A method for controlling the investment of R&D funds
By optimizing the R&D budget based on preset needs and real-time progress in R&D projects, the problem of excessive funds in R&D investment control is solved, and dynamic, precise adjustment and reasonable control of R&D funds are achieved.
Patent Information
- Application Number
- CN202411080810.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-08
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2044-08-08
AI Technical Summary
The existing R&D investment control methods cannot make timely and accurate budget adjustments during the project process, resulting in frequent funding overruns.
By determining the first control budget of the target R&D project based on the preset R&D needs, and optimizing the budget based on real-time project progress and funds, the second control budget is obtained, and the budget is split to determine the health indicators of the funds to achieve dynamic adjustment of R&D funds.
It achieves precise control of R&D funds, avoids excessive funding, and ensures the rationality and effectiveness of project budgets.
Smart Images

Figure CN118607891B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of project fund control, and in particular to an investment control method for research and development funds. Background Art
[0002] The existing method of controlling the investment of R&D funds can only allocate the project R&D funds at the beginning of the project, so as to control the budget. If the R&D funds exceed the budget during the project, it is impossible to adjust the budget in a timely and accurate manner.
[0003] Therefore, the present invention provides a method for controlling the investment of research and development funds. Summary of the invention
[0004] The present invention provides an investment control method for R&D funds, which is used to determine a first control budget of a target R&D project through R&D needs, and optimize the first control budget, and determine the corresponding fund health indicator based on the optimized second control budget, so as to perform further optimization, which can make the budget control of the target R&D project more accurate, thereby realizing dynamic and accurate adjustment of the R&D funds.
[0005] The present invention provides a method for controlling investment of R&D funds, comprising:
[0006] Step 1: Determine the first control budget for the target R&D project to control the funding input based on the preset R&D needs;
[0007] Step 2: Optimize the first control budget based on the real-time project development progress and real-time development funds of the target development project to obtain a second control budget;
[0008] Step 3: Split the second control budget of the target R&D project, and judge the funding health index of each sub-R&D project of the target R&D project in combination with the funding investment trend of the previous project R&D cycle, so as to obtain the comprehensive project budget of the current project R&D cycle;
[0009] Step 4: Invest R&D funds in the target R&D project based on the comprehensive project budget, and obtain R&D funds in real time to dynamically adjust the comprehensive project budget to achieve real-time control of R&D funds.
[0010] Preferably, the first control budget includes labor costs, equipment and material costs, indirect costs, and R&D and testing costs.
[0011] Preferably, the first control budget is optimized based on the real-time project development progress and real-time development funds of the target development project to obtain the second control budget, including:
[0012] Step 21: Obtain the real-time project R&D progress and real-time R&D funds of the target R&D project, and extract the first R&D funds corresponding to the real-time project R&D progress in the first control budget;
[0013] Step 22: Compare the real-time R&D funds with the first R&D funds to obtain a first funds error;
[0014] Step 23: Determine whether the first funding error is greater than a preset funding error;
[0015] If the first budget error is greater than the preset budget error, the first control budget is re-determined by combining the real-time R&D progress and the real-time R&D funds with the R&D needs;
[0016] Otherwise, the first control budget is optimized based on the first budget error to obtain the second control budget.
[0017] Preferably, optimizing the first control budget based on the first budget error to obtain the second control budget includes:
[0018] Step 231: Obtain an error-budget data table based on the first budget error and the first control budget;
[0019] Step 232: performing weighted processing on the sub-budget of the corresponding first control budget based on each first budget error in the error-budget data table to obtain a first processing sub-budget;
[0020] Step 233: Obtain a second control budget based on each first processing sub-budget.
