Sample analysis system and control method thereof
By introducing a controller and a shutdown test tube rack into the sample analysis system, intelligent shutdown is performed based on the working mode and status of the analyzer, which solves the complex problem of shutting down the transmission track and product module, and achieves user convenience and efficient shutdown process operations.
Patent Information
- Application Number
- CN202310383372.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2023-03-31
- Publication Date
- 2024-10-01
AI Technical Summary
In the field of medical testing and diagnosis, the shutdown process of transmission rails and product modules is complicated, affecting scheduling and use and medical staff's time. Especially when shutdown operations need to be performed according to different analysis needs, existing technology cannot meet user convenience needs.
Provides a sample analysis system, including an analyzer, a controller and a shutdown test tube rack. The controller receives the shutdown instruction of the analyzer, obtains its working mode and working status, and controls the shutdown test tube rack and analysis based on a preset shutdown scheduling strategy. Shut down the instrument, including setting the cleaning path to meet the user's customary needs.
It realizes intelligent shutdown based on the working mode and working status of the analyzer, meets user convenience needs, simplifies diversified shutdown process operations, and improves system flexibility and cleaning efficiency.
Smart Images

Figure CN118731387A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of sample analysis, and in particular to a sample analysis system and a control method thereof. Background Art
[0002] Currently, in the field of medical testing and diagnosis, samples are usually placed in sample analysis equipment for testing, wherein the samples are usually loaded on test tube racks and mechanically transported by transmission tracks to achieve streamlined testing operations.
[0003] Usually, multiple product modules and auxiliary modules are installed on a transmission track. Each product module can realize different analysis functions. With the assistance of the auxiliary modules, the processes on each product module can meet the different analysis needs of users.
[0004] However, before the inspection is required and after the inspection is completed, it is often necessary to start or shut down the transmission track switch, and then start or shut down the switches of each product module one by one. At present, due to different analysis requirements in actual situations, after the entire transmission track switch is pressed to shut down, some product modules with special requirements cannot be directly shut down, otherwise it will affect the next scheduling and use. If the product module is shut down after the process is completed, the precious time of medical staff will be delayed. Summary of the invention
[0005] The main technical problem solved by the present application is to provide a sample analysis system and a control method thereof, which can control the analyzer to shut down according to the shutdown scheduling strategy based on the working mode and working status of the analyzer, and can meet the user's convenience needs in a timely manner.
[0006] In order to solve the above technical problems, a technical solution adopted in the present application is: providing a sample analysis system, which includes an analyzer, a controller, a shutdown test tube rack and a transmission track; the analyzer is connected to the controller and is arranged corresponding to the shutdown test tube rack, and the shutdown test tube rack and the analyzer are respectively arranged in sequence along the transmission track; the controller is used to receive the shutdown instruction of the analyzer; the controller obtains the working mode and working status of each analyzer and the preset shutdown scheduling strategy; based on the working mode and working status, the controller controls the shutdown test tube rack and the analyzer to shut down according to the preset shutdown scheduling strategy; wherein the preset shutdown scheduling strategy includes a one-to-one correspondence between the Mth row and Nth column of the shutdown test tube rack and the assigned cleaning paths of the analyzer.
[0007] In order to solve the above technical problems, another technical solution adopted in the present application is: to provide a control method for a sample analysis system, which is applied to the sample analysis system, and the sample analysis system includes: an analyzer, a controller, a shutdown test tube rack and a transmission track; the analyzer is connected to the controller and is arranged corresponding to the shutdown test tube rack, and the shutdown test tube rack and the analyzer are respectively arranged in sequence along the transmission track, and the control method includes: in response to the shutdown instruction of the analyzer, obtaining the working mode and working status of each analyzer and a preset shutdown scheduling strategy; based on the working mode and working status, controlling the shutdown test tube rack and the analyzer to shut down according to the preset shutdown scheduling strategy; wherein the preset shutdown scheduling strategy includes a one-to-one correspondence between the Mth row and Nth column of the shutdown test tube rack and the cleaning paths assigned to the analyzer, and M and N are both positive integers greater than or equal to 1.
[0008] The beneficial effect of the present application is that, different from the prior art, through the above-mentioned method, the present application can control the shutdown test tube rack and the analyzer to shut down according to a preset shutdown scheduling strategy based on the working mode and working status of the analyzer, so as to meet the user's convenience needs in a timely manner and realize diversified shutdown process operations. BRIEF DESCRIPTION OF THE DRAWINGS
[0009] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work. Among them:
[0010] Figure 1 It is a reference structural diagram of a transmission track layout of the sample analysis system of the present application;
[0011] Figure 2 It is a panel diagram of the first pipeline mode management of the sample analysis system of this application;
[0012] Figure 3 It is a flow chart of an implementation method of a control method of a sample analysis system of the present application;
[0013] Figure 4 This application Figure 3 A schematic diagram of the process of the first embodiment before step S12;
[0014] Figure 5 This application Figure 3 A schematic diagram of the process of the second embodiment before step S12;
[0015] Figure 6 This application Figure 3 A schematic diagram of the process of the third embodiment before step S12;
[0016] Figure 7 This application Figure 3 A schematic diagram of the process of the fourth embodiment before step S12;
[0017] Figure 8 This application Figure 3 A schematic diagram of the process of the fifth embodiment before step S12;
[0018] Fig. 9 It is a flowchart of a specific implementation method of the control method of the sample analysis system of the present application. DETAILED DESCRIPTION
[0019] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.
