A tunnel deformation prediction method and system

By preprocessing, component decomposing and clustering the tunnel deformation monitoring data, and selecting a prediction model based on stationarity judgment, the problem of noise influence in tunnel deformation monitoring is solved, the prediction accuracy and speed are improved, and the tunnel deformation early warning is enhanced. reliability.

CN118606731BActive Publication Date: 2024-10-18JIANGXI TOHUI SCI & TECH SHARES CO LTD
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202411080828.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-08
Publication Date
2024-10-18
Estimated Expiration
2044-08-08

AI Technical Summary

Technical Problem

In the existing tunnel deformation monitoring technology, the data collected by the sensors are noisy due to installation location, weather and other factors, which affects the prediction accuracy, resulting in low accuracy of the tunnel deformation early warning process.

Method used

By preprocessing, component decomposition and search clustering of tunnel deformation monitoring data, the stationarity judgment is obtained and an appropriate prediction model is selected for prediction, filtering out noise and improving prediction accuracy.

Benefits of technology

Effectively filter out data noise, improve prediction accuracy and speed, and improve the reliability of tunnel deformation early warning.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118606731B_ABST
    Figure CN118606731B_ABST
Patent Text Reader

Abstract

The present invention provides a tunnel deformation prediction method and system, the method comprising preprocessing tunnel deformation monitoring data; component decomposition of the processed monitoring data; search and clustering processing of the decomposed monitoring data; inputting historical training data into a first preset model and a second preset model for training respectively; judging whether the deformation feature data is stable, if the deformation feature data is stable, inputting the deformation feature data into the first training prediction model for prediction to output a prediction result, if the deformation feature data is not stable, inputting the deformation feature data into the second training prediction model for prediction to output a prediction result. The present invention can effectively filter out noise existing in the data and some data that is not helpful for prediction, and can improve the model prediction speed and model prediction accuracy.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of tunnel deformation prediction, and in particular relates to a tunnel deformation prediction method and system. Background Art

[0002] During tunnel construction or after the completion of a tunnel, the tunnel itself will be damaged to a certain extent due to external forces, and the damage includes the deformation of the tunnel. Therefore, it is very necessary to predict the deformation of the tunnel before the deformation occurs.

[0003] In the prior art, there is a method of obtaining monitoring data of the tunnel by installing sensors around the tunnel, and performing a series of analyses on the monitoring data to thereby issue an early warning of the deformation of the tunnel. However, in actual situations, the data collected by the sensors contain large noise due to factors such as their installation location, weather, sensor damage, and interruption of monitoring data transmission. If the collected data is directly input into the model for deformation prediction, the actual prediction accuracy will be low, which will affect the early warning process of tunnel deformation. Summary of the invention

[0004] In order to solve the above technical problems, the present invention provides a tunnel deformation prediction method and system for solving the technical problems in the prior art.

[0005] On the one hand, the present invention provides the following technical solution, a tunnel deformation prediction method, comprising:

[0006] Acquiring tunnel deformation monitoring data, and preprocessing the tunnel deformation monitoring data to obtain processed monitoring data;

[0007] Decomposing the processed monitoring data into components to obtain decomposed monitoring data;

[0008] Performing search and clustering processing on the decomposed monitoring data to obtain deformation feature data;

[0009] Acquire historical training data, input the historical training data into a first preset model and a second preset model for training, and output a first training prediction model and a second training prediction model respectively;

[0010] Determine whether the deformation feature data is stable. If the deformation feature data is stable, input the deformation feature data into the first training prediction model for prediction to output a prediction result. If the deformation feature data is not stable, input the deformation feature data into the second training prediction model for prediction to output a prediction result.

[0011] Compared with the prior art, the beneficial effects of the present invention are as follows: the present application first obtains tunnel deformation monitoring data, pre-processes the tunnel deformation monitoring data to obtain processed monitoring data; performs component decomposition on the processed monitoring data to obtain decomposed monitoring data; performs search clustering processing on the decomposed monitoring data to obtain deformation feature data; obtains historical training data, inputs the historical training data into a first preset model and a second preset model for training, and outputs a first training prediction model and a second training prediction model respectively; determines whether the deformation feature data is stable, if the deformation feature data is stable, inputs the deformation feature data into the first training prediction model for prediction to output a prediction result, if the deformation feature data is not stable, inputs the deformation feature data into the second training prediction model for prediction to output a prediction result, the present invention first performs a component decomposition process on the data, which can effectively filter out the noise in the data and some data that is not helpful for prediction, so as to improve the prediction accuracy, and performs search clustering processing on the data, so that the processed data can fully reflect the characteristics of the data itself, which can improve the model prediction speed and the model prediction accuracy.