[0021] Preferably, the second control budget of the target R&D project is split, so as to judge the funding health index of each sub-R&D project in combination with the funding investment trend, so as to obtain the comprehensive project budget of the current project R&D cycle, including:
[0022] Step 31: Obtain a first R&D project of the same type as the target R&D project, and analyze the R&D funding investment ratio of each sub-R&D project of the first R&D project, so as to preliminarily determine the initial funding investment ratio of the target R&D project;
[0023] Step 32: Decomposing the second control budget based on the initial funding ratio, thereby obtaining the first project budget of each sub-R&D project;
[0024] Step 33: Based on the R&D funding investment of the target R&D project in the previous R&D cycle, a trend judgment is made on the R&D funding investment to obtain a first funding trend;
[0025] Step 34: Perform trend prediction based on the first funding trend to obtain a second funding trend for the current project R&D cycle, thereby determining a first R&D investment corresponding to the R&D funding for the current project R&D cycle;
[0026] Step 35: extracting the second R&D investment corresponding to the R&D funds in the current project R&D cycle based on the second control budget;
[0027] Step 36: Comprehensively determine the funding health index of the target R&D project based on the first R&D investment and the second R&D investment;
[0028] Step 37: Perform an initial judgment on the funding health indicator, and adjust the second control budget based on the initial judgment result to obtain a third control budget;
[0029] Step 38: Determine the budget rationality of the third control budget based on the R&D funds of R&D projects of the same type as the target R&D project;
[0030] If the budget is reasonable, the third control budget will be used as the fourth control budget;
[0031] Otherwise, the third control budget is adjusted to ensure budget rationality and obtain the fifth control budget;
[0032] Step 39: Perform budget decomposition based on the fourth control budget or the fifth control budget, and determine the R&D budget of each sub-R&D project of the target R&D project in the current project R&D cycle in combination with the first project budget;
[0033] Step 310: Determine the comprehensive project budget of the target R&D project in the current project R&D cycle based on the R&D budget and R&D schedule of each sub-R&D project of the target R&D project in the current project R&D cycle.
[0034] Preferably, the funding health indicators of the target R&D project are comprehensively determined based on the first R&D investment and the second R&D investment, including:
[0035] Determine funding health indicators for target R&D projects;
[0036] ; Among them, when the current project R&D cycle is not the first project R&D cycle of the target R&D project, the funding health indicator is ; When the current project development cycle is the first project development cycle of the target R&D project, the funding health indicator is ; ; The weight of the impact of the first R&D investment on the funding health indicator; is the impact weight of the second R&D investment on the funding health indicator; n is the number of sub-R&D projects of the target R&D project in the current project R&D cycle; The project budget of the i-th sub-R&D project determined based on the second funding trend; is the maximum allowable incremental value of the project budget for the i-th sub-R&D project; The real-time R&D investment of the R&D funds corresponding to the i-th sub-R&D project at the end of the R&D cycle of the current project; The standard R&D investment of the R&D funds corresponding to the i-th sub-R&D project at the end of the R&D cycle of the current project; The maximum estimated cost of the target R&D project; It is the cost loss compensation factor.
[0037] Preferably, an initial judgment is made on the fund health indicator, and based on the initial judgment result, the second control budget is adjusted, including:
[0038] If the funding health indicator is greater than the first health indicator, it is determined that the target R&D project has exceeded the budget in the current project R&D cycle, and a budget warning is issued for the target R&D project;
[0039] If the funding health indicator is less than the first health indicator but greater than the maximum value of the second health indicator, it is judged that the budget of the target R&D project in the current project R&D cycle is too high, and the second control budget needs to be adjusted;
[0040] If the funding health indicator is within the second health indicator range, the target R&D project is judged to have a qualified budget within the current project R&D cycle;
[0041] If the funding health indicator is less than the minimum value of the second health indicator, it is judged that the budget of the target R&D project in the current project R&D cycle is too low, and the second control budget needs to be adjusted.
[0042] Preferably, R&D funds are invested in the target R&D project based on the comprehensive project budget, and the R&D funds are obtained in real time to dynamically adjust the comprehensive project budget to achieve real-time control of the R&D funds, including:
[0043] Step 41: Invest R&D funds in each sub-R&D project of the target R&D project based on the comprehensive project budget;
[0044] Step 42: Obtain the second R&D funds corresponding to the target R&D project in each project R&D cycle, and compare the second R&D funds with the corresponding comprehensive project budget, thereby adjusting the comprehensive project budget based on the comparison result, thereby achieving real-time control of the R&D funds.