[0020] It should be understood that when used in this specification and the appended claims, the term "comprising" indicates the presence of described features, integers, steps, operations, elements and / or components, but does not exclude the presence or addition of one or more other features, integers, steps, operations, elements, components and / or groups thereof.
[0021] It should also be understood that the terms used in this application specification are only for the purpose of describing specific embodiments and are not intended to limit the application. As used in this application specification and the appended claims, unless the context clearly indicates otherwise, the singular forms "a", "an" and "the" are intended to include plural forms.
[0022] It should be further understood that the term “and / or” used in the specification and appended claims refers to any combination and all possible combinations of one or more of the associated listed items, and includes these combinations.
[0023] As used in this specification and the appended claims, the term "if" may be interpreted as "when" or "upon" or "in response to determining" or "in response to detecting," depending on the context. Similarly, the phrases "if it is determined" or "if [described condition or event] is detected" may be interpreted as meaning "upon determination" or "in response to determining" or "upon detection of [described condition or event]" or "in response to detecting [described condition or event]," depending on the context.
[0024] In order to illustrate the technical solution of this application, a sample analysis system is first provided. Figure 1 , Figure 1 This is a reference structural diagram of a transmission track layout of a sample analysis system of the present application, and the sample analysis system includes: an analyzer, a controller, a shutdown test tube rack, and a transmission track. Among them, the analyzer is connected to the controller and is arranged corresponding to the shutdown test tube rack, and the shutdown test tube rack and the analyzer are arranged in sequence along the transmission track.
[0025] In the sample analysis system, the controller can be used to receive the shutdown command of the analyzer; the controller obtains the working mode and working status of each analyzer and the preset shutdown scheduling strategy; based on the working mode and working status, the controller controls the shutdown test tube rack and the analyzer to shut down according to the preset shutdown scheduling strategy.
[0026] The preset shutdown scheduling strategy includes a one-to-one correspondence between the Mth row and Nth column of the shutdown test tube rack and the cleaning paths assigned to the analyzers, and both M and N are positive integers greater than or equal to 1.
[0027] Specifically, the one-to-one correspondence of the cleaning paths may refer to a one-to-one correspondence between the Mth row and Nth column of the shutdown test tube rack and an assigned analyzer, that is, one departure point corresponds to one destination; or the Mth row and Nth column of the shutdown test tube rack may refer to a one-to-one correspondence between the Mth row and Nth column of the shutdown test tube rack and multiple assigned analyzers, that is, one departure point corresponds to multiple destinations, for example, one departure point corresponds to a first analyzer at the first destination and a second analyzer at the second destination, so that the first analyzer and the second analyzer can be associated through the cleaning path to facilitate a more time-saving and efficient cleaning process.
[0028] Since the preset shutdown scheduling strategy is a cleaning allocation rule customized according to the user's habits, through the above method, the present application can control the shutdown test tube rack and the analyzer to shut down according to the preset shutdown scheduling strategy based on the working mode and working status of the analyzer, so that the user's operating habits can be recorded, the user's convenience needs can be met in a timely manner, and diversified shutdown process operations can be realized.
[0029] In order to better record the user's habitual needs, the controller includes a control panel, which can be used to receive associated instructions of the analyzer and the shutdown test tube rack. The controller can control the generation of a preset shutdown scheduling strategy based on the associated instructions.
[0030] The preset shutdown scheduling strategy includes the path association between the number segments of the shutdown test tube rack and the assigned analyzers to form a cleaning path. In addition, the associated cleaning methods can be set to enrich the selection of solutions.
[0031] Therefore, setting up a control panel as a way to implement human-computer interaction is conducive to improving the feasibility of the solution. The use of the control panel reduces the difficulty of operation for medical staff, and due to the memory function of the control panel, the user's different classification habits are recorded during the cleaning operation and shutdown process, and the various cleaning and shutdown tasks in the cleaning process are refined, which is conducive to enriching the preset shutdown scheduling strategy and realizing more refined cleaning and shutdown operations.
[0032] In addition, the controller can also associate and bind the number segments of different test tube racks and the types of test tube racks, and different test tube rack types correspond to different colors. Specifically, through user settings, the color of the test tube rack can be bound to the test tube rack number segment. The user can customize the test tube rack number segment as the function and purpose of the test tube rack number. Suppose the user sets the shutdown test tube rack, the system recognizes it as a shutdown test tube rack by scanning the number segment, and the user distinguishes it by the corresponding color of the test tube rack.
[0033] For example: different test tube rack number segments are used to form an association relationship with the test tube rack type, for example, the 5th test tube rack hole corresponds to the 5th instrument. For another example, in response to the setting association instruction, the gray test tube rack corresponds to the test tube rack number segment [0001, 1000] to indicate a venous whole blood test tube rack; the purple test tube rack corresponds to the test tube rack number segment [1001, 2000] to indicate a trace whole blood test tube rack; the red test tube rack corresponds to the test tube rack number interval segment [2001, 2100] to indicate a quality control test tube rack; the yellow test tube rack number segment [2101, 2200] to indicate a calibration test tube rack; and the green test tube rack number segment [2201, 2300] to indicate a shutdown test tube rack.
[0034] Therefore, by using different test tube rack number segments to divide the test tube rack operation tasks, the operation functions of various test tube racks can be effectively realized. Moreover, the various related tasks do not interfere with each other. Different test tube racks of the sample analysis system perform their respective functions, integrating different operation tasks into one, and enriching the types of operation tasks of the sample analysis system.
