A power monitoring method based on power Internet of Things

Through the monitoring method based on the power Internet of Things, the inclination, heat dissipation and voltage stabilization of the generator in the flood area are analyzed, the problem of generator tipping and overheating is solved, and the security and stability of the power supply are improved.

CN118677114BActive Publication Date: 2024-10-25ZHONGYING QINGCHUANG TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411171009.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-26
Publication Date
2024-10-25
Estimated Expiration
2044-08-26

AI Technical Summary

Technical Problem

In flood-stricken areas, generators are prone to problems such as overturning and overheating due to ground tilt and harsh environments, resulting in reduced power supply stability. Existing technologies fail to effectively monitor and solve these problems.

Method used

Using a monitoring method based on the power Internet of Things, the ground inclination, humidity, operating voltage, frequency, temperature, humidity and wind speed data of the generator are obtained through drones, and the tilt threat coefficient, heat dissipation hazard coefficient and power generation fluctuation coefficient are analyzed to screen the tilt and cooling generators, calculate load adjustment values ​​and cooling equipment requirements, evaluate and notify rescue commanders.

Benefits of technology

It effectively reduces the incidence of generator tipping and overheating, improves the safety and power supply stability of the generator, and ensures the power supply in flooded areas.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118677114B_ABST
    Figure CN118677114B_ABST
Patent Text Reader

Abstract

The invention discloses an electric power monitoring method based on an electric power Internet of Things, and relates to the technical field of electric power monitoring. The invention comprises: step 1. obtaining information of a flood-stricken area, step 2. analyzing the tilt of a generator, step 3. analyzing the heat dissipation of a generator, step 4. analyzing the voltage stabilization of a generator, and step 5. handling a generator fault. The invention ensures the normal use of a generator through intelligent monitoring by an unmanned aerial vehicle. When the generator overheats due to high temperature, high humidity, and low wind speed in the flood-stricken area, the temporary operating load adjustment value of each heat dissipation generator in the flood-stricken area is calculated to reduce the overheating or even damage of the generator, thereby improving the safety of the generator and ensuring the power supply stability in the flood-stricken area. By evaluating the power generation fluctuation coefficient of each generator in the flood-stricken area, the generator is prevented from being further irreversibly damaged as a whole due to a voltage stabilizer failure.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of power monitoring, and in particular to a power monitoring method based on power Internet of Things. Background Art

[0002] When a flood occurs, the power supply in the affected area is often interrupted. During emergency rescue, temporary generators are often used for power supply. The terrain and environment in the flood-stricken area are harsh, and temporary generators are prone to problems such as tipping over and overheating, which requires manual real-time monitoring. However, due to lack of manpower during disaster relief, it is difficult to detect generator problems in time, thereby reducing the safety of the generator. Due to its convenience, the Internet of Things technology can perform automatic monitoring. Therefore, it is necessary to study a power monitoring method using the Internet of Things technology during floods.

[0003] Prior art, such as the invention patent application with announcement number: CN113627678B, discloses a method and system for calculating the distribution substation area submerged by heavy rain-induced floods, which includes: analyzing the equipment coordinate information, weather forecast information, and flood forecast information of the medium-voltage distribution overhead line through a neural network to calculate the scope of the distribution substation area submerged by heavy rain-induced floods. This invention can accurately reflect key elements such as flood arrival time, submerged scope, power outage scope, and regional water depth, which helps the production monitoring command center to guide emergency response work such as load transfer, facility reinforcement, and emergency repair and power restoration.

[0004] The prior art, such as the invention patent application with announcement number: CN117714489A, discloses a power station monitoring method and system based on the Internet of Things, and the method includes: S1, deploying equipment in the power station. This invention allows employees to upload their personal information to the system through the mobile phone APP for identity backup. When the power station is unattended, it is convenient for different maintenance personnel and staff to quickly enter the station for operation. The access control system can also alarm for abnormal behavior of strangers to prevent criminals from destroying the power station, thereby improving the safety of the power station.

[0005] It can be seen from the above scheme that the current power monitoring method lacks certain attention to the environmental status of the generator in the flood-stricken area to determine whether it has a risk of tilting. Due to time constraints during disaster relief, only a simple rain shelter is often built outside the generator. The flood-stricken area generally has high wind speed and slippery ground, which makes the generator easily blown down by strong wind due to weak friction, making it impossible to use the generator normally. At the same time, there is a lack of attention to adjusting the generator load and adding heat dissipation equipment according to the actual environmental conditions in the flood-stricken area. The generator will generate a lot of heat during operation. When the ambient temperature in the flood-stricken area is low and the wind speed is high, it can rely on natural cooling. If the environmental conditions deteriorate, the heat cannot be dissipated in time, which may cause the generator to overheat or even be damaged, thereby reducing the safety of the generator and reducing the power supply stability in the flood-stricken area. Summary of the invention

[0006] The purpose of the present invention is to provide a power monitoring method based on the power Internet of Things, which solves the problems existing in the background technology.