[0045] The present invention provides a method for controlling the investment of R&D funds. The method determines a first control budget of a target R&D project through R&D needs, optimizes the first control budget, determines a corresponding fund health indicator based on the optimized second control budget, and optimizes it again. This can make the budget control of the target R&D project more accurate, thereby achieving dynamic and accurate adjustment of the R&D funds. BRIEF DESCRIPTION OF THE DRAWINGS
[0046] In order to more clearly illustrate the technical solutions in the present invention or the prior art, the following briefly introduces the drawings required for use in the embodiments or the description of the prior art. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0047] Figure 1 It is a flow chart of a method for controlling investment of R&D funds provided by an embodiment of the present invention. DETAILED DESCRIPTION
[0048] In order to make the purpose, technical solution and advantages of the present invention clearer, the technical solution of the present invention will be clearly and completely described below in conjunction with the drawings of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0049] Embodiment 1:
[0050] The embodiment of the present invention provides a method for controlling the investment of R&D funds, such as Figure 1 As shown, including:
[0051] Step 1: Determine the first control budget for the target R&D project to control the funding input based on the preset R&D needs;
[0052] Step 2: Optimize the first control budget based on the real-time project development progress and real-time development funds of the target development project to obtain a second control budget;
[0053] Step 3: Split the second control budget of the target R&D project, and judge the funding health index of each sub-R&D project of the target R&D project in combination with the funding investment trend of the previous project R&D cycle, so as to obtain the comprehensive project budget of the current project R&D cycle;
[0054] Step 4: Invest R&D funds in the target R&D project based on the comprehensive project budget, and obtain R&D funds in real time to dynamically adjust the comprehensive project budget to achieve real-time control of R&D funds.
[0055] In this embodiment, the R&D requirements include functional requirements, performance requirements, security requirements, reliability and availability requirements, compliance requirements, maintenance requirements, cost and resource requirements, etc.
[0056] In this embodiment, the first control budget includes labor costs, equipment and material costs, indirect costs, and R&D and testing costs.
[0057] In this embodiment, the real-time project R&D progress refers to the real-time project progress of the target R&D project, which includes: time progress, resource progress, status progress, etc. The real-time R&D funds refer to the R&D funds of the target R&D project in the real-time project R&D progress, wherein the real-time R&D funds refer to the remaining R&D funds corresponding to the target R&D project up to the real-time project R&D progress.
[0058] In this embodiment, the second control budget is a research and development funding control budget obtained by performing budget weighted optimization on the first control budget based on the real-time project research and development progress and the real-time research and development funding.
[0059] In this embodiment, the funding investment trend is a research and development funding investment trend determined based on the research and development funding investment situation of the target research and development project in the previous project research and development cycle.
[0060] In this embodiment, the funding health index is used to determine the health of the funding investment of the target R&D project. The smaller the funding health index is, the healthier the funding investment is, and the larger the funding health index is, the unhealthier the funding investment is. That is, the larger the funding health index is, the more necessary it is to adjust the control budget.
[0061] In this embodiment, the comprehensive project budget is a project budget of the target R&D project determined based on the R&D funding budget of each sub-R&D project combined with the R&D schedule.
[0062] The beneficial effect of the above technical solution is: determining the first control budget of the target R&D project through R&D needs, and optimizing the first control budget, determining the corresponding funding health indicators based on the optimized second control budget, and then optimizing again, which can make the budget control of the target R&D project more accurate, thereby realizing dynamic and accurate adjustment of R&D funds.
[0063] Embodiment 2:
[0064] Based on Example 1, the first control budget includes labor costs, equipment and material costs, indirect costs, and R&D and testing costs.
[0065] The beneficial effect of the above technical solution is: by judging the R&D needs and thus determining the first control budget, the first control budget can be made to better meet the needs of the target R&D project, making the control of the target R&D project more precise.
[0066] Embodiment 3:
[0067] Based on Example 2, the first control budget is optimized based on the real-time project development progress and real-time development funds of the target development project to obtain a second control budget, including:
[0068] Step 21: Obtain the real-time project R&D progress and real-time R&D funds of the target R&D project, and extract the first R&D funds corresponding to the real-time project R&D progress in the first control budget;
[0069] Step 22: Compare the real-time R&D funds with the first R&D funds to obtain a first funds error;
[0070] Step 23: Determine whether the first funding error is greater than a preset funding error;
[0071] If the first budget error is greater than the preset budget error, the first control budget is re-determined by combining the real-time R&D progress and the real-time R&D funds with the R&D needs;
[0072] Otherwise, the first control budget is optimized based on the first budget error to obtain the second control budget.
