A production workshop management system and method based on data analysis
By building a dynamic scheduling model and predicting the fitness coefficient of the production line, we analyze whether a new production line is needed in the production workshop and plan its construction location and specifications. This solves the problem that the existing system cannot reasonably plan and improves the efficiency of the production line and the system management effect. .
Patent Information
- Application Number
- CN202411096143.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-12
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2044-08-12
AI Technical Summary
The existing production workshop management system cannot effectively analyze the scheduling possibilities of the production line and rationally plan new production lines, resulting in a waste of resources and reduced system usage.
By building a dynamic scheduling model, we can obtain the performance and dynamic index information of the production line, predict the fitness coefficient and scheduling index of the production line, analyze whether a new production line is needed, and plan its construction location and specifications.
This avoids waste of resources, ensures that the new production line meets demand, and improves the processing efficiency and system management effect of the production line.
Smart Images

Figure CN118627860B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of production workshop management, and in particular to a production workshop management system and method based on data analysis. Background Art
[0002] Workshop management refers to a series of management tasks including planning, organizing, directing, coordinating and controlling various production and operation activities carried out by the workshop.
[0003] Nowadays, when managing a production workshop, the production lines in the production workshop are usually scheduled according to the sequence of the production plans in the production workshop. However, frequent scheduling of production lines will waste the production time of the production lines, and it is impossible to analyze whether the current production line has the possibility of being scheduled. At the same time, the existing system cannot reasonably plan the new production lines in the production workshop, which reduces the effectiveness of the system. Summary of the invention
[0004] The purpose of the present invention is to provide a production workshop management system and method based on data analysis to solve the problems raised in the above background technology.
[0005] In order to solve the above technical problems, the present invention provides the following technical solutions: a production workshop management method based on data analysis, the method comprising:
[0006] S10: According to the production status information of each production line in the production workshop, the efficiency index information and dynamic index information of each production line in the production workshop are obtained, and based on the obtained information, a dynamic scheduling model of each production line is constructed;
[0007] S20: Obtain the production plan of each production line, predict the fitness coefficient of each production line under different production plans, and predict the dynamic scheduling coefficient of each production line based on the correlation between the production lines. Based on the prediction results, analyze whether the production workshop needs to add a new production line;
[0008] S30: Plan the construction location and construction specifications of the new production line in the production workshop;
[0009] S40: Based on the planning results, manage the production parameters of the newly added production line in the production workshop.
[0010] Further, the S10 includes:
[0011] S102: When the production line is in normal operation, the efficiency index information and dynamic index information of the production line are obtained. The efficiency index includes production delay time and production energy consumption. Production delay time = β * (actual production time of the production line - scheduled production time of the production line). When the actual production time of the production line - the scheduled production time of the production line> 0, β = 1. When the actual production time of the production line - the scheduled production time of the production line ≤ 0, β = 0. Production energy consumption = working power of a single set of machine equipment in the production line × working time of a single set of machine equipment × proportion of loss of a single set of machine equipment in the process of converting electrical energy into useful energy × number of sets of machine equipment in the production line. Dynamic indicators include process delay time and machine failure conditions.
[0012] S103: The first linear model is constructed with the use time t of the production line as the independent variable and the production energy consumption S of the production line as the dependent variable. The first linear model is: S t =k1*t+b1, the second linear model is constructed with the production line usage time t as the independent variable and the production line process delay time T as the dependent variable. The second linear model is: T t =k2*t+b2, where k1 and k2 represent the weight coefficients of the first linear model and the second linear model respectively, and b1 and b2 represent the weight coefficients of the first linear model and the second linear model respectively;
[0013] Construct a dynamic scheduling model for each production line. The specific dynamic scheduling model is:
[0014] ;
[0015] Where j=1,2,…,n, represents the number of each production line in the existing production line of the production workshop, n represents the total number of production lines, i=1,2,…,m, represents the number of the machine equipment in the production line, m j G represents the total number of machines and equipment installed in the jth production line. vj represents the production delay time of the jth production line at time v, S j(v→t) represents the production energy consumption of the j-th production line when it is used for time t. The corresponding use time of the j-th production line at time v is t, T j(v→t) represents the process delay time corresponding to the j-th production line when it is used for time t. The corresponding use time of the j-th production line at time v is t, r ji =0 or r ji =1, when r ji = 0, it means that the i-th machine equipment in the j-th production line fails. ji =1, indicating that the i-th machine equipment in the j-th production line has not failed, e is a constant and e>1, W vj Represents the scheduling index corresponding to the j-th production line at time v.