[0035] In the transmission track, the sample analysis system is mainly divided into two modes according to the functional division of the analyzer: stand-alone mode and assembly line mode. The controller can switch the mode of the sample system in response to the mode switching command. If the analyzer is set to stand-alone mode, the analyzer and the corresponding stand-alone sampling unit are independent of the transmission track and used differently from the assembly line mode. By independently controlling and using the analyzer in stand-alone mode, it can be used for special scenarios, such as emergency testing.
[0036] The control panel is also used to manage whether the analyzer is in working mode, the start and shut down time of the working mode, and whether the shutdown test tube rack is connected. Figure 2 , Figure 2This is a panel diagram of the pipeline mode management of the sample analysis system of this application. If the pipeline mode is connected in the mode of the product nickname 1, and the startup and shutdown are scheduled, and the test tube clamp shutdown is selected, it means that when the preset time is reached for shutdown, the shutdown test tube rack is connected to enter the shutdown process.
[0037] Furthermore, the sample analysis system also includes a stand-alone sample injection unit, a loading unit, a scanning unit, an unloading unit, a rotating unit, and a test tube arranged on a shutdown test tube rack on the transmission track. The test tube on the shutdown test tube rack can be used as a departure point, and the analyzer can be used as a destination. Medical personnel can place test tubes containing liquid on the test tube rack and then place them on the loading unit. In order to make better use of these units, transmission track equipment such as a scanning unit, a loading unit, and an unloading unit can be arranged on one side of the transmission track, and an analyzer and a stand-alone sample injection unit and a rotating unit that can work in a stand-alone mode can be arranged on the other side of the transmission track.
[0038] In order to facilitate the cleaning work of medical staff, multiple sites can be set in the sample analysis system for the movement and operation path of each unit when working, so as to avoid confusion in the operation of each unit, such as Figure 1 In the system, ABCDEFGHIJ sites are set for each unit. Take the scanning unit scanning the loading unit as an example, where F represents the installation point, which is used to place the test tube rack on the loading unit; D represents the waiting point, which is used to wait for the previous operation process to be completed before continuing to the next site; B represents the sample allocation waiting point, which is used to detect whether there is liquid on the test tube rack or to extract liquid from the shutdown test tube rack containing liquid; A represents another waiting point, which is used to wait for the test tube rack after the liquid extraction is completed; E represents the transportation point, which is used to transport the shutdown test tube rack after the liquid is extracted; G represents another transportation point; and HIJ are the transportation point, installation point and another transportation point of the transmission track on the other side. Therefore, the operation of various shutdown scenarios can meet the multi-faceted needs of medical staff through the operation and cooperation of each site.
[0039] Among them, when the controller determines through the scanning unit that the loading unit is placed on the shutdown test tube rack and the shutdown test tube rack contains liquid, the controller obtains that the working mode is assembly line mode or stand-alone mode, and the working state is ready state, controls the distribution of liquid to the analyzer, and controls the analyzer to perform cleaning and shutdown.
[0040] Furthermore, whether the analyzer is in the assembly line mode or the stand-alone mode, when it is detected that the analyzer is in the shutdown state, it means that the analyzer in the shutdown state has been cleaned, and there is no need to distribute the liquid in the shutdown test tube rack to the analyzer.
[0041] Among them, since the liquid loaded into the shutdown test tube rack during the shutdown process is often cleaning liquid, the cleaning liquid can be divided into conventional cleaning liquid and special cleaning liquid. Different cleaning liquids are used to clean the analyzer according to different cleaning modes. On the basis of meeting user needs, the use of special cleaning liquid can be saved, thereby saving cleaning costs and improving cleaning efficiency.
[0042] In addition, if the controller obtains that the working mode is assembly line mode or stand-alone mode, and detects that the status of its analyzer is working status, it means that the analyzer in the working status may have just completed the detection operation or is in the process of detection operation, and is in a state to be cleaned. In this case, it is necessary to call the liquid in the corresponding shutdown test tube rack to allocate it to the analyzer, so as to facilitate the subsequent cleaning operation of the analyzer.
[0043] Therefore, when the analyzer needs to be cleaned, the liquid in the shutdown test tube rack is allocated to the analyzer, so that while fully meeting the shutdown requirements of the sample analysis system, cleaning liquid can be further saved, thereby improving the cleaning efficiency of the cleaning analyzer.
[0044] On the other hand, the present application also provides a control method for a sample analysis system, see Figure 3 , Figure 3 This is a flow chart of an implementation method of a sample analysis system of the present application. The sample analysis system includes an analyzer, a controller, a shutdown test tube rack, and a transmission track; the analyzer is connected to the controller and is arranged corresponding to the shutdown test tube rack, and the shutdown test tube rack and the analyzer are arranged in sequence along the transmission track. The control method specifically includes the following steps:
[0045] S11: in response to the instruction for setting the association between the analyzer and the shutdown test tube rack, controlling the generation of a preset shutdown scheduling strategy to associate the number segments of the shutdown test tube rack with the analyzer respectively by paths, so as to form multiple cleaning paths;
[0046] Since the workflow of the laboratory is more rigorous and fixed, by utilizing the characteristics of its work, users can customize in the software system whether to specify or all analyzers to shut down using the set shutdown test tube rack. This is basically a customized operation that can meet their subsequent daily work needs.
[0047] Among them, in order to shut down the shutdown test tube rack, the shutdown test tube rack can be placed on the loading unit, and then the controller allocates and transmits it to the analyzer for the shutdown process; if some instruments have special requirements, the customized analyzer does not need to be shut down when shutting down the analyzers in batches, and the analyzer is not allocated, so that the user is provided with a single analyzer to continue sample testing.
