A method for optimizing the surface spraying process of automobile wheel hub decoration parts
By constructing a three-dimensional hub model and global optimization technology, the problem of poor spraying effect on the surface of complex hub structures is solved, and the precise spraying and quality improvement of the hub surface is achieved, ensuring the automation and consistency of the spraying process.
Patent Information
- Application Number
- CN202411171818.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-26
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2044-08-26
AI Technical Summary
In the prior art, it is difficult to achieve uniform and high-quality spraying effect on the surface of complex hub structures, and due to the positional abutment relationship between different surfaces, the continuity and consistency of the spraying effect are difficult to ensure.
By constructing a three-dimensional hub model, the structural posture and spray distance limits of each hub surface are obtained, combined with the spray effect as evaluation indicators, global optimization is carried out to determine the optimal spray control plan, and the plan is adjusted according to the posture relationship of adjacent surfaces , ensure uniform and continuous spraying of the entire hub surface.
Accurate spraying of the hub surface is achieved, the spraying effect and quality is improved, artificial errors are reduced, production efficiency and product quality are improved, and the spraying process is more automated and accurate.
Smart Images

Figure CN118690491B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of spraying technology, and in particular to a method for optimizing the surface spraying process of automobile hub decorative parts. Background Art
[0002] In the automotive manufacturing industry, the wheel hub is an important part of the vehicle, and its appearance quality and performance directly affect the quality and appearance of the whole vehicle. With the continuous advancement of industrial automation technology, the manufacturing and spraying processes of the wheel hub are also being optimized and improved. The traditional wheel hub manufacturing and spraying processes mainly rely on the experience and skills of the workers, and there are certain limitations. For example, during the spraying process, due to the complexity of the wheel hub surface, it is difficult to achieve a uniform and high-quality spraying effect. In addition, due to the position adjacency relationship between different surfaces of the wheel hub, how to ensure the continuity and consistency of the spraying effect is also a challenge.
[0003] In summary, in the prior art, it is difficult to achieve uniform and high-quality spraying effects when performing surface spraying on complex hub structures. Summary of the invention
[0004] The purpose of this application is to provide a method for optimizing the surface spraying process of automobile hub decoration parts, so as to solve the technical problem in the prior art that it is difficult to achieve uniform and high-quality spraying effects when performing surface spraying on complex hub structures.
[0005] In view of the above problems, the present application provides a method for optimizing the surface spraying process of automobile wheel hub decoration parts.
[0006] The present application provides a method for optimizing the surface spraying process of an automobile hub decorative part, wherein the method comprises: constructing a three-dimensional hub model based on the collected hub structural size feature information of the hub decorative part; obtaining a first structural posture of a first hub surface in the three-dimensional hub model, and obtaining a first spraying posture in combination with a spraying distance limit, wherein the first spraying posture refers to the position posture of a first spray head spraying the first hub surface; using the first spraying posture as a spraying optimization constraint, using the spraying effect as a spraying optimization evaluation index, and globally optimizing in a spraying optimization space established based on a first predetermined spraying control index to obtain a first optimal spraying control scheme for the first spray head to spray the first hub surface; obtaining a second hub surface in the three-dimensional hub model, wherein the second hub surface has a posture adjacency relationship with the first hub surface; adjusting the first optimal spraying control scheme in combination with the second structural posture of the second hub surface to obtain a second optimal spraying control scheme; and performing surface spraying control on the second hub surface according to the second optimal spraying control scheme.
[0007] One or more technical solutions provided in this application have at least the following technical effects or advantages:
[0008] This application constructs a three-dimensional hub model by collecting the dimensional feature information of the hub decoration, and uses this model to optimize the spraying process. The main technical goal is to achieve accurate spraying on the hub surface and ensure the spraying effect and quality. First, a three-dimensional hub model is constructed based on the collected hub structure dimensional feature information of the hub decoration. Then, the first structural posture of the first hub surface in the three-dimensional hub model is obtained, and the first spraying posture is obtained in combination with the spraying distance limit. This posture refers to the position and posture of the first spray head spraying the first hub surface. Next, the first spraying posture is used as the spraying optimization constraint, and the spraying effect is used as the spraying optimization evaluation index. The global optimization is performed in the spraying optimization space established based on the first predetermined spraying control index to obtain the first optimal spraying control scheme for the first spray head to spray the first hub surface. Next, the second hub surface in the three-dimensional hub model is obtained, and the hub surface has a posture adjacency relationship with the first hub surface. Then, the first optimal spraying control scheme is adjusted in combination with the second structural posture of the second hub surface to obtain the second optimal spraying control scheme. Finally, the second hub surface is subjected to surface spraying control according to the second optimal spraying control scheme. The present application can realize accurate spraying of the hub surface, improve the spraying effect and quality, and in addition, the spraying process is more automated and accurate, reduces human errors, and improves production efficiency and product quality.
