Double sewage pipe welding device and welding method thereof

By designing an automated welding and material receiving mechanism, the problem of cumbersome operations for workers when welding sewage pipes is solved, an efficient welding process is achieved, work intensity is reduced and efficiency is improved.

CN118616993BActive Publication Date: 2024-10-11SICHUAN JIETU ENVIRONMENTAL PROTECTION SERVICE CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411113489.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-14
Publication Date
2024-10-11
Estimated Expiration
2044-08-14

AI Technical Summary

Technical Problem

In the existing technology, when welding sewage pipes, workers need to manually mark lines and spot weld one by one, resulting in high work intensity and low efficiency.

Method used

A double sewage pipe welding device is designed, including welding, material receiving mechanism and feeding mechanism. Through the automated screw nut pair and oil cylinder drive system, the automatic clamping and welding of the connecting parts is realized, reducing the number of manual operations and time.

Benefits of technology

It greatly reduces the work intensity of workers, significantly improves the welding efficiency of sewage pipes, reduces welding time and processes, and improves welding efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118616993B_ABST
    Figure CN118616993B_ABST
Patent Text Reader

Abstract

The invention discloses a double-root sewage pipe welding device and a welding method thereof, and the invention relates to the technical field of welding, and comprises a backing plate, a welding and material receiving mechanism arranged on the backing plate, and a feeding mechanism for conveying connecting pieces to the welding and material receiving mechanism, wherein the welding and material receiving mechanism comprises an arch frame fixedly arranged on the backing plate, and two bases fixedly arranged on the top surface of the arch frame, and positioning columns are fixedly arranged on the top surfaces of the two bases, and vertical plates are fixedly arranged on the inner sides of the nuts of the screw-nut pair, and welding cylinders and material receiving cylinders are fixedly arranged on the inner end surfaces of the vertical plates, and a movable plate is fixedly arranged on the action end of the piston rod of the welding cylinder, and a spot welding head arranged horizontally is fixedly arranged on the movable plate, and an L-shaped material receiving plate is fixedly arranged on the action end of the piston rod of the material receiving cylinder. The beneficial effects of the invention are: greatly reducing the work intensity of workers and greatly improving the welding efficiency of two sewage pipes.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of welding, in particular to a double-root sewage pipe welding device and a welding method thereof. Background Art

[0002] In farmland ecological management, sewage pipes are usually used to discharge farmland sewage at high positions to treatment fields at low positions, so as to facilitate workers to treat farmland sewage in the treatment fields. In order to increase the discharge speed of farmland sewage, workers use multiple connectors 2 to weld two sewage pipes 1 together. The structure of the two sewage pipes 1 welded together is as follows: Figure 1~Figure 2 As shown, the connecting member 2 includes two collars 3 and a fixing plate 4 connected between the two collars 3. The two collars 3 of each connecting member 2 are respectively welded to the two sewage pipes 1. The structure of the connecting member 2 is as shown in FIG. Figure 3~Figure 4 shown.

[0003] The method in which a worker welds two sewage pipes 1 together through a plurality of connectors 2 is as follows:

[0004] S1. The worker takes out two sewage pipes 1 and places them flat on the ground. The worker marks welding positions on the two sewage pipes 1 at intervals along their lengths, which are marking lines (marking lines are the positions where the connectors 2 are welded on the sewage pipes 1).

[0005] S2. The worker takes out a connector 2 and puts two collars 3 of the connector 2 on two sewage pipes 1 respectively, and ensures that the two collars 3 of the connector 2 are respectively at the first markings;

[0006] S3, the worker steps on the two sewage pipes 1 with his feet, and then operates the spot welding machine to make the spot welding head of the spot welding machine contact the outer surfaces of the two collars 3 of the first connecting piece 2 respectively, thereby achieving the two collars 3 of the first connecting piece 2 being welded to the two sewage pipes 1 respectively, as shown in FIG. Figure 5 The figure shows a schematic diagram of welding the first connecting member 2 to two sewage pipes 1;

[0007] S4, the worker repeats the operations of steps S2 to S3, and welds the remaining multiple connectors 2 between the two sewage pipes 1, thereby finally achieving the welding of the two sewage pipes 1 together through the multiple connectors 2;

[0008] S5. The worker repeats the operations of steps S1 to S4 to continuously weld multiple groups of sewage pipes 1 together.