[0007] In order to solve the above technical problems, the present invention adopts the following technical solutions: The present invention provides an electric power monitoring method based on the electric power Internet of Things, including: Step 1. Acquisition of flood-stricken area information: When a flood occurs and the rescue personnel have built each generator, the ground inclination and ground humidity of the locations of each generator in the flood-stricken area are obtained at the current monitoring time point, and the operating voltage, operating frequency, ambient temperature, ambient humidity and casing temperature values ​​and wind speed values ​​in each direction of each generator in the flood-stricken area are obtained.

[0008] Step 2. Generator tilt analysis: Analyze the tilt threat coefficient of each generator in the flood-stricken area, screen each tilted generator in the flood-stricken area, and evaluate the number of reinforcements for the support poles of each tilted generator in the flood-stricken area.

[0009] Step 3. Generator heat dissipation analysis: Analyze the heat dissipation hazard coefficient of each generator in the flood-stricken area, screen each heat dissipation generator in the flood-stricken area, calculate the temporary operating load adjustment value of each heat dissipation generator in the flood-stricken area, and evaluate the target number of heat dissipation equipment in each direction of each heat dissipation generator in the flood-stricken area.

[0010] Step 4. Generator voltage regulation analysis: Evaluate the power generation fluctuation coefficient of each generator in the flood-stricken area, screen the generators with voltage regulation failures in the flood-stricken area, obtain the power consumption per unit time of each sub-region in the flood-stricken area at each historical monitoring time point, and analyze the temporary power shutdown sub-regions in the flood-stricken area.

[0011] Step 5. Generator fault handling: Send the number of reinforced support poles of each tilted generator in the flood-stricken area, the temporary operating load adjustment value of each voltage-stabilizing fault generator, each heat dissipation generator, and the target number of heat dissipation equipment in each direction to the rescue command personnel, and notify each temporary power shutdown sub-area in the flood-stricken area that it will briefly enter a power outage state.

[0012] Preferably, the tilt threat coefficient of each generator in the flood-hit area is analyzed by a specific analysis method: the weight value of each generator in the flood-hit area, the suitable ground tilt and the suitable ground humidity corresponding to each weight value interval are obtained from a local database, and the suitable ground tilt of each generator in the flood-hit area is mapped. and suitable ground humidity , where x represents the number of each generator, , y is a positive integer greater than 2.

[0013] Calculate the wind impact coefficient of each generator in the flood area based on the wind speed values ​​in each direction of each generator in the flood area .

[0014] Based on the ground slope of each generator in the flood area , ground humidity , analyze the tilt threat coefficient of each generator in the flood area , where e is represented by a natural constant.

[0015] Preferably, the wind impact coefficient of each generator in the flood area is calculated by: , extract the diagonal wind speed values ​​of each generator in the flood area , where n represents the number of each direction, , m is a positive integer greater than 2.

[0016] Obtain the appropriate wind speed value corresponding to each weight value interval from the local database, and map it to obtain the appropriate wind speed value of each generator in the flood-affected area , calculate the wind impact coefficient of each generator in the flood area , where m is the number of directions.

[0017] Preferably, the specific evaluation method for evaluating the number of reinforcements of the supporting poles of each tilted generator belonging to the flood-stricken area is as follows: obtaining the number of reinforcements of the supporting poles corresponding to each tilt threat coefficient interval from the local database, extracting the tilt threat coefficient of each tilted generator belonging to the flood-stricken area according to the tilt threat coefficient of each generator belonging to the flood-stricken area, and mapping to obtain the number of reinforcements of the supporting poles of each tilted generator belonging to the flood-stricken area.

[0018] Preferably, the heat dissipation hazard coefficient of each generator in the flood-stricken area is analyzed by a specific analysis method: according to the ambient temperature, ambient humidity, shell temperature values ​​in each direction, and wind speed values ​​of each generator in the flood-stricken area, the allowable environmental heat dissipation coefficient of each generator in the flood-stricken area at the current monitoring time point is calculated. .

[0019] Obtain the initial shell temperature value of each generator in the flood area when it is not started from the local database .

[0020] According to the shell temperature values ​​of each generator in each direction in the flood area , analyze the heat dissipation hazard coefficient of each generator in the flood area .

[0021] Preferably, the calculation method of the environmental allowable heat dissipation coefficient of each generator in the flood disaster area at the current monitoring time point is as follows: obtaining the suitable ambient temperature for external cooling of each generator in the flood disaster area from the local database , Suitable environmental humidity and suitable wind speed .