[0009] The above description is only an overview of the technical solution of the present application. In order to more clearly understand the technical means of the present application, it can be implemented according to the contents of the specification, and in order to make the above and other purposes, features and advantages of the present application more obvious and easy to understand, the specific implementation methods of the present application are specifically cited below. It should be understood that the content described in this section is not intended to identify the key or important features of the embodiments of the present application, nor is it intended to limit the scope of the present application. Other features of the present application will become easy to understand through the following description. BRIEF DESCRIPTION OF THE DRAWINGS
[0010] In order to more clearly illustrate the technical solutions in the present application or the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings in the following description are only exemplary, and for ordinary technicians in this field, other drawings can be obtained based on the provided drawings without paying any creative work.
[0011] Figure 1 A schematic diagram of a process flow of an optimization method for the surface spraying process of an automobile hub decorative part of the present application;
[0012] Figure 2 This is a flow chart of finding the first optimal spraying control scheme in a method for optimizing the surface spraying process of an automobile hub decoration part in the present application. DETAILED DESCRIPTION
[0013] The present application provides a method for optimizing the surface spraying process of automobile wheel hub decoration parts, which solves the technical problem in the prior art that it is difficult to achieve uniform and high-quality spraying effects when spraying the surface of a complex wheel hub structure. The present application can achieve precise spraying of the wheel hub surface, improve the spraying effect and quality, and in addition, the spraying process is more automated and accurate, reducing human errors and improving production efficiency and product quality.
[0014] Below, the technical solutions in the present application will be clearly and completely described with reference to the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present application, rather than all of the embodiments of the present application. It should be understood that the present application is not limited to the example embodiments described herein. Based on the embodiments of the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present application. It should also be noted that, for the convenience of description, only the parts related to the present application are shown in the accompanying drawings, rather than all of them.
[0015] Please refer to the attached Figure 1 The present application provides a method for optimizing the surface spraying process of automobile wheel hub decoration parts, wherein the method specifically comprises the following steps:
[0016] Step 1: Construct a three-dimensional wheel hub model based on the collected wheel hub structure size feature information of the wheel hub decoration.
[0017] First, the collected wheel hub structure and size feature information of the wheel hub decoration is used to build a 3D wheel hub model, thereby realizing the 3D digitization of the wheel hub decoration and providing an accurate 3D model foundation for the subsequent design, analysis and manufacturing process. This not only improves the accuracy and efficiency of wheel hub design, but also provides strong technical support for the production and customization of wheel hub decorations.
[0018] Specifically, first, it is necessary to collect the wheel hub structural dimension feature information of the wheel hub decoration. This usually involves the use of high-precision measurement tools and technologies, such as laser scanning or 3D coordinate measuring machines, to ensure the accuracy of the dimensional data. Then, using this dimensional information, a 3D model of the wheel hub is constructed through professional 3D modeling software. In this process, the software automatically generates the 3D structure of the wheel hub, including the rim, spokes and other parts based on the input dimensional data. Next, the constructed 3D model is designed and optimized in detail to meet specific design requirements and technical specifications. This may include adjusting parameters such as the shape, size, and material of the wheel hub to ensure the practicality and aesthetics of the model. In addition, after the 3D model is built, it needs to be verified and tested to ensure the accuracy and reliability of the model. This usually involves comparing the model with the actual wheel hub decoration, as well as conducting a series of performance tests. Finally, the constructed and verified 3D wheel hub model is applied to the design, analysis and manufacturing process of the wheel hub decoration to achieve efficient production and customization of the wheel hub decoration.
[0019] In summary, this step can realize the three-dimensional digitization of the wheel hub decoration, provide an accurate three-dimensional model basis for the design, analysis and manufacturing of the wheel hub decoration, and provide a simulation model basis for the surface spraying of the wheel hub decoration.
[0020] Step 2: Obtain a first structural posture of the first hub surface in the three-dimensional hub model, and obtain a first spraying posture in combination with a spraying distance limit, wherein the first spraying posture refers to a position posture of a first spray head spraying the first hub surface.
[0021] This step determines the spraying posture of the first hub surface through the three-dimensional hub model. The first hub surface is any surface to be sprayed in the three-dimensional hub model. By obtaining the structural posture of the first hub surface and combining the spraying distance limit, the scheme aims to accurately calculate the position and posture of the first spray head spraying the hub surface. This ensures the accuracy of the spraying process and the consistency of the hub surface coating quality, which is of great significance for improving hub manufacturing efficiency and product quality.