[0016] Further, the S20 includes:
[0017] S101: Acquire production status information of each existing production line in the production workshop, where the production status includes normal operation status, shutdown status, standby status and maintenance status;
[0018] S201: Obtain the production plan of each production line, which includes production completion time, production volume and production material reserve. Combined with the constructed second linear model, predict the fitness coefficient of each production line under different production plans. The specific prediction formula is:
[0019] ;
[0020] Among them, c j It represents the production completion time corresponding to the production plan when the j-th production line executes the production plan, g j represents the time when the jth production line starts to execute the production plan, g j →t1 indicates that the jth production line is at g j The usage time corresponding to the moment is t1, c j →t2 means the jth production line is at c j The usage time corresponding to the moment is t2, Indicates that a single set of equipment in the jth production line is j The time required to complete a part at a time, U j It represents the production material reserve of the production workshop when the j-th production line starts to execute the production plan, a j It represents the amount of material consumed by a single set of equipment in the jth production line when processing a part. Min represents the minimum value symbol. Y j represents the production volume of the jth production line when executing the production plan, Q j It represents the fitness coefficient of the j-th production line when executing the production plan;
[0021] S202: Acquire the association between the production lines. If the production sequence between two production lines cannot be changed, the two production lines are considered to be associated production lines. If the production sequence between the two production lines can be changed, the two production lines are considered to be unassociated production lines.
[0022] S203: When the jth production line and other production lines in the production workshop are unrelated production lines, according to The dynamic scheduling coefficient of each production line is predicted, where: Indicates that the jth production line is at g j The scheduling index corresponding to the time, Fj represents the dynamic scheduling coefficient of the j-th production line;
[0023] When the jth production line and the pth production line are associated production lines, according to Predict the dynamic scheduling coefficients of the j-th production line and the p-th production line, where p=1,2,…,n and p≠j, Q p It represents the fitness coefficient of the pth production line when executing the production plan. Indicates that the pth production line is in g p The scheduling index corresponding to the time, F p represents the dynamic scheduling coefficient of the p-th production line;
[0024] S204: The number of times the j-th production line is scheduled B j To obtain, j ≥0.6 times H j To obtain, if B j / H j ≥1, it is considered that the production workshop needs to add a new production line. If B j / H j <1, it is considered that the production workshop does not need to add a new production line.
[0025] Further, the S30 includes:
[0026] When it is considered that a new production line is needed in the production workshop, max(B j / H j ) is determined, and based on the determination result, the type of the newly added production line in the production workshop is determined;
[0027] When the type of the newly added production line in the production workshop is the type of the j-th production line, the construction location of the newly added production line in the production workshop is the area to which the j-th production line belongs. The construction specifications of the newly added production line in the production workshop are: the number of sets of machinery and equipment in the newly added production line in the production workshop is K, , Express Round up, where z=1,2,…,B, represents the number corresponding to the number of times the production line is scheduled, B represents the total number, and Y jz represents the production volume of the jth production line when the production plan is executed for the zth time, c jz It represents the production completion time of the j-th production line when the production plan is executed for the z-th time, g jz It indicates the time when the jth production line starts to execute the production plan for the zth time, E jz It represents the time required for a single set of machine equipment in the jth production line to complete a part when the production plan is executed for the zth time.
[0028] Further, the S40 includes: when the type of the newly added production line in the production workshop is the type of the j-th production line, the production parameters of the newly added production line in the production workshop are the production parameters of the j-th production line.