[0048] By responding to the instruction for setting the association between the analyzer and the shutdown test tube rack, the control generates a preset shutdown scheduling strategy to associate the number segments of the shutdown test tube rack with the analyzer respectively, forming multiple cleaning paths, so as to record the user's habitual needs. Among them, the preset shutdown scheduling strategy includes a one-to-one correspondence between the cleaning paths between the Mth row and the Nth column of the shutdown test tube rack and the assigned analyzer, and M and N are both positive integers greater than or equal to 1.
[0049] In order to better record the user's habitual needs, the controller includes a control panel, which can be used to receive the associated instructions of the analyzer and the shutdown test tube rack, and the controller can control the generation of a preset shutdown scheduling strategy based on the associated instructions. The control panel is used to manage whether the analyzer is connected to the working mode, the start-up time and shutdown time of the working mode, and whether the shutdown test tube rack is connected;
[0050] The preset shutdown scheduling strategy includes respectively associating the number segments of the shutdown test tube rack with the assigned analyzers to form a cleaning path.
[0051] Generally, the distribution rules of cleaning liquid test tubes are divided into five cases: First, one cleaning liquid can be distributed to one analyzer. Second, if one cleaning liquid is placed on a row of test tube racks (abbreviated as: one cleaning liquid per row), and N rows are placed, they will be distributed in sequence. Third, if N cleaning liquids are placed on a row of test tube racks (abbreviated as: one row of N cleaning liquids), one analyzer will be allocated to the next analyzer after the sample aspiration is completed, until N cleaning liquids are distributed. Fourth, one cleaning liquid is placed in a row, and N rows or one row of N cleaning liquids are placed. When N cleaning liquids > the number of analyzers set to shut down the test tube rack, the remaining cleaning liquid will not be distributed. Fifth, the user is allowed to place one or more rows of one cleaning liquid or one row of N cleaning liquids at the same time; where N is an integer greater than or equal to 1.
[0052] It is worth noting that: regarding the shutdown cleaning solution, the sample analysis system can assign a unique identification number, and the user does not need to set the system.
[0053] Specifically, for analyzers that are customized to shut down, if they are not modified or changed, users do not need to perform shutdown operations in the sample analysis system every day. Specifically, in assembly line mode or stand-alone mode, when the user places a row of test tube racks and multiple bottles of cleaning solution, or multiple rows of test tube racks and one bottle of cleaning solution per row in the loading unit, the sample analysis system can automatically load, automatically distribute liquids, and read them as shutdown test tube racks and shutdown cleaning solution, and then transport the shutdown test tube racks to the designated analyzer, thereby realizing the automatic shutdown function. In this way, users do not need to remember the rack number segment, sample position, and instrument position, and human-computer interaction operations are also reduced.
[0054] S12: In response to the shutdown instruction of the analyzer, obtaining the working mode and working state of each analyzer and a preset shutdown scheduling strategy;
[0055] Usually, since multiple units are set up in the sample analysis system for the division of labor of detection operations, in order to minimize the impact of each unit on each other and better call for collaboration between each unit, each unit or instrument is configured with an on / off key for independent startup or shutdown control of each unit.
[0056] like Figure 1 In, one-button on / off O and unit on / off key O', of course Figure 1 There are multiple unit on / off keys O', Figure 1 The mark in the figure is only used as a reference. Therefore, multiple shutdown commands can exist simultaneously in the analyzer.
[0057] Since the shutdown scheduling strategy is preset, when the shutdown command of the analyzer is received, the working mode and working status of each analyzer and the preset shutdown scheduling strategy can be obtained first according to the shutdown command; the number segment of the test tube rack and the corresponding shutdown test tube rack are allocated through the preset shutdown scheduling strategy, so that the liquid in the shutdown test tube rack can be subsequently allocated to the analyzer.
[0058] S13: Based on the working mode and working status, the shutdown test tube rack and analyzer are controlled to be shut down according to a preset shutdown scheduling strategy.
[0059] Specifically, the sample analysis system also includes a loading unit and a scanning unit arranged on the transmission track. When the controller determines through the scanning unit that a shutdown test tube rack is placed on the loading unit and that liquid is placed on the shutdown test tube rack, the controller obtains that the working mode is assembly line mode or stand-alone mode, and the working state is ready state, controls the distribution of liquid to the analyzer, and controls the analyzer to perform cleaning and shutdown.
[0060] Usually, in order to detect whether the cleaning meets the requirements, the shutdown conditions of the preset analyzer are set. For example, if the concentration of the cleaning liquid in the part of the analyzer that carries the cleaning liquid reaches a preset value after the preset cleaning program, it means that the analyzer to be shut down has completed the cleaning process, which means that the cleaning has met the preset shutdown conditions. In this way, the analyzer can be controlled to execute shutdown.
[0061] Therefore, through the above method, the present application can control the shutdown test tube rack and analyzer to shut down according to the preset shutdown scheduling strategy based on the working mode and working status of the analyzer, which can meet the user's convenience needs in a timely manner and realize diversified shutdown process operations.
[0062] In addition, the controller can also associate and bind the number segments of different test tube racks and the types of test tube racks, and different test tube rack types correspond to different colors. Specifically, through user settings, the color of the test tube rack can be bound to the test tube rack number segment. The user can customize the test tube rack number segment as the function and purpose of the test tube rack number. Suppose the user sets the shutdown test tube rack, the system recognizes it as a shutdown test tube rack by scanning the number segment, and the user distinguishes it by the corresponding color of the test tube rack.