[0073] In this embodiment, the real-time project R&D progress refers to the real-time project progress of the target R&D project, which includes: time progress, resource progress, status progress, etc. The real-time R&D funds refer to the R&D funds of the target R&D project in the real-time project R&D progress, wherein the real-time R&D funds refer to the remaining R&D funds corresponding to the target R&D project up to the real-time project R&D progress.
[0074] In this embodiment, the first research and development funds refer to the research and development funds corresponding to the real-time project research and development progress in the first control budget.
[0075] In this embodiment, the first budget error refers to the error value between the first research and development budget and the real-time research and development budget.
[0076] In this embodiment, the preset funding error is determined based on the budget accuracy of the target R&D project.
[0077] In this embodiment, the second control budget is a research and development funding control budget obtained by weighted optimization of the first control budget based on the first funding error.
[0078] The beneficial effect of the above technical solution is that the first control budget can be adjusted by real-time project development progress and real-time development funds, so that the obtained control budget can be more accurate.
[0079] Embodiment 4:
[0080] Based on Example 3, the first control budget is optimized based on the first budget error to obtain a second control budget, including:
[0081] Step 231: Obtain an error-budget data table based on the first budget error and the first control budget;
[0082] Step 232: performing weighted processing on the sub-budget of the corresponding first control budget based on each first budget error in the error-budget data table to obtain a first processing sub-budget;
[0083] Step 233: Obtain a second control budget based on each first processing sub-budget.
[0084] In this embodiment, the first column of the error-budget data table contains each error value of the first funding error, the second column contains each sub-budget of the first control budget, and each row represents the budget or budget error of the same R&D sub-project.
[0085] In this embodiment, the first processing sub-budget is obtained by processing the first budget error based on the impact of the first budget error on the budget and combining it with the corresponding sub-budget.
[0086] In this embodiment, the second control budget is a research and development funding control budget obtained by weighted optimization of the first control budget based on the first funding error.
[0087] The beneficial effect of the above technical solution is that by adjusting the first control budget based on the first funding error, the obtained control budget can be made more accurate.
[0088] Embodiment 5:
[0089] Based on Example 3, the second control budget of the target R&D project is split, so as to judge the funding health index of each sub-R&D project in combination with the funding investment trend, so as to obtain a comprehensive project budget for the current project R&D cycle, including:
[0090] Step 31: Obtain a first R&D project of the same type as the target R&D project, and analyze the R&D funding investment ratio of each sub-R&D project of the first R&D project, so as to preliminarily determine the initial funding investment ratio of the target R&D project;
[0091] Step 32: Decomposing the second control budget based on the initial funding ratio, thereby obtaining the first project budget of each sub-R&D project;
[0092] Step 33: Based on the R&D funding investment of the target R&D project in the previous R&D cycle, a trend judgment is made on the R&D funding investment to obtain a first funding trend;
[0093] Step 34: Perform trend prediction based on the first funding trend to obtain a second funding trend for the current project R&D cycle, thereby determining a first R&D investment corresponding to the R&D funding for the current project R&D cycle;
[0094] Step 35: extracting the second R&D investment corresponding to the R&D funds in the current project R&D cycle based on the second control budget;
[0095] Step 36: Comprehensively determine the funding health index of the target R&D project based on the first R&D investment and the second R&D investment;
[0096] Step 37: Perform an initial judgment on the funding health indicator, and adjust the second control budget based on the initial judgment result to obtain a third control budget;
[0097] Step 38: Determine the budget rationality of the third control budget based on the R&D funds of R&D projects of the same type as the target R&D project;
[0098] If the budget is reasonable, the third control budget will be used as the fourth control budget;
[0099] Otherwise, the third control budget is adjusted to ensure budget rationality and obtain the fifth control budget;
[0100] Step 39: Perform budget decomposition based on the fourth control budget or the fifth control budget, and determine the R&D budget of each sub-R&D project of the target R&D project in the current project R&D cycle in combination with the first project budget;
[0101] Step 310: Determine the comprehensive project budget of the target R&D project in the current project R&D cycle based on the R&D budget and R&D schedule of each sub-R&D project of the target R&D project in the current project R&D cycle.
[0102] In this embodiment, the first R&D project refers to a R&D project of the same type as the target R&D project contained in the R&D database.
[0103] In this embodiment, the initial funding investment ratio refers to the funding investment ratio of the target R&D project determined based on the funding investment ratio of each sub-R&D project of the first R&D project in the current project R&D cycle.