[0012] Preferably, the step of preprocessing the tunnel deformation monitoring data to obtain processed monitoring data includes: filtering, smoothing and denoising, identifying missing values, and filling missing values ​​on the tunnel deformation monitoring data in sequence to obtain processed monitoring data.

[0013] Preferably, the step of performing component decomposition on the processed monitoring data to obtain decomposed monitoring data comprises:

[0014] Plotting a curve graph of the processed monitoring data in time series, and searching for peak points and trough points appearing in the curve graph;

[0015] The peak point is fitted with the trough point to obtain the peak line With trough line , calculate the fluctuation mean based on the peak line and the trough line :

[0016] ;

[0017] Based on the fluctuation mean Processing monitoring data with Generate volatility data :

[0018] ;

[0019] Determine whether the first fluctuation data meets the decomposition condition, where the decomposition condition is:

[0020] ;

[0021] In the formula, Indicates the first fluctuation data, Indicates Fluctuation data, represents the decomposition threshold;

[0022] If the first fluctuation data meets the decomposition condition, the first fluctuation data is used as the first characteristic component, and the processing monitoring data Subtract the first fluctuation data to obtain a trend component, and perform a decomposition process based on the trend component and the decomposition equation in a loop to obtain several characteristic components, wherein the decomposition equation is:

[0023] ;

[0024] In the formula, Indicates feature components, Indicates trend component;

[0025] The characteristic components are iteratively processed to obtain decomposed monitoring data.

[0026] Preferably, the step of iteratively processing the characteristic components to obtain decomposed monitoring data includes:

[0027] Store some of the characteristic components into a component array In the above example, the component array Shift to baseband to get the shift array :

[0028] ;

[0029] In the formula, is the pulse function, For time, is plural, is the instantaneous frequency;

[0030] Based on the transfer array Constructing the Iteration Equation :

[0031] ;

[0032] In the formula, is the penalty factor, Indicates time Taking partial derivatives, is the Lagrangian operator;

[0033] Iterate the parameters in the iterative equation until the iteration termination condition is met, output the parameters of the last iteration and update the iterative equation by the parameters of the last iteration, and output based on the updated iterative equation Group decomposition monitoring data.

[0034] Preferably, in the step of iteratively calculating the parameters in the iterative equation until an iteration termination condition is satisfied, outputting the parameters of the last iteration, and updating the iterative equation by the parameters of the last iteration, the parameters after iteration include:

[0035] ;

[0036] In the formula, Indicates The component array obtained after iterations, Indicates processing monitoring data The data obtained by Fourier transform is represents the inverse Fourier transform, Indicates The component array obtained after the iteration is transformed into the array obtained by Fourier transformation. represents the Lagrangian operator The operator obtained by Fourier transform is Indicates frequency;

[0037] ;

[0038] In the formula, express The array obtained after Fourier transformation;

[0039] ;

[0040] In the formula, represents the upper noise limit, Indicates The operator obtained by Fourier transform of the Lagrangian operator after iterations.

[0041] Preferably, the step of performing search and clustering processing on the decomposed monitoring data to obtain deformation feature data includes:

[0042] Will Random selection of group decomposition monitoring data The group decomposition monitoring data is used as the cluster center sequence and the remaining Group decomposition monitoring data and The Euclidean distance between each data in the cluster center sequence is used to construct a distance matrix based on the Euclidean distance. :

[0043] ;

[0044] In the formula, Indicates the remaining Any group of decomposition monitoring data in the group decomposition monitoring data Data and The first cluster center in any cluster center sequence in the group cluster center sequence The Euclidean distance between the data;

[0045] Performing a distance search from the first element in the upper left corner to the last element in the lower right corner of the distance matrix, calculating the cumulative value of the optimal Euclidean distance from the first element in the upper left corner to the last element in the lower right corner, and using the cumulative value as the clustering judgment distance;

[0046] Based on the clustering judgment distance, the remaining The monitoring data is divided into the nearest cluster center sequence by group decomposition, and the new cluster center sequence is selected and divided iteratively to obtain Group deformation feature data.

[0047] Preferably, in the step of judging whether the deformation feature data is smooth, if the deformation feature data is smooth, inputting the deformation feature data into the first training prediction model for prediction to output a prediction result; if the deformation feature data is not smooth, inputting the deformation feature data into the second training prediction model for prediction to output a prediction result, the first training prediction model is an ARMA model, and the second training prediction model is an LSTM model.

