A construction device and construction process for exterior facade of a building project
By designing automated construction equipment for exterior facade construction, the problems of low spraying efficiency and dead corners in the existing technology have been solved. Simultaneous spraying of primer and mortar and automatic spraying of the inner side walls of the window have been realized, improving construction efficiency.
Patent Information
- Application Number
- CN202411017173.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-29
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2044-07-29
AI Technical Summary
The existing building exterior facade spraying technology is inefficient and cannot spray primer and mortar at one time. There are problems with spraying dead corners and wasted man-hours.
A building engineering facade construction device is designed, including a chassis and a counterweight platform. The automatic operation of the spraying unit is realized through a lifting unit and a mobile control unit. The spraying unit is equipped with a storage barrel, a turntable, a nozzle and a telescopic component, and can spray the bottom at the same time. Paint and mortar are sprayed with automatic telescopic nozzles at the window, and the chassis moves laterally along the wall during the rising and falling process.
It realizes the simultaneous spraying of primer and mortar, reduces man-hours, avoids dead corners of spraying, improves work efficiency, and supports automatic spraying of the inner side wall of the window, ensuring continuous operation.
Smart Images

Figure CN118547858B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of building construction, and in particular to a building engineering facade construction device and a construction process. Background Art
[0002] The construction of the exterior facade of a building generally includes facade polishing, cleaning and leveling, facade paving of insulation boards, facade paving of wall tiles or spraying of facade primer and mortar. Usually, only one of the laying of wall tiles and spraying of primer and mortar is required. Among them, in order to improve the appearance of the facade, protect the wall and enhance the thermal insulation performance of the wall, primer and mortar are usually sprayed on the facade in sequence.
[0003] In the traditional facade spraying construction process, manual spraying with a spray gun is generally adopted, and then a hanging basket is used to transport workers from bottom to top for spraying. This method is inefficient, the quality is difficult to guarantee, and there are safety hazards. Based on this, the prior art provides a technical solution for facade spraying. For a more accurate comparison, for example, a Chinese patent with publication number CN111219041A discloses a building exterior wall paint spraying device, including a carrier vehicle, a paint replenishing device is provided on the carrier vehicle, the paint replenishing device is mainly used to replenish the paint required for spraying the exterior wall of the building, a lifting rope device is provided on the upper side of the paint replenishing device, the lifting rope device is used to provide the lifting movement required for spraying the exterior wall of the building, an exterior wall spraying device is provided on the right side of the paint replenishing device, the exterior wall spraying device is arranged on a steel wire rope, a verticality adjustment device is provided on the lifting rope device, the verticality adjustment device is used to adjust the verticality of the steel wire rope, the verticality adjustment device includes a cylinder fixedly connected to the upper end face of the wire wheel box, and the exterior wall spraying device includes a lifting trolley fixedly connected to the steel wire rope.
[0004] When it is in use, the spraying trolley is driven by the rope lifting mechanism to gradually move down from the roof to spray paint on the exterior wall of the building. The positive pressure airflow generated by the air pump enables the spraying trolley to fit onto the exterior wall of the building and move down along the exterior wall. The verticality adjustment mechanism can always keep the rope and the spraying trolley basically vertical during the lifting and lowering of the spraying trolley, so that the nozzle remains basically vertical to the wall during the spraying process, thereby ensuring the spraying quality. After completing one spraying, the rope lifting mechanism drives the spraying trolley to move up and reset, the paint replenishing mechanism replenishes paint to the spraying trolley, and the carrier vehicle drives the entire device to move to the next location for spraying operations.
[0005] However, in the process of spraying the exterior walls of buildings using the above-mentioned prior art, there are still the following shortcomings:
[0006] 1. Since the exterior walls of buildings usually have windows for installing windows, and the rope lifting mechanism drives the spraying trolley to gradually move down from the roof to spray paint on the exterior walls of the building, the spraying trolley cannot reach into the window to spray the side walls, so manual spraying is required again, which affects the spraying efficiency.
[0007] 2. Furthermore, since primer needs to be sprayed on the exterior walls of buildings before spraying paint to enhance the adhesion of the paint, although the above-mentioned prior art can spray paint on the exterior walls of buildings by a spraying trolley, it is impossible to complete the spraying of primer and paint at one time. Therefore, the primer and paint need to be sprayed separately, which increases the workload.
[0008] 3. In addition, after the spraying trolley completes one spraying operation, it needs to be driven upward and reset by a rope lifting mechanism, and the carrier vehicle drives the entire device to move to the next location for another downward spraying operation. The spraying operation cannot be performed during the entire process of moving the device up and down, thereby wasting working time and failing to achieve continuous operation.
[0009] Therefore, based on the above-stated viewpoints, there is still room for improvement in the existing facade spraying methods. Summary of the invention
[0010] In order to solve the above problems, the present invention provides a construction device for the facade of a building project, comprising a chassis and a counterweight platform, wherein a spray unit is installed on one side of the chassis close to the wall, and a lifting unit cooperating with the spray unit is arranged on the counterweight platform, the lifting unit comprises a first take-up wheel installed on the upper end of the counterweight platform through a support frame, a steel cable is wound on the outer wall of the first take-up wheel, and the end of the steel cable away from the first take-up wheel is connected to the chassis, and a mobile control unit is jointly installed between the chassis and the counterweight platform, and the mobile control unit comprises a first controller arranged on the upper end of the chassis and a second controller installed on the upper end of the counterweight platform.
[0011] The spraying unit includes a storage barrel. Two storage barrels for storing primer and mortar respectively are installed inside the chassis. A turntable is rotatably installed on the side of the chassis close to the wall. Two storage chambers are symmetrically installed on the side of the turntable away from the storage barrel. Any storage barrel and the storage chamber on the upper side of the turntable and the other storage barrel and the storage chamber on the lower side of the turntable are connected by a connecting hose. A pressure pump is installed at the connection between the storage barrel and the connecting hose. Two card holders that are clamped on the side walls of the storage chamber are symmetrically arranged on the side walls of the turntable. A nozzle is installed on the side of the storage chamber away from the chassis through a plurality of telescopic rods arranged at equal intervals along the length direction. A telescopic assembly is installed between the nozzle and the card holder. The telescopic assembly includes a detection wheel arranged on the side of the nozzle away from the telescopic rod through a telescopic plate.
