Infrastructure monitoring method and system based on point cloud

The point cloud-based infrastructure monitoring method solves the problems of low data synchronization and processing efficiency in the existing technology, achieves accurate monitoring and prediction of terrain changes, and improves the timeliness of disaster response and infrastructure safety.

CN118506291BActive Publication Date: 2024-10-18SHANDONG SURVEY & DESIGN INST OF WATER CONSERVANCY +1
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410979759.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-07-22
Publication Date
2024-10-18
Estimated Expiration
2044-07-22

AI Technical Summary

Technical Problem

Existing infrastructure monitoring methods are difficult to synchronize and integrate data points at different times and spaces during large-scale terrain monitoring, resulting in the inability to provide accurate terrain change predictions in real time, and are inefficient when processing high-resolution data, affecting the timely response to disasters. safety and effectiveness, thereby posing potential risks to people’s lives and property safety.

Method used

Adopt a point cloud-based infrastructure monitoring method, initialize the spatial positioning of point cloud data through geographical tagging, record longitude, latitude and timestamps, conduct structured arrangement and hierarchical classification, apply terrain change analysis algorithms to identify change indicators and trends, and adjust monitoring equipment parameters and strategies to optimize data collection and analysis frequency to enable real-time terrain change monitoring.

Benefits of technology

It improves data management and processing efficiency, enhances the accuracy and foresight of terrain change analysis, improves infrastructure safety monitoring and disaster prevention capabilities, and ensures timely identification and response to terrain threats.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118506291B_ABST
    Figure CN118506291B_ABST
Patent Text Reader

Abstract

The present invention relates to the field of terrain monitoring technology, specifically to a point cloud-based infrastructure monitoring method and system, the method comprising: based on geographic tags, initializing the spatial positioning of point cloud data, recording the longitude and latitude of each data point, synchronizing using timestamps, structuring the data, generating spatial positioning point cloud data, hierarchically classifying the spatial positioning point cloud data, and grouping them to obtain grouped terrain point cloud data. In the present invention, by recording the longitude and latitude of data points, tracking the location of terrain infrastructure, optimizing the recording of spatial attributes, using timestamp synchronization to enhance the time correlation of data, accurately reflecting the time series of terrain changes, data structuring to improve management efficiency and processing reliability, making terrain change analysis more accurate, and improving the pertinence of data processing through hierarchical classification and grouping of point cloud data. By identifying terrain change indicators and calculating change rates, the foresight and early warning capabilities of monitoring are enhanced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of terrain monitoring technology, and in particular to a point cloud-based infrastructure monitoring method and system. Background Art

[0002] The field of terrain monitoring technology involves the use of various methods and equipment to monitor and analyze physical changes on the surface and underground. The technology is mainly used to predict and assess the potential risks of natural disasters such as landslides, earthquakes, and floods, as well as the impact of human activities on the terrain, such as mining and construction projects. Terrain monitoring technology includes radar interferometry (InSAR), optical and laser ranging (such as LiDAR) technology, and the use of ground and air sensor networks to provide high-resolution terrain change data, thereby helping engineers and scientists monitor the stability of critical infrastructure and natural landforms in real time.

[0003] Among them, the infrastructure monitoring method is a technical means specifically used to evaluate and ensure the safety of public and private infrastructure. Infrastructure includes bridges, roads, dams, buildings, etc. By implementing terrain monitoring technology, the health status of infrastructure can be continuously monitored, structural weaknesses and potential threats can be discovered in a timely manner, and necessary maintenance and repairs can be carried out. This method helps to extend the service life of infrastructure, reduce the occurrence of accidents, and ensure the safety of people’s lives and property.

[0004] Although existing infrastructure monitoring methods are widely used in natural disaster prediction and infrastructure monitoring, they face challenges in data integration and time correlation processing. Especially when conducting large-scale terrain monitoring, existing technologies cannot effectively synchronize and integrate data points from different times and spaces, resulting in the inability to provide accurate terrain change predictions in real time in emergency situations. Existing methods are limited by the efficiency of data processing when processing high-resolution data, making it difficult to maximize their effectiveness in situations that require rapid response. If key data cannot be identified and classified in time during terrain monitoring, it will lead to misinterpretation of terrain changes, which in turn affects the timeliness and effectiveness of disaster response measures. This lack of data processing and time synchronization has led to the neglect or misjudgment of terrain threats in some cases, posing potential risks to people's lives and property safety. Summary of the invention

[0005] This application provides a point cloud-based infrastructure monitoring method and system. Although the existing infrastructure monitoring methods are widely used in natural disaster prediction and infrastructure monitoring, they face challenges in data integration and time correlation processing, especially when conducting large-scale terrain monitoring. The existing technology cannot effectively synchronize and integrate data points from different times and spaces, resulting in the inability to provide accurate terrain change predictions in real time in emergency situations. The existing methods are limited by the efficiency of data processing when processing high-resolution data, making it difficult to maximize their effectiveness when rapid response is required. If key data cannot be identified and classified in time during terrain monitoring, it will lead to misinterpretation of terrain changes, which in turn affects the timeliness and effectiveness of disaster response measures. This lack of data processing and time synchronization, in some cases, leads to the neglect or misjudgment of terrain threats, thus posing a potential risk to people's lives and property safety.

[0006] In view of the above problems, the present application provides a point cloud-based infrastructure monitoring method and system.

[0007] The present application provides a point cloud-based infrastructure monitoring method, wherein the method comprises:

[0008] S1: based on geographic tags, initialize the spatial positioning of point cloud data, record the longitude and latitude of each data point, synchronize using timestamps, perform structured arrangement of data, generate spatial positioning point cloud data, hierarchically classify the spatial positioning point cloud data, and group them to obtain grouped terrain point cloud data;

[0009] S2: Based on the grouped terrain point cloud data, applying a terrain change analysis algorithm, identifying terrain change indicators in each group of data, calculating the change rate of each indicator, obtaining terrain change analysis results, performing trend prediction on the terrain change analysis results, predicting terrain changes in the short term, and generating terrain prediction results;

[0010] S3: Based on the terrain prediction results, determine the key areas that need to be monitored, set the monitoring frequency and accuracy, generate a monitoring plan, apply the monitoring plan to the monitoring equipment, adjust the equipment parameters and match the new monitoring requirements, and obtain the monitoring parameter configuration results;

[0011] S4: Based on the monitoring parameter configuration results, start the monitoring equipment to collect new point cloud data and perform real-time analysis, identify new terrain change trends, obtain new periodic terrain analysis results, adjust the monitoring strategy according to the new periodic terrain analysis results, optimize the data collection period and analysis frequency, and establish an adjusted monitoring strategy.

