A construction personnel movement line management method and system based on BIM model
By using BIM models to build a construction personnel line management system in large-scale engineering construction, the problem of incomplete management of construction personnel line management is solved, and timely and comprehensive management of construction personnel line management is achieved to ensure construction safety.
Patent Information
- Application Number
- CN202411110479.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-14
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2044-08-14
AI Technical Summary
The existing construction personnel flow management methods are not comprehensive enough in large-scale construction construction, especially among high-rise edges or outer construction workers, which can easily lead to life safety risks for construction personnel, and managers need to patrol continuously to prevent deviations.
The construction personnel dynamic line management method based on BIM model is adopted, and by analyzing and planning the construction drawings, building a BIM model, obtaining construction personnel and material data, distributing and simulating the dynamic trajectory, monitoring the dynamic trajectory in real time, calculating the deviation coefficient and influence value, Plan the return route and conduct early warnings to achieve reasonable allocation and comprehensive management of traffic lines.
The timely and comprehensive management of construction traffic lines has been improved, the safety of construction workers has been ensured, and deviations have been discovered and corrected in a timely manner through dynamic planning and difference analysis of the BIM model, which has improved the rationality and safety of construction traffic lines.
Smart Images

Figure CN118627868B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of construction management, and in particular to a construction personnel movement line management method and system based on a BIM model. Background Art
[0002] At present, with the continuous expansion of the scale of engineering construction, the management of large-scale engineering construction through information technology has become the mainstream of the current combination of engineering construction and information technology. The scale of engineering construction is proportional to the number of construction personnel. The larger the scale, the larger the construction team. Therefore, it is necessary to manage personnel of large construction teams to improve the orderliness of construction.
[0003] The existing method for managing the movement of construction personnel usually involves manual path planning by on-site management personnel based on the actual construction situation, dividing several construction paths on the construction site, and assigning a corresponding number of construction personnel to perform construction operations on the construction paths. During the construction process, the construction personnel are managed through manual patrols by management personnel. However, the existing method for managing construction personnel requires management personnel to patrol and manage the construction personnel continuously. In places where there is no patrol, construction personnel may deviate from the assigned construction route, and the management is not comprehensive enough, especially for construction personnel on the edge of high-rise buildings or on the outer layers. If the construction path deviates, it is easy to put the construction personnel's lives in danger. Therefore, the method for managing the movement of construction personnel needs to be further optimized. Summary of the invention
[0004] In order to improve the timeliness and comprehensiveness of the management of construction personnel's movement routes, the present application provides a construction personnel's movement route management method and system based on the BIM model.
[0005] In the first aspect, the above-mentioned invention objective of the present application is achieved through the following technical solutions:
[0006] A construction personnel movement line management method based on a BIM model, comprising:
[0007] Analyze and plan the construction drawings, obtain the construction parameters and corresponding construction steps of the construction project, and build the BIM model of the construction project based on the construction parameters and construction steps;
[0008] Obtain the current construction personnel data and construction material data, and input them into the BIM model for construction simulation. Perform construction personnel and construction material allocation for each construction step to obtain construction route allocation data.
[0009] Acquire the dynamic construction trajectory of each construction worker during the construction process, compare and analyze the difference between the dynamic construction trajectory and the construction line allocation data, and obtain construction line difference data;
[0010] The compliance deviation of the construction movement lines of the construction personnel is analyzed according to the construction movement line difference data, and the corresponding construction movement line regression route is planned according to the compliance deviation, and the relevant construction personnel are warned to obtain the personnel movement line management data.
[0011] By adopting the above technical solution, the construction project is dynamically planned and managed through the BIM model, and reasonable construction line allocation is carried out in combination with the construction personnel data and construction material data, which is helpful to improve the rationality of the construction line allocation, and further analyze the compliance deviation of the construction line in combination with the difference between the dynamic construction trajectory in the construction process and the construction line allocation data, improve the rationality of the construction line deviation analysis, and regress the construction line of the construction personnel in combination with the current deviation position, so as to remind the construction personnel to return to the preset construction path in time according to the regression route, so as to timely manage the construction line of each construction personnel, and comprehensively manage the construction personnel line through the BIM model, so as to improve the comprehensiveness of the construction line management.