[0022] Based on the ambient temperature of each generator in the flood-affected area , Ambient humidity And wind speed values ​​in each direction , calculate the environmental allowable heat dissipation coefficient of each generator in the flood disaster area at the current monitoring time point .

[0023] Preferably, the temporary operating load adjustment value of each heat dissipation generator belonging to the flood disaster area is calculated, and its specific calculation method is: obtain the temporary allowable load adjustment value corresponding to each heat dissipation hazard coefficient interval from the local database, extract the heat dissipation hazard coefficient of each heat dissipation generator belonging to the flood disaster area according to the heat dissipation hazard coefficient of each generator belonging to the flood disaster area, and map to obtain the temporary allowable load adjustment value of each heat dissipation generator belonging to the flood disaster area , where p represents the number of each heat dissipation generator, , q is a positive integer greater than 2.

[0024] Obtain the initial operating load of each heat dissipation generator in the flood-affected area from the local database , calculate the temporary operating load adjustment value of each heat dissipation generator in the flood area .

[0025] Preferably, the target number of heat dissipation equipment in each direction of each heat dissipation generator in the flood-stricken area is evaluated by a specific evaluation method: obtaining from a local database the temperature F that can be reduced per unit time by a unit number of heat dissipation equipment at maximum power.

[0026] Based on the shell temperature values ​​of each generator in each direction in the flood area and the initial case temperature when not started , calculate the number of cooling equipment required for cooling each heat dissipation generator in the flood area to normal temperature in each direction per unit time ,in It is expressed as rounding up and used as the target number of heat dissipation equipment in each direction of each heat dissipation generator in the disaster area.

[0027] Preferably, the power generation fluctuation coefficient of each generator in the flood-stricken area is evaluated by a specific evaluation method: obtaining the operating voltage of each generator in the flood-stricken area at each historical monitoring time point from a local database , operating frequency , where v represents the number of each historical monitoring time point, , w is a positive integer greater than 2.

[0028] Based on the operating voltage of each generator in the flood-affected area , operating frequency , evaluate the voltage fluctuation coefficient of each generator in the flood-affected area , and evaluate the frequency fluctuation coefficient of each generator in the flood area .

[0029] Assess the power generation fluctuation coefficient of each generator in the flood-affected area .

[0030] Preferably, the specific analysis method for analyzing each temporary power shutdown sub-area belonging to the flood-stricken area is as follows: obtaining the power generation of each generator belonging to the flood-stricken area per unit time from the local database, extracting the power generation of each voltage stabilizing fault generator belonging to the flood-stricken area per unit time, calculating the total reduced power generation per unit time due to shutting down all voltage stabilizing fault generators in the flood-stricken area, and marking it as the total reduced power generation in the flood-stricken area.

[0031] Based on the electricity consumption per unit time of each sub-region belonging to the flood-stricken area at each historical monitoring time point, the average electricity consumption of each sub-region belonging to the flood-stricken area at the historical monitoring time point is calculated.

[0032] The sorted sub-regions of the flood-stricken area are obtained from the local database according to the order of importance, the average power consumption of the sorted sub-regions of the flood-stricken area at the historical monitoring time point is obtained, and it is marked as the average power consumption of the sorted sub-regions of the flood-stricken area.

[0033] The average electricity consumption of the first-ranked sub-region of the flood-stricken area is compared with the total reduced power generation. If the average electricity consumption of the first-ranked sub-region of the flood-stricken area is greater than or equal to the total reduced power generation, the first-ranked sub-region is marked as a temporary power-off sub-region. Otherwise, the total average electricity consumption of the first and second sub-regions of the flood-stricken area is compared with the total reduced power generation. If the total average electricity consumption of the first and second sub-regions of the flood-stricken area is greater than or equal to the total reduced power generation, the first and second sub-regions of the flood-stricken area are marked as temporary power-off sub-regions, and so on, so as to screen the temporary power-off sub-regions belonging to the flood-stricken area.

[0034] The beneficial effects of the present invention are as follows: (1) Step 1 of the present invention obtains information on the flood-affected area, by obtaining environmental data of each generator in the flood-affected area, thereby facilitating subsequent analysis.

[0035] (2) Step 2 of the present invention, generator tilt analysis, through intelligent monitoring by drones, can reduce the incidence of generators being blown down by strong winds due to weak friction caused by excessive wind speeds, excessively slippery ground, or excessively tilted ground in flood-stricken areas, thereby ensuring the normal use of the generators.

[0036] (3) Step 3 of the present invention is to analyze the heat dissipation of the generator. When the generator overheats due to high temperature, high humidity and low wind speed in the flood-stricken area, the temporary operating load adjustment value of each heat dissipation generator in the flood-stricken area is calculated through intelligent analysis of the Internet of Things. The target number of heat dissipation equipment in each direction of each heat dissipation generator in the flood-stricken area is evaluated to reduce the possibility of overheating or even damage of the generator, thereby improving the safety of the generator and ensuring the stability of power supply in the flood-stricken area.