[0012] Preferably, the step of acquiring the grouped terrain point cloud data is specifically as follows:

[0013] S111: Based on geographic tags, initialize the spatial positioning of point cloud data, record the latitude, longitude and timestamp of each data point, and use the formula:

[0014]

[0015] Calculate the spatial coordinates of each data point to obtain an initialized spatial coordinate data set, where: represents the spatial coordinates of the ith data point, a and b are the adjustment coefficients of longitude and latitude, represents longitude, represents latitude, represents the exponential growth adjustment of the timestamp, c is the time decay coefficient;

[0016] S112: Structural arrangement of the initialized spatial coordinate data set is performed according to the requirements of geographic information, using the formula:

[0017]

[0018] Integrate the data points to obtain spatial positioning point cloud data, where: Represents spatial positioning point cloud data, represents the exponential decay weight factor of the ith data point, represents the spatial coordinates of the i-th data point, and n represents the total number of data points;

[0019] S113: hierarchically classify the spatial positioning point cloud data, and classify the point cloud data according to terrain and landform factors, using the formula:

[0020]

[0021] Calculate the representative point cloud of each category to obtain hierarchical classification point cloud data, where: represents hierarchical classification point cloud data, m represents the number of point cloud data in the classification, Represents the spatial positioning point cloud data of the jth data point, Represents the classification weight of the jth point;

[0022] S114: performing a grouping operation based on the hierarchical classification point cloud data, using the formula:

[0023]

[0024] The grouped terrain point cloud data is calculated, where: Represents grouped terrain point cloud data, is the classification weight assigned according to geographical features, p represents the number of differentiated terrain classifications, Represents the hierarchical classification point cloud data of the kth category.

[0025] Preferably, the steps of obtaining the terrain change analysis results are specifically:

[0026] S211: Based on the grouped terrain point cloud data, initialize the point cloud data, record the longitude and latitude and timestamp of each data point, and use the formula:

[0027]

[0028] Analyze the position change of each data point corresponding to the initial measurement to obtain the initial indicator of terrain change, where is the initial indicator of terrain change, a and b are the longitude and latitude adjustment coefficients, , are longitude and latitude respectively, is the timestamp, c and d are the time adjustment coefficient and offset constant;

[0029] S212: Calculate the change rate for each of the initial indicators of terrain change, using the formula:

[0030]

[0031] The terrain change rate is calculated, where is the terrain change rate, and represent the current and previous terrain change indicators, respectively, and M is the number of change indicators;

[0032] S213: Integrate the terrain change rate and use the weighted product sum method to evaluate the overall terrain change using the formula:

[0033]

[0034] Generate terrain change analysis results, where is the result of terrain change analysis, K is the number of change rates, is the weight of the kth rate of change, is the kth terrain change rate.

[0035] Preferably, the steps of obtaining the terrain prediction result are specifically as follows:

[0036] S221: extracting data from the terrain change analysis results, applying time series analysis, using the formula:

[0037]

[0038] The exponential smoothing method is used to calculate the initial predicted value and obtain the preliminary terrain trend prediction data, where: For preliminary terrain trend prediction data, is the smoothing coefficient, is the regulating factor, is the analysis result of terrain change at the previous time point, is the predicted terrain data at the previous time point, is the normalization factor;

[0039] S222: Perform error analysis on the preliminary terrain trend prediction data using the formula:

[0040]

[0041] Calculate the difference between the real-time terrain data and the predicted terrain data to generate error data, where is the prediction error, is the result of terrain change analysis at the current time point, is the predicted terrain data at the current time point, is the standardization factor;

[0042] S223: Using the error data to adjust the prediction for the future time period, using the formula:

[0043]

[0044] Adjust the current prediction value according to the error to generate the terrain prediction result, where: is the adjusted predicted terrain data, is the error adjustment coefficient, is the unadjusted predicted terrain data, is the prediction error at the previous time point.

[0045] Preferably, the steps of obtaining the monitoring plan are specifically as follows:

[0046] S311: Calculate the risk factor score of the region according to the terrain prediction result, using the formula:

[0047]

[0048] Calculate the integrated risk score for each area and get a list of key areas, where: represents the integrated risk score of region i, represents the score of the j-th predictor, is a fine-tuning parameter, is the weight coefficient of the jth factor, is the regularization parameter, is a small constant, and n is the total number of predictors;

[0049] S312: According to the key area list, differentiated monitoring frequency and accuracy are set for each area, and the formula is:

[0050]

[0051] Generate monitoring parameters for key areas, where: are the monitoring parameters for key areas, is the integrated risk score of region i, and are the maximum and minimum values ​​of the regional risk score, respectively. is the adjustment parameter, is the exponential parameter.

[0052] S313: Using the monitoring parameters of the key areas, formulate a monitoring strategy and plan for each key area, the formula is:

[0053]

[0054] The monitoring plan is calculated, where is the monitoring plan for region i, is the monitoring parameter setting for region i, is the conversion factor.

[0055] Preferably, the steps of obtaining the monitoring parameter configuration result are specifically as follows:

[0056] S321: Based on the monitoring plan, evaluate the current configuration of the equipment and adjust it by the formula:

[0057]

[0058] Generate a preliminary updated device configuration, where Indicates the device configuration after the initial update. represents the original configuration of the device, P is the monitoring plan, is the learning rate, is the regularization parameter, is a small constant that enhances computational stability, is a tiny constant, is a power;

[0059] S322: Using the initially updated device configuration to adjust the parameters of the monitoring device to match the new monitoring requirements, the formula used is:

[0060]

[0061] Get the adjusted device parameters, where: is the adjusted device parameter, is the initial updated device configuration, is the adjustment parameter, T is the threshold;

[0062] S323: Perform configuration matching according to the adjusted device parameters, using the formula:

[0063]

[0064] Establish monitoring parameter configuration results, where: is the monitoring parameter configuration result, is the adjusted device parameter, is the adjustment factor, R is the monitoring requirement that the equipment should meet, is an additional adjustment factor.

