Flexible job shop energy-saving batch flow scheduling batch optimization method

By combining the equal batch method and variable minimum batch constraints with intelligent optimization algorithms, the problem of strong randomness in the batch optimization of workpieces in the flexible job shop is solved, an efficient batch division and production scheduling scheme is achieved, and the search efficiency and Economic indicators.

CN118732623APending Publication Date: 2024-10-01SHENYANG UNIVERSITY OF TECHNOLOGY
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202410765894.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-13
Publication Date
2024-10-01

AI Technical Summary

Technical Problem

Existing workpiece batch optimization methods in flexible job workshops have problems such as strong randomness, which leads to large performance gaps in batch solutions and low search efficiency for optimal solutions. It is difficult to obtain a better batch division solution within a limited time.

Method used

The equal batch method and variable minimum batch constraints are used to divide the workpiece batch, and through appropriate algorithm evaluation and local search strategies, the algorithm parameters are dynamically adjusted to improve search efficiency, and the multi-objective evolutionary algorithm and intelligent optimization algorithm are combined to optimize the workpiece Batch scheme.

Benefits of technology

It achieves the directionality and efficiency of batch division of workpieces, shortens the completion time, reduces the total energy consumption of the workshop, improves production efficiency and resource utilization, and significantly improves the efficiency of optimal solution search.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118732623A_ABST
    Figure CN118732623A_ABST
Patent Text Reader

Abstract

The invention relates to a flexible job shop energy-saving batch flow scheduling batch optimization method, and belongs to the technical field of shop scheduling. The method mainly comprises the following steps: with completion time and total energy consumption of a workshop as optimization targets, segmenting workpiece batches based on an equivalent batching method and variable minimum batch constraints; evaluating the performance of the workpiece batch division scheme by using a proper algorithm; an initial batch division scheme in each iteration process is kept unchanged, and a local solution space of the problem is searched based on the batch number of workpieces; according to different problem scales under different batching schemes, key parameters of the algorithm are dynamically and adaptively adjusted. According to the optimization framework provided by the invention, a high-quality workpiece batch segmentation and workshop scheduling scheme can be obtained, so that the workshop energy consumption is effectively reduced, and the completion time is shortened.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a batch optimization method for energy-saving batch flow scheduling in a flexible job shop, and belongs to the technical field of shop scheduling. Background Art

[0002] The workshop production of discrete manufacturing enterprises usually has the characteristics of multiple varieties, small batches, high flexibility, customization, and high energy consumption. The energy-saving batch flow scheduling problem in flexible workshops has become the core issue of their workshop production scheduling. The energy-saving batch flow scheduling problem in flexible workshops needs to optimize economic indicators such as energy consumption and completion time while solving the three sub-problems of workpiece batching, machine tool allocation, and process sequencing. There is a strong coupling relationship between the sub-problems, and the optimization result of the previous sub-problem will have an important impact on the optimization performance of the subsequent sub-problems. As the primary problem faced by the optimization of energy-saving batch flow scheduling problems in flexible workshops, the importance of workpiece batch optimization is self-evident.

[0003] The method and size of batch division directly determine the performance of the scheduling plan. Too small a batch will lead to frequent workpiece clamping, tool replacement and inter-process transportation, which will lead to problems such as increased completion time, increased energy consumption and increased production costs. Larger batches may cause an increase in bottleneck processes and insufficient machine tool utilization, which will lead to problems such as extended product delivery time, increased energy consumption and key equipment failure. Therefore, reasonable batch division is the key to improving the performance of workshop scheduling plans. By batching high-quality workpieces, waiting and idle time in the production process can be reduced, the production capacity of equipment can be maximized, and resource utilization can be optimized, thereby shortening completion time and improving production efficiency.