[0022] Specifically, first, it is necessary to obtain the structural posture of the first hub surface in the three-dimensional hub model. This usually involves using three-dimensional modeling software to analyze the hub model and determine the specific position and orientation of the hub surface. Then, combined with the spray distance limit, the first spray posture is calculated. The spray distance limit refers to the ideal distance range between the spray head and the hub surface to ensure the coating thickness and quality. Next, according to the calculated first spray posture, the position and posture of the first spray head are adjusted to align it with the spraying area of the hub surface. In addition, in this process, the working parameters of the spray head, such as the movement speed of the spray gun, the spraying pressure, etc., need to be considered to ensure the spraying effect. Finally, the correctness of the spray posture is verified through actual operation, and necessary adjustments are made to ensure the spraying quality and efficiency.
[0023] In summary, this step can accurately determine the spraying posture of the hub surface in the three-dimensional hub model, thereby ensuring the accuracy of the spraying process and the consistency of the hub surface coating quality.
[0024] Step three: Taking the first spraying posture as the spraying optimization constraint and the spraying effect as the spraying optimization evaluation index, a global optimization is performed in the spraying optimization space established based on the first predetermined spraying control index to obtain the first optimal spraying control scheme for the first spray head to spray the first hub surface.
[0025] The optimal spray control scheme for the first hub surface is determined by a global optimization method. The first spraying posture is used as the constraint condition for spray optimization, and the spraying effect is used as the evaluation index. The search is performed in the spray optimization space established based on the first predetermined spraying control index to find the best spray control scheme. This step is crucial to ensure the efficiency and quality of the spraying process, especially in the spraying of complex hub surfaces, which can significantly improve the uniformity of spraying and the quality of coating.
[0026] Specifically, the first spraying posture is first determined as a constraint for spray optimization. This means that the position and posture of the spray head must conform to the first spraying posture calculated previously. Then, a spray optimization space is established, which is based on predetermined spray control indicators, such as the movement speed of the spray gun, the spray pressure, the distance between the spray gun and the hub surface, etc. Next, a global optimization is performed in the spray optimization space. This involves using optimization algorithms, such as genetic algorithms or particle swarm optimization algorithms, to search for the optimal combination of spray control parameters. In addition, the spraying effect is used as an evaluation indicator to evaluate the spraying quality of different combinations of spray control parameters. Finally, the first optimal spray control scheme obtained through the global optimization process will be used in the actual spraying process to achieve the best spraying effect.
[0027] In summary, this step is based on the first spraying posture and spraying effect evaluation index, and under the predetermined spraying control index, the optimal spraying control scheme for the first hub surface is obtained by global optimization. This helps to improve the efficiency and quality of the spraying process, especially in the spraying of complex hub surfaces, and can ensure the uniformity of spraying and coating quality.
[0028] Step 4: Acquire a second hub surface in the three-dimensional hub model, wherein the second hub surface and the first hub surface have a posture adjacency relationship.
[0029] Identifying and obtaining the second hub surface in the three-dimensional hub model is crucial to ensuring the continuity and consistency of the entire hub spraying process, because it involves the spraying transition between adjacent hub surfaces, which has a direct impact on the overall appearance and quality of the hub. The second hub surface is a hub surface that has a posture adjacency relationship with the first hub surface.
[0030] Specifically, first, identify the second hub face in the established 3D hub model. This usually involves using the analysis tools of the 3D modeling software to determine the location of the second hub face based on the structural features and geometric relationships of the hub. Then, confirm the pose adjacency relationship between the second hub face and the first hub face. The pose adjacency relationship refers to the relative position and orientation of the two hub faces in space. This relationship is crucial to the subsequent spraying process because it determines how the spray head transitions from one hub face to the other. Next, the relevant information of the second hub face, including its pose and adjacency relationship with the first hub face, is input into the control software of the spraying system. In addition, during this process, it may be necessary to preliminarily set and optimize the spraying parameters of the second hub face to ensure consistent spraying effect across the entire hub. Finally, the correct identification and parameter setting of the second hub face is ensured through verification and testing to prepare for the subsequent spraying process.
[0031] In summary, this step can accurately identify and obtain the second hub surface in the three-dimensional hub model, especially the hub surface that has a posture adjacency relationship with the first hub surface. This provides the necessary information and parameters for the subsequent spraying process, ensures the continuity and consistency of the hub spraying, and thus improves the overall appearance and quality of the hub.
[0032] Step five: adjusting the first optimal spraying control scheme in combination with the second structural posture of the second hub surface to obtain a second optimal spraying control scheme.