[0029] A production workshop management system based on data analysis, the system includes a production line dynamic scheduling model building module, a production line new situation prediction module, a production line planning module and a planning management module;
[0030] The production line dynamic scheduling model building module is used to build a dynamic scheduling model for each production line according to the efficiency index information and dynamic index information of each production line in the existing production line of the production workshop;
[0031] The production line addition prediction module is used to analyze and predict the addition of production lines in the production workshop;
[0032] The production line planning module is used to plan the construction location and construction specifications of the new production line in the production workshop;
[0033] The planning management module is used to manage the production parameters of the newly added production line in the production workshop.
[0034] Furthermore, the production line dynamic scheduling model building module includes a production status information acquisition unit, an indicator information acquisition unit, a linear model building unit and a dynamic scheduling model building unit;
[0035] The production status information acquisition unit acquires the production status information of each production line in the existing production line of the production workshop;
[0036] The index information acquisition unit acquires the efficiency index information and dynamic index information of the production line when the production line is in normal operation;
[0037] The linear model building unit builds a first linear model with the use time of the production line as the independent variable and the production energy consumption of the production line as the dependent variable, and builds a second linear model with the use time of the production line as the independent variable and the process delay time of the production line as the dependent variable;
[0038] The dynamic scheduling model construction unit constructs a dynamic scheduling model for each production line according to the constructed first line model, the second line model, and the acquired efficiency index information and dynamic index information.
[0039] Furthermore, the production line addition situation prediction module includes a fitness coefficient prediction unit, an associated production line determination unit, a dynamic scheduling coefficient prediction unit and a production line addition situation prediction unit;
[0040] The fitness coefficient prediction unit predicts the fitness coefficient of each production line under different production plans according to the production plan of each production line and the constructed second linear model;
[0041] The associated production line determination unit determines the association between the two production lines according to the change of the production sequence between the two production lines;
[0042] The dynamic scheduling coefficient prediction unit predicts the dynamic scheduling coefficient of each production line according to the prediction result transmitted by the fitness coefficient prediction unit and the dynamic scheduling model transmitted by the dynamic scheduling model construction unit;
[0043] The production line addition prediction unit analyzes and predicts the addition of production lines in the production workshop based on the prediction results transmitted by the dynamic scheduling coefficient prediction unit and the number of times the production line is scheduled.
[0044] Further, the production line planning module includes a new production line type determination unit, a new production line construction location planning unit and a new production line construction specification planning unit;
[0045] When the new production line type determination unit determines that a new production line is needed in the production workshop, the new production line type determination unit determines the type of the new production line in the production workshop according to the set conditions;
[0046] The new production line construction location planning unit plans the construction location of the new production line in the production workshop according to the type of the new production line in the production workshop;
[0047] The newly added production line construction specification planning unit plans the construction specifications of the newly added production line in the production workshop according to the execution status of the production plan when the production line executes the production plan.
[0048] Furthermore, the planning management module manages the production parameters of the newly added production line in the production workshop according to the type of the newly added production line in the production workshop.
[0049] Compared with the prior art, the beneficial effects achieved by the present invention are:
[0050] 1. The present invention predicts the real-time scheduling index of each production line through the constructed dynamic scheduling model, and analyzes the new production lines in the production workshop in combination with the fitness coefficient of each production line under different production plans, so as to avoid too many new production lines in the production workshop, which leads to waste of resources. In the analysis process, the scheduling constraints of efficiency indicators and dynamic indicators on each production line are taken into account to ensure the reasonable planning of the new production lines, thereby further improving the management effect of the system.
[0051] 2. The present invention analyzes the addition of production lines in a production workshop based on the processing efficiency of parts processed by the production line under different usage environments and the predicted dynamic scheduling coefficient, ensuring that the newly added production lines can meet production needs, thereby reducing the scheduling frequency of each production line and improving the processing efficiency of each production line.
