A power supply station monitoring and management method and system based on operation map

Through the power supply station monitoring and management method based on the operation map, the problem of failure to complete the repair work on time during daily maintenance of working cables is solved, the maintenance efficiency and rationality are improved, and the timely response of the maintenance team and the control of work progress are ensured.

CN118469244BActive Publication Date: 2024-10-18STATE GRID ZHEJIANG ELECTRIC POWER CO LTD NINGBO POWER SUPPLY CO
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410910027.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-07-09
Publication Date
2024-10-18
Estimated Expiration
2044-07-09

AI Technical Summary

Technical Problem

In power grid operation monitoring, it is difficult to ensure orderly maintenance during daily maintenance of working cables, resulting in maintenance work not being completed on time and affecting maintenance efficiency and progress control.

Method used

The power supply station monitoring and management method based on the operation map is adopted to periodically obtain the loss of working cables in the power grid company, screen the cables to be maintained, calculate the maintenance time limit, plan the maintenance route, and adjust the maintenance team and planned maintenance points in emergency situations. Count missed maintenance points to adjust the progress of subsequent work.

Benefits of technology

It improves the efficiency and rationality of maintenance work, ensures that the maintenance team can respond to emergencies in a timely manner, reasonably allocates work intensity, reduces the risk of cable failure to be maintained, and optimizes maintenance routes and the driving distance of the maintenance team.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118469244B_ABST
    Figure CN118469244B_ABST
Patent Text Reader

Abstract

The present invention relates to the technical field of power grid operation monitoring, and in particular to a power supply station monitoring management method and system based on an operation map. The present invention solves the problem of how to smoothly complete the maintenance work while ensuring that the maintenance work is carried out in an orderly manner. To solve the above problem, the present invention provides a management method, including: screening working cables according to loss values ​​to obtain cables to be maintained, determining target maintenance points of a target area within a current cycle according to the cables to be maintained, sorting the target maintenance points according to maintenance time limits, allocating planned maintenance points to various maintenance starting points according to an operation map, and planning maintenance routes; when a working cable needs emergency maintenance during a working day, determining a maintenance team according to the positions of various maintenance teams, and adjusting the planned maintenance points for the working day; when no working cable needs emergency maintenance during a working day, statistics are collected on the completion of the planned maintenance points after the end of the working day.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of power grid operation monitoring, and in particular to a method and system for monitoring and managing a power supply station based on an operation map. Background Art

[0002] The operation monitoring center of the power grid company is a vital operation management department of the power supply company, and is responsible for monitoring the operation status, power load, fault conditions, etc. of the power grid equipment. Once an abnormal situation is found, the staff of the operation monitoring center needs to make judgments and handle it in time. In order to ensure the stable operation of the power system and meet the electricity demand of the society, the working cables need to be maintained regularly to reduce the risk of failure of the working cables.

[0003] Normally, the maintenance cycle of the working cable is based on the line loss value as a reference. When the change in the line loss value reaches the maintenance requirements, the power grid company needs to send corresponding maintenance personnel to maintain the working cables. With the development of urban areas, the number of working cables in urban areas is increasing, and the workload of cable maintenance is also increasing. Therefore, how to reasonably sort out the maintenance work is the key to improving maintenance efficiency. At the same time, in the process of daily maintenance, there may be situations where the working cables fail, and the maintenance work needs to be interrupted to give priority to the repair work. After the maintenance work is completed, the maintenance work often cannot be completed on time, which will cause the work progress of some maintenance teams to be chaotic and difficult to control. Therefore, how to deal with sudden maintenance work in the process of daily maintenance is one of the problems that technical personnel in this field urgently need to solve. Summary of the invention

[0004] The problem solved by the present invention is: during the routine maintenance of a working cable, how to ensure that the maintenance work is carried out in an orderly manner and complete the maintenance work smoothly.

[0005] To solve the above problems, an embodiment of the present invention provides a power supply station monitoring and management method based on an operation map, the management method comprising: periodically obtaining the working cable loss situation of the power grid company within the operation range, and recording the line loss value of each working cable; screening the working cables according to the loss value to obtain the cables to be maintained, and calculating the maintenance time limit of the cables to be maintained; determining the target maintenance points of the target area in the current cycle according to the cables to be maintained, sorting the target maintenance points according to the maintenance time limit, and obtaining the planned maintenance points for each working day; obtaining the maintenance starting point in the target area and the number of maintenance teams corresponding to each maintenance starting point, allocating the planned maintenance points to each maintenance starting point according to the operation map, and planning the maintenance route; when the working cable needs emergency repair during the working day, determining the maintenance team according to the location of each maintenance team, and adjusting the planned maintenance points for the working day; when the working cable does not need emergency repair during the working day, counting the completion of the planned maintenance points after the end of the working day, and recording the unfinished planned maintenance points as missed maintenance points; counting the number of missed maintenance points corresponding to each maintenance starting point, and adjusting the allocation of subsequent planned maintenance points according to the number of missed maintenance points.

[0006] Compared with the existing technology, the technical effects achieved by adopting this technical solution are as follows: the acquisition of line loss values ​​can timely obtain the loss status of each working cable within the operating scope, the screening of cables to be maintained can clarify the objects that the power grid company needs to maintain, and the acquisition of maintenance time limits can provide a reference standard for the maintenance sequence of cables to be maintained, making the maintenance work more reasonable. The planning of maintenance routes allows the power grid company to shorten the driving distance of each maintenance team based on the operation map, thereby improving the maintenance efficiency of the maintenance work. The screening of maintenance teams allows the maintenance teams to respond to sudden maintenance events in a timely manner during the maintenance work, and the adjustment of planned maintenance points also makes the overall work intensity of the maintenance team more reasonable. The statistics of missed maintenance points can count the work progress of each maintenance team on each working day, and adjust the work progress of subsequent working days according to the overall workload.