[0012] In a preferred example, the present application can be further configured as follows: analyzing the compliance deviation of the construction line of construction personnel according to the construction line difference data, planning the corresponding construction line regression route according to the compliance deviation and issuing early warnings to relevant construction personnel, and obtaining personnel line management data, specifically including:
[0013] Calculating the construction deviation coefficient of the corresponding construction line according to the construction line difference data, and analyzing the compliance deviation of the construction line of the construction personnel according to the construction deviation coefficient to obtain the compliance deviation analysis result;
[0014] According to the compliance deviation analysis results, combined with the current deviation position and the compliance construction line position, the construction line with deviation is subjected to construction line regression processing to obtain the regression path data of the deviation personnel;
[0015] According to the regression path data, path deviation warning processing is performed on relevant construction personnel, and the movement line regression parameters of whether the deviated personnel return to the compliant construction movement line according to the regression path are sent to the management personnel to obtain personnel movement line management data.
[0016] In a preferred example, the present application may be further configured as follows: the calculation of the construction deviation coefficient of the corresponding construction line according to the construction line difference data specifically includes:
[0017] The construction deviation coefficient of the single-person construction line is calculated by formula (1), which is as follows:
[0018] (1)
[0019] in, Indicates the construction deviation coefficient of a single-person construction line. Indicates the time it takes for construction workers to move from the starting point to the current deviation position. It indicates the time it takes for construction personnel to move to the destination on the preset compliant construction path according to the construction route allocation data. Indicates the distance between the construction worker's current deviation position and the danger edge. Indicates the distance between the construction worker's current deviation position and the compliant construction path. Indicates the movement distance of the construction workers, Indicates the construction materials carried by the construction workers. Indicates the importance of current construction materials in the construction steps. Indicates the total construction materials required for the current construction step. Indicates the deviation angle between the construction worker's current deviation position and the compliant construction path.
[0020] In a preferred example, the present application may be further configured as follows: the calculation of the construction deviation coefficient of the corresponding construction line according to the construction line difference data also includes:
[0021] Formula (2) is used to express the impact of construction line deviation on the subsequent construction personnel's construction line. Formula (2) is as follows:
[0022] (2)
[0023] in, Indicates the impact of construction line deviation on subsequent construction personnel. Indicates the number of construction workers affected by the construction route, that is, the sum of the current deviation workers and the affected subsequent construction workers. Indicates The time it takes for a construction worker to move from the starting point to the current deviation position, Indicates The time it takes for a construction worker to move to the destination on the preset compliant construction path according to the construction line allocation data. Indicates The distance between the current deviation position of each construction worker and the danger edge, Indicates The distance between the current deviation position of each construction worker and the compliant construction path, Indicates The movement distance of each construction worker, Indicates The construction materials carried by the construction workers, Indicates The importance of the current construction materials carried in the construction steps, Indicates The total construction materials required by the construction workers in the current construction step. Indicates The deviation angle between the current deviation position of a construction worker and the compliant construction path.
[0024] By adopting the above technical solution and combining the construction movement line difference data to calculate the construction deviation coefficient, it is helpful to reasonably analyze the construction movement line deviation of each construction worker and improve the rationality of the construction movement line deviation analysis. In combination with the current construction deviation position and the compliant construction movement line position, the construction movement line with deviation is regressed, which helps to build a reasonable regression path, so that the deviation personnel can perform timely construction path regression. The path deviation warning is issued to the relevant construction personnel through the regression path data, and the deviation personnel are urged to return to the compliant construction movement line according to the regression path. The deviation personnel's movement line regression results are sent to the management personnel, so that the management personnel can comprehensively monitor the deviation of all deviation personnel from the construction line, and further improve the comprehensiveness of the construction line management.
[0025] In a preferred example, the present application can be further configured as follows: the dynamic construction trajectory of each construction worker during the construction process is obtained, and the dynamic construction trajectory is compared and analyzed with the construction line allocation data to obtain the construction line difference data, specifically including:
[0026] Obtain the dynamic construction trajectory of each construction worker in a unit time during the construction process, and analyze the construction deviation direction of the construction worker based on the deviation of the dynamic construction trajectory in adjacent unit time;
[0027] When the construction deviation direction reaches a preset threshold, the dynamic construction trajectory is compared with the construction line allocation data to obtain construction trajectory deviation data;
[0028] The construction trajectory deviation data is associated with the corresponding construction deviation direction to obtain the construction movement line difference data of the construction personnel.
[0029] By adopting the above technical scheme, by obtaining the dynamic construction trajectory of each construction worker in a unit time during the construction process, and combining the dynamic construction trajectory deviation in adjacent unit time, the construction deviation direction analysis is carried out, which is helpful to further subdivide the construction deviation direction and improve the analysis accuracy of the construction deviation direction. In addition, the trajectory deviation comparison result between the dynamic construction trajectory and the construction line preset in the construction line allocation data is combined to obtain the construction trajectory deviation data, which provides a powerful analysis reference for the construction trajectory deviation analysis. In combination with the construction trajectory deviation data and the construction deviation direction, the construction line difference data of the construction workers is obtained, which is helpful to improve the analysis accuracy of the construction line difference data.