[0012] As a preferred technical solution of the present invention, the lifting unit further comprises a fixed block, and two fixed blocks corresponding to the position of the first take-up wheel are symmetrically mounted on both side walls in the length direction of the chassis, and a fixed pulley is arranged on the upper end of the fixed block, and the steel cable on the first take-up wheel passes through the two fixed pulleys corresponding to its position in sequence, and the end of the steel cable away from the first take-up wheel is connected to itself through a connecting buckle;
[0013] A bidirectional motor is arranged on the upper end of the counterweight platform through a motor seat, and two first take-up wheels are respectively sleeved on the outer walls of the output shaft on both sides of the bidirectional motor.
[0014] As a preferred technical solution of the present invention, two L-shaped brackets are symmetrically installed on the upper end of the counterweight platform, and supporting ribs are connected between the L-shaped brackets and the counterweight platform. Support shafts are arranged on opposite sides of the two L-shaped brackets, and two linked pulleys are symmetrically rotated on the outer wall of the support shafts, and the steel cable between the first take-up wheel and the fixed pulley is overlapped on the outer wall of the linked pulley.
[0015] As a preferred technical solution of the present invention, the mobile control unit also includes a second take-up wheel, and the outer wall of the output shaft on either side of the bidirectional motor is also sleeved with a second take-up wheel, and the outer wall of the second take-up wheel is wound with an electric wire, one end of the electric wire is connected to the first controller after passing through the support shaft, and the other end is connected to the second controller;
[0016] Moving wheels are installed at the four corners of the lower end of the chassis through connecting frames. The moving direction of the moving wheels is parallel to the wall. A rotating shaft is installed between two opposite moving wheels. A driving motor connected to the rotating shaft is provided on any one of the moving wheels through a motor cover. The driving motor is electrically connected to the first controller. An auxiliary shaft is provided on the side of the turntable close to the inside of the chassis, and the outer wall of any one of the moving wheels and the auxiliary shaft are connected by a belt.
[0017] As a preferred technical solution of the present invention, multiple positioning plates are installed at equal intervals on both side walls in the width direction of the counterweight platform in the opposite direction of its length, a hydraulic cylinder is arranged at the lower end of the positioning plate, the hydraulic cylinder is electrically connected to the second controller, and a driving wheel is arranged at the bottom of the telescopic end of the hydraulic cylinder.
[0018] As a preferred technical solution of the present invention, the telescopic assembly also includes a connecting piece, a connecting piece is installed on the side of the lower end of the nozzle close to the chassis, a spring rod is arranged between the connecting piece and the card seat, a telescopic guide rod is hinged between the connecting piece and the side of the side wall of the telescopic plate away from the nozzle, and an adjustment rod is installed at each of the four corners of the side of the chassis close to the wall, and an auxiliary wheel is rotatably connected to the end of the adjustment rod away from the chassis, and the auxiliary wheel and the detection wheel are flush with each other on the side away from the chassis, and the telescopic assembly also includes a linkage adjustment branch chain arranged inside the telescopic plate;
[0019] The telescopic guide rod is composed of two tilted control reset rods, one of which has a T-slot on its side wall, and the other has a T-slot on its side wall, and the bottoms of the two control reset rods are flush with each other.
[0020] As a preferred technical solution of the present invention, the nozzle has spray holes on one side away from the telescopic rod and around it, two adjacent nozzles are in sliding contact with each other, and the spray holes between the side walls of two adjacent nozzles are sealed and overlapped, and an electric control switch is arranged inside the nozzle.
[0021] Preferably, the linkage adjustment branch chain includes a receiving hole, the upper end of the fixed end of the telescopic plate is provided with a receiving hole, the telescopic end of the telescopic plate is slidably inserted in the receiving hole, and an execution block is installed on the top of the telescopic end of the telescopic plate, an inverted T-shaped hole is provided on the upper end of the execution block, and a plurality of inverted T-shaped holes on the upper ends of the execution blocks are connected with a detachable linkage rod, and the upper half of the execution block and the lower half thereof are slidably matched;
[0022] A receiving groove is provided inside the lower half of the execution block, and an L-shaped top plate is installed on the top wall of the receiving groove. The horizontal section of the L-shaped top plate is located in the middle of the receiving groove. Two through holes connected to the receiving groove are symmetrically provided on the outer wall of the lower half of the execution block along the thickness direction. Triangular clamping blocks are slidably connected inside the through holes. A V-shaped spring clip is connected between the two triangular clamping blocks. The bending corner of the V-shaped spring clip points to the side of the telescopic end away from the telescopic plate. An auxiliary spring is installed between the outer wall of the bending corner of the V-shaped spring clip and the side wall of the receiving groove. The horizontal section of the L-shaped top plate is slidably connected to the inner wall of the bending corner of the V-shaped spring clip. Two reset springs are symmetrically hinged between the bending parts at both ends of the V-shaped spring clip along the horizontal section of the L-shaped top plate.
[0023] Preferably, an electric heating tube is installed on one side of the turntable close to the wall through a heat-resistant plate, and the electric heating tube is located between the two storage chambers.
[0024] In addition, the present invention also provides a construction process for the facade of a building project, comprising the following steps: S1: device installation: firstly installing a counterweight platform on the top of a building body to be sprayed, and then connecting the counterweight platform to a chassis;
[0025] S2: Wall spraying: The lifting unit controls the lifting of the chassis. During the descent process, the spraying unit sprays the primer and mortar in sequence. After spraying the primer, the electric heating tube dries it, and then sprays the mortar.
[0026] S3: Window sill spraying: When encountering a window sill, the spray unit extends into the window sill and sprays the inner wall of the window sill. Then the spray unit is retracted from the inside of the window sill and continues to spray the wall;
[0027] S4: Device movement: After the chassis lands on the ground, the mobile control unit controls the chassis and the counterweight platform to move synchronously in a direction parallel to the wall;
[0028] S5: The device reverses and continues spraying: After the movement is completed, the spraying unit rotates 180 degrees, and then the lifting unit drives the chassis to rise to continue spraying the wall.
[0029] In summary, the present application includes at least one of the following beneficial technical effects:
[0030] 1. The present invention controls the rise or fall of the chassis through a lifting unit, during which the primer and mortar are sprayed on the building facade in turn through the upper and lower groups of nozzles on the chassis, thereby achieving simultaneous spraying of the primer and mortar, and after the primer spraying is completed, it can be heated and dried in time, so that the mortar is directly sprayed, without waiting for the primer to dry naturally, effectively improving work efficiency.
[0031] 2. When the present invention encounters a window during the spraying process, multiple nozzles and detection wheels with the same width as the window extend into the window under the thrust of the spring rod to spray the inner wall of the window. When the nozzle moves to the bottom of the window, the lower end of the telescopic guide rod contacts the bottom of the window. Then, under the dual action of the gravity of the chassis and the squeezing force of the bottom of the window, the telescopic guide rod drives the nozzle to retract and reset and continue spraying the wall, without the need for manual spraying of the window again.
