Power supply system auxiliary management method based on artificial intelligence
Through the artificial intelligence-based power supply system auxiliary management method, real-time monitoring and analysis of the power grid operating status solves the problem of real-time monitoring and insufficient accuracy in the traditional power grid management method, achieves accurate determination and automated processing of the power grid status, and improves power grid management. efficiency and reliability.
Patent Information
- Application Number
- CN202410477169.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-19
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2044-04-19
AI Technical Summary
Traditional power grid management methods rely on manual inspection and empirical judgment, which cannot achieve real-time monitoring, resulting in inefficient fault handling and difficulty in ensuring the accuracy and reliability of the power grid's operating status.
The AI-based power supply system auxiliary management method is adopted to monitor the power grid operating status information, analyze signal parameters, calculate temperature evaluation values and mutation evaluation values, determine the power grid status in real time, and perform automated adjustment processing.
It achieves the timely discovery and accurate determination of abnormal conditions in the power grid, improves the efficiency and accuracy of power grid management, reduces the need for manual intervention, optimizes the operating efficiency of the power grid, and improves the reliability of power supply.
Smart Images

Figure CN118300270B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of power supply system auxiliary management, and in particular to a power supply system auxiliary management method based on artificial intelligence. Background Art
[0002] In the power supply system, the power grid, as a key infrastructure for power transmission and distribution, carries the important task of transmitting electricity from power stations to thousands of households. The quality of its operation is directly related to the stability, reliability and safety of the entire power system. Therefore, the management of the power grid is particularly important.
[0003] However, traditional power grid management methods mainly rely on manual inspections and empirical judgments, which have many limitations. First, manual inspections cannot achieve real-time monitoring of the power grid and can only be handled after a fault occurs, resulting in inefficient fault handling and may even cause greater safety hazards and inability to perform maintenance in a timely manner. Secondly, although empirical judgments can ensure stable power supply to a certain extent, their accuracy and reliability are often difficult to guarantee for the complex and changeable operating conditions of the power grid. Summary of the invention
[0004] In order to overcome the shortcomings of the background technology, an embodiment of the present invention provides an artificial intelligence-based power supply system auxiliary management method, which can effectively solve the problems involved in the above-mentioned background technology.
[0005] The purpose of the present invention can be achieved through the following technical solutions:
[0006] The power supply system auxiliary management method based on artificial intelligence includes the following steps:
[0007] Step 1: monitoring the operating status information of each power grid in the target area corresponding to the current monitoring period, thereby analyzing the operating status of each power grid in the target area corresponding to the current monitoring period, and obtaining each normal power grid and each marked power grid in the target area;
[0008] Step 2: Real-time monitoring of the signal parameters of each marked power grid corresponding to the target area to obtain the signal parameters of each marked power grid in the target area corresponding to the current monitoring period;
[0009] Step 3: Analyze the temperature evaluation value and abnormal change evaluation value of each marked power grid in the target area corresponding to the current monitoring period, and obtain a signal evaluation parameter set of each marked power grid in the target area corresponding to the current monitoring period;
[0010] Step 4: Analyze the grid status of each marked grid in the target area corresponding to the current monitoring period. If the grid status of a marked grid corresponding to the current monitoring period is determined to be Class A, the marked grid is recorded as a Class A abnormal grid. If the grid status of a marked grid corresponding to the current monitoring period is determined to be Class B, the marked grid is recorded as a Class B abnormal grid, and step 5 is executed at the same time.
[0011] Step 5: It is used to execute processing on the marked power grids of abnormal power grids at various levels in the target area, thereby obtaining adjustment signals and call signals and executing corresponding operation processing.
[0012] Furthermore, the operating status of each power grid in the target area corresponding to the current monitoring period is analyzed. The specific analysis is as follows:
[0013] By acquiring the voltage value, current value and power value in the operating status information of each power grid in the target area corresponding to the current monitoring period, the voltage value, current value and power value in the operating status information of each power grid in the target area corresponding to the current monitoring period are obtained, and the values of the three are extracted for normalization calculation processing to obtain the operating status coefficient of each power grid in the target area corresponding to the current monitoring period;
[0014] The operating status coefficients of the power grids in the target area corresponding to the current monitoring period are compared and analyzed with the reference comparison interval. When the operating status coefficients of the power grids in the target area corresponding to the current monitoring period are within the reference comparison interval, the operating status of the power grids in the target area corresponding to the current monitoring period is determined to be a normal state. Otherwise, the operating status of the power grids in the target area corresponding to the current monitoring period is determined to be an abnormal state. If the operating status of a power grid in the target area corresponding to the current monitoring period is a normal state, the power grid in the target area is recorded as a normal power grid. If the operating status of a power grid in the target area corresponding to the current monitoring period is an abnormal state, the power grid in the target area is recorded as a marked power grid. Thus, normal power grids and marked power grids in the target area are obtained.