[0007] In one embodiment of the present invention, working cables are screened according to loss values ​​to obtain cables to be maintained, and the maintenance time limit of the cables to be maintained is calculated, specifically including: calculating the basic loss rate in the target area through the working cables newly installed within the past year, and correcting the basic loss rate according to the working years of the working cables and the number of repairs of the working cables to obtain the theoretical loss rate; calculating the loss threshold according to the theoretical loss rate and the time length of the current cycle; when the loss change value is greater than or equal to the loss threshold, marking the working cable as a cable to be maintained, and calculating the actual loss rate of the cable to be maintained according to the loss change value, and determining the maintenance time limit of the cable to be maintained according to the actual loss rate.

[0008] Compared with the existing technology, the technical effect achieved by adopting this technical solution is as follows: by calculating the basic loss rate of the working cables newly installed within the past year, the basic loss conditions of each working cable in the target area can be obtained, so that the basic loss rate is more in line with the working environment of the working cable. The calculation of the theoretical loss rate fully considers the damage and aging of the working cable itself, further improving the accuracy of the loss threshold. The calculation of the actual loss rate makes the maintenance time limit more reasonable, reduces the risk of failure of the cables to be maintained, and provides sufficient time for the reasonable arrangement of maintenance work.

[0009] In one embodiment of the present invention, maintenance starting points in a target area and the number of maintenance teams corresponding to each maintenance starting point are obtained, planned maintenance points are allocated to each maintenance starting point according to an operation map, and a maintenance route is planned, specifically including: determining the allocation weight of each maintenance starting point according to the number of maintenance teams, and calculating the initial travel time from each planned maintenance point to each maintenance starting point; selecting initial maintenance points with the same number of maintenance teams according to the maintenance travel time for each maintenance starting point; recording unselected planned maintenance points as subsequent maintenance points, and calculating the subsequent travel time between each subsequent maintenance point and each initial maintenance point; determining the subsequent maintenance point of each initial maintenance point according to the subsequent travel time, until each subsequent maintenance point corresponds to the initial maintenance point, forming an initial route of a working day with each initial maintenance point; counting the unit maintenance time of each initial route, and correcting the initial route according to the unit maintenance time and the allocation weight to obtain a maintenance route.

[0010] Compared with the prior art, the technical effects achieved by adopting this technical solution are as follows: the setting of the initial driving time enables each maintenance starting point to select the best initial maintenance point; the setting of subsequent maintenance points enables the initial route to be planned based on the initial maintenance point, thereby improving the rationality of route planning; the acquisition of unit maintenance time can correct the allocation method of the initial route, thereby achieving a reasonable allocation of multiple maintenance starting points and improving the efficiency of executing maintenance work.

[0011] In one embodiment of the present invention, the unit maintenance time of each initial route is counted, and the initial route is corrected according to the unit maintenance time and the allocation ratio to obtain the maintenance route, specifically including: calculating the adjustable number of each maintenance starting point according to the number of tasks and the allocation ratio; calculating the average maintenance time of all initial routes in a working day, and calculating the actual adjustment number according to the average maintenance time and the unit maintenance time; adjusting the allocation method of the planned maintenance points according to the adjustable number and the actual adjustment number, and determining the maintenance route of the working day according to the adjusted allocation plan.

[0012] Compared with the existing technology, the technical effects achieved by adopting this technical solution are: the acquisition of adjustable quantities can obtain the unreasonableness of the initial route division, the calculation of the average maintenance time and the unit maintenance time can make the actual adjustment quantity more in line with the actual maintenance situation, and balance the workload of each maintenance team while ensuring the maintenance efficiency. The planning of the maintenance route can make it more convenient for the maintenance team to perform maintenance tasks.

[0013] In one embodiment of the present invention, when a working cable needs emergency repair during a working day, a maintenance team is determined according to the location of each maintenance team, and the planned maintenance points of the working day are adjusted, specifically including: marking the location of the working cable as an emergency repair point, and calculating the maintenance travel time of each maintenance team to reach the emergency repair point; the maintenance team includes an emergency team and a reserve team, the emergency team and the reserve team are screened out according to the maintenance travel time, and the emergency team is notified to go to the emergency repair point; when the emergency team arrives at the emergency repair point, it is determined whether additional maintenance personnel are needed based on the damage of the emergency repair point; if so, the reserve team is notified to go to the emergency repair point, and after the maintenance at the emergency repair point is completed, the emergency team and the reserve team each return to the corresponding planned maintenance point; after the end of the working day, the unfinished planned maintenance points are marked as postponed maintenance points, and the planned maintenance points of the next day are adjusted according to the number of postponed maintenance points; if not, the emergency team returns to the planned maintenance point after the maintenance at the emergency repair point is completed.

[0014] Compared with the existing technology, the technical effect achieved by adopting this technical solution is as follows: the selection of the emergency team can start the maintenance work as soon as possible after obtaining the location of the emergency maintenance point, reducing the losses caused by the failure of the working cable; the selection of the reserve team can provide timely support to the emergency team when complex situations arise at the maintenance site, further improving the efficiency of maintenance, postponing the marking of maintenance points, so that the maintenance work delayed by maintenance work can be shared by multiple maintenance starting points, avoiding the emergency team from having to bear too much maintenance work due to the maintenance work.

