High ground stress extra-long mountain tunnel self-adaptive supporting structure based on stress analysis
By adopting an adaptive support structure for high-stress extra-long mountain tunnels designed by force analysis in the tunnel, combined with flexible supports and adaptive buffer components, the problem of damage and safety threats to the support structure caused by drilling and blasting is solved, and stability is achieved. and safety, and the support effect is improved through freeze fixation and waterproofing layers.
Patent Information
- Application Number
- CN202411019667.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-29
- Publication Date
- 2024-10-01
AI Technical Summary
During the tunnel excavation process, although the drilling and blasting method improves the propulsion efficiency, it is dangerous, and the deformation pressure generated by blasting in large-deformation tunnels in soft rock may damage the supporting structure, and the splashed solid objects threaten the safety of workers.
An adaptive support structure for special long mountain tunnels based on high ground stress based on force analysis is adopted, including initial support components, flexible support components and waterproof layers. Combined with external adaptive buffer components, the concrete-filled support box provides rigid and flexible support. It uses springs and rotating plates to weaken the impact force, and freezes the rock formation to prevent ground pressure and water leakage.
It effectively absorbs the deformation pressure of the surrounding rock, ensures the stability of the support structure, and protects the safety of workers. It also improves the support quality through freezing fixation and waterproof layers to ensure that the support structure is not easily damaged and is convenient for recycling, disassembly and transportation.
Smart Images

Figure CN118728431A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of tunnel support, and in particular to an adaptive support structure for a high-ground stress extra-long mountain tunnel based on force analysis. Background Art
[0002] my country has a vast territory with complex and diverse geological and geomorphological structures. Transportation construction often requires building tunnels through mountains and across ridges. With the continuous advancement of transportation network construction, more and more unfavorable geological conditions are encountered during tunnel construction.
[0003] During tunnel excavation, the drilling and blasting method can improve the tunnel advancement efficiency, but drilling and blasting has certain risks. At the same time, when encountering a soft rock large deformation tunnel during tunnel advancement, the deformation pressure on the surrounding rock generated by the blasting may affect the early support. When the impact force of solid objects such as stones, gravel, and rocks generated by the blasting is greater than the support stress of the support structure, it is easy to cause damage to the support structure. At the same time, the splashing solid objects will also pose a safety threat to the workers. Therefore, in response to the above problems, an adaptive support structure for high-stress long mountain tunnels based on force analysis is proposed. Summary of the invention
[0004] The object of the present invention is to provide an adaptive support structure for a high-ground stress extra-long mountain tunnel based on force analysis to solve the problems raised in the above-mentioned background technology.
[0005] To achieve the above object, the present invention provides the following technical solutions:
[0006] As an optional solution of the adaptive support structure for a high-ground stress extra-long mountain tunnel based on force analysis of the present invention, the adaptive support structure for a high-ground stress extra-long mountain tunnel based on force analysis includes an initial support component, a flexible support component and a waterproof layer.
[0007] The outer side of the initial support assembly is a rock layer, the inner side of the initial support assembly is provided with a flexible support assembly, the inner side of the flexible support assembly is provided with a waterproof layer, and the inner side of the waterproof layer is closely provided with a secondary support assembly, and the rear side of the secondary support assembly is inserted with an external adaptive buffer assembly;
[0008] The bottom of the flexible support assembly is fixedly connected to a reinforcement base, and a road surface is arranged above the reinforcement base;
[0009] The flexible support assembly includes a support frame, a support box and a partition, wherein a plurality of support boxes are arranged inside the support frame, and a reinforcement plate is arranged inside each support box, and partitions are fixedly connected to both sides of the reinforcement plate, and the outer side of the partition is fixedly connected to the support frame;
[0010] The external adaptive buffer assembly includes a frame, a rotating plate and an insertion rod. The inner side of the frame is rotatably connected to a plurality of rotating plates. The front end of the frame is fixedly connected to an insertion rod, and the insertion rod is inserted into the interior of the secondary support assembly. A spring is arranged on the outer side of the insertion rod.
[0011] As an optional solution of the adaptive support structure of the high-ground stress extra-long mountain tunnel based on force analysis described in the present invention, the support boxes are staggered along the axial direction of the tunnel.
