A high-energy laser-sealed gas replacement system and method
By designing a high-energy laser sealed chamber gas replacement system, a combination of inlet and outlet pipes was used to achieve stable control of gas flow and cleanliness, solving the problem of unstable gas replacement in existing technologies, improving gas replacement efficiency and cleanliness, and protecting the integrity of optical components.
Patent Information
- Application Number
- CN202311872713.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-29
- Publication Date
- 2026-11-17
- Estimated Expiration
- 2043-12-29
AI Technical Summary
Existing high-energy laser sealed chamber gas replacement systems cannot stably control gas flow, requiring manual adjustment, lack negative pressure capability, and do not have gas clean filtration and detection functions, resulting in low efficiency and failing to meet the high cleanliness requirements of optical systems.
A high-energy laser-sealed gas replacement system is designed. By combining an inlet pipe and an outlet pipe, and utilizing a pressure reducing device, a precise flow control device, a filter, and a monitoring device, the gas pressure and flow rate are adjusted in real time to ensure gas cleanliness. Furthermore, by using a gas cleanliness detection device and a component detection device, stable gas input and appropriate extraction of contaminated gas are achieved.
It improves gas replacement capacity and efficiency, ensures the cleanliness and stability of the gas inside the chamber, avoids turbulent airflow, protects optical components from damage, and meets the high cleanliness requirements of optical systems.
Smart Images

Figure CN117927869B_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of optical system auxiliary equipment technology, and more specifically, relates to a high-energy laser sealed box gas replacement system and method. Background Technology
[0002] Some high-energy laser enclosures with complex optical systems have extremely high requirements for the humidity and cleanliness of the internal environment. Low humidity improves the beam quality of the optical system, while high cleanliness ensures that the surface coatings of the optical components are not damaged by high-energy laser irradiation. Therefore, the optical system enclosures are all sealed and require constant temperature, low humidity, and dust prevention. Due to the precision of the internal optical system, the gas flow rate entering the enclosure is critical to prevent disturbances in the internal airflow, which could cause contaminants to fall onto the optical components and damage their coatings. Therefore, stringent requirements are placed on the environment (temperature, humidity, gas medium, and gas pressure) within the sealed enclosure. To ensure the normal operation of the enclosure, it is necessary to provide gas replacement such as nitrogen, helium, or argon, with a stable and adjustable input flow rate, the ability to reduce the internal gas pressure, and online monitoring of gas cleanliness.
[0003] In related technologies, gas replacement in a sealed chamber is mainly achieved through direct filling of gas cylinders with pressure reducing valves. This method cannot control the stable input flow rate, requires manual adjustment, lacks negative pressure capability, and is both simplistic and inefficient. Furthermore, it lacks gas cleanliness filtration and detection functions, failing to meet the needs of existing projects.
[0004] Therefore, there is an urgent need to design a new type of protective gas replacement device to make up for the shortcomings of existing equipment, which can improve gas replacement capacity, replacement efficiency, gas cleanliness and negative pressure capacity of the chamber. Summary of the Invention
[0005] To address the problems of existing sealed-box gas replacement technologies, such as the inability to control stable flow input, the need for manual adjustment, lack of negative pressure capability, limited functionality and low efficiency, and the absence of gas cleanliness filtration and detection functions, this invention provides a high-energy laser sealed-box gas replacement system and method. By obtaining real-time gas pressure and cleanliness levels within the box, the system controls the intake pipeline to regulate the pressure, limit the flow rate, and further filter the input gas before it enters the box. Through the intake pipeline, the pressure, flow rate, and cleanliness of the input gas meet the environmental requirements within the box. Contaminated gas is then extracted from the box through an extraction pipeline. Flow and pressure monitoring devices monitor the gas pressure and flow rate, ensuring that the extracted contaminated gas flow rate matches the input gas flow rate, preventing turbulent airflow within the box. This system improves gas replacement capacity, efficiency, and gas cleanliness, thus solving these problems.
[0006] To achieve the aforementioned objective, according to a first aspect of the present invention, a high-energy laser sealed enclosure gas replacement system is provided, comprising an air inlet pipe disposed at the input end of the enclosure, the air inlet pipe comprising a pressure reducing device, a flow precision control device, and a first filter connected in a pipeline, the pressure reducing device adjusting the gas pressure in real time according to the operating conditions of the enclosure to control the gas flow rate to be stable, and ensuring the cleanliness of the gas through the first filter; and an exhaust pipe connected to the output end of the enclosure, the exhaust pipe comprising an exhaust device, a flow monitoring device, and a pressure monitoring device, the flow monitoring device and the pressure monitoring device monitoring the flow rate and pressure value inside the enclosure, and using the exhaust device to match the flow rate of the extracted contaminated gas with the flow rate of the input gas, thereby avoiding turbulent airflow inside the enclosure.
