A project construction management method and system based on BIM
Through the BIM-based project construction management method, the construction of digital twin models and virtual camera shooting solve the problems of high labor costs and inability to manage the overall situation in construction management, achieving efficient and convenient construction management.
Patent Information
- Application Number
- CN202410413141.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-08
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2044-04-08
AI Technical Summary
In the construction management of engineering projects, the existing technology has the disadvantages of high labor costs and the inability to carry out global management and remote management, which reduces the efficiency and convenience of construction management.
Adopt a BIM-based project construction management method to build a digital twin model by acquiring multi-modal data from managers to display the overall situation of the construction site, and achieve remote management through virtual camera shooting and fusion of images to optimize the adjustment and information of the display frame exhibit.
It reduces labor costs, realizes global management and remote management, improves the efficiency and convenience of construction management, and improves the operational convenience and information detail of managers.
Smart Images

Figure CN118229225B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of digital twin technology, and in particular to a BIM-based project construction management method and system. Background Art
[0002] In order to ensure that the construction of the project is carried out in an orderly, stable and safe manner, continuous project construction management is required.
[0003] Generally, when conducting project construction management, multiple managers are arranged at the project construction site to conduct on-site management. However, this has its shortcomings: first, managers need to patrol the project construction site, which has a high labor cost; second, the area of the project construction site is often large, and managers cannot conduct overall management of the project construction site, which reduces the efficiency of construction management; third, managers cannot conduct remote management of the project construction site, which is less convenient and less applicable.
[0004] Therefore, a solution is urgently needed. Summary of the invention
[0005] One of the purposes of the present invention is to provide a project construction management method based on BIM. Managers can manage the project construction site by viewing the digital twin. There is no need to patrol the project construction site, which reduces labor costs. The digital twin model displays the status of the project construction site to managers from a global perspective. Managers can manage the project construction site globally, thereby improving construction management efficiency. Secondly, managers can remotely manage the project construction site through the digital twin model, which improves convenience and applicability.
[0006] An embodiment of the present invention provides a BIM-based project construction management method, including:
[0007] When a display terminal reports a management request, obtaining multimodal data of multiple managers viewing the display terminal;
[0008] Determining a plurality of model building constraints based on the multimodal data of each of the managers;
[0009] Based on the BIM engine, a digital twin model of the project construction site is constructed that meets each of the model construction constraints;
[0010] Output the digital twin model to the display terminal.
[0011] Preferably, the BIM-based project construction management method further includes:
[0012] Connecting to a display frame in the display terminal for displaying the digital twin model;
[0013] Acquire an operation sequence generated by each of the managers operating the display frame within a recently preset first time period;
[0014] When the operation sequence meets the standard sequence condition, obtaining the first area of the display frame that was most recently exited in the digital twin model;
[0015] Obtaining a required value for retention of the first region;
[0016] When the required value for retention is greater than or equal to a preset required value threshold, obtaining a first boundary line that the first area in the display frame passes through when exiting the display frame;
[0017] Controlling the first boundary line to move toward a preset enlarged moving direction corresponding to the first boundary line;
[0018] During the movement of the first boundary line, a second boundary line in the display frame other than the first boundary line grows adaptively to keep continuous connection with the first boundary line and keep the connection point with the first boundary line unchanged, and the first boundary line and the second boundary line are connected to form a new display frame;
[0019] When the first area completely enters the new display frame, the first boundary line is controlled to stop moving.
[0020] Preferably, the standard sequence conditions include:
[0021] The operation sequence represents that any one of the managers continuously performs a preset standard operation type operation on the display frame for a duration greater than or equal to a preset first time period and does not perform an operation other than the standard operation type on the display frame for a duration greater than or equal to a preset second time period.
[0022] Preferably, the obtaining of the required retention value of the first area includes:
[0023] Obtaining a second area of the digital twin that is currently located in the display frame;
[0024] Extracting the association relationship between the first area and the second area to obtain an association relationship set;
[0025] Based on a preset retention necessity evaluation library and according to the association relationship set, a retention necessity evaluation is performed on the first region to obtain the retention necessity value.