[0012] As an optional solution of the adaptive support structure for high-ground stress extra-long mountain tunnel based on force analysis described in the present invention, an inclined reinforcement plate is arranged inside each of the support boxes.
[0013] As an optional solution of the adaptive supporting structure of a high-ground stress extra-long mountain tunnel based on force analysis described in the present invention, the support frame, partitions and reinforcement plates are all made of steel plates.
[0014] During tunnel excavation, the drilling and blasting method can improve the tunnel advancement efficiency, but drilling and blasting has certain risks. At the same time, when encountering a soft rock with large deformation during tunnel advancement, the deformation pressure on the surrounding rock generated by the blasting may have an impact on the early support. When the impact force of solid objects such as stones, gravel, and rocks generated by the blasting is greater than the support stress of the support structure, it is easy to cause damage to the support structure. At the same time, the flying solid objects will also pose a safety threat to the workers. After the initial support work is completed, the present invention sets a support frame, and a plurality of support boxes are arranged inside the support frame. The interior of the plurality of support boxes is alternately filled with concrete. The support boxes filled with concrete can provide rigid support for the initial support components, while the support boxes in other parts can provide flexible support for the initial support components, which are used to absorb the deformation pressure of the outer surrounding rock during blasting, thereby ensuring the support quality and ensuring that the support structure is not easily Deformation and damage, the reinforcement plate can provide support for the support box, and further strengthen the support box. Multiple groups of support boxes along the axial direction of the tunnel are staggered, so as to further ensure the overall stability of the flexible support assembly. During the subsequent tunnel excavation work, the insertion rod on one side of the skeleton can be inserted into the docking hole. At the same time, a spring is arranged on the outside of the insertion rod. In conjunction with the rotating plate, when drilling and blasting are carried out, the longitudinal impact force generated by the blasting directly acts on the rotating plate and the skeleton. At this time, under the action of the spring, the rotating plate can rotate, which can effectively and adaptively weaken the impact force. At the same time, the rotating plate can block rock fragments and provide certain protection for the staff. After use, the external adaptive buffer assembly can be removed to facilitate the recycling of the next support. The skeleton adopts two groups of left and right settings, which is convenient for the skeleton to be installed on one side of the secondary support assembly through the insertion rod, and is also convenient for disassembly and transportation.
[0015] As an optional scheme of the adaptive support structure of the high-ground stress extra-long mountain tunnel based on force analysis described in the present invention, the initial support component includes a concrete layer, a hollow support rod and a connecting pipe, a support mesh is arranged inside the concrete layer, and a plurality of groups of hollow support rods are installed on the surface of the support mesh, connecting pipes are arranged between the hollow support rods, and the hollow support rods are connected through the connecting pipes, and the outer side of the hollow support rod at the lowest side is connected to an external pipe.
[0016] As an optional solution of the adaptive support structure for high-ground stress extra-long mountain tunnel based on force analysis described in the present invention, the surface of the hollow support rod is provided with evenly distributed exhaust holes, and the exhaust holes face the rock layer.
[0017] After tunnel excavation, the excavation area needs to be protected. At this time, the initial support components are laid in advance, and then the external pipes are connected through external refrigeration equipment. At this time, the low-temperature refrigerant can be sent into the stratum. Through energy exchange, the stratum around the excavation body is frozen into a continuous frozen soil wall to resist ground pressure and isolate the connection between groundwater and the excavation body. Then, under its protection, sprayed concrete is used for support. This setting can freeze and fix the rock stratum, which is helpful for the subsequent initial support work.
[0018] As an optional solution of the adaptive support structure of the high-ground stress extra-long mountain tunnel based on force analysis described in the present invention, wherein: the secondary support assembly includes a support plate, a prefabricated I-shaped steel and a reinforced steel mesh cover, a plurality of groups of prefabricated I-shaped steels arranged in an arc shape are installed inside the support plate, and a reinforced steel mesh cover fixedly connected to the support plate is arranged on the outside of the prefabricated I-shaped steel;
[0019] The support plate is provided with docking holes on both the front and rear sides, and externally mounted adaptive buffer components are installed inside the docking holes.