[0007] Furthermore, a gas cleanliness detection device is connected in parallel at the output end of the first filter to detect the cleanliness of the filtered gas.
[0008] Furthermore, the intake pipeline also includes a first valve, the input end of which is connected to a pressure reducing device, and the output end of which is connected to a flow precision control device.
[0009] Furthermore, the air intake pipeline also includes a gas flow meter, and the output end of the gas flow meter is provided with multiple sets of air intake branches in parallel; the output end of the air intake branch is connected to the line body, and it includes a third filter and a second valve connected in sequence through a pipe.
[0010] Furthermore, the intake branch is provided with four sets, and the input ends of the four sets of intake branches are respectively connected in parallel to the output end of the gas flow meter through a five-way connector.
[0011] Furthermore, the first filter has a particle filtration range of 1 to 2 μm, which performs coarse filtration on the input protective gas, and the third filter has a particle filtration range of 0.1 to 0.5 μm, which performs fine filtration on the input protective gas.
[0012] Furthermore, the gas extraction pipeline is also equipped with a gas composition detection device.
[0013] Furthermore, the intake pipe is equipped with multiple third valves in parallel at its input end, and the input ends of the multiple third valves are connected to a gas source of the corresponding type of gas. The number of the third valves is the same as the type of protective gas in the housing.
[0014] Furthermore, it also includes a mass spectrometer leak detector.
[0015] According to another aspect of the present invention, a method for gas replacement in a sealed enclosure using high-energy laser is also provided, comprising the following steps:
[0016] S100: Obtain the gas pressure and gas cleanliness inside the chamber;
[0017] S200: Introduces protective gas into the intake pipe for processing;
[0018] S300: The input protective gas is fed into the housing after the pressure is adjusted by the pressure device, the flow rate is adjusted by the precision control device, and the first filter is used to filter the gas to meet the requirements.
[0019] S400: Controls the extraction device to extract gas, and adjusts the extraction power of the extraction device according to the detection values of the flow monitoring device and the pressure monitoring device to make the extracted pollutant gas flow rate match the input gas flow rate.
[0020] S500: If the gas cleanliness of the chamber meets the standard, stop the replacement operation.
[0021] In summary, compared with the prior art, the above-described technical solutions conceived by this invention can achieve the following beneficial effects:
[0022] 1. The gas replacement system of the present invention obtains the gas pressure and gas cleanliness inside the chamber in real time, controls the intake pipeline to regulate the pressure, limit the flow rate, and further filter the gas input from the gas source before inputting it into the chamber. Through the processing of the intake pipeline, the pressure, flow rate, and cleanliness of the input gas meet the environmental requirements inside the chamber. The system extracts the contaminated gas from the chamber through the extraction pipeline. The system monitors the gas pressure and flow rate through flow monitoring devices and pressure monitoring devices to ensure that the flow rate of the extracted contaminated gas matches the flow rate of the input gas, thus avoiding turbulent airflow inside the chamber. This system can improve the gas replacement capacity, replacement efficiency, and gas cleanliness.
[0023] 2. The gas replacement system of the present invention, by providing a main intake path and multiple sets of intake branches, performs coarse filtration of the input protective gas through a first filter in the main intake path, and performs fine filtration of the input protective gas in the intake branches, thereby effectively ensuring the cleanliness of the input protective gas. Furthermore, by providing multiple sets of intake branches connected to the housing, the corresponding intake branches are controlled to open or close according to the flow rate measured by the gas flow meter. That is, when the flow rate is high, multiple sets of intake branches are controlled to open simultaneously to avoid excessive flow at a single intake port of the housing, which would cause turbulence and affect the stable environment inside the housing. When the flow rate is low, a few intake branches are controlled to open to prevent the input of clean protective gas and contaminated gas from being mixed due to excessive flow at multiple intake ports, which would prevent the contaminated gas from being discharged in time.