[0004] Most of the existing related research is based on random batching or empirical batching to deal with its workpiece batching sub-problem, and mainly focuses on the collaborative optimization of its machine tool allocation and process sequencing sub-problems. However, non-directional random batching is highly accidental, while empirical batching is too dependent on the decision maker's prior knowledge, resulting in a large gap in the scheduling performance of batch schemes; in addition, since the performance of the batch scheme needs to be verified based on the pros and cons of the scheduling indicator value under the current scheme, and it is time-consuming to obtain a better solution to the flexible job shop scheduling problem, the time cost of verifying all feasible batch schemes is very high. The above reasons lead to the low efficiency of the optimal batch scheme search of existing methods. Obtaining a better batch division scheme within a limited time is a major problem that needs to be solved urgently in the energy-saving batch flow scheduling optimization of flexible job shops. Summary of the invention

[0005] In view of the above-mentioned deficiencies and improvement needs of the prior art, the present invention proposes a batch optimization method for energy-saving batch flow scheduling in a flexible job workshop, which aims to solve the problems of large performance gap of batch schemes and low efficiency of searching for the optimal scheme due to the strong randomness of workpiece batch division in traditional methods, and to achieve high-quality and efficient division of workpiece batches in flexible job workshops.

[0006] In order to solve the above technical problems, the present invention proposes a batch optimization method for energy-saving batch flow scheduling in a flexible job shop, comprising the following steps: S1, taking completion time, total energy consumption of the workshop, and total processing cost as optimization objectives, dividing the workpiece batch based on the equal batch method and variable minimum batch constraints; S2, using a suitable algorithm to evaluate the performance of the workpiece batch division scheme; S3, keeping the initial batch division scheme unchanged during each iteration, and searching the local solution space of the problem based on the number of workpiece batches; S4, dynamically and adaptively adjusting the key parameters of the algorithm according to the different problem scales under different batching schemes.

[0007] According to the present invention, step S1 includes the following sub-steps:

[0008] Based on the equal batching method, the batch of workpieces is divided according to the minimum batch constraint;

[0009] If the workpiece cannot be completely divided into equal parts, the maximum remaining job batch c is set. When the remaining job batch is greater than c, it is regarded as an independent job. Otherwise, the remaining job is arranged in the last sub-batch. The calculation formula is:

[0010] If V i ≤c, z=0; otherwise, z=1

[0011] Among them, z is a decision variable;

[0012] Workpiece J i The batch size of the lth sub-batch can be expressed as:

[0013] If V i ≤c,l∈[1,U i ]; otherwise, l∈[1,U i +1]

[0014] Among them, U i and V i The workpiece J i The number of batches and workpieces J after batching i The batch size of the last sub-batch after batching;

[0015] Set the number of iterations maxcycle and the search step a to update the current minimum batch value;

[0016] Set up a selectable algorithm set that includes multiple classic and novel intelligent optimization algorithms, and use appropriate algorithms to obtain the optimal scheduling solution under the current minimum batch constraint according to the different problem scales;

[0017] An external archive collection is set to store the workpiece batch division plan and workshop scheduling plan obtained in each iteration, and the current optimal scheduling plan and workpiece batch division plan are updated.

[0018] According to the present invention, step S2 includes the following sub-steps:

[0019] Set up a selectable algorithm set including the second generation fast branch domination sorting genetic algorithm, multi-stage multi-objective evolutionary algorithm, paired offspring constrained large-scale multi-objective evolutionary algorithm, large-scale competitive group optimization algorithm and multi-objective evolutionary algorithm based on Pareto optimal subspace;

[0020] For batch optimization problems of different scales and optimization indicators, different optimization algorithms are selected to evaluate their effectiveness.

[0021] According to the present invention, step S3 includes the following sub-steps:

[0022] Based on the batch partitioning scheme determined by the equal batching method and the variable minimum batch constraint, the probability of each type of workpiece being selected is calculated according to the batch quantity of each workpiece.

