Multi-energy system configuration method and system considering communication base station and power transmission congestion

By constructing communication base stations and multi-energy system models, optimizing the location and access capacity of energy storage power stations solves the problem of transmission congestion caused by new energy fluctuations in multi-energy systems, improves the safety, stability and economy of the system, and avoids The maintenance difficulty and pollution of traditional batteries are eliminated, and the use of hydrogen fuel cells increases the flexibility margin.

CN118137477BActive Publication Date: 2024-10-01NORTHEAST DIANLI UNIVERSITY
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410246948.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-03-05
Publication Date
2024-10-01
Estimated Expiration
2044-03-05

AI Technical Summary

Technical Problem

In multi-energy systems, random fluctuations in the output of a high proportion of new energy sources lead to network-side congestion, which reduces the efficiency of flexible resource transmission and threatens the safe and stable operation of the system. Existing research usually chooses to build new lines for mitigation, but there are difficulties in maintenance and chemical pollution. problem.

Method used

By constructing a communication base station model and a multi-energy system model, we perform quantitative calculations on flexibility, establish a location and capacity model for energy storage power stations, and optimize the location and access capacity of energy storage power stations to reduce source load uncertainty and transmission congestion risks. Use hydrogen fuel cells to replace traditional lead-acid batteries to enhance system flexibility and economy.

Benefits of technology

It effectively reduces the risk of blockage in the transmission network section and improves the safety and stability of the system. Through the green and environmentally friendly advantages of hydrogen fuel cells, it avoids the maintenance difficulty and chemical pollution of traditional batteries, achieving lower total cost and higher flexibility. sexual margin.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118137477B_ABST
    Figure CN118137477B_ABST
Patent Text Reader

Abstract

The present invention discloses a multi-energy system configuration method and system taking into account communication base stations and electric energy transmission congestion, and belongs to the technical field of integrated energy system optimization configuration. The method comprises the following steps: S1, constructing a communication base station model and a multi-energy system model, and performing flexibility quantitative calculation on the communication base station model and the multi-energy system model to obtain a first calculation result, and the first calculation result is used for flexibility optimization configuration; S2, constructing a storage power station site selection and sizing model based on the communication base station model, the multi-energy system model and the first calculation result, and the site selection and sizing model is used for energy storage power station site selection and access capacity optimization configuration. The energy storage power station site selection and sizing model proposed in the present invention performs joint optimization of energy storage power stations and sizing and site selection during planning, effectively reducing the risk of section congestion in the transmission network, and making the power system safer and more stable.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of comprehensive energy system optimization configuration, and specifically relates to a multi-energy system configuration method and system taking into account communication base stations and power transmission congestion. Background Art

[0002] Under the premise that the multi-energy system has sufficient flexibility margin, it is necessary to consider from the perspective of the grid whether the flexibility resources can be transmitted in time to meet the flexibility needs. Faced with the random fluctuation characteristics of a high proportion of renewable energy output, grid-side blockage will not only reduce the flexibility resource transmission efficiency of the entire system, but may even exceed the system grid carrying capacity and threaten the safe and stable operation of the system. Existing research usually chooses to build new lines to alleviate blockage.

[0003] Due to the rapid development of communication technology in recent years, the number of 5G base stations, as the core equipment of the fifth-generation mobile communication network, has grown rapidly. At present, communication base stations mostly use lead-acid batteries as the main power supply and backup power supply, but lead-acid batteries have problems such as difficult maintenance and serious chemical pollution. Therefore, green, environmentally friendly, long-lasting and stable hydrogen fuel cells have become one of the ideal power supply alternatives.

[0004] Since the power consumption equipment of communication base stations is mainly communication equipment and its supporting equipment. In the power consumption of base stations, the power consumption of main equipment and air conditioning accounts for more than 80% of the total power consumption of base stations, of which the power consumption of air conditioning accounts for more than 50% of the total power consumption of base stations, accounting for the largest proportion of the power consumption of all equipment. This is because traditional batteries have very strict operating temperature requirements, such as the operating temperature of lead-acid batteries is around 15-35℃, while hydrogen fuel cell power supply systems have a larger temperature requirement range and can work normally within the indoor temperature of 100℃. In addition, most current communication base stations use lead-acid battery packs as the main power supply and backup power supply. Hydrogen coupling transformation of communication base stations can not only avoid the problems of difficult maintenance and serious chemical pollution of conventional lead-acid batteries, but also obtain better economy and low carbon in long-term planning, obtain greater benefits by sending out excess electricity, and provide flexible adjustment capabilities for new power systems. Summary of the invention

[0005] The present invention aims to address the problem that flexibility resources are becoming increasingly abundant and the uncertainty at both the source and load ends is becoming increasingly obvious. The risk of transmission section blockage caused by flexibility resources in the process of power grid transmission is taken into consideration, and a site selection and sizing method for energy storage power stations is established to minimize the source and load uncertainty and the risk of section transmission blockage caused by the transmission of flexibility resources without increasing the number of lines.