[0063] For example: different test tube rack number segments are used to form an association relationship with the test tube rack type, for example, the 5th test tube rack hole corresponds to the 5th instrument. For another example, in response to the setting association instruction, the gray test tube rack corresponds to the test tube rack number segment [0001, 1000] to indicate a venous whole blood test tube rack; the purple test tube rack corresponds to the test tube rack number segment [1001, 2000] to indicate a trace whole blood test tube rack; the red test tube rack corresponds to the test tube rack number interval segment [2001, 2100] to indicate a quality control test tube rack; the yellow test tube rack number segment [2101, 2200] to indicate a calibration test tube rack; and the green test tube rack number segment [2201, 2300] to indicate a shutdown test tube rack.
[0064] In addition, the retention number of the test tube rack can usually be SR****. From left to right, we can see that: SR indicates the retention number of the special test tube rack; the first star is divided into three cases: SRQ, S indicates the retention number of shutdown, R indicates the retention number of automatic flushing, and Q indicates the retention number for quality control; the second star is divided into two cases: HA, H indicates that the test tube rack is only transported to the analyzer, and A indicates that all analytical instruments connected to the conveyor controller can be transported except SP-10; the third and fourth star are divided into two cases: 00 and 01 to 10, where 00 indicates that the position of the sample in the test tube rack is associated with the unit in the system and the sample is transported accordingly. The sample placed in the test tube rack position 10 is transported to the conveyor "CV1". The sample placed in the test tube rack position 9 is transported to the conveyor "CV2". Similarly, each sample in the sample position to position 1 is transported to the corresponding associated unit. However, the quality control sample is transported to all conveyors in sequence. 01 to 10 indicate that the number of the test tube rack label is associated with the equipment structure and the sample is transported. If the rack label number is "01", it will be transported to conveyor "CV1". If the rack label number is "02", it will be transported to conveyor "CV2". Similarly, all rack label numbers up to number "10" are linked to the corresponding unit of the transport destination and transported*. CV1 is the conveyor (CV-40) on the rack export side connected to the barcode terminal (BT-40). From this position, each conveyor is enumerated in the order of CV2, CV3, and so on.
[0065] Before dispensing the liquid in the test tube, it is very important that the analyzer is working properly. This directly determines whether the liquid in the test tube is dispensed to the corresponding analyzer. Figures 4 to 8 , Figure 4 This application Figure 3 A schematic diagram of the process of the first embodiment before step S12; Figure 5 This application Figure 3 A schematic diagram of the process of the second embodiment before step S12; Figure 6 This application Figure 3 A schematic diagram of the process of the third embodiment before step S12; Figure 7 This application Figure 3 A schematic diagram of the process of the fourth embodiment before step S12; Figure 8 This application Figure 3 FIG. 5 is a flow chart of the fifth embodiment before step S12.
[0066] Specifically, based on the working mode and working status, the steps of controlling the shutdown test tube rack and the analyzer to shut down according to the preset shutdown scheduling strategy include:
[0067] S21: Determine whether a relevant test tube rack is placed on the loading unit and whether there is liquid in the test tube;
[0068] Since the analyzer is basically in the cleaning process during the shutdown process, in order to clean the analyzer, it is often determined whether a test tube rack is placed on the loading unit and whether there is liquid in the test tube after the shutdown command is initiated.
[0069] Usually, through the optocoupler sensing of the logarithmic optocoupler, at the installation point F, after the shutdown test tube rack is placed on the loading unit and is ready, the controller will scan the shutdown test tube rack and the test tube to identify the test tube type and recognize the test tube when it determines that the loading unit has placed the shutdown test tube rack.
[0070] If a shutdown test tube rack is placed on the loading unit and liquid is placed in the test tube, then in response to judging that a shutdown test tube rack is placed on the loading unit and liquid is placed in the test tube, step S22 is entered, that is, the working mode and working status of the analyzer are obtained.
[0071] If there is no shutdown test tube rack on the loading unit and / or no liquid is placed on the shutdown test tube rack, then in response to determining that there is no shutdown test tube rack on the loading unit and / or liquid is placed on the shutdown test tube rack, step S23 is entered, that is, a message reminder is issued.
[0072] If the user does not place the shutdown test tube rack, the sample analysis system will issue a Tost message prompt, which may include: Please place the test tube containing the probe liquid in the shutdown test tube rack and place it on the loading unit, and the system will automatically perform the shutdown operation. The Tost message is a simple message prompt box under the Android system. After the preset time, the prompt will automatically disappear, ending the shutdown process.
[0073] In addition, after responding to the shutdown instruction, the analyzer will be further analyzed on the working state, so the control method also includes:
[0074] S31: Determine whether the analyzer is in a ready state;
[0075] Since the analyzer is basically in a cleaning process during the shutdown process, in order to clean the analyzer, it is often determined whether the analyzer is in a ready state after the shutdown command of the analyzer is initiated.
[0076] If the analyzer is in the ready state, then in response to the determination that the analyzer is in the ready state, the process enters step S32, that is, controlling the distribution of liquid to the analyzer so that the analyzer is cleaned and soaked and shut down.