[0009] However, although the worker's operation method can weld the two sewage pipes 1 together, in actual operation, there are still the following technical defects:

[0010] I. In step S1, workers are required to mark the two sewage pipes 1 along their lengths in advance, and the marking operation undoubtedly increases the welding process, thereby increasing the subsequent welding time of the connecting piece 2 and the two sewage pipes 1, thereby reducing the welding efficiency of the two sewage pipes 1.

[0011] II. In step S3, after stepping on the two sewage pipes 1, the worker needs to manually operate the electric welder so that the spot welding head of the spot welding machine contacts the two rings 3 of the connector 2 respectively. However, there are many connectors 2 to be welded, and the worker has to spot weld them one by one, which not only increases the worker's work intensity, but also increases the welding time between a single connector 2 and the two sewage pipes 1, further reducing the welding efficiency of the two sewage pipes 1.

[0012] Therefore, there is an urgent need for a welding device and a welding method that can greatly reduce the work intensity of workers and greatly improve the welding efficiency of two sewage pipes. Summary of the invention

[0013] The purpose of the present invention is to overcome the shortcomings of the prior art and provide a double sewage pipe welding device and a welding method thereof which can greatly reduce the work intensity of workers and greatly improve the welding efficiency of two sewage pipes.

[0014] The object of the present invention is achieved through the following technical scheme: a double-root sewage pipe welding device, which comprises a pad, a welding and material receiving mechanism arranged on the pad, and a feeding mechanism for conveying connecting pieces to the welding and material receiving mechanism, wherein the welding and material receiving mechanism comprises an arch frame fixedly arranged on the pad, two bases fixedly arranged on the top surface of the arch frame, and positioning columns are fixedly arranged on the top surfaces of the two bases, and two vertically arranged screw rod nut pairs are arranged on the arch frame, and the two screw rod nut pairs are respectively located on the outer sides of the two bases, and the inner sides of the nuts of the screw rod nut pairs are fixedly provided with vertical plates, and the inner end surfaces of the vertical plates are fixedly provided with welding cylinders and material receiving cylinders, and the active end of the welding cylinder piston rod is fixedly provided with a movable plate, and a horizontally arranged spot welding head is fixedly provided on the movable plate, and the other end of the spot welding head is connected to the welding machine via a power cord, and an L-shaped material receiving plate is fixedly provided on the active end of the material receiving cylinder piston rod, and the material receiving plate is located directly below the spot welding head;

[0015] The feeding mechanism includes a platform fixed on the pad, a connecting plate fixed on the top surface of the platform, and a horizontal cylinder fixed on the right end surface of the connecting plate. The piston rod of the horizontal cylinder passes through the connecting plate, and a vertical cylinder is fixed on the extending end. A bracket is fixed on the action end of the piston rod of the vertical cylinder. Clamping cylinders are fixed on the bottom surface of the bracket and at the left and right ends of the bracket, and the chucks of the two clamping cylinders are both set downward.

[0016] The screw-nut pair includes a frame fixed on the top surface of the arch frame, a screw rotatably installed in the frame, and a nut threadedly connected to the screw. A driving motor and a polished rod are also fixed on the frame. The driving motor is connected to the lower end of the screw, the polished rod is arranged parallel to the screw, and the polished rod passes through the nut.

[0017] A plurality of supporting legs are fixedly arranged between the platform and the pad.

[0018] The two clamping cylinders are arranged symmetrically with respect to the vertical cylinder.

[0019] The outer diameter of the positioning column is equal to the inner diameter of the sewage pipe.

[0020] An L-plate is fixedly arranged on the action end of the piston rod of the horizontal oil cylinder, and the vertical oil cylinder is fixedly arranged on the top surface of the L-plate.

[0021] The welding device also includes a controller, which is electrically connected to the horizontal oil cylinder, the vertical oil cylinder, the clamping oil cylinder, the driving motor, the material receiving oil cylinder and the welding oil cylinder via a signal line.

[0022] A welding method for double sewage pipes comprises the following steps:

[0023] S1. A worker stacks a plurality of connectors on the top surface of the platform of the feeding mechanism from bottom to top, and at the same time, ensures that the two collars of the connector on the top layer are respectively directly under the two clamps of the feeding mechanism, thereby realizing pre-stacking of the plurality of connectors;

[0024] S2. Positioning of two sewage pipes: Workers take out two sewage pipes, respectively put them on the two positioning columns of the welding and material connection mechanism, and support the sewage pipes on the top surface of the base. Since the outer diameter of the positioning column is equal to the inner diameter of the sewage pipe, the positioning of the two sewage pipes is achieved. At this time, both sewage pipes are in the welding position;

[0025] S3. The specific steps of welding the first connecting piece to the two sewage pipes are as follows:

[0026] S31, control the piston rod of the vertical oil cylinder of the feeding mechanism to extend downward, the piston rod drives the bracket to move downward, the bracket drives the two clamping oil cylinders to move downward synchronously, the clamping oil cylinder drives the chuck to move downward synchronously, when the piston rod of the vertical oil cylinder extends to the set stroke, the controller controls the vertical oil cylinder to close, at this time, the two chucks are respectively sleeved on the outer walls of the two collars of the topmost connecting piece;

[0027] S32, control the two clamping cylinders to start, the clamping cylinders drive the clamps to close, and the two clamps respectively clamp and fix the two collars of the topmost connecting piece;

[0028] S33, control the piston rod of the vertical oil cylinder to retract upward, the piston rod drives the bracket to move upward, the bracket drives the two clamping oil cylinders to move upward, the clamping oil cylinder drives the chuck to move upward, the chuck drives the first connecting piece to move upward, thereby lifting the first connecting piece;

[0029] S34, the piston rod of the horizontal oil cylinder of the control feeding mechanism extends to the left, the piston rod drives the L plate to move to the left, the L plate drives the vertical oil cylinder to move to the left, the vertical oil cylinder drives the bracket and the two clamping oil cylinders to move to the left, and then drives the first connecting piece to move to the left. When the piston rod of the horizontal oil cylinder is fully extended, the two collars of the first connecting piece are respectively located directly above the two sewage pipes;

[0030] S35, control the piston rod of the vertical oil cylinder to extend downward, the piston rod drives the bracket to move downward, the bracket drives the two clamping oil cylinders to move downward, and then drives the first connecting piece to move downward. When the piston rod of the vertical oil cylinder extends to the set stroke, the controller controls the vertical oil cylinder to close. At this time, the two collars of the first connecting piece are respectively located directly above the two sewage pipes;

[0031] S36, controlling the piston rods of the material receiving cylinders on the two screw nut pairs to extend, and the piston rods drive the material receiving plates to move toward the direction of the corresponding sewage pipes. When the piston rods of the material receiving cylinders are fully extended, the two material receiving plates approach the two sewage pipes respectively. At this time, the two material receiving plates are both in the material receiving position;

[0032] S37, control the two clamping cylinders to close, the clamping cylinders drive the chuck to open, the chuck no longer clamps the collar of the connector, and under its own gravity, the two collars of the connector are respectively sleeved on the two sewage pipes and move downward along the sewage pipes until the two collars of the connector are respectively blocked by the two receiving plates, thereby connecting the connector. At this time, the position of the connector is the welding position of the first connector, and at the same time, the two collars of the connector are respectively opposite to the two spot welding heads;

[0033] S38, the piston rods of the two welding cylinders of the control welding and material receiving mechanism are extended, the piston rods drive the movable plate to move toward the collar, and the movable plate drives the spot welding head to move toward the collar. When the piston rods of the welding cylinders are fully extended, the two spot welding heads contact the outer walls of the two collars of the connecting piece respectively, thereby finally realizing the welding of the first connecting piece between the two sewage pipes;

[0034] S4, control the piston rods of the two welding cylinders of the welding and material receiving mechanism to retract, the piston rods drive the spot welding heads to reset, and then control the piston rods of the two material receiving cylinders to retract, the piston rods drive the material receiving plates to reset; after resetting, control the drive motors of the two screw nut pairs to start, the nuts move upward along the screws, the nuts drive the vertical plates to move upward, the vertical plates drive the welding cylinders and the material receiving cylinders to move upward synchronously, and when the nuts move upward to the set stroke, the controller controls the drive motor to turn off, at which time, the two spot welding heads and the two material receiving plates are just at the next welding station;

[0035] S5. The worker repeats the operations of steps S3 to S4 to weld the multiple connectors between the two sewage pipes, thereby finally welding the two sewage pipes into one body;

[0036] S6. After welding, the worker takes the two welded sewage pipes away from the two positioning columns;

[0037] S7. The worker repeats steps S2 to S6 for multiple times to continuously weld multiple sets of sewage pipes together.