[0006] To achieve the above object, the present invention provides the following solution: a multi-energy system configuration method considering communication base stations and power transmission congestion, comprising the following steps:

[0007] S1. Constructing a communication base station model and a multi-energy system model, and performing flexibility quantification calculation on the communication base station model and the multi-energy system model to obtain a first calculation result, wherein the first calculation result is used for performing flexibility optimization configuration;

[0008] S2. Based on the communication base station model, the multi-energy system model and the first calculation result, a site selection and capacity determination model for an energy storage power station is constructed, and the site selection and capacity determination model is used for site selection and access capacity optimization configuration of an energy storage power station.

[0009] Further preferably, the communication base station model includes:

[0010]

[0011] Where, L CO is the basic load of the communication base station; P CO (t) is the power output of the hydrogen fuel cell of the communication base station during period t; η CO The efficiency of hydrogen fuel cell power generation for communication base stations; R is the volume of hydrogen consumed by the communication base station during period t; CO C is the output climbing coefficient of hydrogen fuel cell; CO Allocate capacity for hydrogen fuel cells; is the calorific value of hydrogen; is the density of hydrogen.

[0012] Further preferably, the flexibility requirement includes an upward flexibility requirement and a downward flexibility requirement;

[0013] Methods for quantifying flexibility include:

[0014]

[0015]

[0016] In the formula, F i,up (t), F e,up (t) are the flexibility adjustment capabilities of each device and energy storage in time period t; F i,dn (t), F e,dn (t) is the downward flexibility adjustment capability of each device and energy storage side during period t; P i (t) is the output of equipment i during period t; r i,up 、r i,dn S is the upward and downward climbing rate of device i; ES (t) is the capacity status of the energy storage power station during period t; η ES , C ES P is the charging and discharging rate and configuration capacity of the energy storage power station; fd,ES (t), P cd,ES(t) is the discharge and charging power of the energy storage power station during period t; P i,max , P i,min Indicates the maximum and minimum output of each device in the time period; S ES,max , S ES,min Indicates the maximum and minimum capacity of the energy storage power station in a time period.

[0017] Further preferably, the flexibility optimization configuration takes the minimum configuration cost under equal annual value and the maximum flexibility margin as the optimization goal;

[0018] The optimization objectives are as follows:

[0019] F=min[F e -sum(F i,up (t)+F i,dn (t)+F e,up (t)+F e,dn (t))],

[0020] In the formula, F represents the overall goal of system planning and operation; F e represents the total economic cost; F i,up (t) represents the upward flexibility margin of each device in period t; F i,dn (t) represents the downward flexibility margin of each device in period t; F e,up (t) represents the upward flexibility margin of the energy storage power station in period t; F e,dn (t) represents the downward flexibility margin of the energy storage power station in period t.

[0021] Further preferably, the site selection and capacity determination model takes the lowest average line load as the objective function, and improves the transmission flexibility of the power grid through the site selection and access capacity optimization of the energy storage power station;

[0022] The objective function includes:

[0023]

[0024] Where N represents the number of system branches.

[0025] Further preferably, the constraints of the energy storage power station include:

[0026]

[0027] In the formula, C ES,n is the capacity of the nth energy storage power station; The charging and discharging power of the nth energy storage station in time period t; The charging and discharging status of the nth energy storage power station in time period t; S is the upper limit ratio of the charging and discharging capacity of the nth energy storage power station in the t period to the total capacity;ES,n (t) is the charge state of the nth energy storage power station in period t; L ES is the hourly self-leakage rate of the energy storage power station.

[0028] Further preferably, the access capacity calculation method and power balance include:

[0029]

[0030]

[0031] Where P ij B is the line transmission power between nodes i and j; ij is the line susceptance between nodes i and j; θ i The voltage phase angle of node i; X ij is the line reactance between nodes i and j; P i out (t) is the output power of node i of the line connected to node i during period t; P i (t) is the electrical load of the ith node in period t; P is the charging and discharging power of energy storage (if any) at node i during period t; s,i (t) is the power supply connected to node i during period t; P ij,n (t) is the transmission power of the nth line connected to the i-th node in time period t.