[0023] Preferably, the probability of the workpiece being selected in step S3 is linearly positively correlated with the number of its batches;

[0024] Set the neighborhood search step size b, update the current minimum batch value, and the updated minimum batch min_p is a random integer in the range of [min_p-b,min_p+b];

[0025] Based on the probability of each workpiece being selected, a certain type of workpiece is randomly selected for batch merging, and the batch of this type of workpiece is re-divided according to the current minimum batch value;

[0026] If the workpiece cannot be completely divided into equal parts, the maximum remaining job batch c is set. When the remaining job batch is greater than c, it is regarded as an independent job. Otherwise, the remaining job is arranged in the last sub-batch. The calculation formula is: If V i ≤c, z=0; otherwise, z=1

[0027] Among them, z is a decision variable;

[0028] Workpiece J i The batch size of the lth sub-batch can be expressed as:

[0029] If V i ≤c,l∈[1,U i ]; otherwise, l∈[1,U i +1]

[0030] Among them, U i and V i The workpiece J i The number of batches and workpieces J after batching i The batch size of the last sub-batch after batching;

[0031] Use a suitable algorithm to evaluate the performance of the batch scheme, and store the current evaluation results in an external archive set; repeat the above steps maxlimit times and output the external archive set.

[0032] Preferably, the suitable algorithm in step S3 is the algorithm with the best performance in the selectable algorithm set.

[0033] According to the present invention, step S4 includes the following sub-steps:

[0034] When the minimum batch size of the workpiece segmentation reaches its initial batch size, the number of iterations will not be increased. The average batch size (Ave_B) of all workpieces in a production batch is used to calculate the parameter maxcycle. The calculation formula is:

[0035]

[0036] Among them, the fix function is used to truncate and round.

[0037] The total number of batches of workpieces (n) × the number of machine tools (m) is used to represent the scale (Problemsize) of the batch flow scheduling problem in the flexible job shop. According to the different problem scales under different batching schemes, the mapping relationship between the parameter maxlimit and the number of iterations (cycle) is determined. The calculation formula is:

[0038] cycle∈[1,maxcycle]

[0039] For the relationship function between the problem size and the number of iterations, given an initial number of loops (Initial_limit), the parameter maxlimit is obtained, and the calculation formula is:

[0040] cycle∈[1,maxcycle]

[0041] The round function is used to round off.

[0042] The beneficial effects of the present invention are as follows: taking the shortest completion time and the lowest total energy consumption of the workshop as the optimization goals, batching the workpieces based on the minimum batch constraint, so that the batching has directionality and the search space is predictable; designing a neighborhood search strategy based on the number of workpiece batches to improve the local search ability of the method; constructing a mapping relationship between batching schemes, problem scale and algorithm parameters, and proposing a problem knowledge-driven adaptive algorithm parameter dynamic adjustment strategy to balance the algorithm search time and performance, and solve the problem that the traditional method has a large performance gap in batching schemes and low efficiency in searching for the optimal solution due to the strong randomness of workpiece batch division, and obtains a workpiece batch division and production scheduling scheme with excellent economic indicators and green indicators. Promote the combination of flexible production batch flow scheduling technology and intelligent optimization, and provide a theoretical basis for multi-variety variable batch production. BRIEF DESCRIPTION OF THE DRAWINGS

[0043] Figure 1(a) and 1(b) 1 is an example diagram of the energy-saving batch flow scheduling problem of the flexible job shop of the present invention, wherein FIG1(a) is a scheduling scheme diagram before the workpieces are batched, and FIG1(b) is a scheduling scheme diagram after the workpieces are batched and optimized;

[0044] Figure 2 This is a framework diagram of the energy-saving batch flow scheduling optimization method for a flexible job shop of the present invention;

[0045] Figure 3 Main effect diagram for parameter settings of the algorithm of the present invention;

[0046] Figure 4 This is the Gantt chart of the batch scheduling scheme after optimization for the benchmark problem MK06 (Ave_B=20) of the present invention. DETAILED DESCRIPTION

[0047] The present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. However, it should be understood that the embodiments are used to explain the present invention but are not used to limit the present invention.

