A sluice station operation management system for water conservancy projects

By comprehensively analyzing the water pressure, water flow rate and water level data and adjusting the PID controller, the problem that a single data cannot support the operation and management of the gate station is solved, the efficiency and safety of the operation of the gate station is improved, and highly automated management is achieved.

CN118707840BActive Publication Date: 2024-11-08ZHONGCHENG TEST TECH (DALIAN) CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411194504.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-29
Publication Date
2024-11-08
Estimated Expiration
2044-08-29

AI Technical Summary

Technical Problem

The existing technology cannot accurately predict and make decisions through single data, affecting the efficiency and safety of gate station operation, resulting in the inability to achieve highly automated gate station operation management.

Method used

The data acquisition module is used to obtain water pressure, water flow rate and water level data, adjust the initial water pressure abnormal parameters through the abnormality analysis module, adjust the analysis module to predict the gate opening, and adjust the PID controller in response to the adjustment module to realize real-time control of the operation of the gate station.

Benefits of technology

Through comprehensive analysis of multiple data sources, the impact of water flow velocity on water pressure abnormality analysis is eliminated, accurate control of gate opening, improve the efficiency and safety of gate station operation, and realize highly automated operation management and decision-making support.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118707840B_ABST
    Figure CN118707840B_ABST
Patent Text Reader

Abstract

The present invention relates to the field of gate station operation control, and specifically to a gate station operation management system for water conservancy projects. The system first obtains the water pressure data and water flow rate data in each pipeline of the gate station to be tested at each moment in a preset time period, and obtains the water level data and water flow rate data of the gate station to be tested at each moment in the preset time period, and obtains the real water pressure abnormality parameters of the gate station to be tested according to the fluctuation difference of the water pressure data between different pipelines and the correlation between the water pressure data and the water flow rate data of the pipeline; predicts the opening of the gate, and adjusts the proportional gain coefficient in the PID controller of the gate station to be tested according to the difference between the expected opening and the actual opening of the gate and the real water pressure abnormality parameters, and uses the adjusted PID controller to control the operation of the gate station to be tested. The present invention can improve the efficiency and safety of the gate station operation and realize highly automated operation management of the gate station.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of gate station operation control, and in particular to a gate station operation management system for water conservancy projects. Background Art

[0002] In water conservancy projects, sluice stations are important facilities for controlling water flow. Timely and effective control and management of the operation of sluice stations can not only improve the efficiency of water resource utilization, but also avoid the occurrence of emergencies such as floods. Therefore, effective control and management of sluice station operation is of great significance to water conservancy projects.

[0003] In related technologies, single data, such as water flow data, is usually used to control and manage the operation of the gate station. However, since a single data cannot fully and accurately reflect the water flow and environmental conditions of the gate station, the existing methods cannot provide accurate prediction and decision support, which affects the efficiency and safety of the gate station operation, and thus it is impossible to achieve highly automated operation and management of the gate station. Summary of the invention

[0004] In order to solve the technical problem that the existing methods cannot provide accurate prediction and decision support, affect the efficiency and safety of gate station operation, and thus cannot achieve highly automated operation and management of gate stations, the purpose of the present invention is to provide a gate station operation management system for water conservancy projects, and the technical solutions adopted are as follows:

[0005] The present invention proposes a sluice station operation management system for a water conservancy project, the system comprising:

[0006] A data acquisition module is used to obtain water pressure data and water flow rate data in each pipeline of the gate station to be tested at each moment in a preset time period, and simultaneously obtain water level data and water flow data of the gate station to be tested at each moment in the preset time period;

[0007] The abnormality analysis module is used to obtain the initial abnormal water pressure parameters of the gate station to be tested according to the fluctuation difference of the water pressure data at different times between different pipelines; analyze the correlation between the water pressure data and the water flow rate data at each time of each pipeline, and adjust the initial abnormal water pressure parameters to obtain the real abnormal water pressure parameters of the gate station to be tested;

[0008] The adjustment analysis module is used to obtain the expected opening of the gate of the gate station to be tested according to the change of water level data and the distribution of water flow data of the gate station to be tested within a preset time period; and obtain the adjustment parameters of the gate station to be tested according to the difference between the expected opening of the gate station to be tested and the preset actual opening, as well as the actual water pressure abnormality parameters of the gate station to be tested;

[0009] The response adjustment module is used to adjust the proportional gain coefficient in the PID controller of the gate station to be tested based on the adjustment parameters of the gate station to be tested, obtain the adjusted PID controller, and use the adjusted PID controller to regulate the operation of the gate station to be tested.

[0010] Furthermore, obtaining the initial water pressure anomaly parameters of the gate station to be tested according to the fluctuation difference of the water pressure data at different times between different pipelines includes:

[0011] According to the difference of water pressure data of each pipeline at each time and the distribution of water pressure data at all times in a preset time period, the water pressure characteristic value of each pipeline is obtained;

[0012] Taking any two pipelines as a pipeline group, and obtaining a water pressure characteristic difference value of each pipeline group according to the difference of the water pressure characteristic values ​​of the two pipelines in each pipeline group;

[0013] The overall level of the water pressure characteristic difference values ​​of all pipeline groups is analyzed to obtain the initial water pressure anomaly parameters of the gate station to be tested.