[0015] In one embodiment of the present invention, after the end of a working day, the unfinished planned maintenance points are marked as deferred maintenance points, and the planned maintenance points for the next day are adjusted according to the number of deferred maintenance points, specifically including: obtaining the maintenance routes corresponding to each maintenance starting point of the next day, and calculating the travel change time of each maintenance route after the deferred maintenance point is inserted into the maintenance route; determining the maintenance route where the deferred maintenance point needs to be inserted according to the travel change time.

[0016] Compared with the existing technology, the technical effect achieved by adopting this technical solution is as follows: the calculation of the driving change time can obtain the impact of postponing the maintenance point on each maintenance route. By selecting the appropriate maintenance route and setting the appropriate maintenance sequence, the efficiency of the maintenance work is improved, and the impact caused by the maintenance work can also be alleviated.

[0017] In one embodiment of the present invention, the number of missed maintenance points corresponding to each maintenance starting point is counted, and the allocation of subsequent planned maintenance points is adjusted according to the number of missed maintenance points, specifically including: obtaining the maintenance time limit and the number of missed days of the missed maintenance points, and determining the urgency of the missed maintenance points according to the number of missed days and the maintenance time limit; limiting the maintenance sequence of the missed maintenance points according to the urgency, and formulating a maintenance route according to the maintenance sequence.

[0018] Compared with the existing technology, the technical effect achieved by adopting this technical solution is as follows: the calculation of the urgency can obtain the impact of the postponement of the missed maintenance points, and the limitation of the maintenance sequence can ensure that the missed maintenance points can be completed within the maintenance time limit, so that the maintenance work can be completed smoothly.

[0019] In one embodiment of the present invention, the maintenance order of the missed maintenance point is limited according to the urgency, and the maintenance route is formulated according to the maintenance order, which specifically includes: obtaining the limited distance between the maintenance starting point and the missed maintenance point, and when the maintenance order of the missed maintenance point is the first, the missed maintenance point is used as the initial maintenance point; when the maintenance order of the missed maintenance point is not the first, the number to be adjusted before the missed maintenance point is obtained, and the order of the missed maintenance point as the subsequent maintenance point is determined according to the number to be adjusted.

[0020] Compared with the existing technology, the technical effect achieved by adopting this technical solution is as follows: the acquisition of the number to be adjusted can ensure that the missed maintenance points can be maintained smoothly, while limited maintenance can be performed on the planned maintenance points between the missed maintenance points and the maintenance starting point, shortening the formation distance of the entire maintenance work and improving the maintenance efficiency of the maintenance work.

[0021] In one embodiment of the present invention, the present invention also provides a power supply station monitoring and management system based on an operation map. The management method as described in the above embodiment is applied to the management system. The management system includes: a storage module, which is used to store the line loss value of each working cable in the target area; a calculation module, which is used to calculate the maintenance time limit of the cable to be maintained; a planning module, which is used to plan the maintenance route; and a sending module, which is used to send information to the maintenance team that the working cable needs urgent repair. The management system has all the technical features of the above management method, which will not be repeated here one by one. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] Figure 1 This is one of the flow charts of the power grid operation monitoring and management method of the present invention;

[0023] Figure 2 This is the second flow chart of the power grid operation monitoring and management method of the present invention;

[0024] Figure 3 This is the third flow chart of the power grid operation monitoring and management method of the present invention;

[0025] Figure 4 This is the fourth flow chart of the power grid operation monitoring and management method of the present invention;

[0026] Figure 5 It is a system schematic diagram of the power grid operation monitoring and management system of the present invention.

[0027] Description of reference numerals:

[0028] 100 - management system; 110 - storage module; 120 - calculation module; 130 - planning module; 140 - sending module. DETAILED DESCRIPTION

[0029] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, specific embodiments of the present invention are described in detail below with reference to the accompanying drawings.

[0030] [First embodiment]

[0031] See also Figure 1 In a specific embodiment, the present invention provides a power supply station monitoring and management method based on an operation map, the management method comprising:

[0032] S100, periodically obtain the working cable loss situation of the power grid company within the operating range, and record the line loss value of each working cable;

[0033] S200, screening the working cables according to the loss values ​​to obtain the cables to be maintained, and calculating the maintenance time limit of the cables to be maintained;

[0034] S300, determining the target maintenance points of the target area in the current cycle according to the cables to be maintained, sorting the target maintenance points according to the maintenance time limit, and obtaining the planned maintenance points for each working day;

[0035] S400, obtaining maintenance starting points in the target area and the number of maintenance teams corresponding to each maintenance starting point, allocating planned maintenance points to each maintenance starting point according to the operation map, and planning maintenance routes;

[0036] S500. When a working cable needs urgent repair during a working day, a maintenance team is determined according to the location of each maintenance team, and the planned maintenance points of the working day are adjusted;

[0037] S600, when no working cable needs emergency maintenance during the working day, the completion status of the planned maintenance points is counted after the working day ends, and the unfinished planned maintenance points are recorded as missed maintenance points;

[0038] S700: Count the number of missed maintenance points corresponding to each maintenance starting point, and adjust the allocation of subsequent planned maintenance points according to the number of missed maintenance points.