[0015] Furthermore, the temperature evaluation values of each marked power grid in the target area corresponding to the current monitoring period are analyzed. The specific analysis is as follows:
[0016] Extract the grid temperature dsc of each marked grid at each monitoring time point in the current monitoring period from the signal parameters of each marked grid in the target area corresponding to the current monitoring period i j , i represents the number of each marked power grid, i=1, 2, 3...n1, n1 represents the total number of numbers of each marked power grid, j represents the number of each monitoring time point, j=1, 2, 3...m, m represents the total number of numbers of each monitoring time point;
[0017] Extract the atmospheric temperature of the target area corresponding to each monitoring period from the system repository, and extract the atmospheric temperature of the target area corresponding to the current monitoring period from it, and at the same time match the atmospheric temperature of the target area corresponding to the current monitoring period with the reference grid temperature corresponding to each set atmospheric temperature to obtain the reference grid temperature DS of the target area corresponding to the current monitoring period;
[0018] The temperature evaluation value wpz of each marked power grid in the target area corresponding to the current monitoring period is calculated by the following formula: i .
[0019] , dsc i j-1 It is represented as the grid temperature of the i-th marked grid at the j-1-th monitoring time point in the current monitoring period, Δdsc is represented as the set reference grid temperature difference, β1, β2, and β3 are represented as the average grid temperature difference corresponding to the set adjacent monitoring time points, the grid temperature difference corresponding to the adjacent monitoring time points, and the influence factors corresponding to the reference grid temperature difference, respectively.
[0020] Furthermore, the abnormal change evaluation values of each marked power grid in the target area corresponding to the current monitoring period are analyzed. The specific analysis is as follows:
[0021] The grid contours of each marked grid corresponding to each monitoring time point in the current monitoring period are extracted from the signal parameters of each marked grid in the target area corresponding to the current monitoring period, and the initial grid contours of each marked grid corresponding to each grid stored in the system storage are extracted based on each marked grid. At the same time, the grid contours of each marked grid corresponding to each monitoring time point in the current monitoring period are overlapped and compared with the initial grid contours of each marked grid, and the overlap area mfd of the grid contours of each marked grid corresponding to each monitoring time point in the current monitoring period is obtained. i j , based on the area of each marked power grid corresponding to the initial power grid contour stored in the system repository, the area mfd corresponding to the initial power grid contour of each marked power grid is extracted i * , so according to the formula Calculate the grid outline overlap value δ1 of each marked grid corresponding to the current monitoring period i , Δmfd is the area difference of the reference contour, mfd i j-1 It is represented as the overlapping area of the grid contour of the i-th marked grid corresponding to the j-1-th monitoring time point in the current monitoring period, and β4 and β5 are respectively represented as the evaluation factors corresponding to the set overlapping area and the overlapping area change rate;
[0022] Extract the grid load fhz of each marked grid at each monitoring time point in the current monitoring period from the signal parameters of each marked grid in the target area corresponding to the current monitoring period i j , and extract the initial grid load fhz corresponding to each marked grid from the initial grid load corresponding to each grid stored in the system repository based on each marked grid i * , according to the formula Calculate the grid load value δ2 of each marked grid corresponding to each monitoring time point in the current monitoring period i j , p represents a natural constant, β6 and β7 represent the influence factor of the set power grid corresponding to the maximum load and the influence factor of the power grid corresponding to the minimum load respectively;
[0023] According to the formula Calculate the abnormal change evaluation value of each marked power grid in the target area corresponding to the current monitoring period i , λ1 and λ2 represent the influence factors corresponding to the set grid profile overlap value and grid load value respectively.