[0048] In a second aspect, the present invention provides the following technical solution, a tunnel deformation prediction system, the system comprising:

[0049] A preprocessing module, used for acquiring tunnel deformation monitoring data, and preprocessing the tunnel deformation monitoring data to obtain processed monitoring data;

[0050] A decomposition module, used for decomposing the processed monitoring data into components to obtain decomposed monitoring data;

[0051] A clustering module, used for performing search and clustering processing on the decomposed monitoring data to obtain deformation feature data;

[0052] A training module, used for acquiring historical training data, inputting the historical training data into a first preset model and a second preset model for training, and outputting a first training prediction model and a second training prediction model respectively;

[0053] The prediction module is used to determine whether the deformation feature data is stable. If the deformation feature data is stable, the deformation feature data is input into the first training prediction model for prediction to output a prediction result. If the deformation feature data is not stable, the deformation feature data is input into the second training prediction model for prediction to output a prediction result.

[0054] In a third aspect, the present invention provides the following technical solution: a computer comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor implements the tunnel deformation prediction method as described above when executing the computer program.

[0055] In a fourth aspect, the present invention provides the following technical solution: a storage medium having a computer program stored thereon, wherein the computer program implements the tunnel deformation prediction method as described above when executed by a processor. BRIEF DESCRIPTION OF THE DRAWINGS

[0056] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0057] Figure 1 A flow chart of a tunnel deformation prediction method provided in Embodiment 1 of the present invention;

[0058] Figure 2 A structural block diagram of a tunnel deformation prediction system provided in Embodiment 2 of the present invention;

[0059] Figure 3 A schematic diagram of the hardware structure of a computer provided in another embodiment of the present invention.

[0060] The embodiments of the present invention will be further described below with reference to the accompanying drawings. DETAILED DESCRIPTION

[0061] Embodiments of the present invention are described in detail below, examples of which are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the embodiments of the present invention, and should not be construed as limiting the present invention.

[0062] Embodiment 1

[0063] In the first embodiment of the present invention, Figure 1 As shown, a tunnel deformation prediction method includes:

[0064] S1. Acquire tunnel deformation monitoring data, and pre-process the tunnel deformation monitoring data to obtain processed monitoring data;

[0065] Specifically, in step S1, the preprocessing process includes filtering, smoothing and denoising, missing value identification, and missing value filling. The above preprocessing process is a commonly used data processing method in the prior art, so it will not be described in detail here.

[0066] S2, performing component decomposition on the processed monitoring data to obtain decomposed monitoring data;

[0067] Wherein, the step S2 comprises:

[0068] S21, plotting a curve graph of the processed monitoring data in time series, and searching for peak points and trough points appearing in the curve graph;

[0069] Specifically, for processing monitoring data, although it has undergone a preprocessing process, a complete time series data will still have certain fluctuations, and the fluctuating data will have several peaks and troughs when drawing a curve graph.

[0070] S22, fitting the peak point and the trough point to obtain a peak line With trough line , calculate the fluctuation mean based on the peak line and the trough line :

[0071] ;

[0072] Specifically, after obtaining the peak points and trough points respectively, the cubic spline interpolation method can be used to connect and fit several peak points and trough points respectively, and the expressions of the connected curves are respectively , , and then by taking the mean of the two expressions, we can get the fluctuation mean, and the fitting method is.

[0073] S23, based on the fluctuation mean Processing monitoring data with Generate volatility data :

[0074] ;

[0075] Specifically, the toggle data generated here is a new data.

[0076] S24, judging whether the first fluctuation data satisfies the decomposition condition, wherein the decomposition condition is:

[0077] ;

[0078] In the formula, Indicates the first fluctuation data, Indicates Fluctuation data, represents the decomposition threshold;

[0079] in, The value range is 0.2-0.3

[0080] S25. If the first fluctuation data satisfies the decomposition condition, the first fluctuation data is used as the first characteristic component, and the processing monitoring data is Subtract the first fluctuation data to obtain a trend component, and perform a decomposition process based on the trend component and the decomposition equation in a loop to obtain several characteristic components, wherein the decomposition equation is:

[0081] ;

[0082] In the formula, Indicates feature components, Indicates trend component;

[0083] Specifically, after obtaining the fluctuation data, it is necessary to determine whether the fluctuation data meets the decomposition conditions. If not, repeat the above steps. If satisfied, use the first fluctuation data obtained as the first decomposed characteristic component, and then subtract the characteristic component from the original processed monitoring data to obtain the corresponding trend component, which reflects the central trend of the data. Then, according to the expression of the decomposition equation, the decomposition and trend component calculation process can be repeated, and finally M characteristic components are obtained.