[0032] 3. After the chassis rises to the top or lands on the ground, the mobile control unit controls the chassis and the counterweight platform to move synchronously in a horizontal direction parallel to the wall. During the movement, the spraying unit rotates 180 degrees, and then the lifting unit drives the chassis to rise to continue spraying the wall, thereby continuing the operation.
[0033] 4. The present invention controls the distance between the nozzle and the building facade by adjusting the branch chain in linkage. First, the linkage rod is installed at the bottom of the inverted T-shaped hole, and it is pulled in the direction to be adjusted to adjust the distance between the nozzle and the building facade to meet the spraying requirements of primers and mortars of different materials. BRIEF DESCRIPTION OF THE DRAWINGS
[0034] The present invention is further described below in conjunction with the accompanying drawings and embodiments.
[0035] Figure 1 It is a structural schematic diagram of the present invention.
[0036] Figure 2 It is a first structural schematic diagram of the spraying unit of the present invention.
[0037] Figure 3 It is a second structural schematic diagram of the spraying unit of the present invention.
[0038] Figure 4 The present invention Figure 3 A partial enlarged view of point A.
[0039] Figure 5 It is a structural schematic diagram of the telescopic rod, the spray head and the telescopic assembly of the present invention.
[0040] Figure 6 It is a structural schematic diagram of the lifting unit of the present invention.
[0041] Figure 7 It is a structural schematic diagram of the mobile control unit of the present invention.
[0042] Figure 8 It is a schematic diagram of the structure between the nozzle and the linkage adjustment branch chain of the present invention.
[0043] Fig. 9 The present invention Figure 8 A partial enlarged view of point B.
[0044] In the figure: 1. chassis; 2. counterweight platform; 21. L-shaped bracket; 22. support rib; 23. support shaft; 24. linkage pulley; 3. spray unit; 31. storage barrel; 32. turntable; 321. heat-resistant plate; 322. electric heating tube; 33. storage chamber; 34. connecting hose; 35. pressure pump; 36. holder; 37. telescopic rod; 38. nozzle; 381. spray hole; 39. telescopic assembly; 391. telescopic plate; 392. detection wheel; 393. connector; 394. spring rod; 395. telescopic guide rod; 396. adjustment rod; 397. auxiliary wheel; 398. linkage adjustment branch chain; 399. control reset rod; 400. T-slot; 401. T-bar; 402. storage hole ; 403, triangular rack; 404, execution block; 405, inverted T-shaped hole; 406, connecting rod; 407, accommodating groove; 408, L-shaped top plate; 409, triangular clamp block; 410, V-shaped spring; 411, auxiliary spring; 412, reset spring; 5, lifting unit; 51, first take-up wheel; 52, steel cable; 53, fixed block; 54, fixed pulley; 55, connecting buckle; 56, bidirectional motor; 6, mobile control unit; 61, first controller; 62, second controller; 63, second take-up wheel; 64, electric wire; 65, connecting frame; 66, moving wheel; 67, rotating shaft; 68, driving motor; 69, auxiliary shaft; 70, belt; 71, positioning plate; 72, hydraulic cylinder; 73, driving wheel. DETAILED DESCRIPTION
[0045] The following is combined with Figure 1-Figure 9 While embodiments of the invention have been described in detail, the invention can be implemented in many different ways as defined and covered by the claims.
[0046] The embodiment of the present application discloses a device for the exterior facade construction of a building project, which explains that the device for the exterior facade construction of a building project is mainly used in the process of spraying the exterior facade of a building project. In terms of technical effect, the rise or fall of the chassis 1 can be controlled. During this period, the primer and mortar are sprayed on the exterior facade of the building in turn through the upper and lower groups of nozzles 38 on the chassis 1, thereby achieving simultaneous spraying of the primer and mortar, and effectively improving work efficiency; especially in the process of spraying, when encountering a window sill, the spraying unit 3 will extend into the window sill and spray the inner wall of the window, and then the spraying unit 3 will be retracted from the inside of the window and continue to spray the wall. Furthermore, the device for the exterior facade construction of a building project can also control the chassis 1 and the counterweight platform 2 to move horizontally in a direction parallel to the wall after the chassis 1 rises to the top or falls to the ground. During the movement, the spraying unit 3 rotates 180 degrees, and then the lifting unit 5 drives the chassis 1 to rise or fall, and continues to spray the wall, thereby continuing the operation.
[0047] Embodiment 1:
[0048] Reference Figure 1 As shown, a building facade construction device includes a chassis 1 and a counterweight platform 2. A spray unit 3 is installed on the chassis 1 close to the wall side, a lifting unit 5 matched with the spray unit 3 is arranged on the counterweight platform 2, and a mobile control unit 6 is installed between the chassis 1 and the counterweight platform 2.
[0049] During the specific implementation process, the counterweight platform 2 is first installed on the top of the building that needs to be sprayed, and then the counterweight platform 2 is connected to the chassis 1. The lifting and lowering of the chassis 1 is then controlled by the lifting unit 5. During the descent, the spraying unit 3 sprays primer and mortar in sequence. After spraying the primer, it is dried by the spraying unit 3, and then the mortar is sprayed. After the chassis 1 falls to the ground, the mobile control unit 6 will control the chassis 1 and the counterweight platform 2 to move horizontally in a direction parallel to the wall synchronously, and then the chassis 1 continues to rise and continue spraying.
[0050] Reference Figure 2 and Figure 3As shown, since the building facade needs to be sprayed with a primer for improving adhesion before spraying mortar, the primer and mortar are sprayed in sequence, which increases the workload and reduces the work efficiency. In order to solve this problem, a spray unit 3 capable of spraying primer and mortar at the same time is provided in the present embodiment. Specifically, the spray unit 3 includes a storage barrel 31. Two storage barrels 31 for storing primer and mortar respectively are installed inside the chassis 1. A turntable 32 is rotatably installed on the side of the chassis 1 close to the wall. Two storage chambers 33 are symmetrically installed on the side of the turntable 32 away from the storage barrel 31. Any storage barrel 31 and the storage chamber 33 on the upper side of the turntable 32 and another storage barrel 31 and the storage chamber 33 on the lower side of the turntable 32 are connected by a connecting hose 34. A pressure pump 35 is installed at the connection between the storage barrel 31 and the connecting hose 34; an electric heating pipe 322 is installed on the side of the turntable 32 close to the wall through a heat-resistant plate 321, and the electric heating pipe 322 is located between the two storage chambers 33.