[0032] The present invention also provides a multi-energy system configuration system considering communication base stations and power transmission congestion, the system is used to implement the above method, including: a model building module and a capacity determination module;

[0033] The model building module is used to build a communication base station model and a multi-energy system model, and perform flexibility quantification calculation on the communication base station model and the multi-energy system model to obtain a first calculation result; the first calculation result is used to perform flexibility optimization configuration;

[0034] The capacity determination module is used to construct a site selection and capacity determination model for an energy storage power station based on the communication base station model, the multi-energy system model and the first calculation result, and based on the site selection and capacity determination model, the site selection and capacity determination model is used to perform site selection and capacity optimization configuration of an energy storage power station.

[0035] Compared with the prior art, the present invention has the following beneficial effects:

[0036] First, in the planning process of the multi-energy coupling system, the communication base station is considered and hydrogen coupling transformation is carried out on it. Under the premise of avoiding the problems of the existing lead-acid battery group as the main power supply and backup power supply of the communication base station, such as the difficulty of maintenance, serious chemical pollution, and harsh working environment, the advantages of hydrogen fuel cells, such as green environmental protection and long-term stability, are fully utilized. Secondly, the traditional energy storage power station planning method only optimizes the capacity and lacks a reasonable and effective site selection planning method. The energy storage power station site selection and capacity determination model proposed in the present invention performs capacity determination and site selection joint optimization on the energy storage power station during planning, effectively reducing the risk of cross-section blocking of the transmission network and making the power system safer and more stable. BRIEF DESCRIPTION OF THE DRAWINGS

[0037] In order to more clearly illustrate the technical solution of the present invention, the following briefly introduces the drawings required for use in the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.

[0038] Figure 1 This is a schematic diagram of the interaction between the operator and the multi-energy coupling system according to an embodiment of the present invention;

[0039] Figure 2 This is a schematic diagram of the structure of a test system according to an embodiment of the present invention;

[0040] Figure 3 A schematic diagram of a blocking situation in which an energy storage power station is provided at a wind-solar power station according to an embodiment of the present invention;

[0041] Figure 4 A schematic diagram of a blocking situation in which an energy storage power station is set at an electric / gas / heat coupling location according to an embodiment of the present invention;

[0042] Figure 5 A schematic diagram of a blocking situation in which electric energy storage is configured using the method of the present invention in an embodiment of the present invention.

[0043] Description of reference numerals:

[0044] 1-14 represent electricity network nodes; 15-21 represent natural gas network nodes; 22-29 represent thermal network nodes. DETAILED DESCRIPTION

[0045] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0046] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the present invention is further described in detail below with reference to the accompanying drawings and specific embodiments.

[0047] Embodiment 1:

[0048] This embodiment provides a multi-energy system configuration method considering communication base stations and power transmission congestion, including the following steps:

[0049] S1. Construct a communication base station model and a multi-energy system model, and perform flexibility quantification calculation on the communication base station model and the multi-energy system model to obtain a first calculation result.

[0050] The load of the communication base station is similar to the trend of the system power load. In order not to affect the quality of urban communication, this embodiment regards the communication load as the basic load that must be met. Its mathematical model is as follows:

[0051]

[0052] Where, L CO is the basic load of the communication base station; P CO (t) is the power output of the hydrogen fuel cell of the communication base station during period t; η CO The efficiency of hydrogen fuel cell power generation for communication base stations; R is the volume of hydrogen consumed by the communication base station during period t; CO C is the output climbing coefficient of hydrogen fuel cell; CO Allocate capacity for hydrogen fuel cells; is the calorific value of hydrogen; is the density of hydrogen.

[0053] Telecommunications operators can participate in flexible quota trading through unified dispatch and transmit excess electricity to the power grid. Hydrogen fuel cells can replace traditional batteries to obtain greater benefits. Figure 1 The figure shows the interactive relationship between the communication base station and the multi-energy system. The profit calculation method is as follows:

[0054]

[0055] Where P sell (t) is the electric energy transmitted to the power grid by the communication operator during period t; S CO is the revenue of the communication operator; p (t) are the electricity price and hydrogen price in period t; T represents the period.

[0056] In this embodiment, the multi-energy system includes: a wind turbine, a photovoltaic device, a thermal power unit, an energy storage device, a hydrogen-blended steam turbine with waste heat recovery, a hydrogen fuel cell cogeneration, an electric boiler, an electrolyzer, and a methanation device.