[0030] In the second aspect, the above invention objective of the present application is achieved through the following technical solutions:
[0031] A construction personnel movement line management system based on a BIM model, comprising:
[0032] The model building module is used to analyze and plan the construction drawings, obtain the construction parameters and corresponding construction steps of the construction project, and build the BIM model of the construction project according to the construction parameters and construction steps;
[0033] The data allocation module is used to obtain the current construction personnel data and construction material data, and input them into the BIM model for construction simulation. The construction personnel and construction material allocation are processed for each construction step to obtain the construction line allocation data;
[0034] A difference analysis module is used to obtain the dynamic construction trajectory of each construction worker during the construction process, and compare and analyze the difference between the dynamic construction trajectory and the construction line allocation data to obtain construction line difference data;
[0035] The movement line management module is used to analyze the compliance deviation of the construction personnel's construction movement line according to the construction movement line difference data, and plan the corresponding construction movement line regression route according to the compliance deviation and issue early warning to the relevant construction personnel to obtain personnel movement line management data.
[0036] By adopting the above technical solution, the construction project is dynamically planned and managed through the BIM model, and reasonable construction route allocation is carried out in combination with the construction personnel data and construction material data, which helps to improve the rationality of the construction route allocation. In combination with the difference between the dynamic construction trajectory in the construction process and the construction route allocation data, the compliance deviation of the construction route is further analyzed to improve the rationality of the construction route deviation analysis. In combination with the current deviation position, the construction route of the construction personnel's construction route is regressed to remind the construction personnel to return to the preset construction path in time according to the regression route, so as to timely manage the construction route of each construction personnel, and comprehensively manage the construction personnel's route through the BIM model to improve the comprehensiveness of the construction route management.
[0037] On the third aspect, the above-mentioned purpose of the present application is achieved through the following technical solutions:
[0038] A computer device includes a memory, a processor, and a computer program stored in the memory and executable on the processor. When the processor executes the computer program, the steps of the above-mentioned method for managing the movement routes of construction personnel based on the BIM model are implemented.
[0039] Fourthly, the above-mentioned purpose of the present application is achieved through the following technical solutions:
[0040] A computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the steps of the construction personnel movement line management method based on the BIM model are implemented.
[0041] In summary, the present application includes at least one of the following beneficial technical effects:
[0042] 1. Dynamically plan and manage construction projects through the BIM model, and reasonably allocate construction routes in combination with construction personnel data and construction material data, which helps to improve the rationality of construction route allocation. In combination with the difference between the dynamic construction trajectory during the construction process and the construction route allocation data, further analyze the compliance deviation of the construction route to improve the rationality of the construction route deviation analysis, and regress the construction route of the construction personnel's construction route in combination with the current deviation position, so as to remind the construction personnel to return to the preset construction path in time according to the regression route, so as to timely manage the construction route of each construction personnel, and comprehensively manage the construction personnel's route through the BIM model to improve the comprehensiveness of the construction route management;
[0043] 2. Calculating the construction deviation coefficient in combination with the construction line difference data is helpful for making a reasonable analysis of the construction line deviation of each construction worker, improving the rationality of the construction line deviation analysis, and combining the current construction deviation position and the compliant construction line position to perform construction line regression processing on the construction line with deviations, which is helpful for building a reasonable regression path, facilitating the deviation personnel to perform timely construction path regression, and issuing path deviation warnings to relevant construction personnel through regression path data, urging the deviation personnel to return to the compliant construction line according to the regression path, and sending the deviation personnel's line regression results to the management side, so that the management personnel can comprehensively monitor the deviation of all deviation personnel from the construction line, and further improve the comprehensiveness of construction line management;
[0044] 3. By obtaining the dynamic construction trajectory of each construction worker in a unit time during the construction process, combined with the dynamic construction trajectory deviation in adjacent unit time, the construction deviation direction analysis is carried out, which helps to further subdivide the construction deviation direction and improve the analysis accuracy of the construction deviation direction. The construction trajectory deviation data is obtained by combining the trajectory deviation comparison results between the dynamic construction trajectory and the construction line preset in the construction line allocation data, which provides a powerful analysis reference for the construction trajectory deviation analysis. The construction line difference data of the construction workers is obtained by combining the construction trajectory deviation data and the construction deviation direction, which helps to improve the analysis accuracy of the construction line difference data. BRIEF DESCRIPTION OF THE DRAWINGS
[0045] Figure 1 This is a flow chart of an implementation method of a construction personnel movement line management method based on a BIM model in this embodiment.
[0046] Figure 2 This is a flowchart for implementing step S30 of a method for managing construction personnel movement routes based on a BIM model in this embodiment.