[0024] Furthermore, the grid status of each marked grid in the target area corresponding to the current monitoring period is analyzed, and the specific analysis is as follows:
[0025] According to the formula Calculate the grid status assessment coefficient SPI for each marked grid in the target area corresponding to the current monitoring period i , λ3 and λ4 represent the weight factors corresponding to the set temperature evaluation value and abnormality evaluation value respectively;
[0026] The grid state assessment coefficient of each marked power grid in the target area corresponding to the current monitoring period is compared with the set grid state assessment threshold. If the grid state assessment coefficient of a marked power grid corresponding to the current monitoring period is less than the set grid state assessment threshold, the grid state of the marked power grid corresponding to the current monitoring period is judged to be Class A, and the marked power grid is recorded as a Class A abnormal power grid. Otherwise, the grid state of the marked power grid corresponding to the current monitoring period is judged to be Class B, and the marked power grid is recorded as a Class B abnormal power grid.
[0027] Furthermore, the marked power grids of abnormal power grids at all levels in the target area are processed, and the specific analysis is as follows:
[0028] Obtain a marked power grid determined as a Class A abnormal power grid in the target area, and generate an adjustment signal. According to the generated adjustment signal, perform adjustment processing, and the specific adjustment processing is: set a preset operating state coefficient of the marked power grid determined as a Class A abnormal power grid in the target area, and at the same time retrieve a power grid state evaluation coefficient of the marked power grid determined as a Class A abnormal power grid in the target area, and match the power grid state evaluation coefficient of the marked power grid determined as a Class A abnormal power grid in the target area with a preset power grid state influencing factor to obtain a power grid state influencing factor, extract the preset operating state coefficient of the marked power grid determined as a Class A abnormal power grid in the target area and the value of the power grid state influencing factor, and multiply them to obtain a reference adjustment value of the marked power grid determined as a Class A abnormal power grid in the target area;
[0029] By acquiring the actual operating state coefficient of the marked power grid determined as Class A abnormal power grid in the target area, the actual operating state coefficient of the marked power grid determined as Class A abnormal power grid in the target area is obtained, and the actual operating state coefficient of the marked power grid determined as Class A abnormal power grid in the target area is compared and analyzed with the reference adjustment value to obtain a reduced operating state coefficient or an increased operating state coefficient, then the actual operating state coefficient of the marked power grid determined as Class A abnormal power grid in the target area is reduced to be consistent with the reference adjustment value or increased to be consistent with the reference adjustment value, and a display notification is performed on the display terminal;
[0030] The marked power grid determined as Class B abnormal power grid in the target area is obtained, and a call-up signal is generated. According to the generated call-up signal, the call-up processing is performed. The specific call-up processing is as follows: the distance between the marked power grid determined as Class B abnormal power grid in the target area and each on-duty management and maintenance personnel is obtained, recorded as the travel distance value, the travel distance value is compared and analyzed with the preset travel distance threshold, and the on-duty management and maintenance personnel whose travel distance value is less than the preset travel distance threshold are determined as target personnel; at the same time, the power grid state assessment coefficient of the marked power grid determined as Class B abnormal power grid in the target area is retrieved, and the power grid state assessment coefficient of the marked power grid determined as Class B abnormal power grid in the target area is compared and analyzed with the preset reference interval. When the power grid state assessment coefficient of the marked power grid determined as Class B abnormal power grid in the target area is within the reference interval, the on-duty management and maintenance personnel R1 is sent to perform the maintenance task, otherwise, the on-duty management and maintenance personnel R2 is sent to perform the maintenance task, and the execution maintenance signal is sent to the target personnel in order from small to large according to the travel distance value, and the notification is displayed on the display terminal.