[0077] Specifically, scheduling allocation can be performed to send the shutdown test tube rack out of the code scanning unit. First, the loading unit is controlled to move the shutdown test tube rack to the sample allocation waiting position, and the liquid is allocated to the analyzer at the sample allocation waiting position. For example, the sample can be allocated to the analyzer at the sample allocation waiting position B. Specifically, the liquid in the shutdown test tube can be allocated to one analyzer or to multiple analyzers. Since the shutdown process has been entered, this can achieve the purpose of cleaning the analyzers one by one. The analyzer is cleaned and soaked with liquid, and when the cleaning meets the preset shutdown conditions, the analyzer and the single-machine sampling unit are shut down.
[0078] In order to achieve the purpose of thorough cleaning, the part of the analyzer used to carry the cleaning liquid can usually be fully immersed, and a shaking process can be preset to fully clean the detection operation part for the next detection operation, thereby improving the accuracy of the analyzer's next detection.
[0079] If the analyzer is not in the ready state, then in response to the determination that the analyzer is not in the ready state, the process proceeds to step S33, that is, waiting for a preset time. After waiting for the preset time, the process returns to step S31 for another determination until the analyzer is determined to be in the ready state, and the liquid in the test tube is distributed to the analyzer.
[0080] In addition, before controlling the steps of dispensing liquid to the analyzer and controlling the analyzer to perform cleaning and shutdown, the control method further includes:
[0081] S41: Determine whether the analyzer is in a fault state;
[0082] During testing, analyzers are often expensive instruments in testing departments. They are often used for repeated testing around the clock. However, such high-frequency use often means high consumption. The analyzers are often worn out very much. In addition, the circuits in the analyzers are also relatively sophisticated and complex. Therefore, before controlling the shutdown test tube rack to distribute liquid to the analyzer, it is often necessary to determine whether the analyzer is in a faulty state.
[0083] If the analyzer is not in a faulty state, then in response to the analyzer not being in a faulty state, the process proceeds to step S42, ie, controlling liquid to be distributed to the analyzer so that the analyzer is cleaned and soaked and shut down.
[0084] If the analyzer is in a fault state, then in response to the analyzer being in a fault state, step S43 is entered, that is, waiting for the fault to be eliminated. After waiting for the fault to be eliminated, the judgment of step S41 can be further returned to be judged again until it is judged that the analyzer is not in a fault state, and the liquid in the test tube is distributed to the analyzer.
[0085] In addition, before controlling the steps of dispensing liquid to the analyzer and controlling the analyzer to perform cleaning and shutdown, the control method further includes:
[0086] S51: determining whether the analyzer is in a busy state;
[0087] The scanning unit is often set at a fixed position and detects the busyness of the operation, so the test tubes on the test tube rack can be transported to the waiting position D through the loading unit, and then the test tubes are transported to the sample distribution waiting position B when waiting for the right time. Therefore, it is necessary to judge whether the analyzer is in a busy state.
[0088] If the analyzer is not in a busy state, then in response to the analyzer not being in a busy state, the process enters step S52, that is, controlling the liquid to be distributed to the analyzer so that the analyzer is cleaned and soaked and shut down.
[0089] If the analyzer is in a busy state, then in response to the analyzer being in a busy state, step S53 is entered, that is, waiting for a preset time. The scanned cleaning liquid test tube is not distributed, and after the busy state is eliminated, the judgment of step S51 can be further returned to be judged again until it is determined that the analyzer is not in a busy state, and the liquid in the test tube is distributed to the analyzer.
[0090] Furthermore, before controlling the steps of dispensing liquid to the analyzer and controlling the analyzer to perform cleaning and shutdown, the control method further includes:
[0091] S61: Determine whether the analyzer is in a dormant state;
[0092] If the analyzer to be analyzed is not in the dormant state, then in response to the analyzer not being in the dormant state, the process proceeds to step S62, that is, controlling the liquid to be distributed to the analyzer so that the analyzer is cleaned and soaked and shut down;
[0093] If the analyzer is in the sleep state, then in response to the analyzer being in the sleep state, the process proceeds to step S63, that is, the analyzer wakes itself up and exits the sleep state. After the analyzer exits the sleep state, the scheduling allocation is performed again.
[0094] In order to test the effectiveness of the control method of the sample analysis system of the present application, a specific embodiment is provided. Fig. 9 , Fig. 9 This is a flow chart of a specific implementation method of the control method of the sample analysis system of the present application, which specifically includes the following steps:
[0095] S701: Obtain shutdown instruction;
[0096] like Figure 2 As shown, if the product is connected to the assembly line mode in the mode with the alias 1, and the startup and shutdown are scheduled, and the test tube clamp shutdown is selected, it means that when the preset time is reached for shutdown, the shutdown test tube rack is connected to enter the shutdown process, and the sample analysis system can obtain the shutdown instruction.
[0097] In addition, when the user or medical staff presses the "one-button start" button for more than 3 seconds, the sample analysis system can obtain the shutdown command. Of course, whether the shutdown command is obtained automatically or passively, as long as it meets the actual needs, it is not limited here.
[0098] S702: Are the shutdown test tube rack and cleaning solution placed on the loading unit?
[0099] Through the optical coupling induction, the controller determines whether the shutdown test tube rack is placed on the loading unit: if the shutdown test tube rack is not placed: the system will prompt a message, that is, enter step S703: pop up a message reminder. Specifically, when the user does not place the shutdown test tube rack, the system will prompt: please place the test tube containing the probe liquid on the shutdown test tube rack, and place it on the loading unit, and the system will automatically perform the shutdown operation.