[0047] Figure 3 This is a flowchart for implementing step S40 of a method for managing construction personnel movement routes based on a BIM model in this embodiment.
[0048] Figure 4 This is a structural block diagram of a construction personnel movement line management system based on a BIM model in this embodiment.
[0049] Figure 5 It is a schematic diagram of the internal structure of a computer device used to implement a method for managing the movement routes of construction personnel. DETAILED DESCRIPTION
[0050] The present application is further described in detail below in conjunction with the accompanying drawings.
[0051] In one embodiment, if Figure 1 As shown, the present application discloses a construction personnel movement line management method based on a BIM model, which specifically includes the following steps:
[0052] S10: Analyze and plan the construction drawings, obtain construction parameters and corresponding construction steps of the construction project, and build a BIM model of the construction project according to the construction parameters and construction steps.
[0053] Specifically, the construction drawings are input into the Revit software to analyze and plan the construction drawings, obtain the construction parameters of the construction project including axis grid, wall, dimensioning, text annotation, etc., as well as the construction steps of the construction project, and combine with the CAD software to model the construction project to obtain the BIM model of the construction project.
[0054] S20: Obtain current construction personnel data and construction material data, and input them into the BIM model for construction simulation, allocate construction personnel and construction materials for each construction step, and obtain construction route allocation data.
[0055] Specifically, the construction personnel data and construction material data, such as the current number of construction teams and the skills that each construction personnel is good at, are input into the BIM model. The BIM model is used to simulate the construction of the current human and material resources. According to the simulation results, construction personnel and construction materials are allocated to each construction step, so that each construction step is equipped with corresponding construction manpower and materials, and orderly personnel management is carried out according to the construction steps, thereby obtaining the construction route allocation data.
[0056] S30: Obtain the dynamic construction trajectory of each construction worker during the construction process, compare and analyze the dynamic construction trajectory with the construction line allocation data, and obtain construction line difference data.
[0057] Specifically, Figure 2 As shown, step S30 includes:
[0058] S301: Obtain the dynamic construction trajectory of each construction worker in a unit time during the construction process, and analyze the construction deviation direction of the construction worker according to the dynamic construction trajectory deviation in adjacent unit times.
[0059] Specifically, the construction path of each construction worker is monitored in real time through the BIM model, so as to obtain the dynamic construction trajectory of each construction worker in unit time during the construction process, calculate the dynamic construction trajectory deviation in adjacent unit time, and analyze the construction deviation direction of the construction workers.
[0060] S302: When the construction deviation direction reaches a preset threshold, the dynamic construction trajectory is compared with the construction line allocation data to obtain construction trajectory deviation data.
[0061] Specifically, when the construction deviation direction reaches a preset threshold, it indicates that the current construction personnel may deviate from the construction path. The trajectory deviation is compared with the dynamic construction trajectory and the line parameters in the construction line allocation data to obtain the construction trajectory deviation data of the current construction personnel.
[0062] S303: Associating the construction trajectory deviation data with the corresponding construction deviation direction to obtain construction movement line difference data of the construction personnel.
[0063] Specifically, the construction unit time of the construction personnel is used as the association point, and the construction trajectory deviation data is data-associated with the corresponding construction deviation direction, so as to obtain the construction movement line difference data of the construction personnel.
[0064] S40: Analyze the compliance deviation of the construction movement lines of the construction personnel according to the construction movement line difference data, plan the corresponding construction movement line regression route according to the compliance deviation, and issue early warnings to the relevant construction personnel to obtain personnel movement line management data.
[0065] Specifically, Figure 3 As shown, step S40 includes:
[0066] S401: Calculate the construction deviation coefficient of the corresponding construction line according to the construction line difference data, analyze the compliance deviation of the construction line of the construction personnel according to the construction deviation coefficient, and obtain the compliance deviation analysis result.
[0067] Specifically, the construction deviation coefficient of a single-person construction line is calculated by formula (1), which is as follows:
[0068] (1)
[0069] in, Indicates the construction deviation coefficient of a single-person construction line. Indicates the time it takes for construction workers to move from the starting point to the current deviation position. It indicates the time it takes for construction personnel to move to the destination on the preset compliant construction path according to the construction route allocation data. Indicates the distance between the construction worker's current deviation position and the danger edge. Indicates the distance between the construction worker's current deviation position and the compliant construction path. Indicates the movement distance of the construction workers, Indicates the construction materials carried by the construction workers. Indicates the importance of current construction materials in the construction steps. Indicates the total construction materials required for the current construction step. Indicates the deviation angle between the construction worker's current deviation position and the compliant construction path.
