Energy storage charging system and control method
By using the communication and control method of the inverter and charging pile in the photovoltaic storage charging system, the remaining available power in the grid-connected state is determined, and the inverter output power is increased when the grid-connected output is limited, solving the problem of photovoltaic module energy The problem of waste is eliminated, and efficient energy utilization and spontaneous self-use of the system are achieved.
Patent Information
- Application Number
- CN202410868587.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-01
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2044-07-01
AI Technical Summary
When the photovoltaic storage and charging system is connected to the grid, the energy generated by the photovoltaic modules may be wasted because the charging piles mainly draw power from the grid, resulting in the inability to effectively utilize the excess energy of the photovoltaic modules.
Design an energy storage charging system, including an inverter, charging pile and energy storage battery. When the inverter is connected to the grid, it determines the remaining available power by obtaining the port power of the grid-connected output port and the charge and discharge information of the energy storage battery. , and sends it to the charging pile, which adjusts the charging power according to the remaining available power. When the grid-connected output port is in a restricted state, the inverter increases the output power, allowing the charging pile to obtain more power from the photovoltaic modules through the inverter to prevent energy waste.
Effectively utilize the energy generated by photovoltaic modules, reduce energy waste, ensure that charging piles can still obtain sufficient power from photovoltaic modules even when the grid-connected output is limited, avoid over-reliance on the power grid, and achieve self-use of the system.
Smart Images

Figure CN118432156B_ABST
Abstract
Description
Technical Field
[0001] The present application belongs to the field of photovoltaic energy storage technology, and in particular, relates to an energy storage charging system and a control method. Background Art
[0002] With the development of the photovoltaic field and the popularization of new energy vehicles, a photovoltaic charging system has been formed that combines charging piles, energy storage batteries, inverters and photovoltaic modules. The photovoltaic charging system can also be connected to the mains to power the charging piles, and the photovoltaic charging system can also be used to power other loads. The electric energy generated by the photovoltaic modules in the photovoltaic charging system will change with the lighting conditions, and the power demand of other loads may also change. When the photovoltaic charging system is in a grid-connected state, if the charging pile mainly draws power from the grid, it is easy for the energy generated by the photovoltaic modules to charge the energy storage batteries in the photovoltaic charging system. There is still excess energy, resulting in energy waste generated by the photovoltaic modules. Summary of the invention
[0003] The embodiments of the present application provide an energy storage charging system and a control method, which can prevent energy waste generated by photovoltaic components.
[0004] In a first aspect, the present application provides an energy storage charging system, including an inverter, a charging pile and an energy storage battery; the DC input terminal of the inverter is used to connect a photovoltaic module; the battery connection terminal of the inverter is used to connect an energy storage battery, the off-grid output port and the grid-connected output port of the inverter are both used to connect the charging pile and the load, and the grid-connected output port is used to connect the power grid; the inverter and the charging pile communicate with each other; wherein, when the inverter is in a grid-connected state, the inverter determines the remaining available power according to the port power of the grid-connected output port and the charge and discharge information of the energy storage battery; wherein the remaining available power at least includes the photovoltaic module can also The power provided to the charging pile; the inverter sends the remaining available power to the charging pile; the charging pile adjusts the charging power of the charging pile to the target device according to the remaining available power and the remaining available target power; when the grid-connected output port is in a restricted state, the remaining available target power is a first power value, and the charging pile obtains a first charging power from the power grid according to the remaining available power and the remaining available target power, and the first charging power is the first power value; when the inverter detects that the charging pile obtains the first charging power from the power grid, the inverter increases its output power, thereby increasing the power obtained by the charging pile from the photovoltaic module through the inverter.
[0005] In the embodiment of the present application, the port power of the grid-connected output port and the charge and discharge information of the energy storage battery are obtained by the inverter in the grid-connected state, the remaining available power of the charging pile is determined according to the port power and the charge and discharge information, and the remaining available power is sent to the charging pile, so that the charging pile can adjust the charging power of the charging pile to the target device according to the remaining available power and the remaining available target power. When the grid-connected output port is in a restricted state, the remaining available target power is the first power value, and the charging pile obtains the first charging power from the power grid according to the remaining available power and the remaining available target power. When the inverter detects that the charging pile obtains the first charging power from the power grid, in order to make the photovoltaic module provide power to the charging pile as much as possible, the inverter controls its output power to increase. At this time, since the grid-connected output port is already in a restricted state, the increased output power of the inverter will still not flow into the power grid, but will be provided to the charging pile and the load, so that the charging pile obtains more power from the photovoltaic module through the inverter, and then the photovoltaic module can output more power to power the charging pile, thereby preventing the energy waste generated by the photovoltaic module.
[0006] In one possible implementation, the inverter is also used for: in response to the grid-connected output port being in a restricted state, the inverter sets the remaining available target power to a first power value, and sends the remaining available target power to the charging pile; or, the inverter is also used for: when the grid-connected output port is in a restricted state, sending the restricted state information to the charging pile; the charging pile receives the restricted state information, and sets the remaining available target power to the first power value according to the restricted state information.
[0007] In one possible implementation, when the output power of the inverter remains stable within a preset time period and the charging pile obtains the first charging power from the power grid, the inverter or the charging pile sets the remaining available target power to zero so that the charging pile stops obtaining power from the power grid.
[0008] In one possible implementation, the inverter is also used to: in response to the grid-connected output port being in an unrestricted state, set the remaining available target power to zero, and send the remaining available target power to the charging pile; or, the inverter is also used to: when the grid-connected output port is in an unrestricted state, send the unrestricted state information to the charging pile; the charging pile receives the unrestricted state information, and sets the remaining available target power to zero according to the unrestricted state information; wherein, when the remaining available target power is zero, the charging pile adjusts the charging power of the charging pile to the target device according to the charging instruction generated by the remaining available power and the remaining available target power until the remaining available power is zero.
[0009] In one possible implementation, the charging and discharging information includes battery information and battery power of the energy storage battery; the inverter is also used for: when the battery information indicates that the energy storage battery is not ready for discharge, the remaining available power is the port power; when the battery information indicates that the energy storage battery is ready for discharge, the remaining available power is the sum of the port power and the battery power.
[0010] In a possible implementation, the charging pile is used to: receive the remaining available power sent by the inverter;
[0011] A charging instruction is generated according to the remaining available power and the remaining available target power; when the remaining available target power is a first power value, the charging pile is enabled to obtain a first charging power from the grid-connected output port according to the charging instruction.
[0012] In one possible implementation, the charging pile is also used to: obtain a first deviation value based on the remaining available power and the remaining available target power received in the current cycle; obtain a second deviation value based on the remaining available power and the remaining available target power received in the previous cycle; and generate a charging instruction corresponding to the current cycle based on the first deviation value, the second deviation value and the charging instruction generated in the previous cycle.
[0013] In one possible implementation, the charging pile is also used to: obtain a first compensation value based on the product of a first deviation value and a first preset parameter; obtain a second compensation value based on the product of a second deviation value and a second preset parameter; wherein the first preset parameter and the second preset parameter are pre-set control parameters; and obtain a charging instruction corresponding to a current cycle based on the sum of the first compensation value, the second compensation value and the charging instruction corresponding to a previous cycle.