[0048] In order to make the present invention more clear, the method of the present invention is described below with a specific embodiment. Figure 1(a) and 1(b) As shown; the flexible job shop energy-saving batch flow scheduling optimization method provided by the embodiment of the present invention, the method steps are as follows Figure 2 As shown, the following steps are included:

[0049] S1, taking completion time, total energy consumption of the workshop and total processing cost as optimization objectives, the workpiece batch is divided based on the equal batch method and variable minimum batch constraints;

[0050] S2, using appropriate algorithms to evaluate the performance of the workpiece batch partitioning scheme;

[0051] S3, keeping the initial batch partitioning scheme unchanged in each iteration process, searching the local solution space of the problem based on the number of workpiece batches;

[0052] S4. Dynamically and adaptively adjust the key parameters of the algorithm according to the different problem sizes under different batching schemes;

[0053] S5. Numerical experiments.

[0054] Furthermore, the step S1 includes the following sub-steps:

[0055] Based on the equal batching method, the batch of workpieces is divided according to the minimum batch constraint;

[0056] Set the maximum remaining job constraint. If the workpiece cannot be completely divided equally, set the maximum remaining job batch c. When the remaining job batch is greater than c, it is considered an independent job. Otherwise, the remaining job is arranged in the last sub-batch. The calculation formula is:

[0057] If V i ≤c, z=0; otherwise, z=1

[0058] Here, z is a decision variable.

[0059] Workpiece J i The batch size of the lth sub-batch can be expressed as:

[0060] If V i ≤c,l∈[1,U i ]; otherwise, l∈[1,U i +1]

[0061] Among them, U i and V i The workpiece J i The number of batches and workpieces J after batching i Batch size of the last subbatch after batching.

[0062] Set the number of iterations maxcycle and the search step a to update the current minimum batch value;

[0063] Set up a selectable algorithm set that includes multiple classic and novel intelligent optimization algorithms, and use appropriate algorithms to obtain the optimal scheduling solution under the current minimum batch constraint according to the different problem scales;

[0064] An external archive collection is set to store the workpiece batch division plan and workshop scheduling plan obtained in each iteration, and the current optimal scheduling plan and workpiece batch division plan are updated.

[0065] Furthermore, the step S2 includes the following sub-steps:

[0066] Set up a selectable algorithm set including the second generation fast branch domination sorting genetic algorithm, multi-stage multi-objective evolutionary algorithm, paired offspring constrained large-scale multi-objective evolutionary algorithm, large-scale competitive group optimization algorithm and multi-objective evolutionary algorithm based on Pareto optimal subspace;

[0067] For batch optimization problems of different scales and optimization indicators, different optimization algorithms are selected to evaluate their effectiveness.

[0068] Furthermore, the step S3 includes the following sub-steps:

[0069] Based on the batch partitioning scheme determined by the equal batching method and the variable minimum batch constraint, the probability of each type of workpiece being selected is calculated according to the batch quantity of each workpiece.

[0070] Preferably, the probability of the workpiece being selected in step S3 is linearly positively correlated with the number of its batches;

[0071] Set the neighborhood search step size b, update the current minimum batch value, and the updated minimum batch min_p is a random integer in the range of [min_p-b,min_p+b];

[0072] Based on the probability of each workpiece being selected, a certain type of workpiece is randomly selected for batch merging, and the batch of this type of workpiece is re-divided according to the current minimum batch value;

[0073] Set the maximum remaining job constraint. If the workpiece cannot be completely divided equally, set the maximum remaining job batch c. When the remaining job batch is greater than c, it is considered an independent job. Otherwise, the remaining job is arranged in the last sub-batch. The calculation formula is:

[0074] If V i ≤c, z=0; otherwise, z=1

[0075] Here, z is a decision variable.

[0076] Workpiece J i The batch size of the lth sub-batch can be expressed as:

[0077] If V i ≤c,l∈[1,U i ]; otherwise, l∈[1,U i +1]

[0078] Among them, U i and V i The workpiece J iThe number of batches and workpieces J after batching i Batch size of the last subbatch after batching.

[0079] Use a suitable algorithm to evaluate the performance of the batch scheme, and store the current evaluation results in an external archive set; repeat the above steps maxlimit times and output the external archive set.

[0080] Preferably, the suitable algorithm in step S3 is the algorithm with the best performance in the selectable algorithm set.

