Clean room construction optimization method based on WBS technology
By calculating and correcting the time difference and distance measurements between data points in the construction of a clean room, combining the similarity and reliability of multi-dimensional monitoring data, local reachable density analysis is carried out, and construction abnormal detection in the existing technology is solved. Accurate problems improve construction efficiency and project management effectiveness.
Patent Information
- Application Number
- CN202410831081.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-26
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2044-06-26
AI Technical Summary
The prior art cannot accurately detect construction abnormalities during the construction of clean rooms, resulting in untimely adjustments in construction, which in turn affects construction efficiency and progress.
By obtaining the construction process data of the clean room, calculating the time difference and distance measurements between sample data points, and making corrections, combining the similarity and reliability of multi-dimensional monitoring data, local reachable density analysis is carried out, abnormal detection and construction are carried out, and Planning adjustment.
It improves the accuracy of abnormal detection of construction sample data points, enhances project management and construction efficiency, and avoids abnormal detection errors caused by environmental factors.
Smart Images

Figure CN118396782B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of data processing, and in particular to a clean room construction optimization method based on WBS technology. Background Art
[0002] In the actual clean room construction process, sufficient design and planning stages can effectively reduce changes and adjustments in the construction process, thereby shortening the construction time. If the design and planning are inadequate, it may lead to construction delays; WBS technology can help the project team decompose the entire construction project into manageable work packages and tasks, so as to better plan the project schedule, resources and costs. Through clear work decomposition, project managers can better control the execution progress of the project, thereby improving the work efficiency of the project team; the existing local reachable density input LOF anomaly detection algorithm directly uses the distance between data points, resulting in inappropriate distance measurement. It does not take into account the actual construction process due to resource limitations, external factors and the impact of actual construction conditions, resulting in inaccurate construction anomaly detection and inability to accurately adjust the construction according to the abnormal results. Summary of the invention
[0003] In order to solve the above problems, the present invention provides a clean room construction optimization method based on WBS technology, the method comprising:
[0004] Obtain several clean room construction process data sets during the project construction process;
[0005] According to the clean room construction process data set, a number of clean room construction sample data points are obtained; according to the difference between the predicted construction time and the initial construction time between any two clean room construction sample data points, the time difference between any two clean room construction sample data points at any two time points is obtained; according to the time difference and the difference of the monitoring data of multiple dimensions at any two time points, the distance measurement between any two clean room construction sample data points at any two time points is obtained; according to the distance measurement and the similarity of the monitoring data of multiple dimensions at any two clean room construction sample data points at any two time points, the corrected distance measurement between any two clean room construction sample data points at any two time points is obtained;
[0006] According to the difference in the dimensional monitoring data between each clean room construction sample data point and other clean room construction sample data points at each time point, the reliability of each clean room construction sample data point at each time point is obtained; according to the reliability of the clean room construction sample data point at each time point and the corrected distance metric, the local reachability density of each clean room construction sample data point is obtained;
[0007] According to the local reachable density, the clean room construction sample data points are detected for anomalies to obtain abnormal results; the construction plan of WBS is adjusted according to the abnormal results.
[0008] Preferably, the method of obtaining a plurality of clean room construction sample data points according to the clean room construction process data set includes:
[0009] Each clean room construction process data set includes several construction stage data sets; each construction stage data set includes several days of dimensional construction data sequences; each day's dimensional construction data sequence includes several monitoring data of different dimensions; a three-dimensional space is constructed with the serial number of the clean room construction process data set, the serial number of the construction stage data set and the time point of the dimensional construction data sequence, and all clean room construction process data sets during the project construction process are input into the three-dimensional space to obtain several clean room construction sample data points.
[0010] Preferably, the method of obtaining the time difference between any two clean room construction sample data points at any two time points according to the difference between the predicted construction time and the initial construction time between any two clean room construction sample data points includes the following specific methods:
[0011] The first The first of the clean room construction sample data points The time point and The difference between the initial construction time of the clean room construction sample data points is recorded as the first difference; the first difference is added to the The ratio of the predicted construction time of the clean room construction sample data points is recorded as the first ratio; The first of the clean room construction sample data points The time point and The difference between the initial construction time of the clean room construction sample data points is recorded as the second difference; the first difference is recorded as the The ratio of the predicted construction time of the clean room construction sample data points is recorded as the second ratio; the absolute value of the difference between the first ratio and the second ratio is recorded as the first Clean room construction sample data points and The clean room construction sample data point is in time point and The time difference at each time point.