[0014] In a second aspect, the present application provides a control method, which is applied to an inverter, and the control method includes: when the inverter is in a grid-connected state, obtaining the port power of the grid-connected output port of the inverter and the charging and discharging information of the energy storage battery; determining the remaining available power according to the port power and the charging and discharging information; wherein the remaining available power at least includes the power that the photovoltaic component can also provide to the charging pile; sending the remaining available power to the charging pile, so that the charging pile can adjust the charging power of the charging pile to the target device according to the remaining available power and the remaining available target power; wherein, when the grid-connected output port is in a restricted state, the remaining available target power is a first power value, and the charging pile obtains a first charging power from the power grid according to the remaining available power and the remaining available target power, and the first charging power is a first power value; when it is detected that the charging pile obtains the first charging power from the power grid, controlling the inverter to increase the output power, thereby increasing the power obtained by the charging pile from the photovoltaic component through the inverter.
[0015] In one possible implementation, the control method also includes: in response to the grid-connected output port being in a restricted state, setting the remaining available target power to a first power value, and sending the remaining available target power to the charging pile; or, when the grid-connected output port is in a restricted state, sending restricted state information to the charging pile; the restricted state information is used to trigger the charging pile to set the remaining available target power to the first power value.
[0016] In one possible implementation, the control method also includes: when the output power of the inverter remains stable within a preset time period and the charging pile obtains a first charging power from the power grid, setting the remaining available target power to zero and sending it to the charging pile so that the charging pile stops obtaining power from the power grid; or, when the output power of the inverter remains stable within a preset time period and the charging pile obtains the first charging power from the power grid, sending output stability information to the charging pile; the output stability information is used to trigger the charging pile to set the remaining available target power to zero.
[0017] In one possible implementation, the control method also includes: in response to the grid-connected output port being in an unrestricted state, setting the remaining available target power to zero, and sending the remaining available target power to the charging pile; or, when the grid-connected output port is in an unrestricted state, sending the unrestricted state information to the charging pile; the unrestricted state information is used to trigger the charging pile to set the remaining available target power to zero; wherein, when the remaining available target power is zero, the charging pile outputs the corresponding charging power to the target device according to the remaining available power and the remaining available target power until the remaining available power is zero.
[0018] In one possible implementation, the charge and discharge information includes battery information and battery power of the energy storage battery; the remaining available power is determined according to the port power and the charge and discharge information, including: when the battery information indicates that the energy storage battery does not meet the discharge conditions, the remaining available power is the port power; when the battery information indicates that the energy storage battery meets the discharge conditions, the remaining available power is the sum of the port power and the battery power.
[0019] In a third aspect, the present application provides a control method, which is applied to a charging pile, and the control method is used to: receive the remaining available power sent by an inverter; the remaining available power is determined by the inverter based on the port power of its grid-connected output port and the charge and discharge information of the energy storage battery, and the remaining available power at least includes the power that the photovoltaic component can also provide to the charging pile; generate a charging instruction based on the remaining available power and the remaining available target power; wherein, when the grid-connected output port is in a restricted state, the remaining available target power is a first power value; when the remaining available target power is the first power value, according to the charging instruction, the charging pile obtains the first charging power from the power grid, so that the inverter increases its output power when it detects that the charging pile obtains the first charging power from the power grid, thereby increasing the power obtained by the charging pile from the photovoltaic component through the inverter; the first charging power is the first power value.
[0020] In one possible implementation, the control method also includes: receiving the remaining available target power sent by the inverter, the remaining available target power being set by the inverter to a first power value when the grid-connected output port is in a restricted state; or, receiving restricted state information sent by the inverter, and setting the remaining available target power to the first power value according to the restricted state information.
[0021] In one possible implementation, the control method also includes: receiving a remaining available target power of zero sent by the inverter; when the output power of the inverter remains stable within a preset time period and the charging pile obtains a first charging power from the power grid, the inverter sets the remaining available target power to zero; or, receiving output stability information sent by the inverter, and setting the remaining available target power to zero according to the output stability information; when the output power of the inverter remains stable within a preset time period and the charging pile obtains the first charging power from the power grid, the inverter sends output stability information to the charging pile.
[0022] In one possible implementation, the control method also includes: receiving a remaining available target power of zero sent by the inverter; or receiving unrestricted status information sent by the inverter, and setting the remaining available target power to zero according to the unrestricted status information; when the remaining available target power is zero, adjusting the charging power of the charging pile to the target device according to the charging instruction generated by the remaining available power and the remaining available target power until the remaining available power is zero; wherein, when the grid-connected output port is in an unrestricted state, the inverter sets the remaining available target power to zero.
[0023] In one possible implementation, the charging pile is an AC charging pile. Accordingly, according to the charging instruction, the charging pile obtains a first charging power from the power grid, including: sending a charging instruction to a target device so that the target device increases the charging power according to the charging instruction, thereby enabling the charging pile to obtain the first charging power from the power grid.
[0024] In one possible implementation, a charging instruction is generated based on the remaining available power and the remaining available target power, including: obtaining a first deviation value based on the remaining available power and the remaining available target power received in the current cycle; obtaining a second deviation value based on the remaining available power and the remaining available target power received in the previous cycle; and generating a charging instruction corresponding to the current cycle based on the first deviation value, the second deviation value, and the charging instruction generated in the previous cycle.
[0025] In one possible implementation, a charging instruction corresponding to the current cycle is generated based on a first deviation value, a second deviation value, and a charging instruction generated in a previous cycle, including: obtaining a first compensation value based on the product of the first deviation value and a first preset parameter; obtaining a second compensation value based on the product of the second deviation value and a second preset parameter; wherein the first preset parameter and the second preset parameter are pre-set control parameters; and obtaining a charging instruction corresponding to the current cycle based on the sum of the first compensation value, the second compensation value, and the charging instruction corresponding to the previous cycle. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 It is a module schematic diagram of the energy storage charging system provided in an embodiment of the present application.
[0027] Figure 2 It is a flowchart of a control method provided in one embodiment of the present application.
[0028] Figure 3 It is a partial flow chart of a control method provided in one embodiment of the present application.
[0029] Figure 4 yes Figure 2 Detailed flowchart of step S120 in FIG.
[0030] Figure 5 It is a flow chart of a control method provided in another embodiment of the present application.
[0031] Figure 6 yes Figure 5 Detailed flowchart of step S400.
[0032] Figure 7 yes Figure 6 Detailed flowchart of step S430 in FIG. DETAILED DESCRIPTION
[0033] It should be noted that the terms "first" and "second" in the specification, claims and drawings of the present application are used to distinguish similar objects, rather than to describe a specific order or sequence. In the specification, claims and drawings of the present application, unless otherwise specified, " / " means or, for example, A / B can mean A or B. For example, A and / or B can mean: A exists alone, A and B exist at the same time, and B exists alone. In addition, the term "multiple" in the specification, claims and drawings of the present application refers to two or more than two.
