A parametric modeling and calculation method for steel grid based on BIM technology

Three-dimensional reconstruction and re-inspection of the steel grid are carried out through BIM technology and binocular vision technology, which solves the problem of high cost of re-inspection of the steel grid and achieves efficient and accurate re-inspection of construction results.

CN118229890BActive Publication Date: 2024-10-29CHINA CONSTR SIXTH ENG BUREAU CIVILENG +1
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410643501.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-05-23
Publication Date
2024-10-29
Estimated Expiration
2044-05-23

AI Technical Summary

Technical Problem

The cost of retesting steel grids is high, and it is difficult to recheck construction results efficiently and accurately with existing technology.

Method used

Using parametric modeling and calculation methods based on BIM technology, a three-dimensional model is generated through binocular image information and position and posture information, and the measured spatial coordinates and error values ​​of key points are determined. The three-dimensional reconstruction results are combined for re-examination, and the accuracy of the three-dimensional reconstruction is used. and compliance probability values ​​to evaluate re-inspection results.

Benefits of technology

Efficient and accurate re-inspection of the steel grid construction results is achieved, the re-inspection cost is reduced, and the re-inspection efficiency and effect are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118229890B_ABST
    Figure CN118229890B_ABST
Patent Text Reader

Abstract

The present application provides a parametric modeling and calculation method for steel grid frames based on BIM technology, which belongs to the field of steel grid frame detection and is used to solve the problem of high cost of re-measurement of steel grid frames in related technologies. The method uses binocular image information to perform three-dimensional reconstruction of the local steel grid frame, and determines the accuracy of the three-dimensional reconstruction based on the distance between the shooting position and the local steel grid frame being photographed. The re-inspection result of the local steel grid frame is determined based on the result of the three-dimensional reconstruction and the comprehensive determination of the three-dimensional reconstruction. On the one hand, it can realize the re-inspection of the construction results of the steel grid frame, and on the other hand, it can ensure the efficiency and effect of the re-inspection.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of steel grid monitoring, and in particular to a parametric modeling and calculation method for steel grids based on BIM technology. Background Art

[0002] Steel grids, also known as steel structure grids, are generally composed of steel structure parts spliced ​​together and are mostly used in the ceilings of various building structures, such as gymnasiums, gas stations, warehouses, etc. After the steel grid is completed, it is necessary to re-measure the steel grid to ensure that the construction results of the steel grid meet the standards. At present, most of the re-measurement of steel grids requires surveyors to use total stations or RTK surveying instruments to complete the work, and the cost of re-measurement is relatively high. Summary of the invention

[0003] The present application provides a parametric modeling and calculation method for steel grid frames based on BIM technology, which is conducive to reducing the cost of re-measurement work of steel grid frames.

[0004] The present application provides a steel grid parametric modeling and calculation method based on BIM technology, which specifically adopts the following technical solutions:

[0005] A parametric modeling and calculation method for steel grid based on BIM technology, comprising:

[0006] Obtain local binocular image information of the steel grid and the position and posture information of the binocular camera;

[0007] Generate a measured local three-dimensional model in a pre-constructed three-dimensional space coordinate system according to the binocular image information and the position and posture information, and determine the measured spatial coordinates of several key points in the measured local three-dimensional model;

[0008] Relative to each key point, determining a measured error value according to the measured spatial coordinates and position and posture information;

[0009] The local re-inspection result information of the steel grid is determined by combining the measured spatial coordinates and measured error values ​​of all key points.

[0010] By adopting the above technical scheme, the binocular image information is used to perform three-dimensional reconstruction of the local steel grid, and the accuracy of the three-dimensional reconstruction is determined according to the distance between the shooting position and the local steel grid. The re-inspection result of the local steel grid is determined based on the result of the three-dimensional reconstruction and the comprehensive determination of the three-dimensional reconstruction. On the one hand, the re-inspection of the steel grid construction results can be achieved, and on the other hand, the efficiency and effectiveness of the re-inspection can be guaranteed.

[0011] Further, the determining a measured error value relative to each key point according to the measured spatial coordinates and position and posture information includes:

[0012] Determine the feature space coordinates of a feature point according to the position and posture information;

[0013] Calculate the critical spatial distance between the measured spatial coordinates and the feature spatial coordinates;

[0014] Substitute the key spatial distance into a pre-trained distance error comparison table to obtain a measured error value of the key point, wherein the distance error comparison table includes a comparison relationship between distance values ​​and error values.