[0026] Preferably, the BIM-based project construction management method further includes:
[0027] Acquire a first dialogue sequence generated by dialogues between the managers within a recently preset second time period;
[0028] constructing a first semantic vector of the first dialogue sequence;
[0029] Matching the first semantic vector with each second semantic vector in a preset first standard semantic vector library respectively;
[0030] When the match is met, the preset attention object determination rule and the preset acquisition time length corresponding to the standard semantic vector that matches the match are obtained;
[0031] Based on the attention object determination rule, determining the attention object that each of the managers is paying attention to from the second area;
[0032] Acquire a second dialogue sequence generated by dialogues between the managers within the acquisition time period in the future;
[0033] constructing a third semantic vector of the second dialogue sequence;
[0034] Matching the third semantic vector with each fourth semantic vector in a preset second standard semantic vector library respectively;
[0035] When the match is confirmed, obtaining a preset shooting angle determination rule corresponding to the fourth semantic vector that is confirmed by the match;
[0036] Based on the shooting angle determination rule, determining a shooting angle for shooting the object of interest in the digital twin model;
[0037] Controlling a virtual camera to capture a perspective image of the object of interest at the shooting perspective in the digital twin model;
[0038] Fusing the perspective images to obtain a fused image;
[0039] The fused image is mapped next to the object of interest.
[0040] An embodiment of the present invention provides a BIM-based project construction management system, including:
[0041] An acquisition module, used for acquiring multimodal data of multiple managers viewing the display terminal when the display terminal reports a management request;
[0042] A determination module, configured to determine a plurality of model building constraints based on the multimodal data of each of the managers;
[0043] A construction module, for constructing a digital twin model of the project construction site that meets each of the model construction constraints based on a BIM engine;
[0044] An output module is used to output the digital twin model to the display terminal.
[0045] Preferably, the BIM-based project construction management system is characterized by further comprising:
[0046] The first auxiliary module is used to include:
[0047] Connecting to a display frame in the display terminal for displaying the digital twin model;
[0048] Acquire an operation sequence generated by each of the managers operating the display frame within a recently preset first time period;
[0049] When the operation sequence meets the standard sequence condition, obtaining the first area of the display frame that was most recently exited in the digital twin model;
[0050] Obtaining a required value for retention of the first region;
[0051] When the required value for retention is greater than or equal to a preset required value threshold, obtaining a first boundary line that the first area in the display frame passes through when exiting the display frame;
[0052] Controlling the first boundary line to move toward a preset enlarged moving direction corresponding to the first boundary line;
[0053] During the movement of the first boundary line, a second boundary line in the display frame other than the first boundary line grows adaptively to keep continuous connection with the first boundary line and keep the connection point with the first boundary line unchanged, and the first boundary line and the second boundary line are connected to form a new display frame;
[0054] When the first area completely enters the new display frame, the first boundary line is controlled to stop moving.
[0055] Preferably, the standard sequence conditions include:
[0056] The operation sequence represents that any one of the managers continuously performs a preset standard operation type operation on the display frame for a duration greater than or equal to a preset first time period and does not perform an operation other than the standard operation type on the display frame for a duration greater than or equal to a preset second time period.
[0057] Preferably, the first auxiliary module obtains the necessary retention value of the first area, including:
[0058] Obtaining a second area of the digital twin that is currently located in the display frame;
[0059] Extracting the association relationship between the first area and the second area to obtain an association relationship set;
[0060] Based on a preset retention necessity evaluation library and according to the association relationship set, a retention necessity evaluation is performed on the first region to obtain the retention necessity value.