[0033] The first optimal spray control scheme determined previously is adjusted according to the structural posture of the second hub surface to obtain the second optimal spray control scheme for the second hub surface. Since the second hub surface is adjacent to the first hub surface in posture, its spray control scheme needs to be adjusted accordingly to ensure the uniformity and consistency of the entire hub spray.
[0034] Specifically, first, the second structural pose of the second hub surface is obtained. This involves using 3D modeling software to analyze the hub model and determine the specific position and direction of the second hub surface. Then, the first optimal spray control scheme is adjusted according to the pose information of the second hub surface. This may include changing the movement path, spray speed, spray pressure and other parameters of the spray gun to adapt to the characteristics and spraying requirements of the second hub surface. Next, an optimization algorithm, such as a genetic algorithm or a particle swarm optimization algorithm, is used to search for the optimal solution in the adjusted spray parameter space to find the optimal spray control scheme for the second hub surface. In addition, in this process, the transition area between the second hub surface and the first hub surface needs to be considered to ensure a smooth transition of the spraying effect. Finally, the correctness of the second optimal spray control scheme is verified through actual operation, and necessary fine-tuning is performed to ensure the spraying quality and efficiency.
[0035] In summary, this step can adjust the first optimal spray control scheme according to the structural position of the second hub surface to obtain the optimal spray control scheme for the second hub surface. This helps to ensure the uniformity and consistency of the entire hub spray, thereby improving the spray quality and overall appearance of the hub surface.
[0036] Step six: performing surface spraying control on the second hub surface according to the second optimal spraying control scheme.
[0037] The second hub surface is actually sprayed according to the determined second optimal spray control scheme. By accurately applying the second optimal spray control scheme, it can be ensured that the second hub surface is sprayed evenly and without defects, thereby improving the overall quality of the hub.
[0038] Specifically, first, the second optimal spray control scheme is input into the control software of the spray system. This scheme includes the optimal spray parameters for the second hub surface, such as the movement speed of the spray gun, the spray pressure, the distance between the spray gun and the hub surface, etc. Then, the spray system is started to spray the second hub surface according to the control scheme. During the spraying process, the spraying system automatically adjusts the position, posture and spraying parameters of the spray head to ensure the accuracy and consistency of the spraying. Next, the spraying process is monitored and the spraying effect is checked in real time to ensure that it meets the predetermined quality standards. In addition, during the spraying process, attention should be paid to the transition area between the second hub surface and the first hub surface to ensure a smooth transition of the spraying effect. Finally, after the spraying of the second hub surface is completed, quality inspection and necessary follow-up treatments, such as drying and curing, are carried out to ensure that the coating is fully adhered and achieves the expected performance.
[0039] In summary, the present application can accurately control the surface spraying of the second hub surface according to the second optimal spraying control scheme, which helps to ensure the quality and appearance of the hub surface spraying, improve the overall quality of the hub, and meet the requirements of high-quality hub manufacturing.
[0040] Further, as attached Figure 2 As shown, step three of this application includes:
[0041] Randomly extract a first spraying scheme in the spraying optimization space; analyze the first spraying simulation data of the first spraying scheme to obtain a first spraying effect index; compare the first spraying effect index with the second spraying effect index of the second spraying scheme in the spraying optimization space to obtain a comparison result; determine the first optimal spraying control scheme according to the comparison result.
[0042] First, the goal of this technical solution is to determine the optimal spray control solution by comparing and analyzing the effect index of different spray solutions in the spray optimization space. The spray effect index is obtained by randomly extracting spray solutions in the spray optimization space and analyzing its simulation data, and then compared with other spray solutions in the space to find the best spray control solution.
[0043] The specific implementation process is as follows: First, the first spraying scheme is randomly extracted from the spraying optimization space. The spraying optimization space is established based on the predetermined spraying control index and contains a variety of possible spraying parameter combinations. Then, the first spraying scheme is simulated and analyzed to obtain its spraying effect index. The spraying effect index is a quantitative index used to evaluate the spraying quality of the spraying scheme, such as the uniformity, thickness, adhesion, etc. of the coating. Next, the effect index of the first spraying scheme is compared with the effect index of the second spraying scheme in the spraying optimization space. This involves the use of a specific comparison algorithm or method to evaluate the pros and cons of the two spraying schemes. In addition, during the comparison process, multiple spraying effect indices may need to be considered to comprehensively evaluate the performance of the spraying scheme. Finally, the first optimal spraying control scheme is determined based on the comparison results. If the effect index of the first spraying scheme is better than or equal to the second spraying scheme, the first spraying scheme is determined as the optimal scheme; otherwise, it is necessary to continue to compare other spraying schemes until the best scheme is found.
[0044] In summary, this technical solution can determine the optimal spray control solution by comparing the effect index of different spray solutions in the spray optimization space. This helps to improve the efficiency and quality of the spray process, especially in applications that require precise control of the spray effect, and can ensure the best spray effect.