[0039] In step S100, the specific scope of the operating range is not limited, and it can be a small area such as a village or a town, or a large area of ​​the entire city. The period for obtaining the working cable loss situation is usually one week. After obtaining the line loss value of each working cable every month, the working cable that needs to be maintained in this working cycle is obtained according to the loss situation. The line loss value of the working cable is updated by manual measurement of the line loss value of each cable device after the end of each cycle. The line loss value is displayed as a percentage. For cable equipment that has just been installed, the line loss value is 0. For cable equipment that cannot work, the line loss value is 100%. The higher the line loss value, the higher the probability of failure of the working cable during work.

[0040] In step S200, whether the working cable is determined to be a cable to be maintained is determined based on the change in the line loss value during the working cycle. The cable to be maintained is only for the working cable that has not had any faults during the working cycle. The greater the change in the line loss value, the more unstable the working state of the cable to be maintained during the working cycle. Therefore, in order to avoid failure of the cable to be maintained, the maintenance period will be shortened accordingly.

[0041] In step S300, the working status of the cable to be maintained is detected and the specific location where maintenance work needs to be performed, namely the target maintenance point, is determined according to the abnormal voltage condition. In one working cycle, multiple target maintenance points will be obtained, and each target maintenance point will have a corresponding maintenance time limit. The power grid company needs to complete the maintenance work on these target maintenance points before the next working cycle is settled. In order to ensure that the maintenance work is carried out in an orderly manner, the maintenance work needs to be sorted out and the planned maintenance points for each working day need to be obtained.

[0042] In step S400, the maintenance starting point refers to the location of the team capable of performing maintenance work, which is usually the specific location of each power subsidiary in the target area. Multiple power subsidiaries are required to perform maintenance together within the operating scope of the power grid company. The number of maintenance teams at each maintenance starting point is also different. The planned maintenance points are allocated according to the number of maintenance teams and the location of the maintenance starting point, and the maintenance route is planned after the allocation is completed.

[0043] In step S500, emergency maintenance means that a working cable has a fault and maintenance work needs to be performed immediately. At this time, the maintenance work needs to be postponed and the maintenance work is performed first. After the maintenance work is completed, the maintenance work will continue. The maintenance team performing the maintenance work will be recorded as the maintenance team, and the planned maintenance points of subsequent working days will be adjusted according to the execution time of the maintenance work.

[0044] In step S600, in order to better manage the work progress of each maintenance team, when the maintenance team does not perform maintenance tasks, it is necessary to count the unfinished maintenance work of the maintenance team and consider the location of the missed maintenance points in the maintenance route of subsequent working days.

[0045] In step S700, the more the number of missed maintenance points is, the lower the corresponding allocation number of planned maintenance points will be. It is necessary to complete the missed maintenance points first, or allocate the missed maintenance points to other maintenance teams to avoid failure of the cables to be maintained due to untimely maintenance.

[0046] The acquisition of line loss values ​​can timely obtain the loss status of each working cable within the operating scope. The screening of cables to be maintained can clarify the objects that the power grid company needs to maintain. The acquisition of maintenance time limits can provide a reference standard for the maintenance order of cables to be maintained, making the maintenance work more reasonable. The planning of maintenance routes allows the power grid company to shorten the driving distance of each maintenance team based on the operation map, thereby improving the maintenance efficiency of maintenance work. The screening of maintenance teams allows the maintenance teams to respond to sudden maintenance events in a timely manner during maintenance work. The adjustment of planned maintenance points also makes the overall work intensity of the maintenance team more reasonable. The statistics of missed maintenance points can count the work progress of each maintenance team on each working day, and adjust the work progress of subsequent working days according to the overall workload.

[0047] [Second embodiment]

[0048] See also Figure 2 In a specific embodiment, the working cables are screened according to the loss values ​​to obtain the cables to be maintained, and the maintenance time limit of the cables to be maintained is calculated, which specifically includes:

[0049] S210, calculating the basic loss rate in the target area through the working cables newly installed in the past year, and correcting the basic loss rate according to the working years of the working cables and the number of maintenance times of the working cables to obtain a theoretical loss rate;

[0050] S220, calculating a loss threshold according to a theoretical loss rate and a duration of a current cycle;

[0051] S230. When the loss change value is greater than or equal to the loss threshold, mark the working cable as a cable to be maintained, calculate the actual loss rate of the cable to be maintained according to the loss change value, and determine the maintenance time limit of the cable to be maintained according to the actual loss rate.

[0052] In step S210, the loss change value is the difference between the line loss value of the working cable in the previous working cycle and the line loss value of the current working cycle. It should be noted that the loss change value is only for the working cable that has not undergone maintenance work. If the working cable has been repaired in the current working cycle, the loss change value that needs to be calculated is the difference between the completion of the maintenance and the end of the current working cycle.

[0053] Furthermore, different working cables have different loss thresholds. The basic loss rate in the target area is calculated by using the working cables newly installed within the past year. The first loss coefficient is obtained by the working years of the working cables. The second loss coefficient is obtained by the number of maintenance times of the working cables. The basic loss rate is corrected according to the first loss coefficient and the second loss coefficient to obtain the theoretical loss rate of the working cable. The loss threshold is calculated based on the theoretical loss rate and the length of the working cycle.

[0054] The working life of the working cable is a, the first loss coefficient is S1, and the first loss coefficient and the working life satisfy the following relationship:

[0055] When a≤2, S1=1;

[0056] When 2<T≤5, S1=1.05;

[0057] When T>5, S1=1.1.