[0065] Preferably, the steps for obtaining the adjusted monitoring strategy are specifically:

[0066] S411: Based on the monitoring parameter configuration result, the difference between the newly collected point cloud data after the monitoring device is started and the previously collected point cloud data is calculated using the formula:

[0067]

[0068] Generate point cloud data differences, where is the difference between the new and old data, represents the newly collected point cloud data, represents the previously collected point cloud data, is the stability coefficient of data point i, is a small increase to avoid division by zero error, and n is the number of data points;

[0069] S412: Based on the difference value of the new and old data, real-time analysis is performed to identify the change trend of the terrain infrastructure, using the formula:

[0070]

[0071] Get the new terrain change trend, among which, For the new terrain change trend, is the difference between the new and old data, is the weight of each point i, n is the number of points, is a small constant used to balance the sum of weights;

[0072] S413: According to the new terrain change trend, the monitoring strategy is adjusted and the data collection cycle and analysis frequency are optimized, using the formula:

[0073]

[0074] The adjusted monitoring strategy is obtained, where For the adjusted monitoring strategy, is the new terrain change trend, C is the current data collection period, F is the current analysis frequency, and are the maximum historical values ​​of terrain change and analysis frequency, and is a tuning parameter.

[0075] A point cloud-based infrastructure monitoring system, the system comprising:

[0076] The point cloud data initialization module is based on geographic tagging. During the point cloud data collection process, the spatial position of each point is associated with a timestamp, the spatial data is located and matched by longitude and latitude, and the time sequence of the data points is determined by the time tag to obtain a spatial time tag set;

[0077] The point cloud data grouping module uses the space-time tag set to divide the data into spatial intervals through geographic information, performs partition management on the data points, and obtains the grouped geographic data set through the spatial definition standard;

[0078] The terrain change analysis module processes the grouped geographic data set, applies terrain change detection logic to the partitioned data, measures the change in terrain height and position offset, extracts terrain dynamic change characteristics using time series comparative analysis, and constructs a terrain change indicator set;

[0079] The monitoring scheme design module evaluates the monitoring requirements of key change areas based on the terrain change indicator set, sets monitoring frequency and accuracy parameters according to the change indicators, adjusts the configuration parameters of the monitoring equipment, and generates a monitoring strategy configuration;

[0080] The real-time monitoring and adjustment module starts the monitoring equipment according to the monitoring strategy configuration, collects new point cloud data in real time, identifies the change trend of infrastructure in the new terrain, adjusts the monitoring strategy and data analysis frequency, and obtains an updated monitoring strategy.

[0081] One or more technical solutions provided in this application have at least the following technical effects or advantages:

[0082] By initializing the spatial positioning of point cloud data and recording the longitude and latitude of each data point, the location of infrastructure data points in each terrain can be accurately tracked. This refined data collection strategy optimizes the spatial attribute recording of data. The synchronous use of timestamps enhances the temporal correlation of data, so that the analysis process can accurately reflect the time series of terrain changes. The data structured approach not only improves the efficiency of data management, but also enhances the reliability of data processing, making subsequent terrain change analysis more accurate. By hierarchically classifying and grouping spatially positioned point cloud data, the pertinence of data processing and the feasibility of operations are improved, allowing for more detailed observation and analysis of changes in specific areas. The strategy of identifying terrain change indicators and calculating the rate of change effectively reveals the trend of terrain changes, further enhancing the foresight and early warning capabilities of terrain monitoring. This structured and layered data processing logic improves the accuracy and efficiency of terrain monitoring, thereby better serving infrastructure safety monitoring and disaster prevention.

[0083] The above description is only an overview of the technical solution of the present application. In order to more clearly understand the technical means of the present application, it can be implemented in accordance with the contents of the specification. In order to make the above and other purposes, features and advantages of the present application more obvious and easy to understand, the specific implementation methods of the present application are listed below. BRIEF DESCRIPTION OF THE DRAWINGS

[0084] Figure 1 The overall flow chart of the infrastructure monitoring method based on point cloud proposed by the present invention;

[0085] Figure 2 A flow chart of grouping terrain point cloud data for the infrastructure monitoring method based on point cloud proposed in the present invention;

[0086] Figure 3 A flow chart of terrain change analysis results of the infrastructure monitoring method based on point cloud proposed by the present invention;

[0087] Figure 4 A flow chart of terrain prediction results of the infrastructure monitoring method based on point cloud proposed by the present invention;

[0088] Figure 5 A flow chart of a monitoring plan for a point cloud-based infrastructure monitoring method proposed in the present invention;

[0089] Figure 6 A flow chart of monitoring parameter configuration results of the infrastructure monitoring method based on point cloud proposed by the present invention;

[0090] Figure 7 A flow chart of an adjusted monitoring strategy for the point cloud-based infrastructure monitoring method proposed in the present invention. DETAILED DESCRIPTION

[0091] The present application provides a point cloud-based infrastructure monitoring method and system.

[0092] Application Overview

[0093] Although the infrastructure monitoring methods in the existing technology are widely used in natural disaster prediction and infrastructure monitoring, they face the challenges of data integration and time correlation processing. Especially when conducting large-scale terrain monitoring, the existing technology cannot effectively synchronize and integrate data points from different time and space, resulting in the inability to provide accurate terrain change predictions in real time in emergency situations. The existing methods are limited by the efficiency of data processing when processing high-resolution data, making it difficult to maximize their effectiveness in situations where rapid response is required. If key data cannot be identified and classified in time during terrain monitoring, it will lead to misinterpretation of terrain changes, which in turn affects the timeliness and effectiveness of disaster response measures. This lack of data processing and time synchronization has led to the neglect or misjudgment of terrain threats in some cases, posing potential risks to people's lives and property safety.

