A highway construction management performance evaluation system based on smart construction sites

By introducing the performance evaluation system of smart construction sites into highway construction management, and using the entropy weight method and gray cluster analysis method, the problem of difficulty in evaluating construction management performance has been solved, and multi-faceted management performance evaluation of highway construction has been achieved, improving Improve the efficiency and level of construction management.

CN118313717BActive Publication Date: 2024-10-18CHINA RAILWAY 23RD BUREAU GRP NO 1 ENG
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410281371.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-03-12
Publication Date
2024-10-18
Estimated Expiration
2044-03-12

AI Technical Summary

Technical Problem

At present, there is a lack of effective performance evaluation system in highway construction management, which makes it difficult to improve the level of construction management. The traditional construction management model cannot meet the complex needs of the construction site.

Method used

The expressway construction management performance evaluation system based on smart construction sites establishes a performance evaluation index system and uses the entropy weight method and gray cluster analysis method to build an evaluation model, covering cost management, schedule management, quality management, safety management and personnel management, and generates Construction management performance ratings.

Benefits of technology

It achieves a comprehensive evaluation of highway construction management performance, improves the efficiency and level of construction management, helps project managers identify improvement measures, and improves the informatization level of construction management.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118313717B_ABST
    Figure CN118313717B_ABST
Patent Text Reader

Abstract

The present invention proposes a highway construction management performance evaluation system based on a smart construction site, comprising: a cost management evaluation terminal, a progress management evaluation terminal, a quality management evaluation terminal, a safety and benefit evaluation terminal, a personnel management evaluation terminal and a performance evaluation server, wherein the performance evaluation server is respectively connected to the cost management evaluation terminal, the progress management evaluation terminal, the quality management evaluation terminal, the safety and benefit evaluation terminal and the personnel management evaluation terminal data; the performance evaluation server is used to construct an evaluation model using the entropy weight method and the gray clustering analysis method, obtain the index scores uploaded by all evaluation terminals, record them in the gray clustering evaluation matrix, input the gray clustering evaluation matrix into the evaluation model, generate the index comprehensive evaluation value using the evaluation model, and determine the evaluation level. The present invention realizes the evaluation of the highway construction management performance level by establishing a highway construction management performance evaluation index system and using the evaluation model.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of construction management, and more particularly to a highway construction management performance evaluation system based on a smart construction site. Background Art

[0002] With the rapid development of highway construction, the scale and complexity of projects are increasing. Furthermore, highway construction suffers from drawbacks such as long construction routes, scattered construction sites, complex construction processes, and long construction cycles. Traditional construction management models can no longer meet the needs of construction site control.

[0003] With the coordinated development of intelligent construction and building industrialization, the smart construction site management model is gradually being applied to highway construction management to improve the shortcomings of traditional construction management models. The smart construction site is the industrial embodiment of the concept of the Smart Earth in the engineering field and is a brand-new concept for the management of the entire project life cycle. A smart construction site refers to the use of information technology to accurately design and simulate construction projects through a three-dimensional design platform. Focusing on construction process management, it establishes an information ecosystem for construction projects that is interconnected, collaborative, intelligently produced, and scientifically managed. This data is then combined with engineering information collected by the Internet of Things for data mining and analysis in a virtual reality environment. This provides process trend forecasts and expert plans, enabling visual and intelligent management of engineering construction, improving the level of information technology in engineering management, and gradually achieving green and ecological construction.

[0004] However, as a new management model, the application of smart construction site management in highway construction has not yet matured. Although relevant technical institutions have conducted research on the application of smart construction sites in highway construction management from the perspectives of technology, construction platforms, and development modules, there is relatively little research on the performance evaluation of highway smart construction site management.

[0005] It can be seen that how to effectively conduct a comprehensive evaluation of the highway construction management performance under the concept of smart construction sites, improve the level of construction management, and achieve construction goals is an urgent problem that needs to be solved at this stage. Summary of the Invention

[0006] In response to the above problems, the purpose of the present invention is to provide a highway construction management performance evaluation system based on smart construction sites. By establishing a highway construction management performance evaluation index system and using the entropy weight method and gray cluster analysis method to construct an evaluation model, the evaluation of highway construction management performance level can be realized, which can optimize the smart construction site construction management system and improve the level of highway construction management.