[0100] If the shutdown test tube rack is placed, the shutdown test tube rack and the test tubes are scanned, and the test tube type identification and test tube recognition are performed, that is, the process goes to step S704: matching the analyzer corresponding to the test tube rack number segment according to the shutdown scheduling strategy.
[0101] S705: Is the analyzer currently in the ready state?
[0102] If the analyzer is not in the ready state, then in response to the determination that the analyzer is not in the ready state, the process proceeds to step S706, that is, waiting for a preset time, and then further returns to the determination of step S705 for another determination until the analyzer is determined to be in the ready state, and then the analyzer is allocated.
[0103] If the analyzer is in the ready state, then in response to the determination that the analyzer is in the ready state, the process proceeds to step S707, that is, further determining whether the analyzer is currently in a fault state.
[0104] S707: Is the analyzer currently in a fault state?
[0105] If the analyzer is in a faulty state, then in response to the analyzer being in a faulty state, the process proceeds to step S708, that is, waiting for the fault to be eliminated. After waiting for the fault to be eliminated, the process can further return to step S707 for further determination until it is determined that the analyzer is not in a faulty state, and then the analyzer is allocated.
[0106] If the analyzer is not in a fault state, then in response to the analyzer not being in a fault state, the process proceeds to step S709, that is, further determining whether the analyzer is currently in a busy state.
[0107] S709: Is the analyzer currently busy?
[0108] If the analyzer is busy, then in response to the analyzer being busy, the process proceeds to step S710, that is, waiting for a preset time, and then further returns to step S709 for further determination until it is determined that the analyzer is not busy, and then the analyzer is allocated.
[0109] If the analyzer is not in a busy state, then in response to the analyzer not being in a busy state, that is, the assigned analyzer is in an idle state, the process proceeds to step S711, that is, further determining whether the analyzer is currently in a sleep state.
[0110] S711: Is the analyzer currently in sleep mode?
[0111] If the analyzer is in a dormant state, then in response to the analyzer being in a dormant state, step S712 is entered, that is, the analyzer wakes itself up and exits the dormant state. After waiting for the fault to be eliminated, the judgment of step S711 can be further returned to perform another judgment until it is determined that the analyzer is not in a fault state, and then the analyzer is allocated.
[0112] If the analyzer is not in the sleep state, then in response to the analyzer not being in the sleep state, the process proceeds to step S713.
[0113] S713: The analyzer grabs the corresponding test tube, sucks the sample for cleaning, returns the test tube, and shuts down after cleaning;
[0114] By performing analyzer allocation, the test tubes containing cleaning fluid are placed on the shutdown test tube rack and put into the loading unit. The sample analysis system will automatically scan and identify, and pre-calculate the test tube rack allocation path based on the identified information (shutdown test tube rack + shutdown cleaning fluid), thereby achieving the matching association between the analyzer and the corresponding test tube rack and the corresponding cleaning path.
[0115] In order to detect whether the cleaning meets the requirements, the part of the analyzer used to carry the cleaning liquid is set to reach a preset concentration after the preset cleaning program, which means that the analyzer has been cleaned, and the cleaning has met the preset shutdown conditions, and the analyzer can be shut down.
[0116] S714: Recover the cleaning liquid test tube and transport it to the unloading unit;
[0117] The system will match the analyzer with the assigned test tube, send the test tube to the loading platform, and send a shutdown command to the analyzer. The analyzer will grab the test tube, suck the sample for cleaning, return the test tube, and shut down after cleaning. At the same time, the scheduling system will recycle the test tube rack and test tube and transport them to the unloading unit.
[0118] S715: Are all instruments turned off?
[0119] Determine whether all pipeline mode analyzers have been shut down. If there is at least one analyzer that has not been shut down, wait for the analyzer to be ready. If all have been shut down, the system sends a shutdown command to each module unit.
[0120] S716: The system sends a shutdown command to each module unit, and at the same time sends a reservation to the hollow computer to shut down the computer after 1 minute;
[0121] At the same time, an appointment is made to the central control computer to shut down the computer in 1 minute, and then shut down its own software. After 1 minute, the central control computer executes the command to turn off the power, shut down the specified analyzer of the test tube rack, shut down the software scheduling system and each unit of the transmission track.
[0122] You can make an appointment for 1 minute or 5 minutes, as long as it meets your actual needs. There is no limitation here.
[0123] S717: Close its own software. After 1 minute, the central control computer will execute the command to turn off the power.
[0124] S718: End.
[0125] Therefore, the present application can provide users with convenient operation and meet users' special needs through the shutdown scheduling strategy of the test tube rack. Specifically, it can have the following beneficial effects:
[0126] 1. Due to the setting of the single-machine power button and the transmission track power button, the single-machine module and the transmission track module are separated, and they can be operated independently without affecting each other, or they can be operated in association, which improves the flexibility of operation.
[0127] 2. When the analyzer is turned off, other units also perform the shutdown operation; when the analyzer is working normally, other units also work normally. In this way, the accessory units follow the analyzer as the main unit for chain operation, which can save cleaning liquid and shutdown time and improve the linkage of the system.
[0128] 3. The combined use of long-term stand-alone mode and temporary stand-alone mode makes the system allocation strategy more flexible and diverse, and the diversified power on and off operations meet the user's convenience needs in a timely manner.
[0129] The above description is only an implementation method of the present application, and does not limit the patent scope of the present application. Any equivalent structure or equivalent process transformation made using the contents of the present application specification and drawings, or directly or indirectly used in other related technical fields, are also included in the patent protection scope of the present application.