[0051] Furthermore, in this embodiment, two holders 36 that are symmetrically connected to the side walls of the storage chamber 33 are provided on the upper and lower side walls of the turntable 32. The storage chamber 33 can be limited and fixed by the holders 36 to prevent the storage chamber 33 from falling when it bears the weight of the primer and mortar; a nozzle 38 is installed on the side of the storage chamber 33 away from the chassis 1 through a plurality of telescopic rods 37 arranged at equal intervals along the length direction, and a telescopic assembly 39 is installed between the nozzle 38 and the holder 36.
[0052] In the specific implementation process, before spraying the wall, the pressure pump 35 is started, and the pressure pump 35 draws the primer and mortar in the two storage barrels 31 into the connecting hose 34 connected thereto, and discharges them into the upper and lower storage chambers 33 respectively, so that the primer enters the storage chamber 33 on the lower side of the turntable 32, and the mortar enters the storage chamber 33 on the upper side of the turntable 32, and then the primer and mortar enter the nozzle 38 through the telescopic rod 37 connected to the storage chamber 33 respectively; then the lifting unit 5 controls the downward movement of the chassis 1, starts the nozzle 38, and sprays the primer and mortar on the building facade in turn through the nozzles 38 on the upper and lower storage chambers 33, thereby realizing the simultaneous spraying of the primer and mortar, and after the primer spraying is completed, the electric heating tube 322 will heat and dry the primer, so as to facilitate the direct spraying of the mortar without waiting for the primer to dry naturally, thereby effectively improving the work efficiency.
[0053] During this period, the telescopic assembly 39 facilitates the vertical lifting of the chassis 1 along the building facade, and ensures that the spray head 38 sprays the inner wall of the window of the building facade, so that there is no dead angle for spraying.
[0054] Reference Figure 3 , Figure 4 and Figure 5As shown, in order to facilitate the spraying of primer and mortar on the windows of the building facade, the nozzle 38 needs to be extended into the inside of the window, and the nozzle 38 needs to be automatically retracted after the spraying is completed; based on this, the present embodiment provides a telescopic assembly 39 for spraying the inside of the window, specifically, the telescopic assembly 39 includes a detection wheel 392 arranged on the side of the nozzle 38 away from the telescopic rod 37 through a telescopic plate 391, and the telescopic assembly 39 also includes a connecting piece 393, and the connecting piece 393 is installed on the side of the lower end of the nozzle 38 close to the chassis 1, and a spring rod 394 is arranged between the connecting piece 393 and the holder 36, and the spring rod 394 always presses the connecting piece 393 The nozzle 38 applies a thrust directed toward the side away from the chassis 1. When the chassis 1 moves down along the building facade, the detection wheel 392 on the nozzle 38 rolls against the building facade under the action of the thrust. A telescopic guide rod 395 is hinged between the connecting piece 393 and the side wall of the telescopic plate 391 away from the nozzle 38. Adjustment rods 396 are installed at the four corners of the chassis 1 close to the wall. The end of the adjustment rod 396 away from the chassis 1 is rotatably connected to an auxiliary wheel 397. The auxiliary wheel 397 is flush with the side of the detection wheel 392 away from the chassis 1. The telescopic assembly 39 also includes a linkage adjustment branch chain 398 arranged inside the telescopic plate 391.
[0055] In the specific implementation process, when spraying the wall, the detection wheel 392 at the front end of the telescopic plate 391 will be close to the wall due to the weight of the chassis 1. At the same time, the four auxiliary wheels 397 on the chassis 1 will be close to the wall together with the detection wheel 392 to assist the overall stability of the chassis 1 during operation. The distance between the auxiliary wheel 397 and the chassis 1 can be adjusted by the adjusting rod 396, and the distance between the nozzle 38 and the building facade can be controlled according to the spraying requirements. Finally, the adjusting rod 396 can be automatically locked to ensure that the distance between the chassis 1 and the building facade does not change.
[0056] When the detection wheel 392 on the lower side of the overall chassis 1 passes the top of the window, multiple nozzles 38 and the detection wheel 392 with the same width as the window extend into the inner side of the window under the thrust of the spring rod 394, thereby spraying the inner wall of the window from top to bottom through the nozzle 38; in addition, the nozzles 38 for spraying primer and mortar can extend into the inner side of the window and spray them when passing through the window; when the nozzle 38 moves to the bottom of the window, the lower end of the telescopic guide rod 395 contacts the bottom of the window, so that under the dual action of the gravity of the chassis 1 and the squeezing force of the bottom of the window, the telescopic guide rod 395 drives the nozzle 38 to retract and reset, thereby completing the spraying of the inside of the window, and then the chassis 1 drives the nozzle 38 to continue to move downward and spray the exterior facade of the building.
[0057] It should be noted that the telescopic guide rod 395 is composed of two control reset rods 399 arranged obliquely, and a T-shaped slot 400 is provided on the side wall of any one of the control reset rods 399, and a T-shaped bar 401 slidably docked in the T-shaped slot 400 is installed on the side wall of the other control reset rod 399; when the detection wheel 392 is retracted and reset from the inside of the window, the telescopic guide rod 395 composed of the two control reset rods 399 can guide the detection wheel 392, and the bottoms of the two control reset rods 399 are flush with each other, thereby reducing the friction between the window and avoiding damage to the primer sprayed on the window.
[0058] It should be further explained that, in the present embodiment, the side of the nozzle 38 away from the telescopic rod 37 and its surroundings are provided with spray holes 381, two adjacent nozzles 38 slide against each other, and the spray holes 381 between the side walls of the two adjacent nozzles 38 overlap in a closed manner, and an electric control switch is provided inside the nozzle 38; therefore, when the ends of the two adjacent nozzles 38 are flush with each other, the spray holes 381 on their side walls overlap, and the electric control switch is in the off state, at which time only the spray holes 381 at the end of the nozzle 38 away from the telescopic rod 37 can carry out spraying.
[0059] On the contrary, when the nozzle 38 needs to spray the window, the nozzle 38 extending into the inner side of the window and the spray hole 381 of the side wall of the nozzle 38 not extending into the inner side of the window are in an open state. At this time, under the action of the nozzle 38, the telescopic rod 37 is in an extended state, so that the electric control switch is in an open state, thereby controlling the spray holes 381 around the nozzle 38 extending into the inner side of the window to open, and the spray holes 381 at one end of the nozzle 38 away from the telescopic rod 37 are closed. In addition, the overlapping spray holes 381 between the multiple nozzles 38 extending into the inner side of the window are also in a closed state, thereby realizing the spraying operation on the inner wall of the window.