[0057] (1) Wind turbine model

[0058] The actual power of the wind turbine is expressed in the following piecewise function form:

[0059]

[0060] Where v is the wind speed at the height of the wind turbine wheel; v ci is the cut-in wind speed of the wind turbine; v co is the cut-out wind speed of the wind turbine; v r is the rated wind speed of the wind turbine; P r is the rated output power of the wind turbine.

[0061] (2) Photovoltaic device model

[0062] The calculation method of photovoltaic power is as follows:

[0063]

[0064] Where P pv额 is the rated power under standard conditions; T(t) is the current temperature; T STC is the standard temperature; G(t) is the current light intensity; G STC is the standard light intensity; k is the temperature coefficient power.

[0065] (3) Thermal power unit model

[0066] First, thermal power units should operate within a certain output range, and the constraints are as follows:

[0067]

[0068] Where P TP,max , P TP,min is the maximum and minimum output of the thermal power unit; P TP (t) is the output of the thermal power unit during period t; Y TP (t) is the operating status of the thermal power unit during period t; Y TP (t) = 0 means the thermal power unit stops running; Y TP (t) = 1 indicates that the thermal power unit operates normally.

[0069] Considering the climbing ability of thermal power units, there are the following constraints:

[0070] -ΔP TP ≤P TP (t)-P TP (t-1)≤ΔP TP ,

[0071] In the formula, ΔP TP is the ramp rate of the thermal power unit.

[0072] (4) Energy storage device model

[0073] The energy storage characteristics of different energy forms are similar. Therefore, they can all be composed of energy storage upper and lower limit constraints, charging and discharging power constraints, energy storage state constraints and energy loss constraints. The specific calculation method is as follows:

[0074]

[0075] In the formula, S ESS (t), S ESS,min , S ESS,max P is the energy storage state, minimum and maximum energy storage capacity limits of the energy storage device during period t; ch (t), P dc (t) represents the charging and releasing power in time period t; L represents the energy loss per hour; Y ch (t), Y dc (t) is the charge and discharge state of the energy storage device during period t, which is a 0-1 variable; u ch (t),u dc (t) represents the upper limit ratio of the charging and discharging power of the energy storage device in time period t; C is the planned configuration capacity of each type of energy storage device, and the capacity of different energy forms is different.

[0076] (5) Hydrogen-blended gas turbine model with waste heat recovery

[0077] According to existing research, when hydrogen is mixed with less than 20% (volume fraction), it will not have a significant impact on the existing pipeline network. In addition, when the hydrogen mixing ratio is 10% to 20%, the operation of the gas turbine is less affected and no modification is required. The mathematical model of the hydrogen-mixed gas turbine is as follows:

[0078]

[0079] Where P CHP (t), H CHP (t) is the electrical output and thermal output of the hydrogen-blended gas turbine during period t; η E,CHP , η H,CHP It indicates the proportion of available electrical energy and thermal energy to the total thermal energy of the mixed gas; is the volume of natural gas and hydrogen consumed by the hydrogen-blended gas turbine during period t; is the calorific value of natural gas and hydrogen; is the density of natural gas and hydrogen; R ECHP , R HCHP C is the electrical and thermal output ramp coefficient of the hydrogen-blended gas turbine; CHP represents the configuration capacity of hydrogen-blended gas turbine; β represents the hydrogen blending ratio; P ORC (t), H ORC (t) The electrical and thermal output of the waste heat recovery device; is the percentage of waste heat recovery used for power generation and heat production; η E,ORC , η H,ORC It is the power generation and heat generation efficiency of the waste heat recovery device.

[0080] (6) Hydrogen fuel cell cogeneration model

[0081] Hydrogen fuel cells mainly use proton exchange membrane fuel cells and solid oxide fuel cells as power generation systems. The model is as follows:

[0082]

[0083] Where P HFC (t), H HFC (t) is the electrical output and thermal output of the hydrogen fuel cell during period t; η E,HFC , η H,HFC Indicates the electrical and thermal output efficiency of hydrogen fuel cells; R is the volume of hydrogen consumed by the hydrogen fuel cell during period t; E,HFC , R H,HFC C is the climbing coefficient of the electrical and thermal output of the hydrogen fuel cell; HFC Configure capacity for hydrogen fuel cells.