[0094] In response to the above technical problems, the overall idea of ​​the technical solution provided by this application is as follows: Example

[0095] like Figure 1 As shown, the present application provides a point cloud-based infrastructure monitoring method, wherein the method includes:

[0096] S1: Based on geographic tags, initialize the spatial positioning of point cloud data, record the longitude and latitude of each data point, synchronize using timestamps, structure the data, generate spatial positioning point cloud data, hierarchically classify the spatial positioning point cloud data, and group them to obtain grouped terrain point cloud data;

[0097] S2: Based on the grouped terrain point cloud data, apply the terrain change analysis algorithm to identify the terrain change indicators in each group of data, calculate the change rate of each indicator, obtain the terrain change analysis results, perform trend forecasting on the terrain change analysis results, predict the terrain changes in the short term, and generate terrain prediction results;

[0098] S3: Based on the terrain prediction results, determine the key areas that need to be strengthened, set the monitoring frequency and accuracy, generate a monitoring plan, apply the monitoring plan to the monitoring equipment, adjust the equipment parameters and match the new monitoring requirements, and obtain the monitoring parameter configuration results;

[0099] S4: Based on the monitoring parameter configuration results, start the monitoring equipment to collect new point cloud data and perform real-time analysis, identify new terrain change trends, obtain new period terrain analysis results, adjust the monitoring strategy according to the new period terrain analysis results, optimize the data collection cycle and analysis frequency, and establish an adjusted monitoring strategy.

[0100] Spatial positioning point cloud data include longitude and latitude coordinates, time stamp, data index number; grouped terrain point cloud data include layered elevation distribution, slope classification, and regional division; terrain change analysis results include change rate, key change indicators, and change point location; terrain prediction results include future change trends, potential impact areas, and change prediction intervals; monitoring plans include monitoring area selection, monitoring frequency setting, and monitoring accuracy requirements; monitoring parameter configuration results include parameter setting values, adjustment areas, and time configuration; new cycle terrain analysis results include change trends, stability assessments, and risk point identification; the adjusted monitoring strategies include collection cycle adjustments, analysis frequency changes, and strategy execution schedules.

[0101] Specifically, if Figure 2 As shown in FIG. 1 , the steps for obtaining grouped terrain point cloud data are as follows:

[0102] S111: Based on geographic tags, initialize the spatial positioning of point cloud data, record the latitude, longitude and timestamp of each data point, and use the formula:

[0103]

[0104] Calculate the spatial coordinates of each data point to obtain an initialized spatial coordinate data set, where: represents the spatial coordinates of the ith data point, a and b are the adjustment coefficients of longitude and latitude, represents longitude, represents latitude, represents the exponential growth adjustment of the timestamp, c is the time decay coefficient;

[0105] S112: Structural arrangement of the initialized spatial coordinate data set is performed according to the requirements of geographic information, using the formula:

[0106]

[0107] Integrate the data points to obtain spatial positioning point cloud data, where: Represents spatial positioning point cloud data, represents the exponential decay weight factor of the ith data point, represents the spatial coordinates of the i-th data point, and n represents the total number of data points;

[0108] S113: Classify the spatial positioning point cloud data hierarchically, and classify the point cloud data according to terrain and landform factors, using the formula:

[0109]

[0110] Calculate the representative point cloud of each category to obtain hierarchical classification point cloud data, where: represents hierarchical classification point cloud data, m represents the number of point cloud data in the classification, Represents the spatial positioning point cloud data of the jth data point, Represents the classification weight of the jth point;

[0111] S114: Perform grouping operation based on hierarchical classification point cloud data, using the formula:

[0112]

[0113] The grouped terrain point cloud data is calculated, where: Represents grouped terrain point cloud data, is the classification weight assigned according to geographical features, p represents the number of differentiated terrain classifications, Represents the hierarchical classification point cloud data of the kth category.

[0114] The spatial coordinate formula of the data point is:

[0115]

[0116] : The longitude of the i-th data point;

[0117] : The latitude of the i-th data point;

[0118] : The timestamp of the ith data point.

[0119] longitude( ) and latitude ( ) is directly obtained from the dataset, and the timestamp ( ) is also obtained from the dataset, indicating the specific time when the data point was recorded;

[0120] Components in the calculation formula:

[0121] Calculate the sum of the squares of the longitude and latitude contributions: ;

[0122] A square root function is applied to adjust the scale of the position data, and an exponential function is used to adjust the influence of timestamps so that more recent timestamps have a greater impact on the results.

[0123] Assumptions , a data point has a specific value of ,

[0124] .

[0125] The calculation formula for spatial positioning point cloud data is:

[0126]

[0127] : Weight factor of the i-th data point;

[0128] Weight Factor This can be determined based on the importance or criteria of the data point, such as data quality or reliability;

[0129] The position influence of each data point is exponentially decayed to reflect the distance or time. The larger the weight, the smaller the contribution of the data point.

[0130] Assumptions , the L values ​​of the data points are 599.90, 450.00, 500.00, and the weight W is 0.05.

[0131]

[0132]

[0133]

[0134]

[0135] The calculation formula for hierarchical classification point cloud data is:

[0136]

[0137] : The classification weight of the jth data point;

[0138] Classification weight Importance can be assigned based on the category to which the data point belongs;

[0139] Will The values ​​of are fed into a cosine function to smooth the range of values ​​and make them suitable for further analysis;

[0140] Assume m=3, weights V are 1, 2, 1.5 respectively, the previous step The result is

[0141]

[0142]

[0143] The calculation formula for grouped terrain point cloud data is:

[0144]

[0145] : The weight of the kth category;

[0146] Category weight depending on geographical or other characteristics;

[0147] For each class The square root of the value is taken to enhance the sensitivity to small values, and then the weighted average is performed according to the weight;

[0148] Assume p=2, weight 2 and 3 respectively, The values ​​are 1.5 and 2.0 respectively:

[0149]

[0150] Specifically, if Figure 3 As shown in the figure, the steps for obtaining the terrain change analysis results are as follows:

[0151] S211: Based on the grouped terrain point cloud data, initialize the point cloud data, record the longitude and latitude and timestamp of each data point, and use the formula:

[0152]

[0153] Analyze the position change of each data point corresponding to the initial measurement to obtain the initial indicator of terrain change, where is the initial indicator of terrain change, a and b are the longitude and latitude adjustment coefficients, , are longitude and latitude respectively, is the timestamp, c and d are the time adjustment coefficient and offset constant;

[0154] S212: Calculate the change rate for each initial indicator of terrain change, using the formula:

[0155]

[0156] The terrain change rate is calculated, where is the terrain change rate, and represent the current and previous terrain change indicators, respectively, and M is the number of change indicators;

[0157] S213: Integrate the terrain change rate and use the weighted product sum method to evaluate the overall terrain change using the formula:

[0158]

[0159] Generate terrain change analysis results, where is the result of terrain change analysis, K is the number of change rates, is the weight of the kth rate of change, is the kth terrain change rate.