[0024] 3. The gas replacement system of the present invention detects the gas composition and concentration in the chamber by means of a gas composition detection device; multiple third valves are connected in parallel at the inlet end of the inlet pipe, and the inlet ends of the multiple third valves are connected to the gas source of the corresponding type of gas; when the gas composition detection device detects that the concentration of the corresponding type of protective gas has dropped to exceed the threshold, the control unit controls the corresponding third valve to open, introduce the corresponding type of protective gas into the exhaust pipe, and input the corresponding amount of protective gas under the action of the exhaust pipe, so that the concentration values of each protective gas in the chamber are within the threshold range, thereby ensuring the stability of the chamber environment, improving the beam quality, and ensuring that the surface film layer of the optical element is not damaged under the irradiation of high-energy laser. Attached Figure Description
[0025] Figure 1 This is a schematic diagram of a high-energy laser sealed box gas replacement system according to the first embodiment of the present invention;
[0026] Figure 2 This is a schematic diagram of the gas replacement system in the second embodiment of the present invention;
[0027] Figure 3 This is a schematic diagram of the intake pipe structure in the third embodiment of the present invention;
[0028] Figure 4 This is a flowchart illustrating the gas replacement method for a high-energy laser sealed box according to an embodiment of the present invention.
[0029] In all the accompanying drawings, the same reference numerals denote the same technical features, specifically: 1-box, 2-gas source, 3-inlet pipe, 301-pressure reducing device, 302-precision flow control device, 303-first filter, 304-gas cleanliness detection device, 305-first valve, 306-gas flow meter, 307-five-way connector, 308-third filter, 309-second valve, 310-connecting flange, 4-extraction pipe, 401-extraction device, 402-flow monitoring device, 403-pressure monitoring device, 404-second filter, 405-mass spectrometer leak detector. Detailed Implementation
[0030] To make the objectives, technical solutions, and advantages of this invention clearer, the invention will be further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative and not intended to limit the invention. Furthermore, the technical features involved in the various embodiments of this invention described below can be combined with each other as long as they do not conflict with each other.
[0031] like Figure 1-3As shown, this embodiment of the invention provides a high-energy laser sealed chamber gas replacement system, including a chamber 1, a gas source 2, an inlet pipe 3, an exhaust pipe 4, and a control unit. The inlet pipe 3 is connected to the gas source 2 at its input end and to the chamber 1 at its output end, and includes a pressure reducing device 301, a flow precision control device 302, a first filter 303, and a gas cleanliness detection device 304; the exhaust pipe 4 is connected to the chamber 1 at its input end and includes an exhaust device 401, a flow monitoring device 402, and a pressure monitoring device 403. When the gas replacement system of the present invention operates, it obtains the gas pressure and gas cleanliness value inside the chamber 1 in real time. The control unit controls the air intake pipe 3 to regulate the pressure, limit the flow rate, and further filter the gas input from the gas source 2 before inputting it into the chamber 1. Through the processing of the air intake pipe 3, the pressure, flow rate, and cleanliness of the input gas meet the environmental requirements inside the chamber 1. The exhaust pipe 4 extracts the contaminated gas from the chamber 1. The gas pressure and flow rate are monitored by the flow monitoring device 402 and the pressure monitoring device 403 to ensure that the flow rate of the extracted contaminated gas matches the flow rate of the input gas, avoiding turbulent airflow inside the chamber 1. The gas replacement system of the present invention can improve the gas replacement capacity, replacement efficiency, and gas cleanliness, and enhance the negative pressure capacity of the chamber.
[0032] As shown in Figure 1, in the first embodiment of the present invention, the housing 1 is equipped with a pressure detection module and a cleanliness detection module, which can detect the pressure and cleanliness inside the housing 1 respectively, and send the detection data to the control unit. The air inlet pipe 3 includes a pressure reducing device 301, a flow precision control device 302, a first filter 303, and a gas cleanliness detection device 304; wherein, the pressure reducing device 301, the flow precision control device 302, and the first filter 303 are connected in sequence through pipes. The input end of the pressure reducing device 301 is connected to the gas source 2, and the pressure of the high-pressure gas input from the gas source 2 is adjusted to make the gas pressure consistent with the gas pressure inside the housing 1; the flow precision control device 302 adjusts the flow rate of the depressurized gas, so that the gas is output at a specified flow rate, which ensures a stable gas flow rate input into the housing 1; the first filter 303 filters the gas after the flow rate adjustment, removing impurity particles from the gas, making the gas input into the housing 1 cleaner. The gas cleanliness detection device 304 is connected in parallel with the output of the first filter 303 to detect the cleanliness of the filtered gas. In this embodiment of the invention, the pressure reducing device 301 is a high-precision pressure reducing valve, and the flow precision control device 302 is a high-precision flow valve.