[0034] It is understandable that the connection relationship described in the present application refers to direct or indirect connection. For example, A is connected to B or A is electrically connected to B, which can be either A and B are directly connected or A and B are indirectly connected through one or more other electrical components, for example, A and C are directly connected, and C and B are directly connected, so that A and B are connected through C.
[0035] It should also be noted that the method disclosed in the embodiments of the present application or the method shown in the flowchart includes one or more steps for implementing the method. Without departing from the scope of the claims, the execution order of multiple steps can be interchangeable with each other, and some of the steps can also be deleted.
[0036] Some embodiments will be described below in conjunction with the accompanying drawings. In the absence of conflict, the following embodiments and features in the embodiments may be combined with each other.
[0037] The power generated by the photovoltaic modules in the photovoltaic charging system will change with the lighting conditions, and the power demand of other loads may also change. When the photovoltaic charging system is in the grid-connected state, if the charging pile mainly draws power from the grid, it is easy for the energy generated by the photovoltaic modules to charge the energy storage batteries in the photovoltaic charging system and still have excess energy, resulting in a waste of energy generated by the photovoltaic modules.
[0038] In view of this, an embodiment of the present application provides an energy storage charging system and a control method, which can prevent energy waste generated by photovoltaic components.
[0039] Please refer to Figure 1 , Figure 1 A module schematic diagram of an energy storage charging system 10 provided in an embodiment of the present application.
[0040] The energy storage charging system 10 includes an inverter 100 , a charging pile 200 and an energy storage battery 300 .
[0041] The DC input terminal of the inverter 100 is connected to the photovoltaic module 20. The battery connection terminal of the inverter 100 is used to connect the energy storage battery 300. The off-grid output port and the grid-connected output port of the inverter 100 are both connected to the charging pile 200 and the load 30, and the grid-connected output port is used to connect to the power grid 40. The inverter 100 and the charging pile 200 communicate with each other.
[0042] The photovoltaic module 20 and the energy storage battery 300 can supply power to the charging pile 200 and the load 30 via the off-grid output port through the inverter 100. When the inverter 100 is in the grid-connected state, that is, when the grid is connected to the grid-connected output port, the grid 40 can also supply power to the charging pile 200 and the load 30 via the grid-connected output port.
[0043] Among them, the energy storage charging system 10 and the control method of the embodiment of the present application are applicable to the case where the inverter 100 is in a grid-connected state, that is, the grid 40 is connected to the grid-connected output port of the inverter 100.
[0044] In the embodiment of the present application, the inverter 100 and the charging pile 200 can be connected by wired communication, such as RS485 bus or CAN bus. Of course, the inverter 100 and the charging pile 200 can also be connected by wireless communication, such as Bluetooth communication, Zigbee communication, UWB communication, etc., and the present application does not limit this.
[0045] In the embodiment of the present application, when the inverter 100 is in a grid-connected state, the inverter 100 determines the remaining available power according to the port power of the grid-connected output port and the charge and discharge information of the energy storage battery 300 , and sends the remaining available power to the charging pile 200 .
[0046] The remaining available power at least includes the power that the photovoltaic assembly 20 can still provide to the charging pile 200. Specifically, the remaining available power at least includes the power that can be additionally provided to the charging pile 200 by the inverter 100 in addition to the power that the photovoltaic assembly 20 has already provided to the charging pile 200 and the load 30 by the inverter 100.
[0047] The charging pile 200 adjusts the charging power of the charging pile 200 to the target device according to the remaining available power and the remaining available target power.
[0048] When the grid-connected output port is in a restricted state, the remaining available target power is a first power value. The charging pile 200 obtains a first charging power from the grid 40 according to the remaining available power and the remaining available target power, and the first charging power is a first power value.
[0049] The grid-connected output port is in a restricted state, which means that the power outputted from the inverter 100 to the power grid 40 through the grid-connected output port is limited. The inverter 100 can determine whether the grid-connected output port is in a restricted state according to the specific value of the port power. For example, a limit value of the port power can be pre-set in the inverter 100. When the port power is greater than or equal to the limit value, it is confirmed that the grid-connected output port is in a restricted state. When the port power is less than the limit value, it is confirmed that the grid-connected output port is in a non-restricted state.
[0050] In some embodiments, the limit value can be set to zero, or a value close to zero, such as 2W, 5W, 10W, etc. At this time, the electric energy generated by the photovoltaic assembly 20 cannot flow into the power grid 40 and can only be used for self-generation and self-use, that is, the electric energy generated by the photovoltaic assembly 20 can only be used to charge the energy storage battery 300 and power the load 30 and the charging pile 200. Of course, in the embodiment of the present application, the limit value is not limited to zero and can be set according to actual needs.
[0051] It is understandable that when the grid-connected output port is in a restricted state, the inverter 100 controls its output power so that the port power output to the grid-connected output port is within the limit value while the inverter 100 supplies power to the load 30 and the charging pile 200. At this time, the photovoltaic power generated by the photovoltaic module 20 may not be completely output through the inverter 100.
[0052] The first charging power is the first power value. In the embodiment of the present application, the first power value can be set according to the actual application requirements. For example, if the power of the grid-connected output port is greater than zero, it indicates that there is power flowing from the inverter 100 to the grid 40 through the grid-connected output port. If the power of the grid-connected output port is less than zero, it indicates that there is power input from the grid 40 through the grid-connected output port, and the first power value is a negative value, for example, it can be set to -100W, -150W, etc. On the contrary, if the power of the grid-connected output port is greater than zero, it indicates that there is power input from the grid 40 through the grid-connected output port, and the power of the grid-connected output port is less than zero, indicating that there is power flowing from the inverter 100 through the grid-connected output port into the grid 40, then the first power value is a positive value, for example, it can be set to 100W, 150W, etc.
[0053] When the grid-connected output port is in a restricted state, the remaining available target power is a first power value, and the charging pile 200 can generate a charging instruction based on the remaining available power and the remaining available target power, so that the charging pile 200 adjusts its charging power for the target device according to the charging instruction, and then the charging pile 200 obtains the first charging power from the power grid 40 through the grid-connected output port according to the charging instruction.
[0054] It can be understood that at this time, in addition to obtaining the first charging power from the power grid 40 through the grid-connected output port, the charging pile 200 also continues to obtain power from the inverter 100 through the off-grid output port.
[0055] When the inverter 100 detects that the charging pile 200 obtains the first charging power from the power grid, the inverter 100 increases its output power, thereby increasing the power obtained by the charging pile 200 from the photovoltaic component 20 through the inverter 100 .
[0056] In the embodiment of the present application, the inverter 100 can confirm whether the charging pile 200 obtains the first charging power from the power grid 40 through the grid-connected output port by detecting the power of the grid-connected output port. For example, the inverter 100 can be provided with a power detector at the grid-connected output port, and the power detector detects the power of the grid-connected output port. When it is detected that the power of the grid-connected output port is the first power value, it is confirmed that the charging pile 200 obtains the first charging power from the grid-connected output port.