[0012] Preferably, the specific formula for obtaining the distance measurement between any two clean room construction sample data points at any two time points according to the time difference and the difference in monitoring data of multiple dimensions between any two clean room construction sample data points at any two time points is:
[0013]
[0014] In the formula, Indicates Clean room construction sample data points and The clean room construction sample data point is in time point and Distance measurement at each time point; Indicates Clean room construction sample data points and The clean room construction sample data point is in time point and Time differences at different time points; Represents the total number of all dimensions of clean room construction sample data points; Indicates The clean room construction sample data point is in At the time point Monitoring data of various dimensions; Indicates The clean room construction sample data point is in At the time point Monitoring data of various dimensions; Indicates taking the absolute value.
[0015] Preferably, the method of obtaining the corrected distance metric of any two clean room construction sample data points at any two time points according to the distance metric and the similarity of the monitoring data of multiple dimensions of any two clean room construction sample data points at any two time points includes the following specific methods:
[0016] Get the The clean room construction sample data point is in At the next time point Dimensions and The correlation of the dimensions and The clean room construction sample data point is in Time point Dimensions and The correlation of the dimensions;
[0017] According to the correlation, get the Clean room construction sample data points and The clean room construction sample data point is in time point and At the next time point Dimensions and The relative differences in the dimensions;
[0018] Get the Clean room construction sample data points and The clean room construction sample data point is in time point and The calculation method of the modified distance metric at each time point is:
[0019]
[0020] In the formula, Indicates Clean room construction sample data points and The clean room construction sample data point is in time point and The modified distance metric at each time point; Indicates Clean room construction sample data points and The clean room construction sample data point is in time point and Distance measurement at each time point; Represents the total number of all dimensions of clean room construction sample data points; Indicates Clean room construction sample data points and The clean room construction sample data point is in time point and At the next time point Dimensions and The relative differences in the dimensions; Represents an exponential function with a natural constant as base.
[0021] Preferably, the obtaining The clean room construction sample data point is in At the next time point Dimensions and The correlation of the dimensions and The clean room construction sample data point is in Time point Dimensions and The specific methods include:
[0022] The first The clean room construction sample data point is in At the time point The monitoring data series of the first dimension and the The clean room construction sample data point is in At the time point The Pearson correlation coefficient between the monitoring data series of the dimensions is used as the The clean room construction sample data point is in At the next time point Dimensions and The correlation of dimensions.
[0023] Preferably, according to the correlation, obtaining the Clean room construction sample data points and The clean room construction sample data point is in time point and At the next time point Dimensions and The relevant differences in the dimensions include:
[0024] The first The clean room construction sample data point is in At the next time point Dimensions and The correlation between the first dimension and The clean room construction sample data point is in Time point Dimensions and The absolute value of the difference in the correlation of the dimensions is taken as the Clean room construction sample data points and The clean room construction sample data point is in time point and At the next time point Dimensions and The relative differences in the dimensions.
[0025] Preferably, the specific formula for obtaining the reliability of each clean room construction sample data point at each time point according to the difference in the monitoring data of the dimension between each clean room construction sample data point and other clean room construction sample data points at each time point is:
[0026]
[0027] In the formula, Indicates The clean room construction sample data point is in reliability at each time point; Represents the total number of all dimensions of clean room construction sample data points; In the The total number of all clean room construction sample data points at a time point; Indicates At the next time point The first of the clean room construction sample data points Monitoring data of various dimensions; Indicates The first of all clean room construction sample data points at a time point The mean of the monitoring data in each dimension; Represents an exponential function with a natural constant as base.