[0058] The second loss coefficient is denoted as S2, the number of maintenance times of the working cable is denoted as b, and the second loss coefficient, the number of maintenance times and the working life satisfy the following relationship:

[0059] When b≤(a÷2)+1, S2=1;

[0060] When (a÷2)+1<b≤a+1, S2=1.05;

[0061] When b>a+1, S2=1.1.

[0062] The basic loss rate is V1, the theoretical loss rate is V2, and the basic loss rate and the theoretical loss rate satisfy the following relationship:

[0063] V2=V1×S1×S2.

[0064] In step S220, the time length of the current cycle is recorded as T1, the loss threshold is Y, and the Yunhao cycle and the theoretical loss rate satisfy the following relationship:

[0065] Y=T1×V2.

[0066] In step S230, when the loss change value is greater than the loss threshold, it indicates that the loss of the working cable in the current cycle is relatively serious, and it is marked as a cable to be maintained. The actual loss rate is obtained by dividing the loss change value by the time length T1. The maintenance time limit is T0, and the actual loss rate is V0. The maintenance time limit and the actual loss rate satisfy the following relationship:

[0067] T0=2Y÷V0-T1.

[0068] For example, T1=20 days, V0=0.02% / day, V2=0.015% / day, then Y=0.3%, T0=10 days. That is to say, under the current working environment, the cable to be maintained needs to be maintained within 10 days, otherwise the probability of failure of the cable to be maintained will be greatly increased.

[0069] By calculating the basic loss rate of the working cables newly installed within the past year, the basic loss conditions of each working cable in the target area can be obtained, making the basic loss rate more in line with the working environment of the working cables. The calculation of the theoretical loss rate fully considers the damage and aging of the working cables themselves, further improving the accuracy of the loss threshold. The calculation of the actual loss rate makes the maintenance time limit more reasonable, reduces the risk of failure of the cables to be maintained, and provides sufficient time for the reasonable arrangement of maintenance work.

[0070] [Third embodiment]

[0071] See also Figure 3 In a specific embodiment, the maintenance starting points in the target area and the number of maintenance teams corresponding to each maintenance starting point are obtained, the planned maintenance points are allocated to each maintenance starting point according to the operation map, and the maintenance route is planned, which specifically includes:

[0072] S410, determining the allocation proportion of each maintenance starting point according to the number of maintenance teams, and calculating the initial travel time from each planned maintenance point to each maintenance starting point;

[0073] S420, each maintenance starting point selects an initial maintenance point with the same number of maintenance teams according to the maintenance travel time, records the unselected planned maintenance points as subsequent maintenance points, and calculates the subsequent travel time between each subsequent maintenance point and each initial maintenance point;

[0074] S430, determining a subsequent maintenance point of each initial maintenance point according to the subsequent travel time, and until each subsequent maintenance point corresponds to the initial maintenance point, forming an initial route of the working day with each initial maintenance point;

[0075] S440: Count the unit maintenance time of each initial route, and modify the initial route according to the unit maintenance time and the allocation ratio to obtain a maintenance route.

[0076] In step S410, the more maintenance teams there are, the greater the corresponding allocation ratio is. The distance from each planned maintenance point to each maintenance starting point is calculated through the operation map, and then the congestion level of the driving road is estimated according to the expected departure time of the maintenance to calculate the initial driving time.

[0077] In step S420, different maintenance starting points have different maintenance teams, so the number of selected initial maintenance points is also different. Usually, the number of selected initial maintenance points is the same as the number of maintenance teams at the maintenance starting point.

[0078] Taking the selected initial maintenance point as a benchmark, the subsequent travel time between each subsequent maintenance point and the initial maintenance point is calculated. The calculation method of the subsequent travel time is the same as the calculation method of the initial travel time, which will not be repeated here.

[0079] In step S430, after a round of subsequent maintenance points is selected, the subsequent maintenance points selected in the previous round are used as a benchmark to continue selecting the remaining subsequent maintenance points until all planned maintenance points are assigned to corresponding initial maintenance points. When all initial maintenance points are selected, the initial route of the current working day is calculated based on the initial maintenance points.

[0080] In step S440, the unit maintenance time is the total driving time required for each initial route to reach each subsequent maintenance point in sequence from the initial maintenance point. If it is divided only according to the driving distance, it will result in too many planned maintenance points that need to be maintained at some maintenance starting points, resulting in reduced efficiency of maintenance work. Therefore, after the initial route is obtained, it needs to be adjusted according to the specific conditions of different maintenance starting points.

[0081] The setting of the initial driving time allows each maintenance starting point to select the best initial maintenance point. The setting of subsequent maintenance points allows the initial route to be planned based on the initial maintenance point, which improves the rationality of route planning. The acquisition of unit maintenance time can correct the allocation method of the initial route, realize the reasonable allocation of multiple maintenance starting points, and improve the efficiency of executing maintenance work.

[0082] [Fourth embodiment]

[0083] See also Figure 4 In a specific embodiment, the unit maintenance time of each initial route is counted, and the initial route is modified according to the unit maintenance time and the allocation ratio to obtain the maintenance route, which specifically includes:

[0084] S441, calculating the adjustable quantity of each maintenance starting point according to the number of tasks and the allocation ratio;

[0085] S442, calculating the average maintenance time of all initial routes on a working day, and calculating the actual adjustment quantity according to the average maintenance time and the unit maintenance time;

[0086] S443. Adjust the allocation method of the planned maintenance points according to the adjustable quantity and the actual adjusted quantity, and determine the maintenance route of the working day according to the adjusted allocation plan.