[0052] 3. The present invention determines the specifications of the newly added production line based on the type of the newly added production line and the production plan of the production line, thereby improving planning accuracy. BRIEF DESCRIPTION OF THE DRAWINGS
[0053] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:
[0054] Figure 1 It is a workflow diagram of a production workshop management system and method based on data analysis of the present invention;
[0055] Figure 2 It is a schematic diagram of the working principle structure of a production workshop management system and method based on data analysis of the present invention. DETAILED DESCRIPTION
[0056] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0057] See also Figure 1 and Figure 2 The present invention provides a technical solution: a production workshop management method based on data analysis, the method comprising:
[0058] S10: According to the production status information of each production line in the production workshop, the efficiency index information and dynamic index information of each production line in the production workshop are obtained, and based on the obtained information, a dynamic scheduling model of each production line is constructed;
[0059] S10 includes:
[0060] S101: Acquire production status information of each existing production line in the production workshop, where the production status includes normal operation status, shutdown status, standby status and maintenance status;
[0061] S102: When the production line is in normal operation, the efficiency index information and dynamic index information of the production line are obtained. The efficiency index includes production delay time and production energy consumption. Production delay time = β * (actual production time of the production line - scheduled production time of the production line). When the actual production time of the production line - the scheduled production time of the production line> 0, β = 1. When the actual production time of the production line - the scheduled production time of the production line ≤ 0, β = 0. Production energy consumption = working power of a single set of equipment in the production line × working time of a single set of equipment × proportion of loss of a single set of equipment in the process of converting electrical energy into useful energy × number of equipment in the production line. Specifically: Assume that the scheduled production time of the production line is The production time is 16:00, and the actual production time of the production line is 16:30. The production delay time of the production line = 1*(16:30-16:00) = 30 minutes. The dynamic indicators include process delay time and machine failure. The process delay time refers to the processing interval time between two adjacent processing parts when the machine equipment in the production line processes the processing parts. Specifically, when the machine equipment in the production line processes the first and second processing parts, the processing completion time of the first processing part is 12:00, and the initial processing time of the second processing part is 12:10. Then the processing interval time between the first and second processing parts = 12:10-12:00 = 10 minutes;
[0062] S103: The first linear model is constructed with the use time t of the production line as the independent variable and the production energy consumption S of the production line as the dependent variable. The first linear model is: S t =k1*t+b1, the second linear model is constructed with the production line usage time t as the independent variable and the production line process delay time T as the dependent variable. The second linear model is: T t =k2*t+b2, where k1 and k2 represent the weight coefficients of the first linear model and the second linear model respectively, and b1 and b2 represent the weight coefficients of the first linear model and the second linear model respectively;
[0063] Construct a dynamic scheduling model for each production line. The specific dynamic scheduling model is:
[0064] ;
[0065] Where j=1,2,…,n, represents the number of each production line in the existing production line of the production workshop, n represents the total number of production lines, i=1,2,…,m, represents the number of the machine equipment in the production line, m j G represents the total number of machines and equipment installed in the jth production line. vj represents the production delay time of the jth production line at time v, S j(v→t)represents the production energy consumption of the j-th production line when it is used for time t. The corresponding use time of the j-th production line at time v is t, T j(v→t) represents the process delay time corresponding to the j-th production line when it is used for time t. The corresponding use time of the j-th production line at time v is t, r ji =0 or r ji =1, when r ji = 0, it means that the i-th machine equipment in the j-th production line fails. ji =1, indicating that the i-th machine equipment in the j-th production line has not failed, e is a constant and e>1, W vj represents the scheduling index corresponding to the j-th production line at time v;
[0066] The dynamic scheduling model constructed is used to predict the real-time scheduling index of each production line, ensuring that when planning new production lines in the production workshop, the production lines in different usage environments have different processing efficiencies for processing parts, which may cause the planned new production lines to fail to meet production needs.