[0007] To achieve the above-mentioned purpose, the present invention is implemented through the following technical solutions:

[0008] The present invention discloses a highway construction management performance evaluation system based on a smart construction site, comprising: a cost management evaluation terminal, a progress management evaluation terminal, a quality management evaluation terminal, a safety and benefit evaluation terminal, a personnel management evaluation terminal, and a performance evaluation server. The performance evaluation server is respectively connected to the cost management evaluation terminal, the progress management evaluation terminal, the quality management evaluation terminal, the safety and benefit evaluation terminal, and the personnel management evaluation terminal.

[0009] a cost management evaluation terminal, configured to obtain cost information of highway construction, identify indicator information of cost management indicators based on the cost information, determine corresponding indicator scores using a first scoring model based on the indicator information, and upload the scores to a performance evaluation server;

[0010] a progress management and evaluation terminal for obtaining project progress information of the highway construction, identifying indicator information of the project progress indicators based on the project progress information, determining corresponding indicator scores using a second scoring model based on the indicator information, and uploading the scores to a performance evaluation server;

[0011] a quality management evaluation terminal for obtaining quality assessment information of highway construction, identifying indicator information of quality assessment indicators based on the quality assessment, determining corresponding indicator scores using a third scoring model based on the indicator information, and uploading the scores to a performance evaluation server;

[0012] a safety benefit evaluation terminal for obtaining safety control information of highway construction, identifying indicator information of safety control indicators based on the safety control information, determining corresponding indicator scores using a fourth scoring model based on the indicator information, and uploading the scores to a performance evaluation server;

[0013] a personnel management evaluation terminal for obtaining personnel management information for highway construction, identifying indicator information of personnel management indicators based on the personnel management information, determining corresponding indicator scores using a fifth scoring model based on the indicator information, and uploading the scores to a performance evaluation server;

[0014] The performance evaluation server is used to construct an evaluation model using the entropy weight method and the gray cluster analysis method, obtain all indicator scores, record all indicator scores into the gray cluster evaluation matrix according to different data upload terminals, input the gray cluster evaluation matrix into the evaluation model, use the evaluation model to generate a comprehensive evaluation value of the indicator, and determine the evaluation level.

[0015] Furthermore, the cost management indicators include the amount of capital investment, project profit margin and project cost control rate; the project progress indicators include the quantitative value of the rationality of the progress plan, the BIM management and control platform coordination rate and the construction period completion rate; the quality assessment indicators include the project acceptance qualification rate, the material monitoring system operation efficiency and the quality assurance measures completion rate; the safety management and control indicators include dangerous operation monitoring and early warning information, on-site safety protection management information, construction environment monitoring realization rate and safety accident occurrence rate; the personnel management and control indicators include visual monitoring management information, personnel intelligent positioning marking rate and personnel work efficiency.

[0016] Furthermore, the grey clustering evaluation matrix is ​​specifically as follows:

[0017]

[0018] Among them, i is the number of the cost management evaluation terminal, progress management evaluation terminal, quality management evaluation terminal, safety and benefit evaluation terminal and personnel management evaluation terminal, i = 1, 2, ..., 5; j is the number of indicator scores of the evaluation terminal corresponding to each number.

[0019] Furthermore, the use of the evaluation model to generate comprehensive evaluation values ​​of indicators and determine the evaluation levels includes:

[0020] Based on the grey clustering evaluation matrix, the entropy weight method is used to determine the indicator weight of each indicator score;

[0021] Based on the grey clustering evaluation matrix and the central point set of the preset construction performance evaluation grade classification mechanism, the grey whitening weight function of each indicator score is determined;

[0022] Construct grey clustering weight matrix;

[0023] Synthesize cluster evaluation matrix;

[0024] The comprehensive evaluation value of the indicator is determined based on the cluster evaluation matrix and the center point set, and the evaluation level is determined according to the preset construction performance evaluation level classification mechanism.