[0087] In step S441, the number of tasks is the number of planned maintenance points that need to be maintained on the current working day, and the allocation ratio is the average number of planned maintenance points required for each maintenance starting point. When there are different numbers of planned maintenance points on the corresponding initial routes from different maintenance starting points, the planned maintenance points are adjusted according to the location of the maintenance starting point.

[0088] The two maintenance starting points that need to be adjusted are recorded as adjustment starting points, and the quantity difference of the planned maintenance points between the two adjustment starting points is calculated to obtain the adjustable quantity.

[0089] In step S442, after the average maintenance time is obtained, the balance time is calculated based on the average maintenance time, the number of planned maintenance points and the number of maintenance starting points, and then the single average maintenance time of each adjustment starting point is calculated, and the actual adjustment quantity is calculated based on the single average maintenance time and the balance time.

[0090] For example, there are four maintenance starting points, each with a maintenance team. There are 16 planned maintenance points on the current working day. Since the allocation ratio is the same, each maintenance starting point should be allocated 4 planned maintenance points. At this time, according to the initial route, the planned maintenance points corresponding to the four maintenance starting points are 2, 4, 4 and 6 respectively. In order to avoid the maintenance team with 6 planned maintenance points being overloaded, the route needs to be adjusted.

[0091] In step S443, after the initial route is adjusted, the driving route on the working day is determined according to the planned maintenance points corresponding to each maintenance starting point to obtain a maintenance route.

[0092] The acquisition of adjustable quantities can reveal the unreasonableness of the initial route division, and the calculation of the average maintenance time and unit maintenance time can make the actual adjustment quantity more in line with the actual maintenance situation, while ensuring the maintenance efficiency and balancing the workload of each maintenance team. The planning of maintenance routes can make it more convenient for maintenance teams to perform maintenance tasks.

[0093] [Fifth embodiment]

[0094] In a specific embodiment, when a working cable needs urgent maintenance during a working day, a maintenance team is determined according to the location of each maintenance team, and the planned maintenance points of the working day are adjusted, specifically including:

[0095] S510, marking the location of the working cable as an emergency maintenance point, and calculating the maintenance travel time for each maintenance team to reach the emergency maintenance point;

[0096] S520: The maintenance team includes an emergency team and a reserve team. The emergency team and the reserve team are selected according to the maintenance travel time, and the emergency team is notified to go to the emergency maintenance point.

[0097] S530, when the emergency team arrives at the emergency repair point, it determines whether additional maintenance personnel are needed based on the damage condition of the emergency repair point;

[0098] S531. If yes, notify the reserve team to go to the emergency maintenance point. After the emergency maintenance point is repaired, the emergency team and the reserve team return to the corresponding planned maintenance point. After the working day is over, the unfinished planned maintenance point is marked as a deferred maintenance point, and the planned maintenance point of the next day is adjusted according to the number of deferred maintenance points.

[0099] S532. If not, the emergency team returns to the planned maintenance point after completing the maintenance at the emergency maintenance point.

[0100] In step S510, maintenance tasks may occur at any time during the work process, and the maintenance team needs to give priority to the maintenance tasks. When the coordinates of the emergency maintenance point are input into the system, the maintenance travel time for each maintenance team to reach the emergency maintenance point will be calculated immediately.

[0101] It should be noted that at this time, it is not possible to only calculate the distance between each maintenance team and the emergency repair point, because the locations of each maintenance team are different, the traffic congestion conditions are different, and the road conditions to the emergency repair point are also different. In order to ensure that the maintenance work is carried out as soon as possible, it is necessary to calculate the maintenance driving time in time according to the operation map.

[0102] In step S520, the team with the shortest maintenance travel time is recorded as the emergency team, and the team with the second shortest maintenance travel time is recorded as the reserve team. The emergency team stops maintenance work and goes directly to the emergency maintenance point. After receiving the maintenance notification, the maintenance team continues to perform maintenance work and is on standby.

[0103] In step S530 to step S532, after the emergency team arrives at the emergency maintenance point, they conduct a maintenance assessment based on the on-site conditions. If the maintenance is difficult, they immediately notify the reserve team to go to the emergency maintenance point. If the emergency team can complete the maintenance on their own, they return to the planned maintenance point after the maintenance is completed.

[0104] It should be noted that maintenance work will inevitably disrupt the original maintenance plan. Therefore, after performing the maintenance work, the number of postponed maintenance points is counted. The postponed maintenance points need to be arranged in the maintenance work of the next working day. That is, the number of planned maintenance points for the next working day is increased by a corresponding number and the maintenance route for the next working day is re-planned.

[0105] The selection of the emergency team can start the maintenance work as soon as possible after obtaining the location of the emergency maintenance point, reducing the losses caused by the working cable failure. The selection of the reserve team can provide timely support to the emergency team when complex situations arise at the maintenance site, further improving the efficiency of maintenance, delaying the marking of maintenance points, and allowing the maintenance work delayed by maintenance work to be shared by multiple maintenance starting points, avoiding excessive maintenance intensity caused by the emergency team's maintenance work.

[0106] [Sixth embodiment]

[0107] In a specific embodiment, after the working day ends, the unfinished planned maintenance points are marked as deferred maintenance points, and the planned maintenance points for the next day are adjusted according to the number of deferred maintenance points, specifically including:

[0108] S531a, obtaining the maintenance route corresponding to each maintenance starting point of the next day, and calculating the travel change time of each maintenance route after the delayed maintenance point is inserted into the maintenance route;

[0109] S531b, determining the maintenance route that needs to be inserted into the postponed maintenance point according to the driving change time.