[0104] In this embodiment, the first project budget refers to the project budget of each sub-R&D project after the second control budget is decomposed based on the initial funding ratio.
[0105] In this embodiment, the first funding trend is a research and development funding investment trend determined based on the research and development funding investment of the target research and development project in the previous project research and development cycle.
[0106] In this embodiment, the second funding trend is a trend forecast based on the first funding trend, so as to obtain the R&D funding trend of the target R&D project in the current project R&D cycle.
[0107] In this embodiment, the first R&D investment is determined based on the second funding trend to determine the R&D funding investment corresponding to the end of the current project R&D cycle.
[0108] In this embodiment, the second R&D investment is the R&D funding investment corresponding to the current project R&D cycle extracted from the second control budget.
[0109] In this embodiment, the funding health index is used to determine the health of the funding investment of the target R&D project. The smaller the funding health index is, the healthier the funding investment is, and the larger the funding health index is, the unhealthier the funding investment is. That is, the larger the funding health index is, the more necessary it is to adjust the control budget.
[0110] In this embodiment, the third control budget refers to the budget obtained by adjusting the second control budget based on the funding health indicator.
[0111] In this embodiment, the budget rationality of the third control budget is judged based on the R&D funds of R&D projects of the same type as the target R&D project. If the budget is reasonable, the third control budget is the fourth control budget. If the budget is unreasonable, the third control budget is adjusted to obtain the fifth control budget.
[0112] In this embodiment, the comprehensive project budget is a project budget of the target R&D project determined based on the R&D funding budget of each sub-R&D project combined with the R&D schedule.
[0113] The beneficial effect of the above technical solution is: by determining the funding health indicators of the target R&D project, the control budget of the target R&D project is adjusted, and the control budget is adjusted in combination with the R&D sequence to obtain a comprehensive project budget, which can make the control budget of the target R&D project more accurate and effective.
[0114] Embodiment 6:
[0115] Based on Example 5, the funding health index of the target R&D project is comprehensively determined based on the first R&D investment and the second R&D investment, including:
[0116] Determine funding health indicators for target R&D projects;
[0117] ; Among them, when the current project R&D cycle is not the first project R&D cycle of the target R&D project, the funding health indicator is ; When the current project development cycle is the first project development cycle of the target R&D project, the funding health indicator is ; ; The weight of the impact of the first R&D investment on the funding health indicator; is the impact weight of the second R&D investment on the funding health indicator; n is the number of sub-R&D projects of the target R&D project in the current project R&D cycle; The project budget of the i-th sub-R&D project determined based on the second funding trend; is the maximum allowable incremental value of the project budget for the i-th sub-R&D project; The real-time R&D investment of the R&D funds corresponding to the i-th sub-R&D project at the end of the R&D cycle of the current project; The standard R&D investment of the R&D funds corresponding to the i-th sub-R&D project at the end of the R&D cycle of the current project; The maximum estimated cost of the target R&D project; It is the cost loss compensation factor.
[0118] In this embodiment, the maximum allowable incremental value refers to the maximum deviating increment corresponding to the project budget of the i-th sub-R&D project, wherein the maximum allowable incremental value is determined based on the maximum allowable fluctuation value of the R&D funds of the target R&D project. For example, the target R&D project can be divided into 10 sub-R&D projects, and the maximum allowable fluctuation value of the R&D funds is 500,000. Then, the maximum allowable incremental value of the R&D funds of each sub-R&D project shall not exceed 500,000, and the sum of the maximum allowable incremental values of the R&D funds of all sub-R&D projects shall be 500,000.
[0119] In this embodiment, the maximum expected financial loss refers to the financial loss caused to the project budget of the i-th sub-R&D project due to market fluctuations.
[0120] In this embodiment, the expense loss compensation factor is based on the expense loss caused by abnormal fluctuations of different costs in the control budget.
[0121] The beneficial effect of the above technical solution is: by determining the funding health indicators of the target R&D project, the control budget of the target R&D project can be adjusted, so that the control budget of the target R&D project can be made more accurate and effective.