[0037] (4) Step 4 of the present invention is to analyze the voltage stabilization of the generator. By evaluating the power generation fluctuation coefficient of each generator in the flood-stricken area, the generator is prevented from being further irreversibly damaged as a whole due to a voltage stabilizer failure. The temporary power shutdown sub-areas in the flood-stricken area are analyzed to facilitate the affected people in the temporary power shutdown sub-areas in the flood-stricken area to respond to the power outage in a timely manner.

[0038] (5) Step 5 of the present invention is to handle generator failures, by sending relevant analysis data to rescue commanders, so as to facilitate their work allocation for power maintenance in the flood-stricken areas. BRIEF DESCRIPTION OF THE DRAWINGS

[0039] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0040] Figure 1 It is a schematic diagram of the method flow of the present invention. DETAILED DESCRIPTION

[0041] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0042] Reference Figure 1 As shown, the present invention provides a power monitoring method based on the power Internet of Things, including: Step 1. Acquisition of flood-stricken area information: When a flood occurs and the rescue personnel have built each generator, the ground inclination and ground humidity of the locations of each generator belonging to the flood-stricken area are obtained at the current monitoring time point, and the operating voltage, operating frequency, ambient temperature, ambient humidity and casing temperature values ​​and wind speed values ​​in each direction of each generator belonging to the flood-stricken area are obtained.

[0043] In a specific embodiment, the ground inclination and ground humidity of each generator belonging to the flood-stricken area are obtained, and the operating voltage, operating frequency, ambient temperature, ambient humidity and casing temperature values ​​and wind speed values ​​of each generator belonging to the flood-stricken area are obtained. The specific acquisition method is: the ground inclination of each generator belonging to the flood-stricken area is obtained by a fixed inclinometer carried by an unmanned aerial vehicle, the ground humidity of each generator belonging to the flood-stricken area is obtained by an electronic ground humidity meter carried by the unmanned aerial vehicle, the operating voltage and operating frequency of each generator belonging to the flood-stricken area are obtained by a voltmeter and a frequency meter built into the generator control terminal, the ambient temperature and ambient humidity of each generator belonging to the flood-stricken area are obtained by a temperature sensor and a humidity sensor carried by the unmanned aerial vehicle, and the casing temperature values ​​and wind speed values ​​in each direction of each generator belonging to the flood-stricken area are obtained by temperature sensors and wind speed sensors installed in each direction of the generator.

[0044] Step 1 of the present invention is to obtain information about the flood-affected area, by obtaining environmental data of each generator in the flood-affected area, so as to facilitate subsequent analysis.

[0045] Step 2. Generator tilt analysis: Analyze the tilt threat coefficient of each generator in the flood-stricken area, screen each tilted generator in the flood-stricken area, and evaluate the number of reinforcements for the support poles of each tilted generator in the flood-stricken area.

[0046] In a specific embodiment, the specific screening method for screening the tilted generators belonging to the flood-stricken area is: obtaining a tilt threat coefficient threshold from a local database, comparing the tilt threat coefficient of each generator belonging to the flood-stricken area with the tilt threat coefficient threshold, if the tilt threat coefficient of a generator belonging to the flood-stricken area is greater than the tilt threat coefficient threshold, then marking the generator as a tilted generator, thereby screening the tilted generators belonging to the flood-stricken area.

[0047] It should be noted that the local database is used to store the tilt threat coefficient threshold, the weight value of each generator belonging to the flood-stricken area, the suitable ground tilt and suitable ground humidity corresponding to each weight value interval, the suitable wind speed value corresponding to each weight value interval, the number of reinforcements of the support poles corresponding to each tilt threat coefficient interval, the heat dissipation hazard coefficient threshold, the initial shell temperature value of each generator belonging to the flood-stricken area when not started, the suitable ambient temperature, suitable ambient humidity and suitable wind speed value for external cooling of each generator belonging to the flood-stricken area, the temporary allowable load adjustment value corresponding to each heat dissipation hazard coefficient interval, the initial operating load of each heat dissipation generator belonging to the flood-stricken area, the temperature that can be reduced per unit time by a unit number of heat dissipation equipment at maximum power, the power generation fluctuation coefficient threshold, the power consumption of each sub-region belonging to the flood-stricken area per unit time at each historical monitoring time point, the operating voltage and operating frequency of each generator belonging to the flood-stricken area at each historical monitoring time point, the power generation of each generator belonging to the flood-stricken area per unit time, and the sorted sub-regions belonging to the flood-stricken area sorted from small to large in terms of importance.