[0038] The invention has the following advantages: greatly reducing the work intensity of workers and greatly improving the welding efficiency of two sewage pipes. BRIEF DESCRIPTION OF THE DRAWINGS

[0039] Figure 1 This is an axonometric view of two sewage pipes welded together;

[0040] Figure 2 for Figure 1 The main cross-sectional diagram of

[0041] Figure 3 is the axonometric drawing of the connecting part;

[0042] Figure 4 for Figure 3 The main cross-sectional diagram of

[0043] Figure 5 A schematic diagram of welding the first connecting piece to two sewage pipes;

[0044] Figure 6 A schematic diagram of the structure of the present invention;

[0045] Figure 7 for Figure 6 The main cross-sectional diagram of

[0046] Figure 8 It is a structural diagram of the welding and material connection mechanism;

[0047] Fig. 9 It is a schematic diagram of the connection between the base and the positioning column;

[0048] Fig.10This is the axonometric drawing of the splice plate;

[0049] Fig.11 It is a structural schematic diagram of the feeding mechanism;

[0050] Fig.12 A schematic diagram of pre-stacking a plurality of connectors sequentially on the top surface of a platform;

[0051] Fig.13 A schematic diagram for positioning two sewage pipes;

[0052] Fig.14 A schematic diagram of two chucks being respectively sleeved on the outer walls of two collars of the topmost connecting piece;

[0053] Fig.15 A schematic diagram for lifting the first connecting member;

[0054] Fig.16 It is a schematic diagram showing that the two collars of the first connecting piece are respectively located directly above the two sewage pipes;

[0055] Fig.17 It is a schematic diagram showing that two receiving plates are both in the receiving station;

[0056] Fig.18 A schematic diagram of two connecting plates connecting the connecting piece;

[0057] Fig.19 It is a schematic diagram of two spot welding heads contacting two outer walls of the collars of the connecting piece respectively;

[0058] Fig. 20 It is a schematic diagram of two spot welding heads and two receiving plates moving to the next welding station;

[0059] In the figure:

[0060] 1-sewage pipe, 2-connector, 3-ring, 4-fixing plate;

[0061] 5- pad, 6- welding and material receiving mechanism, 7- feeding mechanism, 8- arch frame, 9- base, 10- positioning column, 11- screw nut pair, 12- welding cylinder, 13- material receiving cylinder, 14- spot welding head, 15- material receiving plate;

[0062] 16- platform, 17- horizontal cylinder, 18- vertical cylinder, 19- bracket, 20- clamping cylinder, 21- chuck;

[0063] 22-frame, 23-screw rod, 24-nut, 25-driving motor, 26-L plate. DETAILED DESCRIPTION

[0064] The present invention is further described below in conjunction with the accompanying drawings, and the protection scope of the present invention is not limited to the following:

[0065] like Figure 6~Figure 11 As shown, a double-root sewage pipe welding device comprises a backing plate 5, a welding and material receiving mechanism 6 arranged on the backing plate 5, and a feeding mechanism 7 for feeding a connecting piece 2 to the welding and material receiving mechanism 6. The welding and material receiving mechanism 6 comprises an arch frame 8 fixedly arranged on the backing plate 5, and two bases 9 fixedly arranged on the top surface of the arch frame 8. Positioning columns 10 are fixedly arranged on the top surfaces of the two bases 9. The outer diameter of the positioning column 10 is equal to the inner diameter of the sewage pipe 1. The arch frame 8 is provided with two vertically arranged screw nut pairs 11. The two screw nut pairs 11 are provided on the arch frame 8. The screw rod and nut pairs 11 are respectively located on the outside of the two bases 9, and the inner sides of the nuts 24 of the screw rod and nut pairs 11 are fixed with vertical plates. The inner end faces of the vertical plates are fixed with welding cylinders 12 and material receiving cylinders 13. A movable plate is fixed on the active end of the piston rod of the welding cylinder 12, and a horizontally arranged spot welding head 14 is fixed on the movable plate. The other end of the spot welding head 14 is connected to the welding machine via a power cord. An L-shaped material receiving plate 15 is fixed on the active end of the piston rod of the material receiving cylinder 13, and the material receiving plate 15 is located directly below the spot welding head 14.

[0066] The feeding mechanism 7 includes a platform 16 fixed on the pad 5, a connecting plate fixed on the top surface of the platform 16, and a horizontal cylinder 17 fixed on the right end surface of the connecting plate. A plurality of supporting legs are fixed between the platform 16 and the pad 5. The piston rod of the horizontal cylinder 17 passes through the connecting plate, and a vertical cylinder 18 is fixed on the extended end. A bracket 19 is fixed on the active end of the piston rod of the vertical cylinder 18. A clamping cylinder 20 is fixed on the bottom surface of the bracket 19 and on the left and right ends of the bracket 19. The two clamping cylinders 20 are symmetrically arranged about the vertical cylinder 18, and the clamps 21 of the two clamping cylinders 20 are both arranged downward. An L plate 26 is fixed on the active end of the piston rod of the horizontal cylinder 17, and the vertical cylinder 18 is fixed on the top surface of the L plate 26.