[0084] (7) Electric boiler model

[0085] The electric boiler is an electric-thermal coupling device, and its model is as follows:

[0086]

[0087] In the formula, H EB (t) is the heat output of the electric boiler during period t; P EB (t) is the power consumption of the electric boiler during period t; η EB is the operating efficiency of the electric boiler; R EB C is the electric boiler power ramp coefficient; EB Configure capacity for electric boilers.

[0088] (8) Electrolytic cell model

[0089] Electrolyzers produce hydrogen by electrolyzing water and are one of the important sources of hydrogen. The model is as follows:

[0090]

[0091] Where P EL (t) is the power consumption of the electrolytic cell during period t; η EL is the power consumption coefficient of hydrogen production; V EL (t) is the hydrogen production during period t; R EL Electrolyzer climbing coefficient; C EL Configure the capacity for the electrolyzer.

[0092] (9) Methanation device model

[0093] Under the action of the catalyst, the methanogenation device can use hydrogen to reduce carbon monoxide and carbon dioxide to generate methane and water. The model is as follows:

[0094]

[0095] Where P ME (t) is the power consumption of the methanogenation device during period t; The electricity consumption coefficient for producing natural gas and the amount of hydrogen required to produce a unit of methane gas; is the gas production during period t; is the amount of hydrogen consumed during period t; R ME is the power consumption climbing coefficient; C ME Assign capacity to the methanogenation unit.

[0096] Considering the transmission risk of flexible resource sections, the multi-energy system is configured with the goal of optimizing economy and flexibility, while considering the transmission blocking risk of flexible resource sections, as follows:

[0097] The system flexibility requirements include upward flexibility requirements and downward flexibility requirements, which are defined as follows:

[0098]

[0099] P pl (t) = P ld (t)-P WT (t)-P PV (t),

[0100] In the formula, P is the flexibility to adjust the demand up and down during period t; pl (t) is the load demand during period t; P ld (t), P WT (t), P PV (t) is the electricity load, wind power and photovoltaic power generation in period t.

[0101] Considering the output regulation of source-side equipment such as thermal power units and hydrogen-blended cogeneration units, the load-side equipment such as electric boilers and electrolyzers reasonably changes its own load demand and the flexibility regulation capability provided by the energy storage side. Quantify the flexibility regulation capability of the entire system from the perspective of source, load, and storage, and conduct a quantitative analysis of the system flexibility. The calculation method is as follows:

[0102]

[0103]

[0104] In the formula, F i,up (t), F e,up (t) are the flexibility adjustment capabilities of each device and energy storage in time period t; F i,dn (t), F e,dn (t) is the downward flexibility adjustment capability of each device and energy storage side during period t; P i (t) is the output of equipment i during period t; r i,up 、r i,dn S is the upward and downward climbing rate of device i; ES (t) is the capacity status of the energy storage power station during period t; η ES , C ES P is the charging and discharging rate and configuration capacity of the energy storage power station; fd,ES (t), P cd,ES (t) is the discharge and charging power of the energy storage power station during period t; P i,max , P i,min Indicates the maximum and minimum output of each device in the time period; S ES,max , S ES,min Indicates the maximum and minimum capacity of the energy storage power station in a time period.

[0105] Considering the optimization configuration of multi-energy system with improved source-load-energy storage flexibility, the optimization goal is to minimize the system configuration cost under equal annual value and maximize the flexibility margin:

[0106] F=min[F e -sum(F i,up (t)+F i,dn (t)+F e,up (t)+F e,dn (t))],

[0107] In the formula, F represents the overall goal of system planning and operation; F e represents the total economic cost; F i,up (t) represents the upward flexibility margin of each device in period t; F i,dn (t) represents the downward flexibility margin of each device in period t; F e,up (t) represents the upward flexibility margin of the energy storage power station in period t; F e,dn (t) represents the downward flexibility margin of the energy storage power station in period t.

[0108] Among them, F e It can be expressed as:

[0109]

[0110] In the formula, F TP is the cost of thermal power; F WT is the cost of wind power; F PV is the photovoltaic cost; FES The cost of electrical energy storage; Cost of purchasing natural gas; The cost of purchasing hydrogen; F EL F is the cost of hydrogen production by electrolysis of water; ME is the cost of natural gas production by methanogenesis; F HYS is the hydrogen storage cost; F CHP is the cost of combined heat and power generation; F ORC The cost of waste heat recovery for power generation and heating; F EB is the heating cost of electric boiler; F HFC is the cost of hydrogen fuel cells; F HS is the thermal energy storage cost; F TX is the cost of the communication base station.