[0028] Preferably, the local reachable density of each clean room construction sample data point is obtained according to the reliability of the clean room construction sample data point at each time point and the modified distance metric, including the specific method of:
[0029] Any clean room construction sample data point is recorded as the target clean room construction sample data point; the calculation method for obtaining the local reachable density of the target clean room construction sample data point is:
[0030]
[0031] In the formula, Represents the local reachability density of the target clean room construction sample data points; Represents the total number of all time points of the target clean room construction sample data points; Represents the total number of all clean room construction sample data points; Indicates that the target clean room construction sample data point is in reliability at each time point; Represents the target clean room construction sample data point and the The clean room construction sample data point is in time point and The modified distance metric at each time point.
[0032] Preferably, the method of performing anomaly detection on the clean room construction sample data points according to the local reachable density to obtain anomaly results includes the following specific methods:
[0033] The local reachable density of each clean room construction sample data point is input into the LOF anomaly detection algorithm to obtain the degree of anomaly of each clean room construction sample data point; for any clean room construction sample data point, if the degree of anomaly of the clean room construction sample data point is greater than or equal to the threshold parameter , record the time point corresponding to the clean room construction sample data point as an abnormal time point; and group all abnormal time points into an abnormal time point sequence as an abnormal result.
[0034] The beneficial effects of the technical solution of the present invention are as follows: the present invention utilizes time points and monitoring data in the same construction stage during different clean room construction processes to quantify the distance measurement between each clean room construction sample data point, thereby avoiding the situation where the distances between data points of different work types are relatively close; by analyzing the size of the correlation between data of multiple dimensions, the distance is further corrected, so that the obtained distance measurement can avoid the situation where the corresponding monitoring data size of some clean room construction sample data points is similar to the monitoring data of other clean room construction sample data points due to environmental factors, resulting in reduced accuracy of anomaly detection; combined with the difference in monitoring data corresponding to multiple stages at the same time point, the local reachable density of each clean room construction sample data point is further adjusted, so that each clean room construction sample data point is compared with clean room construction sample data points with higher reliability and closer distance, thereby improving the accuracy of the degree of anomaly of the clean room construction sample data point, thereby effectively improving project management and construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0035] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0036] Figure 1 It is a flow chart of the steps of the clean room construction optimization method based on WBS technology of the present invention;
[0037] Figure 2 It is a characteristic relationship flow chart of the clean room construction optimization method based on WBS technology of the present invention. DETAILED DESCRIPTION
[0038] In order to further explain the technical means and effects adopted by the present invention to achieve the predetermined invention purpose, the following is a detailed description of the clean room construction optimization method based on WBS technology proposed by the present invention, its specific implementation method, structure, features and effects, in combination with the accompanying drawings and preferred embodiments. In the following description, different "one embodiment" or "another embodiment" does not necessarily refer to the same embodiment. In addition, specific features, structures or characteristics in one or more embodiments may be combined in any suitable form.
[0039] Unless defined otherwise, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this invention belongs.
[0040] The specific scheme of the clean room construction optimization method based on WBS technology provided by the present invention is described in detail below with reference to the accompanying drawings.
[0041] See also Figure 1 , which shows a flow chart of the steps of a clean room construction optimization method based on WBS technology provided by an embodiment of the present invention, the method comprising the following steps:
[0042] Step S001: Acquire a number of clean room construction process data sets during the project construction process.
[0043] It should be noted that during the clean room construction process, the daily usage of various materials and energy is obtained separately. Through anomaly detection, the multi-dimensional data of the clean room in the current construction process is detected, so that the subsequent WBS construction plan can be adjusted in time for abnormal situations, thereby improving the work efficiency of the project team.
[0044] Specifically, we first need to collect several clean room construction process data sets during the project construction process. The specific process is as follows:
[0045] By counting the material consumption, construction time, energy consumption, and waste emissions of each clean room in the project management stage, clean room design stage, clean room construction preparation stage, construction stage, clean room acceptance and delivery stage during the project construction process, the actual construction time of each clean room in each construction stage during the project construction process is obtained; the data sequence composed of ten different dimensions of monitoring data, including the daily steel bar consumption, concrete consumption, brick and tile consumption, paint consumption, sealant consumption, sealing strip consumption, electricity consumption, water consumption, waste generation, and carbon dioxide emissions of each clean room in each construction stage, is used as the daily dimensional construction data sequence; the set composed of the dimensional construction data sequences of all days in each construction stage is used as the data set of each construction stage; the set composed of the data sets of all construction stage in each clean room is used as the construction process data set of each clean room.