[0160] Derivation of the calculation formula for the initial index of terrain change:

[0161]

[0162] a, b: longitude and latitude adjustment coefficients, set by the geographic information system based on terrain characteristics;

[0163] , : longitude and latitude of the data point;

[0164] : timestamp;

[0165] c, d: Adjust the coefficient and offset of the timestamp effect.

[0166] For a data point, set its longitude =100, latitude =40, timestamp =1609459200;

[0167] Assume a=0.5, b=1.5, c=0.0001, d=100;

[0168] Calculate the adjusted latitude and longitude value: AdjustedValue= ;

[0169] Calculate the time adjustment value:

[0170] ;

[0171] Calculate initial indicators of terrain change : .

[0172] Derivation of the terrain change rate calculation formula:

[0173]

[0174] , : indicators of current and previous terrain changes;

[0175] Assume there are three data points of change indicators, and =[62995, 62998, 62999],

[0176] Calculate the change in value for each point:

[0177] ,

[0178] ,

[0179] ,

[0180] Apply the sine function to calculate the rate of change:

[0181]

[0182] Derivation of calculation formula for terrain change analysis results:

[0183]

[0184] : Weight factor, used to measure the impact of each change rate;

[0185] : The kth terrain change rate.

[0186] Assume there are three rates of change and the corresponding weight factors =[1, 1.5, 2],

[0187] Compute the weighted sum:

[0188] .

[0189] Specifically, if Figure 4 As shown in the figure, the steps for obtaining terrain prediction results are as follows:

[0190] S221: Extract data from the terrain change analysis results and apply time series analysis using the formula:

[0191]

[0192] The exponential smoothing method is used to calculate the initial predicted value and obtain the preliminary terrain trend prediction data, where: For preliminary terrain trend prediction data, is the smoothing coefficient, is the regulating factor, is the analysis result of terrain change at the previous time point, is the predicted terrain data at the previous time point, is the normalization factor;

[0193] S222: Perform error analysis on the preliminary terrain trend prediction data using the formula:

[0194]

[0195] Calculate the difference between the real-time terrain data and the predicted terrain data to generate error data, where is the prediction error, is the result of terrain change analysis at the current time point, is the predicted terrain data at the current time point, is the standardization factor;

[0196] S223: Use the error data to adjust the forecast for the future time period using the formula:

[0197]

[0198] Adjust the current prediction value according to the error to generate the terrain prediction result, where: is the adjusted predicted terrain data, is the error adjustment coefficient, is the unadjusted predicted terrain data, is the prediction error at the previous time point.

[0199] The formula for calculating the preliminary value of the forecast using the exponential smoothing method is:

[0200]

[0201] : Smoothing coefficient, select a value based on the volatility of historical data, for example ;

[0202] : Adjustment factor, which enhances or reduces the impact of historical forecast values, depending on the trend of the data, e.g. ;

[0203] : Normalization factor, used to balance the denominator and avoid the denominator being zero, for example .

[0204] Obtained from historical data , that is, the topographic change result at the previous time point, assumed to be 150;

[0205] Get from previous forecasts , assuming the previous forecast was 140;

[0206] Apply the formula to calculate :

[0207]

[0208]

[0209] Error data formula:

[0210]

[0211] : Normalization factor, e.g. ;

[0212] Get the terrain change result at the current time point , assuming it is 160, use , that is 12900.

[0213] Apply the formula to calculate :

[0214]

[0215] Terrain prediction result formula:

[0216]

[0217] : Error adjustment factor, for example =0.4;

[0218] use , assuming is 57686;

[0219] Apply the formula to calculate :

[0220] .

[0221] Specifically, if Figure 5 As shown in the figure, the steps for obtaining the monitoring plan are as follows:

[0222] S311: Based on the terrain prediction results, calculate the risk factor score of the area using the formula:

[0223]

[0224] Calculate the integrated risk score for each area and get a list of key areas, where: represents the integrated risk score of region i, represents the score of the j-th predictor, is a fine-tuning parameter, is the weight coefficient of the jth factor, is the regularization parameter, is a small constant, and n is the total number of predictors;

[0225] S312: According to the key area list, set differentiated monitoring frequency and accuracy for each area. The formula is:

[0226]

[0227] Generate monitoring parameters for key areas, where: are the monitoring parameters for key areas, is the integrated risk score of region i, and are the maximum and minimum values ​​of the regional risk score, respectively. is the adjustment parameter, is the exponential parameter.

[0228] S313: Using the monitoring parameters of key areas, develop monitoring strategies and plans for each key area. The formula is:

[0229]

[0230] The monitoring plan is calculated, where is the monitoring plan for region i, is the monitoring parameter setting for region i, is the conversion factor.

[0231] The calculation process of integrated risk score:

[0232]

[0233] Data collection: Collect the prediction factors corresponding to each region i data, where j represents the index of the factor, from 1 to n;

[0234] Factor tuning: Add a tuning parameter to each predictor , which can be bias-adjusted based on previous data;

[0235] Square Factor: The adjusted predictor Perform a squaring operation to enhance the impact of factor changes on the final risk score;

[0236] Apply weight: multiply the squared result by the weight of the factor , the weight determines the importance of each factor in the overall risk score;

[0237] Regularization: Use the regularization parameter and a small constant The square root of the digit is used to avoid division by zero errors and balance the calculations;

[0238] Sum: Sum the weighted scores of all factors to get the total risk score of region i

[0239] Assume that a region has three factors and the scores of each factor are , adjust the parameters , weight , the regularization parameter and constant ,

[0240] ,

[0241] ,

[0242] ,

[0243] .