[0061] Preferably, the BIM-based project construction management method further includes:
[0062] The second auxiliary module is used to include:
[0063] Acquire a first dialogue sequence generated by dialogues between the managers within a recently preset second time period;
[0064] constructing a first semantic vector of the first dialogue sequence;
[0065] Matching the first semantic vector with each second semantic vector in a preset first standard semantic vector library respectively;
[0066] When the match is met, the preset attention object determination rule and the preset acquisition time length corresponding to the standard semantic vector that matches the match are obtained;
[0067] Based on the attention object determination rule, determining the attention object that each of the managers is paying attention to from the second area;
[0068] Acquire a second dialogue sequence generated by dialogues between the managers within the acquisition time period in the future;
[0069] constructing a third semantic vector of the second dialogue sequence;
[0070] Matching the third semantic vector with each fourth semantic vector in a preset second standard semantic vector library respectively;
[0071] When the match is confirmed, obtaining a preset shooting angle determination rule corresponding to the fourth semantic vector that is confirmed by the match;
[0072] Based on the shooting angle determination rule, determining a shooting angle for shooting the object of interest in the digital twin model;
[0073] Controlling a virtual camera to capture a perspective image of the object of interest at the shooting perspective in the digital twin model;
[0074] Fusing the perspective images to obtain a fused image;
[0075] The fused image is mapped next to the object of interest.
[0076] Other features and advantages of the present invention will be described in the following description, and partly become apparent from the description, or understood by practicing the present invention. The purpose and other advantages of the present invention can be realized and obtained by the structures particularly pointed out in the written description, claims, and drawings.
[0077] The technical solution of the present invention is further described in detail below through the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS
[0078] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:
[0079] Figure 1 A schematic diagram of a BIM-based project construction management method in an embodiment of the present invention;
[0080] Figure 2 Schematic diagram of a BIM-based project construction management system in an embodiment of the present invention. DETAILED DESCRIPTION
[0081] The preferred embodiments of the present invention are described below in conjunction with the accompanying drawings. It should be understood that the preferred embodiments described herein are only used to illustrate and explain the present invention, and are not used to limit the present invention.
[0082] The embodiment of the present invention provides a project construction management method based on BIM, such as Figure 1 As shown, including:
[0083] S1. When a display terminal reports a management request, obtaining multimodal data of multiple managers viewing the display terminal;
[0084] S2. determining a plurality of model building constraints based on the multimodal data of each of the managers;
[0085] S3. Based on the BIM engine, a digital twin model of the project construction site is constructed that meets each of the model construction constraints;
[0086] S4. Output the digital twin model to the display terminal.
[0087] The display terminal is a mobile smart device for managers to view information, such as: mobile phones, tablets, command screens, etc.; managers are personnel who manage the project construction site; multimodal data include: positions, responsible areas within the project construction site, areas that have been managed historically, etc.; model construction constraints are conditions that make the constructed digital twin model of the project construction site suitable for management personnel to view, for example: the responsible area within the project construction site in the multimodal data is area A, indicating that the manager is responsible for the project construction management of area A, then the production model construction constraint is that area A is included in the digital twin model; the BIM engine can be a BIM platform, BIM software, etc.; when building a digital twin model, the project construction site is digitally twinned, and the digital twin model must meet each model construction constraint; after the digital twin model is built, it is output to the display terminal, and managers can view the digital twin model to manage the project construction site.
[0088] The managers of this application can manage the project construction site by viewing the digital twin. There is no need to patrol the project construction site, which reduces labor costs. The digital twin model shows the status of the project construction site to the managers from a global perspective. The managers can manage the project construction site globally, which improves the construction management efficiency. Secondly, the managers can remotely manage the project construction site through the digital twin model, which improves convenience and applicability.