[0014] Furthermore, obtaining the water pressure characteristic value of each pipeline according to the difference of water pressure data of each pipeline at each time and the distribution of water pressure data at all times within a preset time period includes:

[0015] Taking any pipeline as the target pipeline, analyzing the overall level of water pressure data of the target pipeline at all times within a preset time period to obtain the overall water pressure value of the target pipeline;

[0016] Take any two moments as a moment group, and obtain the water pressure difference value of the target pipeline in each moment group according to the difference of the water pressure data of the target pipeline at two moments in each moment group;

[0017] Analyze the overall level of the water pressure difference values ​​of the target pipeline in all time groups to obtain the water pressure fluctuation degree of the target pipeline;

[0018] The overall water pressure value and the water pressure fluctuation degree are integrated to obtain a water pressure characteristic value of the target pipeline.

[0019] Furthermore, the correlation between the water pressure data and the water flow rate data of each pipeline at each moment is analyzed, and the initial water pressure anomaly parameter is adjusted to obtain the real water pressure anomaly parameter of the gate station to be tested, including:

[0020] The absolute value of the Pearson correlation coefficient between the water pressure data and the water flow rate data of each pipeline at each moment is negatively correlated and mapped as the non-correlation parameter of each pipeline;

[0021] Analyze the overall level of the non-correlated parameters of all pipelines to obtain the abnormal weight value of the gate station to be tested;

[0022] The initial water pressure anomaly parameter of the gate station to be measured is weighted by using the anomaly weight value to obtain the real water pressure anomaly parameter of the gate station to be measured.

[0023] Further, obtaining the expected opening of the gate of the gate station to be tested according to the change of water level data and the distribution of water flow data of the gate station to be tested within a preset time period includes:

[0024] According to the change of water level data and the distribution of water flow data of the gate of the gate station to be tested within a preset time period, the opening degree of the gate station to be tested is obtained;

[0025] The preset maximum opening of the gate of the gate station to be tested is weighted by utilizing the opening degree to obtain the expected opening of the gate of the gate station to be tested.

[0026] Furthermore, obtaining the degree of opening of the gate of the gate station to be tested according to the change of water level data and the distribution of water flow data of the gate station to be tested within a preset time period includes:

[0027] The absolute value of the difference between the water level data of the gate station to be tested between the initial time and the end time of the preset time period is used as the numerator, the length of the preset time period is used as the denominator, and the ratio is used as the water level change rate of the gate station to be tested;

[0028] The water level data of the gate station to be tested at the end time of the preset time period is used as the numerator, the preset water level threshold of the gate station to be tested is used as the denominator, and the ratio is used as the water level proximity of the gate station to be tested;

[0029] The water level change rate and the water level proximity are combined to obtain the water level danger level of the gate station to be tested;

[0030] After analyzing the overall level of water flow data of the gate station to be tested at all times during a preset time period and performing negative correlation mapping, the water flow demand value of the gate station to be tested is obtained;

[0031] The water level danger level and the water flow demand value are integrated and normalized to obtain the opening degree of the gate of the gate station to be tested.

[0032] Furthermore, the obtaining of the adjustment parameters of the gate station to be tested according to the difference between the expected opening and the preset actual opening of the gate station to be tested, and the real water pressure abnormality parameter of the gate station to be tested includes:

[0033] The absolute value of the difference between the expected opening of the gate of the gate station to be tested and the preset actual opening is used as the opening error value of the gate of the gate station to be tested;

[0034] The opening error value of the gate of the gate station to be tested and the actual water pressure abnormality parameter of the gate station to be tested are integrated and normalized to obtain the adjustment parameters of the gate station to be tested.

[0035] Further, the proportional gain coefficient in the PID controller of the gate station to be tested is adjusted based on the adjustment parameter of the gate station to be tested, and obtaining the adjusted PID controller includes:

[0036] The product value of the adjustment parameter of the gate station to be tested and the proportional gain coefficient in the PID controller is used as the adjustment amount;

[0037] The sum of the proportional gain coefficient in the PID controller and the adjustment amount is used as the adjustment proportional gain coefficient, and the PID controller using the adjustment proportional gain coefficient is used as the adjustment PID controller.

[0038] Furthermore, the overall level of the water pressure characteristic difference values ​​of all pipeline groups is analyzed to obtain the initial water pressure anomaly parameters of the gate station to be tested, including:

[0039] The average value of the water pressure characteristic difference values ​​of all pipeline groups is used as the initial water pressure anomaly parameter of the gate station to be tested.

[0040] Furthermore, analyzing the overall level of water pressure data of the target pipeline at all times within a preset time period to obtain the overall water pressure value of the target pipeline includes:

[0041] The average value of the water pressure data of the target pipeline at all times within the preset time period is taken as the overall water pressure value of the target pipeline.

[0042] The present invention has the following beneficial effects:

[0043] The present invention takes into account that the existing methods cannot provide accurate prediction and decision support through single data, which affects the efficiency and safety of the gate station operation, and thus cannot achieve highly automated operation management of the gate station. Therefore, the present invention first obtains the water pressure data and water flow rate data of each pipeline of the gate station to be tested at each moment in the preset time period, and simultaneously obtains the water level data and water flow rate data of the gate station to be tested at each moment in the preset time period. In the operation management of the gate station, it is necessary to keep the water pressure in each pipeline stable to ensure the safe operation of the gate station. Therefore, the possibility of water pressure abnormality in the pipeline of the gate station to be tested is preliminarily reflected by the initial water pressure abnormality parameter. Considering that the change of the water flow rate in the pipeline will also cause The water pressure changes, so the correlation between the water pressure data and the water flow rate data of each pipeline at each moment can be analyzed, and the initial water pressure anomaly parameters can be adjusted to eliminate the influence of the water flow rate on the pipeline water pressure anomaly analysis. In the gate station management, it is necessary to control the gate opening in a timely and accurate manner. Therefore, the present invention first accurately predicts the gate opening, and then based on the error between the expected opening and the actual opening and the real water pressure anomaly parameters, obtains the adjustment parameters of the gate station to be tested, and uses the adjusted PID controller to enable the gate station to respond to various events in a timely manner, thereby improving the efficiency and safety of the gate station operation, and realizing highly automated operation management and decision support of the gate station. BRIEF DESCRIPTION OF THE DRAWINGS