[0020] The prefabricated I-shaped steel and reinforced steel mesh set inside the support plate can ensure the stability of the support plate and the support quality of the support plate. At the same time, a waterproof layer is set between the flexible support component and the secondary support component. At this time, the waterproof layer serves a sealing purpose to avoid water leakage.
[0021] Compared with the prior art, the present invention has the following beneficial effects:
[0022] After the tunnel is excavated, the excavation area needs to be protected. At this time, the initial support components are laid in advance, and then the external pipe is connected through the external refrigeration equipment. At this time, the low-temperature refrigerant can be sent into the stratum. Through energy exchange, the stratum around the excavation body is frozen into a continuous frozen soil wall to resist the ground pressure and isolate the connection between the groundwater and the excavation body. Then, under its protection, sprayed concrete is supported. This setting can freeze and fix the rock stratum, which is helpful for the subsequent initial support work.
[0023] After the initial support work is completed, a support frame is set up, and multiple support boxes are set up inside the support frame. The multiple support boxes are alternately filled with concrete. The support boxes filled with concrete can provide rigid support for the initial support components, while the support boxes in other parts can provide flexible support for the initial support components, which is used to absorb the deformation pressure of the outer surrounding rock during blasting, thereby ensuring the support quality and ensuring that the support structure is not easily deformed and damaged;
[0024] The reinforcement plates provided at the same time can provide support force for the support box, thereby further reinforcing the support box. Multiple groups of support boxes along the axial direction of the tunnel are staggered, thereby further ensuring the overall stability of the flexible support assembly.
[0025] The prefabricated I-shaped steel and reinforced steel mesh cover set inside the support plate can ensure the stability of the support plate and the support quality of the support plate. At the same time, a waterproof layer is set between the flexible support component and the secondary support component. At this time, the waterproof layer plays a sealing purpose to avoid water leakage;
[0026] During the subsequent tunnel excavation work, the insertion rod on one side of the frame can be inserted into the docking hole. At the same time, a spring is arranged on the outside of the insertion rod. In cooperation with the rotating plate, when drilling and blasting are performed, the longitudinal impact force generated by the blasting directly acts on the rotating plate and the frame. At this time, under the action of the spring, the rotating plate can rotate, which can effectively and adaptively weaken the impact force. At the same time, the rotating plate can block rock fragments and provide certain protection for the workers.
[0027] After use, the external adaptive buffer component can be removed to facilitate the recycling of the next support. The skeleton adopts two groups on the left and right, which makes it convenient to install the skeleton on one side of the secondary support component through the insertion rod, and also facilitates disassembly and transportation. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] Figure 1 It is a schematic diagram of the overall structure of the adaptive support structure of a high-ground stress extra-long mountain tunnel based on force analysis;
[0029] Figure 2It is a schematic diagram of the initial support component structure of the adaptive support structure for a high-ground stress extra-long mountain tunnel based on force analysis;
[0030] Figure 3 It is a structural schematic diagram of the flexible support components of the adaptive support structure of a high-ground stress extra-long mountain tunnel based on force analysis;
[0031] Figure 4 It is a structural schematic diagram of the secondary support components of the adaptive support structure of a high-ground stress extra-long mountain tunnel based on force analysis;
[0032] Figure 5 It is a structural schematic diagram of the external adaptive buffer component of the adaptive support structure of a high-ground stress extra-long mountain tunnel based on force analysis;
[0033] Figure 6 This is a structural schematic diagram of the installation of the support box of the adaptive support structure for a high-ground stress extra-long mountain tunnel based on force analysis.
[0034] In the figure: 1. Initial support assembly; 101. Concrete layer; 102. Hollow support rod; 103. Connecting pipe; 104. External pipe; 105. Support mesh; 2. Flexible support assembly; 201. Support frame; 202. Support box; 203. Partition; 204. Reinforcement plate; 3. Waterproof layer; 4. Secondary support assembly; 401. Support plate; 402. Prefabricated I-shaped steel; 403. Reinforced steel mesh; 404. Docking hole; 5. External adaptive buffer assembly; 501. Skeleton; 502. Rotating plate; 503. Insertion rod; 504. Spring; 6. Reinforced base; 7. Road surface. DETAILED DESCRIPTION
[0035] Embodiment 1:
[0036] See also Figure 1 , Figure 3 , Figure 5 and Figure 6 , the present invention provides a technical solution:
[0037] The adaptive support structure of a high-ground stress extra-long mountain tunnel based on force analysis includes an initial support component 1, a flexible support component 2 and a waterproof layer 3.