[0089] In one embodiment, the BIM-based project construction management method further includes:
[0090] Connecting to a display frame in the display terminal for displaying the digital twin model;
[0091] Acquire an operation sequence generated by each of the managers operating the display frame within a recently preset first time period;
[0092] When the operation sequence meets the standard sequence condition, obtaining the first area of the display frame that was most recently exited in the digital twin model;
[0093] Obtaining a required value for retention of the first region;
[0094] When the required value for retention is greater than or equal to a preset required value threshold, obtaining a first boundary line that the first area in the display frame passes through when exiting the display frame;
[0095] Controlling the first boundary line to move toward a preset enlarged moving direction corresponding to the first boundary line;
[0096] During the movement of the first boundary line, a second boundary line in the display frame other than the first boundary line grows adaptively to keep continuous connection with the first boundary line and keep the connection point with the first boundary line unchanged, and the first boundary line and the second boundary line are connected to form a new display frame;
[0097] When the first area completely enters the new display frame, the first boundary line is controlled to stop moving.
[0098] The display frame is used to display the digital twin model. However, due to the limited screen area of the display terminal and the limited detail of the information displayed in the digital twin model, the display frame cannot jointly display all areas and all information of the digital twin model; the first time can be 20 seconds; the manager can drag the display frame, zoom in / out, etc., and sort the generated operations according to the order in which the manager operates the display frame to obtain an operation sequence; when the operation sequence meets the standard sequence conditions, it means that the manager operates the display frame to make part of the area in the digital twin model exit the display frame, and obtains the first area of the digital twin model that most recently exited the display frame; retaining the necessary value represents the degree of necessity of the manager still needing to view the first area. The larger the retaining necessary value, the greater the degree of necessity represented; the necessary value threshold can be 8. When the retaining necessary value is greater than or equal to the necessary value threshold When the value is greater than 0, it means that the administrator still needs to check the first area. When the first area exits the display frame, it will pass through the first boundary line of the display frame. For example, the display frame is a rectangular display frame, and the first area is originally located in the upper left corner of the display frame. When the first area exits the display frame, it will pass through the two sides of the upper left right angle of the display frame, that is, the two first boundary lines. Different boundary lines of the display frame are preset with corresponding expansion movement directions, and the expansion movement direction is the opposite direction of the midpoint of the first boundary line to the center point of the display frame. When the first boundary line moves in the expansion movement direction, the second boundary line grows adaptively, keeping the connection point with the first boundary line unchanged and continuously connected with the first boundary line. In this way, the display area of the new display frame will become larger, and the first area will gradually enter the new display frame. When the first area completely enters the new display frame, the first boundary line is controlled to stop moving. In order to enable this process to be realized, the display frame is usually set in the central area of the display screen of the display terminal to leave space for temporary expansion of the display frame.
[0099] Generally, when managers drag the digital twin model, if they find that the newly viewed area needs to be viewed together with the area that has just been viewed and exited the display frame, the display frame will be reduced so that the newly viewed area and the area that has just been viewed and exited the display frame can enter the display frame together. There are problems with this: first, managers need to adjust the display frame by themselves. Since the reduction operation has a certain degree of error, managers cannot quickly adjust the display frame to just display the newly viewed area and the area that has just been viewed and exited the display frame; second, after the display frame is reduced, the newly viewed area and the area that has just been viewed and exited the display frame can indeed be viewed together, but the detail of the information in the display frame showing the newly viewed area and the area that has just been viewed and exited the display frame will be reduced. If the manager wants to view it in more detail, he still needs to enlarge the display frame again. The embodiment of the present invention can solve two problems: temporarily expanding the first boundary line so that the administrator can view the newly viewed area together with the area that has just been viewed and exited the display frame, and the information displayed in these two areas is displayed in high detail, without the administrator having to determine by himself whether the newly viewed area needs to be viewed together with the area that has just been viewed and exited the display frame, and the new display frame can be quickly adjusted to the most suitable size without the administrator having to adjust it by himself, which greatly improves convenience and is more user-friendly.
[0100] In one embodiment, the standard sequence conditions include:
[0101] The operation sequence represents that any one of the managers continuously performs a preset standard operation type operation on the display frame for a duration greater than or equal to a preset first time period and does not perform an operation other than the standard operation type on the display frame for a duration greater than or equal to a preset second time period.