[0033] The extraction pipeline 4 includes an extraction device 401, a flow monitoring device 402, a pressure monitoring device 403, a second filter 404, and a mass spectrometer leak detector 405. The extraction device 401, flow monitoring device 402, pressure monitoring device 403, and second filter 404 are connected sequentially via pipelines, with the output end of the second filter 404 connected to the housing 1. The extraction device 401 extracts polluted gas from the housing 1 through the pipeline; the flow monitoring device 402 monitors the flow rate of the extracted polluted gas; the pressure monitoring device 403 monitors the pressure of the extracted polluted gas; and the second filter 404 filters the extracted polluted gas to prevent environmental pollution after discharge. By acquiring the internal pressure of chamber 1 and the flow rate of the gas input through inlet pipe 3, and with the monitoring feedback from flow monitoring device 402 and pressure monitoring device 403, the extraction device 401 adjusts its extraction power to match the pressure and flow rate of the extracted contaminated gas with the input clean gas, ensuring stable pressure within chamber 1 and smooth, turbulent flow during the gas replacement process. The mass spectrometer leak detector 405 is connected in parallel to the input of the second filter 404 via a pipeline. It is used to detect potential leaks in chamber 1 and various parts of the gas replacement pipeline. Based on current product usage requirements, its minimum detectable leak rate should not exceed 1 x 10⁻⁸ Pa·m / s.
[0034] In the first embodiment of the present invention, when the gas replacement system is operating, the control unit obtains the gas pressure and gas cleanliness value inside the housing 1. When the gas cleanliness is lower than the threshold, the control unit controls the gas source 2 to input the required protective gas. The input gas is sequentially adjusted by the pressure reducing device 301 to match the gas pressure inside the housing 1, adjusted to the specified flow rate by the flow precision control device 302 for output, and filtered by the first filter 303 before being input into the housing 1. At the same time, based on the obtained gas pressure value inside the housing 1 and the flow rate value of the gas input through the air inlet pipe 3, the control unit controls the air extraction device 401 to extract gas from the housing 1. Under the monitoring feedback of the flow monitoring device 402 and the pressure monitoring device 403 on the extracted gas, the air extraction power of the air extraction device 401 is adjusted in real time to make the pressure and flow rate of the extracted contaminated gas match the input clean gas, ensuring that the pressure inside the housing 1 is stable and that the gas replacement process is smooth and turbulent.
[0035] like Figure 2As shown, in the second embodiment of the present invention, the air intake pipeline 3 includes a pressure reducing device 301, a flow precision control device 302, a first filter 303, a gas cleanliness detection device 304, and a first valve 305. The pressure reducing device 301, the first valve 305, the flow precision control device 302, the first filter 303, and the gas cleanliness detection device 304 are connected sequentially through pipelines. The first valve 305 is a shut-off valve, which is communicatively connected to the control unit and used to control the opening and closing of the air intake pipeline 3. The air extraction pipeline 4 includes an air extraction device 401, a flow monitoring device 402, a pressure monitoring device 403, and a second filter 404 connected sequentially through pipelines, and a mass spectrometer leak detector 405 connected in parallel with the input terminal of the second filter 404.
[0036] In the second embodiment of the present invention, by providing a first valve 305 in the air intake pipe 3, when a negative pressure environment is required in the box 1, the first valve 305 can be controlled by the control unit to cut off the air intake pipe 3 to prevent protective gas from flowing into the box; furthermore, according to the negative pressure value set according to the project-related requirements, the control unit controls the air extraction device 401 to extract air from the box 1 until the air pressure value in the box 1 reaches the set negative pressure value, thereby meeting the project-related requirements.