[0015] Further, the determining of the re-inspection result information by combining the measured spatial coordinates and the measured error value includes:

[0016] Relative to every two key points, determining a distance range value according to the measured spatial coordinates and measured error values ​​of the key points;

[0017] generating a compliance probability value according to the distance range value and the pre-acquired expected distance range;

[0018] Based on the attention weights pre-acquired relative to every two key points, the ratio of the weighted sum of all compliance probability values ​​to the sum of the variances of all compliance probability values ​​is calculated as the re-inspection result score;

[0019] If the re-examination result score is lower than the re-examination score threshold, an abnormal prompt message is generated.

[0020] Further, the determining a distance range value relative to every two key points according to the measured spatial coordinates and the measured error values ​​of the key points includes:

[0021] A maximum distance value and a minimum distance value are determined relative to every two key points. The maximum distance value is equal to the distance value between the measured spatial coordinates of the two key points plus the measured error value of the two key points. The minimum distance value is equal to the distance value between the measured spatial coordinates of the two key points minus the measured error value of the two key points. The distance range value has the minimum distance value as the lower limit and the maximum distance value as the upper limit.

[0022] Further, generating a compliance probability value according to the distance range value and the pre-acquired expected distance range includes:

[0023] Determine the overlap range amplitude of the overlap portion between the distance range value and the expected distance range;

[0024] Determining a distance range amplitude of the distance range value;

[0025] The ratio of the overlap range amplitude to the distance range amplitude is calculated as the compliance probability value.

[0026] Furthermore, the method for obtaining the attention weight includes:

[0027] Obtain an expected distance value relative to every two key points;

[0028] The ratio of the expected distance value to the preset unit distance is calculated as the attention weight.

[0029] Furthermore, the three-dimensional space coordinate system also pre-constructs an expected three-dimensional model of the steel grid, and the expected three-dimensional model includes expected spatial coordinates of all key points of the steel grid;

[0030] The distance value between the expected spatial coordinates of each two key points is the expected distance value;

[0031] Determine an allowable error value relative to every two key points, wherein the allowable error value is associated with a preset ratio of the expected distance value and is within a preset error threshold range;

[0032] The expected distance range has a lower limit of the expected distance value minus the allowable error value, and an upper limit of the expected distance value plus the allowable error value.

[0033] In summary, this application at least has the following beneficial effects:

[0034] A parametric modeling and calculation method for steel grid frames based on BIM technology is provided, which can use binocular vision technology to reconstruct the steel grid frames in three dimensions and conduct re-inspection based on the three-dimensional reconstructed model. The accuracy of the three-dimensional reconstruction is considered during the re-inspection process, which is conducive to ensuring the efficiency of the re-inspection and the accuracy of the re-inspection results.

[0035] It should be understood that the contents described in the Summary of the Invention are not intended to limit the key or important features of the embodiments of the present application, nor are they intended to limit the scope of the present application. Other features of the present application will become easily understood through the following description. BRIEF DESCRIPTION OF THE DRAWINGS

[0036] The above and other features, advantages and aspects of the embodiments of the present application will become more apparent with reference to the following detailed description in conjunction with the accompanying drawings. In the accompanying drawings, the same or similar reference numerals represent the same or similar elements, wherein:

[0037] Figure 1 A schematic diagram showing an exemplary operating environment in which embodiments of the present application can be implemented;

[0038] Figure 2 A flow chart of a parametric modeling and calculation method of a steel grid based on BIM technology in an embodiment of the present application is shown. DETAILED DESCRIPTION

[0039] In order to make the purpose, technical solution and advantages of the embodiments of the present application clearer, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.

[0040] In addition, the term "and / or" in this article is only a description of the association relationship between the associated objects, indicating that there can be three relationships. For example, A and / or B can represent: A exists alone, A and B exist at the same time, and B exists alone. In addition, the character " / " in this article generally indicates that the associated objects before and after are in an "or" relationship.

[0041] The present application provides a parametric modeling and calculation method for steel grid frames based on BIM technology, which can perform efficient and reliable re-inspection of completed steel grid frames.

[0042] Figure 1 A schematic diagram of an exemplary operating environment in which embodiments of the present application can be implemented is shown.

[0043] Reference Figure 1 The operating environment includes a binocular camera 110, a positioning system 120 and a server 130.

[0044] Among them, the binocular camera 110 is used to photograph the steel grid to obtain binocular image information of the entire or local steel grid. To facilitate the actual shooting and mobile operation, the binocular camera 110 can be carried by equipment such as drones to photograph the steel grid from various angles and positions.