[0102] The preset first duration can be 5 seconds; the standard operation type can be a screen drag operation; the second duration can be 8 seconds; when the standard sequence conditions are met, it means that the administrator has dragged the digital twin model in the display frame for a certain period of time to view the new screen, and has stopped dragging the digital twin model. It can be determined that the administrator operated the display frame to cause part of the area in the digital twin model to exit the display frame.
[0103] In one embodiment, obtaining the required retention value of the first area includes:
[0104] Obtaining a second area of the digital twin that is currently located in the display frame;
[0105] Extracting the association relationship between the first area and the second area to obtain an association relationship set;
[0106] Based on a preset retention necessity evaluation library and according to the association relationship set, a retention necessity evaluation is performed on the first region to obtain the retention necessity value.
[0107] The associations in the association set may be those belonging to the same area type (for example, a lifting area), those with construction personnel / operating equipment about to move from one area to another area, etc.; there are necessary weight values corresponding to different associations in the retention necessity evaluation library. The larger the necessary weight value, the degree to which the manager represented still needs to check the first area when the first area has the association with the second area. For example, if the association belongs to the same area type, it means that the manager can check the first area and the second area of the same area type at the same time, and the corresponding necessary weight value is 3; based on the retention necessity evaluation library, when determining the retention necessary value according to the association set, the necessary weight values corresponding to each association in the association set in the retention necessity evaluation library are accumulated and calculated to obtain the value.
[0108] In one embodiment, the BIM-based project construction management method further includes:
[0109] Acquire a first dialogue sequence generated by dialogues between the managers within a recently preset second time period;
[0110] constructing a first semantic vector of the first dialogue sequence;
[0111] Matching the first semantic vector with each second semantic vector in a preset first standard semantic vector library respectively;
[0112] When the match is met, the preset attention object determination rule and the preset acquisition time length corresponding to the standard semantic vector that matches the match are obtained;
[0113] Based on the attention object determination rule, determining the attention object that each of the managers is paying attention to from the second area;
[0114] Acquire a second dialogue sequence generated by dialogues between the managers within the acquisition time period in the future;
[0115] constructing a third semantic vector of the second dialogue sequence;
[0116] Matching the third semantic vector with each fourth semantic vector in a preset second standard semantic vector library respectively;
[0117] When the match is confirmed, obtaining a preset shooting angle determination rule corresponding to the fourth semantic vector that is confirmed by the match;
[0118] Based on the shooting angle determination rule, determining a shooting angle for shooting the object of interest in the digital twin model;
[0119] Controlling a virtual camera to capture a perspective image of the object of interest at the shooting perspective in the digital twin model;
[0120] Fusing the perspective images to obtain a fused image;
[0121] The fused image is mapped next to the object of interest.
[0122] The second time can be 100 seconds; when the managers view the digital twin model together, they will communicate and discuss, and generate dialogues. The dialogues are sorted in the order in which the dialogues are generated to obtain a first dialogue sequence; based on the semantic description technology, a first semantic vector of the first dialogue sequence is constructed; the first standard semantic vector library is preset with a second semantic vector, and the second semantic vector is preset with a corresponding focus object determination rule and acquisition duration. The second semantic vector is constructed based on the semantic description technology according to the dialogue representing that the manager has an object of interest in the digital twin model. When the first semantic vector matches the second semantic vector, it represents that the manager has an object of interest in the digital twin model. The focus object determination rule is how to determine the focus object in the digital twin model based on the dialogue reaction of the manager having an object of interest in the digital twin model. For example: the dialogue is "Look at equipment room B", "What's the matter", indicating that the focus object is equipment room B, then the focus object determination rule is to take equipment room B as the focus object, and the acquisition duration is how long in the future the manager who represents the manager's dialogue reaction to the object of interest in the digital twin model will react. The manager wants to view the focus object from which perspective words, such as: 300 seconds, etc.; obtain the second dialogue sequence generated by the dialogue between each manager in the future time; similarly, based on the semantic description technology, construct the third semantic vector of the second dialogue sequence; the second standard semantic vector library is preset with a fourth semantic vector, and the fourth semantic vector is preset with a corresponding shooting angle determination rule. The fourth semantic vector is constructed based on the semantic description technology according to the dialogue representing that the manager has a viewing angle requirement for the object of interest. When the third semantic vector matches the fourth semantic vector, it represents that the manager has a viewing angle requirement for the object of interest. The shooting angle determination rule is a rule for determining the perspective that the manager who represents the dialogue reaction that the manager has a viewing angle requirement for the object of interest wants to view the object of interest. For example: the dialogue is "look at the inside of equipment room B from the northwest corner of equipment room B", then the shooting angle determination rule is to determine the shooting angle as shooting the inside of equipment room B from the northwest corner of equipment room B; control the virtual camera to shoot the perspective image of the object of interest with the shooting perspective; fuse the perspective images to obtain a fused image; map the fused image next to the object of interest, specifically, it can be mapped to the idle area next to the object of interest that is closest to the object of interest. After mapping, the manager can view the fused image.