[0081] Furthermore, the step S4 includes the following sub-steps:

[0082] When the minimum batch size of the workpiece segmentation reaches its initial batch size, the number of iterations will not be increased. The average batch size (Ave_B) of all workpieces in a production batch is used to calculate the parameter maxcycle. The calculation formula is:

[0083]

[0084] Among them, the fix function is used to truncate and round.

[0085] The total number of batches of workpieces (n) × the number of machine tools (m) is used to represent the scale (Problemsize) of the batch flow scheduling problem in the flexible job shop. According to the different problem scales under different batching schemes, the mapping relationship between the parameter maxlimit and the number of iterations (cycle) is determined. The calculation formula is:

[0086] cycle∈[1,maxcycle]

[0087] For the relationship function between the problem size and the number of iterations, given an initial number of loops (Initial_limit), the parameter maxlimit is obtained, and the calculation formula is:

[0088] cycle∈[1,maxcycle]

[0089] The round function is used to round off.

[0090] Furthermore, the step S5 includes the following sub-steps:

[0091] Explore the influence of the key algorithm parameters min_p, Initial_limit, a, b, and c on the performance of the flexible job shop energy-saving batch flow scheduling optimization method, and obtain the best algorithm parameter combination. The main effect diagram of the algorithm parameters is shown in Figure 3 shown.

[0092] The best algorithm parameter combination is: min_p = 4, Initial_limit = 0.3, a = 2, b=1, and c=10.

[0093] In order to verify the effectiveness of the energy-saving batch flow scheduling optimization method for flexible job shops proposed in this invention, the benchmark case 20×MK06 in the literature "Tian ZQ, Jiang XY, Liu WJ, et al. Knowledge-based lot-splitting optimization method for flexible job shops considering energy consumption [J]. IEEE Transactions on Automation Science and Engineering, early access, 2023." was selected for testing. The example contains 10 workpieces, 10 machine tools, the average number of processes for each workpiece is 15, and each process can be processed by an average of 3 machine tools. The average batch of workpieces is 20. The proposed energy-saving batch flow scheduling optimization method for flexible job shops, the empirical batching method, and the integrated optimization method based on artificial bee colony algorithm and genetic algorithm are used to solve the problem. The statistical results of 10 solutions are shown in Table 1. As can be seen from Table 1, for the average value, the performance of the energy-saving batch flow scheduling optimization method for flexible job shops is improved by 21.9% and 33.7% respectively compared with the empirical batching method and the integrated batching method. The Gantt chart of the optimized scheduling scheme is as follows: Figure 4 As shown in the figure, at this time, the total energy consumption of the workshop is 401362kW·h, the completion time is 4004.3h, and the number of sub-batches of each workpiece is 2, 3, 1, 5, 4, 8, 6, 4, 8 and 4. It can be seen that the energy-saving batch flow scheduling optimization method of the flexible job shop is significantly better than the empirical batch method and the integrated optimization method.

[0094] Table 1 Statistical results of benchmark case 20×MK06 under various batch methods

[0095]

[0096] The above embodiments are only for illustrating the technical concept and features of the present invention, and the purpose is to enable technicians in this field to understand the content of the present invention and implement it. It cannot be used to limit the protection scope of the present invention. All equivalent changes or modifications made according to the essence of the present invention belong to the protection scope of the present invention.

Claims

1. A batch optimization method for energy-saving batch flow scheduling in a flexible job shop, characterized in that: The following steps are involved: S1, batch partitioning strategy based on equal batching method and variable minimum batch constraint; S2, neighborhood search strategy based on the number of workpiece batches; S3. Adaptive dynamic adjustment strategy of key algorithm parameters driven by problem scale.