[0084] S26, iteratively processing the characteristic components to obtain decomposed monitoring data;

[0085] Wherein, the step S26 specifically includes:

[0086] S261, storing the characteristic components into a component array In the above example, the component array Shift to baseband to get the shift array :

[0087] ;

[0088] In the formula, is the pulse function, For time, is plural, is the instantaneous frequency;

[0089] Specifically, when transferring the component array to the baseband format, each data is transformed by HILbert and then multiplied by the corresponding center frequency to obtain the transfer array.

[0090] S262, based on the transfer array Constructing the Iteration Equation :

[0091] ;

[0092] In the formula, is the penalty factor, Indicates time Taking partial derivatives, is the Lagrangian operator;

[0093] Specifically, the above iterative equation is actually an unconstrained variational function, and the optimal solution of the function can be output by iteratively solving the parameters in the above equation.

[0094] S263, iteratively operate the parameters in the iterative equation until the iteration termination condition is met, output the parameters of the last iteration and update the iterative equation by the parameters of the last iteration, and output the updated iterative equation based on the updated iterative equation. Group decomposition monitoring data;

[0095] The iteration termination condition is:

[0096] ;

[0097] If the component array obtained in the last iteration meets the above conditions, the optimal parameters of the iteration are output. If not, the above iteration process is continued. At the same time, after the iteration is completed, the corresponding number of decomposed monitoring data can be obtained according to the number of characteristic components and the updated iteration equation, that is, Group decomposition monitoring data.

[0098] The parameters after iteration include:

[0099] ;

[0100] In the formula, Indicates The component array obtained after iterations, Indicates processing monitoring data The data obtained by Fourier transform is represents the inverse Fourier transform, Indicates The component array obtained after the iteration is transformed into the array obtained by Fourier transformation. represents the Lagrangian operator The operator obtained by Fourier transform is Indicates frequency;

[0101] ;

[0102] In the formula, express The array obtained after Fourier transformation;

[0103] ;

[0104] In the formula, represents the upper noise limit, Indicates The operator obtained by Fourier transform of the Lagrangian operator after iterations;

[0105] Specifically, since the above parameters are Fourier transformed during the iteration process, when the parameters obtained after the iteration are output, they need to be inversely Fourier transformed to convert the frequency domain data into time domain data.

[0106] S3, performing search and clustering processing on the decomposed monitoring data to obtain deformation feature data;

[0107] Wherein, the step S3 comprises:

[0108] S31. Random selection of group decomposition monitoring data The group decomposition monitoring data is used as the cluster center sequence and the remaining Group decomposition monitoring data and The Euclidean distance between each data in the cluster center sequence is used to construct a distance matrix based on the Euclidean distance. :

[0109] ;

[0110] In the formula, Indicates the remaining Any group of decomposition monitoring data in the group decomposition monitoring data Data and The first cluster center in any cluster center sequence in the group cluster center sequence The Euclidean distance between the data;

[0111] S32, starting from the first element in the upper left corner of the distance matrix to the last element in the lower right corner, performing distance search, calculating the cumulative value of the optimal Euclidean distance from the first element in the upper left corner to the last element in the lower right corner, and using the cumulative value as the clustering judgment distance;

[0112] Specifically, the following conditions must be met during the distance search: first, the path must be from the upper left corner to the lower right corner; second, when searching for the path, the adjacent points must be selected point by point, and the search direction is downward and rightward; third, the search can only be performed step by step, not in any direction, and the element jump search cannot be performed;

[0113] The shortest path is searched element by element, and then the accumulated distance of the searched path is used as the clustering judgment distance.

[0114] S33, based on the clustering judgment distance, the remaining The monitoring data is divided into the nearest cluster center sequence by group decomposition, and the new cluster center sequence is selected and divided iteratively to obtain Group deformation feature data;

[0115] Specifically, after the data is divided, the dist function is used to calculate the similarity between the sequences other than the cluster center sequence in each cluster and the cluster center sequence. The sequence corresponding to the minimum similarity is used as the new cluster center, and the clustering process is iterated until the cluster center sequence in each cluster does not change or is cycled to the preset number of times, and then the output is Group deformation feature data.

[0116] S4, obtaining historical training data, inputting the historical training data into the first preset model and the second preset model for training, and outputting the first training prediction model and the second training prediction model respectively;

[0117] Specifically, the historical training data may be monitoring data collected in previous time periods or monitoring data on tunnel deformation. By inputting the historical training data into the first preset model and the second preset model for training, the first training prediction model and the second training prediction model can be obtained.