[0070] In this embodiment, it also includes:
[0071] Formula (2) is used to express the impact of construction line deviation on the subsequent construction personnel's construction line. Formula (2) is as follows:
[0072] (2)
[0073] in, Indicates the impact of construction line deviation on subsequent construction personnel. Indicates the number of construction workers affected by the construction route, that is, the sum of the current deviation workers and the affected subsequent construction workers. Indicates The time it takes for a construction worker to move from the starting point to the current deviation position, Indicates The time it takes for a construction worker to move to the destination on the preset compliant construction path according to the construction line allocation data. Indicates The distance between the current deviation position of each construction worker and the danger edge, Indicates The distance between the current deviation position of each construction worker and the compliant construction path, Indicates The movement distance of each construction worker, Indicates The construction materials carried by the construction workers, Indicates The importance of the current construction materials carried in the construction steps, Indicates The total construction materials required by the construction workers in the current construction step. Indicates The deviation angle between the current deviation position of a construction worker and the compliant construction path.
[0074] When the construction deviation coefficient is greater than the preset deviation threshold, it means that the current construction personnel's construction route is not compliant and there is a construction route deviation. When the construction deviation coefficient is less than or equal to the preset deviation threshold, it means that the current construction personnel's construction route is within the compliance range, thereby obtaining the construction deviation analysis result, wherein the preset deviation threshold is set according to the dangerousness of the current construction step.
[0075] S402: Based on the compliance deviation analysis results, combined with the current deviation position and the compliance construction line position, the construction line with deviation is subjected to construction line regression processing to obtain the regression path data of the deviation personnel.
[0076] Specifically, based on the compliance deviation analysis results, further analysis is conducted on the construction personnel whose movement line deviations are shown in the compliance deviation analysis results. Construction movement line regression processing is performed on the construction movement line with deviations based on the current deviation position of the deviation personnel and the compliant construction movement line position. Regression obstacle avoidance processing is performed based on the placement of components on the regression path and regression obstacles such as other construction personnel, thereby obtaining the regression path data of the deviation personnel.
[0077] S403: Perform path deviation warning processing on relevant construction personnel according to the regression path data, and send the path regression parameters of whether the deviated personnel return to the compliant construction path according to the regression path to the management personnel to obtain personnel path management data.
[0078] Specifically, the regression path data is sent to the relevant construction personnel, and the construction personnel are warned of path deviation, and are reminded to return to the compliant construction route according to the regression path. The route regression parameters of whether the deviated personnel have returned to the compliant construction route according to the regression path are sent to the management side, which is convenient for the management side to manage each construction personnel, thereby obtaining personnel route management data.
[0079] It should be understood that the size of the serial numbers of the steps in the above embodiments does not mean the order of execution. The execution order of each process should be determined by its function and internal logic, and should not constitute any limitation on the implementation process of the embodiments of the present application.
[0080] In one embodiment, a construction personnel movement line management system based on a BIM model is provided, and the construction personnel movement line management system based on a BIM model corresponds one-to-one to the construction personnel movement line management method based on a BIM model in the above embodiment. Figure 4 As shown in the figure, the construction personnel movement line management system based on the BIM model includes a model building module, a data allocation module, a difference analysis module and a movement line management module. The detailed description of each functional module is as follows:
[0081] The model building module is used to parse and plan the construction drawings, obtain the construction parameters and corresponding construction steps of the construction project, and build the BIM model of the construction project based on the construction parameters and construction steps.
[0082] The data allocation module is used to obtain the current construction personnel data and construction material data, and input them into the BIM model for construction simulation. It allocates construction personnel and construction materials for each construction step to obtain construction route allocation data.
[0083] The difference analysis module is used to obtain the dynamic construction trajectory of each construction worker during the construction process, compare and analyze the dynamic construction trajectory with the construction line allocation data, and obtain the construction line difference data.
[0084] The movement line management module is used to analyze the compliance deviation of the construction personnel's construction movement lines based on the construction movement line difference data, and plan the corresponding construction movement line regression route based on the compliance deviation and issue early warnings to relevant construction personnel to obtain personnel movement line management data.
[0085] Preferably, the traffic line management module specifically includes:
[0086] The deviation analysis submodule is used to calculate the construction deviation coefficient of the corresponding construction line according to the construction line difference data, analyze the compliance deviation of the construction line of the construction personnel according to the construction deviation coefficient, and obtain the compliance deviation analysis result.
[0087] The path regression submodule is used to perform construction line regression processing on the construction line with deviations based on the compliance deviation analysis results, combined with the current deviation position and the compliant construction line position, to obtain the regression path data of the deviation personnel.