[0031] Compared with the prior art, the present invention has the following beneficial effects:
[0032] The present invention monitors the operating status information of each power grid in the target area, thereby analyzing the current operating status of each power grid, obtaining each normal power grid and each marked power grid, thereby achieving the goal of helping to timely discover abnormal conditions of the power grid and providing an important basis for subsequent abnormal processing;
[0033] By acquiring the signal parameters of each marked power grid in the target area in real time and analyzing them, the temperature evaluation value and abnormal change evaluation value of each marked power grid in the target area corresponding to the current monitoring period are obtained. The temperature evaluation value reflects the temperature change of the power grid, while the abnormal change evaluation value reflects the abnormal degree of the power grid. Through the analysis of these evaluation values, the health status of the power grid can be comprehensively evaluated, providing an important basis for the determination of the power grid status, thereby achieving accurate determination of the power grid status, providing clear guidance for subsequent abnormal processing, and providing strong guarantee for the stable operation of the power supply system, which not only helps to improve the efficiency and accuracy of power grid management, but also provides technical support for the sustainable development of the power industry;
[0034] By conducting corresponding analysis and processing on marked power grids that are judged to be abnormal power grids at different levels, the automatic monitoring and adjustment of the power grid status is realized, the need for manual intervention is reduced, and the refinement and intelligence of management are improved, which is conducive to optimizing the power grid operation efficiency, improving power supply reliability, and injecting new vitality into the sustainable development of the power industry. BRIEF DESCRIPTION OF THE DRAWINGS
[0035] In order to facilitate understanding by those skilled in the art, the present invention is further described below in conjunction with the accompanying drawings;
[0036] Figure 1 A block diagram of the method of the present invention. DETAILED DESCRIPTION
[0037] The technical solution of the present invention will be clearly and completely described below in conjunction with the embodiments. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0038] like Figure 1 As shown, the power supply system auxiliary management method based on artificial intelligence includes the following steps:
[0039] Step 1: Grid operation status analysis: It is used to monitor the operation status information of each grid in the target area corresponding to the current monitoring period, thereby analyzing the operation status of each grid in the target area corresponding to the current monitoring period. The specific analysis method is as follows:
[0040] By obtaining the voltage value, current value and power value in the operating status information of each power grid in the target area corresponding to the current monitoring period, the voltage value, current value and power value in the operating status information of each power grid in the target area corresponding to the current monitoring period are obtained, and they are calibrated as yz g 、dz g and gz g , g represents the number of each power grid, g=1, 2, 3...n, n represents the total number of power grid numbers, and the values of the three are extracted for normalization processing according to the formula: , the operating state coefficient DWZ of each power grid in the target area corresponding to the current monitoring period is obtained, where e represents a natural constant, η1, η2 and η3 represent the weight coefficients of voltage value, current value and power value respectively, and η1>η2>η3. The weight coefficient is used to balance the weight of each data in the formula calculation, thereby promoting the accuracy of the calculation result;
[0041] Compare and analyze the operating status coefficients of each power grid in the target area corresponding to the current monitoring period with the reference comparison interval. When the operating status coefficients of each power grid in the target area corresponding to the current monitoring period are within the reference comparison interval, the operating status of each power grid in the target area corresponding to the current monitoring period is determined to be a normal state. When the operating status coefficients of each power grid in the target area corresponding to the current monitoring period are outside the reference comparison interval, the operating status of each power grid in the target area corresponding to the current monitoring period is determined to be an abnormal state. If the operating status of a power grid in the target area corresponding to the current monitoring period is a normal state, the power grid in the target area is recorded as a normal power grid. If the operating status of a power grid in the target area corresponding to the current monitoring period is an abnormal state, the power grid in the target area is recorded as a marked power grid. Thus, normal power grids and marked power grids in the target area are obtained. Among them, the normal power grid refers to the power grid operating normally in the target area, and the marked power grid refers to the power grid operating abnormally in the target area.
[0042] Step 2: Power grid signal monitoring: used to monitor the signal parameters of each marked power grid corresponding to the target area in real time, and obtain the signal parameters of each marked power grid in the target area corresponding to the current monitoring period; wherein the signal parameters of each marked power grid in the target area corresponding to the current monitoring period are specifically: the power grid temperature of each marked power grid at each monitoring time point in the current monitoring period and the power grid profile and power grid load of each marked power grid at each monitoring time point in the current monitoring period;
[0043] Step 3: Power grid signal analysis: used to analyze the temperature evaluation value and abnormal change evaluation value of each marked power grid in the target area corresponding to the current monitoring period. The specific analysis process is as follows:
[0044] Extract the grid temperature dsc of each marked grid at each monitoring time point in the current monitoring period from the signal parameters of each marked grid in the target area corresponding to the current monitoring period i j , i represents the number of each marked power grid, i=1, 2, 3...n1, n1 represents the total number of the marked power grid numbers, n1<n, j represents the number of each monitoring time point, j=1, 2, 3...m, m represents the total number of the monitoring time point numbers;
[0045] Extract the atmospheric temperature of the target area corresponding to each monitoring period from the system repository, and extract the atmospheric temperature of the target area corresponding to the current monitoring period from it, and at the same time match the atmospheric temperature of the target area corresponding to the current monitoring period with the reference grid temperature corresponding to each set atmospheric temperature to obtain the reference grid temperature DS of the target area corresponding to the current monitoring period;
[0046] The temperature evaluation value wpz of each marked power grid in the target area corresponding to the current monitoring period is calculated by the following formula: i .