[0111] The economic costs include: planning investment costs and equipment operation and maintenance costs, which are calculated as follows:

[0112]

[0113]

[0114]

[0115]

[0116]

[0117]

[0118]

[0119]

[0120]

[0121]

[0122]

[0123]

[0124]

[0125]

[0126] In the formula, are coal price and operation and maintenance cost coefficient respectively; m MH (t) is the coal consumption in period t; C HYS , is the hydrogen storage tank capacity, unit investment cost, and operation and maintenance cost coefficient; P WT,cur (t), P WT (t) is the wind power abandonment and wind power generation in period t; γ WT,cur , γ WT P is the penalty cost for wind abandonment and the operation and maintenance cost per unit of wind power generation; PV,cur (t), P PV (t) is the amount of photovoltaic abandoned light and photovoltaic power generation in period t; γ PV,cur , γ PV C is the penalty cost for abandonment of solar power and the operation and maintenance cost per unit of photovoltaic power generation; ES , They are energy storage capacity, unit investment cost, and operation and maintenance cost coefficient of energy storage power station; is the unit natural gas price and the system natural gas purchase volume during period t; is the unit hydrogen price and the amount of hydrogen purchased during period t; C EL , is the configuration capacity of the electrolyzer, the investment cost per unit capacity, the amount of hydrogen consumed in period t, and the operation and maintenance cost per unit volume of hydrogen consumed; C ME , are the configuration capacity of the methanogen, the investment cost per unit capacity, the amount of natural gas generated in period t, and the operation and maintenance cost per unit of natural gas generated; C CHP , V CHP (t) The capacity, investment cost per unit capacity, gas consumption in period t and unit operation and maintenance cost of CHP are configured; ORC , P ORC (t) The configuration capacity, investment cost per unit capacity, power generation during period t, and unit operation and maintenance cost of the waste heat boiler are C HFC , P HFC (t), γ HFC2 C is the hydrogen fuel cell configuration capacity, unit capacity investment cost, power generation during time period t, and unit operation and maintenance cost; EB , P EB (t) Configure the capacity, investment cost per unit capacity, power consumption in period t, and unit operation and maintenance cost for the electric boiler; The investment cost per unit capacity and unit operation and maintenance cost for transforming communication base stations into hydrogen fuel cells.

[0127] like Figure 2As shown, this embodiment takes the city-level electricity / gas / heat multi-energy coupling system as the research object, and the test system is composed of a modified 14-node power network (nodes 1-14), a 7-node natural gas network (nodes 15-21) and an 8-node thermal network (nodes 22-29) coupled. The planning model established in this embodiment is based on the historical hourly measured data of a city throughout the year. The k-means method is used to cluster and generate 4 typical daily scenes containing electricity load, gas load, heat load, and meteorological data. Each typical day takes each hour as a time period, and the simulation cycle of the example is 96h. The system planning target year is set to 20 years, and the specific parameters are shown in Table 1 below.

[0128] Table 1

[0129]

[0130] In order to verify the feasibility and effectiveness of the communication base station transformation in this embodiment, the operation and maintenance / planning costs and the planned capacity of each equipment of electricity / gas / heat / storage are calculated based on the Matlab platform using the Gurobi commercial solver as shown in Tables 2 and 3.

[0131] Table 2

[0132]

[0133] Table 3

[0134]

[0135] Based on the test system mentioned above, it can be seen from Table 2 that after considering the hydrogen coupling transformation of the communication base station, the system flexibility margin is increased by 1388.05MW, and the total cost is reduced by 2.9725 million yuan. Considering the hydrogen coupling transformation of the communication base station will result in higher investment costs, but at the same time, the communication base station transfers part of the charge and provides greater flexibility adjustment space for other equipment, which works together with the base station's own flexibility adjustment capability to enable the system to obtain greater flexibility margin at a lower cost.

[0136] As shown in Table 3, the energy storage power station has been greatly improved after considering the hydrogen coupling transformation of the communication base station. This shows that the energy storage power station has a good energy regulation effect in complex multi-energy coupling systems and when considering the interests of multiple parties. It is an indispensable link in the optimization of multiple interests and the optimal configuration of complex systems. Hydrogen fuel cells have planned a large capacity in both cases, indicating that hydrogen fuel cells have unique advantages in power generation efficiency and power generation costs, and the prospects for the utilization of hydrogen energy are very broad.

[0137] S2. Based on the communication base station model, the multi-energy system model and the first calculation result, a site selection and capacity determination model for the energy storage power station is constructed, and based on the site selection and capacity determination model, the site selection and access capacity of the energy storage power station are determined.