[0088] The movement line management submodule is used to carry out path deviation warning processing for relevant construction personnel based on the regression path data, and send the movement line regression parameters of whether the deviated personnel return to the compliant construction movement line according to the regression path to the management personnel to obtain the personnel movement line management data.
[0089] Preferably, the deviation analysis submodule specifically includes:
[0090] The construction deviation coefficient of the single-person construction line is calculated by formula (1), which is as follows:
[0091] (1)
[0092] in, Indicates the construction deviation coefficient of a single-person construction line. Indicates the time it takes for construction workers to move from the starting point to the current deviation position. It indicates the time it takes for construction personnel to move to the destination on the preset compliant construction path according to the construction route allocation data. Indicates the distance between the construction worker's current deviation position and the danger edge. Indicates the distance between the construction worker's current deviation position and the compliant construction path. Indicates the movement distance of the construction workers, Indicates the construction materials carried by the construction workers. Indicates the importance of current construction materials in the construction steps. Indicates the total construction materials required for the current construction step. Indicates the deviation angle between the construction worker's current deviation position and the compliant construction path.
[0093] Preferably, the deviation analysis submodule further includes:
[0094] Formula (2) is used to express the impact of construction line deviation on the subsequent construction personnel's construction line. Formula (2) is as follows:
[0095] (2)
[0096] in, Indicates the impact of construction line deviation on subsequent construction personnel. Indicates the number of construction workers affected by the construction route, that is, the sum of the current deviation workers and the affected subsequent construction workers. Indicates The time it takes for a construction worker to move from the starting point to the current deviation position, Indicates The time it takes for a construction worker to move to the destination on the preset compliant construction path according to the construction line allocation data. Indicates The distance between the current deviation position of each construction worker and the danger edge, Indicates The distance between the current deviation position of each construction worker and the compliant construction path, Indicates The movement distance of each construction worker, Indicates The construction materials carried by the construction workers, Indicates The importance of the current construction materials carried in the construction steps, Indicates The total construction materials required by the construction workers in the current construction step. Indicates The deviation angle between the current deviation position of a construction worker and the compliant construction path.
[0097] Preferably, the difference analysis module specifically includes:
[0098] The deviation direction analysis submodule is used to obtain the dynamic construction trajectory of each construction worker in a unit time during the construction process, and analyze the construction deviation direction of the construction worker according to the deviation of the dynamic construction trajectory in adjacent unit times.
[0099] The trajectory deviation analysis submodule is used to compare the dynamic construction trajectory with the construction line allocation data to obtain the construction trajectory deviation data when the construction deviation direction reaches a preset threshold.
[0100] The data association submodule is used to associate the construction trajectory deviation data with the corresponding construction deviation direction to obtain the construction movement line difference data of the construction personnel.
[0101] For the specific limitations of the construction personnel movement line management system based on the BIM model, please refer to the limitations of the construction personnel movement line management method based on the BIM model above, which will not be repeated here. Each module in the above-mentioned construction personnel movement line management system based on the BIM model can be implemented in whole or in part through software, hardware and a combination thereof. The above-mentioned modules can be embedded in or independent of the processor in the computer device in the form of hardware, or can be stored in the memory of the computer device in the form of software, so that the processor can call and execute the operations corresponding to the above modules.
[0102] In one embodiment, a computer device is provided. The computer device may be a server, and its internal structure diagram may be as follows: Figure 5 As shown. The computer device includes a processor, a memory, a network interface and a database connected through a system bus. Among them, the processor of the computer device is used to provide computing and control capabilities. The memory of the computer device includes a non-volatile storage medium and an internal memory. The non-volatile storage medium stores an operating system, a computer program and a database. The internal memory provides an environment for the operation of the operating system and the computer program in the non-volatile storage medium. The database of the computer device is used to store data on the BIM model for the management of the movement lines of construction personnel. The network interface of the computer device is used to communicate with an external terminal through a network connection. When the computer program is executed by the processor, a method for managing the movement lines of construction personnel based on the BIM model is implemented.
[0103] In one embodiment, a computer-readable storage medium is provided, on which a computer program is stored. When the computer program is executed by a processor, the steps of a construction personnel movement line management method based on a BIM model are implemented.
[0104] Those of ordinary skill in the art can understand that all or part of the processes in the above-mentioned embodiment methods can be completed by instructing the relevant hardware through a computer program, and the computer program can be stored in a non-volatile computer-readable storage medium. When the computer program is executed, it can include the processes of the embodiments of the above-mentioned methods. Among them, any reference to memory, storage, database or other media used in the embodiments provided in this application may include non-volatile and / or volatile memory. Non-volatile memory may include read-only memory (ROM), programmable ROM (PROM), electrically programmable ROM (EPROM), electrically erasable programmable ROM (EEPROM) or flash memory. Volatile memory may include random access memory (RAM) or external cache memory. By way of illustration and not limitation, RAM is available in many forms, such as static RAM (SRAM), dynamic RAM (DRAM), synchronous DRAM (SDRAM), double data rate SDRAM (DDRSDRAM), enhanced SDRAM (ESDRAM), synchronous link (Synchlink) DRAM (SLDRAM), memory bus (Rambus) direct RAM (RDRAM), direct memory bus dynamic RAM (DRDRAM), and memory bus dynamic RAM (RDRAM), etc.