[0046] Among them, each clean room construction process data set includes several construction stage data sets; each construction stage data set includes several days of dimensional construction data sequences; each day's dimensional construction data sequence includes several monitoring data of different dimensions.
[0047] So far, several clean room construction process data sets during the project construction process have been obtained through the above method.
[0048] Step S002: obtain a number of clean room construction sample data points; obtain the time difference between any two clean room construction sample data points at any two time points; obtain the distance measurement between any two clean room construction sample data points at any two time points; obtain the corrected distance measurement between any two clean room construction sample data points at any two time points.
[0049] It should be noted that the traditional LOF anomaly detection is measured based on the relative local density of each data point. In the clean room construction process, since the data changes in different construction stages are closely related to the construction content, it is considered to use the monitoring data of different dimensions in different clean rooms in different construction stages on different days as sample points in LOF anomaly detection. Therefore, it is necessary to measure the distance between any two sample points. Considering the construction process of different clean rooms, due to the difference in clean room scale, the construction time of the same construction stage will also be different. Therefore, the distance is initially corrected using the ratio of the length of time from the construction stage to the present. Then, considering the influence of some abnormal external environments, the correlation between multiple dimensional data produces a large error, and the distance between sample points with large differences in the correlation of each dimensional data is further corrected. Then, considering the data changes of each point and the data changes of the construction stage in the same time, whether the total workload or material consumption is at a similar level, it can avoid the influence of personnel transfer on anomaly detection due to the construction differences of different clean rooms, that is, misjudging normal data points as abnormal data, and then obtain the final anomaly detection results to adjust the WBS work structure.
[0050] Specifically, for any clean room construction process data set, the predicted construction duration of each construction phase data set in the clean room construction process data set is obtained through WBS work structure decomposition.
[0051] A three-dimensional space is constructed with the serial number of the clean room construction process data set, the serial number of the construction stage data set and the time points of the dimensional construction data sequence. All clean room construction process data sets during the project construction process are input into the three-dimensional space to obtain several clean room construction sample data points; among them, each clean room construction sample data point corresponds to a predicted construction duration, initial construction time, multiple time points and multiple dimensional monitoring data.
[0052] At this point, several sample data points are obtained.
[0053] It should be noted that the construction data of different clean rooms on different days cannot be directly compared, the specific construction tasks corresponding to each day are different, and due to the different construction areas, the daily data changes are different. For example, the daily concrete consumption corresponding to the foundation and the wall will be different, and the two cannot be directly compared. Therefore, the Euclidean distance between traditional data points cannot be a good constant for daily data anomalies; consider using the proportion of the construction time of the remaining clean rooms in the same stage to the entire construction time, further amplifying the distance between data points in different periods, and thus obtaining a more accurate distance measurement.
[0054] 1. Obtain the time difference between any two clean room construction sample data points at any two time points.
[0055] Specifically, according to the difference between the predicted construction time and the initial construction time between any two clean room construction sample data points, the time difference between any two clean room construction sample data points at any two time points is obtained.
[0056] For Clean room construction sample data points and clean room construction sample data points, as an example, obtain the Clean room construction sample data points and The clean room construction sample data point is in time point and The calculation method of the time difference at each time point is:
[0057]
[0058] In the formula, Indicates Clean room construction sample data points and The clean room construction sample data point is in time point and Time differences at different time points; Indicates The first of the clean room construction sample data points time point; Indicates The initial construction time of each clean room construction sample data point; Indicates The predicted construction time of clean room construction sample data points; Indicates The first of the clean room construction sample data points time point; Indicates The initial construction time of each clean room construction sample data point; Indicates The predicted construction time of clean room construction sample data points; Indicates taking the absolute value.
[0059] At this point, the time difference between any two clean room construction sample data points at any two time points is obtained.
[0060] 2. Obtain the distance measurement between any two clean room construction sample data points at any two time points.
[0061] Specifically, according to the time difference and the difference of monitoring data of multiple dimensions of any two clean room construction sample data points at any two time points, the distance measurement between any two clean room construction sample data points at any two time points is obtained.