[0025] Furthermore, the grey clustering evaluation matrix is ​​used to determine the indicator weight of each indicator score using the entropy weight method, including:

[0026] The grey clustering evaluation matrix A is standardized to obtain the standardized matrix B = (b ij )m×n;

[0027] in, i=1,2,…,m;j=1,2,…,n;by formula Calculate the entropy value e of the j-th indicator score j ;

[0028] Among them, e j >0; k is the coefficient, By formula d j =1-e j Calculate the deviation d of the jth evaluation score j ;

[0029] By formula Calculate the jth evaluation index weight W j .

[0030] Furthermore, the preset construction performance evaluation classification mechanism includes:

[0031] The construction performance evaluation level is divided into five levels, the gray categories are set as e = {1, 2, 3, 4, 5}, and the evaluation score range of each level is determined;

[0032] Among them, the evaluation score interval of the first level is [8,10], the evaluation score interval of the second level is [6,8), the evaluation score interval of the third level is [4,6), the evaluation score interval of the fourth level is [2,4), and the evaluation score interval of the fifth level is [0,2);

[0033] According to the center point vector principle, the point with the maximum degree of each evaluation score is taken as the center point, and the center point set Q = {9, 7, 5, 3, 1} is generated.

[0034] Furthermore, the gray whitening weight function of each indicator score is determined based on the gray clustering evaluation matrix and the central point set of the preset construction performance evaluation grade classification mechanism, including:

[0035] If the indicator score a ij The evaluation level is the first level, the gray class e = 1, the gray number θ1∈[0, 9, ∞], and the gray whitening weight function of the first level is:

[0036]

[0037] If the indicator score a ij The evaluation level is the second level, the gray class e = 2, the gray number θ2∈[0, 7, 14], and the gray whitening weight function of the first level is:

[0038]

[0039] If the indicator score a ij The evaluation level is the third level, the gray class e = 3, the gray number θ3∈[0, 5, 10], and the gray whitening weight function of the third level is:

[0040]

[0041] If the indicator score a ij The evaluation level is the fourth level, the gray class e = 4, the gray number θ4∈[0, 3, 6], and the gray whitening weight function of the fourth level is:

[0042]

[0043] If the indicator score a ij The evaluation level is the fifth level, the gray class e = 5, the gray number θ5∈[0, 1, 2], and the gray whitening weight function of the fifth level is:

[0044]

[0045] Furthermore, the construction of the grey clustering weight matrix includes:

[0046] Let X ije Indicates the index score a ij The clustering coefficient of the gray class e, X ij is the total clustering coefficient, then:

[0047]

[0048]

[0049] Based on the determined gray whitening weight function, calculate the gray clustering weight vector r ije =X ije / X ij , and construct the grey clustering weight matrix corresponding to the grey clustering evaluation matrix A:

[0050]

[0051] Furthermore, the synthetic cluster evaluation matrix includes:

[0052] Assume that the primary clustering evaluation matrix is:

[0053] Z=W·R

[0054] Among them, W is based on the indicator weight W j The generated indicator weight matrix;

[0055] Assume that the comprehensive evaluation matrix of the target layer is Z0 = [Z1, Z2, ..., Zn], then the target layer evaluation vector is:

[0056] M=W0·Z0=[M1, M2,…,M n ].

[0057] Furthermore, the comprehensive evaluation value of the indicators is determined based on the cluster evaluation matrix and the center point set, and the evaluation grade is determined according to the preset construction performance evaluation grade classification mechanism, including:

[0058] Through the formula P = M·Q T Integrate the target layer evaluation vector and the center point vector to synthesize the comprehensive evaluation value P of the index;

[0059] The evaluation level is determined based on the evaluation score range of each level.

[0060] Compared with the prior art, the present invention has the following beneficial effects:

[0061] 1. Based on the principles of smart construction site management systems and highway construction management theory, this invention establishes a highway construction management performance evaluation system under the concept of smart construction sites. The evaluation system can cover five aspects: cost management, schedule management, quality management, safety management and personnel management.