[0045] The positioning system 120 is used to position the binocular camera 110. Specifically, multiple positioning base stations can be configured at the construction site, and multiple positioning terminals can be configured in the drone equipped with the binocular camera 110. By positioning the multiple positioning terminals, the position and posture information of the binocular camera 110 can be obtained.

[0046] The server 130 is connected to the binocular camera 110 and the positioning system 120, and is used to obtain binocular image information and position and posture information of the binocular camera 110, so as to re-inspect the overall or local construction results of the steel grid frame. The re-inspection is defined here as: judging whether the construction effect of the steel grid frame meets the expected construction effect.

[0047] Figure 2 A flow chart of a steel grid parametric modeling and calculation method based on BIM technology in an embodiment of the present application is shown. The method can be Figure 1 The server 130 executes in.

[0048] Reference Figure 2 , the method specifically comprises the following steps:

[0049] S210: Obtaining binocular image information of a part of the steel grid and position and posture information of the binocular camera 110.

[0050] Since the server 130 is connected to the binocular camera 110 and the positioning system 120 , the server 130 can directly obtain the binocular image information captured by the binocular camera 110 and the position and posture information of the binocular camera 110 .

[0051] The binocular image information includes a first visual image and a second visual image, and shooting directions of the first visual image and the second visual image form a certain angle.

[0052] The position and posture information reflects the position and posture of the binocular camera 110. Specifically, a three-dimensional space coordinate system can be pre-constructed based on the position of the positioning base station in the positioning system 120. The position of the positioning base station is fixed in the three-dimensional space coordinate system. The three-dimensional model of the binocular camera 110 can be reconstructed in the three-dimensional space coordinate system, and the position and posture of the camera three-dimensional model can be used to reflect the position and posture information of the binocular camera 110 in reality in the three-dimensional space coordinate system.

[0053] S220: Generate a measured local three-dimensional model in a pre-constructed three-dimensional space coordinate system according to the binocular image information and the position and posture information, and determine the measured space coordinates of several key points in the measured local three-dimensional model.

[0054] In the method of this step, the pre-constructed three-dimensional space coordinate system can refer to the description in the previous steps.

[0055] The generation of the measured local three-dimensional model based on binocular image information relies on the three-dimensional reconstruction technology based on binocular vision in the existing technology. Since the binocular image information captures the local steel grid, the local steel grid can be three-dimensionally reconstructed based on the binocular image information, and the measured local three-dimensional model of the local steel grid is generated in the three-dimensional space coordinate system.

[0056] The relative position and posture relationship between the camera 3D model and the measured local 3D model in the 3D space coordinate system reflects the relative position and posture relationship between the binocular camera 110 and the local steel grid being photographed in reality.

[0057] In an embodiment of the present application, based on the pre-acquired steel grid construction drawings, an expected three-dimensional model of the steel grid is also pre-constructed in the three-dimensional space coordinate system, and the expected three-dimensional model reflects the construction results of the steel grid under ideal conditions.

[0058] Several key points are manually marked in the expected 3D model in advance. The key points represent the steel grid position points that need to be critically controlled during construction and the steel grid position points that need to be critically detected and measured after construction. The key points can also be called key feature points, which can be identified in the expected 3D model and the measured local 3D model based on feature recognition technology, such as the endpoints and connection points of steel structure parts. The position of the key points can reflect whether the construction position of the steel grid is ideal, and the relative positions between different key points can reflect the degree of deformation of the steel grid construction results.

[0059] After constructing the measured local three-dimensional model in the three-dimensional space coordinate system, the key points included in the measured local three-dimensional model can be identified, and the coordinates of the key points in the three-dimensional space coordinate system can be determined accordingly.

[0060] S230: For each key point, determine a measured error value according to the measured spatial coordinates and position and posture information.

[0061] The method of this step specifically includes: determining the feature space coordinates of a feature point based on the position and posture information; calculating the key space distance between the measured space coordinates and the feature space coordinates; substituting the key space distance into a pre-trained distance error comparison table to obtain the measured error value of the key point, and the distance error comparison table includes a comparison relationship between distance values ​​and error values.