[0118] S5, judging whether the deformation feature data is stable, if the deformation feature data is stable, inputting the deformation feature data into the first training prediction model for prediction, so as to output a prediction result, if the deformation feature data is not stable, inputting the deformation feature data into the second training prediction model for prediction, so as to output a prediction result;

[0119] Specifically, in step S5, the first training prediction model is an ARMA model, and the second training prediction model is an LSTM model. First, the autocorrelation coefficient of the deformed feature data is used, and whether the data is stable is judged according to the change amplitude of the autocorrelation coefficient and whether it tends to 0. If the data is stable, the ARMA model can be used for prediction output. If the data is not stable, the LSTM model can be used to predict the data. Selecting different models to predict data according to whether the data is stable can further improve the prediction accuracy.

[0120] The tunnel deformation prediction method provided in the first embodiment of the present invention first obtains tunnel deformation monitoring data, pre-processes the tunnel deformation monitoring data to obtain processed monitoring data; performs component decomposition on the processed monitoring data to obtain decomposed monitoring data; performs search clustering processing on the decomposed monitoring data to obtain deformation feature data; obtains historical training data, inputs the historical training data into a first preset model and a second preset model for training, and outputs a first training prediction model and a second training prediction model respectively; determines whether the deformation feature data is stable, if the deformation feature data is stable, inputs the deformation feature data into the first training prediction model for prediction, and outputs a prediction result; if the deformation feature data is not stable, inputs the deformation feature data into the second training prediction model for prediction, and outputs a prediction result. The present invention first performs a component decomposition process on the data, which can effectively filter out the noise in the data and some data that is not helpful for prediction, so as to improve the prediction accuracy, and performs search clustering processing on the data, so that the processed data can fully reflect the characteristics of the data itself, which can improve the model prediction speed and the model prediction accuracy.

[0121] Embodiment 2

[0122] like Figure 2 As shown, in the second embodiment of the present invention, a tunnel deformation prediction system is provided, and the system includes:

[0123] A preprocessing module 1 is used to obtain tunnel deformation monitoring data and preprocess the tunnel deformation monitoring data to obtain processed monitoring data;

[0124] A decomposition module 2, used for decomposing the processed monitoring data into components to obtain decomposed monitoring data;

[0125] A clustering module 3 is used to perform search and clustering processing on the decomposed monitoring data to obtain deformation feature data;

[0126] Training module 4, used for acquiring historical training data, inputting the historical training data into the first preset model and the second preset model for training, and outputting the first training prediction model and the second training prediction model respectively;

[0127] Prediction module 5 is used to determine whether the deformation feature data is stable. If the deformation feature data is stable, the deformation feature data is input into the first training prediction model for prediction to output a prediction result. If the deformation feature data is not stable, the deformation feature data is input into the second training prediction model for prediction to output a prediction result.

[0128] The decomposition module 2 comprises:

[0129] A drawing submodule, used for drawing a curve graph of the processing monitoring data in time sequence, and searching for peak points and trough points appearing in the curve graph;

[0130] The fitting submodule is used to fit the peak point and the trough point to obtain the peak line With trough line , calculate the fluctuation mean based on the peak line and the trough line :

[0131] ;

[0132] Generate a submodule for Processing monitoring data with Generate volatility data :

[0133] ;

[0134] The conditional submodule is used to determine whether the first fluctuation data meets the decomposition condition, where the decomposition condition is:

[0135] ;

[0136] In the formula, Indicates the first fluctuation data, Indicates Fluctuation data, represents the decomposition threshold;

[0137] A decomposition submodule is used to use the first fluctuation data as the first characteristic component if the first fluctuation data meets the decomposition condition, and to process the monitoring data Subtract the first fluctuation data to obtain a trend component, and perform a decomposition process based on the trend component and the decomposition equation in a loop to obtain several characteristic components, wherein the decomposition equation is:

[0138] ;

[0139] In the formula, Indicates feature components, Indicates trend component;

[0140] The iterative submodule is used to iteratively process the characteristic components to obtain decomposed monitoring data.

[0141] The iterator module includes:

[0142] A transfer unit, used to store some of the characteristic components into a component array In the above example, the component array Shift to baseband to get the shift array :

[0143] ;

[0144] In the formula, is the pulse function, For time, is plural, is the instantaneous frequency;

[0145] Equation building unit for transferring arrays based on the Constructing the Iteration Equation :

[0146] ;

[0147] In the formula, is the penalty factor, Indicates time Taking partial derivatives, is the Lagrangian operator;

[0148] The operation unit is used to perform iterative operations on the parameters in the iterative equation until the iteration termination condition is met, output the parameters of the last iteration and update the iterative equation by the parameters of the last iteration, and output based on the updated iterative equation Group decomposition monitoring data.