[0062] 2. Considering that some evaluation indicators are difficult to quantify, the present invention introduces the grey cluster analysis method and combines it with the entropy weight method to construct a comprehensive evaluation model of highway project construction management performance under the concept of smart construction site, so as to realize the highway construction management performance evaluation.

[0063] 3. The present invention realizes the evaluation of the performance level of highway construction management under the concept of smart construction sites, which is beneficial for project managers to understand the deficiencies in the application of smart construction site management systems, timely analyze performance indicator elements, and thus clarify improvement measures and improve project construction management efficiency.

[0064] It can be seen that compared with the prior art, the present invention has outstanding substantial features and significant progress, and the beneficial effects of its implementation are also obvious. BRIEF DESCRIPTION OF THE DRAWINGS

[0065] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the following briefly introduces the drawings required for use in the embodiments or the description of the prior art. Obviously, the drawings described below are merely embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on the provided drawings without paying any creative work.

[0066] Figure 1 It is a system structure diagram of a specific implementation method of the present invention.

[0067] Figure 2 It is a schematic diagram of the highway construction management performance evaluation process according to a specific embodiment of the present invention. DETAILED DESCRIPTION

[0068] In order to enable those skilled in the art to better understand the present invention, the present invention is further described in detail below with reference to the accompanying drawings and specific embodiments. Obviously, the embodiments described are only some embodiments of the present invention, not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the present invention.

[0069] See also Figure 1 As shown, this embodiment provides a highway construction management performance evaluation system based on a smart construction site, including: a cost management evaluation terminal, a progress management evaluation terminal, a quality management evaluation terminal, a safety and benefit evaluation terminal, a personnel management evaluation terminal and a performance evaluation server. The performance evaluation server is respectively connected to the cost management evaluation terminal, the progress management evaluation terminal, the quality management evaluation terminal, the safety and benefit evaluation terminal and the personnel management evaluation terminal.

[0070] Specifically, the cost management evaluation terminal is used to obtain cost information for highway construction, identify cost management indicators based on this cost information, determine corresponding indicator scores using a first scoring model based on the indicator information, and upload the scores to the performance evaluation server. Cost management indicators include three types of information: capital investment amount, project profit margin, and project cost control rate.

[0071] The progress management and evaluation terminal is used to obtain project progress information for highway construction, identify project progress indicators based on the project progress information, determine corresponding indicator scores based on the indicator information using a second scoring model, and upload the scores to the performance evaluation server. The project progress indicators include three types of indicator information: a quantitative value for the rationality of the schedule plan, a BIM management and control platform collaboration rate, and a construction period completion rate.

[0072] The quality management and evaluation terminal is used to obtain quality assessment information for highway construction, identify quality assessment indicators based on the quality assessment, determine corresponding indicator scores based on the indicator information using a third scoring model, and upload the scores to the performance evaluation server. The quality assessment indicators include three types of information: project acceptance rate, material monitoring system operating efficiency, and quality assurance measure completion rate.

[0073] The safety benefit evaluation terminal is used to obtain safety management and control information for highway construction, identify safety management and control indicators based on this safety management and control information, determine corresponding indicator scores based on this indicator information using a fourth scoring model, and upload these scores to the performance evaluation server. Safety management and control indicators include four types of indicator information: dangerous operation monitoring and early warning information, on-site safety protection management information, construction environment monitoring implementation rate, and safety accident incidence rate.

[0074] The personnel management evaluation terminal is used to obtain personnel management information for highway construction, identify personnel management indicators based on this information, determine corresponding indicator scores using the fifth scoring model based on the indicator information, and upload the scores to the performance evaluation server. The personnel management indicators include three types of information: visual monitoring management information, personnel intelligent positioning and marking rate, and personnel work efficiency.