[0138] At the same time, this embodiment also provides a model for site selection and capacity determination of energy storage power stations. The site selection and capacity determination model takes the lowest average load rate of all lines as the objective function, improves the transmission flexibility of the power grid through the optimal site selection and access capacity optimization of energy storage power stations, and solves the transmission section blocking problem that may occur when the output of large-scale flexible resources fluctuates. The objective function is as follows:

[0139]

[0140] Where N represents the number of system branches; represents the maximum transmission power of the nth branch; P n (t) represents the transmission power of the nth branch at time t.

[0141] The energy storage power station can be configured at each node in the system. Since the land cost corresponding to the energy storage area is relatively high, in this embodiment, no more than N WZ Energy storage power stations are configured at different locations, and the energy storage power stations distributed at different nodes have the following constraints:

[0142]

[0143] In the formula, C ES,n is the capacity of the nth energy storage power station; The charging and discharging power of the nth energy storage station in time period t; The charging and discharging status of the nth energy storage power station in time period t; S is the upper limit ratio of the charging and discharging capacity of the nth energy storage power station in the t period to the total capacity; ES,n (t) is the charge state of the nth energy storage power station in period t; L ES is the hourly self-leakage rate of the energy storage power station.

[0144] In order to simplify the calculation and improve the solution speed, this embodiment uses DC power flow to calculate the line power. The calculation formula and power balance are as follows:

[0145]

[0146]

[0147] Where P ij B is the line transmission power between nodes i and j; ij is the line susceptance between nodes i and j; θ i The voltage phase angle of node i; X ij is the line reactance between nodes i and j; P i out (t) is the output power of node i of the line connected to node i during period t; Pi (t) is the electrical load of the ith node in period t; P is the charging and discharging power of energy storage (if any) at node i during period t; s,i (t) is the power supply connected to node i during period t; P ij,n (t) is the transmission power of the nth line connected to the i-th node in time period t.

[0148] In order to verify the effectiveness of the method for siting and configuring energy storage power stations considering the risk of flexible transmission section blocking proposed in this embodiment, on the basis of considering the hydrogen coupling transformation of communication base stations, from the perspective of energy storage siting and configuration, it is set up to configure energy storage power stations at wind and solar access nodes using conventional methods, configure energy storage power stations at electricity / gas / heat coupling nodes, and use the energy storage power station siting method considering the risk of flexible transmission section blocking to obtain the results for comparative analysis.

[0149] Since the land cost needs to be considered when planning the energy storage battery, in this embodiment, the energy storage is configured at no more than 5 geographical locations. The configuration results under each method are shown in Table 4. The line blocking risk of each branch at different time periods under different scenarios is shown in Table 4. Figure 3 , Figure 4 , Figure 5 As shown, the overall grid-side flexibility index is 65.75%, 68.12% and 60.53%. The smaller the index, the smaller the overall line section blocking risk. As can be seen from the figure, branches 2-5 and 10 have a higher blocking risk than other branches. By comparison, it is found that the overall potential section transmission blocking risk has been significantly reduced in the planning scheme proposed in this embodiment, which fully proves the effectiveness of the energy storage power station site selection and configuration method proposed in this embodiment.

[0150] Table 4

[0151]

[0152] The above results show that the optimization configuration scheme proposed in this embodiment improves the economy and flexibility of the entire system, and the flexibility of the constructed urban-level multi-energy coupling system considering the transformation of communication base stations enhances the effectiveness and economy of the configuration method.

[0153] Embodiment 2:

[0154] This embodiment provides a multi-energy system configuration system considering communication base stations and power transmission congestion, including: a model building module and a capacity determination module;

[0155] The model building module is used to build a communication base station model and a multi-energy system model, and perform flexibility quantification calculation on the communication base station model and the multi-energy system model to obtain a first calculation result; the first calculation result is used to perform flexibility optimization configuration;

[0156] The capacity determination module is used to construct a site selection and capacity determination model for an energy storage power station based on the communication base station model, the multi-energy system model and the first calculation result, and based on the site selection and capacity determination model, the site selection and capacity determination model is used to perform site selection and capacity optimization configuration of the energy storage power station.

[0157] The embodiments described above are only descriptions of the preferred embodiments of the present invention and are not intended to limit the scope of the present invention. Without departing from the design spirit of the present invention, various modifications and improvements made to the technical solutions of the present invention by ordinary technicians in this field should all fall within the protection scope determined by the claims of the present invention.