[0105] Those skilled in the art will clearly understand that for the sake of convenience and brevity of description, only the division of the above-mentioned functional units and modules is used as an example. In actual applications, the above-mentioned functions can be distributed and completed by different functional units and modules as needed, that is, the internal structure of the system can be divided into different functional units or modules to complete all or part of the functions described above.
[0106] The embodiments described above are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application has been described in detail with reference to the aforementioned embodiments, a person skilled in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some of the technical features may be replaced by equivalents. Such modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present application, and should all be included in the protection scope of the present application.
Claims
1. A construction personnel movement line management method based on BIM model, characterized in that: include: Analyze and plan the construction drawings, obtain the construction parameters and corresponding construction steps of the construction project, and build the BIM model of the construction project based on the construction parameters and construction steps; Obtain the current construction personnel data and construction material data, and input them into the BIM model for construction simulation. Perform construction personnel and construction material allocation for each construction step to obtain construction route allocation data. Acquire the dynamic construction trajectory of each construction worker during the construction process, compare and analyze the difference between the dynamic construction trajectory and the construction line allocation data, and obtain construction line difference data; Analyze the compliance deviation of the construction movement lines of the construction personnel according to the construction movement line difference data, plan the corresponding construction movement line regression route according to the compliance deviation, and issue early warnings to the relevant construction personnel to obtain personnel movement line management data; The analysis of the compliance deviation of the construction personnel's construction movement line according to the construction movement line difference data, planning the corresponding construction movement line regression route according to the compliance deviation and issuing early warnings to relevant construction personnel to obtain personnel movement line management data specifically includes: Calculating the construction deviation coefficient of the corresponding construction line according to the construction line difference data, and analyzing the compliance deviation of the construction line of the construction personnel according to the construction deviation coefficient to obtain the compliance deviation analysis result; According to the compliance deviation analysis results, combined with the current deviation position and the compliance construction line position, the construction line with deviation is subjected to construction line regression processing to obtain the regression path data of the deviation personnel; Perform path deviation warning processing on relevant construction personnel according to the regression path data, and send the path regression parameters of whether the deviated personnel return to the compliant construction path according to the regression path to the management personnel to obtain personnel path management data; The step of calculating the construction deviation coefficient of the corresponding construction line according to the construction line difference data specifically includes: The construction deviation coefficient of the single-person construction line is calculated by formula (1), which is as follows: (1) in, Indicates the construction deviation coefficient of a single-person construction line. Indicates the time it takes for construction workers to move from the starting point to the current deviation position. It indicates the time it takes for construction personnel to move to the destination on the preset compliant construction path according to the construction route allocation data. Indicates the distance between the construction worker's current deviation position and the danger edge. Indicates the distance between the construction worker's current deviation position and the compliant construction path. Indicates the movement distance of the construction workers, Indicates the construction materials carried by the construction workers. Indicates the importance of current construction materials in the construction steps. Indicates the total construction materials required for the current construction step. Indicates the deviation angle between the construction worker's current deviation position and the compliant construction path; Wherein, the calculating of the construction deviation coefficient of the corresponding construction line according to the construction line difference data further includes: Formula (2) is used to express the impact of construction line deviation on the subsequent construction personnel's construction line. Formula (2) is as follows: (2) in, Indicates the impact of construction line deviation on subsequent construction personnel. Indicates the number of construction workers affected by the construction route, that is, the sum of the current deviation workers and the affected subsequent construction workers. Indicates The time it takes for a construction worker to move from the starting point to the current deviation position, Indicates The time it takes for a construction worker to move to the destination on the preset compliant construction path according to the construction line allocation data. Indicates The distance between the current deviation position of each construction worker and the danger edge, Indicates The distance between the current deviation position of each construction worker and the compliant construction path, Indicates The movement distance of each construction worker, Indicates The construction materials carried by the construction workers, Indicates The importance of the current construction materials carried in the construction steps, Indicates The total construction materials required by the construction workers in the current construction step. Indicates The deviation angle between the current deviation position of a construction worker and the compliant construction path.