[0075] It should be noted that the five scoring models used in the above-mentioned terminals are all constructed using scoring model algorithms commonly used in this field. Commonly used scoring model algorithms include but are not limited to average score algorithms, weighted average algorithms, collaborative filtering algorithms, etc. The average score algorithm is a simple and common scoring algorithm that adds up all scores and then takes the average as the final score. The weighted average algorithm introduces a weight factor based on the average score algorithm and performs weighted calculations based on the importance of different scores. The collaborative filtering algorithm predicts scores based on the user's historical behavior and preferences, and recommends appropriate scores by discovering similarities between users. These scoring model algorithms can play an important role in different fields and scenarios.

[0076] The performance evaluation server is used to construct an evaluation model using the entropy weight method and the gray cluster analysis method, obtain all indicator scores, record all indicator scores into the gray cluster evaluation matrix according to different data upload terminals, input the gray cluster evaluation matrix into the evaluation model, use the evaluation model to generate a comprehensive evaluation value of the indicator, and determine the evaluation level.

[0077] In a specific implementation, the performance evaluation server is specifically used to execute a highway construction management performance evaluation process, such as Figure 2 As shown, the following steps are included:

[0078] S1: Obtain all indicator scores, and upload all indicator scores to the terminal according to different data and record them in the grey clustering evaluation matrix.

[0079] As an example, the grey clustering evaluation matrix A is as follows:

[0080]

[0081] Where i is the number of the cost management evaluation terminal, progress management evaluation terminal, quality management evaluation terminal, safety benefit evaluation terminal and personnel management evaluation terminal, i = 1, 2, ..., 5; j is the number of indicator scores of the evaluation terminal corresponding to each number. Specifically, in the above grey clustering evaluation matrix A, a 11 is the index score of the amount of capital investment, a 12 is the index score of the project profit rate, a 13 is the index score of the project cost control rate; a21 The index score for the quantitative value of the schedule rationality, a 22 is the index score of the BIM management and control platform collaboration rate, a 23 is the index score of the construction period completion rate; a 31 is the index score of the project acceptance rate, a 32 is the index score of the material monitoring system operation efficiency, a 33 is the indicator score of the completion rate of quality assurance measures; 41 is the index score of dangerous operation monitoring and early warning information, a 42 The index score of on-site safety protection management information, a 43 is the index score of construction environment monitoring realization rate, a 44 is the index score of safety accident rate; a 51 For the indicator score of visual monitoring management information, a 52 The indicator score for the personnel intelligent positioning marking rate, a 53 It is the indicator score of personnel work efficiency.

[0082] S2: Based on the grey clustering evaluation matrix, the entropy weight method is used to determine the indicator weight of each indicator score.

[0083] As an example, firstly, the grey clustering evaluation matrix A is normalized to obtain the normalized matrix B = (b ij )m×n.

[0084] in,

[0085] Then, by the formula Calculate the entropy value e of the j-th indicator score j ; Among them, e j >0; k is the coefficient,

[0086] At this time, through the formula d j =1-e j Calculate the deviation d of the jth evaluation score j .

[0087] Finally, through the formula Calculate the jth evaluation index weight W j .

[0088] S3: Based on the grey clustering evaluation matrix and the central point set of the preset construction performance evaluation grade classification mechanism, the grey whitening weight function of each indicator score is determined.

[0089] As an example, the construction performance evaluation level is divided into five levels: "excellent", "good", "qualified", "poor", and "very poor", and the gray categories are set to e = {1, 2, 3, 4, 5}, and the evaluation score range for each level is determined.

[0090] Specifically, the evaluation score interval for excellent grade is [8, 10), the evaluation score interval for good grade is [6, 8), the evaluation score interval for qualified grade is [4, 6), the evaluation score interval for poor grade is [2, 4), and the evaluation score interval for extremely poor grade is [0, 2].

[0091] According to the central point vector principle and the actual situation of the project, the point with the maximum degree of each evaluation score is taken as the central point to generate the central point set Q = {9, 7, 5, 3, 1}.