[0038] The outer side of the initial support component 1 is a rock layer, the inner side of the initial support component 1 is provided with a flexible support component 2, the inner side of the flexible support component 2 is provided with a waterproof layer 3, and the inner side of the waterproof layer 3 is closely provided with a secondary support component 4, and the rear side of the secondary support component 4 is inserted with an external adaptive buffer component 5;
[0039] The bottom of the flexible support assembly 2 is fixedly connected to a reinforcement base 6, and a road surface 7 is arranged above the reinforcement base 6;
[0040] The flexible support assembly 2 comprises a support frame 201, a support box 202 and a partition 203. A plurality of support boxes 202 are arranged inside the support frame 201, and a reinforcement plate 204 is arranged inside each of the support boxes 202. The partitions 203 are fixedly connected to both sides of the reinforcement plate 204, and the outer side of the partition 203 is fixedly connected to the support frame 201.
[0041] The above-mentioned external adaptive buffer component 5 includes a skeleton 501, a rotating plate 502 and an insertion rod 503. The inner side of the above-mentioned skeleton 501 is rotatably connected with multiple rotating plates 502. The front end of the above-mentioned skeleton 501 is fixedly connected with an insertion rod 503, and the insertion rod 503 is inserted into the interior of the secondary support component 4. The outer side of the above-mentioned insertion rod 503 is provided with a spring 504.
[0042] The above-mentioned support boxes 202 are staggered along the axial direction of the tunnel.
[0043] Each of the support boxes 202 is provided with an inclined reinforcement plate 204 therein.
[0044] The support frame 201, the partition plate 203 and the reinforcement plate 204 are all made of steel plates.
[0045] During tunnel excavation, the drilling and blasting method can improve the advancement efficiency of the tunnel, but drilling and blasting has certain risks. At the same time, when encountering a soft rock with large deformation during tunnel advancement, the deformation pressure on the surrounding rock generated by the blasting may affect the early support. When the impact force of solid objects such as stones, gravel, and rocks generated by the blasting is greater than the support stress of the support structure, it is easy to cause damage to the support structure. At the same time, the splashing solid objects will also pose a safety threat to the workers. The flexible support component 2 provided by the present invention can provide flexible support for the support. After the initial support work is completed, a support frame 201 is provided, and a plurality of support boxes 202 are provided inside the support frame 201. The interior of the plurality of support boxes 202 is alternately filled with concrete. The support boxes 202 filled with concrete can provide rigid support for the initial support component 1, and the support boxes 202 at other parts can provide flexible support for the initial support component 1, which is used to absorb the deformation pressure of the outer surrounding rock during blasting, thereby ensuring the support quality and ensuring that the support structure is not easily deformed and damaged. The reinforcement plate 204 can provide support force for the support box 202, thereby further reinforcing the support box 202. Multiple groups of support boxes 202 along the axial direction of the tunnel are staggered, thereby further ensuring the overall stability of the flexible support assembly 2. When performing subsequent tunnel excavation work, the insertion rod 503 on one side of the skeleton 501 can be inserted into the docking hole 404. At the same time, a spring 504 is arranged on the outside of the insertion rod 503, and in conjunction with the rotating plate 502, when drilling and blasting are performed, the longitudinal impact force generated by the blasting directly acts on the rotating plate 502 and the skeleton 501. At this time, under the action of the spring 504, the rotating plate 502 can rotate, which can effectively and adaptively weaken the impact force. At the same time, the rotating plate 502 can block rock fragments and provide a certain protection for the staff. After use, the external adaptive buffer assembly 5 can be removed to facilitate the recycling of the next support. The skeleton 501 adopts a left and right two-group arrangement, which is convenient for the skeleton 501 to be installed on one side of the secondary support assembly 4 through the insertion rod 503, and is also convenient for disassembly and transportation;
[0046] In this embodiment, the waterproof layer 3 is arranged between the flexible support component 2 and the secondary support component 4, which can effectively prevent water from leaking from the rock formation and dripping into the tunnel, thereby achieving the purpose of waterproofing. At the same time, after the secondary support component 4 is assembled, its insertion rod 503 is inserted into the rear side of the assembled secondary support component 4. At this time, a spring 504 is arranged on the outside of the insertion rod 503. When the blasting is carried out in the next tunnel area, the arranged spring 504 and the rotatable rotating plate 502 can effectively block the impact force generated by the blasting, thereby achieving the purpose of adaptive buffering protection. At the same time, the rotating plate 502 can block the splashing rock fragments, thereby achieving the purpose of protecting the support structure, while providing a certain safety guarantee for the health and safety of the construction personnel.