[0044] In order to more clearly illustrate the technical solutions and advantages in the embodiments of the present invention or the prior art, the drawings required for use in the embodiments or the prior art descriptions are briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0045] Figure 1 A block diagram of a sluice station operation management system for a water conservancy project provided by one embodiment of the present invention;

[0046] Figure 2 A flow chart of a method for obtaining abnormal initial water pressure parameters of a gate station to be tested provided by one embodiment of the present invention;

[0047] Figure 3 A flow chart of a method for obtaining the expected opening of a gate at a gate station to be tested provided in one embodiment of the present invention. DETAILED DESCRIPTION

[0048] In order to further explain the technical means and effects adopted by the present invention to achieve the predetermined invention purpose, the following is a detailed description of the specific implementation method, structure, features and effects of a sluice station operation management system for water conservancy projects proposed by the present invention in combination with the accompanying drawings and preferred embodiments. In the following description, different "one embodiment" or "another embodiment" does not necessarily refer to the same embodiment. In addition, specific features, structures or characteristics in one or more embodiments may be combined in any suitable form.

[0049] Unless defined otherwise, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this invention belongs.

[0050] The following is a detailed description of a specific solution of a sluice station operation management system for a water conservancy project provided by the present invention in conjunction with the accompanying drawings.

[0051] See also Figure 1 , which shows a block diagram of a sluice station operation management system for a water conservancy project provided by an embodiment of the present invention. The system includes: a data acquisition module 101, an abnormality analysis module 102, a regulation analysis module 103, and a response regulation module 104.

[0052] The data acquisition module 101 is used to obtain the water pressure data and water flow rate data in each pipeline of the gate station to be tested at each moment in a preset time period, and simultaneously obtain the water level data and water flow rate data of the gate station to be tested at each moment in the preset time period.

[0053] A plurality of pipelines are usually deployed in the sluice station of a water conservancy project to control and adjust the direction and speed of water flow to ensure the safe operation of the project and the effective use of water resources. Since the pipeline may be blocked or leaked, the operation of the sluice station may be abnormal, and the blockage or leakage of the pipeline may cause the water pressure in the pipeline to be abnormal. Therefore, in an embodiment of the present invention, a pressure sensor is first installed in each pipeline of the sluice station to be tested, and the pressure sensor is used to collect the water pressure data of each pipeline at each moment in a preset time period. At the same time, a flow rate sensor is installed in each pipeline, and the flow rate sensor is used to collect the water flow rate data of each pipeline at each moment in the preset time period, so as to provide a data basis for the subsequent calculation and analysis of the abnormal water pressure of the pipeline.

[0054] The key part of a water conservancy project sluice station is the gate, which controls the water flow and adjusts the flow and water level upstream and downstream. Therefore, in the operation control of the sluice station of the water conservancy project, the key is to control the gate opening. By accurately adjusting the gate opening, the water flow and water level can be finely controlled, which is extremely important for water resource management, flood and drought prevention, ecological protection, etc. Therefore, in an embodiment of the present invention, a water level sensor is installed near the sluice station to be tested, and the water level data at each moment in a preset time period is collected through the water level sensor. At the same time, a flow sensor is installed downstream of the sluice station, and the water flow data at each moment in the preset time period is collected through the flow sensor.

[0055] The data collection time intervals of various sensors are the same. In one embodiment of the present invention, the data collection time interval is set to 1 second. The specific value of the time interval can also be set by the implementer according to the specific implementation scenario and is not limited here. The value range of the preset time period is , in hours. In one embodiment of the present invention, the length of the preset time period is set to 1 hour. The specific value of the preset time period can also be set by the implementer according to the specific implementation scenario, which is not limited here.

[0056] The abnormality analysis module 102 is used to obtain the initial water pressure abnormality parameters of the gate station to be tested according to the fluctuation difference of the water pressure data at each moment between different pipelines; analyze the correlation between the water pressure data and the water flow rate data at each moment of each pipeline, and adjust the initial water pressure abnormality parameters to obtain the real water pressure abnormality parameters of the gate station to be tested.

[0057] In the operation and management of the gate station, it is necessary to ensure that the water pressure in each pipeline remains stable to ensure the safe operation of the gate station. Under normal circumstances, the water pressure fluctuations in different pipelines of the gate station to be tested are similar during the preset time period. When abnormal conditions such as blockage or leakage occur in the pipeline, the water pressure fluctuations in each pipeline will be different. Therefore, the fluctuation differences in the water pressure data at different times between different pipelines can be analyzed. The initial water pressure anomaly parameters obtained can be used to preliminarily reflect the possibility of water pressure anomalies in the pipeline system of the gate station to be tested. The initial water pressure anomaly parameters can be further adjusted later to accurately reflect the water pressure anomalies in the pipeline system of the gate station to be tested.

[0058] Preferably, in one embodiment of the present invention, the method for obtaining the initial water pressure abnormality parameters of the gate station to be tested specifically includes:

[0059] See also Figure 2 , which shows a flow chart of a method for obtaining initial water pressure abnormality parameters of a gate station to be tested provided by an embodiment of the present invention.

[0060] Step S201: obtaining a water pressure characteristic value of each pipeline according to the difference of water pressure data of each pipeline at each moment and the distribution of water pressure data at all moments in a preset time period.