[0092] Based on the above-mentioned grade score interval and center point combination, five different gray whitening weight functions are determined as follows:

[0093] When the index score a ij When the evaluation level is excellent, the gray class e = 1, the gray number θ1∈[0, 9, ∞], and the gray whitening weight function of the excellent level are:

[0094]

[0095] When the index score a ij When the evaluation level is good, the gray class e = 2, the gray number θ2∈[0, 7, 14], and the gray whitening weight function of the good level are:

[0096]

[0097] When the index score a ij When the evaluation level is qualified, the gray class e = 3, the gray number θ3∈[0, 5, 10], and the gray whitening weight function of the qualified level are:

[0098]

[0099] When the index score a ij When the evaluation level is poor, the gray class e = 4, the gray number θ4∈[0, 3, 6], and the gray whitening weight function of the poor level is:

[0100]

[0101] When the index score a ij The evaluation level is the extreme level, the gray class e = 5, the gray number θ5∈[0, 1, 2], and the gray whitening weight function of the extreme level is:

[0102]

[0103] S4: Construct the grey clustering weight matrix.

[0104] As an example, let X ije Indicates the index score a ij The clustering coefficient of the gray class e, X ij is the total clustering coefficient, then:

[0105]

[0106]

[0107] Based on the determined gray whitening weight function, calculate the gray clustering weight vector r ije =X ije / X ij , and construct the grey clustering weight matrix corresponding to the grey clustering evaluation matrix A:

[0108]

[0109] S5: Synthetic cluster evaluation matrix.

[0110] As an example, let the primary clustering evaluation matrix be:

[0111] Z = W·R;

[0112] Among them, W is based on the indicator weight W j The generated indicator weight matrix.

[0113] Assume that the comprehensive evaluation matrix of the target layer is Z0 = [Z1, Z2, ..., Zn], then the target layer evaluation vector is: M = W0·Z0 = [M1, M2, ..., M n ].

[0114] S6: Determine the comprehensive evaluation value of the indicator based on the cluster evaluation matrix and the center point set, and determine the evaluation level according to the preset construction performance evaluation level classification mechanism.

[0115] As an example, first, by the formula P = M·Q T The target layer evaluation vector and the center point vector are integrated to synthesize the comprehensive evaluation value P of the index; then, the evaluation level is determined according to the evaluation score interval of each level.

[0116] For example, the comprehensive evaluation value of the highway project's construction management performance was 7.085, which falls within the good-grade evaluation score range of [6, 8]. Therefore, the highway project's construction management performance rating was "good." Field research indicates that this evaluation result is generally consistent with the actual construction site conditions. After the project department implemented "smart construction site" integrated management technology in construction management, the project's standardized management level and management efficiency were significantly improved. By optimizing the management team, fully monitoring materials, real-time tracking of equipment and personnel, and comprehensively controlling the site, the deep integration of information technology and project management has yielded significant social and economic benefits.

[0117] By analyzing the evaluation results, if the project wants to further improve construction management efficiency and enhance the quality, safety and economic benefits of the project: first, it should pay more attention to evaluation indicators with greater weights, such as project cost control rate, schedule rationality, project acceptance rate, safety accident rate and personnel work efficiency, and improve them in combination with the existing conditions of the project; second, increase investment in smart construction site management, continuously improve the integration of construction management information and lightweight work; finally, strengthen the maintenance of the smart construction site system, further improve operational efficiency and reduce the safety accident rate.

[0118] It can be seen that the present invention provides a highway construction management performance evaluation system based on smart construction sites. By establishing a highway construction management performance evaluation index system and using the entropy weight method and gray cluster analysis method to construct an evaluation model, the evaluation of highway construction management performance level can be realized. It can optimize the smart construction site construction management system and improve the level of highway construction management.

[0119] The various embodiments in this specification are described in a progressive manner, with each embodiment focusing on its differences from the other embodiments. References to the same or similar parts between the various embodiments are sufficient. The methods disclosed in the embodiments are described briefly because they correspond to the systems disclosed in the embodiments. For relevant details, refer to the method description.