[0060] Reference Figure 6 and Figure 7 As shown, in order to facilitate the spraying of primer and mortar on the wall of the building facade, the chassis 1 needs to be lifted and lowered; based on this, a lifting unit 5 for lifting the chassis 1 is provided in this embodiment. Specifically, the lifting unit 5 includes a first take-up wheel 51 installed on the upper end of the counterweight platform 2 through a support frame, and a steel cable 52 is wound around the outer wall of the first take-up wheel 51. The end of the steel cable 52 away from the first take-up wheel 51 is connected to the chassis 1, and two side walls in the length direction of the chassis 1 are symmetrically installed with two fixed blocks 53 corresponding to the position of the first take-up wheel 51, and a fixed pulley 54 is arranged on the upper end of the fixed block 53. The steel cable 52 on the first take-up wheel 51 passes through the two fixed pulleys 54 corresponding to its position in turn, and the end of the steel cable 52 away from the first take-up wheel 51 is connected to itself through a connecting buckle 55; a bidirectional motor 56 is arranged on the upper end of the counterweight platform 2 through a motor seat, and the two first take-up wheels 51 are respectively sleeved on the outer walls of the output shaft on both sides of the bidirectional motor 56.
[0061] Furthermore, in this embodiment, two L-shaped brackets 21 are symmetrically installed on the upper end of the counterweight platform 2, and a support rib 22 is connected between the L-shaped bracket 21 and the counterweight platform 2. Support shafts 23 are arranged on opposite sides of the two L-shaped brackets 21. Two linkage pulleys 24 are symmetrically rotated on the outer wall of the support shaft 23, and the steel cable 52 between the first take-up wheel 51 and the fixed pulley 54 is overlapped on the outer wall of the linkage pulley 24.
[0062] During the specific implementation process, the bidirectional motor 56 is started, and the bidirectional motor 56 drives the first take-up wheel 51 to rotate. The first take-up wheel 51 drives the chassis 1 to move upward through the cooperation between the steel cable 52 and the fixed pulley 54. At this time, the nozzle 38 on the chassis 1 can spray the building facade; after the chassis 1 rises to the top of the building facade, the counterweight platform 2 and the chassis 1 are driven by the mobile control unit 6 to move horizontally along the wall as a whole, and then the bidirectional motor 56 drives the first take-up wheel 51 to rotate in the opposite direction, and the first take-up wheel 51 unwinds the steel cable 52. At this time, the chassis 1 descends under the action of its own gravity and drives the nozzle 38 to spray the building facade. In this way, the chassis 1 can cooperate with the nozzle 38 to spray the building facade during the rising and falling processes, which can effectively reduce the workload and improve work efficiency.
[0063] It should be noted that while the chassis 1 is rising and falling, the second take-up wheel 63 on the output shaft of the bidirectional motor 56 rotates synchronously with the first take-up wheel 51, so that the second take-up wheel 63 winds and unwinds the wire 64, preventing the wire 64 from getting tangled due to being too long or breaking due to being too short, thereby causing safety hazards.
[0064] Reference Figure 7 As shown, in order to facilitate continuous and efficient operation on the wall of the building's exterior facade, the chassis 1 needs to rise to the top of the building or move horizontally along the building when it descends to the ground, so that the chassis 1 can drive the nozzle 38 to continue spraying operations; based on this, a mobile control unit 6 is provided in this embodiment, specifically, the mobile control unit 6 includes a first controller 61 arranged at the upper end of the chassis 1 and a second controller 62 installed at the upper end of the counterweight platform 2, the mobile control unit 6 also includes a second take-up wheel 63, the outer wall of the output shaft on either side of the bidirectional motor 56 is also sleeved with a second take-up wheel 63, the outer wall of the second take-up wheel 63 is wound with an electric wire 64, one end of the electric wire 64 is connected to the first controller 61 after passing through the support shaft 23, and the other end is connected to the second controller 62.
[0065] Furthermore, in this embodiment, moving wheels 66 are installed at the four corners of the lower end of the chassis 1 through a connecting frame 65, the moving direction of the moving wheels 66 is parallel to the wall, a rotating shaft 67 is installed between two opposite moving wheels 66, and a driving motor 68 connected to the rotating shaft 67 is provided on any one of the moving wheels 66 through a motor cover, and the driving motor 68 is electrically connected to the first controller 61, and an auxiliary shaft 69 is provided on the side of the turntable 32 close to the inside of the chassis 1, and the outer wall of any one of the moving wheels 66 and the auxiliary shaft 69 are connected by a belt 70.
[0066] Furthermore, in the present embodiment, a plurality of positioning plates 71 are installed at equal intervals on both side walls in the width direction of the counterweight platform 2 in the opposite direction along its length, a hydraulic cylinder 72 is provided at the lower end of the positioning plate 71, the hydraulic cylinder 72 is electrically connected to the second controller 62, and a driving wheel 73 is provided at the bottom of the telescopic end of the hydraulic cylinder 72.
[0067] During the specific implementation process, when the chassis 1 rises to the top of the building, the first controller 61 transmits a signal to the second controller 62, and the second controller 62 controls multiple hydraulic cylinders 72 to start at the same time, and the telescopic end of the hydraulic cylinder 72 extends and controls the driving wheel 73 to contact the top of the building. At this time, the hydraulic cylinder 72 lifts the counterweight platform 2 upward and maintains a certain distance from the top of the building. Then the second controller 62 controls the driving wheel 73 to rotate and drive the counterweight platform 2 and the chassis 1 to move horizontally along the wall as a whole. The horizontal movement distance of the counterweight platform 2 and the chassis 1 is equal to the length of the chassis 1. Then the telescopic end of the hydraulic cylinder 72 is retracted, so that the counterweight platform 2 is in contact with the top of the building again.
[0068] When the chassis 1 descends to the ground, the driving wheel 73 comes into contact with the ground. At this time, the first controller 61 controls the driving motor 68 to start, and the driving motor 68 drives the moving wheel 66 to rotate through the rotating shaft 67, so that the moving wheel 66 drives the chassis 1 to move horizontally along the wall. At this time, the counterweight platform 2 moves horizontally synchronously under the action of the driving wheel 73.
[0069] It should be noted that when the chassis 1 rises to the top of the building and descends to the ground and moves horizontally, the drive motor 68 will drive the rotating shaft 67 to rotate, and the rotating shaft 67 drives the auxiliary shaft 69 and the turntable 32 to rotate synchronously through the belt 70, so that the turntable 32 rotates 180 degrees, and the storage chamber 33, the nozzle 38 and the detection wheel 392 on the turntable 32 all move 180 degrees in a circumferential direction to achieve the flipping of the nozzle 38. Then the drive motor 68 stops running. At this time, the chassis 1 descends, and the nozzle 38 can also spray the facade of the building; thereby, the chassis 1 can move horizontally along the facade of the building in sequence during the rising and falling process, so that the facade of the building can be fully sprayed, and work efficiency can be improved.