[0110] In step S531a, the deferred maintenance point is inserted between any two planned maintenance points, and the driving change time after the insertion is calculated according to the operation map. For example, the driving time between two adjacent planned maintenance points is 20 minutes, and the time from the two planned maintenance points to the deferred maintenance point is 12 minutes and 15 minutes respectively. At this time, the driving change time after the insertion is 7 minutes.

[0111] In step S531b, after calculating the travel change time between any two planned maintenance points, the delayed maintenance point is inserted into the corresponding position of the maintenance route of the maintenance route with the shortest travel change time. It should be noted that after the delayed maintenance point is inserted, there is no need to correct the maintenance route again according to the adjustable number and the actual adjustment number, and the maintenance work can be directly performed according to the result after insertion.

[0112] The calculation of travel change time can reveal the impact of postponing maintenance points on each maintenance route. By selecting appropriate maintenance routes and setting appropriate maintenance sequences, the efficiency of maintenance work can be improved and the impact caused by maintenance work can be alleviated.

[0113] [Seventh embodiment]

[0114] In a specific embodiment, the number of missed maintenance points corresponding to each maintenance starting point is counted, and the allocation of subsequent planned maintenance points is adjusted according to the number of missed maintenance points, specifically including:

[0115] S710, obtaining the maintenance time limit and number of days for the missed maintenance point, and determining the urgency of the missed maintenance point according to the number of days for the missed maintenance and the maintenance time limit;

[0116] S720: Define the maintenance sequence of the missed maintenance points according to the urgency, and formulate a maintenance route according to the maintenance sequence.

[0117] In step S710, the maintenance work of the missed maintenance points is usually completed on the next working day after the maintenance task is performed. However, sometimes the missed maintenance points are missed continuously because the next day is a rest day or there is another maintenance task on the next day. Therefore, when the missed maintenance point needs to be inserted into the maintenance route for the second time, the urgency coefficient of the missed maintenance point needs to be calculated and the urgency is determined based on the urgency coefficient.

[0118] It should be noted that the postponement of maintenance points is caused by maintenance tasks, so the tasks can be shared by all maintenance teams, but the omission of maintenance points is caused by the maintenance team's own insufficient work efficiency, so they need to undertake the maintenance work themselves.

[0119] The number of missed days is T3, the urgency coefficient is D, and the urgency, maintenance deadline, and number of missed days satisfy the following relationship:

[0120] D = (T0-T3) ÷ T0;

[0121] When 0≤D≤20%, the urgency level is high;

[0122] When 20%<D≤60%, the urgency level is medium;

[0123] When D>60%, the urgency level is low.

[0124] In step S720, the higher the urgency, the higher the maintenance ranking. When the urgency is high, the maintenance ranking can only be limited to the first two digits. When the urgency is medium, the maintenance ranking can only be limited to the first five digits. When the urgency is low, the maintenance ranking is not limited.

[0125] The calculation of the urgency can determine the impact of missed maintenance points due to postponement. The limitation of maintenance sequence can ensure that the missed maintenance points can be completed within the maintenance time limit, so that the maintenance work can be completed smoothly.

[0126] [Eighth embodiment]

[0127] In a specific embodiment, the maintenance sequence of the missed maintenance points is limited according to the urgency, and a maintenance route is formulated according to the maintenance sequence, specifically including:

[0128] S721, obtaining a limited distance between the maintenance starting point and the missed maintenance point, and when the maintenance order of the missed maintenance point is first, taking the missed maintenance point as the initial maintenance point;

[0129] S722: When the maintenance ranking of the missed maintenance point is not the first, obtain the number of items to be adjusted before the missed maintenance point, and determine the ranking of the missed maintenance point as a subsequent maintenance point according to the number of items to be adjusted.

[0130] In step S721 and step S722, when the emergency coefficient D=0, the maintenance order of the missing maintenance point is first. When the emergency coefficients of multiple missing maintenance points are all 0, they are allocated to different maintenance starting points. At this time, the missing maintenance point is directly used as the initial maintenance point.

[0131] When the maintenance order of the missed maintenance point can be adjusted, determine the number of planned maintenance points that can be placed before the missed maintenance point, and record it as the number to be adjusted. If the maintenance order is limited to 3, it means that the number to be adjusted is 2. After the limited distance is obtained, calculate the adjustment distance of each planned point to the missed maintenance point, and select the planned maintenance points whose adjustment distance is less than the limited distance, and record them as adjusted maintenance points. Plan the maintenance route according to the distance from the adjusted maintenance point to the initial maintenance point.

[0132] The acquisition of the quantity to be adjusted can ensure that the missed maintenance points can be maintained smoothly, while limited maintenance can be performed on the planned maintenance points between the missed maintenance points and the maintenance starting point, shortening the formation distance of the entire maintenance work and improving the maintenance efficiency of the maintenance work.

[0133] [Ninth embodiment]

[0134] See also Figure 5 In a specific embodiment, the present invention also provides a power supply station monitoring and management system 100 based on an operation map. The management method described in the above embodiment is applied to the management system 100. The management system 100 includes: a storage module 110, the storage module 110 is used to store the line loss value of each working cable in the target area; a calculation module 120, the calculation module 120 is used to calculate the maintenance time limit of the cable to be maintained; a planning module 130, the planning module 130 is used to plan the maintenance route; a sending module 140, the sending module 140 is used to send information that the working cable needs urgent maintenance to the maintenance team. The management system 100 has all the technical features of the above management method, which will not be repeated here one by one.