[0047] , dsc i j-1 It is represented as the grid temperature of the i-th marked grid at the j-1-th monitoring time point in the current monitoring period, Δdsc is represented as the set reference grid temperature difference, β1, β2, β3 are represented as the average grid temperature difference corresponding to the set adjacent monitoring time points, the grid temperature difference corresponding to the adjacent monitoring time points, and the influence factor corresponding to the reference grid temperature difference, respectively;
[0048] The grid contours of each marked grid corresponding to each monitoring time point in the current monitoring period are extracted from the signal parameters of each marked grid in the target area corresponding to the current monitoring period, and the initial grid contours of each marked grid corresponding to each grid stored in the system storage are extracted based on each marked grid. At the same time, the grid contours of each marked grid corresponding to each monitoring time point in the current monitoring period are overlapped and compared with the initial grid contours of each marked grid, and the overlap area mfd of the grid contours of each marked grid corresponding to each monitoring time point in the current monitoring period is obtained. i j , based on the area of each marked power grid corresponding to the initial power grid contour stored in the system repository, the area mfd corresponding to the initial power grid contour of each marked power grid is extracted i * , so according to the formula Calculate the grid outline overlap value δ1 of each marked grid corresponding to the current monitoring period i , Δmfd is the area difference of the reference contour, mfd i j-1It is represented as the overlapping area of the grid contour of the i-th marked grid corresponding to the j-1-th monitoring time point in the current monitoring period, and β4 and β5 are respectively represented as the evaluation factors corresponding to the set overlapping area and the overlapping area change rate;
[0049] Extract the grid load fhz of each marked grid at each monitoring time point in the current monitoring period from the signal parameters of each marked grid in the target area corresponding to the current monitoring period i j , and extract the initial grid load fhz corresponding to each marked grid from the initial grid load corresponding to each grid stored in the system repository based on each marked grid i * , according to the formula Calculate the grid load value δ2 of each marked grid corresponding to each monitoring time point in the current monitoring period i j , p represents a natural constant, β6 and β7 represent the influence factor of the set power grid corresponding to the maximum load and the influence factor of the power grid corresponding to the minimum load respectively;
[0050] According to the formula Calculate the abnormal change evaluation value of each marked power grid in the target area corresponding to the current monitoring period i , λ1 and λ2 represent the influence factors corresponding to the set grid profile overlap value and grid load value respectively.
[0051] The temperature evaluation value and abnormal change evaluation value of each marked power grid in the target area corresponding to the current monitoring period constitute a signal evaluation parameter set of each marked power grid in the target area corresponding to the current monitoring period;
[0052] Step 4: Grid status analysis: used to analyze the grid status of each marked grid in the target area corresponding to the current monitoring period. The specific analysis steps are as follows:
[0053] According to the formula Calculate the grid status assessment coefficient SPI for each marked grid in the target area corresponding to the current monitoring period i , λ3 and λ4 represent the weight factors corresponding to the set temperature evaluation value and abnormality evaluation value respectively;
[0054] The grid state assessment coefficient of each marked power grid in the target area corresponding to the current monitoring period is compared with the set grid state assessment threshold. If the grid state assessment coefficient of a marked power grid corresponding to the current monitoring period is less than the set grid state assessment threshold, the grid state of the marked power grid corresponding to the current monitoring period is determined to be Class A, and the marked power grid is recorded as a Class A abnormal power grid. Otherwise, the grid state of the marked power grid corresponding to the current monitoring period is determined to be Class B, and the marked power grid is recorded as a Class B abnormal power grid. At the same time, step five is executed, wherein the Class A abnormal power grid is a power grid with short circuit and overload in the target area, and the Class B abnormal power grid is a power grid with apparent abnormal changes in the target area.