[0244] Formula for calculating monitoring parameters of key areas:

[0245]

[0246] Determine extreme values: First determine the maximum value among all regions’ risk scores and minimum value ;

[0247] Calculate the difference: For each region i, calculate its risk score With the maximum value This helps to reduce the range of fractional changes and make frequency adjustments more sensitive;

[0248] Standardization: Divide the result obtained in the previous step by the square root of the difference between the maximum and minimum risk scores to perform standardization to ensure that all values ​​are between 0 and 1;

[0249] Apply the adjustment parameter: multiply the normalized result by the adjustment parameter , the flexibility to adjust monitoring frequency as needed.

[0250] Apply nonlinear transformation: Exponentially transform the above result Processing further adjusts the nonlinear characteristics of the frequency, making the adjustment of the monitoring frequency more sensitive to changes in the risk score.

[0251] Assumptions , the risk score of the region is , , adjustment parameters , nonlinear index ,

[0252]

[0253] ,

[0254] .

[0255] Developing a Monitoring Plan Formula

[0256]

[0257] Calculating square roots: Monitoring frequency Calculate its square root to adjust the frequency sensitivity;

[0258] Adjusting program intensity: via conversion factors To adjust the implementation intensity of the monitoring plan, this factor can be set according to actual needs;

[0259] Calculate the final monitoring plan value: Convert the conversion factor Divide by the calculated square root value to obtain the specific monitoring plan intensity for each area.

[0260] Assuming conversion factor , known ,

[0261] .

[0262] Specifically, if Figure 6 As shown, the steps for obtaining the monitoring parameter configuration results are as follows:

[0263] S321: Based on the monitoring plan, evaluate the current configuration of the equipment and adjust it through the formula:

[0264]

[0265] Generate a preliminary updated device configuration, where Indicates the device configuration after the initial update. represents the original configuration of the device, P is the monitoring plan, is the learning rate, is the regularization parameter, is a small constant that enhances computational stability, is a tiny constant, is a power;

[0266] S322: Use the device configuration after the initial update to adjust the parameters of the monitoring device to match the new monitoring requirements. The formula used is:

[0267]

[0268] Get the adjusted device parameters, where: is the adjusted device parameter, is the initial updated device configuration, is the adjustment parameter, T is the threshold;

[0269] S323: Perform configuration matching according to the adjusted device parameters, using the formula:

[0270]

[0271] Establish monitoring parameter configuration results, where: is the monitoring parameter configuration result, is the adjusted device parameter, is the adjustment factor, R is the monitoring requirement that the equipment should meet, is an additional adjustment factor.

[0272] Derivation of the device configuration formula after preliminary update:

[0273]

[0274] Original device configuration : Assumption It is obtained through the last detection of the device. Here it is assumed ;

[0275] Monitoring plan P: P represents the target configuration value adjusted according to the new monitoring requirements, assuming P=70

[0276] Learning Rate : is a preset constant that controls the speed of configuration updates. Assume =0.1;

[0277] Regularization parameter and a small constant : and To ensure that the denominator is not zero and the adjustment process is smooth, assume =2 and =1;

[0278] Fine-tuning constant and power : Used to further adjust the value of the denominator to improve the accuracy of the adjustment, assuming , To adjust for the nonlinear effects of updates, assume =2.

[0279] Hypothetical calculation The difference: ;

[0280] Raise the difference to a power ;

[0281] Calculate the denominator: ;

[0282] Apply the formula to calculate .

[0283] The derivation formula of the adjusted equipment parameters is:

[0284]

[0285] Adjusted equipment parameters : Obtained from formula 1, here we use =62.41;

[0286] Adjustment parameters And the threshold T: Controls the steepness of the curve, assuming =0.5, T is the center point of adjustment, assuming T=60;

[0287] Assume that the exponential part is calculated: ;

[0288] Apply the formula to calculate .

[0289] Monitoring parameter configuration result derivation formula:

[0290]

[0291] Adjusted equipment parameters : Obtained from formula 2, here we use =48;

[0292] Modulating Factor and additional adjustment factor : Determine the sensitivity of the configuration adjustment, assuming =0.2, To fine-tune the final result, assume =0.1;

[0293] The monitoring requirement R that the equipment should meet: Assume R=75;

[0294] Calculate the denominator: ;

[0295] calculate The difference and apply the formula :

[0296] .

[0297] Specifically, if Figure 7 As shown, the steps for obtaining the adjusted monitoring strategy are as follows:

[0298] S411: Based on the monitoring parameter configuration results, the point cloud data newly collected after the monitoring device is started is calculated to see the difference with the previously collected point cloud data, using the formula:

[0299]

[0300] Generate point cloud data differences, where is the difference between the new and old data, represents the newly collected point cloud data, represents the previously collected point cloud data, is the stability coefficient of data point i, is a small increase to avoid division by zero error, and n is the number of data points;

[0301] S412: Based on the difference between the new and old data, real-time analysis is performed to identify the changing trend of the terrain infrastructure using the formula:

[0302]

[0303] Get the new terrain change trend, among which, For the new terrain change trend, is the difference between the new and old data, is the weight of each point i, n is the number of points, is a small constant used to balance the sum of weights;

[0304] S413: According to the new terrain change trend, adjust the monitoring strategy and optimize the data collection cycle and analysis frequency, using the formula:

[0305]

[0306] The adjusted monitoring strategy is obtained, where For the adjusted monitoring strategy, is the new terrain change trend, C is the current data collection period, F is the current analysis frequency, and are the maximum historical values ​​of terrain change and analysis frequency, and is a tuning parameter.

[0307] The difference formula between new and old data is:

[0308]

[0309] Assume that new point cloud data collected from monitoring equipment is a vector: =[10, 12, 15];

[0310] Assume that the point cloud data collected previously is a vector: ;

[0311] For each point i, calculate the absolute difference between the old and new data: ;

[0312] Assume that the stability coefficient of each point i is yes: ;

[0313] Set small constant is 0.01 to avoid division by zero error;

[0314] Apply the formula to calculate the difference in point cloud data: .