[0048] In a specific embodiment of the present invention, the tilt threat coefficient of each generator in the flood area is analyzed, and the specific analysis method is: the weight value of each generator in the flood area, the suitable ground tilt and the suitable ground humidity corresponding to each weight value interval are obtained from the local database, and the suitable ground tilt of each generator in the flood area is mapped. and suitable ground humidity , where x represents the number of each generator, , y is a positive integer greater than 2.

[0049] Calculate the wind impact coefficient of each generator in the flood area based on the wind speed values ​​in each direction of each generator in the flood area .

[0050] Based on the ground slope of each generator in the flood area , ground humidity , analyze the tilt threat coefficient of each generator in the flood area , where e is represented by a natural constant.

[0051] In a specific embodiment of the present invention, the wind influence coefficient of each generator in the flood area is calculated by: based on the wind speed value of each generator in each direction in the flood area , extract the diagonal wind speed values ​​of each generator in the flood area , where n represents the number of each direction, , m is a positive integer greater than 2.

[0052] Obtain the appropriate wind speed value corresponding to each weight value interval from the local database, and map it to obtain the appropriate wind speed value of each generator in the flood-affected area , calculate the wind impact coefficient of each generator in the flood area , where m is the number of directions.

[0053] In a specific embodiment of the present invention, the evaluation of the number of reinforcements of the supporting poles of each tilted generator belonging to the flood-stricken area is carried out by obtaining the number of reinforcements of the supporting poles corresponding to each tilt threat coefficient interval from a local database, extracting the tilt threat coefficient of each tilted generator belonging to the flood-stricken area according to the tilt threat coefficient of each generator belonging to the flood-stricken area, and mapping to obtain the number of reinforcements of the supporting poles of each tilted generator belonging to the flood-stricken area.

[0054] Step 2 of the present invention is to analyze the tilt of the generator. Through intelligent monitoring by drones, the incidence of the generator being blown down by strong winds due to weak friction caused by excessive wind speeds, excessively slippery ground, and excessively tilted ground in flood-stricken areas can be reduced, thereby ensuring the normal use of the generator.

[0055] Step 3. Generator heat dissipation analysis: Analyze the heat dissipation hazard coefficient of each generator in the flood-stricken area, screen each heat dissipation generator in the flood-stricken area, calculate the temporary operating load adjustment value of each heat dissipation generator in the flood-stricken area, and evaluate the target number of heat dissipation equipment in each direction of each heat dissipation generator in the flood-stricken area.

[0056] In a specific embodiment, the screening of the heat dissipation generators belonging to the flood-stricken area comprises the following specific screening method: obtaining a heat dissipation hazard coefficient threshold from a local database, comparing the heat dissipation hazard coefficient of each generator belonging to the flood-stricken area with the heat dissipation hazard coefficient threshold; if the heat dissipation hazard coefficient of a generator belonging to the flood-stricken area is greater than the heat dissipation hazard coefficient threshold, marking the generator as a tilted generator, thereby screening the heat dissipation generators belonging to the flood-stricken area.

[0057] In a specific embodiment of the present invention, the heat dissipation hazard coefficient of each generator in the flood-stricken area is analyzed, and the specific analysis method is: according to the ambient temperature, ambient humidity, shell temperature value in each direction, and wind speed value of each generator in the flood-stricken area, the environmental allowable heat dissipation coefficient of each generator in the flood-stricken area at the current monitoring time point is calculated. .

[0058] Obtain the initial shell temperature value of each generator in the flood area when it is not started from the local database .

[0059] According to the shell temperature values ​​of each generator in each direction in the flood area , analyze the heat dissipation hazard coefficient of each generator in the flood area .

[0060] In a specific embodiment of the present invention, the calculation method of the allowable heat dissipation coefficient of the environment of each generator in the flood disaster area at the current monitoring time point is as follows: obtaining the suitable ambient temperature for external cooling of each generator in the flood disaster area from the local database , Suitable environmental humidity and suitable wind speed .

[0061] Based on the ambient temperature of each generator in the flood-affected area , Ambient humidity And wind speed values ​​in each direction , calculate the environmental allowable heat dissipation coefficient of each generator in the flood disaster area at the current monitoring time point .

[0062] In a specific embodiment of the present invention, the temporary operating load adjustment value of each heat dissipation generator belonging to the flood disaster area is calculated, and its specific calculation method is: obtain the temporary allowable load adjustment value corresponding to each heat dissipation hazard coefficient interval from the local database, extract the heat dissipation hazard coefficient of each heat dissipation generator belonging to the flood disaster area according to the heat dissipation hazard coefficient of each generator belonging to the flood disaster area, and map the temporary allowable load adjustment value of each heat dissipation generator belonging to the flood disaster area. , where p represents the number of each heat dissipation generator, , q is a positive integer greater than 2.

[0063] Obtain the initial operating load of each heat dissipation generator in the flood-affected area from the local database , calculate the temporary operating load adjustment value of each heat dissipation generator in the flood area .