[0122] Embodiment 7:
[0123] Based on Example 5, an initial judgment is made on the fund health indicator, and a budget adjustment is made to the second control budget based on the initial judgment result, including:
[0124] If the funding health indicator is greater than the first health indicator, it is determined that the target R&D project has exceeded the budget in the current project R&D cycle, and a budget warning is issued for the target R&D project;
[0125] If the funding health indicator is less than the first health indicator but greater than the maximum value of the second health indicator, it is judged that the budget of the target R&D project in the current project R&D cycle is too high, and the second control budget needs to be adjusted;
[0126] If the funding health indicator is within the second health indicator range, the target R&D project is judged to have a qualified budget within the current project R&D cycle;
[0127] If the funding health indicator is less than the minimum value of the second health indicator, it is judged that the budget of the target R&D project in the current project R&D cycle is too low, and the second control budget needs to be adjusted.
[0128] In this embodiment, the first health indicator is greater than the second health indicator.
[0129] In this embodiment, the first health indicator, the maximum value of the second health indicator, and the minimum value of the second health indicator are all determined based on the budget fluctuation allowed for the target R&D project.
[0130] In this embodiment, the budget adjustment refers to adjusting the second control budget based on the funding health indicator. The smaller the funding health indicator is, the smaller the adjustment to the second control budget is.
[0131] The beneficial effect of the above technical solution is: by judging the health indicators of funds and adjusting the control budget, the control of R&D funds can be made more accurate.
[0132] Embodiment 8:
[0133] Based on Example 5, R&D funds are invested in the target R&D project based on the comprehensive project budget, and the R&D funds are obtained in real time to dynamically adjust the comprehensive project budget to achieve real-time control of the R&D funds, including:
[0134] Step 41: Invest R&D funds in each sub-R&D project of the target R&D project based on the comprehensive project budget;
[0135] Step 42: Obtain the second R&D funds corresponding to the target R&D project in each project R&D cycle, and compare the second R&D funds with the corresponding comprehensive project budget, thereby adjusting the comprehensive project budget based on the comparison result, thereby achieving real-time control of the R&D funds.
[0136] In this embodiment, the second R&D funds refer to the use of corresponding R&D funds obtained in each project R&D cycle when the R&D funds are invested.
[0137] The beneficial effect of the above technical solution is: by judging the R&D funds of each project R&D cycle, the comprehensive project budget can be adjusted in real time, which can make the control of R&D funds more accurate and timely, and the project budget can be adjusted in real time according to the use of R&D funds.
[0138] The above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit the same. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some of the technical features may be replaced by equivalents. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present invention.
Claims
1. A method for controlling the investment of R&D funds, characterized in that: include: Step 1: Determine the first control budget for the target R&D project to control the funding input based on the preset R&D needs; Step 2: Optimize the first control budget based on the real-time project development progress and real-time development funds of the target development project to obtain a second control budget; Step 3: Split the second control budget of the target R&D project, and judge the funding health index of each sub-R&D project of the target R&D project in combination with the funding investment trend of the previous project R&D cycle, so as to obtain the comprehensive project budget of the current project R&D cycle; Step 4: Invest R&D funds in the target R&D project based on the comprehensive project budget, and obtain R&D funds in real time to dynamically adjust the comprehensive project budget to achieve real-time control of R&D funds; The first control budget is optimized based on the real-time project development progress and real-time development funds of the target development project to obtain the second control budget, including: Step 21: Obtain the real-time project R&D progress and real-time R&D funds of the target R&D project, and extract the first R&D funds corresponding to the real-time project R&D progress in the first control budget; Step 22: Compare the real-time R&D funds with the first R&D funds to obtain a first funds error; Step 23: Determine whether the first funding error is greater than a preset funding error; If the first budget error is greater than the preset budget error, the first control budget is re-determined by combining the real-time R&D progress and the real-time R&D funds with the R&D needs; Otherwise, the first control budget is optimized based on the first budget error to obtain the second control budget; The first control budget is optimized based on the first funding error to obtain the second control budget, including: Step 231: Obtain an error-budget data table based on the first budget error and the first control budget; Step 232: performing weighted processing on the sub-budget of the corresponding first control budget based on each first budget error in the error-budget data table to obtain a first processing sub-budget; Step 233: Obtain a second control budget based on each first processing sub-budget; Among them, the second control budget of the target R&D project is split, and the funding health indicators