[0123] Generally, when each manager views a digital twin model, they will communicate and discuss. During the communication and discussion, it is generally inconvenient to operate the digital twin model. In addition, during the communication and discussion, an object of interest may be generated in the digital twin model, and it may be necessary to view the object of interest in the digital twin model from multiple perspectives. In the case where it is inconvenient to operate the digital twin model, it is even more inconvenient to perform complex operations such as multi-perspective adjustment and switching back and forth. Therefore, the embodiment of the present invention first determines whether each manager has an object of interest. When it is yes, the shooting perspective is adaptively determined, and the fused picture after the picture taken by the virtual camera is displayed to the manager. The manager does not need to operate by himself, which improves the comfort of the manager in communicating and discussing, is more humane, and improves the management efficiency of the manager to a certain extent, and is particularly applicable.
[0124] The embodiment of the present invention provides a BIM-based project construction management system. Figure 2 As shown, including:
[0125] An acquisition module 1 is used to acquire multimodal data of multiple managers viewing the display terminal when the display terminal reports a management request;
[0126] A determination module 2, configured to determine a plurality of model building constraints based on the multimodal data of each of the managers;
[0127] Construction module 3, used to construct a digital twin model of the project construction site that meets each of the model construction constraints based on the BIM engine;
[0128] The output module 4 is used to output the digital twin model to the display terminal.
[0129] The BIM-based project construction management system also includes:
[0130] The first auxiliary module is used to include:
[0131] Connecting to a display frame in the display terminal for displaying the digital twin model;
[0132] Acquire an operation sequence generated by each of the managers operating the display frame within a recently preset first time period;
[0133] When the operation sequence meets the standard sequence condition, obtaining the first area of the display frame that was most recently exited in the digital twin model;
[0134] Obtaining a required value for retention of the first region;
[0135] When the required value for retention is greater than or equal to a preset required value threshold, obtaining a first boundary line that the first area in the display frame passes through when exiting the display frame;
[0136] Controlling the first boundary line to move toward a preset enlarged moving direction corresponding to the first boundary line;
[0137] During the movement of the first boundary line, a second boundary line in the display frame other than the first boundary line grows adaptively to keep continuous connection with the first boundary line and keep the connection point with the first boundary line unchanged, and the first boundary line and the second boundary line are connected to form a new display frame;
[0138] When the first area completely enters the new display frame, the first boundary line is controlled to stop moving.
[0139] The standard sequence conditions include:
[0140] The operation sequence represents that any one of the managers continuously performs a preset standard operation type operation on the display frame for a duration greater than or equal to a preset first time period and does not perform an operation other than the standard operation type on the display frame for a duration greater than or equal to a preset second time period.
[0141] The first auxiliary module obtains the necessary reservation value of the first area, including:
[0142] Obtaining a second area of the digital twin that is currently located in the display frame;
[0143] Extracting the association relationship between the first area and the second area to obtain an association relationship set;
[0144] Based on a preset retention necessity evaluation library and according to the association relationship set, a retention necessity evaluation is performed on the first region to obtain the retention necessity value.