[0067] S20: Obtain the production plan of each production line, predict the fitness coefficient of each production line under different production plans, and predict the dynamic scheduling coefficient of each production line based on the correlation between the production lines. Based on the prediction results, analyze whether the production workshop needs to add a new production line;
[0068] The S20 includes:
[0069] S201: Obtain the production plan of each production line, which includes production completion time, production volume and production material reserve. Combined with the constructed second linear model, predict the fitness coefficient of each production line under different production plans. The specific prediction formula is:
[0070] ;
[0071] Among them, c j It represents the production completion time corresponding to the production plan when the j-th production line executes the production plan, g j represents the time when the jth production line starts to execute the production plan, g j →t1 indicates that the jth production line is at g j The usage time corresponding to the moment is t1, c j →t2 means the jth production line is at c j The usage time corresponding to the moment is t2, Indicates that a single set of equipment in the jth production line is j The time required to complete a part at a time, U jIt represents the production material reserve of the production workshop when the j-th production line starts to execute the production plan, a j It represents the amount of material consumed by a single set of equipment in the jth production line when processing a part. Min represents the minimum value symbol. Y j represents the production volume of the jth production line when executing the production plan, represents the process delay time corresponding to the j-th production line when executing the production plan, Q j It represents the fitness coefficient of the jth production line when executing the production plan. The fitness coefficient refers to the probability value that the production line can complete the production plan;
[0072] S202: Acquire the association between the production lines. If the production sequence between two production lines cannot be changed, the two production lines are considered to be associated production lines. If the production sequence between the two production lines can be changed, the two production lines are considered to be unassociated production lines.
[0073] S203: When the jth production line and other production lines in the production workshop are unrelated production lines, according to The dynamic scheduling coefficient of each production line is predicted, where: Indicates that the jth production line is at g j The scheduling index corresponding to the time, F j represents the dynamic scheduling coefficient of the j-th production line;
[0074] When the jth production line and the pth production line are associated production lines, according to Predict the dynamic scheduling coefficients of the j-th production line and the p-th production line, where p=1,2,…,n and p≠j, Q p It represents the fitness coefficient of the pth production line when executing the production plan. Indicates that the pth production line is in g p The scheduling index corresponding to the time, F p represents the dynamic scheduling coefficient of the pth production line; the dynamic scheduling coefficient refers to the degree of scheduling of the production line under the constraints of dynamic indicators and efficiency indicators;
[0075] S204: The number of times the j-th production line is scheduled B j To obtain, j ≥0.6 times H j To obtain, if B j / H j ≥1, it is considered that the production workshop needs to add a new production line. If B j / H j <1, it is considered that the production workshop does not need to add a new production line;
[0076] According to the dispatchability of existing production lines in the production workshop, analyze and predict the new production lines in the production workshop to avoid excessive new production lines in the production workshop, which will lead to waste of resources;
[0077] S30: Plan the construction location and construction specifications of the new production line in the production workshop;
[0078] S30 includes:
[0079] When it is considered that a new production line is needed in the production workshop, max(B j / H j ) is determined, and based on the determination result, the type of the newly added production line in the production workshop is determined;
[0080] When the type of the newly added production line in the production workshop is the type of the j-th production line, the construction location of the newly added production line in the production workshop is the area to which the j-th production line belongs. The construction specifications of the newly added production line in the production workshop are: the number of sets of machinery and equipment in the newly added production line in the production workshop is K, , Express Round up, where z=1,2,…,B, represents the number corresponding to the number of times the production line is scheduled, B represents the total number, and Y jz represents the production volume of the jth production line when the production plan is executed for the zth time, c jz It represents the production completion time of the j-th production line when the production plan is executed for the z-th time, g jz It indicates the time when the jth production line starts to execute the production plan for the zth time, E jz It represents the time required for a single set of equipment in the jth production line to complete a part when the production plan is executed for the zth time;
[0081] S40: Based on the planning results, manage the production parameters of the newly added production lines in the production workshop;
[0082] S40 includes: when the type of the newly added production line in the production workshop is the type of the j-th production line, the production parameters of the newly added production line in the production workshop are the production parameters of the j-th production line.