2. The construction personnel movement line management method based on the BIM model according to claim 1 is characterized in that: The obtaining of the dynamic construction trajectory of each construction worker during the construction process, and performing a difference comparison analysis between the dynamic construction trajectory and the construction line allocation data to obtain the construction line difference data specifically includes: Obtain the dynamic construction trajectory of each construction worker in a unit time during the construction process, and analyze the construction deviation direction of the construction worker based on the deviation of the dynamic construction trajectory in adjacent unit time; When the construction deviation direction reaches a preset threshold, the dynamic construction trajectory is compared with the construction line allocation data to obtain construction trajectory deviation data; The construction trajectory deviation data is associated with the corresponding construction deviation direction to obtain the construction movement line difference data of the construction personnel.
3. A construction personnel movement line management system based on BIM model, characterized in that: include: The model building module is used to analyze and plan the construction drawings, obtain the construction parameters and corresponding construction steps of the construction project, and build the BIM model of the construction project according to the construction parameters and construction steps; The data allocation module is used to obtain the current construction personnel data and construction material data, and input them into the BIM model for construction simulation. The construction personnel and construction material allocation are processed for each construction step to obtain the construction line allocation data; A difference analysis module is used to obtain the dynamic construction trajectory of each construction worker during the construction process, and compare and analyze the difference between the dynamic construction trajectory and the construction line allocation data to obtain construction line difference data; A movement line management module is used to analyze the compliance deviation of the construction line of construction personnel according to the construction line difference data, and plan the corresponding construction line regression route according to the compliance deviation and issue early warning to relevant construction personnel to obtain personnel movement line management data; The traffic line management module specifically includes: A deviation analysis submodule, used to calculate the construction deviation coefficient of the corresponding construction line according to the construction line difference data, and analyze the compliance deviation of the construction line of the construction personnel according to the construction deviation coefficient to obtain the compliance deviation analysis result; A path regression submodule is used to perform construction line regression processing on the construction line with deviations according to the compliance deviation analysis results, combined with the current deviation position and the compliance construction line position, to obtain the regression path data of the deviation personnel; The movement line management submodule is used to perform path deviation warning processing on relevant construction personnel according to the regression path data, and send the movement line regression parameters of whether the deviated personnel return to the compliant construction movement line according to the regression path to the management personnel to obtain personnel movement line management data; The deviation analysis submodule specifically includes: The construction deviation coefficient of the single-person construction line is calculated by formula (1), which is as follows: (1) in, Indicates the construction deviation coefficient of a single-person construction line. Indicates the time it takes for construction workers to move from the starting point to the current deviation position. It indicates the time it takes for construction personnel to move to the destination on the preset compliant construction path according to the construction route allocation data. Indicates the distance between the construction worker's current deviation position and the danger edge. Indicates the distance between the construction worker's current deviation position and the compliant construction path. Indicates the movement distance of the construction workers, Indicates the construction materials carried by the construction workers. Indicates the importance of current construction materials in the construction steps. Indicates the total construction materials required for the current construction step. Indicates the deviation angle between the construction worker's current deviation position and the compliant construction path; Wherein, the deviation analysis submodule also includes: Formula (2) is used to express the impact of construction line deviation on the subsequent construction personnel's construction line. Formula (2) is as follows: (2) in, Indicates the impact of construction line deviation on subsequent construction personnel. Indicates the number of construction workers affected by the construction route, that is, the sum of the current deviation workers and the affected subsequent construction workers. Indicates The time it takes for a construction worker to move from the starting point to the current deviation position, Indicates The time it takes for a construction worker to move to the destination on the preset compliant construction path according to the construction line allocation data. Indicates The distance between the current deviation position of each construction worker and the danger edge, Indicates The distance between the current deviation position of each construction worker and the compliant construction path, Indicates The movement distance of each construction worker, Indicates The construction materials carried by the construction workers, Indicates The importance of the current construction materials carried in the construction steps, Indicates The total construction materials required by the construction workers in the current construction step. Indicates The deviation angle between the current deviation position of a construction worker and the compliant construction path.
4. A computer device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that: When the processor executes the computer program, the steps of the construction personnel movement line management method based on the BIM model as described in any one of claims 1 to 2 are implemented.
5. A computer-readable storage medium storing a computer program, characterized in that: When the computer program is executed by a processor, the steps of the construction personnel movement line management method based on the BIM model as described in any one of claims 1 to 2 are implemented.
Citation Information
Patent Citations
Highway constructor safety positioning management system and method
CN114333233A
Field construction personnel management and control system and method based on digital twinning
CN116911522A
Engineering construction supervision method and system based on video analysis
CN117372427A
Real-time calculation-based power construction personnel track acquisition method and device
CN117768845A
Highway construction progress intelligent prediction method and system
CN117829382A