[0061] First, it is necessary to analyze the water pressure change characteristics and the overall distribution of water pressure in each pipeline. By analyzing the water pressure characteristics in each pipeline, the difference in water pressure data at each moment in each pipeline and the distribution of water pressure data at all moments in a preset time period can be analyzed. The obtained water pressure characteristic values ​​reflect the fluctuation characteristics and overall distribution characteristics of the water pressure data in each pipeline, providing a data basis for the subsequent analysis of the abnormal water pressure situation in the pipeline system of the gate station to be tested.

[0062] Preferably, in one embodiment of the present invention, the method for obtaining the water pressure characteristic value of each pipeline specifically includes:

[0063] Take any pipeline as the target pipeline, analyze the overall level of water pressure data of the target pipeline at all times within a preset time period, and obtain the overall water pressure value of the target pipeline. The larger the overall water pressure value, the greater the water pressure of the target pipeline within the preset time period.

[0064] In an embodiment of the present invention, the average value or median of the water pressure data of the target pipeline at all times within a preset time period can be used as the overall water pressure value of the target pipeline to achieve an overall level analysis of the water pressure data of the target pipeline at all times within the preset time period, which is not limited here.

[0065] Take any two moments as a moment group, and obtain the water pressure difference value of the target pipeline in each moment group according to the difference in water pressure data of the target pipeline at two moments in each moment group. The larger the water pressure difference value, the greater the water pressure difference between any two moments in the target pipeline.

[0066] In one embodiment of the present invention, the absolute value of the difference between the water pressure data of the target pipeline at two moments in each moment group may be used as the water pressure difference value of the target pipeline in each moment group to analyze the difference between the two.

[0067] The overall level of the water pressure difference values ​​of the target pipeline in all time groups is analyzed to obtain the water pressure fluctuation degree of the target pipeline. The greater the water pressure fluctuation degree, the more obvious the water pressure fluctuation of the target pipeline within the preset time period.

[0068] In an embodiment of the present invention, the average or median of the water pressure difference values ​​of the target pipeline in all time groups can be used as the water pressure fluctuation degree of the target pipeline to achieve the overall level analysis of the water pressure difference values ​​of the target pipeline in all time groups, which is not limited here.

[0069] The overall water pressure value and the degree of water pressure fluctuation are combined to obtain the water pressure characteristic value of the target pipeline. The larger the water pressure characteristic value, the greater the water pressure in the target pipeline is in general and the more obvious the fluctuation is during the preset time period.

[0070] In the embodiment of the present invention, the product value or the sum value of the overall water pressure value and the water pressure fluctuation degree may be used as the water pressure characteristic value of the target pipeline to achieve a combination of the two, which is not limited here.

[0071] As an example, in one embodiment of the present invention, the expression of the water pressure characteristic value of each pipeline can be specifically, for example, as follows:

[0072]

[0073] in, Indicates the water pressure characteristic value of the target pipeline; Indicates the overall water pressure value of the target pipeline; and Respectively represent the target pipeline in Water pressure data at two moments in a moment group; Indicates that the target pipeline is in The water pressure difference value of each time group; Indicates the number of moment groups; Indicates the degree of water pressure fluctuation in the target pipeline.

[0074] The water pressure characteristic value of each pipeline can be obtained by the same method as above.

[0075] Step S202: Take any two pipelines as a pipeline group, and obtain the water pressure characteristic difference value of each pipeline group according to the difference in the water pressure characteristic values ​​of the two pipelines in each pipeline group; analyze the overall level of the water pressure characteristic difference values ​​of all pipeline groups to obtain the initial water pressure anomaly parameters of the gate station to be tested.

[0076] From the above analysis, it can be seen that the greater the difference in water pressure fluctuations and overall distribution between pipelines, the more likely it is that the pipeline system of the gate station to be tested will have an abnormal situation. Therefore, any two pipelines can be first regarded as a pipeline group, and the water pressure characteristic difference value of each pipeline group can be obtained according to the difference in the water pressure characteristic values ​​of the two pipelines in each pipeline group. The larger the water pressure characteristic difference value, the greater the difference in the water pressure characteristics of the two pipelines in the pipeline group. Then, the overall level of the water pressure characteristic difference values ​​of all pipeline groups is analyzed to obtain the initial water pressure abnormality parameters of the gate station to be tested. The larger the initial water pressure abnormality parameters, the greater the possibility of abnormality in the pipeline system of the gate station to be tested.

[0077] In one embodiment of the present invention, the absolute value of the difference between the water pressure characteristic values ​​of two pipes in each pipe group may be used as the water pressure characteristic difference value of each pipe group to analyze the difference between the two.

[0078] In an embodiment of the present invention, the average or median of the water pressure characteristic difference values ​​of all pipeline groups can be used as the initial water pressure anomaly parameter of the gate station to be tested to achieve an overall level analysis of the water pressure characteristic difference values ​​of all pipeline groups, which is not limited here.

[0079] As an example, in one embodiment of the present invention, the expression of the initial water pressure abnormality parameter of the gate station to be tested can be specifically, for example, as follows:

[0080]

[0081] in, Indicates the initial water pressure abnormality parameter of the gate station to be tested; and Respectively represent The water pressure characteristic values ​​of two pipes in a pipe group; Indicates the number of pipeline groups; Indicates The water pressure characteristic difference value of each pipeline group.