[0045] Furthermore, the present application includes:
[0046] The first predetermined spraying control index includes a first spraying pressure and a first nozzle diameter, the first spraying pressure has a first pressure limit, and the first nozzle diameter has a first diameter limit; the first spraying scheme is established based on a first pressure value in the first pressure limit and a first diameter value in the first diameter limit.
[0047] First of all, the core of this technical solution is to establish the first spraying scheme according to the predetermined spraying control indicators. The spraying control indicators include spraying pressure and nozzle diameter, and each indicator has its specific limit range. By selecting a pressure value in the spraying pressure limit and a diameter value in the nozzle diameter limit, a specific spraying scheme can be established. This scheme will serve as the starting point for spraying optimization and will be used for subsequent spraying simulation and effect evaluation to determine the optimal spraying control parameters.
[0048] The specific implementation process is as follows: First, determine the first predetermined spray control index, namely the spray pressure and nozzle diameter. The spray pressure is a key parameter that affects the speed and flow rate of the paint spray, while the nozzle diameter affects the shape and range of the paint spray. Then, set a limit range for each index. For example, the first pressure limit may be a pressure interval, such as 10-20 bar; the first diameter limit may be a diameter interval, such as 1-2 mm. Next, based on these limits, select a specific pressure value and diameter value to form the first spray scheme. For example, 15 bar can be selected as the first pressure value and 1.5 mm as the first diameter value. In addition, when forming a spray scheme, other spray parameters may also need to be considered, such as the movement speed of the spray gun, the spray distance, etc. Finally, the formed first spray scheme is input into the spray simulation system for simulation analysis to obtain its spray effect index, which provides a basis for the subsequent spray optimization process.
[0049] In summary, this technical solution can be used to build a specific spraying plan based on the predetermined spraying control indicators and limit ranges, which provides a basis for the subsequent spraying simulation and optimization process.
[0050] Furthermore, the present application includes:
[0051] Based on the spraying efficiency dimension, the first spraying area in the first spraying simulation data is extracted; based on the spraying quality dimension, the first appearance quality and the first unit flow rate in the first spraying simulation data are extracted, and the first spraying quality is obtained by weighted analysis; the first spraying area and the first spraying quality after normalization are analyzed using the coefficient of variation principle to obtain the first spraying effect index.
[0052] First of all, the goal of this technical solution is to evaluate the spraying effect from two dimensions, spraying efficiency and spraying quality, by analyzing the spraying simulation data, and to obtain a comprehensive spraying effect index using the coefficient of variation principle. The spraying efficiency dimension is measured by extracting the spraying area, while the spraying quality dimension combines the appearance quality and unit flow rate and is evaluated through weighted analysis.
[0053] The specific implementation process is as follows: First, the first spraying area related to the spraying efficiency is extracted from the first spraying simulation data. The spraying area refers to the coverage of the paint in a spraying operation, which is an important indicator for measuring the spraying efficiency. Then, based on the spraying quality dimension, the first appearance quality and the first unit flow rate are extracted from the simulation data. The appearance quality refers to the appearance effect of the coating, such as smoothness, color uniformity, etc., while the unit flow rate refers to the amount of paint sprayed per unit time. Next, the first appearance quality and the first unit flow rate are weighted to obtain the first spraying quality. The weighted analysis is to give different weights to the appearance quality and unit flow rate according to the degree of influence on the spraying quality. In addition, in order to obtain a comprehensive spraying effect index, the spraying area and the spraying quality need to be normalized and analyzed using the coefficient of variation principle. The coefficient of variation is a statistic that measures the relative discreteness of data, which can help evaluate the stability and reliability of the spraying effect. Finally, the first spraying effect index obtained by analyzing the coefficient of variation principle can comprehensively reflect the efficiency and quality of the spraying scheme and provide a basis for selecting the optimal spraying control scheme.
[0054] In summary, this technical solution can analyze the spraying simulation data from two dimensions: spraying efficiency and spraying quality, and use the coefficient of variation principle to obtain a comprehensive spraying effect index. This helps to comprehensively evaluate the pros and cons of the spraying solution, especially in applications that need to balance spraying efficiency and quality, and can provide an important reference for selecting the optimal spraying control solution.
[0055] Furthermore, the present application includes:
[0056] The first hub surface is meshed in the three-dimensional hub model to obtain a first meshing result, wherein the first meshing result includes multiple meshes; a first rough spraying result of the first hub surface is obtained, wherein the first rough spraying result refers to the result after the first spray head sprays the first hub surface based on the first optimal spraying control scheme; a first unsprayed mesh set is obtained according to a first sprayed mesh set corresponding to the first spraying result traversed and matched among the multiple meshes; the second spray head sprays the first hub surface based on a first optimal spraying path generated by analyzing the first unsprayed mesh set, wherein a second spraying diameter of the second spray head is much smaller than the first spraying diameter of the first spray head.