of each sub-R&D project are judged in combination with the funding investment trend, so as to obtain the comprehensive project budget of the current project R&D cycle, including: Step 31: Obtain a first R&D project of the same type as the target R&D project, and analyze the R&D funding investment ratio of each sub-R&D project of the first R&D project, so as to preliminarily determine the initial funding investment ratio of the target R&D project; Step 32: Decomposing the second control budget based on the initial funding ratio, thereby obtaining the first project budget of each sub-R&D project; Step 33: Based on the R&D funding investment of the target R&D project in the previous R&D cycle, a trend judgment is made on the R&D funding investment to obtain a first funding trend; Step 34: Perform trend prediction based on the first funding trend to obtain a second funding trend for the current project R&D cycle, thereby determining a first R&D investment corresponding to the R&D funding for the current project R&D cycle; Step 35: extracting the second R&D investment corresponding to the R&D funds in the current project R&D cycle based on the second control budget; Step 36: Comprehensively determine the funding health index of the target R&D project based on the first R&D investment and the second R&D investment; Step 37: Perform an initial judgment on the funding health indicator, and adjust the second control budget based on the initial judgment result to obtain a third control budget; Step 38: Determine the budget rationality of the third control budget based on the R&D funds of R&D projects of the same type as the target R&D project; If the budget is reasonable, the third control budget will be used as the fourth control budget; Otherwise, the third control budget is adjusted to ensure budget rationality and obtain the fifth control budget; Step 39: Perform budget decomposition based on the fourth control budget or the fifth control budget, and determine the R&D budget of each sub-R&D project of the target R&D project in the current project R&D cycle in combination with the first project budget; Step 310: Determine the comprehensive project budget of the target R&D project in the current project R&D cycle based on the R&D budget and R&D sequence of each sub-project of the target R&D project in the current project R&D cycle; Among them, the funding health indicators of the target R&D project are determined based on the first R&D investment and the second R&D investment, including: Determine funding health indicators for target R&D projects; ; ; Among them, when the current project R&D cycle is not the first project R&D cycle of the target R&D project, the funding health indicator is ; When the current project development cycle is the first project development cycle of the target R&D project, the funding health indicator is ; ; The weight of the impact of the first R&D investment on the funding health indicator; is the impact weight of the second R&D investment on the funding health indicator; n is the number of sub-R&D projects of the target R&D project in the current project R&D cycle; The project budget of the i-th sub-R&D project determined based on the second funding trend; is the maximum allowable incremental value of the project budget for the i-th sub-R&D project; The real-time R&D investment of the R&D funds corresponding to the i-th sub-R&D project at the end of the R&D cycle of the current project; The standard R&D investment of the R&D funds corresponding to the i-th sub-R&D project at the end of the R&D cycle of the current project; The maximum estimated cost of the target R&D project; It is the cost loss compensation factor.
2. A method for controlling investment in R&D funds according to claim 1, characterized in that: The first control budget includes labor costs, equipment and material costs, indirect costs, and R&D and testing costs.
3. The method for controlling the investment of R&D funds according to claim 1, characterized in that: Make an initial judgment on the funding health indicators and adjust the second control budget based on the initial judgment results, including: If the funding health indicator is greater than the first health indicator, it is determined that the target R&D project has exceeded the budget in the current project R&D cycle, and a budget warning is issued for the target R&D project; If the funding health indicator is less than the first health indicator but greater than the maximum value of the second health indicator, it is judged that the budget of the target R&D project in the current project R&D cycle is too high, and the second control budget needs to be adjusted; If the funding health indicator is within the second health indicator range, the target R&D project is judged to have a qualified budget within the current project R&D cycle; If the funding health indicator is less than the minimum value of the second health indicator, it is judged that the budget of the target R&D project in the current project R&D cycle is too low, and the second control budget needs to be adjusted.
4. The method for controlling the investment of R&D funds according to claim 1, characterized in that: Based on the comprehensive project budget, research and development funds are invested in the target research and development project, and the research and development funds are obtained in real time to dynamically adjust the comprehensive project budget to achieve real-time control of research and development funds, including: Step 41: Invest R&D funds in each sub-R&D project of the target R&D project based on the comprehensive project budget; Step 42: Obtain the second R&D funds corresponding to the target R&D project in each project R&D cycle, and compare the second R&D funds with the corresponding comprehensive project budget, thereby adjusting the comprehensive project budget based on the comparison result, thereby achieving real-time control of the R&D funds.