[0062] It should be understood that, when the parameters such as the shooting pixel value of the binocular camera 110 are constant, the farther the distance between the photographed position and the shooting position, the lower the accuracy of the binocular image information in reflecting the actual steel grid situation, and the lower the accuracy of the measured local three-dimensional model obtained by the corresponding three-dimensional reconstruction, and vice versa, the closer the distance between the photographed position and the shooting position, the higher the accuracy of the binocular image information in reflecting the actual steel grid situation, and the higher the accuracy of the measured local three-dimensional model obtained by the corresponding three-dimensional reconstruction. Therefore, based on this principle, a distance error comparison table can be pre-trained based on data experience, and the distance error comparison table can reflect the comparison relationship between the distance between the photographed position and the shooting position and the distance error (accuracy) of the three-dimensional reconstruction.

[0063] S240: Determine the local re-inspection result information of the steel grid by combining the measured spatial coordinates and measured error values ​​of all key points.

[0064] The method of this step specifically includes: relative to every two key points, determining a distance range value according to the measured spatial coordinates and the measured error values ​​of the key points; generating a compliance probability value according to the distance range value and the pre-acquired expected distance range; based on the pre-acquired attention weights relative to every two key points, calculating the ratio of the weighted sum of all compliance probability values ​​to the sum of the variances of all compliance probability values ​​as the re-inspection result score; if the re-inspection result score is lower than the re-inspection score threshold, generating an abnormal prompt message.

[0065] In the method of this step, determining a distance range value relative to every two key points based on the measured spatial coordinates and the measured error values ​​of the key points includes: determining a maximum distance value and a minimum distance value relative to every two key points, the maximum distance value is equal to the distance value between the measured spatial coordinates of the two key points plus the measured error value of the two key points, the minimum distance value is equal to the distance value between the measured spatial coordinates of the two key points minus the measured error value of the two key points, and the distance range value has the minimum distance value as the lower limit and the maximum distance value as the upper limit.

[0066] In the method of this step, generating a compliance probability value based on the distance range value and the pre-acquired expected distance range includes: determining the overlap range amplitude of the overlapped part of the distance range value and the expected distance range; determining the distance range amplitude of the distance range value; and calculating the ratio of the overlap range amplitude to the distance range amplitude as the compliance probability value.

[0067] In the method of this step, the method for obtaining the attention weight includes: obtaining an expected distance value relative to every two key points; calculating the ratio of the expected distance value to the preset unit distance as the attention weight. The preset unit distance is a constant preset based on data experience and human experience. When calculating the re-inspection result score, first calculate the weighted sum of all compliance probability values ​​based on the attention weight as the first result, then calculate the variance of all compliance probability values ​​as the second result, and finally calculate the ratio of the first result to the second result as the re-inspection result score.

[0068] In the method of this step, the expected three-dimensional model of the steel grid includes the expected spatial coordinates of all key points of the steel grid; the distance value between the expected spatial coordinates of every two key points is the expected distance value; an allowable error value is determined relative to every two key points, and the allowable error value is associated with a preset ratio of the expected distance value and is within a preset error threshold range; the expected distance range has the result of subtracting the allowable error value from the expected distance value as the lower limit of the range, and has the result of adding the allowable error value to the expected distance value as the upper limit of the range.

[0069] If the re-inspection result score is lower than the re-inspection score threshold, it reflects that the measured spatial coordinates of the key points in the measured local three-dimensional model exceed the expected spatial coordinates by a large number and / or to a large extent, and the degree to which the measured spatial coordinates exceed the corresponding expected spatial coordinates varies, indicating that the construction results deviate seriously from the expected results. An abnormal prompt message can be used to prompt relevant personnel to conduct manual re-inspection or adjust the construction results.

[0070] This method can be applied to the re-inspection of steel grid construction results, that is, to check the deviation between the construction results and the expected results. Of course, this method can also be applied to the early warning of the degree of deformation of the steel grid over time.

[0071] It should be noted that, for the aforementioned method embodiments, for the sake of simplicity of description, they are all expressed as a series of action combinations, but those skilled in the art should be aware that the present application is not limited by the described order of actions, because according to the embodiments of the present application, certain steps can be performed in other orders or simultaneously. Secondly, those skilled in the art should also be aware that the embodiments described in the specification are all optional embodiments, and the actions and modules involved are not necessarily required by the present application.

[0072] In summary, this application at least has the following beneficial effects:

[0073] A parametric modeling and calculation method for steel grid frames based on BIM technology is provided, which can use binocular vision technology to reconstruct the steel grid frames in three dimensions and conduct re-inspection based on the three-dimensional reconstructed model. The accuracy of the three-dimensional reconstruction is considered during the re-inspection process, which is conducive to ensuring the efficiency of the re-inspection and the accuracy of the re-inspection results.

