes a task management module, which is connected with a production management module, a safety management module, a project management module, a group management module and a comprehensive management module through an interface; The task management module includes multiple function modules: task ledger function module, schedule function module, personal log function module, class meeting function module and task template function module; The schedule function module provides different task viewing perspectives for different roles: For task managers, check the execution status of assigned tasks in the Gantt chart; For task executors, they can view the basic information and time requirements of the tasks they need to perform in the Gantt chart; The personal log function module records the task execution process. When creating a task, the system breaks down the completion steps and elements of the task. When filling in the log, the executor records the day's work content and progress by checking the steps or elements. When all steps and items are completed, the task summary page of the corresponding module is automatically called up to provide completion summary feedback of the corresponding module. The class meeting function module implements the daily pre-shift work arrangements and safety precautions publicity, as well as the post-shift work completion summary; the system automatically generates the pre-shift work arrangement content based on the tasks that have been assigned but not yet completed in the current task ledger, or the user can manually adjust it; The process of the task template function module is as follows: For tasks that users need to issue repeatedly or periodically, they can create task templates in advance and then reference them when creating tasks. The task ledger function module includes multiple function modules: task creation function module, task assignment function module, task execution function module and task completion function module; The task creation function module is connected to the internal system. Each management module issues task instructions in its own module. The system automatically collects them into the task module through the corresponding interface. After the task is assigned and executed, the result feedback component of each module is called to feedback the task execution status. After the task execution status is confirmed by the corresponding task issuer, it is fed back to the task management module and the task is completed. The production management module includes multiple functional modules: annual maintenance plan function module, production task notification management function module, defect work order management function module, tool management function module, operation knowledge base management function module and basic data management function module; The specific process of the production management module is as follows: S101, the annual maintenance plan function module realizes the function of arranging the annual maintenance plan for hydropower plant equipment; S102, the production task notification function module realizes the daily production task notification issuance process of the production management department; S103, the defect work order function module obtains defect work orders from the external production system, reminds relevant professionals to handle them, and classifies and queries unprocessed and processed defects; S104, the tool management function module combines with relevant hardware to realize the non-contact in-and-out registration management of tools between teams; S105, the operation knowledge base function module realizes the connection with the relevant attachments of the production system; S106, the basic data function module realizes the function of defining the information of the maintenance project library, standard operating procedures, warehouse files and material files; The safety management module includes multiple functional modules: safety target management module, safety organizational structure management module, safety qualification management module, laws and regulations management module, hidden danger investigation and control module, risk management module and natural disaster early warning management module. The specific process of the safety management module is as follows: S201, the safety target management function module realizes the safety target management of all levels of the hydropower plant throughout the year; S202, the safety organization structure function module realizes the management of the safety organization and personnel of the hydropower plant; S203, the safety qualification function module realizes the registration of special operation personnel and safety management personnel qualifications of power plants, as well as the management and reminder of the re-certification time and validity period; S204, the legal system function module realizes the maintenance of laws, regulations, standards, specifications and management systems; at the same time, the system synchronizes external data sources to achieve automatic content updates; S205, the hidden danger investigation and management function module realizes safety inspection and hidden danger management; S206, the risk management function module realizes the management of the operation activity risk and equipment and facility risk library; S207, the natural disaster warning function module realizes the definition of various warning levels of various natural disasters, the corresponding action measures of each team, and the action record when the warning is generated; the forecast information of natural disasters can be obtained from external data sources; The project management module includes multiple functional modules: project information management module, project classification module, project node template management module, project progress management module, outsourcing unit management module and training and examination module. The specific process of the project management module is as follows: S301, the project information management function module defines and edits basic project information, progress node information and project manager information, and also supports obtaining information from external data sources; S302, the project classification function module implements the project classification definition, and sets the corresponding project category when setting the classification, so that the system automatically classifies the project according to the category; S303, the project node template function module realizes the personalized customization requirements of different project progress nodes. Users set different types of node templates, define the corresponding project nodes and the attachment materials required for node achievement in the template. When referenced to the project, the project automatically controls the project progress according to the node; S304, the project progress management function module implements the following functions: managing the requirements for uploading the required documents and materials for the node and submitting them for review when the project progress node of the outsourcing unit is completed; S305, the outsourcing unit module implements outsourcing unit information management, outsourcing unit project manager management, and outsourcing personnel management; when the outsourcing project manager is defined, the outsourcing unit subsystem login account is automatically generated; S306, the training and examination module realizes the business needs of the power plant for safety education and training examinations for outsourced personnel; The group management module includes multiple functional modules, including dual organizational life account management module, rationalization suggestion module, suggestion box module, comment and voting module and team culture module; The comprehensive management module includes multiple functional modules: duty work management module, key work management module, business application module, human resources management module, skill management module, and meeting management module. The specific process of the comprehensive management module is as follows: S401, the key work module implements the task arrangement and work reporting of key work and supervision work. Among them, key work and supervision work automatically create tasks for relevant reporters according to the definition in the work report configuration, and the reporter records and feedbacks the information execution process in the task management; S402, the business application function module realizes the functions of power plant official vehicle application, mailing application, overtime meal application and application information statistics; S403, the human resources management function module realizes the synchronization of external data source information, and realizes the functions of employee basic information query, employee birthday reminder and reserve cadre application; S404, the skill management module realizes the relevant business management of power plant staff learning, training and examination; including the functions of learning material management, training plan, question bank management, examination management and expert database; S405, the conference management module implements the internal conference management business of the hydropower plant, including conference room management, conference application, and conference arrangement functions.