[0067] The screw-nut pair 11 includes a frame 22 fixed on the top surface of the arch frame 8, a screw 23 rotatably installed in the frame 22, and a nut 24 threadedly connected to the screw 23. A driving motor 25 and a polished rod are also fixed on the frame 22. The driving motor 25 is connected to the lower end of the screw 23, the polished rod is arranged parallel to the screw 23, and the polished rod passes through the nut.

[0068] The welding device also includes a controller, which is electrically connected to the horizontal cylinder 17, the vertical cylinder 18, the clamping cylinder 20, the drive motor 25, the material receiving cylinder 13 and the welding cylinder 12 via a signal line. The worker can control the extension or retraction of the piston rods of the horizontal cylinder 17, the vertical cylinder 18, the material receiving cylinder 13 and the welding cylinder 12 through the controller, and can also control the start or shut down of the drive motor 25 and the clamping cylinder 20. When the clamping cylinder 20 is started, the chuck 21 is closed, which facilitates the worker's operation.

[0069] A welding method for double sewage pipes comprises the following steps:

[0070] S1, workers stack multiple pieces of the above-mentioned material on the top surface of the platform 16 of the feeding mechanism 7 from bottom to top. Figure 3~Figure 4 The connector 2 shown in the figure, at the same time, ensure that the two collars 3 of the topmost connector 2 are respectively directly below the two clamps 21 of the feeding mechanism 7, so as to achieve pre-stacking of multiple connectors 2, as shown in FIG. Fig.12 As shown;

[0071] S2. Positioning of two sewage pipes 1: The worker takes out two sewage pipes 1, and respectively puts the two sewage pipes 1 on the two positioning columns 10 of the welding and material connection mechanism 6, and supports the sewage pipes 1 on the top surface of the base 9. Since the outer diameter of the positioning column 10 is equal to the inner diameter of the sewage pipe 1, the positioning of the two sewage pipes 1 is achieved. Fig.13 As shown, at this time, both sewage pipes 1 are in the welding position;

[0072] S3, welding of the first connecting piece 2 and the two sewage pipes 1, the specific operation steps are as follows:

[0073] S31, control the piston rod of the vertical cylinder 18 of the feeding mechanism 7 to extend downward, the piston rod drives the bracket 19 to move downward, the bracket 19 drives the two clamping cylinders 20 to move downward synchronously, the clamping cylinders 20 drives the chucks 21 to move downward synchronously, when the piston rod of the vertical cylinder 18 extends to the set stroke, the controller controls the vertical cylinder 18 to close, at this time, the two chucks 21 are respectively sleeved on the outer walls of the two collars 3 of the topmost connecting piece 2, as shown in FIG. Fig.14 As shown;

[0074] S32, control the two clamping cylinders 20 to start, the clamping cylinders 20 drive the clamps 21 to close, and the two clamps 21 clamp and fix the two collars 3 of the topmost connecting piece 2 respectively;

[0075] S33, control the piston rod of the vertical oil cylinder 18 to retract upward, the piston rod drives the bracket 19 to move upward, the bracket 19 drives the two clamping oil cylinders 20 to move upward, the clamping oil cylinders 20 drives the chuck 21 to move upward, the chuck 21 drives the first connecting member 2 to move upward, so as to lift the first connecting member 2, as shown in FIG. Fig.15 As shown;

[0076] S34, the piston rod of the horizontal oil cylinder 17 of the control feeding mechanism 7 extends to the left, the piston rod drives the L plate 26 to move to the left, the L plate 26 drives the vertical oil cylinder 18 to move to the left, the vertical oil cylinder 18 drives the bracket 19 and the two clamping oil cylinders 20 to move to the left, and then drives the first connecting piece 2 to move to the left. When the piston rod of the horizontal oil cylinder 17 is fully extended, the two collars 3 of the first connecting piece 2 are respectively located directly above the two sewage pipes 1, as shown in FIG. Fig.16 As shown;

[0077] S35, control the piston rod of the vertical oil cylinder 18 to extend downward, the piston rod drives the bracket 19 to move downward, the bracket 19 drives the two clamping oil cylinders 20 to move downward, and then drives the first connecting piece 2 to move downward. When the piston rod of the vertical oil cylinder 18 extends to the set stroke, the controller controls the vertical oil cylinder 18 to close. At this time, the two collars 3 of the first connecting piece 2 are respectively located directly above the two sewage pipes 1, such as Fig.17 As shown;