[0055] Step 5: Abnormal power grid execution processing: It is used to execute the marked power grids of abnormal power grids of various levels in the target area. The specific process is as follows:
[0056] Obtain a marked power grid determined as a Class A abnormal power grid in the target area, and generate an adjustment signal. According to the generated adjustment signal, perform adjustment processing, and the specific adjustment processing is: set a preset operating state coefficient of the marked power grid determined as a Class A abnormal power grid in the target area, and at the same time retrieve a power grid state evaluation coefficient of the marked power grid determined as a Class A abnormal power grid in the target area, and match the power grid state evaluation coefficient of the marked power grid determined as a Class A abnormal power grid in the target area with a preset power grid state influencing factor to obtain a power grid state influencing factor, extract the preset operating state coefficient of the marked power grid determined as a Class A abnormal power grid in the target area and the value of the power grid state influencing factor, and multiply them to obtain a reference adjustment value of the marked power grid determined as a Class A abnormal power grid in the target area;
[0057] By acquiring the actual operating state coefficient of the marked power grid determined as Class A abnormal power grid in the target area, the actual operating state coefficient of the marked power grid determined as Class A abnormal power grid in the target area is obtained, and the actual operating state coefficient of the marked power grid determined as Class A abnormal power grid in the target area is compared and analyzed with the reference adjustment value;
[0058] If the actual operating state coefficient of the marked power grid determined as Class A abnormal power grid in the target area is greater than the reference adjustment value, the operating state coefficient is reduced, and the actual operating state coefficient of the marked power grid determined as Class A abnormal power grid in the target area is reduced to be consistent with the reference adjustment value, and a display notification is made on the display terminal;
[0059] If the actual operating state coefficient of the marked power grid determined as Class A abnormal power grid in the target area is less than the reference adjustment value, the operating state coefficient is increased, and the actual operating state coefficient of the marked power grid determined as Class A abnormal power grid in the target area is increased to be consistent with the reference adjustment value, and a display notification is made on the display terminal;
[0060] The marked power grid in the target area that is determined to be a Class B abnormal power grid is obtained, and a retrieval signal is generated. According to the generated retrieval signal, the retrieval process is performed. The specific retrieval process is as follows: at the same time, the location information of the on-the-job management and maintenance personnel is located and scanned by GPS, thereby obtaining the location coordinates of each on-the-job management and maintenance personnel, and obtaining the distance between the marked power grid determined to be a Class B abnormal power grid in the target area and each on-the-job management and maintenance personnel, which is recorded as the travel distance value, and the travel distance value is compared and analyzed with the preset travel distance threshold, and the on-the-job management and maintenance personnel whose travel distance value is less than the preset travel distance threshold are determined as target personnel; at the same time, the marked power grid in the target area that is determined to be a Class B abnormal power grid is retrieved. The grid state assessment coefficient of the marked grid of the target area is compared and analyzed with the preset reference interval. When the grid state assessment coefficient of the marked grid of the target area is determined to be a Class B abnormal grid is within the reference interval, the on-the-job management and maintenance personnel R1 is sent to perform the maintenance task. When the grid state assessment coefficient of the marked grid of the target area is determined to be a Class B abnormal grid is outside the reference interval, the on-the-job management and maintenance personnel R2 is sent to perform the maintenance task, and the execution maintenance signal is sent to the target personnel in order from small to large according to the distance value, and the notification is displayed on the display terminal.
[0061] The preferred embodiments of the present invention disclosed above are only used to help explain the present invention. The preferred embodiments do not describe all the details in detail, nor do they limit the invention to only specific implementation methods. Obviously, many modifications and changes can be made according to the content of this specification. This specification selects and specifically describes these embodiments in order to better explain the principles and practical applications of the present invention, so that those skilled in the art can understand and use the present invention well. The present invention is limited only by the claims and their full scope and equivalents.