[0149] The clustering module 3 comprises:

[0150] The distance calculation submodule is used to Random selection of group decomposition monitoring data The group decomposition monitoring data is used as the cluster center sequence and the remaining Group decomposition monitoring data and The Euclidean distance between each data in the cluster center sequence is used to construct a distance matrix based on the Euclidean distance. :

[0151] ;

[0152] In the formula, Indicates the remaining Any group of decomposition monitoring data in the group decomposition monitoring data Data and The first cluster center in any cluster center sequence in the group cluster center sequence The Euclidean distance between the data;

[0153] A search submodule, configured to perform a distance search starting from the first element in the upper left corner to the last element in the lower right corner of the distance matrix, calculate the cumulative value of the optimal Euclidean distance from the first element in the upper left corner to the last element in the lower right corner, and use the cumulative value as the clustering judgment distance;

[0154] The division submodule is used to divide the remaining The monitoring data is divided into the nearest cluster center sequence by group decomposition, and the new cluster center sequence is selected and divided iteratively to obtain Group deformation feature data.

[0155] In some other embodiments of the present invention, the embodiments of the present invention provide the following technical solution: a computer, comprising a memory 102, a processor 101, and a computer program stored in the memory 102 and executable on the processor 101, wherein the processor 101 implements the tunnel deformation prediction method as described above when executing the computer program.

[0156] Specifically, the processor 101 may include a central processing unit (CPU), or an application specific integrated circuit (ASIC), or may be configured to implement one or more integrated circuits of the embodiment of the present invention.

[0157] Among them, the memory 102 may include a large-capacity memory for data or instructions. By way of example and not limitation, the memory 102 may include a hard disk drive (HDD), a floppy disk drive, a solid state drive (SSD), a flash memory, an optical disk, a magneto-optical disk, a magnetic tape, or a universal serial bus (USB) drive, or a combination of two or more of these. Where appropriate, the memory 102 may include a removable or non-removable (or fixed) medium. Where appropriate, the memory 102 may be inside or outside the data processing device. In a specific embodiment, the memory 102 is a non-volatile memory. In a specific embodiment, the memory 102 includes a read-only memory (ROM) and a random access memory (RAM). Where appropriate, the ROM may be a mask-programmed ROM, a programmable ROM (PROM), an erasable PROM (EPROM), an electrically erasable PROM (EEPROM), an electrically alterable ROM (EAROM) or a flash memory (FLASH), or a combination of two or more of these. Under appropriate circumstances, the RAM can be a static random access memory (SRAM) or a dynamic random access memory (DRAM), wherein the DRAM can be a fast page mode dynamic random access memory (FPMDRAM), an extended date out dynamic random access memory (EDODRAM), a synchronous dynamic random access memory (SDRAM), etc.

[0158] The memory 102 may be used to store or cache various data files that need to be processed and / or used for communication, as well as possible computer program instructions executed by the processor 101 .

[0159] The processor 101 implements the above tunnel deformation prediction method by reading and executing computer program instructions stored in the memory 102 .

[0160] In some embodiments, the computer may further include a communication interface 103 and a bus 100. Figure 3 As shown, the processor 101, the memory 102, and the communication interface 103 are connected via a bus 100 and communicate with each other.

[0161] The communication interface 103 is used to implement communication between the modules, devices, units and / or equipment in the embodiment of the present invention. The communication interface 103 can also implement data communication with other components such as: external devices, image / data acquisition equipment, databases, external storage, and image / data processing workstations.

[0162] The bus 100 includes hardware, software or both, and couples the components of the computer device to each other. The bus 100 includes but is not limited to at least one of the following: a data bus, an address bus, a control bus, an expansion bus, and a local bus. By way of example and not limitation, bus 100 may include an Accelerated Graphics Port (AGP) or other graphics bus, an Extended Industry Standard Architecture (EISA) bus, a Front Side Bus (FSB), a Hyper Transport (HT) interconnect, an Industry Standard Architecture (ISA) bus, an InfiniBand interconnect, a Low Pin Count (LPC) bus, a memory bus, a Micro Channel Architecture (MCA) bus, a Peripheral Component Interconnect (PCI) bus, a PCI-Express (PCI-X) bus, a Serial Advanced Technology Attachment (SATA) bus, a Video Electronics Standards Association Local Bus (VLB) bus, or other suitable buses or a combination of two or more of these. Where appropriate, bus 100 may include one or more buses. Although embodiments of the present invention describe and illustrate a particular bus, the present invention contemplates any suitable bus or interconnect.