[0047] The support boxes 202 are arranged in multiple groups and are alternately filled with concrete. While ensuring the overall stability of the device, the hollow support boxes 202 can provide a certain degree of flexible support. The staggered support boxes 202 can ensure the overall stability of the flexible support component 2, and inclined reinforcement plates 204 are installed between the partitions 203. According to the initial support component 1 of rock extrusion and then act on the flexible support component 2, after force analysis, the simple partitions 203 support the support frame 201 of the flexible support component 2, and the stability of the support box 202 is poor. The support box 202 is similar to a quadrilateral and has no stability. At this time, the inclined reinforcement plate 204 can effectively divide the support box 202 into two cavities similar to triangles, which can achieve the purpose of effective support. When the flexible support component 2 is extruded, its gravity is concentrated on the outer surface of the flexible support component 2, and the reinforcement plate 204 is inclined to the outside, which can provide effective support.
[0048] Example 2
[0049] This embodiment is an improvement on embodiment 1. Figure 1 and Figure 2 Specifically, the initial support assembly 1 includes a concrete layer 101, a hollow support rod 102 and a connecting pipe 103. A support mesh 105 is arranged inside the concrete layer 101, and a plurality of groups of hollow support rods 102 are installed on the surface of the support mesh 105. Connecting pipes 103 are arranged between the hollow support rods 102, and the hollow support rods 102 are connected through the connecting pipes 103. An external pipe 104 is connected to the outside of the hollow support rod 102 on the lowest side.
[0050] The surface of the hollow support rod 102 is provided with evenly distributed exhaust holes, and the exhaust holes face the rock layer.
[0051] After tunnel excavation, the excavation area needs to be protected. At this time, the initial support assembly 1 is pre-laid, the support mesh 105 is assembled first, and the hollow support rods 102 are installed on the surface of the support mesh 105. The multiple hollow support rods 102 are connected through the connecting pipe 103, and the external pipe 104 is installed. Then, the external pipe 104 is connected through an external refrigeration device. At this time, the low-temperature refrigerant can be sent into the stratum. Through energy exchange, the stratum around the excavation body is frozen into a continuous frozen soil wall to resist the ground pressure and isolate the connection between the groundwater and the excavation body. Then, under its protection, sprayed concrete is used for support. This setting can freeze and fix the rock stratum to avoid the fall of soft rock soil and stones in the rock layer when spraying concrete, which is helpful for the subsequent initial support work.
[0052] Example 3
[0053] This embodiment is an improvement on embodiment 2. Figure 1 and Figure 4 Specifically, the secondary support assembly 4 includes a support plate 401, a prefabricated I-shaped steel 402 and a reinforced steel mesh cover 403. A plurality of groups of arc-shaped prefabricated I-shaped steel 402 are installed inside the support plate 401, and a reinforced steel mesh cover 403 fixedly connected to the support plate 401 is arranged on the outer side of the prefabricated I-shaped steel 402;
[0054] The support plate 401 is provided with docking holes 404 at both the front and rear sides, and an external adaptive buffer component 5 is installed inside the docking hole 404 .
[0055] The prefabricated I-shaped steel 402 and the reinforced steel mesh 403 arranged inside the support plate 401 can ensure the stability of the support plate 401 and the support quality of the support plate 401. At the same time, a waterproof layer 3 is arranged between the flexible support component 2 and the secondary support component 4. At this time, the waterproof layer 3 serves the purpose of sealing to avoid water leakage;
[0056] In this embodiment, docking holes 404 are provided on the front and rear sides of the support plate 401. The docking holes 404 on the rear side of the support plate 401 are convenient for use with the external adaptive buffer assembly 5, convenient for connecting the external adaptive buffer assembly 5, and convenient for blocking the impact force of subsequent blasting. The docking holes 404 on the front side of the support plate 401 are convenient for aligning the docking holes 404 of the secondary support assemblies 4 on the front and rear sides when assembling the next secondary support assembly 4, and then inserting an external connecting rod into it to achieve the purpose of positioning.