[0057] In the embodiment of the present application, when the inverter 100 detects that the charging pile 200 obtains the first charging power from the grid-connected output port, in order to make the photovoltaic module 20 provide power to the charging pile 200 as much as possible, the inverter 100 increases its output power. At this time, since the port power is already in a limited state, the increased output power of the inverter 100 will still not flow into the power grid 40, but will be provided to the charging pile 200 and the load 30 through the off-grid output port, so that the charging pile 200 obtains more power from the photovoltaic module 20 through the inverter 100, and then the photovoltaic module 20 can output more power to power the charging pile 200, thereby preventing the energy waste generated by the photovoltaic module 20.
[0058] The energy storage charging system 10 and the control method provided by the embodiment of the present invention will be described in detail below through specific embodiments.
[0059] See also Figure 2 , which shows a flow chart of a control method provided by an embodiment of the present invention. The control method is applied to the inverter 100. The control method includes:
[0060] S110: When the inverter is in a grid-connected state, obtain the port power of the grid-connected output port and the charge and discharge information of the energy storage battery.
[0061] It is understood that the inverter 100 can determine whether it is in the grid-connected state by performing a grid-connected detection on its grid-connected output port. When it is detected that the grid 40 is connected to the grid-connected output port, it is determined that the inverter 100 is in the grid-connected state.
[0062] The inverter 100 can obtain the port power of the grid-connected output port through a power detector, or can perform current detection and voltage detection on the grid-connected output port through a current detection circuit and a voltage detection circuit (not shown in the figure), and obtain the port power of the grid-connected output port according to the detected voltage and current. When the inverter 100 obtains the port power through the power detector, the power detector can be set independently of the inverter 100. For example, the power detector can be an electric meter (not shown in the figure), and the electric meter is connected to the grid-connected output port of the inverter 100. The port power of the grid-connected output port is obtained through the electric meter detection. When the inverter 100 obtains the port power through the current and voltage detected by the current detection circuit and the voltage detection circuit, the current detection circuit and the voltage detection circuit can be integrated in the inverter 100, or can be set independently of the inverter 100, and this application does not limit this.
[0063] The inverter 100 can obtain the charging and discharging information of the energy storage battery 300 by communicating with the battery management system in the energy storage battery 300 .
[0064] S120: Determine the remaining available power of the charging pile according to the port power and the charging and discharging information.
[0065] The remaining available power at least includes the power that the photovoltaic assembly 20 can still provide to the charging pile 200. Specifically, the remaining available power at least includes the power that can be additionally provided to the charging pile 200 by the inverter 100 in addition to the power that the photovoltaic assembly 20 has already provided to the charging pile 200 and the load 30 by the inverter 100.
[0066] S130: Send the remaining available power to the charging pile, so that the charging pile can adjust the charging power of the charging pile to the target device according to the remaining available power and the remaining available target power.
[0067] The inverter 100 sends the remaining available power to the charging pile 200. When the grid-connected output port is in a restricted state, the remaining available target power is the first power value. At this time, the charging pile 200 obtains the first charging power from the power grid 40 according to the remaining available power and the remaining available target power, and the first charging power is the first power value.
[0068] It can be understood that the inverter 100 can confirm whether the grid-connected output port is in a restricted state according to the obtained port power. For details, please refer to the description of the aforementioned energy storage charging system 10, which will not be further described here.
[0069] S140: When it is detected that the charging pile obtains the first charging power from the power grid, the inverter is controlled to increase the output power, thereby increasing the power obtained by the charging pile from the photovoltaic component 20 through the inverter.
[0070] When the inverter 100 detects that the charging pile 200 obtains the first charging power from the power grid 40 through the grid-connected output port, its output power is increased. Since the port power of the grid-connected output port is already in a limited state, the output power of the inverter 100 will be provided to the charging pile 200 and the load 30 via the off-grid output port. The power of the load 30 cannot be controlled by the inverter 100, and the load 30 obtains it directly from the off-grid output terminal of the inverter 100 according to its own operating requirements. Therefore, when the load power 30 does not change, the increased power will be provided to the charging pile 200 through the off-grid output terminal, so that the charging pile 200 obtains more power from the photovoltaic module 20 through the inverter 100, and then the photovoltaic module 20 can output more power to power the charging pile 200, thereby preventing the energy waste generated by the photovoltaic module 20.
[0071] It can be understood that the inverter 100 can confirm whether the charging pile 200 obtains the first charging power from the power grid 40 through the grid-connected output port by detecting the power of the grid-connected output port. For details, see the aforementioned energy storage charging system 10.
[0072] In the embodiment of the present application, the control method applied to the inverter 100 may be executed by a control device in the inverter 100, such as a microcontroller unit (MCU), a digital signal processor (DSP) or an energy management system (EMS) in the inverter 100. The control device may include multiple controllers or control chips, such as a DSP chip and a RAM (Random Access Memory) chip.
[0073] It is understandable that, in the embodiment of the present application, the inverter 100 may repeatedly perform steps S110 to S140 until all the energy generated by the photovoltaic assembly 20 is output by the inverter 100. For example, the inverter 100 repeatedly performs steps S110 to S140 at a preset cycle, and reacquires the port power of the grid-connected output port of the inverter 100 and the charge and discharge information of the energy storage battery 300 in each cycle, thereby updating the remaining available power.
[0074] In some embodiments, the control method may further include: in response to the grid-connected output port being in a restricted state, setting the remaining available target power to a first power value, and sending the remaining available target power to the charging pile 200 .
[0075] That is, when the inverter 100 detects that the grid-connected output port is in a restricted state, the inverter 100 sets the remaining available target power to the first power value, and sends the remaining available target power set to the first power value to the charging pile 200 .
[0076] In some other embodiments, the control method may further include: when the grid-connected output port is in a restricted state, sending restricted state information to the charging pile 200 .
[0077] The limited state information is used to trigger the charging pile to set the remaining available target power to the first power value. At this time, the remaining available target power is a parameter built into the charging pile 200, and the charging pile 200 sets the remaining available target power to the first power value when receiving the limited state information.
[0078] In some embodiments, the control method may further include: when the output power of the inverter 100 remains stable within a preset time period and the charging pile 200 obtains the first charging power from the power grid 40, the remaining available target power is set to zero and sent to the charging pile 200, so that the charging pile 200 stops obtaining power from the power grid.
[0079] The inverter 100 repeats the above steps S110 to S140. Each time it is detected that the charging pile 200 obtains the first charging power from the grid-connected output port, the inverter 100 controls the inverter 100 to increase the output power, so that the power obtained by the charging pile 200 from the photovoltaic module 20 through the inverter 100 gradually increases. When the power output of the photovoltaic module 20 has reached the maximum, the output power of the inverter 100 can no longer be increased, which will cause the output power of the inverter 100 to remain stable and no longer increase. Therefore, when the inverter 100 detects that the output power of the inverter 100 remains stable within the preset time and the charging pile 200 obtains the first charging power from the power grid 40, the remaining available target power is set to zero. The charging pile 200 can obtain power only from the off-grid output port of the inverter 100 according to the remaining available power and the remaining available target power, and stops obtaining power from the power grid 40 through the grid-connected output port of the inverter 100.