[0082] The fluid mechanics effect caused by the change of water flow velocity in the pipeline will also cause the water pressure in the pipeline to change. This change of water pressure in the pipeline caused by the water flow velocity is a normal phenomenon. Therefore, the initial water pressure anomaly parameters obtained above cannot accurately reflect the possibility of abnormal conditions such as blockage or leakage in the pipeline system of the gate station to be tested. Further analysis is required in combination with the water flow velocity data of the pipeline. First, the correlation between the water pressure data and the water flow velocity data of each pipeline at each moment is analyzed. The weaker the correlation between the water pressure data and the water flow data, the lower the possibility that the water pressure change in the pipeline is caused by the water flow velocity, and the higher the confidence that the pipeline system has an abnormal condition. Therefore, the initial water pressure anomaly parameters of the gate station to be tested can be further adjusted. The actual water pressure anomaly parameters obtained can accurately reflect the possibility of water pressure anomaly in the pipeline system of the gate station to be tested, thereby eliminating the influence of water flow velocity on pipeline water pressure anomaly analysis, and subsequently the operation of the gate station to be tested is regulated based on the actual water pressure anomaly parameters.

[0083] Preferably, in one embodiment of the present invention, the method for obtaining the real abnormal water pressure parameters of the gate station to be tested specifically includes:

[0084] The absolute value of the Pearson correlation coefficient between the water pressure data and the water flow rate data of each pipeline at each moment is negatively correlated and mapped as the non-correlation parameter of each pipeline. The larger the non-correlation parameter is, the weaker the correlation between the water pressure data and the water flow rate data of each pipeline is.

[0085] Since the value range of the Pearson correlation coefficient is , and the closer the absolute value of the Pearson correlation coefficient is to the value 1, the stronger the correlation is. Therefore, in other embodiments of the present invention, the difference between the Pearson correlation coefficient between the value 1 and the water pressure data and the water flow rate data of each pipeline at each moment can also be used as the non-correlation parameter of each pipeline.

[0086] The overall level of non-correlated parameters of all pipelines is analyzed to obtain the abnormal weight value of the gate station to be tested. The larger the abnormal weight value, the greater the confidence that the pipeline system of the gate station to be tested has an abnormality.

[0087] In the embodiment of the present invention, the average value or median of the non-correlation parameters of all pipelines can be used as the abnormal weight value of the gate station to be tested to achieve the overall level analysis of the non-correlation parameters of all pipelines, which is not limited here.

[0088] Then, the abnormal weight value can be used to weight the initial abnormal water pressure parameters of the gate station to be tested, so as to obtain the real abnormal water pressure parameters of the gate station to be tested.

[0089] As an example, in one embodiment of the present invention, the expression of the actual water pressure abnormality parameter of the gate station to be tested can be specifically, for example, as follows:

[0090]

[0091] in, Indicates the actual abnormal water pressure parameters of the gate station to be tested; Indicates the initial water pressure abnormality parameter of the gate station to be tested; Indicates Pearson correlation coefficient between water pressure data and water flow rate data of each pipeline; Indicates the preset first adjustment parameter, which is used to prevent the denominator from being 0. The value range is In one embodiment of the present invention, Set to 1, The specific value of can also be set by the implementer according to the specific implementation scenario and is not limited here; Indicates Non-correlated parameters of the pipeline; Indicates the abnormal weight value of the gate station to be tested; Indicates the number of pipelines in the gate station to be tested.

[0092] It should be noted that in other embodiments of the present invention, the positive and negative correlations may be represented by other basic mathematical operations, which will not be elaborated herein.

[0093] The regulation analysis module 103 is used to obtain the expected opening of the gate of the gate station to be tested based on the changes in the water level data and the distribution of the water flow data of the gate station to be tested within a preset time period; and to obtain the regulation parameters of the gate station to be tested based on the difference between the expected opening of the gate of the gate station to be tested and the preset actual opening, as well as the actual water pressure abnormality parameters of the gate station to be tested.

[0094] In the management of gate stations, it is necessary to control the opening of the gate in a timely and accurate manner. By accurately adjusting the opening of the gate, the water flow and water level can be carefully controlled to improve the efficiency of water resource utilization or prevent the occurrence of disasters such as sudden floods. Therefore, the embodiment of the present invention first predicts the opening of the gate of the gate station to be tested based on the changes in water level data and the distribution of water flow data of the gate station to be tested within a preset time period, and obtains the expected opening of the gate of the gate station to be tested. Subsequently, the error between the expected opening and the actual opening of the gate can be analyzed. At the same time, combined with the actual water pressure abnormality parameters obtained above, the operation of the gate station to be tested is adjusted and optimized, thereby improving the operation efficiency of the gate station to be tested and realizing highly automated operation management.

[0095] Preferably, in one embodiment of the present invention, the method for obtaining the expected opening of the gate of the gate station to be tested specifically includes:

[0096] See also Figure 3 , which shows a flow chart of a method for obtaining the expected opening of a gate of a gate station to be tested provided by an embodiment of the present invention.

[0097] Step S301: Obtain the opening degree of the gate of the gate station to be tested according to the change of water level data and the distribution of water flow data of the gate station to be tested within a preset time period.

[0098] Since the key factors affecting the opening of the gate of the sluice station to be tested are the water level changes and water flow conditions near the sluice station to be tested, for example, when the water level gradually rises and reaches the threshold, it is necessary to increase the gate opening so that the water flow can be discharged in time to prevent the occurrence of floods and waterlogging disasters. When the water flow downstream of the sluice station to be tested is small, it is also necessary to increase the opening of the sluice station gate to maintain the stability of the water flow and improve the utilization rate of water resources. Therefore, the changes in water level data and the distribution of water flow data of the sluice station to be tested within a preset time period can be analyzed, and the degree of opening obtained can be used to reflect the degree to which the gate of the sluice station to be tested needs to be opened, and the gate opening can be predicted based on the degree of opening.