[0064] In a specific embodiment of the present invention, the target number of heat dissipation equipment in each direction of each heat dissipation generator in the flood-stricken area is evaluated by a specific evaluation method: obtaining the temperature F that can be reduced per unit time at maximum power by a unit number of heat dissipation equipment from a local database.

[0065] Based on the shell temperature values ​​of each generator in each direction in the flood area and the initial case temperature when not started , calculate the number of cooling equipment required for cooling each heat dissipation generator in the flood area to normal temperature in each direction per unit time ,in It is expressed as rounding up and used as the target number of heat dissipation equipment in each direction of each heat dissipation generator in the disaster area.

[0066] Step 3 of the present invention is to analyze the heat dissipation of the generator. Through intelligent analysis of the Internet of Things, when the generator overheats due to high temperature, high humidity and low wind speed in the flood-stricken area, the temporary operating load adjustment value of each heat dissipation generator in the flood-stricken area is calculated, and the target number of heat dissipation equipment in each direction of each heat dissipation generator in the flood-stricken area is evaluated to reduce the possibility of overheating or even damage of the generator, thereby improving the safety of the generator and ensuring the stability of power supply in the flood-stricken area.

[0067] Step 4. Generator voltage regulation analysis: Evaluate the power generation fluctuation coefficient of each generator in the flood-stricken area, screen the generators with voltage regulation failures in the flood-stricken area, obtain the power consumption per unit time of each sub-region in the flood-stricken area at each historical monitoring time point, and analyze the temporary power shutdown sub-regions in the flood-stricken area.

[0068] In a specific embodiment, the screening of the voltage stabilizing fault generators in the flood-hit area is as follows: obtaining a power generation fluctuation coefficient threshold from a local database, comparing the power generation fluctuation coefficient of each generator in the flood-hit area with the power generation fluctuation coefficient threshold, and if the power generation fluctuation coefficient of a generator in the flood-hit area is greater than the power generation fluctuation coefficient threshold, marking the generator as a tilted generator, thereby screening the voltage stabilizing fault generators in the flood-hit area.

[0069] In a specific embodiment, the power consumption per unit time of each sub-region belonging to the flood-stricken area at each historical monitoring time point is obtained by a specific method: the power consumption per unit time of each sub-region belonging to the flood-stricken area at each historical monitoring time point is obtained from a local database.

[0070] In a specific embodiment of the present invention, the power generation fluctuation coefficient of each generator in the flood-stricken area is evaluated by a specific evaluation method: the operating voltage of each generator in the flood-stricken area at each historical monitoring time point is obtained from a local database. , operating frequency , where v represents the number of each historical monitoring time point, , w is a positive integer greater than 2.

[0071] Based on the operating voltage of each generator in the flood-affected area , operating frequency , evaluate the voltage fluctuation coefficient of each generator in the flood-affected area , and evaluate the frequency fluctuation coefficient of each generator in the flood area .

[0072] Assess the power generation fluctuation coefficient of each generator in the flood-affected area .

[0073] In a specific embodiment of the present invention, the specific analysis method for analyzing the temporary power shutdown sub-areas belonging to the flood-stricken area is as follows: obtaining the power generation of each generator belonging to the flood-stricken area per unit time from the local database, extracting the power generation of each voltage stabilizing fault generator belonging to the flood-stricken area per unit time, calculating the total reduced power generation per unit time due to shutting down all voltage stabilizing fault generators in the flood-stricken area, and marking it as the total reduced power generation in the flood-stricken area.

[0074] Based on the electricity consumption per unit time of each sub-region belonging to the flood-stricken area at each historical monitoring time point, the average electricity consumption of each sub-region belonging to the flood-stricken area at the historical monitoring time point is calculated.

[0075] The sorted sub-regions of the flood-stricken area are obtained from the local database according to the order of importance, the average power consumption of the sorted sub-regions of the flood-stricken area at the historical monitoring time point is obtained, and it is marked as the average power consumption of the sorted sub-regions of the flood-stricken area.

[0076] The average electricity consumption of the first-ranked sub-region of the flood-stricken area is compared with the total reduced power generation. If the average electricity consumption of the first-ranked sub-region of the flood-stricken area is greater than or equal to the total reduced power generation, the first-ranked sub-region is marked as a temporary power-off sub-region. Otherwise, the total average electricity consumption of the first and second sub-regions of the flood-stricken area is compared with the total reduced power generation. If the total average electricity consumption of the first and second sub-regions of the flood-stricken area is greater than or equal to the total reduced power generation, the first and second sub-regions of the flood-stricken area are marked as temporary power-off sub-regions, and so on, so as to screen the temporary power-off sub-regions belonging to the flood-stricken area.