[0145] The BIM-based project construction management method also includes:
[0146] The second auxiliary module is used to include:
[0147] Acquire a first dialogue sequence generated by dialogues between the managers within a recently preset second time period;
[0148] constructing a first semantic vector of the first dialogue sequence;
[0149] Matching the first semantic vector with each second semantic vector in a preset first standard semantic vector library respectively;
[0150] When the match is met, the preset attention object determination rule and the preset acquisition time length corresponding to the standard semantic vector that matches the match are obtained;
[0151] Based on the attention object determination rule, determining the attention object that each of the managers is paying attention to from the second area;
[0152] Acquire a second dialogue sequence generated by dialogues between the managers within the acquisition time period in the future;
[0153] constructing a third semantic vector of the second dialogue sequence;
[0154] Matching the third semantic vector with each fourth semantic vector in a preset second standard semantic vector library respectively;
[0155] When the match is confirmed, obtaining a preset shooting angle determination rule corresponding to the fourth semantic vector that is confirmed by the match;
[0156] Based on the shooting angle determination rule, determining a shooting angle for shooting the object of interest in the digital twin model;
[0157] Controlling a virtual camera to capture a perspective image of the object of interest at the shooting perspective in the digital twin model;
[0158] Fusing the perspective images to obtain a fused image;
[0159] The fused image is mapped next to the object of interest.
[0160] Obviously, those skilled in the art can make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if these modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include these modifications and variations.
Claims
1. A BIM-based project construction management method, characterized in that: include: When a display terminal reports a management request, obtaining multimodal data of multiple managers viewing the display terminal; Determining a plurality of model building constraints based on the multimodal data of each of the managers; Based on the BIM engine, a digital twin model of the project construction site is constructed that meets each of the model construction constraints; Outputting the digital twin model to the display terminal; Also includes: Connecting to a display frame in the display terminal for displaying the digital twin model; Acquire an operation sequence generated by each of the managers operating the display frame within a recently preset first time period; When the operation sequence meets the standard sequence condition, obtaining the first area of the display frame that was most recently exited in the digital twin model; Obtaining a required value for retention of the first region; When the required value for retention is greater than or equal to a preset required value threshold, obtaining a first boundary line that the first area in the display frame passes through when exiting the display frame; Controlling the first boundary line to move toward a preset enlarged moving direction corresponding to the first boundary line; During the movement of the first boundary line, a second boundary line in the display frame other than the first boundary line grows adaptively to keep continuous connection with the first boundary line and keep the connection point with the first boundary line unchanged, and the first boundary line and the second boundary line are connected to form a new display frame; When the first area completely enters the new display frame, controlling the first boundary line to stop moving; The standard sequence conditions include: The operation sequence represents that any one of the managers continuously performs a preset standard operation type operation on the display frame for a period of time greater than or equal to a preset first time period and does not perform an operation of a non-standard operation type on the display frame for a period of time greater than or equal to a preset second time period; The obtaining of the required retention value of the first area includes: Obtaining a second area of the digital twin that is currently located in the display frame; Extracting the association relationship between the first area and the second area to obtain an association relationship set; Based on a preset retention necessity evaluation library and according to the association relationship set, a retention necessity evaluation is performed on the first region to obtain the retention necessity value.
2. A BIM-based project construction management method as claimed in claim 1, characterized in that: Also includes: Acquire a first dialogue sequence generated by dialogues between the managers within a recently preset second time period; constructing a first semantic vector of the first dialogue sequence; Matching the first semantic vector with each second semantic vector in a preset first standard semantic vector library respectively; When the match is met, the preset attention object determination rule and the preset acquisition time length corresponding to the standard semantic vector that matches the match are obtained; Based on the attention object determination rule, determining the attention object that each of the managers is paying attention to from the second area; Acquire a second dialogue sequence generated by dialogues between the managers within the acquisition time period in the future; constructing a third semantic vector of the second dialogue sequence; Matching the third semantic vector with each fourth semantic vector in a preset second standard semantic vector library respectively; When the match is confirmed, obtaining a preset shooting angle determination rule corresponding to the fourth semantic vector that is confirmed by the match; Based on the shooting angle determination rule, determining a shooting angle for shooting the object of interest in the digital twin model; Controlling a virtual camera to capture a perspective image of the object of interest at the shooting perspective in the digital twin model; Fusing the perspective images to obtain a fused image; The fused image is mapped next to the object of interest.