[0315] Real-time analysis of new terrain change trend formula:

[0316]

[0317] Apply weights:

[0318] Assume that the weight of each data point is yes: ;

[0319] Compute the weight-adjusted difference and weighted sum:

[0320] Calculate the weight-adjusted difference: ;

[0321] Calculate the sum of the weights plus a small constant ;

[0322] Calculate new terrain trends :

[0323] Application formula: .

[0324] The monitoring strategy formula adjusted according to the new period terrain analysis results is:

[0325]

[0326] Basic parameter assumptions:

[0327] Current data collection cycle C=5, current analysis frequency F=2, maximum historical terrain change =30, maximum analysis frequency =5, adjustment parameters =0.05 and =0.02;

[0328] Calculate the monitoring strategy adjustment factor:

[0329] Adjustment Factor: ;

[0330] Frequency adjustment factor: ;

[0331] Calculation of adjusted surveillance strategy :

[0332] Application formula: .

[0333] Point cloud-based infrastructure monitoring system, the system includes:

[0334] The point cloud data initialization module is based on geographic tagging. During the point cloud data collection process, the spatial position of each point is associated with a timestamp, the spatial data is located and matched by longitude and latitude, and the time sequence of the data points is determined by the time tag to obtain a spatial time tag set;

[0335] The point cloud data grouping module uses a space-time tag set to divide the data into spatial intervals through geographic information, partitions the data points, and obtains grouped geographic data sets through spatial definition standards;

[0336] The terrain change analysis module processes the grouped geographic data sets, applies terrain change detection logic to the partitioned data, measures the changes in terrain height and position offset, extracts the dynamic change characteristics of terrain using time series comparative analysis, and constructs a set of terrain change indicators;

[0337] The monitoring scheme design module evaluates the monitoring needs of key change areas based on the terrain change indicator set, sets the monitoring frequency and accuracy parameters according to the change indicators, adjusts the configuration parameters of the monitoring equipment, and generates the monitoring strategy configuration;

[0338] The real-time monitoring and adjustment module starts the monitoring equipment according to the monitoring strategy configuration, collects new point cloud data in real time, identifies the changing trend of infrastructure in the new terrain, adjusts the monitoring strategy and data analysis frequency, and obtains the updated monitoring strategy.

[0339] Although the present application has been described in conjunction with specific features and embodiments thereof, it is obvious that various modifications and combinations may be made thereto without departing from the spirit and scope of the present application. Accordingly, this specification and the drawings are merely exemplary illustrations of the present application as defined by the appended claims, and are deemed to have covered any and all modifications, variations, combinations or equivalents within the scope of the present application. Obviously, a person skilled in the art may make various modifications and variations to the present application without departing from the scope of the present application. Thus, if these modifications and variations of the present application fall within the scope of the claims of the present application and their equivalents, the present application is intended to include these modifications and variations.

Claims

1. A point cloud-based infrastructure monitoring method, characterized in that: The method comprises: Initialize the spatial positioning of the point cloud data based on geographic tags, record the longitude and latitude of each data point, synchronize using timestamps, structure the data, generate spatial positioning point cloud data, hierarchically classify the spatial positioning point cloud data, and group them to obtain grouped terrain point cloud data; Based on the grouped terrain point cloud data, applying a terrain change analysis algorithm, identifying terrain change indicators in each group of data, calculating the change rate of each indicator, obtaining terrain change analysis results, performing trend forecasting on the terrain change analysis results, forecasting terrain changes in the short term, and generating terrain forecast results; The steps for obtaining the terrain change analysis results are specifically as follows: Based on the grouped terrain point cloud data, the point cloud data is initialized, and the latitude, longitude and timestamp of each data point are recorded, using the formula: ; Analyze the position change of each data point corresponding to the initial measurement to obtain the initial indicator of terrain change, where is the initial indicator of terrain change, a and b are the longitude and latitude adjustment coefficients, , are longitude and latitude respectively, is the timestamp, c and d are the time adjustment coefficient and offset constant; For each of the initial indicators of terrain change, the rate of change is calculated using the formula: ; The terrain change rate is calculated, where is the terrain change rate, and represent the current and previous terrain change indicators, respectively, and M is the number of change indicators; Integrating the terrain change rates, the weighted product-sum method is used to assess the overall terrain change using the formula: ; Generate terrain change analysis results, where is the result of terrain change analysis, K is the number of change rates, is the weight of the kth rate of change, is the kth terrain change rate; Based on the terrain prediction results, determine the key areas that need to be strengthened in monitoring, set the monitoring frequency and accuracy, generate a monitoring plan, apply the monitoring plan to the monitoring equipment, adjust the equipment parameters and match the new monitoring requirements, and obtain the monitoring parameter configuration results; Based on the monitoring parameter configuration results, the monitoring equipment is started to collect new point cloud data and perform real-time analysis to identify new terrain change trends and obtain new periodic terrain analysis results. The monitoring strategy is adjusted according to the new periodic terrain analysis results to optimize the data collection cycle and analysis frequency and establish an adjusted monitoring strategy.

2. The infrastructure monitoring method based on point cloud according to claim 1, characterized in that: The steps for obtaining the grouped terrain point cloud data are specifically as follows: Based on geographic tags, initialize the spatial positioning of point cloud data, record the latitude and longitude and timestamp of each data point, and use the formula: ; Calculate the spatial coordinates of each data point to obtain an initialized spatial coordinate data set, where: represents the spatial coordinates of the ith data point, a and b are the adjustment coefficients of longitude and latitude, represents longitude, represents latitude, represents the exponential growth adjustment of the timestamp, c is the time decay coefficient; The initialized spatial coordinate data set is structured and arranged according to the requirements of geographic information, using the formula: ; Integrate the data points to obtain spatial positioning point cloud data, where: Represents spatial positioning point cloud data, Representative The exponential decay weight factor for the data points is represents the spatial coordinates of the i-th data point, and n represents the total number of data points; The spatial positioning point cloud data is hierarchically classified, and the point cloud data is classified according to terrain and landform factors, using the formula: ; Calculate the representative point cloud of each category to obtain hierarchical classification point cloud data, where: represents hierarchical classification point cloud data, m represents the number of point cloud data in the classification, Represents the spatial positioning point cloud data of the jth data point, Represents the classification weight of the jth point; The grouping operation is performed based on the hierarchical classification point cloud data, using the formula: ; The grouped terrain point cloud data is calculated, where: Represents grouped terrain point cloud data, is the classification weight assigned according to geographical features, p represents the number of differentiated terrain classifications, Represents the hierarchical classification point cloud data of the kth category.