[0078] S36, control the piston rods of the receiving cylinders 13 on the two screw nut pairs 11 to extend, and the piston rods drive the receiving plates 15 to move toward the corresponding sewage pipes 1. When the piston rods of the receiving cylinders 13 are fully extended, the two receiving plates 15 approach the two sewage pipes 1 respectively. At this time, the two receiving plates 15 are both in the receiving position. Fig.17 As shown;

[0079] S37, control the two clamping cylinders 20 to close, the clamping cylinders 20 drive the chuck 21 to open, the chuck 21 no longer clamps the collar 3 of the connector 2, and under its own gravity, the two collars 3 of the connector 2 are respectively sleeved on the two sewage pipes 1 and move downward along the sewage pipes 1 until the two collars 3 of the connector 2 are respectively blocked by the two receiving plates 15, thereby achieving the connection of the connector 2, such as Fig.18 As shown, at this time, the position of the connecting member 2 is the welding position of the first connecting member 2, and at the same time, the two collars 3 of the connecting member 2 are respectively opposite to the two spot welding heads 14;

[0080] S38, control the piston rods of the two welding cylinders 12 of the welding and material receiving mechanism 6 to extend, the piston rods drive the movable plate to move toward the collar 3, and the movable plate drives the spot welding head 14 to move toward the collar 3. When the piston rods of the welding cylinders 12 are fully extended, the two spot welding heads 14 contact the outer walls of the two collars 3 of the connecting piece 2 respectively, as shown in FIG. Fig.19 As shown, the first connecting piece 2 is finally welded between the two sewage pipes 1;

[0081] S4, control the piston rods of the two welding cylinders 12 of the welding and material receiving mechanism 6 to retract, and the piston rods drive the spot welding head 14 to reset, and then control the piston rods of the two material receiving cylinders 13 to retract, and the piston rods drive the material receiving plate 15 to reset; after resetting, control the drive motors 25 of the two screw nut pairs 11 to start, and the nut 24 moves upward along the screw 23, and the nut 24 drives the vertical plate to move upward, and the vertical plate drives the welding cylinder 12 and the material receiving cylinder 13 to move upward synchronously, and when the nut 24 moves upward to the set stroke, the controller controls the drive motor 25 to turn off, at this time, the two spot welding heads 14 and the two material receiving plates 15 are just in the next welding position, such as Fig. 20 As shown;

[0082] S5. The worker repeats the operations of steps S3 to S4 to weld the multiple connectors 2 between the two sewage pipes 1, thereby finally welding the two sewage pipes 1 into one body. The structure of the two sewage pipes 1 after welding is as follows: Figure 1~Figure 2 As shown;

[0083] Among them, from steps S3 to S5, it can be known that the welding device can automatically and quickly weld multiple connectors 2 to two sewage pipes 1 through the linkage of welding and the material receiving mechanism 6 and the feeding mechanism 7, thereby realizing the welding of the two sewage pipes 1 into one in a short time. It can be seen that compared with the welding method in the workshop, the welding device does not require workers to spot weld one by one, which not only greatly reduces the work intensity of the workers, but also greatly shortens the welding time of the connector 2 and the two sewage pipes 1, thereby greatly improving the welding efficiency of the two sewage pipes 1.

[0084] In addition, the welding device controls the extension of the piston rod of the material receiving cylinder 13 to make the material receiving plate 15 close to the sewage pipe 1, so that the connecting piece 2 sliding downward along the sewage pipe 1 is received by the material receiving plate 15, and the position of receiving the connecting piece 2 is the welding position of the connecting piece 2, and finally, by extending the piston rod of the welding cylinder 12, the connecting piece 2 can be welded to the sewage pipe 1 through the spot welding head 14. It can be seen that compared with the welding method in the workshop, the welding device does not need to mark the two sewage pipes 1 along their length direction in advance before welding, thereby greatly saving the welding process, thereby shortening the subsequent welding time of the connecting piece 2 and the two sewage pipes 1, and further improving the welding efficiency of the two sewage pipes 1.

[0085] S6. After welding is completed, the worker removes the two welded sewage pipes 1 from the two positioning columns 10;

[0086] S7. The worker repeats the operations of steps S2 to S6 for multiple times, and can continuously weld multiple groups of sewage pipes 1 together.