[0062] For Clean room construction sample data points and clean room construction sample data points, as an example, obtain the Clean room construction sample data points and The clean room construction sample data point is in time point and The calculation method of the distance metric at each time point is:
[0063]
[0064] In the formula, Indicates Clean room construction sample data points and The clean room construction sample data point is in time point and Distance measurement at each time point; Indicates Clean room construction sample data points and The clean room construction sample data point is in time point and Time differences at different time points; Represents the total number of all dimensions of clean room construction sample data points; Indicates The clean room construction sample data point is in At the time point Monitoring data of various dimensions; Indicates The clean room construction sample data point is in At the time point Monitoring data of various dimensions; Indicates taking the absolute value.
[0065] At this point, the distance measurement between any two clean room construction sample data points at any two time points is obtained.
[0066] 3. Obtain the corrected distance measurement between any two clean room construction sample data points at any two time points.
[0067] It should be noted that since the above distance measurement still considers the size of monitoring data between two clean room construction sample data points; and for data of different construction scales, the distance between normal construction data in the same construction stage will be larger, and there will be a situation where the distance between some abnormal data points and normal data points is smaller; for example, in the process of large-scale approach room construction, the current material and energy consumption data may become smaller due to weather reasons, but this will reduce the distance between the smaller-scale clean room construction data, and cannot better reflect the abnormal situation of the data, so it is necessary to consider the correlation of data changes in multiple dimensions and further revise the above distance measurement.
[0068] Specifically, for Clean room construction sample data points and clean room construction sample data points, The clean room construction sample data points are from the first time point to the All the The monitoring data of dimensions form a data sequence, recorded as The clean room construction sample data point is in At the time point The monitoring data series of the dimensions; The clean room construction sample data points are from the first time point to the All the The monitoring data of dimensions form a data sequence, recorded as The clean room construction sample data point is in At the time point Monitoring data series of dimensions;
[0069] The first The clean room construction sample data points are from the first time point to the All the The monitoring data of dimensions form a data sequence, recorded as The clean room construction sample data point is in The time point The monitoring data series of the dimensions; The clean room construction sample data points are from the first time point to the All the The monitoring data of dimensions form a data sequence, recorded as The clean room construction sample data point is in At the time point A monitoring data series of multiple dimensions.
[0070] The first The clean room construction sample data point is in At the time point The monitoring data series of the first dimension and the The clean room construction sample data point is in At the time point The Pearson correlation coefficient between the monitoring data series of the dimensions is used as the The clean room construction sample data point is in At the next time point Dimensions and The correlation of the dimensions;
[0071] The first The clean room construction sample data point is in The time point The monitoring data series of the first dimension and the The clean room construction sample data point is in At the time point The Pearson correlation coefficient between the monitoring data series of the dimensions is used as the The clean room construction sample data point is in Time point Dimensions and The correlation of dimensions.
[0072] The first The clean room construction sample data point is in At the next time point Dimensions and The correlation between the first dimension and The clean room construction sample data point is in Time point Dimensions and The absolute value of the difference in the correlation of the dimensions is taken as the Clean room construction sample data points and The clean room construction sample data point is in time point and At the next time point Dimensions and The relative differences in the dimensions.
[0073] Furthermore, according to the distance metric and the similarity of the monitoring data of multiple dimensions of any two clean room construction sample data points at any two time points, the corrected distance metric of any two clean room construction sample data points at any two time points is obtained.
[0074] As an example, get the Clean room construction sample data points and The clean room construction sample data point is in time point and The calculation method of the modified distance metric at each time point is:
[0075]
[0076] In the formula, Indicates Clean room construction sample data points and The clean room construction sample data point is in time point and The modified distance metric at each time point; Indicates Clean room construction sample data points and The clean room construction sample data point is in time point and Distance measurement at each time point; Represents the total number of all dimensions of clean room construction sample data points; Indicates Clean room construction sample data points and The clean room construction sample data point is in time point and At the next time point Dimensions and The relative differences in the dimensions; represents an exponential function with a natural constant as the base, and the embodiment adopts The model shows an inverse proportional relationship. As the input of the model, implementers can choose the inverse proportional function according to actual conditions.