[0083] A production workshop management system based on data analysis, the system includes a production line dynamic scheduling model building module, a production line new situation prediction module, a production line planning module and a planning management module;
[0084] The production line dynamic scheduling model building module is used to build a dynamic scheduling model for each production line according to the efficiency index information and dynamic index information of each production line in the existing production line of the production workshop;
[0085] The production line dynamic scheduling model building module includes a production status information acquisition unit, an indicator information acquisition unit, a linear model building unit and a dynamic scheduling model building unit;
[0086] The production status information acquisition unit acquires the production status information of each production line in the existing production line of the production workshop;
[0087] The index information acquisition unit acquires the efficiency index information and dynamic index information of the production line when the production line is in normal operation;
[0088] The linear model building unit builds a first linear model with the use time of the production line as the independent variable and the production energy consumption of the production line as the dependent variable, and builds a second linear model with the use time of the production line as the independent variable and the process delay time of the production line as the dependent variable;
[0089] The dynamic scheduling model building unit builds a dynamic scheduling model for each production line according to the built first-line model, the second-line model, and the acquired efficiency index information and dynamic index information;
[0090] The production line addition prediction module is used to analyze and predict the addition of production lines in the production workshop;
[0091] The production line new situation prediction module includes a fitness coefficient prediction unit, an associated production line determination unit, a dynamic scheduling coefficient prediction unit and a production line new situation prediction unit;
[0092] The fitness coefficient prediction unit predicts the fitness coefficient of each production line under different production plans according to the production plan of each production line and the constructed second linear model;
[0093] The associated production line determination unit determines the association between the two production lines according to the change of the production sequence between the two production lines;
[0094] The dynamic scheduling coefficient prediction unit predicts the dynamic scheduling coefficient of each production line according to the prediction result transmitted by the fitness coefficient prediction unit and the dynamic scheduling model transmitted by the dynamic scheduling model building unit;
[0095] The production line addition prediction unit uses the prediction results transmitted by the dynamic scheduling coefficient prediction unit and the number of times the production line is scheduled to analyze and predict the addition of production lines in the production workshop;
[0096] The production line planning module is used to plan the construction location and construction specifications of new production lines in the production workshop;
[0097] The production line planning module includes a new production line type determination unit, a new production line construction location planning unit and a new production line construction specification planning unit;
[0098] When the new production line type determination unit determines that a new production line is needed in the production workshop, it determines the type of the new production line in the production workshop according to the set conditions;
[0099] The new production line construction location planning unit plans the construction location of the new production line in the production workshop according to the type of the new production line in the production workshop;
[0100] The new production line construction specification planning unit plans the construction specifications of the new production line in the production workshop according to the execution of the production plan by the production line;
[0101] The planning management module is used to manage the production parameters of the newly added production lines in the production workshop;
[0102] The planning management module manages the production parameters of the newly added production lines in the production workshop according to the types of the newly added production lines in the production workshop.
[0103] Example 1: Assume that there are 3 production lines in the production workshop, B1 / H1=0.8, B2 / H2=1.2, B3 / H3=1.3, then when it is considered that the production workshop needs to add a new production line, max(B j / H j ) = B3 / H3 = 1.3, then the type of the new production line in the production workshop is the type of the third production line;
[0104] The construction location of the new production line in the production workshop is the area where the third production line belongs;
[0105] Assume that when the third production line is executing the production plan, the production completion time corresponding to the production plan is c3=17:00, and the time when the third production line starts to execute the production plan is g j =12:00, the time required for a single set of equipment in the third production line to complete a part at 12:00 is 20 minutes, and the corresponding production volume of the third production line when executing the production plan is Y j =50, there is 1 set of machinery and equipment in the third production line, and the number of times the third production line is scheduled is 1, then the number of machinery and equipment sets in the new production line in the production workshop is:
[0106] ;
[0107] The construction specifications of the new production line in the production workshop are: the number of sets of machines and equipment in the new production line in the production workshop is 3.