[0087] Finally, it should be noted that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A double sewage pipe welding device, characterized in that: It comprises a backing plate (5), a welding and material receiving mechanism (6) arranged on the backing plate (5), and a feeding mechanism (7) for feeding a connecting piece (2) to the welding and material receiving mechanism (6). The welding and material receiving mechanism (6) comprises an arch frame (8) fixedly arranged on the backing plate (5), two bases (9) fixedly arranged on the top surface of the arch frame (8), and positioning columns (10) are fixedly arranged on the top surfaces of the two bases (9). The arch frame (8) is provided with two vertically arranged screw nut pairs (11), and the two screw nut pairs (11) are respectively located at two A vertical plate is fixedly provided on the outer side of each base (9) and the inner side of the nut (24) of the screw nut pair (11). A welding cylinder (12) and a material receiving cylinder (13) are fixedly provided on the inner end surface of the vertical plate. A movable plate is fixedly provided on the active end of the piston rod of the welding cylinder (12). A horizontally arranged spot welding head (14) is fixedly provided on the movable plate. The other end of the spot welding head (14) is connected to the welding machine via a power cord. An L-shaped material receiving plate (15) is fixedly provided on the active end of the piston rod of the material receiving cylinder (13). The material receiving plate (15) is located directly below the spot welding head (14). The feeding mechanism (7) comprises a platform (16) fixedly mounted on the pad (5), a connecting plate fixedly mounted on the top surface of the platform (16), and a horizontal oil cylinder (17) fixedly mounted on the right end surface of the connecting plate. The piston rod of the horizontal oil cylinder (17) passes through the connecting plate, and a vertical oil cylinder (18) is fixedly mounted on the extending end. A bracket (19) is fixedly mounted on the action end of the piston rod of the vertical oil cylinder (18). A clamping oil cylinder (20) is fixedly mounted on the bottom surface of the bracket (19) and at the left and right ends of the bracket (19). The clamping heads (21) of the two clamping oil cylinders (20) are both arranged downward.

2. A double sewage pipe welding device according to claim 1, characterized in that: The screw rod and nut pair (11) comprises a frame (22) fixedly mounted on the top surface of the arch frame (8), a screw rod (23) rotatably mounted in the frame (22), and a nut (24) threadedly connected to the screw rod (23). A drive motor (25) and a polished rod are also fixedly mounted on the frame (22). The drive motor (25) is connected to the lower end of the screw rod (23). The polished rod is arranged parallel to the screw rod (23), and the polished rod passes through the nut.

3. A double sewage pipe welding device according to claim 2, characterized in that: A plurality of supporting legs are fixedly arranged between the platform (16) and the pad (5).

4. A double sewage pipe welding device according to claim 3, characterized in that: The two clamping oil cylinders (20) are arranged symmetrically with respect to the vertical oil cylinder (18).

5. A double sewage pipe welding device according to claim 4, characterized in that: The outer diameter of the positioning column (10) is equal to the inner diameter of the sewage pipe (1).

6. A double sewage pipe welding device according to claim 5, characterized in that: An L-plate (26) is fixedly provided on the action end of the piston rod of the horizontal oil cylinder (17), and the vertical oil cylinder (18) is fixedly provided on the top surface of the L-plate (26).

7. A double sewage pipe welding device according to claim 6, characterized in that: The welding device also includes a controller, which is electrically connected to the horizontal cylinder (17), the vertical cylinder (18), the clamping cylinder (20), the drive motor (25), the material receiving cylinder (13) and the welding cylinder (12) via a signal line.