[0080] At this time, the charging pile 200 continues to charge the target device with the power currently obtained from the off-grid output port of the inverter 100, and the photovoltaic module 20 outputs its maximum output power to the inverter 100 and stops obtaining power from the power grid 40. This can prevent energy waste of the photovoltaic module 20 and enable the charging pile 200 to stop taking power from the power grid 40, thereby realizing the self-generation and self-use of the energy storage charging system 10.
[0081] In some other embodiments, the control method may further include: when the output power of the inverter 100 remains stable within a preset time period and the charging pile 200 obtains the first charging power from the power grid 40, sending output stability information to the charging pile 200.
[0082] The output stability information is used to trigger the charging pile 200 to set the remaining available target power to zero. In this embodiment, when the output power of the inverter 100 remains stable within a preset time and the charging pile 200 also maintains obtaining the first charging power from the power grid 40, the inverter 100 sends the output stability information to the charging pile 200, and the charging pile 200 sets the remaining available target power to zero according to the output stability information, thereby causing the charging pile 200 to stop obtaining power from the power grid 40, thereby realizing the self-generation and self-use of the energy storage charging system 10.
[0083] like Figure 3 As shown, in some embodiments, the control method may further include:
[0084] S150 : In response to the grid-connected output port being in an unrestricted state, setting the remaining available target power to zero.
[0085] The grid-connected output port is in an unrestricted state, that is, the power output from the grid-connected output port to the grid 40 is not in a restricted state. The unrestricted state may be that the port power does not reach the restricted value, or that the power output from the grid-connected output port to the grid 40 is not restricted.
[0086] At this time, the inverter 100 does not limit the power output to the grid-connected output port, and the photovoltaic module 20 outputs its maximum power according to the maximum power tracking algorithm. The inverter 100 outputs all the power output from the photovoltaic module 20 to the inverter 100.
[0087] S160: Send the remaining available target power to the charging pile.
[0088] By sending the remaining available target power to the charging pile 200, when the remaining available target power is zero, the charging pile 200 outputs the corresponding charging power to the target device according to the remaining available power and the remaining available target power, and then adjusts the power obtained by the charging pile 200 from the inverter 100, and gradually adjusts the remaining available power to the remaining available target power until the remaining available power is zero.
[0089] In other embodiments, Figure 4 As shown, the control method may further include: when the grid-connected output port is in an unrestricted state, sending unrestricted state information to the charging pile 200 .
[0090] The non-restricted state information is used to trigger the charging pile to set the remaining available target power to zero. That is, the inverter 100 sends the non-restricted state information to the charging pile 200, and the charging pile 200 sets the remaining available target power to zero according to the non-restricted state information. When the charging pile 200 outputs the corresponding charging power to the target device according to the remaining available power and the remaining available target power of zero, the charging pile 200 only obtains power from the inverter 100 through the off-grid output port, and no longer obtains power from the power grid 40 through the grid-connected output port.
[0091] In some embodiments, the charge and discharge information includes battery information and battery power of the energy storage battery 300. Figure 4 , step S120 may include:
[0092] S121. When the battery information indicates that the energy storage battery is not in a discharge condition, the remaining available power is the port power.
[0093] It can be understood that when the energy storage battery 300 does not meet the discharge conditions, it means that the energy storage battery 300 cannot be discharged, and thus cannot output power to the inverter 100 to power the charging pile 200, so the remaining available power only includes the port power. Specifically, the remaining available power is Pev, the port power is Pmeter, then Pev=Pmeter.
[0094] The battery information may include information such as the power level and temperature of the energy storage battery 300. Whether the energy storage battery 300 is in a discharge condition can be confirmed based on information such as the power level and temperature of the energy storage battery 300. For example, when the power level of the energy storage battery 300 is lower than a preset power level, the energy storage battery 300 cannot be discharged and can only be charged, and it is confirmed that the energy storage battery 300 is not in a discharge condition. Or when the temperature of the energy storage battery 300 is lower than a preset temperature, the energy storage battery 300 cannot be discharged, and it is confirmed that the energy storage battery 300 is not in a discharge condition.
[0095] In some other embodiments, since the power grid 40 will be connected to the grid-connected output port, the charge and discharge time can be set for the energy storage battery 300. For example, in the high electricity price stage, the energy storage battery 300 is in the discharge time and can be discharged to power the load 30 and the charging pile 200. In the low electricity price stage and the flat electricity price stage, the energy storage battery 300 is in the charging time and cannot be discharged, that is, it cannot power the load 30 and the charging pile 200. This can reduce the frequency of users using the power grid 40 in the high electricity price stage and reduce the user's electricity cost. Based on this, the battery information may include the charge and discharge time of the energy storage battery 300. If the energy storage battery 300 is in the discharge time in the current time period, it indicates that the energy storage battery 300 is in the discharge condition. If the energy storage battery 300 is in the charging time in the current time period, it indicates that the energy storage battery 300 is not in the discharge condition.
[0096] S122: When the battery information indicates that the energy storage battery is ready for discharge, the remaining available power is the sum of the port power and the battery power.
[0097] When the energy storage battery 300 is in discharge condition, the energy storage battery 300 can output power to the inverter 100 to supply power to the charging pile 200, so the remaining available power is the sum of the port power and the battery power. Specifically, the battery power is Pbat, then the remaining available power Pev=Pmeter+Pbat.
[0098] It can be understood that when the energy storage battery 300 is in a discharge condition, the energy storage battery 300 may be discharging or being charged by the photovoltaic module 20. When the battery power is greater than zero, it means that the photovoltaic module 20 is charging the energy storage battery 300. At this time, the remaining available power is the sum of the port power and the battery power. The inverter 100 hopes to provide the power used by the photovoltaic module 20 to charge the energy storage battery 300 to the inverter 100 to supply power to the charging pile 200. At this time, if the photovoltaic module 20 has excess power in addition to the power used to charge the energy storage battery 300 and the power already provided to the inverter 100 for output, the excess power will be provided to the inverter 100 to supply power to the charging pile 200. Since the charging pile 200 obtains the first charging power from the power grid 40 through the grid-connected output port, the inverter 100 continuously increases the output power until the photovoltaic component 20 outputs its maximum output power to the inverter 100, and the power provided to charge the energy storage battery 300 is also provided to the inverter 100 to power the charging pile 200.
[0099] The inverter 100 can obtain the battery voltage and battery current of the energy storage battery 300 by performing voltage detection and current detection on the energy storage battery 300, and obtain the battery power according to the product of the obtained battery voltage and battery current. It can be understood that the inverter 100 can be provided with a voltage detection circuit and a current detection circuit connected to the energy storage battery 300, and the voltage detection and current detection of the energy storage battery 300 are performed by the voltage detection circuit and the current detection circuit to obtain the battery voltage and battery current. The voltage detection circuit and the current detection circuit connected to the energy storage battery 300 can be set independently of the control device in the inverter 100, or can be integrated in the control device in the inverter 100, and the present application does not limit this.