Claims
1. Power supply system auxiliary management method based on artificial intelligence, It is characterized in that The following steps are involved: Step 1: monitoring the operating status information of each power grid in the target area corresponding to the current monitoring period, thereby analyzing the operating status of each power grid in the target area corresponding to the current monitoring period, and obtaining each normal power grid and each marked power grid in the target area; Step 2: Real-time monitoring of the signal parameters of each marked power grid corresponding to the target area to obtain the signal parameters of each marked power grid in the target area corresponding to the current monitoring period; Step 3: Analyze the temperature evaluation value and abnormal change evaluation value of each marked power grid in the target area corresponding to the current monitoring period, and obtain the signal evaluation parameter set of each marked power grid in the target area corresponding to the current monitoring period; analyze the temperature evaluation value of each marked power grid in the target area corresponding to the current monitoring period, and the specific analysis is as follows: Extract the grid temperature of each marked grid at each monitoring time point in the current monitoring period from the signal parameters of each marked grid in the target area corresponding to the current monitoring period , i represents the number of each marked power grid, i=1, 2, 3...n1, n1 represents the total number of numbers of each marked power grid, j represents the number of each monitoring time point, j=1, 2, 3...m, m represents the total number of numbers of each monitoring time point; Extract the atmospheric temperature of the target area corresponding to each monitoring period from the system repository, and extract the atmospheric temperature of the target area corresponding to the current monitoring period from it , and at the same time, the atmospheric temperature of the target area corresponding to the current monitoring period is matched with the reference grid temperature corresponding to each set atmospheric temperature to obtain the reference grid temperature DS of the target area corresponding to the current monitoring period; The temperature evaluation value of each marked power grid in the target area corresponding to the current monitoring period is calculated by the following formula: ; , It is represented as the grid temperature of the i-th marked grid at the j-1-th monitoring time point in the current monitoring period, Δdsc is represented as the set reference grid temperature difference, β1, β2, β3 are represented as the average grid temperature difference corresponding to the set adjacent monitoring time points, the grid temperature difference corresponding to the adjacent monitoring time points, and the influence factor corresponding to the reference grid temperature difference, respectively; The abnormal change evaluation values of each marked power grid in the target area corresponding to the current monitoring period are analyzed. The specific analysis is as follows: The grid contours of each marked grid corresponding to each monitoring time point in the current monitoring period are extracted from the signal parameters of each marked grid in the target area corresponding to the current monitoring period, and the initial grid contours of each marked grid corresponding to each grid stored in the system storage are extracted based on each marked grid. At the same time, the grid contours of each marked grid corresponding to each monitoring time point in the current monitoring period are overlapped and compared with the initial grid contours of each marked grid, so as to obtain the overlap area of the grid contours of each marked grid corresponding to each monitoring time point in the current monitoring period. , based on the area of each marked power grid corresponding to the initial power grid contour stored in the system repository, the area of each marked power grid corresponding to the initial power grid contour is extracted , so according to the formula Calculate the grid outline overlap value of each marked grid corresponding to the current monitoring period , Δmfd is the set reference contour area difference, It is represented as the overlapping area of the grid contour of the i-th marked grid corresponding to the j-1-th monitoring time point in the current monitoring period, and β4 and β5 are respectively represented as the evaluation factors corresponding to the set overlapping area and the overlapping area change rate; Extract the grid load of each marked grid at each monitoring time point in the current monitoring period from the signal parameters of each marked grid in the target area corresponding to the current monitoring period , and extract the initial grid load corresponding to each marked grid from the initial grid load corresponding to each grid stored in the system repository based on each marked grid , according to the formula Calculate the grid load value of each marked grid corresponding to each monitoring time point in the current monitoring period , p represents a natural constant, β6 and β7 represent the influence factor of the set power grid corresponding to the maximum load and the influence factor of the power grid corresponding to the minimum load respectively; According to the formula Calculate the abnormal change evaluation value of each marked power grid in the target area corresponding to the current monitoring period , λ1 and λ2 represent the influence factors corresponding to the set grid profile coincidence value and grid load value respectively; Step 4: Analyze the grid status of each marked grid in the target area corresponding to the current monitoring period. If the grid status of a marked grid corresponding to the current monitoring period is determined to be Class A, the marked grid is recorded as a Class A abnormal grid. If the grid status of a marked grid corresponding to the current monitoring period is determined to be Class B, the marked grid is recorded as a Class B abnormal grid, and step 5 is executed at the same time. Step 5: It is used to execute processing on the marked power grids of abnormal power grids at various levels in the target area, thereby obtaining adjustment signals and call signals and executing corresponding operation processing.
2. According to the artificial intelligence-based power supply system auxiliary management method of claim 1, It is characterized in that The operating status of each power grid in the target area corresponding to the current monitoring period is analyzed. The specific analysis is as follows: By acquiring the voltage value, current value and power value in the operating status information of each power grid in the target area corresponding to the current monitoring period, the voltage value, current value and power value in the operating status information of each power grid in the target area corresponding to the current monitoring period are obtained, and the values of the three are extracted for normalization calculation processing to obtain the operating status coefficient of each power grid in the target area corresponding to the current monitoring period; Compare and analyze the operating state coefficients of each power grid in the target area corresponding to the current monitoring period with the reference comparison interval. When the operating state coefficients of each power grid in the target area corresponding to the current monitoring period are within the reference comparison interval, the operating state of each power grid in the target area corresponding to the current monitoring period is determined to be a normal state. Otherwise, the operating state of each power grid in the target area corresponding to the current monitoring period is determined to be an abnormal state. If the operating status of a power grid in the target area corresponding to the current monitoring period is normal, the power grid in the target area is recorded as a normal power grid. If the operating status of a power grid in the target area corresponding to the current monitoring period is abnormal, the power grid in the target area is recorded as a marked power grid; thus, normal power grids and marked power grids in the target area are obtained.