Claims

1. A multi-energy system configuration method considering communication base stations and power transmission congestion, characterized in that: The following steps are involved: S1. Constructing a communication base station model and a multi-energy system model, and performing flexibility quantification calculation on the communication base station model and the multi-energy system model to obtain a first calculation result, wherein the first calculation result is used for performing flexibility optimization configuration; S2. Based on the communication base station model, the multi-energy system model and the first calculation result, construct a site selection and capacity determination model for an energy storage power station, wherein the site selection and capacity determination model is used for site selection and access capacity optimization configuration of an energy storage power station; The communication base station model includes: Where, L CO is the basic load of the communication base station; P CO (t) is the power output of the hydrogen fuel cell of the communication base station during period t; η CO The efficiency of hydrogen fuel cell power generation for communication base stations; R is the volume of hydrogen consumed by the communication base station during period t; CO C is the output climbing coefficient of hydrogen fuel cell; CO Allocate capacity for hydrogen fuel cells; is the calorific value of hydrogen; is the density of hydrogen; Flexibility requirements include upward flexibility requirements and downward flexibility requirements; Methods for quantifying flexibility include: In the formula, F i,up (t), F e,up (t) are the flexibility adjustment capabilities of each device and energy storage in time period t; F i,dn (t), F e ,dn (t) is the downward flexibility adjustment capability of each device and energy storage side during period t; P i (t) is the output of equipment i during period t; r i,up 、r i,dn S is the upward and downward climbing rate of device i; ES (t) is the capacity status of the energy storage power station during period t; η ES , C ES P is the charging and discharging rate and configuration capacity of the energy storage power station; fd,ES (t), P cd,ES (t) is the discharge and charging power of the energy storage power station during period t; P i,max , P i,min Indicates the maximum and minimum output of each device in the time period; S ES,max , S ES,min Indicates the maximum and minimum capacity of the energy storage power station in the time period; The flexibility optimization configuration is to minimize the configuration cost under equal annual value and maximize the flexibility margin as the optimization goal; The optimization objectives are as follows: F=min[F e -sum(F i,up (t)+F i,dn (t)+F e,up (t)+F e,dn (t))], In the formula, F represents the overall goal of system planning and operation; F e represents the total economic cost; F i,up (t) represents the upward flexibility margin of each device in period t; F i,dn (t) represents the downward flexibility margin of each device in period t; F e,up (t) represents the upward flexibility margin of the energy storage power station in period t; F e,dn (t) represents the downward flexibility margin of the energy storage power station in period t; The site selection and capacity determination model takes the lowest average line load as the objective function, and improves the transmission flexibility of the power grid by optimizing the site selection and access capacity of the energy storage power station; The objective function includes: Where N represents the number of system branches; The access capacity calculation method and power balance include: Where P ij B is the line transmission power between nodes i and j; ij is the line susceptance between nodes i and j; θ i The voltage phase angle of node i; X ij is the line reactance between nodes i and j; P i out (t) is the output power of node i of the line connected to node i during period t; P i (t) is the electrical load of the ith node in period t; P is the charging and discharging power of energy storage (if any) at node i during period t; s,i (t) is the power source connected to node i during period t; P ij,n (t) is the transmission power of the nth line connected to the i-th node in time period t.

2. The multi-energy system configuration method considering communication base stations and power transmission congestion according to claim 1 is characterized in that: The constraints of the energy storage power station include: In the formula, C ES,n is the capacity of the nth energy storage power station; The charging and discharging power of the nth energy storage station in time period t; The charging and discharging status of the nth energy storage power station in time period t; S is the upper limit ratio of the charging and discharging capacity of the nth energy storage power station in the t period to the total capacity; ES,n (t) is the charge state of the nth energy storage power station in time period t; L ES is the hourly self-leakage rate of the energy storage power station.

3. A multi-energy system configuration system considering communication base stations and power transmission congestion, the system is used to implement the method described in any one of claims 1-2, characterized in that: include: Model building module and volume determination module; The model building module is used to build a communication base station model and a multi-energy system model, and perform flexibility quantification calculation on the communication base station model and the multi-energy system model to obtain a first calculation result; The first calculation result is used to perform flexibility optimization configuration; The capacity determination module is used to construct a site selection and capacity determination model for an energy storage power station based on the communication base station model, the multi-energy system model and the first calculation result, and based on the site selection and capacity determination model, the site selection and capacity determination model is used to perform site selection and capacity optimization configuration of an energy storage power station.