[0163] The computer can execute the tunnel deformation prediction method of the present invention based on the acquired tunnel deformation prediction system, thereby realizing tunnel deformation prediction.

[0164] In some further embodiments of the present invention, in combination with the above-mentioned tunnel deformation prediction method, the embodiments of the present invention provide the following technical solutions: a storage medium having a computer program stored thereon, and the computer program implements the above-mentioned tunnel deformation prediction method when executed by a processor.

[0165] Those skilled in the art will appreciate that the logic and / or steps represented in the flowchart or otherwise described herein, for example, may be considered as an ordered list of executable instructions for implementing logical functions, and may be specifically implemented in any computer-readable medium for use by an instruction execution system, device or apparatus (such as a computer-based system, a system including a processor, or other system that can fetch instructions from an instruction execution system, device or apparatus and execute instructions), or in conjunction with such instruction execution systems, devices or apparatuses. For purposes of this specification, "computer-readable medium" may be any device that can contain, store, communicate, propagate or transmit a program for use by an instruction execution system, device or apparatus, or in conjunction with such instruction execution systems, devices or apparatuses.

[0166] More specific examples of readable media (a non-exhaustive list) include the following: an electrical connection with one or more wires (electronic device), a portable computer disk case (magnetic device), a random access memory (RAM), a read-only memory (ROM), an erasable and programmable read-only memory (EPROM or flash memory), an optical fiber device, and a portable compact disk read-only memory (CDROM). In addition, the computer-readable medium may even be a paper or other suitable medium on which the program is printed, since the program may be obtained electronically, for example, by optically scanning the paper or other medium, followed by editing, deciphering or, if necessary, processing in another suitable manner, and then stored in a computer memory.

[0167] It should be understood that the various parts of the present invention can be implemented by hardware, software, firmware or a combination thereof. In the above-mentioned embodiments, multiple steps or methods can be implemented by software or firmware stored in a memory and executed by a suitable instruction execution system. For example, if implemented by hardware, as in another embodiment, it can be implemented by any one of the following technologies known in the art or a combination thereof: a discrete logic circuit having a logic gate circuit for implementing a logic function for a data signal, a dedicated integrated circuit having a suitable combination of logic gate circuits, a programmable gate array (PGA), a field programmable gate array (FPGA), etc.

[0168] The technical features of the above-described embodiments may be arbitrarily combined. To make the description concise, not all possible combinations of the technical features in the above-described embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.

[0169] The above-mentioned embodiments only express several implementation methods of the present invention, and the descriptions thereof are relatively specific and detailed, but they cannot be understood as limiting the scope of the invention patent. It should be pointed out that, for ordinary technicians in this field, several variations and improvements can be made without departing from the concept of the present invention, and these all belong to the protection scope of the present invention. Therefore, the protection scope of the patent of the present invention shall be subject to the attached claims.