[0037] like Figure 3As shown, in the third embodiment of the present invention, the intake pipeline 1 includes an intake main pipeline and intake branch pipelines. The input end of the intake main pipeline is connected to the air source 2 and includes a pressure reducing device 301, a flow precision control device 302, a first filter 303, a first valve 305, and a gas flow meter 306 connected in sequence through pipelines. The intake branch pipeline includes a third filter 308 and a second valve 309. The intake branch pipeline is provided in four sets. The input ends of the four sets of intake branch pipelines are respectively connected to the output end of the intake main pipeline through a five-way connector 307, and the output ends of the four sets of intake branch pipelines are respectively connected to the housing 1 through a connecting flange 310. During gas replacement, the first valve 305 in the main intake path is open. The control unit controls the pressure reducing device 301 and the flow precision control device 302 to regulate and limit the pressure of the input protective gas. After being filtered by the first filter 303, the gas is input into the intake branch. The second valve 309 in the intake branch is opened, allowing the coarsely filtered gas to be introduced. After being finely filtered by the third filter 308, the gas is input into the housing 1 through the connecting flange 310 for gas replacement. The gas flow meter 306 is communicatively connected to the control unit to detect the flow rate of the input protective gas and controls the corresponding intake branch to open or close based on the flow rate. The second valve 309 is a gas solenoid valve, which is communicatively connected to the control unit and can control the opening or closing of the intake branch. The first filter 303 has a particle filtration range of 1-2 μm, which performs coarse filtration of the input protective gas. The third filter 308 has a particle filtration range of 0.1-0.5 μm, which performs fine filtration of the input protective gas, thereby effectively ensuring the cleanliness of the input protective gas.
[0038] In the third embodiment of the present invention, by providing a main air intake path and multiple sets of air intake branches, the input protective gas is coarsely filtered by a first filter 303 in the main air intake path, and finely filtered in the air intake branches, thereby effectively ensuring the cleanliness of the input protective gas. Furthermore, by providing multiple sets of air intake branches connected to the housing 1, the corresponding air intake branches are controlled to open or close according to the flow rate measured by the gas flow meter 306. That is, when the flow rate is large, multiple sets of air intake branches are controlled to open simultaneously to avoid excessive flow at a single air intake port of the housing 1, which would cause turbulence and affect the stable environment inside the housing 1. When the flow rate is small, a few air intake branches are controlled to open to avoid multiple air intake ports with insufficient flow rates causing the input clean protective gas to mix with the polluted gas, resulting in the polluted gas not being discharged in time.
[0039] In the fourth embodiment of the present invention, the number of intake branches can be set according to the maximum flow rate of the input protective gas, and the number is one or more. The intake branches are connected to the intake main support through corresponding multi-channel connectors.
[0040] In the fifth embodiment of the present invention, a gas composition detection device is further provided in the exhaust pipe 4 for detecting the gas composition and concentration in the chamber 1; the gas composition detection device is installed on the exhaust pipe 4; furthermore, multiple third valves are connected in parallel at the input end of the inlet pipe 3, and the input ends of the multiple third valves are connected to the gas source 2 of the corresponding type of gas. The number of the third valves is the same as the type of protective gas in the chamber 1. Through communication connection with the control unit, the required type of protective gas is input into the chamber 1. During gas replacement, when the gas composition detection device detects that the concentration of the corresponding type of protective gas has dropped to exceed the threshold, the control unit controls the corresponding third valve to open, introduce the corresponding type of protective gas into the exhaust pipe 4, and input the corresponding amount of protective gas under the action of the exhaust pipe 4, so that the concentration values of each protective gas in the chamber 1 are within the threshold range, thereby ensuring the stability of the environment of the chamber 1, improving the beam quality, and ensuring that the surface film layer of the optical element is not damaged under the irradiation of high-energy laser.
[0041] In a sixth embodiment of the present invention, a method for gas replacement in a sealed box using high-energy laser is also provided, comprising the following steps:
[0042] S100: Obtain the gas pressure and gas cleanliness inside chamber 1;
[0043] S200: The protective gas is introduced into the intake pipe 3 for processing;
[0044] S300: The input protective gas is adjusted by the pressure device 301, the flow rate is adjusted by the precision control device 302, and the first filter 303 is used to filter it to meet the requirements before it is input into the housing 1;
[0045] S400: Control the extraction device 401 to extract air, and adjust the extraction power of the extraction device 401 according to the detection values of the flow monitoring device 402 and the pressure monitoring device 403 to make the extracted pollutant gas flow rate match the input gas flow rate.
[0046] S500: If the gas cleanliness of chamber 1 meets the standard, stop the replacement operation.
[0047] Those skilled in the art will readily understand that the above description is merely a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, and improvements made within the spirit and principles of the present invention should be included within the scope of protection of the present invention.