[0108] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0109] Finally, it should be noted that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A production workshop management method based on data analysis, characterized in that: The method comprises: S10: According to the production status information of each production line in the production workshop, the efficiency index information and dynamic index information of each production line in the production workshop are obtained, and based on the obtained information, a dynamic scheduling model of each production line is constructed; The S10 includes: S101: Acquire production status information of each existing production line in the production workshop, where the production status includes normal operation status, shutdown status, standby status and maintenance status; S102: When the production line is in normal operation, the efficiency index information and dynamic index information of the production line are obtained. The efficiency index includes production delay time and production energy consumption. Production delay time = β * (actual production time of the production line - scheduled production time of the production line). When the actual production time of the production line - the scheduled production time of the production line> 0, β = 1. When the actual production time of the production line - the scheduled production time of the production line ≤ 0, β = 0. Production energy consumption = working power of a single set of machine equipment in the production line × working time of a single set of machine equipment × proportion of loss of a single set of machine equipment in the process of converting electrical energy into useful energy × number of sets of machine equipment in the production line. Dynamic indicators include process delay time and machine failure conditions. S103: The first linear model is constructed with the use time t of the production line as the independent variable and the production energy consumption S of the production line as the dependent variable. The first linear model is: S t =k1*t+b1, the second linear model is constructed with the production line usage time t as the independent variable and the production line process delay time T as the dependent variable. The second linear model is: T t =k2*t+b2, where k1 and k2 represent the weight coefficients of the first linear model and the second linear model respectively, and b1 and b2 represent the weight coefficients of the first linear model and the second linear model respectively; Construct a dynamic scheduling model for each production line. The specific dynamic scheduling model is: ; Where j=1,2,…,n, represents the number of each production line in the existing production line of the production workshop, n represents the total number of production lines, i=1,2,…,m, represents the number of the machine equipment in the production line, m j G represents the total number of machines and equipment installed in the jth production line. vj represents the production delay time of the jth production line at time v, S j(v→t) represents the production energy consumption of the j-th production line when it is used for time t. The corresponding use time of the j-th production line at time v is t, T j(v→t) represents the process delay time corresponding to the j-th production line when it is used for time t. The corresponding use time of the j-th production line at time v is t, r ji =0 or r ji =1, when r ji = 0, it means that the i-th machine equipment in the j-th production line fails. ji =1, indicating that the i-th machine equipment in the j-th production line has not failed, e is a constant and e>1, W vj represents the scheduling index corresponding to the j-th production line at time v; S20: Obtain the production plan of each production line, predict the fitness coefficient of each production line under different production plans, and predict the dynamic scheduling coefficient of each production line based on the correlation between the production lines. Based on the prediction results, analyze whether the production workshop needs to add a new production line; The S20 includes: S201: Obtain the production plan of each production line, which includes production completion time, production volume and production material reserve. Combined with the constructed second linear model, predict the fitness coefficient of each production line under different production plans. The specific prediction formula is: ; Among them, c j It represents the production completion time corresponding to the production plan when the j-th production line executes the production plan, g j represents the time when the jth production line starts to execute the production plan, g j →t1 indicates that the jth production line is at g j The usage time corresponding to the moment is t1, c j →t2 means the jth production line is at c j The usage time corresponding to the moment is t2, Indicates that a single set of equipment in the jth production line is in g j The time required to complete a part at a time, U j It represents the production material reserve of the production workshop when the j-th production line starts to execute the production plan, a j It represents the amount of material consumed by a single set of equipment in the jth production line when processing a part. Min represents the minimum value symbol. Y j represents the production volume of the jth production line when executing the production plan, Q j It represents the fitness coefficient of the j-th production line when executing the production plan; S202: Acquire the association between the production lines. If the production sequence between two production lines cannot be changed, the two production lines are considered to be associated production lines. If the production sequence between the two production lines can be changed, the two production lines are considered to be unassociated production lines. S203: When the jth production line and other production lines in the production workshop are unrelated production lines, according to The dynamic scheduling coefficient of each production line is predicted, where: Indicates that the jth production line is at g j The scheduling index corresponding to the time, F j represents the dynamic scheduling coefficient of the j-th production line; When the jth production line and the pth production line are associated production lines, according to Predict the dynamic scheduling coefficients of the j-th production line and the p-th production line, where p=1,2,…,n and p≠j, Q p It represents the fitness coefficient of the pth production line when executing the production plan. Indicates that the pth production line is in g p The scheduling index corresponding to the time, F p represents the dynamic scheduling coefficient of the p-th production line; S204: The number of times the j-th production line is scheduled B j To obtain, j ≥0.6 times H j To obtain, if B j / H j ≥1, it is considered that the production workshop needs to add a new production line. If B j / H j <1, it is considered that the production workshop does not need to add a new production line; S30: Plan the construction location and construction specifications of the new production line in the production workshop; The S30 includes: When it is considered that a new production line is needed in the production workshop, max(B j / H j ) is determined, and based on the determination result, the type of the newly added production line in the production workshop is determined; When the type of the newly added production line in the production workshop is the type of the j-th production line, the construction location of the newly added production line in the production workshop is the area to which the j-th production line belongs. The construction specifications of the newly added production line in the production workshop are: the number of sets of machinery and equipment in the newly added production line in the production workshop is K, , Express Round up, where z=1,2,…,B, represents the number corresponding to the number of times the production line is scheduled, B represents the total number, and Y jz represents the production volume of the jth production line when the production plan is executed for the zth time, c jz It represents the production completion time of the j-th production line when the production plan is executed for the z-th time, g jz It indicates the time when the jth production line starts to execute the production plan for the zth time, E jz It represents the time required for a single set of equipment in the jth production line to complete a part when the production plan is executed for the zth time; S40: Based on the planning results, manage the production parameters of the newly added production lines in the production workshop; The S40 includes: when the type of the newly added production line in the production workshop is the type to which the j-th production line belongs, the production parameters of the newly added production line in the production workshop are the production parameters of the j-th production line.