3. The infrastructure monitoring method based on point cloud according to claim 1, characterized in that: The steps for obtaining the terrain prediction result are specifically as follows: Data were extracted from the terrain change analysis results and time series analysis was applied using the formula: ; The exponential smoothing method is used to calculate the initial predicted value and obtain the preliminary terrain trend prediction data, where: For preliminary terrain trend prediction data, is the smoothing coefficient, is the regulating factor, is the result of terrain change analysis at the previous time point, is the predicted terrain data at the previous time point, is the normalization factor; The error analysis of the preliminary terrain trend prediction data is carried out using the formula: ; Calculate the difference between the real-time terrain data and the predicted terrain data to generate error data, where is the prediction error, is the result of terrain change analysis at the current time point, is the predicted terrain data at the current time point, is the standardization factor; The error data is used to adjust the forecast for future time periods using the formula: ; Adjust the current prediction value according to the error to generate the terrain prediction result, where: is the adjusted predicted terrain data, is the error adjustment coefficient, is the unadjusted predicted terrain data, is the prediction error at the previous time point.

4. The infrastructure monitoring method based on point cloud according to claim 3, characterized in that: The steps for obtaining the monitoring plan are specifically as follows: Based on the terrain prediction results, the risk factor score of the area is calculated using the formula: ; Calculate the integrated risk score for each area and get a list of key areas, where: represents the integrated risk score of region i, represents the score of the j-th predictor, is a fine-tuning parameter, is the weight coefficient of the jth factor, is the regularization parameter, is a small constant, and n is the total number of predictors; According to the list of key areas, differentiated monitoring frequency and accuracy are set for each area. The formula is: ; Generate monitoring parameters for key areas, where: are the monitoring parameters for key areas, is the integrated risk score of region i, and are the maximum and minimum values ​​of the regional risk score, respectively; is the adjustment parameter, is the exponential parameter; Using the monitoring parameters of the key areas, a monitoring strategy and plan are formulated for each key area. The formula is: ; The monitoring plan is calculated, where is the monitoring plan for region i, is the monitoring parameter setting for region i, is the conversion factor.

5. The infrastructure monitoring method based on point cloud according to claim 4, characterized in that: The steps for obtaining the monitoring parameter configuration result are specifically as follows: Based on the monitoring plan, evaluate the current configuration of the equipment and adjust it using the formula: ; Generate a preliminary updated device configuration, where Indicates the device configuration after the initial update. represents the original configuration of the device, P is the monitoring plan, is the learning rate, is the regularization parameter, is a small constant that enhances computational stability, is a tiny constant, is a power; The parameters of the monitoring equipment are adjusted using the device configuration after the preliminary update to match the new monitoring requirements. The formula used is: ; Get the adjusted device parameters, where: is the adjusted device parameter, is the initial updated device configuration, is the adjustment parameter, T is the threshold; According to the adjusted device parameters, configuration matching is performed using the formula: ; Establish monitoring parameter configuration results, where: is the monitoring parameter configuration result, is the adjusted device parameter, is the adjustment factor, R is the monitoring requirement that the equipment should meet, is an additional adjustment factor.

6. The infrastructure monitoring method based on point cloud according to claim 5, characterized in that: The steps for obtaining the adjusted monitoring strategy are specifically as follows: Based on the monitoring parameter configuration results, the difference between the newly collected point cloud data after the monitoring device is started and the previously collected point cloud data is calculated using the formula: ; Generate point cloud data differences, where is the difference between the new and old data, represents the newly collected point cloud data, represents the previously collected point cloud data, is the stability coefficient of data point i, is a small increase to avoid division by zero error, and n is the number of data points; Based on the difference between the new and old data, real-time analysis is performed to identify the changing trend of the terrain infrastructure, using the formula: ; Get the new terrain change trend, among which, For the new terrain change trend, is the difference between the new and old data, is the weight of each point i, n is the number of points, is a small constant used to balance the sum of weights; According to the new terrain change trend, the monitoring strategy is adjusted and the data collection cycle and analysis frequency are optimized. The formula used is: ; The adjusted monitoring strategy is obtained, where For the adjusted monitoring strategy, is the new terrain change trend, C is the current data collection period, F is the current analysis frequency, and are the maximum historical values ​​of terrain change and analysis frequency, and is a tuning parameter.

7. Point cloud-based infrastructure monitoring system, characterized in that: According to any one of claims 1 to 6, the point cloud-based infrastructure monitoring method is implemented, and the system comprises: The point cloud data initialization module is based on geographic tagging. During the point cloud data collection process, the spatial position of each point is associated with a timestamp, the spatial data is located and matched by longitude and latitude, and the time sequence of the data points is determined by the time tag to obtain a spatial time tag set; The point cloud data grouping module uses the space-time tag set to divide the data into spatial intervals through geographic information, performs partition management on the data points, and obtains the grouped geographic data set through the spatial definition standard; The terrain change analysis module processes the grouped geographic data set, applies terrain change detection logic to the partitioned data, measures the change in terrain height and position offset, extracts terrain dynamic change characteristics using time series comparative analysis, and constructs a terrain change indicator set; The monitoring scheme design module evaluates the monitoring requirements of key change areas based on the terrain change indicator set, sets monitoring frequency and accuracy parameters according to the change indicators, adjusts the configuration parameters of the monitoring equipment, and generates a monitoring strategy configuration; The real-time monitoring and adjustment module starts the monitoring equipment according to the monitoring strategy configuration, collects new point cloud data in real time, identifies the change trend of infrastructure in the new terrain, adjusts the monitoring strategy and data analysis frequency, and obtains an updated monitoring strategy.

Citation Information

Patent Citations

  • Pollution reduction and carbon reduction coupling index analysis method and system based on big data

    CN118365005A

  • Systems and methods for determining crop yields with high resolution geo-referenced sensors

    US20170016870A1