[0135] Although the present invention is disclosed as above, the present invention is not limited thereto. Any person skilled in the art can make various changes and modifications without departing from the spirit and scope of the present invention. Therefore, the protection scope of the present invention shall be subject to the scope defined by the claims.

Claims

1. A power supply station monitoring and management method based on an operation map, characterized in that: The management method comprises: Periodically obtain the working cable loss information of the power grid company within the operating range, and record the line loss value of each working cable; Screening the working cables according to the line loss values ​​to obtain cables to be maintained, and calculating the maintenance time limit of the cables to be maintained; Determine the target maintenance points of the target area in the current cycle according to the cables to be maintained, sort the target maintenance points according to the maintenance time limit, and obtain the planned maintenance points for each working day; Obtaining the maintenance starting points in the target area and the number of maintenance teams corresponding to each maintenance starting point, allocating the planned maintenance points to each maintenance starting point according to the operation map, and planning the maintenance route; When the working cable needs urgent maintenance during the working day, the maintenance team is determined according to the location of each maintenance team, and the planned maintenance point of the working day is adjusted; The step of screening the working cables according to the line loss values ​​to obtain cables to be maintained, and calculating the maintenance time limit of the cables to be maintained specifically includes: Calculating the basic loss rate in the target area through the working cables newly installed in the last year, and correcting the basic loss rate according to the working years of the working cables and the number of maintenance times of the working cables to obtain a theoretical loss rate; Calculating a loss threshold according to the theoretical loss rate and the duration of the current cycle; When the loss change value is greater than or equal to the loss threshold, the working cable is marked as a cable to be maintained, and the actual loss rate of the cable to be maintained is calculated according to the loss change value, and the maintenance time limit of the cable to be maintained is determined according to the actual loss rate; The obtaining of the maintenance starting points in the target area and the number of maintenance teams corresponding to each maintenance starting point, allocating the planned maintenance points to each maintenance starting point according to the operation map, and planning the maintenance route specifically includes: Determine the allocation weight of each maintenance starting point according to the number of the maintenance teams, and calculate the initial travel time from each planned maintenance point to each maintenance starting point; Each of the maintenance starting points selects the same number of initial maintenance points as the maintenance teams according to the maintenance travel time; Recording the planned maintenance points that are not selected as subsequent maintenance points, and calculating the subsequent travel time between each of the subsequent maintenance points and each of the initial maintenance points; Determine a subsequent maintenance point of each of the initial maintenance points according to the subsequent travel time, and until each of the subsequent maintenance points corresponds to the initial maintenance point, an initial route of the working day is formed with each of the initial maintenance points; Counting the unit maintenance time of each of the initial routes, and modifying the initial routes according to the unit maintenance time and the allocation proportion to obtain the maintenance route; The counting of the unit maintenance time of each of the initial routes and correcting the initial routes according to the unit maintenance time and the allocation proportion to obtain the maintenance route specifically includes: Calculate the adjustable quantity of each maintenance starting point according to the number of tasks and the allocation ratio; Calculate the average maintenance duration of all the initial routes on the working day, and calculate the actual adjustment quantity according to the average maintenance duration and the unit maintenance duration; Adjusting the allocation method of the planned maintenance points according to the adjustable quantity and the actual adjusted quantity, and determining the maintenance route of the working day according to the adjusted allocation plan; When the working cable needs urgent maintenance during the working day, the maintenance team is determined according to the location of each maintenance team, and the planned maintenance point of the working day is adjusted, specifically including: Marking the location of the working cable as an emergency maintenance point, and calculating the maintenance travel time of each maintenance team to reach the emergency maintenance point; The maintenance team includes an emergency team and a reserve team. The emergency team and the reserve team are selected according to the maintenance travel time, and the emergency team is notified to go to the emergency maintenance point. When the emergency team arrives at the emergency repair point, it is determined whether additional maintenance personnel are needed according to the damage condition of the emergency repair point; If yes, the reserve team is notified to go to the emergency maintenance point. After the emergency maintenance point is repaired, the emergency team and the reserve team return to the corresponding planned maintenance point respectively. After the working day is over, the unfinished planned maintenance points are marked as deferred maintenance points, and the planned maintenance points for the next day are adjusted according to the number of deferred maintenance points; If not, the emergency team returns to the planned maintenance point after completing the maintenance at the emergency maintenance point; After the working day ends, marking the unfinished planned maintenance points as deferred maintenance points, and adjusting the planned maintenance points of the next day according to the number of the deferred maintenance points, specifically includes: Obtaining the maintenance route corresponding to each maintenance starting point of the next day, and calculating the travel change time of each maintenance route after the postponed maintenance point is inserted into the maintenance route; The maintenance route where the postponed maintenance point needs to be inserted is determined according to the travel change time.

2. A power supply station monitoring and management system based on an operation map, characterized in that: The management method according to claim 1 is applied to the management system, and the management system comprises: A storage module, the storage module is used to store the line loss value of each working cable in the target area; A calculation module, the calculation module is used to calculate the maintenance time limit of the cable to be maintained; A planning module, the planning module is used to plan the maintenance route; A sending module is used to send information that the working cable needs urgent repair to the maintenance team.

Citation Information

Patent Citations

  • Elevator maintenance rescue path planning method and system based on digital twinning

    CN116933959A

  • Power transmission line monitoring method and device based on optical fiber sensing technology

    CN118017697A