[0077] So far, the modified distance measurement of any two clean room construction sample data points at any two time points is obtained through the above method.
[0078] Step S003: Obtain the reliability of each clean room construction sample data point at each time point; obtain the local reachability density of each clean room construction sample data point according to the reliability of the clean room construction sample data point at each time point and the modified distance metric.
[0079] It should be noted that, considering the construction process of clean rooms of different scales, there will be some time overlap between different construction stages. For example, during the civil construction, the installation of some electromechanical equipment can be started, such as installing pipes for air-conditioning systems or brackets for purification equipment. The time overlap between the civil construction stage and the electromechanical equipment installation stage will lead to personnel scheduling in different construction stages. However, in the traditional LOF anomaly detection algorithm, only the density relationship between multiple adjacent points is considered, without considering whether the data changes of each adjacent point are due to normal changes in construction progress such as personnel scheduling, or caused by other abnormal factors such as the environment, so that the local reachable density of each point has a certain error. Therefore, it is considered to use the data changes corresponding to the construction stages with time overlap to improve the local reachable density of each clean room construction sample data point.
[0080] 1. Obtain the reliability of each clean room construction sample data point at each time point.
[0081] Specifically, the reliability of each clean room construction sample data point at each time point is obtained according to the difference in the monitoring data of the dimension between each clean room construction sample data point and other clean room construction sample data points at each time point.
[0082] As an example, get the The clean room construction sample data point is in The reliability of each time point is calculated as:
[0083]
[0084] In the formula, Indicates The clean room construction sample data point is in reliability at each time point; Represents the total number of all dimensions of clean room construction sample data points; In the The total number of all clean room construction sample data points at a time point; Indicates At the next time point The first of the clean room construction sample data points Monitoring data of various dimensions; Indicates The first of all clean room construction sample data points at a time point The mean of the monitoring data in each dimension; represents an exponential function with a natural constant as the base, and the embodiment adopts Model to present inverse proportional relationship and normalization, As the input of the model, the implementer can choose the inverse proportional function and the normalization function according to the actual situation.
[0085] At this point, the reliability of each clean room construction sample data point at each time point is obtained.
[0086] 2. Obtain the local reachability density of each clean room construction sample data point.
[0087] It should be noted that when multiple stages of construction are carried out on the same day, whether the total working hours of all workers increase or decrease compared with the previous time, by summing the data under multiple construction stages, it can be determined whether the change in data is due to factors such as personnel transfers, and then the reliability of the clean room construction sample data points at each time point can be obtained; for clean room construction sample data points with higher reliability, the weight of their local reachable density should be higher, otherwise, the weight of their corresponding distance should be reduced, so that the final abnormal density measurement is determined by the clean room construction sample data points with higher reliability and closer distance.
[0088] Specifically, according to the reliability of the clean room construction sample data point at each time point and the modified distance metric, the local reachability density of each clean room construction sample data point is obtained.
[0089] Record any clean room construction sample data point as the target clean room construction sample data point, and the calculation method for obtaining the local reachable density of the target clean room construction sample data point is:
[0090]
[0091] In the formula, Represents the local reachability density of the target clean room construction sample data points; Represents the total number of all time points of the target clean room construction sample data points; Represents the total number of all clean room construction sample data points; Indicates that the target clean room construction sample data point is in reliability at each time point; Represents the target clean room construction sample data point and the The clean room construction sample data point is in time point and The modified distance metric at each time point.
[0092] At this point, the local reachable density of each clean room construction sample data point is obtained.
[0093] Step S004: perform anomaly detection on the clean room construction sample data points according to the local reachable density to obtain anomaly results; and adjust the construction plan of the WBS according to the anomaly detection results.
[0094] Preset a threshold parameter , wherein this embodiment is based on This example is described as an example, and this embodiment is not specifically limited. It depends on the specific implementation situation.
[0095] Specifically, the local reachable density of each clean room construction sample data point is input into the LOF anomaly detection algorithm to obtain the degree of anomaly of each clean room construction sample data point; for any clean room construction sample data point, if the degree of anomaly of the clean room construction sample data point is greater than or equal to the threshold parameter , record the time point corresponding to the clean room construction sample data point as an abnormal time point; group all abnormal time points into an abnormal time point sequence as an abnormal result; adjust the WBS construction plan according to the abnormal result, and re-plan the task and resource allocation.