[0120] The steps of the methods or algorithms described in conjunction with the embodiments disclosed herein may be implemented directly using hardware, a software module executed by a processor, or a combination of the two. The software module may be placed in a random access memory (RAM), internal memory, read-only memory (ROM), electrically programmable ROM, electrically erasable programmable ROM, registers, a hard disk, a removable disk, a CD-ROM, or any other form of storage medium known in the art.

[0121] Finally, it should be noted that, in this document, relational terms such as first and second, etc., are used only to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any actual relationship or order between these entities or operations. Moreover, the terms "comprises," "comprising," or any other variations thereof are intended to cover non-exclusive inclusion, such that a process, method, article, or device comprising a series of elements includes not only those elements, but also other elements not explicitly listed, or elements inherent to such process, method, article, or device. In the absence of further limitations, an element defined by the phrase "comprising a ..." does not exclude the presence of additional identical elements in the process, method, article, or device comprising the element.

[0122] The above is a detailed introduction to the highway construction management performance evaluation system based on smart construction sites provided by the present invention. This article uses specific examples to illustrate the principles and implementation methods of the present invention. The description of the above embodiments is only used to help understand the method of the present invention and its core ideas. It should be pointed out that for ordinary technicians in this technical field, without departing from the principles of the present invention, the present invention can also be improved and modified in several ways, and these improvements and modifications also fall within the scope of protection of the claims of the present invention.