[0074] The above description is only a preferred embodiment of the present application and an explanation of the technical principles used. Those skilled in the art should understand that the scope of disclosure involved in the present application is not limited to the technical solution formed by a specific combination of the above technical features, but should also cover other technical solutions formed by any combination of the above technical features or their equivalent features without departing from the aforementioned disclosed concept. For example, the above features are replaced with the technical features with similar functions disclosed in this application (but not limited to) by each other to form a technical solution.

Claims

1. A parametric modeling and calculation method for steel grid based on BIM technology, characterized in that: include: Acquiring binocular image information of a part of the steel grid and position and posture information of the binocular camera (110); Generate a measured local three-dimensional model in a pre-constructed three-dimensional space coordinate system according to the binocular image information and the position and posture information, and determine the measured spatial coordinates of several key points in the measured local three-dimensional model; Relative to each key point, determining a measured error value according to the measured spatial coordinates and position and posture information; Determine the local re-inspection result information of the steel grid by combining the measured spatial coordinates and measured error values ​​of all key points; The re-inspection result information of the local steel grid determined by combining the measured spatial coordinates and measured error values ​​of all key points includes: Relative to every two key points, determining a distance range value according to the measured spatial coordinates and measured error values ​​of the key points; A compliance probability value is generated according to the distance range value and the pre-acquired expected distance range, the expected three-dimensional model of the steel grid includes the expected spatial coordinates of all key points of the steel grid; the distance value between the expected spatial coordinates of every two key points is the expected distance value; an allowable error value is determined relative to every two key points, the allowable error value is associated with a preset ratio of the expected distance value, and is within a preset error threshold range; the expected distance range takes the result of subtracting the allowable error value from the expected distance value as the lower limit of the range, and takes the result of adding the allowable error value to the expected distance value as the upper limit of the range; Based on the attention weights pre-acquired relative to every two key points, the ratio of the weighted sum of all compliance probability values ​​to the sum of the variances of all compliance probability values ​​is calculated as the re-inspection result score; If the re-examination result score is lower than the re-examination score threshold, an abnormal prompt message is generated.

2. The method according to claim 1, characterized in that The step of determining a measured error value relative to each key point according to the measured spatial coordinates and position and posture information comprises: Determine the feature space coordinates of a feature point according to the position and posture information; Calculate the critical spatial distance between the measured spatial coordinates and the feature spatial coordinates; Substitute the key spatial distance into a pre-trained distance error comparison table to obtain a measured error value of the key point, wherein the distance error comparison table includes a comparison relationship between distance values ​​and error values.

3. The method according to claim 1, characterized in that The determining of a distance range value relative to every two key points according to the measured spatial coordinates and the measured error values ​​of the key points comprises: A maximum distance value and a minimum distance value are determined relative to every two key points. The maximum distance value is equal to the distance value between the measured spatial coordinates of the two key points plus the measured error value of the two key points. The minimum distance value is equal to the distance value between the measured spatial coordinates of the two key points minus the measured error value of the two key points. The distance range value has the minimum distance value as the lower limit and the maximum distance value as the upper limit.

4. The method according to claim 1, characterized in that: The generating a compliance probability value according to the distance range value and the pre-acquired expected distance range includes: Determine the overlap range amplitude of the overlap portion between the distance range value and the expected distance range; Determining a distance range amplitude of the distance range value; The ratio of the overlap range amplitude to the distance range amplitude is calculated as the compliance probability value.

5. The method according to claim 1, characterized in that The method for obtaining the attention weight includes: Obtain an expected distance value relative to every two key points; The ratio of the expected distance value to the preset unit distance is calculated as the attention weight.

6. The method according to claim 1, characterized in that The three-dimensional space coordinate system also pre-constructs an expected three-dimensional model of the steel grid, and the expected three-dimensional model includes expected space coordinates of all key points of the steel grid; The distance value between the expected spatial coordinates of each two key points is the expected distance value; Determine an allowable error value relative to every two key points, wherein the allowable error value is associated with a preset ratio of the expected distance value and is within a preset error threshold range; The expected distance range has a lower limit of the expected distance value minus the allowable error value, and an upper limit of the expected distance value plus the allowable error value.

Citation Information

Patent Citations

  • Three-dimensional reconstruction point cloud error compensation method and system based on stereoscopic vision

    CN112991464A

  • Steel truss modeling method and system based on unmanned aerial vehicle and storage medium

    CN116361996A