[0096] Among them, the LOF anomaly detection algorithm is a prior art and will not be described in detail in this embodiment.
[0097] See also Figure 2 , which shows the characteristic relationship flow chart of the clean room construction optimization method based on WBS technology.
[0098] At this point, this embodiment is completed.
[0099] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the principles of the present invention should be included in the protection scope of the present invention.
Claims
1. The clean room construction optimization method based on WBS technology is characterized by: The method comprises the following steps: Obtain several clean room construction process data sets during the project construction process; According to the clean room construction process data set, a number of clean room construction sample data points are obtained; according to the difference between the predicted construction time and the initial construction time between any two clean room construction sample data points, the time difference between any two clean room construction sample data points at any two time points is obtained; according to the time difference and the difference of the monitoring data of multiple dimensions at any two time points, the distance measurement between any two clean room construction sample data points at any two time points is obtained; according to the distance measurement and the similarity of the monitoring data of multiple dimensions at any two clean room construction sample data points at any two time points, the corrected distance measurement between any two clean room construction sample data points at any two time points is obtained; The method of obtaining the corrected distance metric between any two clean room construction sample data points at any two time points based on the distance metric and the similarity of the monitoring data of multiple dimensions between any two clean room construction sample data points at any two time points includes: Get the The clean room construction sample data point is in At the next time point Dimensions and The correlation of the dimensions and The clean room construction sample data point is in Time point Dimensions and The correlation of the dimensions; According to the correlation, get the Clean room construction sample data points and The clean room construction sample data point is in time point and At the next time point Dimensions and The relative differences in the dimensions; Get the Clean room construction sample data points and The clean room construction sample data point is in time point and The calculation method of the modified distance metric at each time point is: In the formula, Indicates Clean room construction sample data points and The clean room construction sample data point is in time point and The modified distance metric at each time point; Indicates Clean room construction sample data points and The clean room construction sample data point is in time point and Distance measurement at each time point; Represents the total number of all dimensions of clean room construction sample data points; Indicates Clean room construction sample data points and The clean room construction sample data point is in time point and At the next time point Dimensions and The relative differences in the dimensions; represents an exponential function with a natural constant as base; According to the difference in the dimensional monitoring data between each clean room construction sample data point and other clean room construction sample data points at each time point, the reliability of each clean room construction sample data point at each time point is obtained; according to the reliability of the clean room construction sample data point at each time point and the corrected distance metric, the local reachability density of each clean room construction sample data point is obtained; The local reachable density of each clean room construction sample data point is obtained according to the reliability of the clean room construction sample data point at each time point and the modified distance metric, including the specific method of: Any clean room construction sample data point is recorded as the target clean room construction sample data point; the calculation method for obtaining the local reachable density of the target clean room construction sample data point is: In the formula, Represents the local reachability density of the target clean room construction sample data points; Represents the total number of all time points of the target clean room construction sample data points; Represents the total number of all clean room construction sample data points; Indicates that the target clean room construction sample data point is in reliability at each time point; Represents the target clean room construction sample data point and the The clean room construction sample data point is in time point and The modified distance metric at each time point; According to the local reachable density, the clean room construction sample data points are detected for anomalies to obtain abnormal results; the construction plan of WBS is adjusted according to the abnormal results.
2. The clean room construction optimization method based on WBS technology according to claim 1 is characterized in that: The specific method of obtaining a number of clean room construction sample data points according to the clean room construction process data set is as follows: Each clean room construction process data set includes several construction stage data sets; each construction stage data set includes several days of dimensional construction data sequences; each day's dimensional construction data sequence includes several monitoring data of different dimensions; a three-dimensional space is constructed with the serial number of the clean room construction process data set, the serial number of the construction stage data set and the time point of the dimensional construction data sequence, and all clean room construction process data sets during the project construction process are input into the three-dimensional space to obtain several clean room construction sample data points.