Claims
1. A high-energy laser-sealed gas replacement system for a sealed enclosure, characterized in that, include: An air inlet pipe (3) is provided at the input end of the housing (1). The air inlet pipe (3) includes a pressure reducing device (301), a flow precision control device (302), and a first filter (303) connected in a pipeline. The pressure reducing device (301) adjusts the gas pressure in real time according to the working conditions of the housing (1) to control the gas flow rate to be stable, and ensures the cleanliness of the gas through the first filter (303). The air inlet pipe (3) also includes a gas flow meter (306). The output end of the gas flow meter (306) is provided with multiple sets of air inlet branches in parallel. The output end of the air inlet branches is connected to the housing (1), and includes a third filter (308) and a second valve (309) connected in sequence through a pipe. The input end of the air inlet pipe (3) is provided with multiple third valves in parallel. The input ends of the multiple third valves are connected to the gas source (2) of the corresponding type of gas. The number of third valves is the same as the type of protective gas in the housing (1). And an exhaust pipe (4) connected to the output end of the box (1), the exhaust pipe (4) includes an exhaust device (401), a flow monitoring device (402) and a pressure monitoring device (403). The flow monitoring device (402) and the pressure monitoring device (403) monitor the flow and pressure values inside the box (1) and use the exhaust device (401) to match the flow rate of the extracted pollutant gas with the flow rate of the input gas, so as to avoid turbulent airflow inside the box (1); It also includes a control unit, which obtains the gas pressure and gas cleanliness in the box (1) in real time, controls the inlet pipe (3) to regulate the pressure, limit the flow, and further filter the gas before it is put into the box (1), controls the exhaust pipe (4) to extract the polluted gas in the box (1), and adjusts the exhaust power of the exhaust device (401) according to the monitoring feedback of the flow monitoring device (402) and the pressure monitoring device (403); The box (1) is equipped with a pressure detection module and a cleanliness detection module, which respectively detect the pressure and cleanliness inside the box (1) and send the detection data to the control unit.
2. The high-energy laser sealed chamber gas replacement system according to claim 1, characterized in that, The first filter (303) is provided with a gas cleanliness detection device (304) connected in parallel at the output end. The gas cleanliness detection device (304) detects the cleanliness of the filtered gas.
3. The high-energy laser sealed chamber gas replacement system according to claim 1, characterized in that, The intake pipe (3) also includes a first valve (305), whose input end is connected to the pressure reducing device (301) and whose output end is connected to the flow precision control device (302).
4. A high-energy laser-sealed gas replacement system for a sealed enclosure according to any one of claims 1-3, characterized in that, The intake branch is provided with four sets, and the input ends of the four sets of intake branches are connected in parallel with the output end of the gas flow meter (306) through a five-way connector (307).
5. A high-energy laser-sealed gas replacement system for a sealed enclosure according to any one of claims 1-3, characterized in that, The first filter (303) has a particle filtration range of 1 to 2 μm and performs coarse filtration on the input protective gas, while the third filter (308) has a particle filtration range of 0.1 to 0.5 μm and performs fine filtration on the input protective gas.
6. A high-energy laser-sealed gas replacement system for a sealed enclosure according to any one of claims 1-3, characterized in that, The gas extraction pipeline (4) is also equipped with a gas composition detection device.
7. A high-energy laser-sealed gas replacement system for a sealed enclosure according to any one of claims 1-3, characterized in that, It also includes a mass spectrometer leak detector (405).
8. A method for gas replacement in a sealed enclosure using high-energy laser, characterized in that, The application of the high-energy laser sealed chamber gas replacement system as described in any one of claims 1-7 includes the following steps: S100: Obtain the gas pressure and gas cleanliness inside the chamber (1); S200: The protective gas is introduced into the intake pipe (3) for processing; S300: The input protective gas is adjusted by the pressure reducing device (301), the flow rate is adjusted by the precision control device (302), and the first filter (303) is used to filter it to meet the requirements before it is input into the box (1). S400: Control the air extraction device (401) to extract air, and adjust the air extraction power of the air extraction device (401) according to the detection values of the flow monitoring device (402) and the pressure monitoring device (403) to make the flow rate of the extracted pollutant gas match the flow rate of the input gas. S500: If the gas cleanliness of the test chamber (1) meets the standard, stop the replacement operation.
Citation Information
Patent Citations
Anti-fragility system for semiconductor processing provisioning using multiple special sensors and algorithms
CN116018672A
Vacuumizing device and solar cell processing system
CN219079642U
Gas exchanging apparatus
KR101352466B1
Apparatus and method for feeding gases for use in semiconductor manufacturing
US20010013363A1