[0100] It can be understood that in the embodiment of the present application, the inverter 100 determines the remaining available power based on the port power and the charging and discharging information. When the grid-connected output port is limited, its output power is automatically limited so that the power output to the off-grid output port satisfies the power supply for the charging pile 200 and the load 30, and the power output to the grid-connected output port is within the limit value.
[0101] For the inverter 100, it is not certain whether the photovoltaic component 20 has excess power to supply power to the charging pile 200. When the grid-connected output port is in a restricted state, the port power is a limit value. The remaining available power is not the power that the actual photovoltaic component 20 can still provide to the charging pile 200. At this time, the remaining available target power is set to the first power value through the inverter 100 or the charging pile 200, so that the charging pile 200 obtains the first charging power from the power grid 40 through the grid-connected output port according to the remaining available target power. The inverter 100 is internally provided with a self-generated and self-used power supply logic. When it is detected that the charging pile 200 obtains the first charging power from the power grid 40, the inverter 100 controls its output power to increase, so that the inverter 100 can supplement the power obtained from the power grid 40 for the charging pile 200. If there is excess power in the photovoltaic component 20 or the photovoltaic component 20 and the energy storage battery 300, the inverter 100 can increase the output power. Until the power of the photovoltaic component 20 or the photovoltaic component 20 and the energy storage battery 300 is fully output and the output power of the inverter 100 can no longer be increased, the remaining available target power is set to zero, so that the inverter 100 maintains the power output at this time, and the charging pile 200 stops obtaining power from the power grid 40.
[0102] In this way, by setting the remaining available target power to the first power value when the grid-connected output port is in a restricted state, the charging pile 200 is disturbed to obtain power from the power grid 40, so that the photovoltaic component 20 can output excess power to the off-grid output port to power the charging pile 200, thereby maximizing the use of the energy generated by the photovoltaic component 20 and preventing the waste of energy generated by the photovoltaic component 20.
[0103] See also Figure 5 , which shows a flow chart of a control method provided by another embodiment of the present application, the control method is applied to a charging pile 200, and the control method includes:
[0104] S300: Receive the remaining available power sent by the inverter.
[0105] The remaining available power is determined by the inverter 100 according to the port power of the grid-connected output port and the charge and discharge information of the energy storage battery 300 , and the remaining available power at least includes the power that the photovoltaic assembly 20 can still provide to the charging pile.
[0106] S400: Generate a charging instruction according to the remaining available power and the remaining available target power.
[0107] The remaining available target power is set to the first power value when the grid-connected output port of the inverter 100 is in a restricted state. In the embodiment of the present application, the charging pile 200 can generate a charging instruction based on the received remaining available power and the remaining available target power. In some specific examples, the charging pile 200 can perform PI adjustment on the remaining available power and the remaining available target power to obtain a charging instruction.
[0108] S500: When the remaining available target power is a first power value, enable the charging pile to obtain a first charging power from the power grid according to a charging instruction.
[0109] In this way, when the inverter 100 detects that the charging pile 200 obtains the first charging power from the power grid 40 through the grid-connected output port, the inverter 100 increases the output power of the inverter 100, thereby increasing the power obtained by the charging pile 200 from the photovoltaic module 20 through the inverter 100. The first charging power is the first power value.
[0110] In the embodiment of the present application, the control method applied to the charging pile 200 can be executed by a control device in the charging pile 200, such as a microcontroller unit (MCU) or a digital signal processor (DSP) in the charging pile 200.
[0111] It can be understood that in the embodiment of the present application, the charging pile 200 can repeatedly execute steps S300 to S400 to gradually increase the output power of the inverter 100, and then gradually increase the power obtained by the charging pile 200 from the photovoltaic component 20 through the inverter 100 until the power output of the photovoltaic component 20 reaches a maximum.
[0112] In some embodiments, the control method may further include: receiving the remaining available target power sent by the inverter 100. The remaining available target power is set to the first power value by the inverter 100 when the grid-connected output port is in a restricted state. It is understood that the charging pile 200 can receive the remaining available target power and the remaining available power sent by the inverter 100 at the same time.
[0113] Furthermore, the control method may further include: receiving a remaining available target power of zero sent by the inverter 100 .
[0114] Among them, when the output power of the inverter 100 remains stable within a preset time period and the charging pile 200 continues to obtain the first charging power from the power grid 40, the inverter 100 sets the remaining available target power to zero and sends it to the charging pile 200.
[0115] When the remaining available target power is zero, the charging pile 200 generates a charging instruction according to the remaining available power and the remaining available target power of zero, and according to the charging instruction, the charging pile 200 stops obtaining power from the power grid 40 and only obtains power from the inverter 100.
[0116] In this embodiment, when the grid-connected output port is in an unrestricted state, the inverter 100 sets the remaining available target power to zero. Correspondingly, the control method may further include: receiving the remaining available target power of zero sent by the inverter 100 .
[0117] When the grid-connected output port is in an unrestricted state, the charging pile 200 receives the remaining available target power of zero sent by the inverter 100, and the charging pile 200 generates a charging instruction based on the current remaining available power and the remaining available target power, and adjusts the charging power of the charging pile 200 to the target device according to the charging instruction until the remaining available power is zero.
[0118] In some other embodiments, the control method may further include: receiving limited state information sent by the inverter 100, and setting the remaining available target power to the first power value according to the limited state information.
[0119] At this time, the remaining available target power is a parameter built into the charging pile 200 , and the charging pile 200 sets the remaining available target power to the first power value when receiving the limited state information from the inverter 100 .
[0120] Furthermore, the control method may further include: receiving output stability information sent by the inverter 100, and setting the remaining available target power to zero according to the output stability information.
[0121] At this time, the charging pile 200 sets the remaining available target power to zero according to the output stability information sent by the inverter 100, and then generates a charging instruction according to the remaining available power and the remaining available target power of zero, and according to the charging instruction, the charging pile 200 stops obtaining power from the power grid 40 and only obtains power from the inverter 100.
[0122] In this embodiment, when the grid-connected output port is in an unrestricted state, the inverter 100 sends unrestricted state information to the charging pile 200. Correspondingly, the control method may further include: receiving the unrestricted state information sent by the inverter 100, and setting the remaining available target power to zero according to the unrestricted state information.
[0123] When the grid-connected output port is in an unrestricted state, the charging pile 200 generates a charging instruction according to the remaining available power and the remaining available target power of zero, and adjusts the charging power of the charging pile 200 to the target device according to the charging instruction until the remaining available power is zero.
[0124] In some embodiments, the charging pile may be an AC charging pile. Correspondingly, step S500 may include: sending a charging instruction to a target device, so that the target device increases the charging power according to the charging instruction, thereby enabling the charging pile 200 to obtain the first charging power from the power grid 40 .
[0125] The target device adjusts the charging power obtained from the charging pile 200 according to the charging instruction. Since the remaining available target power is the first power value, the charging pile 200 needs to obtain the first charging power (first power value) from the power grid 40 through the grid-connected output port to meet the charging needs of the target device.