3. The clean room construction optimization method based on WBS technology according to claim 1 is characterized in that: The specific method of obtaining the time difference between any two clean room construction sample data points at any two time points according to the difference between the predicted construction time and the initial construction time between any two clean room construction sample data points is as follows: The first The first of the clean room construction sample data points The time point and The difference between the initial construction time of the clean room construction sample data points is recorded as the first difference; the first difference is added to the The ratio of the predicted construction time of the clean room construction sample data points is recorded as the first ratio; The first of the clean room construction sample data points The time point and The difference between the initial construction time of the clean room construction sample data points is recorded as the second difference; the first difference is recorded as the The ratio of the predicted construction time of the clean room construction sample data points is recorded as the second ratio; the absolute value of the difference between the first ratio and the second ratio is recorded as the first Clean room construction sample data points and The clean room construction sample data point is in time point and The time difference at each time point.
4. The clean room construction optimization method based on WBS technology according to claim 1 is characterized in that: The specific formula for obtaining the distance measurement between any two clean room construction sample data points at any two time points according to the time difference and the difference in monitoring data of multiple dimensions between any two clean room construction sample data points at any two time points is: In the formula, Indicates Clean room construction sample data points and The clean room construction sample data point is in time point and Distance measurement at each time point; Indicates Clean room construction sample data points and The clean room construction sample data point is in time point and Time differences at different time points; Represents the total number of all dimensions of clean room construction sample data points; Indicates The clean room construction sample data point is in At the time point Monitoring data of various dimensions; Indicates The clean room construction sample data point is in At the time point Monitoring data of various dimensions; Indicates taking the absolute value.
5. The clean room construction optimization method based on WBS technology according to claim 1 is characterized in that: The acquisition The clean room construction sample data point is in At the next time point Dimensions and The correlation of the dimensions and The clean room construction sample data point is in Time point Dimensions and The specific methods include: The first The clean room construction sample data point is in At the time point The monitoring data series of the first dimension and the The clean room construction sample data point is in At the time point The Pearson correlation coefficient between the monitoring data series of the dimensions is used as the The clean room construction sample data point is in At the next time point Dimensions and The correlation of dimensions.
6. The clean room construction optimization method based on WBS technology according to claim 1 is characterized in that: According to the correlation, obtain the Clean room construction sample data points and The clean room construction sample data point is in time point and At the next time point Dimensions and The relevant differences in the dimensions include: The first The clean room construction sample data point is in At the next time point Dimensions and The correlation between the dimensions and The clean room construction sample data point is in Time point Dimensions and The absolute value of the difference in the correlation of the dimensions is taken as the Clean room construction sample data points and The clean room construction sample data point is in time point and At the next time point Dimensions and The relative differences in the dimensions.
7. The clean room construction optimization method based on WBS technology according to claim 1 is characterized in that: According to the difference in the monitoring data of the dimension between each clean room construction sample data point and other clean room construction sample data points at each time point, the specific formula for obtaining the reliability of each clean room construction sample data point at each time point is: In the formula, Indicates The clean room construction sample data point is in reliability at each time point; Represents the total number of all dimensions of clean room construction sample data points; In the The total number of all clean room construction sample data points at a time point; Indicates At the next time point The first of the clean room construction sample data points Monitoring data of various dimensions; Indicates The first of all clean room construction sample data points at a time point The mean of the monitoring data in each dimension; Represents an exponential function with a natural constant as base.
8. The clean room construction optimization method based on WBS technology according to claim 1 is characterized in that: The specific method of performing anomaly detection on the clean room construction sample data points according to the local reachable density to obtain anomaly results includes: The local reachable density of each clean room construction sample data point is input into the LOF anomaly detection algorithm to obtain the degree of anomaly of each clean room construction sample data point; for any clean room construction sample data point, if the degree of anomaly of the clean room construction sample data point is greater than or equal to the threshold parameter , record the time point corresponding to the clean room construction sample data point as an abnormal time point; and group all abnormal time points into an abnormal time point sequence as an abnormal result.
Citation Information
Patent Citations
Traffic abnormality detection system based on grey LOF (Live Object Framework), and detection method thereof
CN107257351A
Intelligent electric meter fault rate estimation method and system under multi-environmental stress
CN113484813A
Building photovoltaic potential assessment method and system based on parametric analysis
CN117172620A
Method and system for anomaly detection in data sets
US20130304710A1