8. A method for welding double sewage pipes, using the double sewage pipe welding device according to claim 7, characterized in that: It includes the following steps: S1. A worker stacks a plurality of connectors (2) on the top surface of the platform (16) of the feeding mechanism (7) from bottom to top, and at the same time, ensures that the two collars (3) of the connector (2) on the top layer are respectively located directly below the two clamps (21) of the feeding mechanism (7), thereby achieving pre-stacking of the plurality of connectors (2); S2. Positioning of the two sewage pipes (1): the worker takes out the two sewage pipes (1), respectively puts the two sewage pipes (1) on the two positioning columns (10) of the welding and material connection mechanism (6), and supports the sewage pipes (1) on the top surface of the base (9). Since the outer diameter of the positioning column (10) is equal to the inner diameter of the sewage pipe (1), the positioning of the two sewage pipes (1) is achieved. At this time, the two sewage pipes (1) are both in the welding position; S3. Welding of the first connecting piece (2) and the two sewage pipes (1), the specific operation steps are as follows: S31, controlling the piston rod of the vertical oil cylinder (18) of the feeding mechanism (7) to extend downward, the piston rod drives the bracket (19) to move downward, the bracket (19) drives the two clamping oil cylinders (20) to move downward synchronously, the clamping oil cylinders (20) drives the chuck (21) to move downward synchronously, when the piston rod of the vertical oil cylinder (18) extends to a set stroke, the controller controls the vertical oil cylinder (18) to close, at which time, the two chucks (21) are respectively sleeved on the outer walls of the two collars (3) of the topmost connecting piece (2); S32, controlling the two clamping oil cylinders (20) to start, the clamping oil cylinders (20) drive the clamping heads (21) to close, and the two clamping heads (21) respectively clamp and fix the two collars (3) of the topmost connecting piece (2); S33, controlling the piston rod of the vertical oil cylinder (18) to retract upward, the piston rod drives the bracket (19) to move upward, the bracket (19) drives the two clamping oil cylinders (20) to move upward, the clamping oil cylinders (20) drive the chuck (21) to move upward, and the chuck (21) drives the first connecting member (2) to move upward, thereby lifting the first connecting member (2); S34, the piston rod of the horizontal oil cylinder (17) of the control feeding mechanism (7) extends to the left, the piston rod drives the L plate (26) to move to the left, the L plate (26) drives the vertical oil cylinder (18) to move to the left, the vertical oil cylinder (18) drives the bracket (19) and the two clamping oil cylinders (20) to move to the left, and then drives the first connecting member (2) to move to the left. When the piston rod of the horizontal oil cylinder (17) is fully extended, the two collars (3) of the first connecting member (2) are respectively located directly above the two sewage pipes (1); S35, controlling the piston rod of the vertical oil cylinder (18) to extend downward, the piston rod drives the bracket (19) to move downward, the bracket (19) drives the two clamping oil cylinders (20) to move downward, and then drives the first connecting piece (2) to move downward. When the piston rod of the vertical oil cylinder (18) extends to a set stroke, the controller controls the vertical oil cylinder (18) to close. At this time, the two collars (3) of the first connecting piece (2) are respectively located directly above the two sewage pipes (1); S36, controlling the piston rods of the material receiving cylinders (13) on the two screw nut pairs (11) to extend, and the piston rods drive the material receiving plates (15) to move in the direction of the corresponding sewage pipes (1). When the piston rods of the material receiving cylinders (13) are fully extended, the two material receiving plates (15) are respectively close to the two sewage pipes (1). At this time, the two material receiving plates (15) are both in the material receiving position; S37, control the two clamping cylinders (20) to close, the clamping cylinders (20) drive the chuck (21) to open, the chuck (21) no longer clamps the collar (3) of the connecting piece (2), and under its own weight, the two collars (3) of the connecting piece (2) are respectively sleeved on the two sewage pipes (1) and move downward along the sewage pipes (1) until the two collars (3) of the connecting piece (2) are respectively blocked by the two receiving plates (15), thereby achieving the connection of the connecting piece (2). At this time, the position of the connecting piece (2) is the welding position of the first connecting piece (2), and at the same time, the two collars (3) of the connecting piece (2) are respectively opposite to the two spot welding heads (14); S38, the piston rods of the two welding cylinders (12) of the control welding and material receiving mechanism (6) are extended, the piston rods drive the movable plate to move toward the collar (3), and the movable plate drives the spot welding head (14) to move toward the collar (3). When the piston rod of the welding cylinder (12) is fully extended, the two spot welding heads (14) respectively contact the outer walls of the two collars (3) of the connecting piece (2), thereby finally achieving the welding of the first connecting piece (2) between the two sewage pipes (1); S4, control the piston rods of the two welding cylinders (12) of the welding and material receiving mechanism (6) to retract, the piston rods drive the spot welding head (14) to reset, and then control the piston rods of the two material receiving cylinders (13) to retract, the piston rods drive the material receiving plate (15) to reset; after resetting, control the drive motors (25) of the two screw nut pairs (11) to start, the nuts (24) move upward along the screws (23), the nuts (24) drive the vertical plate to move upward, the vertical plate drives the welding cylinder (12) and the material receiving cylinder (13) to move upward synchronously, and when the nuts (24) move upward to the set stroke, the controller controls the drive motor (25) to turn off, at which time, the two spot welding heads (14) and the two material receiving plates (15) are just at the next welding station; S5. The worker repeats the operations of steps S3 to S4 to weld the plurality of connectors (2) between the two sewage pipes (1), thereby finally welding the two sewage pipes (1) together. S6. After welding is completed, the worker removes the two welded sewage pipes (1) from the two positioning columns (10); S7. The worker repeats the operations of steps S2 to S6 for multiple times, and can continuously weld multiple sets of sewage pipes (1) together.