2. A production workshop management system based on data analysis applied to the production workshop management method based on data analysis according to claim 1, characterized in that: The system includes a production line dynamic scheduling model building module, a production line new situation prediction module, a production line planning module and a planning management module; The production line dynamic scheduling model building module is used to build a dynamic scheduling model for each production line according to the efficiency index information and dynamic index information of each production line in the existing production line of the production workshop; The production line addition prediction module is used to analyze and predict the addition of production lines in the production workshop; The production line planning module is used to plan the construction location and construction specifications of the new production line in the production workshop; The planning management module is used to manage the production parameters of the newly added production line in the production workshop.
3. The production workshop management system based on data analysis according to claim 2 is characterized in that: The production line dynamic scheduling model building module includes a production status information acquisition unit, an indicator information acquisition unit, a linear model building unit and a dynamic scheduling model building unit; The production status information acquisition unit acquires the production status information of each production line in the existing production line of the production workshop; The index information acquisition unit acquires the efficiency index information and dynamic index information of the production line when the production line is in normal operation; The linear model building unit builds a first linear model with the use time of the production line as the independent variable and the production energy consumption of the production line as the dependent variable, and builds a second linear model with the use time of the production line as the independent variable and the process delay time of the production line as the dependent variable; The dynamic scheduling model construction unit constructs a dynamic scheduling model for each production line according to the constructed first line model, the second line model, and the acquired efficiency index information and dynamic index information.
4. The production workshop management system based on data analysis according to claim 3 is characterized in that: The production line new situation prediction module includes a fitness coefficient prediction unit, an associated production line determination unit, a dynamic scheduling coefficient prediction unit and a production line new situation prediction unit; The fitness coefficient prediction unit predicts the fitness coefficient of each production line under different production plans according to the production plan of each production line and the constructed second linear model; The associated production line determination unit determines the association between the two production lines according to the change of the production sequence between the two production lines; The dynamic scheduling coefficient prediction unit predicts the dynamic scheduling coefficient of each production line according to the prediction result transmitted by the fitness coefficient prediction unit and the dynamic scheduling model transmitted by the dynamic scheduling model construction unit; The production line addition prediction unit analyzes and predicts the addition of production lines in the production workshop based on the prediction results transmitted by the dynamic scheduling coefficient prediction unit and the number of times the production line is scheduled.
5. The production workshop management system based on data analysis according to claim 4 is characterized in that: The production line planning module includes a new production line type determination unit, a new production line construction location planning unit and a new production line construction specification planning unit; When the new production line type determination unit determines that a new production line is needed in the production workshop, the new production line type determination unit determines the type of the new production line in the production workshop according to the set conditions; The new production line construction location planning unit plans the construction location of the new production line in the production workshop according to the type of the new production line in the production workshop; The newly added production line construction specification planning unit plans the construction specifications of the newly added production line in the production workshop according to the execution status of the production plan when the production line executes the production plan.
6. The production workshop management system based on data analysis according to claim 5, characterized in that: The planning management module manages the production parameters of the newly added production lines in the production workshop according to the types of the newly added production lines in the production workshop.