[0126] Of course, the charging pile 200 of the present application may also be a DC charging pile. In this case, the charging pile 200 may directly obtain the first charging power from the power grid 40 through the grid-connected output port according to the charging instruction.
[0127] like Figure 6 As shown, in some embodiments, Figure 5 Step S400 in may include:
[0128] S410: Obtain a first deviation value according to the remaining available power received in the current cycle and the remaining available target power.
[0129] It is understandable that the charging pile 200 can receive the remaining available power sent by the inverter 100 at a preset period. The charging pile 200 obtains the first deviation value based on the remaining available power received in the current period and the remaining available target power. Among them, the remaining available power in the current period is Pev (n), the remaining available target power in the current period is Pref (n), and the first deviation value is Pev (n) - Pref (n).
[0130] S420: Obtain a second deviation value according to the remaining available power received in the previous cycle and the remaining available target power.
[0131] It can be understood that in the current cycle, the remaining available power and the remaining available target power of the previous cycle can be stored in the charging pile 200, so that the charging pile 200 can obtain the second deviation value. It can be understood that since the first deviation value of the current cycle is calculated in each cycle, the second deviation value is the first deviation value of the previous cycle. Specifically, the remaining available power of the previous cycle is Pev (n-1), the remaining available target power of the previous cycle is Pref (n-1), and the second deviation value is Pev (n-1) - Pref (n-1).
[0132] S430, generating a charging instruction corresponding to the current cycle according to the first deviation value, the second deviation value and the charging instruction generated in the previous cycle.
[0133] The charging pile 200 generates a charging instruction corresponding to the current cycle according to the first deviation value, the second deviation value and the charging instruction generated in the previous cycle.
[0134] Specifically, if Figure 7 As shown, step S430 may include:
[0135] S431. Obtain a first compensation value according to a product of a first deviation value and a first preset parameter.
[0136] The first preset parameter is a preset control parameter. If the first preset parameter is kp, the first compensation value is: kp*[Pev(n)-Pref(n)].
[0137] S432: Obtain a second compensation value according to the product of the second deviation value and the second preset parameter.
[0138] The second preset parameter is a preset control parameter. If the second preset parameter is ki, the second compensation value is: ki*[Pev(n-1)-Pref(n-1)].
[0139] S433, obtaining a charging instruction corresponding to the current cycle according to the sum of the first compensation value, the second compensation value, and the charging instruction corresponding to the previous cycle.
[0140] The charging instruction of the previous cycle is Pwm (n-1), and the charging instruction of the current cycle is Pwm (n). Then, the charging instruction of the current cycle can be obtained as follows:
[0141] Pwm(n)=kp*[Pev(n)-Pref(n)]+ki*[Pev(n-1)-Pref(n-1)]+ Pwm(n-1);
[0142] It is understood that the charging instruction can be a control signal for controlling the operation of the charging circuit in the target device, such as a PWM control signal. The target device controls the operation of the charging circuit through the charging instruction, thereby controlling the charging circuit in the target device to obtain the corresponding charging power from the charging pile 200.
[0143] In the embodiment of the present application, the target device may be a new energy vehicle, that is, the charging pile 200 may charge the new energy vehicle. The charging pile 200 may send a charging instruction to the charging system of the new energy vehicle, and the charging system controls the new energy vehicle to charge according to the charging instruction, so that the new energy vehicle obtains the corresponding charging power from the charging pile 200 according to the charging instruction.
[0144] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present application and are not intended to limit them. In the actual application process, the entire content of the technical solutions described in any embodiment of the present application can be implemented, or some content can be added, or some content can be deleted, or some content can be changed / replaced. Although the present application is described in detail with reference to the preferred embodiments, it should be understood by those of ordinary skill in the art that the technical solutions of the present application can be modified or replaced by equivalents without departing from the spirit and scope of the technical solutions of the present application.
Claims
1. An energy storage charging system, characterized in that: Including inverter, charging pile and energy storage battery; The DC input terminal of the inverter is used to connect to a photovoltaic module; The battery connection end of the inverter is used to connect the energy storage battery, the off-grid output port and the grid-connected output port of the inverter are both used to connect the charging pile and the load, and the grid-connected output port is used to connect the power grid; the inverter and the charging pile communicate with each other; Wherein, when the inverter is in a grid-connected state, the inverter determines the remaining available power according to the port power of the grid-connected output port and the charge and discharge information of the energy storage battery; wherein, the remaining available power at least includes the power that the photovoltaic module can additionally provide to the charging pile through the inverter; The inverter sends the remaining available power to the charging pile; The charging pile adjusts the charging power of the charging pile to the target device according to the remaining available power and the remaining available target power; when the grid-connected output port is in a restricted state, the remaining available target power is a first power value, and the charging pile obtains a first charging power from the grid according to the remaining available power and the remaining available target power, and the first charging power is the first power value; the restricted state means that the power output by the inverter to the grid through the grid-connected output port is limited; When the inverter detects that the charging pile obtains the first charging power from the power grid, the inverter increases its output power, thereby increasing the power obtained by the charging pile from the photovoltaic component through the inverter.
2. The energy storage charging system according to claim 1, characterized in that: The inverter is also used for: In response to the grid-connected output port being in a restricted state, the inverter sets the remaining available target power to the first power value, and sends the remaining available target power to the charging pile; Alternatively, the inverter is further used to: when the grid-connected output port is in a restricted state, send restricted state information to the charging pile; the charging pile receives the restricted state information and sets the remaining available target power to the first power value according to the restricted state information.
3. The energy storage charging system according to claim 2, characterized in that: When the output power of the inverter remains stable within a preset time period and the charging pile obtains the first charging power from the power grid, the inverter or the charging pile sets the remaining available target power to zero so that the charging pile stops obtaining power from the power grid.
4. The energy storage charging system according to claim 1, characterized in that: The inverter is also used for: In response to the grid-connected output port being in an unrestricted state, setting the remaining available target power to zero, and sending the remaining available target power to the charging pile; Alternatively, the inverter is further configured to: when the grid-connected output port is in an unrestricted state, send unrestricted state information to the charging pile; the charging pile receives the unrestricted state information, and sets the remaining available target power to zero according to the unrestricted state information; When the remaining available target power is zero, the charging pile adjusts the charging power of the charging pile to the target device according to the charging instruction generated by the remaining available power and the remaining available target power until the remaining available power is zero.
5. The energy storage charging system according to claim 1, characterized in that: The charging and discharging information includes battery information and battery power of the energy storage battery; The inverter is also used for: When the battery information indicates that the energy storage battery does not meet the discharge condition, the remaining available power is the port power; When the battery information indicates that the energy storage battery is ready for discharge, the remaining available power is the sum of the port power and the battery power.
6. The energy storage charging system according to any one of claims 1 to 5, characterized in that: The charging pile is used for: receiving the remaining available power sent by the inverter; generating a charging instruction according to the remaining available power and the remaining available target power; When the remaining available target power is the first power value, the charging pile is enabled to obtain the first charging power from the grid-connected output port according to the charging instruction.