Claims
1. A sample analysis system, characterized in that: include: Analyzers, controllers, shutdown tube racks, and transfer tracks; The analyzer is connected to the controller and is arranged corresponding to the shutdown test tube rack, and the shutdown test tube rack and the analyzer are arranged in sequence along the transmission track respectively; The controller is used to receive the shutdown instruction of the analyzer; the controller obtains the working mode and working state of each analyzer and the preset shutdown scheduling strategy; The controller controls the shutdown test tube rack and the analyzer to shut down according to the preset shutdown scheduling strategy based on the working mode and the working state; The preset shutdown scheduling strategy includes a one-to-one correspondence between the Mth row and Nth column of the shutdown test tube rack and the cleaning paths assigned to the analyzers, and both M and N are positive integers greater than or equal to 1.
2. The sample analysis system according to claim 1, characterized in that: The controller includes a control panel; The control panel is used to receive the association instruction of the analyzer and the shutdown test tube rack, and the controller controls to generate the preset shutdown scheduling strategy based on the association instruction, and the preset shutdown scheduling strategy includes the number segment of the shutdown test tube rack and the assigned analyzer to form the cleaning path; The control panel is used to manage whether the analyzer is connected to the working mode, the start time and shutdown time of the working mode, and whether the shutdown test tube rack is connected.
3. The sample analysis system according to claim 1 or 2, characterized in that: The sample analysis system further comprises a loading unit and a scanning unit arranged on the transmission track, and a test tube arranged on the test tube rack to shut down the machine; When the controller determines through the scanning unit that the shutdown test tube rack is placed on the loading unit and the test tube contains liquid, the controller obtains that the working mode is the transmission track mode or the stand-alone mode, and the working state is the ready state. The controller controls the distribution of the liquid to the analyzer, and controls the analyzer to perform cleaning and shutdown.
4. A control method for a sample analysis system, applied to a sample analysis system, characterized in that: The sample analysis system comprises: an analyzer, a controller, a shutdown test tube rack and a transmission track; the analyzer is connected to the controller and is arranged corresponding to the shutdown test tube rack, and the shutdown test tube rack and the analyzer are arranged in sequence along the transmission track respectively, and the control method comprises: In response to the shutdown instruction of the analyzer, obtaining the working mode and working state of each of the analyzers and a preset shutdown scheduling strategy; Based on the working mode and the working state, controlling the shutdown test tube rack and the analyzer to shut down according to the preset shutdown scheduling strategy; The preset shutdown scheduling strategy includes a one-to-one correspondence between the Mth row and Nth column of the shutdown test tube rack and the cleaning paths assigned to the analyzers, and both M and N are positive integers greater than or equal to 1.
5. The control method according to claim 4, characterized in that: The controller includes a control panel, the control panel is used to receive the associated instructions of the analyzer and the shutdown test tube rack and the control panel is used to manage whether the analyzer is connected to the working mode, the startup time and shutdown time of the working mode, and whether the shutdown test tube rack is connected; Before the step of obtaining the working mode and working state of each of the analyzers in response to the shutdown instruction of the analyzer, the control method further includes: In response to the instruction for setting the association between the analyzer and the shutdown test tube rack, the preset shutdown scheduling strategy is controlled to associate the number segments of the shutdown test tube rack with the analyzer respectively to form a plurality of cleaning paths.
6. The control method according to claim 5, characterized in that: The control method further comprises: Associate and bind the number segments and test tube rack types of different test tube racks; Among them, the test tube rack types include at least a venous whole blood test tube rack, a micro whole blood test tube rack, a quality control test tube rack and a calibration test tube rack.
7. The control method according to claim 6, characterized in that: The sample analysis system further comprises a loading unit and a scanning unit arranged on the transmission track, and a test tube arranged on the test tube rack to shut down the machine; The step of controlling the shutdown test tube rack and the analyzer to shut down according to the preset shutdown scheduling strategy based on the working mode and the working state includes: When it is determined by the scanning unit that the shutdown test tube rack is placed on the loading unit and the test tube contains liquid, it is obtained that the working mode is the assembly line mode or the stand-alone mode, and the working state is the ready state; The liquid is distributed to the analyzer by control, and the analyzer is cleaned and shut down.
8. The control method according to claim 7, characterized in that: Before the steps of controlling the distribution of the liquid to the analyzer and controlling the analyzer to clean and shut down, the method further includes: Determining whether the analyzer is in a fault state; In response to the analyzer not being in a fault state, controlling the distribution of the liquid to the analyzer so that the analyzer is cleaned and soaked and shut down is performed; In response to the analyzer being in a fault state, no dispensing is performed and the fault is awaited to be eliminated.
9. The control method according to claim 7, characterized in that: Before the steps of controlling the distribution of the liquid to the analyzer and controlling the analyzer to clean and shut down, the method further includes: Determine whether the analyzer is busy; In response to the analyzer not being in a busy state, controlling the distribution of the liquid to the analyzer so that the analyzer is cleaned and soaked and shut down; In response to the analyzer being in a busy state, no allocation is performed and a preset time is waited to determine whether it is in a busy state again.
10. The control method according to claim 7, characterized in that: Before the steps of controlling the distribution of the liquid to the analyzer and controlling the analyzer to clean and shut down, the method further includes: Determine whether the analyzer is in sleep mode; In response to the analyzer not being in a dormant state, controlling the distribution of the liquid to the analyzer so that the analyzer is cleaned and soaked and shut down; In response to the analyzer being in the sleep state, the analyzer wakes itself up and exits the sleep state.