[0057] First of all, the core of this technical solution is to achieve accurate spraying of the hub surface through meshing and analysis of spraying results. The first hub surface is meshed in the three-dimensional hub model, and then the first spraying is performed based on the first optimal spraying control scheme to obtain the first rough spraying result. Then, by analyzing the sprayed mesh set, the unsprayed mesh set is determined, and the second spray head is used to perform fine spraying on the unsprayed area based on the optimal spraying path. The spraying diameter of the second spray head is much smaller than that of the first spray head, which helps to improve the accuracy of spraying and the quality of the hub surface.
[0058] The specific implementation process is as follows: First, mesh the first hub surface in the three-dimensional hub model. Meshing is to divide the hub surface into multiple small areas for subsequent spraying analysis and control. Then, according to the first optimal spraying control scheme, the first hub surface is sprayed for the first time using the first spray head to obtain the first rough spraying result. The initial spraying usually covers most of the area, but there may be some small areas that are not sprayed or not sprayed enough. Next, by traversing the matching spraying results in the divided grid, the sprayed mesh set and the unsprayed mesh set are determined. The sprayed mesh set refers to the mesh that has been sprayed by the first spray head, while the unsprayed mesh set is the mesh that has not been covered by the initial spraying. In addition, the unsprayed mesh set is analyzed to generate the first optimal spraying path. This path is the basis for the second spray head to perform fine spraying, aiming to accurately cover the unsprayed area. Finally, the second spray head is used to perform fine spraying on the first hub surface along the generated optimal spraying path. Since the spraying diameter of the second spray head is much smaller than that of the first spray head, the spraying range and coating thickness can be controlled more accurately, thereby improving the spraying quality of the hub surface.
[0059] In summary, this technical solution can achieve accurate spraying of the hub surface through meshing and spraying result analysis. The unsprayed area is determined by the initial spraying, and a small diameter spray head is used for fine spraying, which can significantly improve the spraying quality and overall appearance of the hub surface.
[0060] Furthermore, the present application includes:
[0061] The first grid extracted from the first unsprayed grid set is used as the first sprayed grid; a first neighborhood grid of the first sprayed grid is obtained in the first unsprayed grid set, and the first neighborhood grid includes a plurality of neighborhood grids; a first distance from a first neighborhood grid to the first sprayed grid and a second distance from a second neighborhood grid to the first sprayed grid are obtained in sequence from the plurality of neighborhood grids; a second sprayed grid is determined by comparing the first distance and the second distance, and the first optimal spraying path is obtained in combination with the first sprayed grid.
[0062] First, the goal of this technical solution is to determine the optimal spraying path so that the unsprayed area of the first hub surface can be finely sprayed using the second spray head. The optimal spraying path is constructed by taking the first grid in the unsprayed grid set as the starting spraying grid and comparing the distance in its neighboring grids to determine the next spraying grid.
[0063] The specific implementation process is as follows: First, extract the first grid from the unsprayed grid set as the first spraying grid. This is the starting point for fine spraying. Then, obtain the neighborhood grid of the first spraying grid in the first unsprayed grid set. Neighboring grids refer to grids that are directly adjacent to the first spraying grid, and they are the key to spraying path planning. Next, obtain the distance between each grid in the neighborhood grid and the first spraying grid in turn. This includes the first distance from the first neighborhood grid to the first spraying grid, and the second distance from the second neighborhood grid to the first spraying grid. This distance information is used to determine the next spraying grid. Then, compare the first distance and the second distance to determine the second spraying grid. Usually, the neighborhood grid closest to the first spraying grid is selected as the second spraying grid. In addition, the first spraying grid and the second spraying grid are combined, and this process is continued until all unsprayed grids are covered, thereby constructing the first optimal spraying path. Finally, the second spray head is used to finely spray the first hub surface along the first optimal spraying path to ensure accurate coverage of the unsprayed area.
[0064] In summary, this technical solution can determine the optimal spraying path by comparing the distances of the neighborhood grids, thereby achieving precise spraying of the unsprayed areas on the hub surface.
[0065] Furthermore, the present application includes:
[0066] Determine a second spraying posture according to the first grid posture of the first spraying grid; read a predetermined spraying control scheme; the second spray head sprays the first hub surface according to the first optimal spraying path and based on the predetermined spraying control scheme in the second spraying posture.