Claims

1. A highway construction management performance evaluation system based on smart construction sites, characterized in that: include: A cost management evaluation terminal, a progress management evaluation terminal, a quality management evaluation terminal, a safety and benefit evaluation terminal, a personnel management evaluation terminal and a performance evaluation server, wherein the performance evaluation server is respectively connected with data of the cost management evaluation terminal, the progress management evaluation terminal, the quality management evaluation terminal, the safety and benefit evaluation terminal and the personnel management evaluation terminal; A cost management evaluation terminal is used to obtain cost information of highway construction, identify indicator information of cost management indicators based on the cost information, determine corresponding indicator scores using a first scoring model according to the indicator information, and upload the scores to a performance evaluation server; A progress management and evaluation terminal is used to obtain project progress information of expressway construction, identify indicator information of project progress indicators based on the project progress information, determine corresponding indicator scores using a second scoring model according to the indicator information, and upload the scores to a performance evaluation server; A quality management evaluation terminal is used to obtain quality evaluation information of highway construction, identify indicator information of quality evaluation indicators based on the quality evaluation, determine corresponding indicator scores using a third scoring model according to the indicator information, and upload the scores to a performance evaluation server; A safety benefit evaluation terminal is used to obtain safety control information of highway construction, identify indicator information of safety control indicators based on the safety control information, determine corresponding indicator scores using a fourth scoring model according to the indicator information, and upload the scores to a performance evaluation server; A personnel management evaluation terminal is used to obtain personnel control information of highway construction, identify indicator information of personnel control indicators based on the personnel control information, determine corresponding indicator scores using a fifth scoring model according to the indicator information, and upload the scores to a performance evaluation server; The performance evaluation server is used to construct an evaluation model using the entropy weight method and the gray cluster analysis method, obtain all indicator scores, record all indicator scores into a gray cluster evaluation matrix according to different data upload terminals, input the gray cluster evaluation matrix into the evaluation model, generate a comprehensive evaluation value of the indicator using the evaluation model, and determine the evaluation level; The cost management indicators include the amount of capital investment, project profit rate and project cost control rate; the project progress indicators include the quantitative value of the rationality of the progress plan, the coordination rate of the BIM management and control platform and the completion rate of the construction period; the quality assessment indicators include the project acceptance qualification rate, the operating efficiency of the material monitoring system and the completion rate of quality assurance measures; the safety management and control indicators include dangerous operation monitoring and early warning information, on-site safety protection management information, construction environment monitoring realization rate and safety accident occurrence rate; the personnel management and control indicators include visual monitoring management information, personnel intelligent positioning marking rate and personnel work efficiency; The grey clustering evaluation matrix is ​​as follows: ; Where i is the number of the cost management evaluation terminal, schedule management evaluation terminal, quality management evaluation terminal, safety benefit evaluation terminal and personnel management evaluation terminal, i=1,2,…,5; j is the number of indicator scores of the evaluation terminal corresponding to each number; The method of using the evaluation model to generate a comprehensive evaluation value of the indicator and determine the evaluation level includes: Based on the grey clustering evaluation matrix, the entropy weight method is used to determine the indicator weight of each indicator score; Based on the grey clustering evaluation matrix and the central point set of the preset construction performance evaluation grade classification mechanism, the grey whitening weight function of each indicator score is determined; Construct grey clustering weight matrix; Synthesize cluster evaluation matrix; Determine the comprehensive evaluation value of the indicator based on the cluster evaluation matrix and the center point set, and determine the evaluation level according to the preset construction performance evaluation level classification mechanism; The method of determining the indicator weight of each indicator score based on the grey clustering evaluation matrix by using the entropy weight method includes: Grey clustering evaluation matrix After standardization, we get the standardized matrix B=(b ij )m×n; in, , i=1,2,…,m; j=1,2,…,n; By formula Calculate the entropy value e of the jth indicator score j ; Among them, e j >0; ; k is the coefficient, ; By formula Calculate the deviation d of the jth evaluation score j ; By formula Calculate the jth evaluation index weight W j ; The preset construction performance evaluation classification mechanism includes: The construction performance evaluation level is divided into five levels, the gray category is set as e={1,2,3,4,5}, and the evaluation score range of each level is determined; Among them, the evaluation score interval of the first level is [8,10], the evaluation score interval of the second level is [6,8), the evaluation score interval of the third level is [4,6), the evaluation score interval of the fourth level is [2,4), and the evaluation score interval of the fifth level is [0,2); According to the central point vector principle, the point with the maximum degree of each evaluation score is taken as the central point, and the central point set Q={9, 7, 5, 3, 1} is generated; The gray whitening weight function for each indicator score is determined based on the gray clustering evaluation matrix and the central point set of the preset construction performance evaluation grade classification mechanism, including: If the index score The evaluation level is the first level, gray class e=1, gray number ∈[0,9,∞], the gray whitening weight function of the first level is: ; If the index score The evaluation level is the second level, gray class e=2, gray number ∈[0,7,14], the gray whitening weight function of the first level is: ; If the index score The evaluation level is the third level, gray class e=3, gray number ∈[0,5,10], the third level gray whitening weight function is: ; If the index score The evaluation level is the fourth level, gray class e=4, gray number ∈[0,3,6], the gray whitening weight function of the fourth level is: ; If the index score The evaluation level is the fifth level, gray class e=5, gray number ∈[0,1,2], the fifth level gray whitening weight function is: ; The construction of the grey clustering weight matrix includes: set up Indicates the index score The clustering coefficient belonging to the gray class e, is the total clustering coefficient, then: ; ; Based on the determined gray whitening weight function, calculate the gray clustering weight vector r ije =X ije / X ij , and construct the grey clustering evaluation matrix The corresponding grey clustering weight matrix: ; The synthetic clustering evaluation matrix includes: Assume the primary clustering evaluation matrix is: ; in, Based on the indicator weight W j The generated indicator weight matrix; Assume that the comprehensive evaluation matrix of the target layer is Z0=[Z1,Z2,…,Zn], then the target layer evaluation vector is: 。 2. According to the highway construction management performance evaluation system based on smart construction sites according to claim 1, it is characterized in that: The comprehensive evaluation value of the indicator is determined based on the cluster evaluation matrix and the center point set, and the evaluation grade is determined according to the preset construction performance evaluation grade classification mechanism, including: By formula Integrate the target layer evaluation vector with the center point vector to synthesize the comprehensive evaluation value of the index ; The evaluation level is determined based on the evaluation score range of each level.

Citation Information

Patent Citations

  • Quality-effect evaluation method for electric power supply station

    CN113689134A

  • Distribution network operation planning comprehensive evaluation and investment benefit analysis method

    CN114154776A