[0070] It should be further explained that when the chassis 1 rises to the top of the building, the drive motor 68 will control the turntable 32 to rotate in the opposite direction of the movement direction of the counterweight platform 2 through the rotating shaft 67 and the auxiliary shaft 69 to prevent the turntable 32 from continuing to rotate in the same direction and causing the connecting hose 34 to be entangled.
[0071] Embodiment 2:
[0072] Reference Figure 8 and Fig. 9 As shown, on the basis of the first embodiment, in order to facilitate the spraying needs of different wall surfaces; since the primer and mortar materials that need to be sprayed on different wall surfaces are different, the distance between the nozzle 38 and the wall surface needs to be adjusted when spraying the primer and mortar; based on this, the present embodiment provides a specific linkage adjustment branch chain 398, specifically, the linkage adjustment branch chain 398 includes a storage hole 402, and the upper end of the fixed end of the telescopic plate 391 is provided with a storage hole 402, the telescopic end of the telescopic plate 391 is slidably inserted in the storage hole 402, and the upper sides of the inner walls on both sides of the width direction of the storage hole 402 are provided with multiple triangular racks 403 at equal intervals along the length direction, and an execution block 404 is installed on the top of the telescopic end of the telescopic plate 391, and an inverted T-shaped hole 405 is opened on the upper end of the execution block 404, and the inverted T-shaped holes 405 on the upper ends of the multiple execution blocks 404 are connected with a detachable linkage rod 406, and the upper half of the execution block 404 is slidably matched with the lower half.
[0073] Further, in this embodiment, a receiving groove 407 is provided inside the lower half of the execution block 404, and an L-shaped top plate 408 is installed on the top wall of the receiving groove 407. The horizontal section of the L-shaped top plate 408 is located in the middle of the receiving groove 407. Two through holes connected to the receiving groove 407 are symmetrically provided on the outer wall of the lower half of the execution block 404 along the thickness direction. A triangular clamping block 409 that slides against the triangular rack 403 is slidably connected inside the through hole. The triangular rack 403 is close to the nozzle 38 on one side and the triangular clamping block 409 is away from the nozzle 38 on the other side. One side of 8 is a parallel inclined structure, a V-shaped spring piece 410 is connected between the two triangular blocks 409, the bend of the V-shaped spring piece 410 points to the side of the telescopic end away from the telescopic plate 391, an auxiliary spring 411 is installed between the outer wall of the bend of the V-shaped spring piece 410 and the side wall of the accommodating groove 407, the horizontal section of the L-shaped top plate 408 is slidably abutted against the inner wall of the bend of the V-shaped spring piece 410, and two return springs 412 are symmetrically hinged between the bends at both ends of the V-shaped spring piece 410 along the horizontal section of the L-shaped top plate 408.
[0074] During the specific implementation process, the connecting rod 406 is first installed at the bottom of the multiple inverted T-shaped holes 405, and then the connecting rod 406 is pulled in the direction that needs to be adjusted. When the connecting rod 406 is pulled toward the side close to the detection wheel 392, the triangular clamping block 409 will shrink into the through hole under the extrusion pressure of the triangular rack 403; when the telescopic plate 391 is adjusted to a suitable length, the connecting rod 406 is released, and the triangular clamping block 409 pops out and engages with the triangular rack 403 under the elastic force of the V-shaped spring piece 410, the return spring 412 and the auxiliary spring 411, so as to facilitate the adjustment of the nozzle 38 to the side away from the building facade. At this time, the distance between the nozzle 38 and the building facade is increased, thereby meeting the spraying requirements of primers and mortars of different materials.
[0075] When the connecting rod 406 is pulled to the side away from the detection wheel 392, the upper half of the execution block 404 drives the L-shaped top plate 408 to push the V-shaped spring piece 410, and the V-shaped spring piece 410 drives the triangular clamping block 409 to shrink into the through hole; when the telescopic plate 391 is adjusted to a suitable length, the connecting rod 406 is released, and the triangular clamping block 409 also pops out to engage with the triangular rack 403, so as to facilitate the adjustment of the nozzle 38 to the side close to the building facade. At this time, the distance between the nozzle 38 and the building facade is reduced; then the connecting rod 406 can be taken out from the inverted T-shaped hole 405.
[0076] In addition, when the linkage rod 406 adjusts the length of the telescopic plate 391 , the telescopic guide rod 395 will be adaptively telescoped accordingly.
[0077] In addition, the present invention also provides a construction process for the exterior facade of a building project, comprising the following steps:
[0078] S1: Device installation: First, install the counterweight platform 2 on the top of the building that needs to be sprayed, and then connect the counterweight platform 2 to the chassis 1.
[0079] S2: Wall spraying: Before spraying the wall, start the pressure pump 35, which draws the primer and mortar in the two storage barrels 31 into the connecting hoses 34 connected thereto, and discharges them into the upper and lower storage chambers 33, respectively, so that the primer enters the storage chamber 33 on the lower side of the turntable 32, and the mortar enters the storage chamber 33 on the upper side of the turntable 32.
[0080] Start the bidirectional motor 56, which drives the first take-up wheel 51 to rotate. The first take-up wheel 51 winds and unwinds the steel cable 52 in turn. The first take-up wheel 51 drives the chassis 1 to move upward or downward in turn through the cooperation between the steel cable 52 and the fixed pulley 54; during this period, start the nozzle 38, and spray the primer and mortar on the wall in turn through the nozzles 38 on the upper and lower storage chambers 33, so as to achieve simultaneous spraying of the primer and mortar, and after the primer spraying is completed, the electric heating tube 322 will heat and dry the primer, so as to facilitate direct spraying of the mortar without waiting for the primer to dry naturally; in this way, the chassis 1 can cooperate with the nozzle 38 to spray the building facade during the rising and falling processes, which can effectively reduce the workload and improve work efficiency.
[0081] S3: Window sill spraying: When the detection wheel 392 on the lower side of the integral chassis 1 passes the top of the window, a plurality of nozzles 38 and the detection wheel 392 having the same width as the window extend into the inner side of the window under the thrust of the spring rod 394, thereby spraying the inner side wall of the window from top to bottom through the nozzles 38; in addition, the nozzles 38 for spraying primer and mortar can extend into the inner side of the window and spray them when passing through the window.