[0099] Preferably, in one embodiment of the present invention, the method for obtaining the opening degree of the gate of the gate station to be tested specifically includes:

[0100] The absolute value of the difference in water level data between the initial moment and the end moment of the preset time period at the gate station to be tested is used as the numerator, the length of the preset time period is used as the denominator, and the ratio is used as the water level change rate of the gate station to be tested.

[0101] Among them, the unit of the length of the preset time period can be selected as minutes or seconds, which is not limited here. In one embodiment of the present invention, the unit of the length of the preset time period is set to minutes. That is, in one embodiment of the present invention, if the preset time period is 1 hour, the length of the preset time period here is 60.

[0102] The water level data of the gate station to be tested at the end time of the preset time period is used as the numerator, the preset water level threshold of the gate station to be tested is used as the denominator, and the ratio is used as the water level proximity of the gate station to be tested. The greater the water level proximity, the closer the water level is to the preset water level threshold, and thus the more dangerous the water level is.

[0103] In one embodiment of the present invention, the preset water level threshold is set to 2 meters. The preset water level threshold can also be set by the implementer according to the specific implementation scenario, which is not limited here.

[0104] The water level change rate and water level proximity are combined to obtain the water level danger level of the gate station to be tested. The greater the water level danger level, the faster the water level changes and the closer it is to the preset water level threshold. This means that the water level at the gate station to be tested is more dangerous and the gate opening needs to be increased.

[0105] In the embodiment of the present invention, the product value or the sum value of the water level change rate and the water level proximity can be used as the water level danger level of the gate station to be tested to achieve a combination of the two, which is not limited here.

[0106] After analyzing the overall level of water flow data of the gate station to be tested at all times in the preset time period and performing negative correlation mapping, the water flow demand value of the gate station to be tested is obtained. The larger the water flow demand value, the greater the demand for water flow downstream of the gate station to be tested, and the gate opening needs to be increased.

[0107] In an embodiment of the present invention, the overall level of water flow data of the gate station to be tested at all times in the preset time period can be analyzed by calculating the average value or median of the water flow data of the gate station to be tested at all times in the preset time period, which is not limited here.

[0108] The greater the water level danger level and the water flow demand value, the greater the need to increase the gate opening. Therefore, the water level danger level and the water flow demand value can be integrated and normalized to obtain the opening degree of the gate of the gate station to be tested.

[0109] In the embodiment of the present invention, the integration of the water level danger level and the water flow demand value can be achieved by calculating the product value or the sum value of the two, which is not limited here.

[0110] As an example, in one embodiment of the present invention, the expression of the opening degree of the gate of the gate station to be tested can be specifically, for example, as follows:

[0111]

[0112]

[0113] in, Indicates the degree of opening of the gate of the gate station to be tested; Indicates the danger level of the water level at the gate station to be tested; Indicates the average value of water flow data at all times of the gate station to be tested in a preset time period; Indicates the preset second adjustment parameter, which is used to prevent the denominator from being 0. The value range is In one embodiment of the present invention, Set to 0.01, The specific value of can also be set by the implementer according to the specific implementation scenario and is not limited here; Represents the water level data of the gate station to be tested at the initial moment of a preset time period; Indicates the water level data of the gate station to be tested at the end time of the preset time period; Indicates the preset water level threshold of the gate station to be tested; Indicates the water flow demand value of the gate station to be tested; Indicates the rate of change of water level at the gate station to be tested; Indicates the proximity of the water level of the sluice station to be measured; Represents the hyperbolic tangent function, which is used for normalization.

[0114] It should be noted that in other embodiments of the present invention, the positive and negative correlations may be represented by other basic mathematical operations, which will not be elaborated herein.

[0115] Step S302: using the opening degree, weighting the preset maximum opening of the gate of the gate station to be tested to obtain the expected opening of the gate of the gate station to be tested.

[0116] The greater the degree of opening of the gate of the gate station to be tested, the greater the required opening of the gate. Therefore, the degree of opening can be used to weight the preset maximum opening of the gate of the gate station to be tested, and the expected opening of the gate of the gate station to be tested can be obtained to predict the gate opening.

[0117] Among them, the value range of the preset maximum opening is , in meters. In one embodiment of the present invention, the preset maximum opening is set to 5 meters. The specific value of the preset maximum opening can also be set by the implementer according to the specific implementation scenario, which is not limited here.

[0118] As an example, in one embodiment of the present invention, the expression of the expected opening of the gate of the gate station to be tested can be specifically, for example, as follows:

[0119]

[0120] in, Indicates the expected opening of the gate of the gate station to be tested; Indicates the degree of opening of the gate of the gate station to be tested; Indicates the preset maximum opening of the gate of the gate station to be tested.

[0121] In the gate station operation system of the water conservancy project, the system itself will determine the actual opening of the gate through data analysis. When the difference between the expected opening and the actual opening obtained above is large, it means that the response error of the gate station operation system is large. At this time, it is necessary to adjust the response speed of the gate station operation system. At the same time, when the pipeline system of the gate station is abnormal, it is also necessary to adjust the response speed of the gate station operation system to cope with the occurrence of emergencies and improve the efficiency and safety of the gate station operation, so as to realize its highly automated operation management. Therefore, the adjustment parameters of the gate station to be tested can be obtained according to the difference between the expected opening of the gate of the gate station to be tested and the preset actual opening, as well as the actual water pressure abnormality parameters of the gate station to be tested. Subsequently, the operation of the gate station to be tested can be regulated based on the adjustment parameters to adapt to changes in various situations.