[0067] First of all, the core of this technical solution is to determine the second spraying posture and finely spray the first hub surface according to the predetermined spraying control scheme and the optimal spraying path. By determining the second spraying posture according to the posture of the first spraying grid and reading the predetermined spraying control scheme, the solution aims to achieve high precision and uniformity of the hub surface spraying.
[0068] The specific implementation process is as follows: First, determine the second spraying posture according to the posture of the first spraying grid. The posture of the first spraying grid refers to its specific position and direction in the three-dimensional hub model, and the second spraying posture is calculated based on this posture to ensure that the spray head can accurately align with the spraying area. Then, read the predetermined spraying control scheme. Next, under the second spraying posture, the second spray head sprays the first hub surface according to the first optimal spraying path. The optimal spraying path is determined based on the distance analysis of the unsprayed grid set and the neighborhood grid, aiming to ensure the uniformity and accuracy of the spraying. In addition, during the spraying process, the second spray head automatically adjusts the spraying parameters according to the predetermined spraying control scheme to adapt to different spraying requirements. Finally, after completing the fine spraying of the first hub surface, quality inspection and necessary follow-up processing are carried out to ensure that the coating is fully adhered and achieves the expected performance.
[0069] In summary, this technical solution can determine the second spraying posture according to the posture of the first spraying grid, and perform fine spraying on the first hub surface according to a predetermined spraying control scheme and an optimal spraying path.
[0070] Furthermore, the present application includes:
[0071] Obtain a second predetermined spray control indicator of the second spray head, the second predetermined spray control indicator including a second spray pressure and a second nozzle diameter, the second spray pressure having a second pressure limit, and the second nozzle diameter having a second diameter limit; extract the second pressure value in the second pressure limit, and combine it with the second diameter value in the second diameter limit to form a second spray scheme; analyze the second spray simulation data of the second spray scheme to obtain a second unit flow rate; when the deviation between the second unit flow rate and the first unit flow rate is less than the deviation limit, record the second spray scheme as the predetermined spray control scheme.
[0072] First of all, the core of this technical solution is to determine a predetermined spray control scheme that meets the quality requirements by analyzing and adjusting the predetermined spray control indicators of the second spray head. This involves the selection of the second spray pressure and nozzle diameter, as well as the analysis of the spray simulation data to obtain the best spray scheme.
[0073] The specific implementation process is as follows: First, obtain the second predetermined spray control index of the second spray head, including the second spray pressure and the second nozzle diameter. These indicators each have a corresponding limit range, namely the second pressure limit and the second diameter limit. Then, select a pressure value from the second pressure limit, and combine it with a diameter value in the second diameter limit to form a second spray scheme. This scheme will be used for spray simulation analysis. Next, analyze the simulation data of the second spray scheme to obtain the second unit flow rate. Unit flow rate refers to the amount of paint sprayed per unit time, which is an important indicator for evaluating the spray scheme. Finally, compare the second unit flow rate with the first unit flow rate. If their deviation is less than the predetermined deviation limit, the second spray scheme is recorded as a predetermined spray control scheme. This means that the second spray scheme meets the quality requirements and can be used in the actual spray process.
[0074] In summary, this technical solution can determine a predetermined spraying control scheme that meets quality requirements by analyzing and adjusting the predetermined spraying control index of the second spraying head.
[0075] In summary, the method for optimizing the surface spraying process of automobile hub decoration parts provided in this application has the following technical effects:
[0076] This application constructs a three-dimensional hub model by collecting the dimensional feature information of the hub decoration, and uses this model to optimize the spraying process. The main technical goal is to achieve accurate spraying on the hub surface and ensure the spraying effect and quality. First, a three-dimensional hub model is constructed based on the collected hub structure dimensional feature information of the hub decoration. Then, the first structural posture of the first hub surface in the three-dimensional hub model is obtained, and the first spraying posture is obtained in combination with the spraying distance limit. This posture refers to the position and posture of the first spray head spraying the first hub surface. Next, the first spraying posture is used as the spraying optimization constraint, and the spraying effect is used as the spraying optimization evaluation index. The global optimization is performed in the spraying optimization space established based on the first predetermined spraying control index to obtain the first optimal spraying control scheme for the first spray head to spray the first hub surface. Next, the second hub surface in the three-dimensional hub model is obtained, and the hub surface has a posture adjacency relationship with the first hub surface. Then, the first optimal spraying control scheme is adjusted in combination with the second structural posture of the second hub surface to obtain the second optimal spraying control scheme. Finally, the second hub surface is subjected to surface spraying control according to the second optimal spraying control scheme. The present application can realize accurate spraying of the hub surface, improve the spraying effect and quality, and in addition, the spraying process is more automated and accurate, reduces human errors, and improves production efficiency and product quality.