[0082] When the nozzle 38 moves to the bottom of the window, the lower end of the telescopic guide rod 395 contacts the bottom of the window. Therefore, under the dual effects of the gravity of the chassis 1 and the squeezing force of the bottom of the window, the telescopic guide rod 395 drives the nozzle 38 to retract and reset, thereby completing the spraying of the inside of the window. Then the chassis 1 drives the nozzle 38 to continue to move downward and spray the exterior facade of the building.
[0083] S4: Device movement: When the chassis 1 rises to the top of the building, the first controller 61 transmits a signal to the second controller 62, and the second controller 62 controls multiple hydraulic cylinders 72 to start at the same time, and the telescopic end of the hydraulic cylinder 72 extends and controls the driving wheel 73 to contact the top of the building. At this time, the hydraulic cylinder 72 lifts the counterweight platform 2 upward and keeps a certain distance from the top of the building. Then the second controller 62 controls the driving wheel 73 to rotate and drive the counterweight platform 2 and the chassis 1 to move horizontally along the wall as a whole. The horizontal movement distance of the counterweight platform 2 and the chassis 1 is equal to the length of the chassis 1. Then the telescopic end of the hydraulic cylinder 72 is retracted, so that the counterweight platform 2 contacts the top of the building again; then the lifting unit 5 controls the chassis 1 to descend and continue spraying.
[0084] When the chassis 1 descends to the ground, the driving wheel 73 comes into contact with the ground. At this time, the first controller 61 controls the driving motor 68 to start, and the driving motor 68 drives the moving wheel 66 to rotate through the rotating shaft 67, so that the moving wheel 66 drives the chassis 1 to move horizontally along the wall. At this time, the counterweight platform 2 moves horizontally synchronously under the action of the driving wheel 73; then the lifting unit 5 controls the chassis 1 to rise and continue spraying.
[0085] S5: The device reverses and continues spraying: When the chassis 1 rises to the top of the building or descends to the ground and moves horizontally, the drive motor 68 will drive the shaft 67 to rotate, and the shaft 67 drives the auxiliary shaft 69 and the turntable 32 to rotate synchronously through the belt 70, so that the turntable 32 rotates 180 degrees, and the storage chamber 33, the nozzle 38 and the detection wheel 392 on the turntable 32 all move 180 degrees in a circumferential direction to achieve the flipping of the nozzle 38, and then the drive motor 68 stops running. At this time, the chassis 1 descends or rises, and the nozzle 38 can also spray the facade of the building; thereby, the chassis 1 can move horizontally along the facade of the building in sequence during the rising and falling process, so that the facade of the building can be fully sprayed, and work efficiency can be improved.
[0086] It will be apparent to those skilled in the art that the invention is not limited to the details of the exemplary embodiments described above and that the invention can be implemented in other specific forms without departing from the spirit or essential features of the invention. Therefore, the embodiments should be considered exemplary and non-limiting in all respects, and the scope of the invention is defined by the appended claims rather than the foregoing description, and it is intended that all variations falling within the meaning and scope of the equivalent elements of the claims be included in the invention. Any reference numeral in a claim should not be considered as limiting the claim to which it relates.
[0087] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.
Claims
1. A building facade construction device, comprising a chassis (1) and a counterweight platform (2), characterized in that: A spraying unit (3) is installed on the side of the chassis (1) close to the wall, and a lifting unit (5) cooperating with the spraying unit (3) is arranged on the counterweight platform (2). The lifting unit (5) comprises a first take-up wheel (51) installed on the upper end of the counterweight platform (2) via a support frame, a steel cable (52) is wound around the outer wall of the first take-up wheel (51), and an end of the steel cable (52) away from the first take-up wheel (51) is connected to the chassis (1). A mobile control unit (6) is installed between the chassis (1) and the counterweight platform (2), and the mobile control unit (6) comprises a first controller (61) arranged on the upper end of the chassis (1) and a second controller (62) installed on the upper end of the counterweight platform (2), wherein: The spraying unit (3) comprises a storage barrel (31). Two storage barrels (31) for storing primer and mortar respectively are installed inside the chassis (1). A turntable (32) is rotatably installed on a side of the chassis (1) close to the wall. Two material storage chambers (33) are symmetrically installed on the side of the turntable (32) away from the storage barrels (31). Any storage barrel (31) and the material storage chamber (33) on the upper side of the turntable (32), as well as another storage barrel (31) and the material storage chamber (33) on the lower side of the turntable (32) are connected by a connecting hose (34). The storage barrels (31) are connected to the storage chamber (33) on the upper side of the turntable (32). A pressure pump (35) is installed at the connection between the rotating disk (32) and the connecting hose (34), two clamping seats (36) are symmetrically arranged on the upper and lower sides of the side wall of the material storage chamber (33), and the side of the material storage chamber (33) away from the chassis (1) is equipped with a nozzle (38) through a plurality of telescopic rods (37) arranged at equal intervals along the length direction, and a telescopic assembly (39) is installed between the nozzle (38) and the clamping seat (36), and the telescopic assembly (39) includes a detection wheel (392) arranged on the side of the nozzle (38) away from the telescopic rod (37) through a telescopic plate (391).
2. A building facade construction device according to claim 1, characterized in that: The lifting unit (5) further comprises a fixed block (53), and two fixed blocks (53) corresponding to the positions of the first take-up wheel (51) are symmetrically mounted on both side walls in the length direction of the chassis (1), and a fixed pulley (54) is arranged on the upper end of the fixed block (53), and the steel cable (52) on the first take-up wheel (51) passes through the two fixed pulleys (54) corresponding to its position in sequence, and the end of the steel cable (52) away from the first take-up wheel (51) is connected to itself via a connecting buckle (55); A bidirectional motor (56) is arranged at the upper end of the counterweight platform (2) via a motor seat, and two first wire take-up wheels (51) are respectively sleeved on the outer walls of the output shaft on both sides of the bidirectional motor (56).
3. A building facade construction device according to claim 1, characterized in that: Two L-shaped brackets (21) are symmetrically mounted on the upper end of the counterweight platform (2); a support rib (22) is connected between the L-shaped bracket (21) and the counterweight platform (2); a support shaft (23) is arranged on opposite sides of the two L-shaped brackets (21); two linkage pulleys (24) are symmetrically rotatably sleeved on the outer wall of the support shaft (23); and a steel cable (52) between the first take-up wheel (51) and the fixed pulley (54) is overlapped on the outer wall of the linkage pulley (24).