[0122] Preferably, in one embodiment of the present invention, the method for obtaining the adjustment parameters of the gate station to be tested specifically includes:

[0123] The absolute value of the difference between the expected opening of the gate of the gate station to be tested and the preset actual opening is taken as the opening error value of the gate of the gate station to be tested; the opening error value of the gate of the gate station to be tested and the actual water pressure abnormality parameters of the gate station to be tested are integrated and normalized to obtain the adjustment parameters of the gate station to be tested.

[0124] It should be noted that, in one embodiment of the present invention, the preset actual opening is set to 2 meters. The preset actual opening needs to be set based on the actual gate station system and is not limited here.

[0125] In the embodiment of the present invention, the integration of the two can be achieved by calculating the product value or the sum value of the opening error value of the gate of the gate station to be tested and the real water pressure abnormality parameter of the gate station to be tested, which is not limited here.

[0126] As an example, in one embodiment of the present invention, the expression of the adjustment parameter of the gate station to be tested may be specifically, for example, as follows:

[0127]

[0128] in, Indicates the adjustment parameters of the gate station to be tested; Indicates the actual abnormal water pressure parameters of the gate station to be tested; Indicates the expected opening of the gate of the gate station to be tested; Indicates the preset actual opening of the gate of the gate station to be tested; Indicates the opening error value of the gate of the gate station to be tested; Represents the hyperbolic tangent function, which is used for normalization.

[0129] The response adjustment module 104 is used to adjust the proportional gain coefficient of the PID controller of the gate station to be tested based on the adjustment parameters of the gate station to be tested, obtain the adjusted PID controller, and use the adjusted PID controller to regulate the operation of the gate station to be tested.

[0130] Normally, the gate station operation system achieves various responses through the PID controller. The proportional gain coefficient is an important parameter in the PID controller. It determines the control system's sensitivity to deviations and response speed. The larger the adjustment parameter, the more abnormal the gate pipeline system is. The gate opening does not match the actual situation, resulting in a large deviation. Therefore, it is necessary to increase the proportional gain coefficient in the PID controller of the gate station to be tested to a certain extent by adjusting the parameters to improve the response speed of the gate station operation system.

[0131] Preferably, in one embodiment of the present invention, the method for adjusting the acquisition of the PID controller specifically includes:

[0132] The product of the regulating parameter of the gate station to be tested and the proportional gain coefficient in the PID controller is used as the adjustment amount; the sum of the proportional gain coefficient in the PID controller and the adjustment amount is used as the adjustment proportional gain coefficient, and the PID controller using the adjustment proportional gain coefficient is used as the adjustment PID controller.

[0133] As an example, in one embodiment of the present invention, the expression for adjusting the proportional gain coefficient may be specifically, for example, as follows:

[0134]

[0135] in, Indicates adjustment of proportional gain coefficient; Represents the proportional gain coefficient of the PID controller; Indicates the adjustment parameters of the gate station to be tested; Indicates the adjustment amount.

[0136] Then, the gate station operation system can use the PID controller to adjust the response speed of the gate station under test, improve the efficiency and safety of the gate station operation, and realize highly automated operation management.

[0137] In summary, the embodiment of the present invention first obtains the water pressure data and water flow rate data in each pipeline of the gate station to be tested at each moment in a preset time period, and simultaneously obtains the water level data and water flow rate data of the gate station to be tested at each moment in the preset time period; obtains the initial water pressure anomaly parameters of the gate station to be tested according to the fluctuation difference of the water pressure data at each moment between different pipelines; analyzes the correlation between the water pressure data and the water flow rate data of each pipeline at each moment, and adjusts the initial water pressure anomaly parameters to obtain the real water pressure anomaly parameters of the gate station to be tested; obtains the expected opening of the gate of the gate station to be tested according to the change of the water level data and the distribution of the water flow rate data of the gate station to be tested within the preset time period; obtains the adjustment parameters of the gate station to be tested according to the difference between the expected opening and the preset actual opening of the gate of the gate station to be tested, and the real water pressure anomaly parameters of the gate station to be tested; based on the adjustment parameters of the gate station to be tested, adjusts the proportional gain coefficient in the PID controller of the gate station to be tested to obtain the adjustment PID controller, and uses the adjustment PID controller to regulate the operation of the gate station to be tested.

[0138] It should be noted that the sequence of the above embodiments of the present invention is only for description and does not represent the advantages and disadvantages of the embodiments. The processes depicted in the accompanying drawings do not necessarily require the specific order or continuous order shown to achieve the desired results. In some embodiments, multitasking and parallel processing are also possible or may be advantageous.

[0139] The various embodiments in this specification are described in a progressive manner, and the same or similar parts between the various embodiments can be referenced to each other, and each embodiment focuses on the differences from other embodiments.