[0077] Step 4 of the present invention is to analyze the voltage stabilization of the generator, by evaluating the power generation fluctuation coefficient of each generator in the flood-stricken area, to prevent the generator from being further irreversibly damaged as a whole due to a voltage stabilizer failure, and to analyze the temporary power shutdown sub-areas in the flood-stricken area, so that the affected people in the temporary power shutdown sub-areas in the flood-stricken area can respond to the power outage in a timely manner.

[0078] Step 5. Generator fault handling: Send the number of reinforced support poles of each tilted generator in the flood-stricken area, the temporary operating load adjustment value of each voltage-stabilizing fault generator, each heat dissipation generator, and the target number of heat dissipation equipment in each direction to the rescue command personnel, and notify each temporary power shutdown sub-area in the flood-stricken area that it will briefly enter a power outage state.

[0079] Step 5 of the present invention is to handle generator failures, by sending relevant analysis data to rescue commanders, thereby facilitating their work allocation for power maintenance in flood-stricken areas.

[0080] The above contents are merely examples and explanations of the concept of the present invention. Those skilled in the art may make various modifications or additions to the specific embodiments described or replace them in a similar manner. As long as they do not deviate from the concept of the invention or exceed the scope defined by the present invention, they shall all fall within the protection scope of the present invention.

Claims

1. A power monitoring method based on power Internet of Things, characterized in that: include: Step 1. Obtaining information about the flood-affected area: When a flood occurs and the rescuers have built the generators, obtain the ground inclination and ground humidity of the generators in the flood-affected area at the current monitoring time point, and obtain the operating voltage, operating frequency, ambient temperature, ambient humidity, and shell temperature and wind speed values ​​of the generators in the flood-affected area in all directions; Step 2. Generator tilt analysis: Analyze the tilt threat coefficient of each generator in the flood area, screen the tilted generators in the flood area, and evaluate the reinforcement quantity of the support poles of each tilted generator in the flood area; The specific analysis method for analyzing the tilt threat coefficient of each generator in the flood disaster area is as follows: The weight values ​​of each generator in the flood-stricken area, the appropriate ground inclination and appropriate ground humidity corresponding to each weight value interval are obtained from the local database, and the appropriate ground inclination a of each generator in the flood-stricken area is mapped. x and suitable ground humidity b x , where x represents the number of each generator, x=1, 2, ..., y, and y is a positive integer greater than 2; According to the wind speed values ​​in each direction of each generator in the flood area, calculate the wind impact coefficient A of each generator in the flood area x ; According to the ground inclination c of each generator in the flood area x , ground humidity x , analyze the tilt threat coefficient of each generator in the flood area Where e represents a natural constant; The specific calculation method for calculating the wind influence coefficient of each generator in the flood area is as follows: According to the wind speed value f in each direction of each generator in the flood area xn , extract the diagonal wind speed values ​​g of each generator in the flood area xn , where n represents the number of each direction, n = 1, 2, ..., m, and m is a positive integer greater than 2; Obtain the appropriate wind speed value corresponding to each weight value interval from the local database, and map it to obtain the appropriate wind speed value h of each generator in the flood area x , calculate the wind impact coefficient of each generator in the flood area Where m is the number of directions; Step 3. Generator heat dissipation analysis: Analyze the heat dissipation hazard coefficient of each generator in the flood-affected area, screen each heat dissipation generator in the flood-affected area, calculate the temporary operating load adjustment value of each heat dissipation generator in the flood-affected area, and evaluate the target number of heat dissipation equipment in each direction of each heat dissipation generator in the flood-affected area; The specific analysis method for analyzing the heat dissipation hazard coefficient of each generator in the flood-affected area is as follows: According to the ambient temperature, ambient humidity, shell temperature and wind speed of each generator in the flood area, calculate the allowable environmental heat dissipation coefficient B of each generator in the flood area at the current monitoring time point. x ; Obtain the initial shell temperature value C of each generator in the flood disaster area before it is started from the local database x ; According to the shell temperature value D of each generator in each direction in the flood area xn , analyze the heat dissipation hazard coefficient of each generator in the flood area The specific calculation method of calculating the environmental allowable heat dissipation coefficient of each generator in the flood disaster area at the current monitoring time point is: Obtain the suitable ambient temperature H for external cooling of each generator in the flood disaster area from the local database x , Suitable environmental humidity K x and suitable wind speed value L x ; According to the ambient temperature h of each generator in the flood area x 、Ambient humidity k x And the wind speed value l in each direction xn , calculate the environmental allowable heat dissipation coefficient of each generator in the flood disaster area at the current monitoring time point Step 4. Generator voltage stabilization analysis: evaluate the power generation fluctuation coefficient of each generator in the flood-affected area, screen the generators with voltage stabilization failures in the flood-affected area, obtain the power consumption per unit time of each sub-region in the flood-affected area at each historical monitoring time point, and analyze the temporary power shutdown sub-regions in the flood-affected area; The specific evaluation method for evaluating the power generation fluctuation coefficient of each generator in the flood-affected area is as follows: Obtain the operating voltage t of each generator in the flood disaster area at each historical monitoring time point from the local database xv , operating frequency u xv , where v represents the number of each historical monitoring time point, v = 1, 2, ..., w, w is a positive integer greater than 2; According to the operating voltage T of each generator in the flood area x , operating frequency Y x , evaluate the voltage fluctuation coefficient of each generator in the flood-affected area And evaluate the frequency fluctuation coefficient of each generator in the flood area Assess the power generation fluctuation coefficient of each generator in the flood-affected area Step 5. Generator fault handling: Send the number of reinforced support poles of each tilted generator in the flood-stricken area, the temporary operating load adjustment value of each voltage-stabilizing fault generator, each heat dissipation generator, and the target number of heat dissipation equipment in each direction to the rescue command personnel, and notify each temporary power shutdown sub-area in the flood-stricken area that it will briefly enter a power outage state.