4. A building facade construction device according to claim 1, characterized in that: The mobile control unit (6) further comprises a second wire take-up wheel (63), the outer wall of the output shaft on either side of the bidirectional motor (56) is also sleeved with the second wire take-up wheel (63), the outer wall of the second wire take-up wheel (63) is wound with an electric wire (64), one end of the electric wire (64) is connected to the first controller (61) after passing through the support shaft (23), and the other end is connected to the second controller (62); Moving wheels (66) are installed at the four corners of the lower end of the chassis (1) through a connecting frame (65); the moving direction of the moving wheels (66) is parallel to the wall surface; a rotating shaft (67) is installed between two opposing moving wheels (66); a driving motor (68) connected to the rotating shaft (67) is arranged on any one of the moving wheels (66) through a motor cover; the driving motor (68) is electrically connected to the first controller (61); an auxiliary shaft (69) is arranged on one side of the turntable (32) close to the inside of the chassis (1); and an outer wall of any one of the moving wheels (66) and the auxiliary shaft (69) are connected via a belt (70).
5. The building facade construction device according to claim 1, characterized in that: A plurality of positioning plates (71) are installed at equal intervals on both side walls in the width direction of the counterweight platform (2) in the opposite direction of its length, a hydraulic cylinder (72) is arranged at the lower end of the positioning plate (71), the hydraulic cylinder (72) is electrically connected to the second controller (62), and a driving wheel (73) is arranged at the bottom of the telescopic end of the hydraulic cylinder (72).
6. A building facade construction device according to claim 1, characterized in that: The telescopic assembly (39) further comprises a connecting piece (393), the connecting piece (393) being installed on a side of the lower end of the nozzle (38) close to the chassis (1), a spring rod (394) being arranged between the connecting piece (393) and the holder (36), a telescopic guide rod (395) being hingedly connected between the connecting piece (393) and a side of the side wall of the telescopic plate (391) away from the nozzle (38), an adjustment rod (396) being installed on each of the four corners of the side of the chassis (1) close to the wall, an auxiliary wheel (397) being rotatably connected to an end of the adjustment rod (396) away from the chassis (1), the auxiliary wheel (397) being flush with a side of the detection wheel (392) away from the chassis (1), and the telescopic assembly (39) further comprises a linkage adjustment branch chain (398) arranged inside the telescopic plate (391); The telescopic guide rod (395) is composed of two control reset rods (399) arranged obliquely, a T-shaped slot (400) is provided on the side wall of any one of the control reset rods (399), and a T-shaped strip (401) slidably docked in the T-shaped slot (400) is installed on the side wall of the other control reset rod (399), and the bottoms of the two control reset rods (399) are flush with each other.
7. A building facade construction device according to claim 1, characterized in that: The spray head (38) is provided with spray holes (381) on one side away from the telescopic rod (37) and around its periphery. Two adjacent spray heads (38) are in sliding contact with each other, and the spray holes (381) between the side walls of the two adjacent spray heads (38) are sealed and overlapped. An electric control switch is provided inside the spray head (38).
8. The building facade construction device according to claim 6, characterized in that: The linkage adjustment branch chain (398) comprises a storage hole (402), the upper end of the fixed end of the telescopic plate (391) is provided with the storage hole (402), the telescopic end of the telescopic plate (391) is slidably inserted in the storage hole (402), the upper sides of the inner walls on both sides of the width direction of the storage hole (402) are provided with a plurality of triangular racks (403) at equal intervals along the length direction, and an execution block (404) is installed on the top of the telescopic end of the telescopic plate (391), the upper end of the execution block (404) is provided with an inverted T-shaped hole (405), the inverted T-shaped holes (405) at the upper ends of the plurality of execution blocks (404) are connected with a detachable linkage rod (406), and the upper half of the execution block (404) and the lower half thereof are slidably matched; A receiving groove (407) is provided inside the lower half of the execution block (404), and an L-shaped top plate (408) is installed on the top wall of the receiving groove (407). The horizontal section of the L-shaped top plate (408) is located in the middle of the receiving groove (407). Two through holes connected to the receiving groove (407) are symmetrically provided on the outer wall of the lower half of the execution block (404) along the thickness direction. A triangular clamping block (409) that slidably contacts the triangular rack (403) is provided inside the through holes. The triangular rack (403) is close to the nozzle (38) on one side and the triangular clamping block (409) is away from the nozzle (38) on the other side. They are all parallel inclined structures, a V-shaped spring (410) is connected between the two triangular clamping blocks (409), the bend of the V-shaped spring (410) points to the side of the telescopic end away from the telescopic plate (391), an auxiliary spring (411) is installed between the outer wall of the bend of the V-shaped spring (410) and the side wall of the accommodating groove (407), the horizontal section of the L-shaped top plate (408) is slidably abutted against the inner wall of the bend of the V-shaped spring (410), and two return springs (412) are symmetrically hinged between the bends at both ends of the V-shaped spring (410) along the horizontal section of the L-shaped top plate (408).
9. The building facade construction device according to claim 1, characterized in that: An electric heating pipe (322) is installed on one side of the rotating disk (32) close to the wall through a heat-resistant plate (321), and the electric heating pipe (322) is located between the two material storage chambers (33).
10. A construction process for the exterior facade of a building project, comprising the construction device for the exterior facade of a building project as claimed in claim 9, characterized in that: The construction process includes the following steps: S1: Device installation: first install the counterweight platform (2) on the top of the building to be sprayed, and then connect the counterweight platform (2) to the chassis (1); S2: wall spraying: the lifting and lowering of the chassis (1) is controlled by the lifting unit (5), and during the lowering process, the spraying unit (3) sprays the primer and mortar in sequence. After the primer is sprayed, the electric heating pipe (322) dries it, and then the mortar is sprayed; S3: Window sill spraying: When encountering a window sill, the spraying unit (3) extends into the window sill and sprays the inner wall of the window sill. Then the spraying unit (3) is withdrawn from the inside of the window sill and continues to spray the wall; S4: device movement: after the chassis (1) lands on the ground, the movement control unit (6) controls the chassis (1) and the counterweight platform (2) to move synchronously in a horizontal direction parallel to the wall; S5: The device is reversed and spraying continues: After the movement is completed, the spraying unit (3) rotates 180 degrees, and then the lifting unit (5) drives the chassis (1) to rise, and the wall continues to be sprayed.
Citation Information
Patent Citations
Building outer wall surface coating spraying device
CN111219041A
Outer wall protection material spraying device and spraying process thereof
CN113235876A
Exterior wall coating construction equipment and construction method thereof
CN113958095A
Reciprocating type suspension spraying equipment for external wall thermal insulation layer
CN115450403A
Building decoration wall surface spraying device
CN116771070A