3. The power supply system auxiliary management method based on artificial intelligence according to claim 1, It is characterized in that The grid status of each marked grid in the target area corresponding to the current monitoring period is analyzed. The specific analysis is as follows: According to the formula Calculate the grid status assessment coefficient of each marked grid in the target area corresponding to the current monitoring period , λ3 and λ4 represent the weight factors corresponding to the set temperature evaluation value and abnormality evaluation value respectively; The grid state assessment coefficient of each marked power grid in the target area corresponding to the current monitoring period is compared with the set grid state assessment threshold. If the grid state assessment coefficient of a marked power grid corresponding to the current monitoring period is less than the set grid state assessment threshold, the grid state of the marked power grid corresponding to the current monitoring period is judged to be Class A, and the marked power grid is recorded as a Class A abnormal power grid. Otherwise, the grid state of the marked power grid corresponding to the current monitoring period is judged to be Class B, and the marked power grid is recorded as a Class B abnormal power grid.
4. The power supply system auxiliary management method based on artificial intelligence according to claim 1, It is characterized in that The marked power grids of abnormal power grids at all levels in the target area are processed, and the specific analysis is as follows: Obtain a marked power grid determined as a Class A abnormal power grid in the target area, and generate an adjustment signal. According to the generated adjustment signal, perform adjustment processing, and the specific adjustment processing is: set a preset operating state coefficient of the marked power grid determined as a Class A abnormal power grid in the target area, and at the same time retrieve a power grid state evaluation coefficient of the marked power grid determined as a Class A abnormal power grid in the target area, and match the power grid state evaluation coefficient of the marked power grid determined as a Class A abnormal power grid in the target area with a preset power grid state influencing factor to obtain a power grid state influencing factor, extract the preset operating state coefficient of the marked power grid determined as a Class A abnormal power grid in the target area and the value of the power grid state influencing factor, and multiply them to obtain a reference adjustment value of the marked power grid determined as a Class A abnormal power grid in the target area; By acquiring the actual operating state coefficient of the marked power grid determined as Class A abnormal power grid in the target area, the actual operating state coefficient of the marked power grid determined as Class A abnormal power grid in the target area is obtained, and the actual operating state coefficient of the marked power grid determined as Class A abnormal power grid in the target area is compared and analyzed with the reference adjustment value to obtain a reduced operating state coefficient or an increased operating state coefficient, then the actual operating state coefficient of the marked power grid determined as Class A abnormal power grid in the target area is reduced to be consistent with the reference adjustment value or increased to be consistent with the reference adjustment value, and a display notification is performed on the display terminal; The marked power grid determined as Class B abnormal power grid in the target area is obtained, and a call-up signal is generated. According to the generated call-up signal, the call-up processing is performed. The specific call-up processing is as follows: the distance between the marked power grid determined as Class B abnormal power grid in the target area and each on-duty management and maintenance personnel is obtained, recorded as the travel distance value, the travel distance value is compared and analyzed with the preset travel distance threshold, and the on-duty management and maintenance personnel whose travel distance value is less than the preset travel distance threshold are determined as target personnel; at the same time, the power grid state assessment coefficient of the marked power grid determined as Class B abnormal power grid in the target area is retrieved, and the power grid state assessment coefficient of the marked power grid determined as Class B abnormal power grid in the target area is compared and analyzed with the preset reference interval. When the power grid state assessment coefficient of the marked power grid determined as Class B abnormal power grid in the target area is within the reference interval, the on-duty management and maintenance personnel R1 is sent to perform the maintenance task, otherwise, the on-duty management and maintenance personnel R2 is sent to perform the maintenance task, and the execution maintenance signal is sent to the target personnel in order from small to large according to the travel distance value, and the notification is displayed on the display terminal.
Citation Information
Patent Citations
Voltage out-of-limit reason analysis method and system of power distribution network and storage medium
CN110266000A
Low-power-consumption operation system for node equipment of Internet of Things
CN116722641A