Claims

1. A tunnel deformation prediction method, characterized in that: include: Acquiring tunnel deformation monitoring data, and preprocessing the tunnel deformation monitoring data to obtain processed monitoring data; Decomposing the processed monitoring data into components to obtain decomposed monitoring data; Performing search and clustering processing on the decomposed monitoring data to obtain deformation feature data; Acquire historical training data, input the historical training data into a first preset model and a second preset model for training, and output a first training prediction model and a second training prediction model respectively; Determine whether the deformation feature data is stable. If the deformation feature data is stable, input the deformation feature data into the first training prediction model for prediction to output a prediction result. If the deformation feature data is not stable, input the deformation feature data into the second training prediction model for prediction to output a prediction result. The step of performing component decomposition on the processed monitoring data to obtain decomposed monitoring data comprises: Plotting a curve graph of the processed monitoring data in time series, and searching for peak points and trough points appearing in the curve graph; The peak point is fitted with the trough point to obtain the peak line With trough line , calculate the fluctuation mean based on the peak line and the trough line : ; Based on the fluctuation mean Processing monitoring data with Generate volatility data : ; Determine whether the first fluctuation data meets the decomposition condition, where the decomposition condition is: ; In the formula, Indicates the first fluctuation data, Indicates Fluctuation data, represents the decomposition threshold; If the first fluctuation data meets the decomposition condition, the first fluctuation data is used as the first characteristic component, and the processing monitoring data Subtract the first fluctuation data to obtain a trend component, and perform a decomposition process based on the trend component and the decomposition equation in a loop to obtain several characteristic components, wherein the decomposition equation is: ; In the formula, Indicates feature components, Indicates trend component; Iteratively processing the characteristic components to obtain decomposed monitoring data; The step of iteratively processing the characteristic components to obtain decomposed monitoring data comprises: Store some of the characteristic components into a component array In the above example, the component array Shift to baseband to get the shift array : ; In the formula, is the pulse function, For time, is plural, is the instantaneous frequency; Based on the transfer array Constructing the Iteration Equation : ; In the formula, is the penalty factor, Indicates time Taking partial derivatives, is the Lagrangian operator; Iterate the parameters in the iterative equation until the iteration termination condition is met, output the parameters of the last iteration and update the iterative equation by the parameters of the last iteration, and output based on the updated iterative equation Group decomposition monitoring data; In the step of iteratively calculating the parameters in the iterative equation until an iteration termination condition is satisfied, outputting the parameters of the last iteration, and updating the iterative equation by the parameters of the last iteration, the parameters after iteration include: ; In the formula, Indicates The component array obtained after iterations, Indicates processing monitoring data The data obtained by Fourier transform is represents the inverse Fourier transform, Indicates The component array obtained after the iteration is transformed into the array obtained by Fourier transformation. represents the Lagrangian operator The operator obtained by Fourier transform is Indicates frequency; ; In the formula, express The array obtained after Fourier transformation; ; In the formula, represents the upper noise limit, Indicates The operator obtained by Fourier transform of the Lagrangian operator after iterations; The step of performing search and clustering processing on the decomposed monitoring data to obtain deformation feature data comprises: Will Random selection of group decomposition monitoring data The group decomposition monitoring data is used as the cluster center sequence and the remaining Group decomposition monitoring data and The Euclidean distance between each data in the cluster center sequence is used to construct a distance matrix based on the Euclidean distance. : ; In the formula, Indicates the remaining Any group of decomposition monitoring data in the group decomposition monitoring data Data and The first cluster center in any cluster center sequence in the group cluster center sequence The Euclidean distance between the data; Performing a distance search from the first element in the upper left corner to the last element in the lower right corner of the distance matrix, calculating the cumulative value of the optimal Euclidean distance from the first element in the upper left corner to the last element in the lower right corner, and using the cumulative value as the clustering judgment distance; Based on the clustering judgment distance, the remaining The monitoring data is divided into the nearest cluster center sequence by group decomposition, and the new cluster center sequence is selected and divided iteratively to obtain Group deformation feature data; In the step of judging whether the deformation feature data is smooth, if the deformation feature data is smooth, inputting the deformation feature data into the first training prediction model for prediction to output a prediction result; if the deformation feature data is not smooth, inputting the deformation feature data into the second training prediction model for prediction to output a prediction result, the first training prediction model is an ARMA model, and the second training prediction model is an LSTM model.

2. The tunnel deformation prediction method according to claim 1, characterized in that: The step of preprocessing the tunnel deformation monitoring data to obtain processed monitoring data includes: performing filtering processing, smoothing and denoising, missing value identification, and missing value filling on the tunnel deformation monitoring data in sequence to obtain processed monitoring data.

3. A tunnel deformation prediction system, the system adopts the tunnel deformation prediction method according to claim 1, characterized in that: The system comprises: A preprocessing module, used for acquiring tunnel deformation monitoring data, and preprocessing the tunnel deformation monitoring data to obtain processed monitoring data; A decomposition module, used for decomposing the processed monitoring data into components to obtain decomposed monitoring data; A clustering module, used for performing search and clustering processing on the decomposed monitoring data to obtain deformation feature data; A training module, used for acquiring historical training data, inputting the historical training data into a first preset model and a second preset model for training, and outputting a first training prediction model and a second training prediction model respectively; The prediction module is used to determine whether the deformation feature data is stable. If the deformation feature data is stable, the deformation feature data is input into the first training prediction model for prediction to output a prediction result. If the deformation feature data is not stable, the deformation feature data is input into the second training prediction model for prediction to output a prediction result.

4. A computer comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that: When the processor executes the computer program, the tunnel deformation prediction method according to any one of claims 1 to 2 is implemented.

5. A storage medium, characterized in that: The storage medium stores a computer program, and when the computer program is executed by a processor, the tunnel deformation prediction method according to any one of claims 1 to 2 is implemented.

Citation Information

Patent Citations

  • Network traffic abnormality online detection method and system, computer equipment and storage medium

    CN112329713A

  • Mountain tunnel portal prediction model based on excavation deformation characteristics

    CN116542138A

  • Project review software defect prediction method and system

    CN117389886A

  • Tunnel monitoring data prediction method and system

    CN117540153A

  • Slope displacement prediction method and system based on monitoring data