2. The method for optimizing energy-saving batch flow scheduling in a flexible job shop according to claim 1, characterized in that: Batch partitioning strategies based on equal batching methods and variable minimum batch constraints include: Based on the equal batching method, the workpiece batch is divided according to the minimum batch constraint. If the workpiece cannot be completely divided, the maximum remaining job batch c is set. When the remaining job batch is greater than c, it is regarded as an independent job. Otherwise, the remaining job is arranged in the last sub-batch. The calculation formula is: If V i ≤c, z=0; otherwise, z=1 Among them, z is a decision variable, Workpiece J i The batch size of the lth sub-batch can be expressed as: If V i ≤c,l∈[1,U i ]; otherwise, l∈[1,U i +1] Among them, U i and V i The workpiece J i The number of batches and workpieces J after batching i The batch size of the last subbatch after batching, Set the number of iterations maxcycle and the search step a to update the current minimum batch value; set a selectable algorithm set that includes multiple classic and novel intelligent optimization algorithms, and use appropriate algorithms to obtain the optimal scheduling plan under the current minimum batch constraint according to the different problem scales; set an external archive collection to store the workpiece batch division plan and workshop scheduling plan obtained in each iteration, and update the current optimal scheduling plan and workpiece batching plan.

3. The energy-saving batch flow scheduling and batch optimization method for a flexible job shop as claimed in claim 1 or 2, characterized in that: The neighborhood search strategy based on the number of batches of workpieces includes: Based on the batch division scheme determined by the equal batching method and the variable minimum batch constraint, the probability of each type of workpiece being selected is calculated according to the batch number of each workpiece, where the probability of a workpiece being selected is linearly positively correlated with its batch number; the neighborhood search step size b is set, and the current minimum batch value is updated. The updated minimum batch min_p is a random integer in the range of [min_p-b,min_p+b]; based on the probability of each workpiece being selected, a certain type of workpiece is randomly selected for batch merging, and the batch of this type of workpiece is re-divided according to the current minimum batch value; if the workpiece cannot be completely divided equally, the maximum remaining job batch c is set. When the remaining job batch is greater than c, it is regarded as an independent job. Otherwise, the remaining job is arranged in the last sub-batch. The calculation formula is: If V i ≤c, z=0; otherwise, z=1 Among them, z is a decision variable; Workpiece J i The batch size of the lth sub-batch can be expressed as: If V i ≤c,l∈[1,U i ]; otherwise, l∈[1,U i +1] Among them, U i and V i The workpiece J i The number of batches and workpieces J after batching i The batch size of the last sub-batch after batching; Use a suitable algorithm to evaluate the performance of the batch scheme, and store the current evaluation results in an external archive set; repeat the above steps maxlimit times and output the external archive set.

4. The method for optimizing energy-saving batch flow scheduling in a flexible job shop according to claim 3, characterized in that: The problem scale-driven adaptive dynamic adjustment strategy for key algorithm parameters includes: The parameter maxcycle is calculated using the average batch size (Ave_B) of all workpieces in a production batch. The calculation formula is: Among them, the fix function is used to truncate and round. The total number of batches of workpieces (n) × the number of machine tools (m) is used to represent the scale (Problemsize) of the flexible job shop batch flow scheduling problem, and the mapping relationship between the parameter maxlimit and the number of iterations (cycle) is determined. On this basis, an initial number of cycles (Initial_limit) is given to obtain the parameter maxlimit, and the calculation formula is: The round function is used to round off.

5. The method for optimizing energy-saving batch flow scheduling in a flexible job shop according to claim 4, characterized in that: In the process of obtaining the optimal scheduling solution under the current minimum batch constraint by using a suitable algorithm, the suitable algorithm is a second-generation fast distribution dominance sorting genetic algorithm, a multi-stage multi-objective evolutionary algorithm, a paired offspring constrained large-scale multi-objective evolutionary algorithm, a large-scale competitive group optimization algorithm, or a multi-objective evolutionary algorithm based on Pareto optimal subspace.

Citation Information

Patent Citations

  • Mixed-flow-batch scheduling optimization method for workshop production of sensors

    CN112462704A

  • Self-adaptive batch scheduling method with preparation process for flexible job shop

    CN112668789A

  • Multi-variety small-batch multi-target flexible job shop energy consumption optimization scheduling method

    CN112882449A

  • Inconsistent batch flow flexible job shop scheduling method and system

    CN116974245A

  • Optimization method for multi-target batch flow scheduling problem of PCB assembly workshop

    CN117908489A