[0057] This article uses specific examples to illustrate the principles and implementation methods of the present invention. The above examples are only used to help understand the method and core ideas of the present invention. The above is only a preferred implementation of the present invention. It should be pointed out that due to the limitations of textual expression and the objective existence of infinite specific structures, ordinary technicians in this technical field can make several improvements, modifications or changes without departing from the principles of the present invention, and can also combine the above technical features in an appropriate manner; these improvements, modifications, changes or combinations, or the direct application of the inventive concept and technical solution to other occasions without improvement, should be regarded as the protection scope of the present invention.
Claims
1. The adaptive support structure of high-ground stress extra-long mountain tunnel based on force analysis is characterized by: It comprises an initial support component (1), a flexible support component (2) and a waterproof layer (3), The outer side of the initial support component (1) is a rock layer, the inner side of the initial support component (1) is provided with a flexible support component (2), the inner side of the flexible support component (2) is provided with a waterproof layer (3), and the inner side of the waterproof layer (3) is closely provided with a secondary support component (4), and the rear side of the secondary support component (4) is inserted with an external adaptive buffer component (5); The bottom of the flexible support assembly (2) is fixedly connected to a reinforcement base (6), and a road surface (7) is arranged above the reinforcement base (6); The initial support assembly (1) comprises a concrete layer (101), a hollow support rod (102) and a connecting pipe (103); a support mesh (105) is arranged inside the concrete layer (101), and a plurality of groups of hollow support rods (102) are installed on the surface of the support mesh (105); connecting pipes (103) are arranged between the hollow support rods (102), and the hollow support rods (102) are connected through the connecting pipes (103); and an external pipe (104) is connected to the outside of the hollow support rod (102) at the lowest side; The flexible support assembly (2) comprises a support frame (201), a support box (202) and a partition (203); a plurality of support boxes (202) are arranged inside the support frame (201); and a reinforcement plate (204) is arranged inside each of the support boxes (202); both sides of the reinforcement plate (204) are fixedly connected to the partition (203); and the outer side of the partition (203) is fixedly connected to the support frame (201); The secondary support assembly (4) comprises a support plate (401), a prefabricated I-shaped steel (402) and a reinforced steel mesh cover (403); a plurality of groups of prefabricated I-shaped steel (402) arranged in an arc shape are installed inside the support plate (401); and a reinforced steel mesh cover (403) fixedly connected to the support plate (401) is arranged on the outer side of the prefabricated I-shaped steel (402); The support plate (401) is provided with docking holes (404) on both the front and rear sides, and an externally mounted adaptive buffer assembly (5) is installed inside the docking hole (404); The externally mounted adaptive buffer assembly (5) comprises a frame (501), a rotating plate (502) and an insertion rod (503); a plurality of rotating plates (502) are rotatably connected to the inner side of the frame (501); the front end of the frame (501) is fixedly connected to the insertion rod (503); the insertion rod (503) is inserted into the interior of the secondary support assembly (4); and a spring (504) is arranged on the outer side of the insertion rod (503).
2. The adaptive support structure for high-ground stress extra-long mountain tunnel based on force analysis according to claim 1 is characterized by: The surface of the hollow support rod (102) is provided with evenly distributed exhaust holes, and the exhaust holes face the rock layer.
3. The adaptive support structure for high-ground stress extra-long mountain tunnel based on force analysis according to claim 1 is characterized by: The support boxes (202) are arranged in a staggered manner along the axial direction of the tunnel.
4. The adaptive support structure for high-ground stress extra-long mountain tunnel based on force analysis according to claim 1 is characterized by: Each support box (202) is provided with an inclined reinforcement plate (204) inside.
5. The adaptive support structure for high-ground stress extra-long mountain tunnel based on force analysis according to claim 1 is characterized by: The support frame (201), the partition plate (203) and the reinforcement plate (204) are all made of steel plates.