7. The energy storage charging system according to claim 6, characterized in that: The charging pile is also used for: Obtaining a first deviation value according to the remaining available power received in the current cycle and the remaining available target power; Obtaining a second deviation value according to the remaining available power received in a previous cycle and the remaining available target power; The charging instruction corresponding to the current cycle is generated according to the first deviation value, the second deviation value and the charging instruction generated in the previous cycle.
8. The energy storage charging system according to claim 7, characterized in that: The charging pile is also used for: Obtaining a first compensation value according to the product of the first deviation value and a first preset parameter; Obtaining a second compensation value according to the product of the second deviation value and a second preset parameter; wherein the first preset parameter and the second preset parameter are preset control parameters; The charging instruction corresponding to the current cycle is obtained according to the sum of the first compensation value, the second compensation value and the charging instruction corresponding to the previous cycle.
9. A control method, characterized in that: Applied to an inverter, the control method includes: When the inverter is in a grid-connected state, obtaining the port power of the grid-connected output port of the inverter and the charging and discharging information of the energy storage battery; Determine the remaining available power according to the port power and the charging and discharging information; wherein the remaining available power at least includes the power that the photovoltaic component can additionally provide to the charging pile through the inverter; The remaining available power is sent to the charging pile, so that the charging pile can adjust the charging power of the charging pile to the target device according to the remaining available power and the remaining available target power; wherein, when the grid-connected output port is in a restricted state, the remaining available target power is a first power value, and the charging pile obtains a first charging power from the grid according to the remaining available power and the remaining available target power, and the first charging power is the first power value; the restricted state means that the power output by the inverter to the grid through the grid-connected output port is limited; When it is detected that the charging pile obtains the first charging power from the power grid, the inverter is controlled to increase the output power, thereby increasing the power obtained by the charging pile from the photovoltaic component through the inverter.
10. The control method according to claim 9, characterized in that: The control method further comprises: In response to the grid-connected output port being in a restricted state, setting the remaining available target power to the first power value, and sending the remaining available target power to the charging pile; Alternatively, when the grid-connected output port is in a restricted state, restricted state information is sent to the charging pile; the restricted state information is used to trigger the charging pile to set the remaining available target power to the first power value.
11. The control method according to claim 10, characterized in that: The control method further comprises: When the output power of the inverter remains stable within a preset time and the charging pile obtains the first charging power from the power grid, the remaining available target power is set to zero and sent to the charging pile, so that the charging pile stops obtaining power from the power grid; Alternatively, when the output power of the inverter remains stable within a preset time period and the charging pile obtains the first charging power from the power grid, output stability information is sent to the charging pile; the output stability information is used to trigger the charging pile to set the remaining available target power to zero.
12. The control method according to claim 9, characterized in that: The control method further comprises: In response to the grid-connected output port being in an unrestricted state, setting the remaining available target power to zero, and sending the remaining available target power to the charging pile; Alternatively, when the grid-connected output port is in an unrestricted state, unrestricted state information is sent to the charging pile; the unrestricted state information is used to trigger the charging pile to set the remaining available target power to zero; Among them, when the remaining available target power is zero, the charging pile outputs the corresponding charging power to the target device according to the remaining available power and the remaining available target power until the remaining available power is zero.
13. The control method according to any one of claims 9 to 12, characterized in that: The charging and discharging information includes battery information and battery power of the energy storage battery; The determining the remaining available power according to the port power and the charge and discharge information includes: When the battery information indicates that the energy storage battery does not meet the discharge condition, the remaining available power is the port power; When the battery information indicates that the energy storage battery is ready for discharge, the remaining available power is the sum of the port power and the battery power.
14. A control method, characterized in that: Applied to charging piles, the control method is used to: Receive the remaining available power sent by the inverter; the remaining available power is determined by the inverter according to the port power of its grid-connected output port and the charging and discharging information of the energy storage battery, and the remaining available power at least includes the power that the photovoltaic module can additionally provide to the charging pile through the inverter; Generate a charging instruction according to the remaining available power and the remaining available target power; wherein, when the grid-connected output port is in a restricted state, the remaining available target power is a first power value; the restricted state means that the power outputted by the inverter to the grid through the grid-connected output port is restricted; When the remaining available target power is the first power value, the charging pile obtains the first charging power from the power grid according to the charging instruction, so that the inverter increases its output power when detecting that the charging pile obtains the first charging power from the power grid, thereby increasing the power obtained by the charging pile from the photovoltaic component through the inverter; the first charging power is the first power value.
15. The control method according to claim 14, characterized in that: The control method further comprises: receiving the remaining available target power sent by the inverter, wherein the remaining available target power is set by the inverter to the first power value when the grid-connected output port is in a restricted state; Alternatively, limited state information sent by the inverter is received, and the remaining available target power is set to the first power value according to the limited state information.
16. The control method according to claim 15, characterized in that: The control method further comprises: receiving the remaining available target power of zero sent by the inverter; when the output power of the inverter remains stable within a preset time and the charging pile obtains the first charging power from the power grid, the inverter sets the remaining available target power to zero; Alternatively, the output stability information sent by the inverter is received, and the remaining available target power is set to zero according to the output stability information; when the output power of the inverter remains stable within a preset time period and the charging pile obtains the first charging power from the power grid, the inverter sends the output stability information to the charging pile.
17. The control method according to claim 14, characterized in that: The control method further comprises: receiving the remaining available target power of zero sent by the inverter; or receiving the unrestricted state information sent by the inverter, and setting the remaining available target power to zero according to the unrestricted state information; When the remaining available target power is zero, adjusting the charging power of the charging pile to the target device according to the charging instruction generated by the remaining available power and the remaining available target power until the remaining available power is zero; Wherein, when the grid-connected output port is in an unrestricted state, the inverter sets the remaining available target power to zero.
18. The control method according to claim 14, characterized in that: The charging pile is an AC charging pile. Correspondingly, the step of enabling the charging pile to obtain a first charging power from the power grid according to the charging instruction includes: The charging instruction is sent to the target device, so that the target device increases the charging power according to the charging instruction, thereby enabling the charging pile to obtain the first charging power from the power grid.
19. The control method according to any one of claims 14 to 18, characterized in that: The generating a charging instruction according to the remaining available power and the remaining available target power includes: Obtaining a first deviation value according to the remaining available power received in the current cycle and the remaining available target power; Obtaining a second deviation value according to the remaining available power received in a previous cycle and the remaining available target power; The charging instruction corresponding to the current cycle is generated according to the first deviation value, the second deviation value and the charging instruction generated in the previous cycle.
20. The control method according to claim 19, characterized in that: The step of generating the charging instruction corresponding to the current cycle according to the first deviation value, the second deviation value, and the charging instruction generated in the previous cycle includes: Obtaining a first compensation value according to the product of the first deviation value and a first preset parameter; Obtaining a second compensation value according to the product of the second deviation value and a second preset parameter; wherein the first preset parameter and the second preset parameter are preset control parameters; The charging instruction corresponding to the current cycle is obtained according to the sum of the first compensation value, the second compensation value and the charging instruction corresponding to the previous cycle.