3. A BIM-based project construction management system, characterized in that: include: An acquisition module, used for acquiring multimodal data of multiple managers viewing the display terminal when the display terminal reports a management request; A determination module, configured to determine a plurality of model building constraints based on the multimodal data of each of the managers; A construction module, for constructing a digital twin model of the project construction site that meets each of the model construction constraints based on a BIM engine; An output module, used to output the digital twin model to the display terminal; Also includes: The first auxiliary module is used to include: Connecting to a display frame in the display terminal for displaying the digital twin model; Acquire an operation sequence generated by each of the managers operating the display frame within a recently preset first time period; When the operation sequence meets the standard sequence condition, obtaining the first area of the display frame that was most recently exited in the digital twin model; Obtaining a required value for retention of the first region; When the required value for retention is greater than or equal to a preset required value threshold, obtaining a first boundary line that the first area in the display frame passes through when exiting the display frame; Controlling the first boundary line to move toward a preset enlarged moving direction corresponding to the first boundary line; During the movement of the first boundary line, a second boundary line in the display frame other than the first boundary line grows adaptively to keep continuous connection with the first boundary line and keep the connection point with the first boundary line unchanged, and the first boundary line and the second boundary line are connected to form a new display frame; When the first area completely enters the new display frame, controlling the first boundary line to stop moving; The standard sequence conditions include: The operation sequence represents that any one of the managers continuously performs a preset standard operation type operation on the display frame for a period of time greater than or equal to a preset first time period and does not perform an operation of a non-standard operation type on the display frame for a period of time greater than or equal to a preset second time period; The first auxiliary module obtains the necessary reservation value of the first area, including: Obtaining a second area of the digital twin that is currently located in the display frame; Extracting the association relationship between the first area and the second area to obtain an association relationship set; Based on a preset retention necessity evaluation library and according to the association relationship set, a retention necessity evaluation is performed on the first region to obtain the retention necessity value.
4. A BIM-based project construction management system as claimed in claim 3, characterized in that: Also includes: The second auxiliary module is used to include: Acquire a first dialogue sequence generated by dialogues between the managers within a recently preset second time period; constructing a first semantic vector of the first dialogue sequence; Matching the first semantic vector with each second semantic vector in a preset first standard semantic vector library respectively; When the match is met, the preset attention object determination rule and the preset acquisition time length corresponding to the standard semantic vector that matches the match are obtained; Based on the attention object determination rule, determining the attention object that each of the managers is paying attention to from the second area; Acquire a second dialogue sequence generated by dialogues between the managers within the acquisition time period in the future; constructing a third semantic vector of the second dialogue sequence; Matching the third semantic vector with each fourth semantic vector in a preset second standard semantic vector library respectively; When the match is confirmed, obtaining a preset shooting angle determination rule corresponding to the fourth semantic vector that is confirmed by the match; Based on the shooting angle determination rule, determining a shooting angle for shooting the object of interest in the digital twin model; Controlling a virtual camera to capture a perspective image of the object of interest at the shooting perspective in the digital twin model; Fusing the perspective images to obtain a fused image; The fused image is mapped next to the object of interest.
Citation Information
Patent Citations
Petrochemical wharf digital twin management method and system
CN116384901A
Digital twin pipe gallery system based on reduced-order simulation model and real-time calibration algorithm
CN116542185A
Field construction personnel management and control system and method based on digital twinning
CN116911522A
Decision-making system and analysis method for rail transit engineering data analysis