Claims

1. A sluice station operation management system for water conservancy projects, characterized in that: The system comprises: A data acquisition module is used to obtain water pressure data and water flow rate data in each pipeline of the gate station to be tested at each moment in a preset time period, and simultaneously obtain water level data and water flow data of the gate station to be tested at each moment in the preset time period; The abnormality analysis module is used to obtain the initial abnormal water pressure parameters of the gate station to be tested according to the fluctuation difference of the water pressure data at different times between different pipelines; analyze the correlation between the water pressure data and the water flow rate data at each time of each pipeline, and adjust the initial abnormal water pressure parameters to obtain the real abnormal water pressure parameters of the gate station to be tested; The adjustment analysis module is used to obtain the expected opening of the gate of the gate station to be tested according to the change of water level data and the distribution of water flow data of the gate station to be tested within a preset time period; and obtain the adjustment parameters of the gate station to be tested according to the difference between the expected opening of the gate station to be tested and the preset actual opening, as well as the actual water pressure abnormality parameters of the gate station to be tested; A response adjustment module, used for adjusting the proportional gain coefficient in the PID controller of the gate station to be tested based on the adjustment parameters of the gate station to be tested, obtaining an adjusted PID controller, and using the adjusted PID controller to regulate the operation of the gate station to be tested; The method of obtaining the initial water pressure anomaly parameters of the gate station to be tested according to the fluctuation difference of the water pressure data at different times between different pipelines includes: According to the difference of water pressure data of each pipeline at each time and the distribution of water pressure data at all times in a preset time period, the water pressure characteristic value of each pipeline is obtained; Taking any two pipelines as a pipeline group, and obtaining a water pressure characteristic difference value of each pipeline group according to the difference of the water pressure characteristic values ​​of the two pipelines in each pipeline group; Analyze the overall level of the water pressure characteristic difference values ​​of all pipeline groups to obtain the initial water pressure anomaly parameters of the gate station to be tested; The step of obtaining the water pressure characteristic value of each pipeline according to the difference of water pressure data of each pipeline at each time and the distribution of water pressure data at all times within a preset time period includes: Taking any pipeline as the target pipeline, analyzing the overall level of water pressure data of the target pipeline at all times within a preset time period to obtain the overall water pressure value of the target pipeline; Take any two moments as a moment group, and obtain the water pressure difference value of the target pipeline in each moment group according to the difference of the water pressure data of the target pipeline at two moments in each moment group; Analyze the overall level of the water pressure difference values ​​of the target pipeline in all time groups to obtain the water pressure fluctuation degree of the target pipeline; The overall water pressure value and the water pressure fluctuation degree are integrated to obtain a water pressure characteristic value of the target pipeline; The analysis of the correlation between the water pressure data and the water flow rate data of each pipeline at each moment, and the adjustment of the initial water pressure anomaly parameter to obtain the real water pressure anomaly parameter of the gate station to be tested includes: The absolute value of the Pearson correlation coefficient between the water pressure data and the water flow rate data of each pipeline at each moment is negatively correlated and mapped as the non-correlation parameter of each pipeline; Analyze the overall level of the non-correlated parameters of all pipelines to obtain the abnormal weight value of the gate station to be tested; The initial water pressure anomaly parameter of the gate station to be measured is weighted by using the anomaly weight value to obtain the real water pressure anomaly parameter of the gate station to be measured.

2. A sluice station operation management system for water conservancy projects according to claim 1, characterized in that: The step of obtaining the expected opening of the gate of the gate station to be tested according to the change of water level data and the distribution of water flow data of the gate station to be tested within a preset time period includes: According to the change of water level data and the distribution of water flow data of the gate of the gate station to be tested within a preset time period, the opening degree of the gate station to be tested is obtained; The preset maximum opening of the gate of the gate station to be tested is weighted by utilizing the opening degree to obtain the expected opening of the gate of the gate station to be tested.

3. A sluice station operation management system for water conservancy projects according to claim 2, characterized in that: The step of obtaining the degree of opening of the gate of the gate station to be tested according to the change of water level data and the distribution of water flow data of the gate station to be tested within a preset time period includes: The absolute value of the difference between the water level data of the gate station to be tested between the initial time and the end time of the preset time period is used as the numerator, the length of the preset time period is used as the denominator, and the ratio is used as the water level change rate of the gate station to be tested; The water level data of the gate station to be tested at the end time of the preset time period is used as the numerator, the preset water level threshold of the gate station to be tested is used as the denominator, and the ratio is used as the water level proximity of the gate station to be tested; The water level change rate and the water level proximity are combined to obtain the water level danger level of the gate station to be tested; After analyzing the overall level of water flow data of the gate station to be tested at all times during a preset time period and performing negative correlation mapping, the water flow demand value of the gate station to be tested is obtained; The water level danger level and the water flow demand value are integrated and normalized to obtain the opening degree of the gate of the gate station to be tested.

4. A sluice station operation management system for water conservancy projects according to claim 1, characterized in that: The step of obtaining the adjustment parameters of the gate station to be tested according to the difference between the expected opening and the preset actual opening of the gate station to be tested, and the real water pressure abnormality parameter of the gate station to be tested comprises: The absolute value of the difference between the expected opening of the gate of the gate station to be tested and the preset actual opening is used as the opening error value of the gate of the gate station to be tested; The opening error value of the gate of the gate station to be tested and the actual water pressure abnormality parameter of the gate station to be tested are integrated and normalized to obtain the adjustment parameters of the gate station to be tested.

5. A sluice station operation management system for water conservancy projects according to claim 1, characterized in that: The step of adjusting the proportional gain coefficient of the PID controller of the gate station to be tested based on the adjustment parameter of the gate station to be tested to obtain the adjusted PID controller comprises: The product value of the adjustment parameter of the gate station to be tested and the proportional gain coefficient in the PID controller is used as the adjustment amount; The sum of the proportional gain coefficient in the PID controller and the adjustment amount is used as the adjustment proportional gain coefficient, and the PID controller using the adjustment proportional gain coefficient is used as the adjustment PID controller.

6. A sluice station operation management system for water conservancy projects according to claim 1, characterized in that: The overall level of the water pressure characteristic difference values ​​of all pipeline groups is analyzed to obtain the initial water pressure abnormality parameters of the gate station to be tested, including: The average value of the water pressure characteristic difference values ​​of all pipeline groups is used as the initial water pressure anomaly parameter of the gate station to be tested.

7. A sluice station operation management system for water conservancy projects according to claim 1, characterized in that: Analyzing the overall level of water pressure data of the target pipeline at all times within a preset time period to obtain the overall water pressure value of the target pipeline includes: The average value of the water pressure data of the target pipeline at all times within the preset time period is taken as the overall water pressure value of the target pipeline.