2. The power monitoring method based on the power Internet of Things according to claim 1 is characterized in that: The specific evaluation method for evaluating the number of reinforcements of the support poles of each inclined generator in the flood-affected area is as follows: The number of reinforcements for the support poles corresponding to each tilt threat coefficient interval is obtained from the local database. According to the tilt threat coefficients of each generator in the flood area, the tilt threat coefficients of each tilted generator in the flood area are extracted, and the number of reinforcements for the support poles of each tilted generator in the flood area is mapped.

3. The power monitoring method based on the power Internet of Things according to claim 1 is characterized in that: The specific calculation method of calculating the temporary operating load adjustment value of each heat dissipation generator in the flood disaster area is: The temporary allowable load adjustment value corresponding to each heat dissipation hazard coefficient interval is obtained from the local database. According to the heat dissipation hazard coefficient of each generator in the flood disaster area, the heat dissipation hazard coefficient of each heat dissipation generator in the flood disaster area is extracted, and the temporary allowable load adjustment value r of each heat dissipation generator in the flood disaster area is mapped. p , where p represents the serial number of each heat dissipation generator, p = 1, 2, ..., q, q is a positive integer greater than 2; Obtain the initial operating load s of each heat dissipation generator in the flood disaster area from the local database p , calculate the temporary operating load adjustment value ε of each heat dissipation generator in the flood area p =r p +s p .

4. The power monitoring method based on the power Internet of Things according to claim 3 is characterized in that: The specific evaluation method for evaluating the target number of heat dissipation equipment in each direction of each heat dissipation generator in the flood disaster area is as follows: Obtain the temperature F that can be reduced per unit time under maximum power of a unit number of heat dissipation equipment from the local database; Based on the shell temperature value D of each generator in each direction in the flood area xn and the initial case temperature C when not started x , calculate the number of cooling equipment required for cooling each heat dissipation generator in the flood area to normal temperature in each direction per unit time in It is expressed as rounding up and used as the target number of heat dissipation equipment in each direction of each heat dissipation generator in the disaster area.

5. The power monitoring method based on the power Internet of Things according to claim 1 is characterized in that: The specific analysis method for analyzing the temporary power shutdown sub-areas belonging to the flood disaster area is as follows: Obtain the power generation of each generator in the flood-stricken area per unit time from the local database, extract the power generation of each voltage-stabilizing fault generator in the flood-stricken area per unit time, calculate the total power generation reduction per unit time due to shutting down all voltage-stabilizing fault generators in the flood-stricken area, and mark it as the total power generation reduction in the flood-stricken area; Based on the power consumption per unit time of each sub-region of the flood-stricken area at each historical monitoring time point, the average power consumption of each sub-region of the flood-stricken area at the historical monitoring time point is calculated; Obtain from the local database the sorted sub-regions of the flood-stricken area sorted from small to large in importance, obtain the average power consumption of the sorted sub-regions of the flood-stricken area at the historical monitoring time point, and mark it as the average power consumption of the sorted sub-regions of the flood-stricken area; The average electricity consumption of the first-ranked sub-region of the flood-stricken area is compared with the total reduced power generation. If the average electricity consumption of the first-ranked sub-region of the flood-stricken area is greater than or equal to the total reduced power generation, the first-ranked sub-region is marked as a temporary power-off sub-region. Otherwise, the total average electricity consumption of the first and second sub-regions of the flood-stricken area is compared with the total reduced power generation. If the total average electricity consumption of the first and second sub-regions of the flood-stricken area is greater than or equal to the total reduced power generation, the first and second sub-regions of the flood-stricken area are marked as temporary power-off sub-regions, and so on, so as to screen the temporary power-off sub-regions belonging to the flood-stricken area.