[0077] The above description of the disclosed embodiments enables those skilled in the art to implement or use the present application. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present application. Therefore, the present application will not be limited to the embodiments shown herein, but will conform to the widest scope consistent with the principles and novel features disclosed herein.
[0078] Obviously, those skilled in the art can make various changes and modifications to the present application without departing from the spirit and scope of the present application. Thus, if these modifications and variations of the present application belong to the scope of the present application and its equivalent technology, the present application is also intended to include these modifications and variations.
Claims
1. A method for optimizing the surface spraying process of automobile wheel hub decoration parts, characterized in that: include: Constructing a three-dimensional wheel hub model based on the collected wheel hub structure size feature information of the wheel hub decoration; Acquire a first structural posture of a first hub surface in the three-dimensional hub model, and obtain a first spraying posture in combination with a spraying distance limit, wherein the first spraying posture refers to a position posture of a first spray head spraying the first hub surface; Taking the first spraying posture as a spraying optimization constraint and the spraying effect as a spraying optimization evaluation index, a first optimal spraying control scheme for spraying the first hub surface by the first spray head is obtained by global optimization in a spraying optimization space established based on a first predetermined spraying control index; Acquire a second hub surface in the three-dimensional hub model, wherein the second hub surface and the first hub surface have a posture adjacency relationship; The first optimal spraying control scheme is adjusted in combination with the second structural position of the second hub surface to obtain a second optimal spraying control scheme; Performing surface spraying control on the second hub surface according to the second optimal spraying control scheme; Wherein, the method comprises: Randomly extracting a first spraying scheme in the spraying optimization space; Analyzing first spraying simulation data of the first spraying scheme to obtain a first spraying effect index; Comparing the first spraying effect index with the second spraying effect index of the second spraying scheme in the spraying optimization space to obtain a comparison result; Determine the first optimal spraying control scheme according to the comparison result; Wherein, the method comprises: Based on the spraying efficiency dimension, extracting a first spraying area in the first spraying simulation data; Based on the spraying quality dimension, extracting the first appearance quality and the first unit flow rate in the first spraying simulation data, and performing weighted analysis to obtain the first spraying quality; Analyzing the first spraying area and the first spraying quality after normalization using the coefficient of variation principle to obtain the first spraying effect index; Wherein, the method further comprises: Meshing the first hub surface in the three-dimensional hub model to obtain a first meshing result, wherein the first meshing result includes a plurality of meshes; Acquire a first rough spray result of the first hub surface, where the first rough spray result refers to a result after the first spray head sprays the first hub surface based on the first optimal spray control scheme; Obtaining a first unsprayed grid set according to a first sprayed grid set corresponding to a first spraying result traversed and matched among the plurality of grids; The second spray head sprays the first hub surface based on a first optimal spray path generated by analyzing the first unsprayed grid set, wherein a second spray diameter of the second spray head is much smaller than a first spray diameter of the first spray head; Wherein, the method comprises: Using the first mesh extracted from the first unsprayed mesh set as the first sprayed mesh; Acquire a first neighborhood grid of the first sprayed grid in the first unsprayed grid set, wherein the first neighborhood grid includes a plurality of neighborhood grids; Sequentially acquiring a first distance from a first neighborhood grid to the first spraying grid and a second distance from a second neighborhood grid to the first spraying grid among the plurality of neighborhood grids; Determine a second spraying grid by comparing the first distance and the second distance, and obtain the first optimal spraying path by combining the first spraying grid; Wherein, the method further comprises: Determining a second spraying posture according to a first grid posture of the first spraying grid; Read the predetermined spraying control plan; The second spray head sprays the first hub surface in the second spraying posture according to the first optimal spraying path and based on the predetermined spraying control scheme; Wherein, the method comprises: Acquire a second predetermined spraying control index of the second spraying head, wherein the second predetermined spraying control index includes a second spraying pressure and a second nozzle diameter, wherein the second spraying pressure has a second pressure limit value, and the second nozzle diameter has a second diameter limit value; Extracting a second pressure value in the second pressure limit, and combining it with a second diameter value in the second diameter limit to form a second spraying scheme; Analyze the second spraying simulation data of the second spraying scheme to obtain a second unit flow rate; When the deviation between the second unit flow rate and the first unit flow rate is less than a deviation limit, the second spraying scheme is recorded as the predetermined spraying control scheme.
2. The method according to claim 1, characterized in that: The method comprises: The first predetermined spraying control index includes a first spraying pressure and a first nozzle diameter, the first spraying pressure has a first pressure limit, and the first nozzle diameter has a first diameter limit; The first spray plan is constructed based on a first pressure value in the first pressure limits and a first diameter value in the first diameter limits.